Top Banner
Advanced Engineering Projects Management Dr. Nabil I El Sawalhi Assistant Professor of Construction Management 1 AEPM L6
35
Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
  • Advanced Engineering

    Projects Management

    Dr. Nabil I El SawalhiAssistant Professor of Construction

    Management

    1AEPM L6

  • Costs of Project

    The cost of project is divided into two types:

    1. The initial capital cost

    2. The subsequent operation and

    maintenance costs

    2AEPM L6

  • Capital Cost

    1. Land acquisition, including assembly, holding and improvement.

    2. Planning and feasibility studies.

    3. Architectural and engineering design.

    4. Construction, including materials, equipment and labor.

    5. Field supervision of construction.

    3AEPM L6

  • Capital Cost

    6. Construction financing.

    7. Insurance and taxes during construction.

    8. Owner's general office overhead.

    9. Equipment and furnishings not included in construction.

    10. Inspection and testing.

    AEPM L6 4

  • Operation and Maintenance Cost

    1. Land rent, if applicable.

    2. Operating staff.

    3. Labor and material for maintenance and

    repairs.

    4. Periodic renovations.

    5. Insurance and taxes.

    6. Financing costs.

    7. Utilities.

    8. Owner's other expenses.

    5AEPM L6

  • In most construction budgets, there is an

    allowance for contingencies or

    unexpected costs occurring during

    construction.

    It varies in value from 2.5 % to 10%

    according to the nature and complexity of

    the project.

    6AEPM L6

  • Types of Construction Cost

    Estimates

    The required levels of accuracy of

    construction cost estimates vary at

    different stages of project development

    A construction cost estimate serves one of

    the three basic functions:

    Design;

    Bid (Tender) and;

    Control.

    7AEPM L6

  • Classification of Capital Cost

    Estimates AACE International (formerly the American

    Association of Cost Engineers) has

    proposed three classifications of cost

    estimates. In increasing order of accuracy,

    the various major types of estimates

    Type Accuracy

    Order of magnitude -30% to +50%

    Budget -15% to +30%

    Definitive -5% to +15% AEPM L6 8

  • 1. Design Estimates

    Design estimate is classified as:

    1.Screening estimates (or order of magnitude

    estimates)

    2.Preliminary estimates (or conceptual

    estimates)

    3.Detailed estimates (or definitive estimates)

    4. Engineer's estimates based on plans and

    specifications

    9AEPM L6

  • 2. Bid Estimates

    Bid estimates is usually derived from a

    combination of the following approaches.

    1. Subcontractor quotations

    2. Quantity takeoffs

    3. Construction procedures.

    10AEPM L6

  • 3. Control Estimates

    A control estimate is derived from

    available information to establish:

    Budget estimate for financing;

    Budgeted cost after contracting but prior to

    construction;

    Estimated cost to completion during the

    progress of construction.

    11AEPM L6

  • 1.Screening estimates (or order

    of magnitude estimates) To find the order of magnitude the

    following methods can be used:

    1. Judgment

    2. cost capacity

    3. Parametric

    4. Unit Method

    AEPM L6 12

  • 2.Conceptual and Preliminary

    Estimate

    Is made in the early phases of a project

    They tell the owner about the initial budget

    and feasibility of scope of the project.

    It vary from one type of project to another

    Most of conceptual estimating methods

    are: 1. time - referenced cost indices

    2. Cost-capacity factor

    3. Parameter CostAEPM L6 13

  • Cost Indices

    It shows changes of cost over time

    Some types reflects changes in

    technology, methods, and productivity.

    Generally they are applied to the

    construction phase.

    Though they can account for the total

    design-construction package

    They are periodically published in the

    Engineering News RecordAEPM L6 14

  • Type of Cost Indices

    It derived by two different approaches

    1. periodically re-prices and total a constant

    package of resources that serve input to typical

    construction project.

    The index is computed by dividing this cost by

    cost of resources in a base references period.

    For example:

    Components: 1088 board feet of limber (2x4,

    s4s, 20-city average)

    AEPM L6 15

  • 2500 pounds of structural steel shapes, base

    mill price

    2256 pounds of Portland cement (bulk, 20-

    city average)

    68.3 hrs of skilled labor (20-city average)

    We can convert from one base period to

    another as follows:

    Current cost= 2730 (assumed)

    Base cost (1967)= 676

    AEPM L6 16

  • Index on 1967 base = index to be

    converted/ index of 1967 base

    Relative to original

    (1913=100) base

    = 2730/676

    2730/676x 100=400%

    AEPM L6 17

  • Opinion

    In the absence of data and shortage of time,

    there may be no way to evaluate designs

    rather than opinion.

    The key to opinion estimating is human ware.

    The individual is selected to a job because of

    his experience, common sense, and

    knowledge.

    Opinion estimating is done collectively in

    conferences.

    AEPM L6 18

  • Cost Capacity Factor

    Cost indices focus on cost changes over

    time, cost capacity factors apply to

    changes in :

    Size;

    Scope;

    Or capacity of projects of similar types.

    Non-liner increase in cost with size.

    AEPM L6 19

  • C2 = C1 (Q2/Q1)X

    Where c2 = estimated cost of new facility of

    capacity Q2

    C1 = known cost of facility of capacity Q1

    And the exponent X = the cost-capacity factor

    for this type of work.

    X is empirically derived factor based on well-

    documented historical records for different kinds

    of projects.

    The capacities represented by Q= the size of

    capacity

    Example: tons of steel per produced by a steel

    mill operating at capacity. AEPM L6 20

  • This cost-capacity equation is often called

    the six-tenths rule or the seven-tenths rule

    because the exponent, n, has an approximate value of 0.60-0.7 for many

    types of plants and equipment.

    The use of the cost-capacity formula is

    also limited in accuracy because the

    exponent generally is not constant and

    does change as equipment size increasesAEPM L6 21

  • For this reason and because of structural

    differences as equipment is increased in

    size, the formula should generally be

    limited for maximum accuracy to capacity

    ratios of 2:1 or less and, in any event,

    should never be used at ratios above 5:1.

    AEPM L6 22

  • AEPM L6 23

  • AEPM L6 24

  • AEPM L6 25

  • AEPM L6 26

    Area Estimate This is prepared depending on the basis of the

    area of building, the rate being deducted from the cost of similar building having similar specification, heights and construction in the locality.

    It is calculated by finding the area of the building and multiplying by the unit area rate. The area is calculated from the covered area by taking external dimension of the building at the floor level.

    Courtyard and other open areas should not be included in the area.

  • For multistory buildings there are two

    methods to use:

    A) All floors including basement floor and

    roof have an equal cost

    B) Basement and roof have different cost.

    AEPM L6 27

  • Example 1.

    A building of size 20x35m consist of :

    Basement, g floor,1st floor, 2nd floor and roof. And the

    total cost of building is 630,000 $. Calulate the cost of

    m2 assuming that:

    A) all floors including basement and roof have the same

    cost

    B) cost of basement is 60% of cost of the rest of floors

    and cost of roof is 40% of cost of rest floors.

    AEPM L6 28

  • a) Assumption 1

    Basement and other floor area = 700x5=3500m2

    Cost per m2 = 630,000/3500= 180$

    b) Assumption 2

    basement area = 700 x .6 = 420m2

    Roof area = 700x.4 = 280m2

    Other floors = 700x 3 = 2100

    Total area = 2800m

    Cost of floor =630000/2800 =225$

    Cost of basement= 225x0.6 = 135$

    Cost of roof = 225x0.4 =$90

    AEPM L6 29

  • AEPM L6 30

    Cube Rate Estimate for Building

    It is an approximate estimate and it is prepared based on cubical contents of the building.

    The cube rate being deducted from the cost of similar building having similar specifications and construction, in the locality.

    Cubic rate is more accurate than the area because it considers the height of the building.

  • Cubic MethodExample (2)

    A building of size 40x60m and consist of

    basement, g floor, 1st floor , 2nd floor. The height

    of the buildings are :

    2.8m for basement. 3.0m for all other floors. The

    total cost is $2,250,000. Estimate the cost of

    cubic meter using the following two

    assumptions:

    A) the cost of all floors are the same

    B) the cost of cubic meter of basement is %60 of

    other floorsAEPM L6 31

  • a) assumption 1 Volume of basement = 40x60x2.8 = 6720m3

    Volume of any other floor = 40x60x3 = 7200m3

    Total volume of all floors = 6720x1+7200x3= 28,320 m3

    Cost of cubic meter = 2,250,000/28320= $ 79,450

    b) assumption 2

    Volume of basement = 40x60x2.8x0.60= 4032m3

    Volume of any other floor = 40x60x3 = 7200m3

    Total volume of all floors= 4032x1+7200x3 = 25,632 m3

    Cost of cubic meter = 2,250,000/22,632= $ 87,780

    AEPM L6 32

  • 4. Unit method

    The unit method use historical & quantitative evidence and leads to a cost driver easily understood.

    Other names of unit method are:

    -average, order of magnitude;

    -Lump sum

    -Function

    -Parameter.

    -Module estimating

    AEPM L6 33

  • Unit continued..

    It involves various modifications.

    Extensions of this method lead to the factor

    estimating method.

    Examples:

    Cost of house per square foot,

    Cost of electrical transmission per mile,

    Construction cost per hospital bed,

    Chemical plant cost per barrel of oil capacity.

    AEPM L6 34

  • Detailed Estimate

    Done after approving of conceptual designs and

    after most of detailed designs work is complete.

    Quantity take-off is done to prepare total

    quantities.

    The unit price is developed and multiplied by the

    total quantities. The resulting sum represent the

    estimated direct cost.

    The addition indirect cost, plant and equipment,

    home office overhead profit and contengency

    will develop the total estimated costAEPM L6 35