7/24/2019 0810 Power Swing Relaying in the Texas Panhandle - An Out-Of-Step Odyssey FINAL 03312015
1/56
Power Swing Relaying
in the Texas Panhandle
An Out
-
Of
-
Step Odyssey
Presented by Kevin W. Jones, P.E.
Principal System Protection Engineer
68th Annual Conference for Protective Relay Engineers
March 31, 2015
7/24/2019 0810 Power Swing Relaying in the Texas Panhandle - An Out-Of-Step Odyssey FINAL 03312015
2/56
2
Outline
History of the Southwestern Public ServiceCompany (SPS) System
Brief Review of Power Swing Basics
Early SPS Power Swing Philosophy Modern SPS Power Swing Philosophy
Early Philosophy in the Modern World
Conclusions
7/24/2019 0810 Power Swing Relaying in the Texas Panhandle - An Out-Of-Step Odyssey FINAL 03312015
3/56
3
SPS System History
Company history began as anelectric franchise in 1904 inRoswell, NM
By the early 1930s, SPS had
expanded throughout the TexasPanhandle and Texas SouthPlains
The southeast New Mexicoregion was electrically isolatedfrom the Texas region until1946
Electrically
Isolated
7/24/2019 0810 Power Swing Relaying in the Texas Panhandle - An Out-Of-Step Odyssey FINAL 03312015
4/56
4
SPS System History
In the Fall of 1946, SPS placedits first 115 kV line in servicefrom Carlsbad, New Mexico toDenver City, Texas
This line stretched 109 milesand completed theinterconnection of all the SPSservice territory
UFO crash in June, 1947 nearRoswell???
109 Mile 115 kV
Transmission
Line
7/24/2019 0810 Power Swing Relaying in the Texas Panhandle - An Out-Of-Step Odyssey FINAL 03312015
5/56
5
SPS System History
The electrical system continuedto grow through the 1950s andearly 1960s
The SPS system remained
isolated from the rest of theEastern grid
7/24/2019 0810 Power Swing Relaying in the Texas Panhandle - An Out-Of-Step Odyssey FINAL 03312015
6/56
6
SPS System History
In May 1963, the 115 kV linefrom Guymon, Oklahoma toLiberal, Kansas wassynchronized and closed tyingSPS to the Eastern Interconnect
for the first time
Too weak to be left closedpermanently
7/24/2019 0810 Power Swing Relaying in the Texas Panhandle - An Out-Of-Step Odyssey FINAL 03312015
7/56
7
SPS System History
In 1964, a major outage foreverchanged SPSs approach to system-wide protection
A large Amarillo generating unit
tripped while another unit was off-line for maintenance
The northsouth tie lines tripped,resulting in a Texas North blackout
7/24/2019 0810 Power Swing Relaying in the Texas Panhandle - An Out-Of-Step Odyssey FINAL 03312015
8/56
8
SPS System History
Out-of-step tripping was allowed toforce islanding at strategic locationsto create three load/generation
islands PSB was installed on all looped
transmission lines
Under frequency relaying wasinstalled throughout the system at
three steps
About 10% of system load was to beshed at each UF step
Texas
North
New
Mexico
Texas
South
1964 Lessons Learned
7/24/2019 0810 Power Swing Relaying in the Texas Panhandle - An Out-Of-Step Odyssey FINAL 03312015
9/56
9
SPS System History
In May 1972, SPS connected to theEastern Interconnect via a new 230kV line from Amarillo, Texas to Elk
City, Oklahoma From 1983 to 1985, 11 tie line
power swing trips occurred,resulting in islanding with theEastern Interconnect and UF loadshed
Five events were caused by theloss of a single 350 MW generationunit
Growing Pains
7/24/2019 0810 Power Swing Relaying in the Texas Panhandle - An Out-Of-Step Odyssey FINAL 03312015
10/56
10
SPS System History
By 1985, the first 345 kV line wasbuilt from Abernathy, Texas toOklaunion, Texas
This new line strengthened the SPS
connection to the EasternInterconnect, allowing the 115 kVties to be operated closed
This stronger system stabilized theSPS system, and no power swingtrips occurred again until an event in1996 and another event in 2008
7/24/2019 0810 Power Swing Relaying in the Texas Panhandle - An Out-Of-Step Odyssey FINAL 03312015
11/56
11
SPS System History
11
In 1996, A 230 kV bus fault resultedin the loss of about 1000 MW ofgeneration and the loss of nineinternal 230 kV transmission lines
All the Eastern Interconnect andTexas North to Texas South tie linestripped
All levels of UFLS tripped
75% (~2000 MW) of system load waslost by UFLS and tie line trips
This is the largest system outage tothe SPS system
Stronger System, Test #1
7/24/2019 0810 Power Swing Relaying in the Texas Panhandle - An Out-Of-Step Odyssey FINAL 03312015
12/56
SPS System History
12
Stronger System, Test #2 In 2008, a loss of 800 MW of
generation caused EasternInterconnect tie line trips
The tie line trips resulted in a decayof system frequency, resulting inlevel 1 UFLS tripping (59.3 Hz)
Around 650 MW of load was shed(about 15% of system load)
7/24/2019 0810 Power Swing Relaying in the Texas Panhandle - An Out-Of-Step Odyssey FINAL 03312015
13/56
13
SPS System History
Today, the SPS connection to theEastern Interconnect has beenfurther strengthened by the addition
of three 345 kV lines
SPSs islanding scheme has beentested and proven to preventsystem-wide blackouts
The increased strengthening of the
SPS system has resulted in lessfrequent islanding events
Strongest System
7/24/2019 0810 Power Swing Relaying in the Texas Panhandle - An Out-Of-Step Odyssey FINAL 03312015
14/56
14
Power Swing Basics
What is a power swing?
Power Swing: a variation in three
phase power flow which occurs
when the generator rotor anglesare advancing or retarding relative
to each other in response to
changes in load magnitude and
direction, line switching, loss of
generation, faults, and other
system disturbances [1].
7/24/2019 0810 Power Swing Relaying in the Texas Panhandle - An Out-Of-Step Odyssey FINAL 03312015
15/56
Power Swing Basics
What causes power swings?
15
Faults
o Generators accelerate until fault clears
Loss of Loado Generators accelerate Pm > Pe
Loss of Generation
o Generators decelerate Pm < Pe
Switching (line, capacitor, inductor, etc.)o Changes in power flow affect generator
output
7/24/2019 0810 Power Swing Relaying in the Texas Panhandle - An Out-Of-Step Odyssey FINAL 03312015
16/56
Power Swing Basics
Stable power swing (generator)
16
Rotor Angle
(degrees)
Time (seconds)
Angle damps out with time
0
120
System Angle < 120 degrees
7/24/2019 0810 Power Swing Relaying in the Texas Panhandle - An Out-Of-Step Odyssey FINAL 03312015
17/56
Power Swing Basics
Un-stable power swing (generator)
17
Time (seconds)
0
180
Rotor Angle
(degrees)
120
Angle continues to
increase with time
System Angle > 120 degrees
Pole Slip
7/24/2019 0810 Power Swing Relaying in the Texas Panhandle - An Out-Of-Step Odyssey FINAL 03312015
18/56
Power Swing Basics
Effects of power swings
18
Relays can trip undesirably for stable power swings if not
set properly
Generators can be damaged after they slip a pole during
unstable power swings Breakers can be damaged if they try to open during
unstable power swings if the system angle is near 180
degrees
7/24/2019 0810 Power Swing Relaying in the Texas Panhandle - An Out-Of-Step Odyssey FINAL 03312015
19/56
19
Power Swing Basics
Power Swing Studies in the R-X Impedance Plane
Data required to perform a power swing study
o Line impedance (ZL)
o Sending end source impedance (ZS)
o Receiving end source impedance (ZR)o Parallel transfer impedance (ZTR)
o System maximum slip rate (Hz or degrees/second)
ZS ZR
ZTR
ZL
7/24/2019 0810 Power Swing Relaying in the Texas Panhandle - An Out-Of-Step Odyssey FINAL 03312015
20/56
20
Power Swing Basics
Line Impedance
Sending end source
impedance
Receiving end
source impedance
System Impedance
in the R X Plane
Total system source
impedance
Equal emf power
swing trajectory
Equal emf stabilityboundary
7/24/2019 0810 Power Swing Relaying in the Texas Panhandle - An Out-Of-Step Odyssey FINAL 03312015
21/56
21
Power Swing Basics
System Impedance
in the R X Plane
ES
ER
ES > ER
ES = 1.0 p.u.
ER = 0.7 p.u.
ES / ER = 1.43
ES < ERES = 0.7 p.u.
ER
= 1.0 p.u.
ES / ER = 0.7
ES = ER
ES / ER = 1.0
7/24/2019 0810 Power Swing Relaying in the Texas Panhandle - An Out-Of-Step Odyssey FINAL 03312015
22/56
22
Power Swing Basics
Slip Rate Calculation:
Inner angle Ai
Outer angle Ao
=( ) ()
360
()
=(120 90) 60()
360
2.0()
= 2.5
7/24/2019 0810 Power Swing Relaying in the Texas Panhandle - An Out-Of-Step Odyssey FINAL 03312015
23/56
23
Power Swing Basics
23
PSB timer starts
here when outer
blinder is entered
PSB timer expires
before inner blinder is
reached blocking Z1
and Z2
Swing ends and new
steady state operatingpoint is achieved
Steady state load
operating point
pre-swing
PSB Example:
7/24/2019 0810 Power Swing Relaying in the Texas Panhandle - An Out-Of-Step Odyssey FINAL 03312015
24/56
24
Power Swing Basics
OST Example:
OST timer starts
here when outer
blinder is entered
OST timer expires
before inner blinder is
reached
Breaker trips as the
system angle is getting
smaller
Steady state load
operating point
pre-swing
OST armed to trip on-the-way-out when inner blinder is
entered (can also trip here)
Systems slip-a-pole where
the system angle is 180
degrees
TOWO occurs whenswing leaves inner
blinder
7/24/2019 0810 Power Swing Relaying in the Texas Panhandle - An Out-Of-Step Odyssey FINAL 03312015
25/56
25
Early SPS Power Swing Philosophy
Power Swing Tools of the Early Years
Prior to 1962, graph paper, slide rules and DCcalculating boards were used
Stability studies were run off-site on AC networkanalyzers
In 1962, SPS used an IBM 1620 computer to run loadflow, short circuit and stability studies
7/24/2019 0810 Power Swing Relaying in the Texas Panhandle - An Out-Of-Step Odyssey FINAL 03312015
26/56
26
Early SPS Power Swing Philosophy
Early PSB (Mho) Relay Settings Philosophy
Only block tripping of 3-phase elements on zone 1and zone 2 relays
Set PSB mho concentric about zone 2 The PSB timer was fixed at 3 to 4 cycles, depending
on manufacturer
7/24/2019 0810 Power Swing Relaying in the Texas Panhandle - An Out-Of-Step Odyssey FINAL 03312015
27/56
27
Early SPS Power Swing Philosophy
Early PSB (Mho) Relay Settings Philosophy
The first PSB philosophy seta buffer zone of half zone 2around zone 2
As zone 2 grew, the gapbetween the relays grewproportionally
This philosophy allowed forhigher slip rates, but less line
loadability This philosophy remained
until about the mid 1990s(~40 years)
7/24/2019 0810 Power Swing Relaying in the Texas Panhandle - An Out-Of-Step Odyssey FINAL 03312015
28/56
28
Early SPS Power Swing Philosophy
Early PSB (Mho) Relay Settings Philosophy
The next philosophy set theoffset mho a fixed 2-ohmssecondary separation from
zone 2
With this philosophy, as thezone 2 grew, the gap betweenzone 2 and the PSB relaydecreased
This philosophy allowed forbetter line loadability, butlower slip rates
7/24/2019 0810 Power Swing Relaying in the Texas Panhandle - An Out-Of-Step Odyssey FINAL 03312015
29/56
29
Early SPS Power Swing Philosophy
Early OST Relay Settings Philosophy
Identify lines to be tripped to form balancedload/generation islands
One end of line was typically tripped to keep tappedload energized or to keep the line energized for VARsupport
OST Philosophy in a nutshell:
Set Per I.M.
7/24/2019 0810 Power Swing Relaying in the Texas Panhandle - An Out-Of-Step Odyssey FINAL 03312015
30/56
30
Early SPS Power Swing Philosophy
Early OST Relay Settings Philosophy
OST Relays:
Concentric mho
7/24/2019 0810 Power Swing Relaying in the Texas Panhandle - An Out-Of-Step Odyssey FINAL 03312015
31/56
31
Early SPS Power Swing Philosophy
Early OST Relay Settings Philosophy
OST Relays:
Dual blinder
Inner blinders set between arc
impedance region and 120 degrees
(120 150 degrees typically)
Arc Impedance
Region
Outer blinders set to
accommodate a
3.33 Hz slip rate
=(144.5 84.0) 60()
360
3.0()
= 3.36
7/24/2019 0810 Power Swing Relaying in the Texas Panhandle - An Out-Of-Step Odyssey FINAL 03312015
32/56
32
Early SPS Power Swing Philosophy
Early OST Relay Settings Philosophy
OST Relays:
Lens
Outer tomato set at70 degrees
Middle circle set at
108 degrees
Inner lens set at
151 degrees
Reach set beyond
system impedance
7/24/2019 0810 Power Swing Relaying in the Texas Panhandle - An Out-Of-Step Odyssey FINAL 03312015
33/56
33
Modern SPS Power Swing Philosophy
Power Swing Tools of the Modern Years
Short circuit programmacro to plot reducedsystem impedance and
theoretical swingtrajectories
7/24/2019 0810 Power Swing Relaying in the Texas Panhandle - An Out-Of-Step Odyssey FINAL 03312015
34/56
34
Modern SPS Power Swing Philosophy
Power Swing Tools of the Modern Years
Out-of-step analysisspreadsheet
7/24/2019 0810 Power Swing Relaying in the Texas Panhandle - An Out-Of-Step Odyssey FINAL 03312015
35/56
35
Modern SPS Power Swing Philosophy
Power Swing Tools of the Modern Years
Out-of-step COMTRADE filecalculator using MathCAD
COMTRADE file play-backthrough relay using test set
7/24/2019 0810 Power Swing Relaying in the Texas Panhandle - An Out-Of-Step Odyssey FINAL 03312015
36/56
36
Modern SPS Power Swing Philosophy
Modern PSB Relay Settings Philosophy
PSB Major Considerations
NERC PRC-023 load limit
o Outer blinder must not encroach upon load region
Worst case system slip rate (Hz)
o Typically 2-5 Hz for stable swings
Worst case expected arc impedance
o Inner blinder must not be set too close to arc
impedance region if used to supervise Z1 or Z2tripping
7/24/2019 0810 Power Swing Relaying in the Texas Panhandle - An Out-Of-Step Odyssey FINAL 03312015
37/56
37
Modern SPS Power Swing Philosophy
Modern PSB Relay Settings Philosophy
37
Set outer PSB blinders
just inside the NERC
PRC-023 limit
7/24/2019 0810 Power Swing Relaying in the Texas Panhandle - An Out-Of-Step Odyssey FINAL 03312015
38/56
38
Modern SPS Power Swing Philosophy
Modern PSB Relay Settings Philosophy
Set inner PSB blinders
just outside zone 2
phase mho circle
7/24/2019 0810 Power Swing Relaying in the Texas Panhandle - An Out-Of-Step Odyssey FINAL 03312015
39/56
39
Set top inner blinder a
percentage BEYOND
the apparent impedance
for a L-L fault at the
remote bus
Why???
Modern SPS Power Swing Philosophy
Modern PSB Relay Settings Philosophy
7/24/2019 0810 Power Swing Relaying in the Texas Panhandle - An Out-Of-Step Odyssey FINAL 03312015
40/56
40
Fault at end of the line could fall
between inner and outer top
blinders, allowing the OOS block
timer to expire before the Z2
timer, thus delaying the Z2 trip
until the negative sequence
unblock timer times out!
This would be considered a slow
trip mis-operation.
Modern PSB Relay Settings Philosophy
Modern SPS Power Swing Philosophy
7/24/2019 0810 Power Swing Relaying in the Texas Panhandle - An Out-Of-Step Odyssey FINAL 03312015
41/56
41
Set top outer blinder to 0.1 ohms
secondary higher than top inner
blinder
Set bottom blinders to mirror top
blinders (current philosophy)
Modern SPS Power Swing Philosophy
Modern PSB Relay Settings Philosophy
7/24/2019 0810 Power Swing Relaying in the Texas Panhandle - An Out-Of-Step Odyssey FINAL 03312015
42/56
42
PSB spreadsheet final graph
Modern PSB Relay Settings Philosophy
Modern SPS Power Swing Philosophy
Set OOS block time delay to
achieve a slip rate of at least 2.5
Hz (current philosophy)
Set higher than minimum distanceelement operating time based
upon SIR (see relay instruction
manuals)
7/24/2019 0810 Power Swing Relaying in the Texas Panhandle - An Out-Of-Step Odyssey FINAL 03312015
43/56
43
Modern SPS Power Swing Philosophy
Modern OST Relay Settings Philosophy OST Major Considerations
NERC PRC-023 load limit
Worst case system slip rate (Hz)
o Typically 2-10+ Hz for un-stable swings
Worst case expected arc impedance
Slow evolving faults
o OST time delay should be > 1.5 cycles!!!
7/24/2019 0810 Power Swing Relaying in the Texas Panhandle - An Out-Of-Step Odyssey FINAL 03312015
44/56
44
Modern SPS Power Swing Philosophy
Modern OST Relay Settings Philosophy
OST Settings
Outer blinder settings are set the same as PSB blinders
Inner blinder set between arc impedance zone and 120
degree system angle
Top and bottom blinders should be set to account for areasonable worst case weak system
Set for minimum slip rate of 3 Hz (current philosophy)
7/24/2019 0810 Power Swing Relaying in the Texas Panhandle - An Out-Of-Step Odyssey FINAL 03312015
45/56
45
Modern SPS Power Swing Philosophy
Modern OST Relay Settings Philosophy
Final actual in-service settings
7/24/2019 0810 Power Swing Relaying in the Texas Panhandle - An Out-Of-Step Odyssey FINAL 03312015
46/56
46
Modern SPS Power Swing Philosophy
Modern OST Relay Settings Philosophy
Final actual in-service settings
Arc Impedance
Region
Inner Blinder
Supervision of
Z1 and Z2Required!
=
(147.6 93.0) 60()
360
2.0()
= 4.55
Supervise Breaker Tripping
with Outer Blinder
7/24/2019 0810 Power Swing Relaying in the Texas Panhandle - An Out-Of-Step Odyssey FINAL 03312015
47/56
47
Modern SPS Power Swing Philosophy
Modern OST Relay Settings Philosophy
NERC PRC-026
7/24/2019 0810 Power Swing Relaying in the Texas Panhandle - An Out-Of-Step Odyssey FINAL 03312015
48/56
48
Early Philosophy in the Modern World
SPS still has over 100 Electromechanical PSB relays inservice
NERC PRC-023 will be effective for 100-200 kV lineswithin the next couple of years
Some of these relays will have to be evaluated toensure they comply with PRC-023
7/24/2019 0810 Power Swing Relaying in the Texas Panhandle - An Out-Of-Step Odyssey FINAL 03312015
49/56
49
Early Philosophy in the Modern World
50% of zone 2 buffer philosophy check:
NERC PRC-023
Load Region
NERC Region
Violation!!!
=(98 50) 60()
360
4.0()
= 2.0
23-mile 115 kV line
7/24/2019 0810 Power Swing Relaying in the Texas Panhandle - An Out-Of-Step Odyssey FINAL 03312015
50/56
50
Early Philosophy in the Modern World
50% of zone 2 buffer philosophy check:
=
(114 59) 60()
360
4.0()
= 2.29
Pull Z2 back to
125% of line
impedance
=(114 59) 60()
3603.0()
=3.06
23-mile 115 kV line
7/24/2019 0810 Power Swing Relaying in the Texas Panhandle - An Out-Of-Step Odyssey FINAL 03312015
51/56
51
Early Philosophy in the Modern World
2-ohm secondary separation philosophy check:
= (121 69) 60()360
3.0()
= 2.89
Different 23-mile115 kV line
Good!!!
7/24/2019 0810 Power Swing Relaying in the Texas Panhandle - An Out-Of-Step Odyssey FINAL 03312015
52/56
52
Early Philosophy in the Modern World
2-ohm secondary separation philosophy check:
= (105 79) 60()360
3.0()
= 1.44
Same line, impedancedoubled, ignore load limit
NOT Good!!!
7/24/2019 0810 Power Swing Relaying in the Texas Panhandle - An Out-Of-Step Odyssey FINAL 03312015
53/56
53
Conclusions
Conclusions
SPSs external and internal islanding strategy has beenproven to avoid total system blackouts
Technological advancements in analysis tools have
improved confidence in power swing settings Technological advancements in power swing relaying
have added much needed flexibility to allow relays to beset to achieve desired slip rates
NERC Reliability Standards PRC-023 and PRC-026 will
require re-evaluation of power swing philosophies
7/24/2019 0810 Power Swing Relaying in the Texas Panhandle - An Out-Of-Step Odyssey FINAL 03312015
54/56
54
Conclusions
Moving Forward
SPS will have to re-evaluate its existing islanding schemevalidity with SPP performing Balancing Authorityfunctions
SPS will continue to refine and test power swing settingsusing simulations and COMTRADE play-back
IEEE PSRC Working Group D29 will create a tutorial onsettings conventional blinder power swing settings in asimulated environment
The Odyssey Continues
7/24/2019 0810 Power Swing Relaying in the Texas Panhandle - An Out-Of-Step Odyssey FINAL 03312015
55/56
55
Questions???
7/24/2019 0810 Power Swing Relaying in the Texas Panhandle - An Out-Of-Step Odyssey FINAL 03312015
56/56
56
References
[1] IEEE Power System Relaying Committee WG D6, Power Swing and Out -of-Step Considerations on Transmission Lines, July2005. Available: http://www.pes-psrc.org.