Top Banner
1 Chapter 11. Order Point Inventory Control Methods Homework problems: 1, 2, 3, 5.
27

1 Chapter 11. Order Point Inventory Control Methods Homework problems: 1, 2, 3, 5.

Mar 29, 2015

Download

Documents

Ayden Hollands
Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Page 1: 1 Chapter 11. Order Point Inventory Control Methods Homework problems: 1, 2, 3, 5.

1

Chapter 11. Order Point Inventory Control Methods

Homework problems: 1, 2, 3, 5.

Page 2: 1 Chapter 11. Order Point Inventory Control Methods Homework problems: 1, 2, 3, 5.

Order Point Inventory Control Methods

Order point methods are used to determine appropriate order quantities and timing for individual independent-demand product items that are characterized by random customer demand.Performed well, these inventory management functions can provide appropriate levels of customer service without excess levels of inventory and/or cost.

Page 3: 1 Chapter 11. Order Point Inventory Control Methods Homework problems: 1, 2, 3, 5.

3

1. Basic Concepts

Independent DemandWhen item’s demand is influenced by market conditions and is not related to (i.e., is “independent” of) production decision for any other item.Wholesale and retail merchandise (finished goods), service industry inventory, end-item and replacement-part inventories, spare-parts, MRO (maintenance, repair, and operating) supplies. Demand must be forecast

Dependent DemandWhen item’s demand derives from (i.e., “depend” on) the production decisions for its parents. All intermediate and purchased items in manufacturing.Demand must be derived.

Page 4: 1 Chapter 11. Order Point Inventory Control Methods Homework problems: 1, 2, 3, 5.

4

Functions of the 4 Types of Inventory

Cycle Stock/InventoryCreated when we place orders LESS frequently.The longer the cycle, the bigger the Q (order quantity).Helps with customer service, ordering cost, setups, transportation rates, and material costs.Equal to Q/2, when demand rate is constant and uniform.

Safety Stock/InventoryCreated when we place an order sooner than when it is needed, or more than the expected demand during lead time. . Protects against three types of uncertainty: demand, lead time, and supply.Helps with customer service and missing parts.

Page 5: 1 Chapter 11. Order Point Inventory Control Methods Homework problems: 1, 2, 3, 5.

5

Functions of Inventory

Anticipation Stock/InventoryCreated by overproducing during the slack season or overbuying before a price increase or capacity shortage.Helps absorb uneven rates of demand and supply.

Pipeline (transit) Stock/InventoryCreated by the time spent to move and produce materials. Can be in any of three stages:

Inbound, within the plant, outboundEqual to d x L, where,

d: avg. demand per period L: the # of periods in the lead time to move between two

points.

Page 6: 1 Chapter 11. Order Point Inventory Control Methods Homework problems: 1, 2, 3, 5.

6

Functions of Inventory ExampleManagement has decided to establish three distribution centers (DCs) in different region of the country to save on transportation costs. For one of the products, the average weekly demand at each DC will be 50 units. The product is valued at $650 per unit. Average shipment sizes into each DC will be 350 units per trip. The average lead time will be two weeks. Each DC will carry one week’s supply as safety stock, since the demand during the lead time sometimes exceed its average of 100 units (50x2). Anticipation inventory should be negligible.

a) How many dollars of cycle inventory will be held at each DC, on the average?

b) How many dollars of safety stock will be held at each DC?c) How many dollars of pipeline inventory will be in transit for each

DC, on the average?d) How much inventory, on the average, will be held at each DC?e) Which type of inventory is your first candidate for reduction?

Page 7: 1 Chapter 11. Order Point Inventory Control Methods Homework problems: 1, 2, 3, 5.

7

Functions of Inventory Example

Solution:a) Cycle Inventory = (350/2)($650)=$113,750.b) Safety stock = (1)(50)($650)=$32,500.c) Pipeline inventory = (2)(50)($650)= $65,000d) Inventory at DC = cycle + safety + pipeline =

$211,250e) Cycle inventory

Page 8: 1 Chapter 11. Order Point Inventory Control Methods Homework problems: 1, 2, 3, 5.

8

Inventory Reduction

Type Primary Lever Secondary

Cycle Reduce Q Reduce ordering and setup

costs.

Safety Place orders closer Improve forecasting.to the time when Reduce lead time.they must be received Reduce uncertainty.

Anticipation Vary production rate Level out demand rates.to follow demand rate

Pipeline Cut production- Forward inventory positioning.

distribution lead time Selection of suppliers andcarriers.Reduce Q.

Page 9: 1 Chapter 11. Order Point Inventory Control Methods Homework problems: 1, 2, 3, 5.

9

Where are the Inventories?

Inventories are held in: manufacturing (36%), retail trade (25%), wholesales trade (23%), farm (8%), other (8%).

Inventory Total:3.6 monthly sales in 1970s

3.1 monthly sales in 1980s

2.7 monthly sales in 1990s (> $1 trillion)

Page 10: 1 Chapter 11. Order Point Inventory Control Methods Homework problems: 1, 2, 3, 5.

10

2. Management Issues – Two Fundamental Inventory Questions/Decisions

1. How Much?2. When?

See. Figure 11.2 for models

Page 11: 1 Chapter 11. Order Point Inventory Control Methods Homework problems: 1, 2, 3, 5.

11

Inventory System Performance

Inventory MeasuresStart with physical count in units, volume, or weight.Average aggregate inventory value (total value of all items held in inventory)Weeks of Supply. Divide average aggregate inventory value by weekly sales (at cost, i.e., cost of goods sold) of finished goods. Inventory Turnover (turns). Divide annual sales (at cost, i.e., cost of goods sold) by average aggregate inventory value.Fill Rate. The % of units immediately available when requested by customers, measuring customer service level.

Page 12: 1 Chapter 11. Order Point Inventory Control Methods Homework problems: 1, 2, 3, 5.

12

Inventory System Performance Example

A recent accounting statement showed average aggregate inventories (RM+WIP+FG) to be $6,821,000. This year’s cost of goods sold is $19.2 million. The company operates 52 weeks per year. How many weeks of supply are being held? What is the inventory turnover?

Solution:

Weeks of supply= ($6,821,000)/($19,200,000)/52=18.5 weeks.

Inventory turnover= ($19,200,000)/($6,821,000)= 2.8 turns.

Page 13: 1 Chapter 11. Order Point Inventory Control Methods Homework problems: 1, 2, 3, 5.

13

Inventory Costs =

Ordering costs: physical counting, paperwork, fax/phone, receipt verification, etc. e.g., $95/order vs. $7/order

+Holding/carrying costs: cost of capital (5~35%), taxes, insurance, obsolescence, warehousing, etc. Typically annual holding costs = 20~40%.

+Stockout/shortage costs: back order, lost sales, lost goodwill. Customer service level ↔ inventory investment

+ Cost of items

Page 14: 1 Chapter 11. Order Point Inventory Control Methods Homework problems: 1, 2, 3, 5.

14

Five Assumptions of EOQ

Demand is known and constant

Whole lots ordering

Only two relevant costs

Item independence

Certainty in lead time and supply

Page 15: 1 Chapter 11. Order Point Inventory Control Methods Homework problems: 1, 2, 3, 5.

15

Economic Order Quantity (EOQ)

A: annual demand

Q: order quantity

CP: ordering (preparation) cost per order

CH: carrying cost per unit per year

Annual inventory carrying cost= (Q/2)·CH

Annual ordering cost= (A/Q) ·CP

Total annual cost (TAC) = (A/Q)·CP + (Q/2)·CH

Finding the optimal order quantity that minimizes TAC using

Calculus

Observation (Fig 11.4)

Economic time between order (TBO) in weeks = EOQ/(A/52)

Page 16: 1 Chapter 11. Order Point Inventory Control Methods Homework problems: 1, 2, 3, 5.

16

EOQ SensitivityWhat happens to cycle inventory if the demand rate increases?What happens to lot sizes if setup/ordering cost decreases?What happens to lot size if interest rates drop?

How critical are errors in estimating A, CP, CH ?Overestimate A by 300% → overestimate EOQ by 100%Total cost curve is relatively “flat” around the minimum cost ordering quantity, implying total cost performance is relatively insensitive to small changes in order quality around the optimal order quantity.EOQ is robust.When setup cost → 0, EOQ → small → small lot production in JIT.

Page 17: 1 Chapter 11. Order Point Inventory Control Methods Homework problems: 1, 2, 3, 5.

17

Reorder Timing DecisionsUnder the (Q,R) rule, an order for a fixed quantity (Q) is placed whenever the stock level reaches a reorder point (R). Reorder point = average demand during the average replenishment lead time + safety stock.

Reorder point is influenced by demand, lead time, demand uncertainty, and lead time uncertainty.When both demand and lead time are constant, reorder point = expected demand during lead time, and no safety stock is needed.

R= d + S

Page 18: 1 Chapter 11. Order Point Inventory Control Methods Homework problems: 1, 2, 3, 5.

18

Reorder Point Decisions:Discrete Distribution of Demand during Lead Time

Safety Stock can be determined using (1) stockout risk or probability or (2) customer service level (fill rate).

Stockout Risk: the probability of not meeting demand during ANY given replenishment

order cycle. e.g., 5% stockout; See Figure 11.5.

Fill Rate (Customer Service Level): the % of demand, measured in units, that can be supplied

directly out of inventory. See Fig. 11.7

Normal Distribution provides a close approximation to a given discrete distribution, facilitating and simplifying the reorder point (and thus safety stock) calculations.

Page 19: 1 Chapter 11. Order Point Inventory Control Methods Homework problems: 1, 2, 3, 5.

Reorder point and Stockout Probability

With a lead time of one day, 95% of cycles will experience demand for 7 or fewer units

Sum of demand probability is 0.05 (5%)

Reorder point of 7 units will provide 5% chance of stockout during a one day lead time

Page 20: 1 Chapter 11. Order Point Inventory Control Methods Homework problems: 1, 2, 3, 5.

Introducing Safety Stock for variable demand

During the replenishment lead time (1 day), demand can range from 1 through 9 units.

If demand during lead time is less than 5 units, inventory reaches a point between b and c.

If demand during the 1 day lead time exceeds 5 units, inventory level reaches a point between c and e.

Average demand=5 units/day

Lead time= 1 day

Page 21: 1 Chapter 11. Order Point Inventory Control Methods Homework problems: 1, 2, 3, 5.

Fig. 7 Determining safety stock for specified service levels

Know how to construct this table

d

RddPQMax

Rd 1

))(()/100(100SL

* Calculated by

d

RddPMax

Rd 1

))(( ⱡ Assuming order quantity (Q) is 5 units; annual demand=1,250

P(d) = probability of a demand of d units during the replenishment lead timedMax = maximum demand during the replenishment lead time

Page 22: 1 Chapter 11. Order Point Inventory Control Methods Homework problems: 1, 2, 3, 5.

Reorder Point Decisions:Continuous Distribution of Demand during Lead Time

The ROP based on a Normaldistribution of lead time demand

Note. Service level is defined differently with continuous demand.

Page 23: 1 Chapter 11. Order Point Inventory Control Methods Homework problems: 1, 2, 3, 5.

Reorder Point Decisions:Continuous Distribution of Demand during Lead Time

Page 24: 1 Chapter 11. Order Point Inventory Control Methods Homework problems: 1, 2, 3, 5.

24

Reorder Point Decisions:Continuous Distribution of Demand during Lead Time

Probability of Stocking Out CriterionConstant demand and variable lead time

R= d x LT + Z·d·σLT

Variable demand and constant lead time

R= d x LT + Z· √LT · σd (cf. equation 11.18)

Variable demand and variable lead time

R= d x LT + Z·√LT· σd2 + d 2 · σ2

LT (cf. equation 11.20)

Where d= average daily or weekly demand,

σd = standard deviation of demand per day or week,

σLT = standard deviation of lead time per day or week

Page 25: 1 Chapter 11. Order Point Inventory Control Methods Homework problems: 1, 2, 3, 5.

25

Reorder Point Decisions: Continuous Demand Example

The injection molding department of a company uses 40 ponds of a powder a day. Inventory is reordered when the amount on hand is 240 pounds. Lead time averages 5 days. It is normally distributed and has a standard deviation of 2 days. a). What is the probability of a stockout during lead time?

b). What reorder point would provide a 5% stockout?

Page 26: 1 Chapter 11. Order Point Inventory Control Methods Homework problems: 1, 2, 3, 5.

26

Reorder Point Decisions

Note that while discrete demand distributions (e.g., Figure 11.5) can be approximated by the continuous Normal distribution for reorder point decisions (e.g., discussions in the section of Continuous Distribution on page 433 and Customer Service Criterion on page 435), the results won’t be optimal.

Thus, when demand is discrete, equation 11.8 should be used. When demand is continuous, the formulas on slide 21 should be used.

Page 27: 1 Chapter 11. Order Point Inventory Control Methods Homework problems: 1, 2, 3, 5.

Principles

The difference between dependent and independent demand must serve as the first basis for determining appropriate inventory management procedures.

Organizational criteria must be clearly established before we set safety stock levels and measure performance.

Savings in inventory-related costs can be achieved by a joint determination of the order point and order quantity parameters.

The functions of inventory are useful principles to apply in determining whether or not inventory reductions can be made.