1 City Commission Workshop for the DRAFT Basis of Design Report December 14, 2015 CRAVEN THOMPSON & ASSOCIATES, INC.
Jan 19, 2016
1
City Commission Workshopfor the
DRAFT Basis of Design Report
December 14, 2015CRAVEN THOMPSON & ASSOCIATES, INC.
2
Basis of Design Report (BODR) Purpose
• A BODR is the Reference Manual for a City to identify, plan for,
finance and construct infrastructure improvements over the course of time. It is supported by realistic planning documents, solid financial policies targeted for the implementation of stated goals and trends on the government’s accomplishments and progress toward these goals.• The BODR allows the City the ability to apply for
Grants and sell Municipal Bonds to finance the Improvements. The BODR is the planning document necessary to secure these types of funding.
• Other sources of financing may include impact fees and usage fees from transporation, water and sewer.
3
Basis of Design Report (BODR) Purpose
• Improvements will be prioritized based on the infrastructure
assessment of each quadrant of the City. However, prioritization needs to be able to adapt when different funding sources
become available for other types of Improvements in lesser prioritized Quadrant.
4
Basis of Design Report (BODR) Preparation Costs
• Typical BODR Consultant Fees:• $500 - $750 per acre for a complete BODR • Includes Water, Wastewater, Storm, Roads,
Sidewalks, Landscaping, Improvements, including Cost Estimates, Phasing and Capacity Analysis
• City of Hallandale Beach is 2,800 acres • BODR fee for Hallandale Beach $ 665,000 - $240
per acre• BODR scope includes all the above items except
Water and Wastewater capacity and design of improvements. The improvement Studies have been completed and the capacity Studies as forthcoming. Only the recommended improvements were included in the Cost Estimate. Conceptual Permitting for the Storm Drainage System is also not included.
5
Basis of Design Report (BODR) CTA BODR Projects
North Central County NIP BODR1,000 Acres
Central County NIP BODR 1,600 Acres
South County NIP BODR 1,800 Acres
Miami Gardens Livable Neighborhood BODR 400 Acres
Hallandale Beach BODR 2,800 Acres
6
Basis of Design Report (BODR)Community Benefit Plan
• The CTA Community Benefit Plan has involved the hiring of
Annette Aristide, a Hallandale Beach Resident and FAU Engineering Student. • Annette has been working part-time on the BODR for
nearly a eleven (11) months and will continue to work on the BODR to its completion. We have committed $15,000
to the CBP for this Project. • She is a Junior with a 3.50 GPA and is expected to graduate in 2017.• Annette is also part of our CBP for the Bluesten Park Project.
66
7
Basis of Design Report (BODR)Elements
Infrastructure Improvements Consist of:• Storm Drainage System• Domestic Wastewater Collection and Transmission
System• Domestic Water Distribution System• Roadways and Sidewalks• Landscape and Streetscape
Other Elements Consist of:• Environmental and Public Impacts • Cost Estimates• Scheduling/Phasing • Regulatory Considerations
8
Basis of Design Report (BODR) Development Process
• A BODR identifies all the elements of Infrastructure Improvements
beginning with an assessment of the existing conditions, followed by the master planning for the proposed subsurface utilities, roadway and sidewalk improvements, including bicycle lanes and bus stops, landscape and hardscape as well as street lighting.• Development of the improvements are derived from
several sources, Current Engineering Standards, Agency Criteria, City Priorities, Maintenance Issues Environmental Concerns and Land Development.
• Once all the improvements are defined, the cost
analysis takes place. • The costs associated with the improvements within the
BODR will be linked to a price index (CPI, ENR 20 Cities, etc.) in order to adjust the costs for the future.
9
Basis of Design Report (BODR)2,800 Acres Divided into Four (4) Quadrants
Components
10
Basis of Design Report (BODR)Storm Drainage System
11
Basis of Design Report (BODR)Wastewater Collection and Transmission System
12
Basis of Design Report (BODR)Water Distribution System
13
Basis of Design Report (BODR)Roadways, Bike Lanes & Sidewalks
14
Basis of Design Report (BODR)Roadways, Bike Lanes & Sidewalks
15
Basis of Design Report (BODR) Priority and approach
• Based on the assessment of each Quadrant’s existing infrastructure
and needs to comply with current Standards the order of priority is as follows:• Southwest• Northwest• Northeast • Southeast
• To implement the construction of the Improvements it is recommended to complete one Quadrant at a time. This will allow for disruption to be localized in one section of the City and not spread throughout.
• Each Quadrant should be further divided into four (4) Bid Packages less than 200 acres in size. Bid Packages of this size are manageable from a constructability, funding and competitive competition standpoint.
16
Basis of Design Report (BODR)Preliminary Cost Estimate
17
Basis of Design Report (BODR) Additional Elements not included in BODR
The following Reports, Studies and Revisions are not included in the BODR due to timing and scoping of BODR.
• Transit Mobility Study • Comprehensive Plan Amendment • Water and Sewer Capacity Study • Storm Drainage Pump Station (SW Quadrant)
18
Basis of Design Report (BODR) Next Steps
• Draft BODR due in January 2016• Final BODR due in May 2016• City Commission Adopt BODR • Determine Funding Options • Engineering Design of Quadrants (12 Months per Bid
Package)• Public Involvement Phase during Design Period • Permitting and Bidding Assistance (4 Months)• Construction (18 Months per Bid Package)