1 COCOMO II Integrated with Crystal Ball ® Risk Analysis Software Clate Stansbury MCR, LLC cstansbury @mcri.com (703) 506-4600 Prepared for 19 th International Forum on COCOMO Software Cost Modeling University of Southern California Los Angeles CA 27 October 2004
28

1 COCOMO II Integrated with Crystal Ball ® Risk Analysis Software Clate Stansbury MCR, LLC [email protected] (703) 506-4600 Prepared for 19 th International.

Dec 17, 2015

Download

Documents

David Ross
Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Page 1: 1 COCOMO II Integrated with Crystal Ball ® Risk Analysis Software Clate Stansbury MCR, LLC cstansbury@mcri.com (703) 506-4600 Prepared for 19 th International.

1

COCOMO II Integrated withCrystal Ball® Risk Analysis Software

Clate StansburyMCR, LLC

[email protected](703) 506-4600

Prepared for

19th International Forum on COCOMO Software Cost ModelingUniversity of Southern California

Los Angeles CA27 October 2004

Page 2: 1 COCOMO II Integrated with Crystal Ball ® Risk Analysis Software Clate Stansbury MCR, LLC cstansbury@mcri.com (703) 506-4600 Prepared for 19 th International.

2

Contents

• Purpose: Describing Uncertainty• Representing Uncertain Inputs• Simulating Costs• Correlating Inputs and Costs• Summary

Page 3: 1 COCOMO II Integrated with Crystal Ball ® Risk Analysis Software Clate Stansbury MCR, LLC cstansbury@mcri.com (703) 506-4600 Prepared for 19 th International.

3

Traditional “Roll-Up” Method (Too Simple)

• Define “Best Estimate” of Each Cost Element to be the Most Likely Cost of that Element

• List Cost Elements in a Work-Breakdown Structure (WBS)

– Calculate “Best Estimate” of Cost for Each Element– Sum All Best Estimates– Define Result to be “Best Estimate” of Total Project

Cost

• Two Problems With Roll-up Method

1. Ignores Uncertainty—Only Outputs a Point Estimate

2. Estimate is Too Low (We’ll Discuss Later)

Page 4: 1 COCOMO II Integrated with Crystal Ball ® Risk Analysis Software Clate Stansbury MCR, LLC cstansbury@mcri.com (703) 506-4600 Prepared for 19 th International.

4

Estimators Must Describe Uncertainty

• Report Cost As a Statistical Quantity, Not a Point– Cost of Any Incomplete Program Is Uncertain

– Estimator Must Report That Uncertainty as Part of His or Her Delivered Estimate

• Cost-risk Analysis Allows Estimator to Report Cost As a Probability Distribution, So Decision-maker Is Made Aware of

– Expected Cost (Mean)

– 50th Percentile Cost (Median)

– 80th Percentile Cost

– Overrun Probability of Project Budget

Page 5: 1 COCOMO II Integrated with Crystal Ball ® Risk Analysis Software Clate Stansbury MCR, LLC cstansbury@mcri.com (703) 506-4600 Prepared for 19 th International.

5

What a Cost Estimate Should Look Like

“S-Curve”

“Density Curve”

Frequency Chart

.000

.005

.010

.015

.020

0

49.25

98.5

147.7

197

462.43 537.16 611.89 686.62 761.35

10,000 Trials 71 Outliers

Forecast: A8

Cumulativ e Chart

.000

.250

.500

.750

1.000

0

10000

462.43 537.16 611.89 686.62 761.35

10,000 Trials 71 Outliers

Forecast: A8

(Crystal Ball Outputs)

Page 6: 1 COCOMO II Integrated with Crystal Ball ® Risk Analysis Software Clate Stansbury MCR, LLC cstansbury@mcri.com (703) 506-4600 Prepared for 19 th International.

6

Representing Uncertain Inputs Using Triangular Distributions

Page 7: 1 COCOMO II Integrated with Crystal Ball ® Risk Analysis Software Clate Stansbury MCR, LLC cstansbury@mcri.com (703) 506-4600 Prepared for 19 th International.

7

Triangular Distribution of Element Cost, Reflecting Uncertainty in “Best” Estimate

OptimisticCost

Best-Estimate Cost (Mode = Most Likely)

Cost Implication of Technical, Programmatic Assessment

DE

NS

ITY

L M H$

Page 8: 1 COCOMO II Integrated with Crystal Ball ® Risk Analysis Software Clate Stansbury MCR, LLC cstansbury@mcri.com (703) 506-4600 Prepared for 19 th International.

8

COCOMO Cost Drivers as Triangular Distributions

Why triangular distribution?

• Triangular Distribution is Simple and Malleable

• Parameters (Optimistic, Most Likely, Pessimistic) Are Easy to Define and Explain

• Could Have User Provide Parameters for Normal, Lognormal, Exponential, Uniform, or Beta Distributions, for Example, if More is known about the distributions

• Good Topic for Further Research….

Page 9: 1 COCOMO II Integrated with Crystal Ball ® Risk Analysis Software Clate Stansbury MCR, LLC cstansbury@mcri.com (703) 506-4600 Prepared for 19 th International.

9

COCOMO Cost Drivers as Triangular Distributions

• For Each COCOMO II Input …– Input Request Interpreted as a Triangular Distribution– User Estimates Optimistic, Most Likely, and Pessimistic Values

(which may not always be all different from each other)

Optimistic Pessimistic

Most Likely (mode)

Prob

ability

Cost

User provides three values for each COCOMO II input, as though there were three separate projects.

Range of Realistic Input Values

Page 10: 1 COCOMO II Integrated with Crystal Ball ® Risk Analysis Software Clate Stansbury MCR, LLC cstansbury@mcri.com (703) 506-4600 Prepared for 19 th International.

10

COCOMO Cost Drivers as Triangular Distributions

0.90 1.14

Page 11: 1 COCOMO II Integrated with Crystal Ball ® Risk Analysis Software Clate Stansbury MCR, LLC cstansbury@mcri.com (703) 506-4600 Prepared for 19 th International.

11

Processing Uncertainty Using Simulations

Page 12: 1 COCOMO II Integrated with Crystal Ball ® Risk Analysis Software Clate Stansbury MCR, LLC cstansbury@mcri.com (703) 506-4600 Prepared for 19 th International.

12

How to Process Triangular Distributions?

• Taking the Product of Effort Multipliers When Each EM is a Triangular Distribution?

• How to Sum Code Counts for All CSCIs?

• How to Compute Rest of COCOMO II Algorithm?

Page 13: 1 COCOMO II Integrated with Crystal Ball ® Risk Analysis Software Clate Stansbury MCR, LLC cstansbury@mcri.com (703) 506-4600 Prepared for 19 th International.

13

Process Optimistic, ML, Pessimistic as 3 Separate Projects (Too Simple)

• Perform “Roll-up” Method Three Times– Input Optimistic Values into COCOMO II

– Input Most Likely Values into COCOMO II

– Input Pessimistic Values into COCOMO II

• Obtain Total Project Effort as a Triangular Distribution

Page 14: 1 COCOMO II Integrated with Crystal Ball ® Risk Analysis Software Clate Stansbury MCR, LLC cstansbury@mcri.com (703) 506-4600 Prepared for 19 th International.

14

Why “Roll-up” Doesn’t Work

MERGE INPUT DISTRIBUTIONS INTO TOTAL-COST DISTRIBUTION

ROLL-UP TO MOST LIKELYTOTAL COST

REAL MOST LIKELYTOTAL COST

$

WBS-ELEMENT TRIANGULAR INPUT DISTRIBUTIONS

.

.

.

$

$

$MostLikely

MostLikely

MostLikely

Page 15: 1 COCOMO II Integrated with Crystal Ball ® Risk Analysis Software Clate Stansbury MCR, LLC cstansbury@mcri.com (703) 506-4600 Prepared for 19 th International.

15

Use Monte Carlo Simulation to Process the Input Triangular Distributions

Trial 2Trial 10,000Trial 1

=SUM($G$4:$G$8)

Assumption Cell G5

Total Cost

Forecast

Page 16: 1 COCOMO II Integrated with Crystal Ball ® Risk Analysis Software Clate Stansbury MCR, LLC cstansbury@mcri.com (703) 506-4600 Prepared for 19 th International.

16

Crystal Ball Risk- Analysis Software• Commercially Available Third-Party Software Add-on to

Excel, Marketed by Decisioneering, Inc., 2530 S. Parker Road, Suite 220, Aurora, CO 80014, (800) 289-2550

• Inputs– Parameters Defining WBS-Element Distributions– Rank Correlations Among WBS-Element Cost Distributions

• Mathematics– Monte-Carlo (Random) or Latin Hypercube (Stratified)

Statistical Sampling– Virtually All Probability Distributions That Have Names Can Be

Used– Suggests Adjustments to Inconsistent Input Correlation Matrix

• Outputs– Percentiles and Other Statistics of Program Cost– Cost Probability Density and Cumulative Distribution Graphics

Page 17: 1 COCOMO II Integrated with Crystal Ball ® Risk Analysis Software Clate Stansbury MCR, LLC cstansbury@mcri.com (703) 506-4600 Prepared for 19 th International.

17

Representing Correlations Among Risks

Page 18: 1 COCOMO II Integrated with Crystal Ball ® Risk Analysis Software Clate Stansbury MCR, LLC cstansbury@mcri.com (703) 506-4600 Prepared for 19 th International.

18

Risks are Correlated

• Resolving One Cost Driver’s Risk Issues by Spending More Money Often Involves Increasing Values of Several Other Drivers as Well

– For Example, the Monte Carlo Could Generate a High RELY Value and a Low DOCU Value for the Same Trial, Which Doesn’t Make Any Sense

– Schedule Slippage Due to Problems in One CSCI Lead to Cost Growth and Schedule Slippage in Other CSCIs

• As We Will Soon See, Correlation Tends to Increase the Variance of the Total-Cost Probability Distribution

• Numerical Values of Correlations are Difficult to Estimate, but That’s Another Story

Page 19: 1 COCOMO II Integrated with Crystal Ball ® Risk Analysis Software Clate Stansbury MCR, LLC cstansbury@mcri.com (703) 506-4600 Prepared for 19 th International.

19

Maximum Possible Underestimation of Total-Cost Sigma

• Percent Underestimated σ When Correlation Assumed to be 0 Instead of (n=# of Input Values)

0

20

40

60

80

100

0 0.1 0.2 0.3 0.4 0.5 0.6 0.7 0.8 0.9 1

Actual Correlation

Perc

ent U

ndere

stim

ate

d

n = 10

n = 30

n = 100n = 1000

0

20

40

60

80

100

0 0.1 0.2 0.3 0.4 0.5 0.6 0.7 0.8 0.9 1

Actual Correlation

Perc

ent U

ndere

stim

ate

d

n = 10

n = 30

n = 100n = 1000

Page 20: 1 COCOMO II Integrated with Crystal Ball ® Risk Analysis Software Clate Stansbury MCR, LLC cstansbury@mcri.com (703) 506-4600 Prepared for 19 th International.

20

Determining Correlations Among COCOMO II Cost Drivers

• Default Correlations to 0.2

• More Detailed Default Correlations?– Higher Correlation Between RELY and DOCU?

– COCOMO II Security Extension Cost Driver Related to Existing Cost Drivers

Page 21: 1 COCOMO II Integrated with Crystal Ball ® Risk Analysis Software Clate Stansbury MCR, LLC cstansbury@mcri.com (703) 506-4600 Prepared for 19 th International.

21

Summary

• Estimator Must Model Uncertainty• Describe Uncertainty by Representing COCOMO

Inputs as Triangular Distributions• Calculate Implications of Uncertainty by Using

Monte Carlo or Latin Hypercube Simulations to Perform COCOMO II Algorithm

• Consider Correlation Among CSCI Risks and Costs

• Professional Software, e.g., Crystal Ball, is Available to do Computations

Page 22: 1 COCOMO II Integrated with Crystal Ball ® Risk Analysis Software Clate Stansbury MCR, LLC cstansbury@mcri.com (703) 506-4600 Prepared for 19 th International.

22

AcronymsAA Assessment and Assimilation

AT Automatically Translated code

CB Crystal Ball

CM Percent of Code Modified

COCOMO Constructive Cost Model

CSCI Computer Software Cost Integrator

DM Percent of Design Modified

EI External Input

EIF External Interface File

EO External Output

EQ External Inquiry

ILF Internal Logical File

IM Effort for Integration

KSLOC Thousands of Source Lines of Code

MS Microsoft

O,M,P Optimistic, Most Likely, Pessimistic

SCED Schedule compression/expansion rating

SLOC Source Lines of Code

SU Software

UFP Unadjusted Function Point

UNFM Programmer Unfamiliarity rating

USC University of Southern California

WBS Work Breakdown Structure

Page 23: 1 COCOMO II Integrated with Crystal Ball ® Risk Analysis Software Clate Stansbury MCR, LLC cstansbury@mcri.com (703) 506-4600 Prepared for 19 th International.

23

Backup Slides

Page 24: 1 COCOMO II Integrated with Crystal Ball ® Risk Analysis Software Clate Stansbury MCR, LLC cstansbury@mcri.com (703) 506-4600 Prepared for 19 th International.

24

Correlation Matters

• Suppose for Simplicity

– There are n Cost Elements

– Each

– Each Corr(Ci ,Cj ) = < 1

– Total Cost

Var C i 2

Var C Var C Var C Var Cik

n

i

n

j i

n

i j

1 1

1

12

n n n 2 21

n n 2 1 1

Correlation 0 1

VarC n2 n n 21 1 n22

Page 25: 1 COCOMO II Integrated with Crystal Ball ® Risk Analysis Software Clate Stansbury MCR, LLC cstansbury@mcri.com (703) 506-4600 Prepared for 19 th International.

25

Correlation Matrices Allow User to Adjust Correlations

• One Matrix for Each CSCI Allows Estimator to Set Correlations Among Cost Drivers for that CSCI

How to Record Inter-CSCI Information?

• One Matrix for All Inputs in All CSCI’sDifficult for User (and Developer!) to Manipulate

• One Matrix for Project with which the Estimator Sets Correlations Among the Efforts of the CSCI’s

But CSCI Costs are Not Inputs (aka Assumptions). Only Inputs Can Be Correlated

Page 26: 1 COCOMO II Integrated with Crystal Ball ® Risk Analysis Software Clate Stansbury MCR, LLC cstansbury@mcri.com (703) 506-4600 Prepared for 19 th International.

26

Selection of Correlation Values• “Ignoring” Correlation Issue is Equivalent to

Assuming that Risks are Uncorrelated, i.e., that All Correlations are Zero

• Square of Correlation (namely, R2) Represents Percentage of Variation in one WBS Element’s Cost that is Attributable to Influence of Another’s

• Reasonable Choice of Nonzero Values Brings You Closer to Truth

• Most Elements are, in Fact, Pairwise Correlated• 0.2 is at “Knee” of Curve on Previous Charts, thereby

Providing Most of the Benefits at Least Commitment

Correlation % Influenced

0.00 0%0.10 1%0.32 10%0.50 25%0.71 50%

Page 27: 1 COCOMO II Integrated with Crystal Ball ® Risk Analysis Software Clate Stansbury MCR, LLC cstansbury@mcri.com (703) 506-4600 Prepared for 19 th International.

27

Cost-Risk Analysis Works by Simulating System Cost

• In Engineering Work, Computer Simulation of System Performance is Standard Practice, with Key Performance Characteristics Modeled by Monte Carlo Analysis as Random Variables, e.g.

– Data Throughput– Time to Lock– Time Between Data Receipt and Delivery– Atmospheric Conditions

• Cost-Risk Analysis Enables the Cost Analyst to Conduct a Computer Simulation of System Cost

– WBS-element Costs Are Modeled As Random Variables– Total System Cost Distribution is Determined by Monte

Carlo Simulation– Cost is Treated as a Performance Criterion

Page 28: 1 COCOMO II Integrated with Crystal Ball ® Risk Analysis Software Clate Stansbury MCR, LLC cstansbury@mcri.com (703) 506-4600 Prepared for 19 th International.

28

Traditional “Roll-Up” Method (Too Simple)

• Define “Best Estimate” of Each Cost Element to be the Most Likely Cost of that Element

• List Cost Elements in a Work-Breakdown Structure (WBS)

– Calculate “Best Estimate” of Cost for Each Element

– Sum All Best Estimates– Define Result to be “Best Estimate” of Total

Project Cost

• Unfortunately, It Turns Out That Things are Not as Simple as They Seem – There are a Lot of Problems with This Approach