SESSION 7 The Project Cycle Part 1
42

07 PROJECT CYCLE A

Apr 09, 2018

Download

Documents

philip_kock
Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Page 1: 07 PROJECT CYCLE A

8/8/2019 07 PROJECT CYCLE A

http://slidepdf.com/reader/full/07-project-cycle-a 1/42

SESSION 7

The Project Cycle Part 1

Page 2: 07 PROJECT CYCLE A

8/8/2019 07 PROJECT CYCLE A

http://slidepdf.com/reader/full/07-project-cycle-a 2/42

Eight Things You Need to Know 

Page 3: 07 PROJECT CYCLE A

8/8/2019 07 PROJECT CYCLE A

http://slidepdf.com/reader/full/07-project-cycle-a 3/42

Project Definition

Page 4: 07 PROJECT CYCLE A

8/8/2019 07 PROJECT CYCLE A

http://slidepdf.com/reader/full/07-project-cycle-a 4/42

Project Definition

Page 5: 07 PROJECT CYCLE A

8/8/2019 07 PROJECT CYCLE A

http://slidepdf.com/reader/full/07-project-cycle-a 5/42

Project Definition

Page 6: 07 PROJECT CYCLE A

8/8/2019 07 PROJECT CYCLE A

http://slidepdf.com/reader/full/07-project-cycle-a 6/42

Charter

Par Heading

1. Project Need/Opportunity 

2. Final Product/Deliverable

3. H

igh Level Deliver

ables4. Milestones

5.  Limits and Exclusions A ssumptions Potential Barriers

6. S cope statements

In Scope Out of Scope

7. Technical/ Functional Requirements

Page 7: 07 PROJECT CYCLE A

8/8/2019 07 PROJECT CYCLE A

http://slidepdf.com/reader/full/07-project-cycle-a 7/42

Charter

Par Heading

8. Organizational Arr angements Project Governance Project Team Project Reporting A rrangements

9. Stakeholder  A nalysis

10. Budget Estimate

Page 8: 07 PROJECT CYCLE A

8/8/2019 07 PROJECT CYCLE A

http://slidepdf.com/reader/full/07-project-cycle-a 8/42

Charter

³ Thus, the Project Charter providesa broad definition and essentially mandate the project and based on

this it is possible to break down work to be performed (throughthe Work Breakdown Structure),and then to put the work into asequence (with network diagramming) and on a time line

(scheduling, using techniquessuch as the Gant/Schedule BarChart´)

Page 9: 07 PROJECT CYCLE A

8/8/2019 07 PROJECT CYCLE A

http://slidepdf.com/reader/full/07-project-cycle-a 9/42

Project Definition

Broad scope and mandateBroad scope and mandate

Work Breakdown Structure (Work Breakdown Structure (WBSWBS) )

Integrating the WBS with theIntegrating the WBS with theOrganization StructureOrganization Structure

Coding the WBS for the InformationCoding the WBS for the InformationSystemSystem

Page 10: 07 PROJECT CYCLE A

8/8/2019 07 PROJECT CYCLE A

http://slidepdf.com/reader/full/07-project-cycle-a 10/42

Creating the Work Breakdown Structure

Work Breakdown Structure (WBS):

A  hier ar chical outline (map) that identifies theproducts (deliverables) and work elements involved in

a project;

 Defines t he r elationship of the final deliverable(the project) to its sub deliverables, and in turn, their relationships to work packages (collection of elementsrelated to work that must be done);

Best suited for design and build projects that havetangible outcomes rather than process-orientedprojects.

Page 11: 07 PROJECT CYCLE A

8/8/2019 07 PROJECT CYCLE A

http://slidepdf.com/reader/full/07-project-cycle-a 11/42

Creating the Work Breakdown Structure

 WBS

Facilitates evaluation of cost, time, and technicalperformance of the organization on a project

Provides management with information appropriate toeach organizational level

Helps in the development of the organization breakdownstructure (OBS), which assigns project responsibilities toorganizational units and individuals

Helps manage plan, schedule, and budget

Defines communication channels and assists incoordinating the various project elements

Page 12: 07 PROJECT CYCLE A

8/8/2019 07 PROJECT CYCLE A

http://slidepdf.com/reader/full/07-project-cycle-a 12/42

 Work Package

It is output-oriented (not output in itself)in that it:

Defines work ( what);

Identifies time to complete a work package(how long);

Identifies a time-phased budget to complete a

 wor

k package(cost ± linked to a cost cent

r

e); Identifies resources needed to complete a work 

package (how much)

Page 13: 07 PROJECT CYCLE A

8/8/2019 07 PROJECT CYCLE A

http://slidepdf.com/reader/full/07-project-cycle-a 13/42

 Work Package

It is output-oriented (not output in itself)in that it:

Identifies a single person responsible for units

of work ( who); Identifies monitoring points (milestones) for 

measuring success;

Roughly 10

days maximum(80

hour

s) ±experience shows.

Page 14: 07 PROJECT CYCLE A

8/8/2019 07 PROJECT CYCLE A

http://slidepdf.com/reader/full/07-project-cycle-a 14/42

Creating the Work Breakdown Structure

Page 15: 07 PROJECT CYCLE A

8/8/2019 07 PROJECT CYCLE A

http://slidepdf.com/reader/full/07-project-cycle-a 15/42

Creating the Work Breakdown Structure

Page 16: 07 PROJECT CYCLE A

8/8/2019 07 PROJECT CYCLE A

http://slidepdf.com/reader/full/07-project-cycle-a 16/42

Project Definition

Broad scope and mandateBroad scope and mandate

Work Breakdown Structure (Work Breakdown Structure (WBSWBS) )

Integrating the WBS with theIntegrating the WBS with theOrganization StructureOrganization Structure

Coding the WBS for the InformationCoding the WBS for the InformationSystemSystem

Page 17: 07 PROJECT CYCLE A

8/8/2019 07 PROJECT CYCLE A

http://slidepdf.com/reader/full/07-project-cycle-a 17/42

Example

Page 18: 07 PROJECT CYCLE A

8/8/2019 07 PROJECT CYCLE A

http://slidepdf.com/reader/full/07-project-cycle-a 18/42

Project Definition

Page 19: 07 PROJECT CYCLE A

8/8/2019 07 PROJECT CYCLE A

http://slidepdf.com/reader/full/07-project-cycle-a 19/42

The Work-Package

It is output-oriented (not output in itself) in that it:

Defines work ( what);

Identifies time to complete a work package (how long);

Identifies a time-phased budget to complete a work package(cost ± linked to a cost centre);

Identifies resources needed to complete a work package (how much);

Identifies a single person responsible for units of work ( who);

Identifies monitoring points (milestones) for measuringsuccess;

Roughly 10 days maximum (80 hours) ± experience shows.

Page 20: 07 PROJECT CYCLE A

8/8/2019 07 PROJECT CYCLE A

http://slidepdf.com/reader/full/07-project-cycle-a 20/42

Page 21: 07 PROJECT CYCLE A

8/8/2019 07 PROJECT CYCLE A

http://slidepdf.com/reader/full/07-project-cycle-a 21/42

³RingFence´

Page 22: 07 PROJECT CYCLE A

8/8/2019 07 PROJECT CYCLE A

http://slidepdf.com/reader/full/07-project-cycle-a 22/42

Project Definition

Broad scope and mandateBroad scope and mandate

Work Breakdown Structure (Work Breakdown Structure (WBSWBS) )

Integrating the WBS with theIntegrating the WBS with theOrganization StructureOrganization Structure

Coding the WBS for the InformationCoding the WBS for the InformationSystemSystem

Page 23: 07 PROJECT CYCLE A

8/8/2019 07 PROJECT CYCLE A

http://slidepdf.com/reader/full/07-project-cycle-a 23/42

Page 24: 07 PROJECT CYCLE A

8/8/2019 07 PROJECT CYCLE A

http://slidepdf.com/reader/full/07-project-cycle-a 24/42

 1. TY PE FIN A L DELIV ER  A BLE2. TY PE IN SUB DELIV ER  A BLES

Page 25: 07 PROJECT CYCLE A

8/8/2019 07 PROJECT CYCLE A

http://slidepdf.com/reader/full/07-project-cycle-a 25/42

 3. INDENT A LL SUB DELIV ER  A BLES(CRE A TES REL A TIONSHIPS)

Page 26: 07 PROJECT CYCLE A

8/8/2019 07 PROJECT CYCLE A

http://slidepdf.com/reader/full/07-project-cycle-a 26/42

 4. INSERT A ND TY PE T A SKS TH A T A RE REL A TED TO RESPECTIV ESUB DELIV ER  A BLES

Page 27: 07 PROJECT CYCLE A

8/8/2019 07 PROJECT CYCLE A

http://slidepdf.com/reader/full/07-project-cycle-a 27/42

 5. INDENT ACTIVITES TO RELE VA NTSUB-DELIV ER  A BLE

(CRE A TES REL A TIONSHIPS)

Page 28: 07 PROJECT CYCLE A

8/8/2019 07 PROJECT CYCLE A

http://slidepdf.com/reader/full/07-project-cycle-a 28/42

Page 29: 07 PROJECT CYCLE A

8/8/2019 07 PROJECT CYCLE A

http://slidepdf.com/reader/full/07-project-cycle-a 29/42

Page 30: 07 PROJECT CYCLE A

8/8/2019 07 PROJECT CYCLE A

http://slidepdf.com/reader/full/07-project-cycle-a 30/42

Page 31: 07 PROJECT CYCLE A

8/8/2019 07 PROJECT CYCLE A

http://slidepdf.com/reader/full/07-project-cycle-a 31/42

Page 32: 07 PROJECT CYCLE A

8/8/2019 07 PROJECT CYCLE A

http://slidepdf.com/reader/full/07-project-cycle-a 32/42

Page 33: 07 PROJECT CYCLE A

8/8/2019 07 PROJECT CYCLE A

http://slidepdf.com/reader/full/07-project-cycle-a 33/42

Page 34: 07 PROJECT CYCLE A

8/8/2019 07 PROJECT CYCLE A

http://slidepdf.com/reader/full/07-project-cycle-a 34/42

Page 35: 07 PROJECT CYCLE A

8/8/2019 07 PROJECT CYCLE A

http://slidepdf.com/reader/full/07-project-cycle-a 35/42

35

Page 36: 07 PROJECT CYCLE A

8/8/2019 07 PROJECT CYCLE A

http://slidepdf.com/reader/full/07-project-cycle-a 36/42

FIGURE 4.1

SCOPE

RESOUR CES

DELIV ERY 

CLIM A TE

TIME

Page 37: 07 PROJECT CYCLE A

8/8/2019 07 PROJECT CYCLE A

http://slidepdf.com/reader/full/07-project-cycle-a 37/42

Page 38: 07 PROJECT CYCLE A

8/8/2019 07 PROJECT CYCLE A

http://slidepdf.com/reader/full/07-project-cycle-a 38/42

Labor

MaterialDirect Cost

Office rent Electricity 

Indirect Cost

Page 39: 07 PROJECT CYCLE A

8/8/2019 07 PROJECT CYCLE A

http://slidepdf.com/reader/full/07-project-cycle-a 39/42

Labor Material Proratedcosts

Other

Page 40: 07 PROJECT CYCLE A

8/8/2019 07 PROJECT CYCLE A

http://slidepdf.com/reader/full/07-project-cycle-a 40/42

R 100

R 100

R 100

R 300

R 100

R 100

R 100

R 300

R 600

R 600

R 300

R 300

R 900

R 300

R 300

R 300

R 1500 R 1000

R 600R 400

R 100

R 100

R 100

R 100 R 200

R 200

R 200

R 2100

Page 41: 07 PROJECT CYCLE A

8/8/2019 07 PROJECT CYCLE A

http://slidepdf.com/reader/full/07-project-cycle-a 41/42

R 1000

R 600R 400

R 100

R 100

R 100

R 100 R 200

R 200

R 200

Cost Centre