Advanced Engineering Projects Management Dr. Nabil I El Sawalhi Assistant Professor of Construction Management 1 AEPM L6
Sep 05, 2015
Advanced Engineering
Projects Management
Dr. Nabil I El SawalhiAssistant Professor of Construction
Management
1AEPM L6
Costs of Project
The cost of project is divided into two types:
1. The initial capital cost
2. The subsequent operation and
maintenance costs
2AEPM L6
Capital Cost
1. Land acquisition, including assembly, holding and improvement.
2. Planning and feasibility studies.
3. Architectural and engineering design.
4. Construction, including materials, equipment and labor.
5. Field supervision of construction.
3AEPM L6
Capital Cost
6. Construction financing.
7. Insurance and taxes during construction.
8. Owner's general office overhead.
9. Equipment and furnishings not included in construction.
10. Inspection and testing.
AEPM L6 4
Operation and Maintenance Cost
1. Land rent, if applicable.
2. Operating staff.
3. Labor and material for maintenance and
repairs.
4. Periodic renovations.
5. Insurance and taxes.
6. Financing costs.
7. Utilities.
8. Owner's other expenses.
5AEPM L6
In most construction budgets, there is an
allowance for contingencies or
unexpected costs occurring during
construction.
It varies in value from 2.5 % to 10%
according to the nature and complexity of
the project.
6AEPM L6
Types of Construction Cost
Estimates
The required levels of accuracy of
construction cost estimates vary at
different stages of project development
A construction cost estimate serves one of
the three basic functions:
Design;
Bid (Tender) and;
Control.
7AEPM L6
Classification of Capital Cost
Estimates AACE International (formerly the American
Association of Cost Engineers) has
proposed three classifications of cost
estimates. In increasing order of accuracy,
the various major types of estimates
Type Accuracy
Order of magnitude -30% to +50%
Budget -15% to +30%
Definitive -5% to +15% AEPM L6 8
1. Design Estimates
Design estimate is classified as:
1.Screening estimates (or order of magnitude
estimates)
2.Preliminary estimates (or conceptual
estimates)
3.Detailed estimates (or definitive estimates)
4. Engineer's estimates based on plans and
specifications
9AEPM L6
2. Bid Estimates
Bid estimates is usually derived from a
combination of the following approaches.
1. Subcontractor quotations
2. Quantity takeoffs
3. Construction procedures.
10AEPM L6
3. Control Estimates
A control estimate is derived from
available information to establish:
Budget estimate for financing;
Budgeted cost after contracting but prior to
construction;
Estimated cost to completion during the
progress of construction.
11AEPM L6
1.Screening estimates (or order
of magnitude estimates) To find the order of magnitude the
following methods can be used:
1. Judgment
2. cost capacity
3. Parametric
4. Unit Method
AEPM L6 12
2.Conceptual and Preliminary
Estimate
Is made in the early phases of a project
They tell the owner about the initial budget
and feasibility of scope of the project.
It vary from one type of project to another
Most of conceptual estimating methods
are: 1. time - referenced cost indices
2. Cost-capacity factor
3. Parameter CostAEPM L6 13
Cost Indices
It shows changes of cost over time
Some types reflects changes in
technology, methods, and productivity.
Generally they are applied to the
construction phase.
Though they can account for the total
design-construction package
They are periodically published in the
Engineering News RecordAEPM L6 14
Type of Cost Indices
It derived by two different approaches
1. periodically re-prices and total a constant
package of resources that serve input to typical
construction project.
The index is computed by dividing this cost by
cost of resources in a base references period.
For example:
Components: 1088 board feet of limber (2x4,
s4s, 20-city average)
AEPM L6 15
2500 pounds of structural steel shapes, base
mill price
2256 pounds of Portland cement (bulk, 20-
city average)
68.3 hrs of skilled labor (20-city average)
We can convert from one base period to
another as follows:
Current cost= 2730 (assumed)
Base cost (1967)= 676
AEPM L6 16
Index on 1967 base = index to be
converted/ index of 1967 base
Relative to original
(1913=100) base
= 2730/676
2730/676x 100=400%
AEPM L6 17
Opinion
In the absence of data and shortage of time,
there may be no way to evaluate designs
rather than opinion.
The key to opinion estimating is human ware.
The individual is selected to a job because of
his experience, common sense, and
knowledge.
Opinion estimating is done collectively in
conferences.
AEPM L6 18
Cost Capacity Factor
Cost indices focus on cost changes over
time, cost capacity factors apply to
changes in :
Size;
Scope;
Or capacity of projects of similar types.
Non-liner increase in cost with size.
AEPM L6 19
C2 = C1 (Q2/Q1)X
Where c2 = estimated cost of new facility of
capacity Q2
C1 = known cost of facility of capacity Q1
And the exponent X = the cost-capacity factor
for this type of work.
X is empirically derived factor based on well-
documented historical records for different kinds
of projects.
The capacities represented by Q= the size of
capacity
Example: tons of steel per produced by a steel
mill operating at capacity. AEPM L6 20
This cost-capacity equation is often called
the six-tenths rule or the seven-tenths rule
because the exponent, n, has an approximate value of 0.60-0.7 for many
types of plants and equipment.
The use of the cost-capacity formula is
also limited in accuracy because the
exponent generally is not constant and
does change as equipment size increasesAEPM L6 21
For this reason and because of structural
differences as equipment is increased in
size, the formula should generally be
limited for maximum accuracy to capacity
ratios of 2:1 or less and, in any event,
should never be used at ratios above 5:1.
AEPM L6 22
AEPM L6 23
AEPM L6 24
AEPM L6 25
AEPM L6 26
Area Estimate This is prepared depending on the basis of the
area of building, the rate being deducted from the cost of similar building having similar specification, heights and construction in the locality.
It is calculated by finding the area of the building and multiplying by the unit area rate. The area is calculated from the covered area by taking external dimension of the building at the floor level.
Courtyard and other open areas should not be included in the area.
For multistory buildings there are two
methods to use:
A) All floors including basement floor and
roof have an equal cost
B) Basement and roof have different cost.
AEPM L6 27
Example 1.
A building of size 20x35m consist of :
Basement, g floor,1st floor, 2nd floor and roof. And the
total cost of building is 630,000 $. Calulate the cost of
m2 assuming that:
A) all floors including basement and roof have the same
cost
B) cost of basement is 60% of cost of the rest of floors
and cost of roof is 40% of cost of rest floors.
AEPM L6 28
a) Assumption 1
Basement and other floor area = 700x5=3500m2
Cost per m2 = 630,000/3500= 180$
b) Assumption 2
basement area = 700 x .6 = 420m2
Roof area = 700x.4 = 280m2
Other floors = 700x 3 = 2100
Total area = 2800m
Cost of floor =630000/2800 =225$
Cost of basement= 225x0.6 = 135$
Cost of roof = 225x0.4 =$90
AEPM L6 29
AEPM L6 30
Cube Rate Estimate for Building
It is an approximate estimate and it is prepared based on cubical contents of the building.
The cube rate being deducted from the cost of similar building having similar specifications and construction, in the locality.
Cubic rate is more accurate than the area because it considers the height of the building.
Cubic MethodExample (2)
A building of size 40x60m and consist of
basement, g floor, 1st floor , 2nd floor. The height
of the buildings are :
2.8m for basement. 3.0m for all other floors. The
total cost is $2,250,000. Estimate the cost of
cubic meter using the following two
assumptions:
A) the cost of all floors are the same
B) the cost of cubic meter of basement is %60 of
other floorsAEPM L6 31
a) assumption 1 Volume of basement = 40x60x2.8 = 6720m3
Volume of any other floor = 40x60x3 = 7200m3
Total volume of all floors = 6720x1+7200x3= 28,320 m3
Cost of cubic meter = 2,250,000/28320= $ 79,450
b) assumption 2
Volume of basement = 40x60x2.8x0.60= 4032m3
Volume of any other floor = 40x60x3 = 7200m3
Total volume of all floors= 4032x1+7200x3 = 25,632 m3
Cost of cubic meter = 2,250,000/22,632= $ 87,780
AEPM L6 32
4. Unit method
The unit method use historical & quantitative evidence and leads to a cost driver easily understood.
Other names of unit method are:
-average, order of magnitude;
-Lump sum
-Function
-Parameter.
-Module estimating
AEPM L6 33
Unit continued..
It involves various modifications.
Extensions of this method lead to the factor
estimating method.
Examples:
Cost of house per square foot,
Cost of electrical transmission per mile,
Construction cost per hospital bed,
Chemical plant cost per barrel of oil capacity.
AEPM L6 34
Detailed Estimate
Done after approving of conceptual designs and
after most of detailed designs work is complete.
Quantity take-off is done to prepare total
quantities.
The unit price is developed and multiplied by the
total quantities. The resulting sum represent the
estimated direct cost.
The addition indirect cost, plant and equipment,
home office overhead profit and contengency
will develop the total estimated costAEPM L6 35