-
ABEINSA 3-Mar-14Abeinsa Business Development Rev.00
S# Description Unit Unit rate Amount # (SAR/unit) (SAR)
1.00 Clearing of the soil 1.01 Site clearance
Clearing and grubbing of site upto 300 mm depth including
uprooting vegetation, grass, bushes, shrubs, saplings and trees
girth up to 300 mm, removal of stumps of trees of all girth size,
stacking of serviceable material and disposal of unserviceable
materials at a designated dumping yard within a lead of 10 km. The
quoted rate shall include all local permits and fees as
applicable.
2.00 Site Grading2.01 Hill cutting
2.01.01Excavation in Hill Area in Soil by Mechanical Means
(Excavation in soil in hilly area bymechanical means including
cutting and trimming of side slopes and disposing of excavatedearth
with all lifts and lead upto 1000 metres)
m3 777,900.00
2.01.02
Excavation in Hilly Area in Ordinary Rock by Mechanical Means
not RequiringBlasting. (Excavation in hilly area in ordinary rock
not requiring ballasting by mechanicalmeans including cutting and
trimming of slopes and disposal of cut material with all lift
andlead upto 1000 metres )
m3 466,800.00
2.01.03
Excavation in Hilly Areas in Hard Rock Requiring control
Blasting (Excavation in hilly areas inhard rock requiring
blasting,by drilling, blasting and breaking,trimming of bottom and
side slopes as per the approved drawings and disposal of cut
material with all lifts and lead upto 1000 metres including
labour,blasting material & permits.)
m3 311,200.00
2.01.04Breaking of boulders into suitable size as required as
per specifications and seggregating the same for Area filling .
m
3 200,000.00
2.01.05 stabilization of quarry faces to prevent landslides and
rock fall during & after the hill cutting . m2 30,000.00
2.01.06construction of temporary earthen storm water drain at
top & bottom of the hill to make dry during the hill cutting
m
3 1,000.00
2.02 Area Filling for Rock fill Embankment ( Raising of Land
from MSL +7m to MSL +1 3.0m)
2.02.01
Area filling for Rockfill embankment in suitable thickness of
layers with selected rock fill of suitable size obtained directly
from hill cutting for above lifts including clearing of areas of
filling spreading, grading for required level and slope, dressing
of filled up area, watering and rolling/compacting with the aid of
mechanical means, carrying outfield compaction tests , plate load
bearing tests and achieving 25 Ton/m2 bearing capacity at MSL +13 m
Lvl, as per sultanate of Oman standard specifications and direction
of the Engineer.
m3 300,000.00
Appendix-5, Exhibit-0Project: 100 MW CCCP or Engine based Power
Plant at Musandam, Oman
Bill of Quantities for Civil & Structural works
Quantity
- m2 - 52,500.00
-
S# Description Unit Unit rate Amount # (SAR/unit) (SAR)
Quantity
Area Filling for soil Embankment ( Raising of Land from MSL +13m
to MSL +15.0m)
2.02.02
Area filling in suitable thickness of layers not exceeding 250
mm with selected soil/rock of size 0-100mm, obtained directly from
hill cutting for above lifts including clearing of areas of filling
spreading, grading for required level and slope, dressing of filled
up area, watering and rolling/compacting with the aid of mechanical
means, carrying outfield compaction tests etc. all as per sultanate
of oman standard specification and direction of the Engineer.
m3 110,000.00
3.00 Earthworks for Foundations
3.01 Excavation in soft soil / disintegrated rock - Depth 0 to
2.00 meters below ground
Excavation at depth 0.00 to 2.00 meter below ground by
mechanical means for foundations of equipment,buildings, drain,
pit, trenches, manholes etc. in ordinary soils including
Soft/Disntegrated rock, in both Dry an Wet conditions, including
setting out works, pumping and bailing out surface and subsoil
water, Shoring, Strutting, Slush removal, as per Drawing and
Specifications.The bed of the excavation shall be made level and
firm by watering and ramming.
3.02 Excavation in soft soil / disintegrated rock - Depth 2.00
to 4.00 meters below ground
Excavation at depth 2.00 to 4.00 meter below ground by
mechanical means for foundations of equipment,buildings, drain,
pit, trenches, manholes etc. in ordinary soils including
Soft/Disntegrated rock, in both Dry an Wet conditions, including
setting out works, pumping and bailing out surface and subsoil
water, Shoring, Strutting, Slush removal, as per Drawing and
Specifications.The bed of the excavation shall be made level and
firm by watering and ramming.
3.03 Excavation in soft soil / disintegrated rock - Depth 0.00
to 2.00 meters below groundExcavation at depth 0.00 to 2.00 meter
below ground by manual means for foundations of equipment, drain,
pit, trenches, manholes etc. in ordinary soils including
Soft/Disntegrated rock, in both Dry an Wet conditions, including
setting out works, pumping and bailing out surface and subsoil
water, Shoring, Strutting, Slush removal, as per Drawing and
Specifications.The bed of the excavation shall be made level and
firm by watering and ramming.
4.01 Backfilling of soil and disposal4.02 Backfilling with
excavated soil
Backfilling with excavated soil from the excavation at site,
compacted in layers about 20 cm thick at least up to 95% of the
maximum dry density as determined by the standard Proctor test
(ASTM D 698, AASHTO T 180).
4.03 Filling with clean sandFilling with clean sand, including
transport, placing, compacted and all the necessary for the correct
execution.
4.04 Filling with imported earthFilling with imported and
selected proper ground, compacted in layers about 8 inches thick at
least up to 95% of the maximum dry density as determined by the
standard Proctor test (ASTM D 698, AASHTO T 99).
-
-
-
-
-
-
2,000.00 m3 -
m3 - 1,000.00
m3 - 2,000.00
m3 - 7,500.00
m3 500.00 -
m3 - 15,000.00
-
S# Description Unit Unit rate Amount # (SAR/unit) (SAR)
Quantity
4.05 Compacted coarse stone 32-65 mm (Sub - Base)Supply and
placing of compacted coarse stone 32-65 mm size for sub-base
compacted to 95% Proctor Modified.
4.06 Compacted stone grit 4-32 mm (Base)Supply and placing of
compacted stone grit 4-32 mm size for base compacted to 95% Proctor
Modified.
4.07 Filling with gravelSupply, spreading & levelling with
gravel of size 30-70 mm size at transformer yard, switchyard area
and other area as directed by EPC contractor in layer of 100 mm.
etc all complete.
4.08 Disposal of surplus excavated soilLoading, transporting and
disposal of surplus excavated soil at a designated location within
a lead of 10 Kms. from site. The disposal shall be carried out as
per local regulation. The quoted price shall include dust control
measures, transportation, housekeeping etc. all complete.
5.00 Concrete
5.01Provision and placing of mass concrete of grade C15 (28th
day cube strength 15 N/mm2) under the foundations
Provision and placing of mass concrete (characteristic
resistance of 15 N/mm2) under the foundations. Cement shall be Type
I Ordinary portland cement, minimum cement content shall be 200
Kg/m3 and maximum water-cement ratio shall be 0.6 and nominal size
of20 mm aggregate,as per the drawings, specifications and
directions of Engineer, excluding the cost of shuttering and
reinforcement but inclussive of all other materials, tools, plant,
labour curing, dewatering, taking cubes and its testing and
provided test results complete.
5.02Provision and placing of concrete of grade C40 (28th day
cube strength 40 N/mm2) for all sub-structures &
super-structures
Provision and placing of concrete (characteristic resistance of
40 N/mm2) for varous sub-structures & super-structures as
listed below including compaction, cure and protection of concrete.
Cement shall be Type I Ordinary portland cement, minimum cement
content shall be 375 Kg/m3 and maximum water-cement ratio shall be
0.42,.as per the drawings, specifications and directions of
Engineer excluding the cost of shuttering and reinforcement but
inclussive of all other materials, tools, plant, labour curing,
dewatering, taking cubes and its testing and provided test results
complete
5.02.01 Foundation m3 2,000.00 - - 5.02.02 Slabs m3 1,500.00 - -
5.02.03 Walls m3 750.00 - - 5.02.04 Columns m3 750.00 - - 5.02.05
Beams m3 1,500.00 - -
5.03 Extra over items nos. 5.01 & 5.02 for concrete with
Sulphate Resistant portland cement.5.03.01 For mass concrete -
15N/mm2 m3 500.00 - - 5.03.02 For structural concrete - 40 N/mm2 m3
500.00 - -
-
-
-
-
-
-
m3 - 500.00
m3 - 10,000.00
m3 - 500.00
m3 - 500.00
m3 - 500.00
-
S# Description Unit Unit rate Amount # (SAR/unit) (SAR)
Quantity
5.04Provision and placing of concrete of grade C25 (28th day
cube strength 25 N/mm2) under steps & basesProvision and
placing of concrete (characteristic resistance of 25 N/mm2)for
steps & bases . Cement shall be Type I Ordinary portland
cement, minimum cement content shall be 250 Kg/m3 and maximum
water-cement ratio shall be 0.45 and nominal size of20 mm
aggregate,as per the drawings, specifications and directions of
Engineer excluding the cost of shuttering and reinforcement but
inclussive of all other materials, tools, plant, labour curing,
dewatering, taking cubes and its testing and provided test results
complete
m3 300.00
5.05Provision and placing of concrete of grade C10 (28th day
cube strength 10 N/mm2) under floor screedProvision and placing of
concrete (characteristic resistance of 10 N/mm2)for screed concrete
. Cement shall be Type I Ordinary portland cement, minimum cement
content shall be 180 Kg/m3 and maximum water-cement ratio shall be
0.6 and nominal size of10 mm aggregate,as per the drawings,
specifications and directions of Engineer excluding the cost of
shuttering and reinforcement but inclussive of all other materials,
tools, plant, labour curing, dewatering, taking cubes and its
testing and provided test results complete
m3 100.00
5.06 Grouting
Provision and placing of non shrinking and chloride free grout
under base platesas per the drawings, specifications and directions
of Engineer inclussive of all other materials, tools, plant, labour
curing, dewatering, taking cubes and its testing and provided test
results complete, The grout shall have the following minimum
characteristicsCompressive strength (BS 1881 part 1, 1983) 26 MPa @
1 day 55 MPa @ 7 days and66 MPa @ 28 daysExpansion characteristics
(ASTM C940 -98a): Up to 2% @ 24 hours
6.00 Formwork6.01 Formwork - Straight in profile
Providing, centering, fixing & stripping of good quality
formwork straight in profile at all heights & depths including
centering & steel Scaffolding all complete as per drawings,
specifications and direction of the EPC Contractor/Client.
6.01.01 Foundation m2 6,000.00 - 6.01.02 Slabs m2 7,000.00 -
6.01.03 Staircase m2 500.00 - 6.01.04 Walls m2 2,500.00 - 6.01.05
Columns m2 750.00 - 6.01.06 Beams m2 1,500.00 -
-
m2
m3 - 5.00
-
S# Description Unit Unit rate Amount # (SAR/unit) (SAR)
Quantity
6.02 Formwork - Curved in profileProviding, centering, fixing
& stripping of good quality formwork curved in profile at all
heights & depths including centering & steel Scaffolding
all complete as per drawings, specifications and direction of the
EPC Contractor/Client.
6.02.01 Walls m2 250.00 - 6.02.02 Columns m2 250.00 - 6.02.03
Beams m2 250.00 -
6.03 Extra-over item nos. 6.01 & 6.02 for providing fair
finish6.03.01 For walls straight in profile m2 500.00 - 6.03.02 For
columns straight in profile m2 500.00 - 6.03.03 For beams straight
in profile m2 500.00 - 6.03.04 For walls curved in profile m2
500.00 - 6.03.05 For columns curved in profile m2 500.00 - 6.03.06
For beams curved in profile m2 500.00 -
7.00 Reinforcement Bars7.01 Reinforcement bars for concrete
(Uncoated)
Supplying of reinforcing steel,Preparation of bar bending
shedules,placing & positioning of HYSD reinforcement bars with
characteristic strength of fy = 460 N/mm2 and compliant with
BS-4449,including welding joints at all levels above and below
ground level for reinforced cement concrete and precast reinforced
cement concrete works including cutting, bending, cranking,
binding, tack welding, spot welding as necessary, binding
wire(1.5mm annealedwire), spacerblocks, electrodes etc,
straightening and decoiling wherever necessary all as per drawings,
specifications and directions of the engineer, all materials,tools,
plant, labour etc, complete. ( authentically accepted laps and
chairs will be paid in this item ).
7.02 Reinforcement bars for concrete (corossion resistant)
Provision and placing of corrosion resistant HYSD reinforcement
bars (CRS bars) with characteristic strength of fy = 460 N/mm2 and
compliant with BS-4449, including overlap lengths and tied with
wires.including welding joints at all levels above and below ground
level for reinforced cement concrete and precast reinforced cement
concrete works including cutting, bending, cranking, binding, tack
welding, spot welding as necessary, binding wire(1.5mm
annealedwire), spacerblocks, electrodes etc, straightening and
decoiling wherever necessary all as per drawings, specifications
and directions of the engineer, all materials,tools, plant, labour
etc, complete. ( authentically accepted laps and chairs will be
paid in this item ).
-
-
M.Tons - 400.00
M.Tons - 150.00
-
S# Description Unit Unit rate Amount # (SAR/unit) (SAR)
Quantity
8.00 Structural steel & Ancillaries8.01 Structural steel
Supply, fabrication & erection of structural steel including
loading, unloadig, shifting to work location, preparation of
fabrication drawings, surface preparation painting as per
specification & drawings.Structural steel conforming to
BS-EN-10025 -S355 (Grade-50) at all elevations involving rolled
Sections (including mild steel rounds), built up Sections
fabricated out of plates, rolled Sections and combination of plates
and rolled Sections, in columns, beams, gantry girders, bunkers,
silos, hoppers, roof trusses, portals, laced purlins, space frames,
shear connectors, hangers, struts, monorails, galleries,
stiffeners, wall beams, sheeting runners, brackets, stub columns,
bracings, cleats, trestles, base plates, splice plates, chequered
plate flooring, decking and seal plates, diaphragm, steel frame
grid over false ceiling, walkway platforms, ladders, stairs,
stringers, treads, landings, toeplates, MS Rungs, insert plates,
edge angles, embedments, lugs, posts,stays, louvers, lacings,
gusset plates, safety chains for walkways adjacent to crane girders
etc; for Engine hall and other buildings.Surface Preparation- Blast
clean for ferrous metals shall be according to S3.21/EP160/2-FE
Sa2.5 according to EN ISO- 8501 Painting- shop Primer -two coats of
epoxy zinc rich DFT- 75 microns Mid coat - High build miceous iron
oxide pigmented epoxy coating DFT-150 microns Finish coat -
Polyurethene top coat as approved colour DFT -75 microns
8.01.01
Extra over item nos. 8.01 for using Intumescent painting system
to provide 2 hrs protection to steel structures according to
BS:476-1987Surface Preparation- Blast clean as per Fe Sa2.5
according to EN ISO- 8501 Painting- shop Primer -two coats of epoxy
zinc rich DFT- 75 microns Mid coat - Intumescent paint with
suitable thickness to suit 2 hrs fire protection Finish coat -
Polyurethene top coat as approved colour DFT -50 microns
m2 1,000.00
8.02 Handrails and railingsProviding & fabricating steel
tube handrails of Nominal bore dia. of 38mm of top rail of 1.1 m
height with 38mm dia middle tube and vertical post at every 1.0m
c/c with necessary toe guards of 100m high x 4mm thick steel plate
including chain links of 6mm wide at openings, providing and
fabrications as per the detail designs and drawings or as directed
including cutting, fabricating, ransporting erecting, fixing in
postion,grouting of post with cement mortar, making welded
connection, including galvanised coating.Hand railings shall be
steel pipe and shall be constructed pipe conforming to BS1387Steel
Tubes and Tubulars Suitable for Screwing to BS21 Pipe Threads"
Medium class
Mtons 6.00
8.03 LaddersProviding & fixing of steel ladders of width
450mm conforming to BS- 4211 with stringers made of flat sections
of 65 mm x 13 mm spaced 380 mm apart, rungs made of 25 mm dia solid
rods spaced at 250 mm centres,inluding galvanised coating .
MTons 5.00
- M.Tons - 500.00
-
S# Description Unit Unit rate Amount # (SAR/unit) (SAR)
Quantity
8.04 Gratingproviding & fixing Galvanised gratingof 25 mm
thick, made up of flat bars and rods with seat angles,anchors and
supports of Galvanized steel including welding and as per details
drawings.
MTons 20.00
8.05 chequered plateProviding & fixing 6 o/p chequered plate
of weight not less than 53.2 kg/sq.m with all fasteners etc
complete as per the drawing
Mtons 20.00
8.06 Galvanized steel structureSupply ,fabrication and erection
of galvanized steel structure in frames, columns and beams, as well
as provision, fabrication and erection at site with bolted
connections.
8.07 Anchor bolts M-20 to M-24
Supply & fixing of MS anchor bolts including nuts and
washers from M-20 to M-24 according to BS 3692 grade 8.8 upto 0.75
meter of length and washers conforming to BS 4320, embedded in the
concrete including providing templates, consumables, labour,
housekeeping etc. all complete.
8.08 Anchor bolts M-27 to M-36
Supply & fixing of MS anchor bolts including nuts and
washers from M-27 to M-36 according to BS 3692 grade 8.8 upto 1.0
meter of length and washers conforming to BS 4320, embedded in the
concrete including providing templates, consumables, labour,
housekeeping etc. all complete.
8.09 Anchor bolts M-30 to M-36
Supply & fixing of MS anchor bolts including nuts and
washers from M-30 to M-36 according to BS 3692 grade 8.8 upto 1.25
meter of lengthand washers conforming to BS 4320, embedded in the
concrete including providing templates, consumables, labour,
housekeeping etc. all complete.
8.10 Field connection bolts M-20 to M-24 (BS 3692 Grade 8.8)
Supply & fixing of galvanized field connection bolts
including nuts and washers from M-20 to M-24 according to BS 3692
Grade 8.8,and washers conforming to BS 4320 including providing
templates, consumables, labour, housekeeping etc. all complete.
9.00 Metal cladding & ventilators9.01 Insulated metal
cladding system for roof and walls
Cladding for roofs and walls fabricated with insulated acoustic
sandwich panels comprising of two 0.85 mm thick aluminium sheets of
profile colour coated with 80 mm thk polyurethane insulation of
Kingspan Panel make or approved equivalent to achieve U value of
0.25 W/m2k including provision of all fasteners, sealant, labour,
scaffolding, housekeeping, erection,all necessary accessories,
power tools and devices to complete a proper and RAECOure
erection.
9.01.01 For roof m2 800.00 - - 9.01.02 For walls m2 2,500.00 -
-
-
-
-
-
-
M.Tons - 100.00
Kgs - 2,000.00
Kgs - 2,000.00
Kgs - 2,000.00
Kgs 2,000.00 -
-
S# Description Unit Unit rate Amount # (SAR/unit) (SAR)
Quantity
9.02 Single skin metal cladding for roof and wallsCladding for
roof and walls in aluminium sheet of 0.7 mm thick profile colour
coated with sandwich panel of 80mm thick polyurethane insulation of
of U -value 0.25W/m2k, including provision of all fasteners,
sealant, labour, scaffolding, housekeeping, erection,all necessary
accessories, power tools and devices to complete a proper and
RAECOure erection.
9.03 Flashing & Trim
Supply & installation of flashing & trim of 0.45 mm
thick galvanized steel sheet to eaves, corners, bases, frame
openings, fascias and fillers including all material, fasteners,
sealant, etc. all complete.
9.04 Roof kerb
Supply & installation of roof kerbs fabricated from 1.2 mm
thick, zinc-coated (galvanized) steel sheet or aluminium-zinc
alloy-coated steel sheet pre-painted with coil coating; with welded
top box and bottom skirt, and integral full-length cricket.
Fabricate curb sub-framing of minimum 1.5 mm thick, angle-, C-, or
Z-shaped steel sheet. Fabricate curb and sub-framing to withstand
indicated loads, of size and height indicated. Finish roof curbs to
match metal roof panels. The Contractor shall insulate all roof
curbs with 75 mm thick, rigid insulation.The quoted rate shall
include all materials, tools, labour, consumables, scaffolding etc.
all complete.
9.05 Galvanized steel ridgeGalvanized steel ridge of 0.6 mm
thick, placed in metallic building, with minimum development of 300
mm, even fixation accesories and waterproof joints. Measured in
true magnitude.
9.06 Roof ventilatorSupply and installation of non-power turbine
ventilator including all accessories, sealants, fasteners, labour,
scaffolding, consumables etc. all complete.
9.07 Roof &side wall GlazingSupplying & fixing of 4mm
thick Polycarbonate sheets transparent and smoke tinted,including
alumnimum frames on the roofs & side walls and sealing joints
as per the specifications & drawings including cutting of metal
sheet, all fixtures & fasterns, labour complete.
m2 50.00
-
-
-
-
- Each - 50.00
m - 1,500.00
m2 - 650.00
m - 50.00
m 1,500.00 -
-
S# Description Unit Unit rate Amount # (SAR/unit) (SAR)
Quantity
10.00 Masonry and Finishes10.01 Concrete block wall (39 x 19 x
14 cm) with minimum compressive stength of 10.5 N/mm2
Supply & laying of 200 mm thick concrete masonry unit in
cement lime mortar 1:1:6 (1 part cement: 1 part of lime:3 parts
coarse sand) for external walls upto 3.00 m height including raking
out joints, curing, scaffolding etc. all complete excluding
plastering and painting.Every fourth course of brick works shall be
provided with reinforcement steel.The quote rate shall include all
materials, scaffolding, tools, labour etc. all items necessary for
satisfactory completion of works.
10.02 Concrete block wall (39 x 19 x 9cm)with minimum
compressive stength of 10.5 N/mm2Supply & laying of 100 mm
thick concrete masonry unit in cement mortar 1:1:6 (1 part cement:1
part lime: 3 parts coarse sand) for internal walls including raking
out joints, curing, scaffolding etc. all complete excluding
plastering and painting.Every fourth course of brick works shall be
provided with reinforcement steel.The quote rate shall include all
materials, scaffolding, tools, labour etc. all items necessary for
satisfactory completion of works.
10.03 External plasterProviding 20 mm thick plaster in three
layers (base, browning & finish coat) on external surfaces with
cement mortar 1:3 to a smooth finish including making grooves, all
materials, scaffolding, curing etc. all complete as per
specifications and drawings.Approved waterproof agent and
plasticizer shall be added to the mix. Top coat shall be in
"Tyrolean" finish of uniform thickness and texture.The quote rate
shall include all materials, scaffolding, tools, labour etc. all
items necessary for satisfactory completion of works.
m2 2,500.00 -
10.04 Internal plaster (Vertical surface)Providing 12 mm thick
plaster in three layers (base, browning & finish coat) on
internal surfaces with cement sand mortar in 1:3 ratio and applied
to a smooth finish including making grooves, all materials,
scaffolding, curing etc. all complete as per specifications and
drawings.The quote rate shall include all materials, scaffolding,
tools, labour etc. all items necessary for satisfactory completion
of works.
m2 2,500.00 -
-
- m2 - 2,500.00
m2 - 2,500.00
-
S# Description Unit Unit rate Amount # (SAR/unit) (SAR)
Quantity
10.05 Ceiling plaster
Providing 6 mm thick plaster on ceiling with cement mortar 1:3
to a smooth finish including making grooves, all materials,
scaffolding, curing etc. all complete as per specifications and
drawings.
m2 1,500.00 -
10.06 Alkali Resistant Tiles on wallsSupply and fixing of Alkali
resistant tiles on walls upto height of 3.00 meters of size 200 mm
x 200 mm x 20 mm thk on 15 mm thk bedding of cement mortar of ratio
1:3, joint width of 2 mm, including grouting of joints,
housekeeping, scaffolding etc. all complete
m2 500.00 -
10.07 Alkali Resistant Tiles on floorSupply and fixing of
anti-skid Alkali resistant tiles of size 200 mm x 200 mm x 20 mm
thk on 25 mm thk bedding of cement mortar of ratio 1:3, joint width
of 6 mm including grouting of joints, housekeeping etc. all
complete
m2 500.00 -
10.08 Glazed Ceramic Tiles on wallsSupply and fixing of glazed
ceramic tiles of size 200 mm x 200 mm x 7 mm thk on 15 mm thk
bedding of cement mortar of ratio 1:3, joint width of 2 mm
including grouting of joints, housekeeping etc. all complete
m2 500.00 -
10.09 Unglazed Ceramic Tiles on floor
Supply and fixing of unglazed antislip ceramic tiles of size 600
mm x 600 mm x 7 mm thk on 25 mm thk bedding of cement mortar of
ratio 1:3, joint width of 2 mm including grouting of joints,
housekeeping etc. all complete
m2 500.00 -
10.10 Concrete hardner floor finsih
Supply and application of polyurethere based coating system on
concrete surfaces in specified areas including provision of tools,
sealing, housekeeping etc. all complete.The primed surface shall be
coverd with a polyurethene based hard wearing flexible base coat
consisting of two component self smoothing compound with a nonslip
finish.The top finishing coat shall be a 2 pack- polyurethene based
ocating giving a flexible wearingsurface suitable for mechanical
workshops.
10.11 CarpetSupply and installation of carpet for office &
prayer area procured locally of reputed or approved equivalent make
including adhesive, consumables, tools etc all complete.
-
-
m2 250.00
m2 50.00 -
-
S# Description Unit Unit rate Amount # (SAR/unit) (SAR)
Quantity
10.12 Suspended ceilings
Suspended ceiling with acoustic gypsum tile:Providing and fixing
20 mm thick gypsum fibre board false ceiling tiled false ceiling of
approved materials of size 1200X600 mm in true horizontal level
suspended on inter locking metal grid of powder coated aluminum
frames consisting of main "T" runner with suitably spaced joints to
get requird length and of size 24X38mm made from 0.30mm thick
(minimun) sheet spaced at 1200mm center to center and cross "T" of
size 24X25mm made of 0.30mm thick (minimun) sheet, 1200mm long
spaced between main "T" at 600mm center to center to form a grid of
1200X600 mm and secondary cross "T" of length 600mm and size
24X25mm made of 0.30mm thick (minimun) sheet,To be interlocked at
middle of the 1200X600 panel to form grids of 600X600mm and wall
angle of size 21X21X0.3 mm and laying false ceiling tiles of
approved texture in the grid including, wherever, required,
cutting/making, opening of services like diffusers, grills, light
fittings, fixtures, smoke detectors etc. Main "T" runner to be
suspended from ceiling using GI sloted cleats fixed to ceiling with
6mm dia and 50mm long dash fastener , 4mm GI adjustable rod with
galvanised level clips spaced at 1200mm center to center along main
"T" bottom exposed width of 24mm of all T-sections shall be
pre-painted with polyester paint, all complete at all heights as
per specifications, drawings and as directed by engineer in charge.
Texture, colour, shape, finish, type, brand to be approved by
engineer in charge.
m2 500.00 - -
10.13 Flase Flooring
Providing and fixing of raised flooring system 600 mm high
comprising of 600 x 600 x 32 mm cement fill metallic false flooring
panel with 1.2 mm antistatic high pressure laminate tile on top.
The supporting arrangement for cement fill metallic panels false
flooring shall consist of seamless pipe 25 mm. outer dia and 12 mm
thick base plates. The pipes shall be fixed on the floor @ 600 mm
c/c with 50x6 mm metal screw with nilon rowal plug. The pipe heads
will have MS check nut and M18x 100 long studs with jackhead zinc
plated of size 90x90x4 mm thick over which GI stringer 30x20x1.5
thk having pre punched holes 6 mm dia for the fixing of panels,Base
plate size - 100 x 100 x 10 mm;The rate shall include panel,
supporting arrangement, submission & approval of samples,
tools, labour, housekeeping etc. all complete.
m2 500.00 -
10.14 Expansion joint 12 mmProvision and placing of expansion
joints 12 mm thick between surfaces of concrete, formed by
polyurethane expanded and sealed with resistant bicomponent to
frictions and heavy traffic. Measurement according to the
theoretical length in planes.
10.15 SkirtingCeramic tile skirting shall be 200 x 150 mmx 7 mm
with a bullnosed top to plastered walls with CM1:6, the skirting
standing 5mm proud of the walls finish and with a square top to
tiled walls, the skirting finishing flush with the tilling, the
cove radius not less than 15mm. The bases shall be of the same
quality as the above-specified ceramic tiles.
m2 100.00
- m - 1,500.00
-
S# Description Unit Unit rate Amount # (SAR/unit) (SAR)
Quantity
11.00 Miscellaneous steel11.01 Galvanized Standard Steel
Doors
Standard steel doors and frames made of cold-rolled steel, door
faces will be made of cold-rolled sheet steel too 0,8mm of
thickness, including welding, painting and all necessary accesories
to complete a RAECOure erection.
11.02 Steel stairs Supply and erction of steel stairs with 1,2
meter of wide, made of hot-rolled steel, including welding,
painting and all necessary accesories to complete a RAECOure
placement.
12.00 Woodwork12.01 Timber wall panels
Supply and fixing of timber wall panels upto height of 2.15
meters in prayer room including all fixtures, fasteners, adhesives,
sealants etc. all complete.
13.00 Painting13.01 External Painting
Providing and applying to exterior surfaces at all elevations
two coats of exterior weather and oil resistant emulsion paint over
POP of approved manufacture, colour and shade(as per manufacturers
instructions over a coat of primer,) and all as per specifications,
drawings, and directions of the engineer, including surface
preparation, scaffolding, all materials, labour etc, complete (
(including the cost of primer).
13.02 Internal PaintingProviding and painting interior surfaces
at all elevations with two coats of acrylic emulsion paint of
approved manufacture, colour and shade over a coat of primer as per
manufactures recommendations and including surface preparation,
scaffolding, all materials, labour etc, complete. (including the
cost of primer).
13.03 Painting on ceilingsproviding & painting on all
interior ceiling/soffits at all elevations with two coats of
approved emuslion paint @ 12-14 m2/ltr, applied over two coats of
putty, applied over primer@ 7-9 m2/ltr. Include all scafffolding,
labour etc.
13.04 Painting above flase ceiling
Providing and painting all block walls above the false ceiling
with 3 coats of silane- siloxane coating @ 0.25 lits/m2 for each
coat.
13.05Painting on internal surfaces of buried structures (like
Cable trenchs, culverts, ductbanks & lifting stations)All
internal surface of concrete structures buried below ground, shall
be provided a heavy duty coating to provide long term protection
against carbonation, chloride ingress & surface abrassion.The
coating shall be solvent free coal tar extended epoxy resin of two
coats with minimum DFT of 400 micron each coat.The coating shall be
suitable for direct application on concrete surfacs without use of
primer.
-
-
-
m2 - 50.00
m2 250.00
m2 250.00
m2 - 150.00
m - 50.00
m2 1,200.00
m2 500.00
m2 1,000.00
-
S# Description Unit Unit rate Amount # (SAR/unit) (SAR)
Quantity
13.06 Bitumen coating for Below ground concrete structures
incontact with soil/water
Supply and application of 2 coats of high build bitumen coating
which shall vbe flexible,damp & vapour proof surface applied
liquid memebrane to underground concrete surfaces having the solid
content 50% by weight and zero percent water permeability. The
quoted rate shall include all necessary application of primer,
tools, scaffolding etc. all complete.
14.00 Vapour barrier, waterproofing & thermal
insulation14.01 Tanking membrane
Supply and application of tanking membrane Fosroc Proofex or
equivalent in two layers on underground concrete surface of approve
make. The quoted rate shall include all necessary application of
adhesive, tools, scaffolding etc. all complete.
14.02 Roof waterproofingSupply and application of roof
waterproofing system comprising of the following:1. Concrete
screedof minimum 50 mm thick with 10mm size agreegates;2.
Polyethylene-sheet vapour retarder 1.5 mm thick solar reflective
roof cold applied,flexible, preformed water proofing membrane
comprising a 4 layer cross laminated HDPE carrierfilm with a solar
reflective & self adhesive rubber/bitumen compound conforming
to ASTM D638 , with a maximum moisture vapour transmission rate of
0.2g/m2/24 hrs3. Extruded High density polystyrene rijid foam board
600x1200x100 thick, compressive strength 280kPA, water
absoprtion
-
S# Description Unit Unit rate Amount # (SAR/unit) (SAR)
Quantity
14.05 Geotextile MembraneSupply and laying of geotextile
membrane of thickness 2.3 mm and weight 0.27 kg/cm2 including
cutting, overlaps, adhesives, housekeeping etc. all complete. The
lining materials shall be warranted against manufacturing defects
and material degradation for a period of 30 years from the date of
official acceptance by the Company/Engineer. Materials that fail
within the warranty period shall be replaced at no cost to the
Company.
14.06 WaterstopSupply and installation of 225 mm wide, 6 mm
thick PVC waterstop of Fosroc or equivalent make at slab-wall
joints of underground tanks.
14.07 Joint SealantSupply and installation of closed cell
expanded polyethylenefoam of size 25 mm x 25 mm including backing
strip of polysulphide compound, cleaning the joint etc. all
complete.
14.08 Damp proof courseSupply and application of 2 coat of water
repellent silicone sealer, film-forming, polymerized,
silicone-resin water repellent for dense substrates. It shall be a
solvent or water-based solution containing not less than 3% and up
to 5% solids by weight, and shall comply with FS SS-W-110C. Such a
course shall be applied below concrete masonry units.
15.00 Downspouts and Gutters15.01 Gutters in galvanized mild
steel steel
Provision and placing of gutters in buildings, including all
necessary accesories to complete as per specifications &
drawings
15.02 Downspouts galvanized diameter 150 mmDownspouts pipes
diam. 150 mm, made of galvanized mild steel medium gauge, including
joints and all necessaries to complete as per specifications &
drawings.
15.03 Downspouts PVC diameter 150 mmDownspouts pipes diam. 150
mm, made of PVC, including joints and all necessaries to complete
as per specifications & drawings
16.00 Supply and laying of GI Pipes
Supply and laying of GI pipes including joining, pressure
testing etc. all complete for various diameters.
16.01 25 mm dia m 25.00 16.02 40 mm dia m 25.00 16.03 60 mm dia
m 25.00
-
-
-
-
-
-
-
m - 250.00
m 500.00
m - 250.00
m 500.00
m2 650.00
m2 500.00
m - 250.00
-
S# Description Unit Unit rate Amount # (SAR/unit) (SAR)
Quantity
17.00 Supply and laying of drainage pipes
17.01Supply and laying of cast iron pipes including joining,
pressure testing etc. all complete for various diameters.
17.01.01 90 mm dia. m 25.00 17.01.02 200 mm dia. m 25.00
17.01.03 315 mm dia. m 25.00 17.01.04 400 mm dia. m 25.00 17.01.05
600 mm dia. m 25.00
17.02Supply and laying of RCC pipes including joining, pressure
testing etc. all complete for various diameters.
17.02.01 300 mm dia. m 25.00 17.02.02 400 mm dia. m 25.00
17.02.03 600 mm dia. m 25.00 17.02.04 900 mm dia. m 25.00
17.03 Concrete manholeProvision, placing and levelling of
concrete manhole with forged iron cover (diameter of the manhole
1.10 m minimum and 2.50 m depth), with 150 mm minimum thickness for
floor slab and 150 mm minimum thickness for walls, including
excavation, soil improvement and compaction, placing of the manhole
and final refilling (where necessary) around the manhole.
17.04 Precast concrete pit 63x63cm and 1m depth for
connectionsProvision, placing and levelling of precast concrete pit
for conections with forged iron cover (square RAECOtion of 63x63 cm
width minimum), with 100 mm minimum thickness for floor slab and
150 mm minimum thickness for walls, including excavation, soil
improvement and compaction, placing of the pit and final refilling
(where necessary) around the pit.
17.05 Collecting pits (culvert) 51x34cm, 60cm depthCollecting
pits of concrete (culvert) 51x34cm RAECOtion and 60cm depth, with
forged iron cover, including excavation, backfilling and transport
of the leftover ground to a licensed suitable site.
17.06 Separating fat pitInspection box separator fat, made with
walls of 20 cm of solid brick, flattened and polished inwardly with
cement mortar, on concrete floor of 15 cm of thickness and fences
with ductile iron covers, class c (250 KN), with a total length of
3 m and a width of 1.5 m with a depth of the existing collector
include also; excavation, fill, compaction and transport of waste
to landfill.
17.07Supply and laying of PVC pipes including joining, pressure
testing etc. all complete for various diameters.
17.07.01 100 mm dia. m 25.00 17.07.02 150 mm dia. m 25.00
-
-
-
- m - 5.00
Each - 5.00
Each - 5.00
Each - 5.00
-
S# Description Unit Unit rate Amount # (SAR/unit) (SAR)
Quantity
17.08Supply and laying of HDPE pipes including joining, pressure
testing etc. all complete for various diameters.
17.08.01 100 mm dia. m 25.00 17.08.02 150 mm dia. m 25.00
18.00 Roads18.01 Asphalt Road
18.01.01 Preparation of subgrade as per Oman General
specification of roads section 300Excavation upto required depth,
watering and rolling of the subgrade with rollers to achieve
maximum density of 95%, irregularities or depressions that develop
during the compaction shall be corrected to the specified grade by
loosening the material at these places and adding, removing, or
replacing the material.
18.01.02 Sub-base courseas per Oman General specification of
roads section 300Supply and laying of sub-base course with
well-graded materials of the class or classes shown on the drawings
or specifications. All materials shall be free from organic matter,
shale or other deleterious matter and shall be of such quality that
it will bind readily to form a firm stable base for placement of
flexible pavement.
18.01.03 Base course as per Oman General specification of roads
section 300Supply and laying of base course with well-graded
materials of the class or classes shown on the drawings or
specifications. All materials shall be free from organic matter,
shale or other deleterious matter and shall be of such quality that
it will bind readily to form a firm stable base for placement of
flexible pavement.
18.01.04 Prime coat as per Oman General specification of roads
section 400Supply and application of prime coat uniformly to the
sub-base course using a pressure distributor at a rate between 1.0
to 1.75 litres per square metre.The primer shall be applied to a
width of at least 300 mm greater on each side of the specified
width of the finished surface. The prime coat shall be of
medium-curing type cutback asphalt consisting of asphaltic base
fluxed with suitable petroleum distillates. The product shall be
free of water, show no separation prior to use, shall not foam when
heated to application temperature and shall conform to the
requirements of Grade MC-70 or MC-250 of ASTM D2027.
-
-
-
-
m3
m3
1,500.00
500.00
500.00
m2
m2 1,500.00
-
S# Description Unit Unit rate Amount # (SAR/unit) (SAR)
Quantity
18.01.05 Binder course - 100 mm thk as per Oman General
specification of roads section 400Supply and laying of asphaltic
concrete comprising of Asphalt Cement of homogenous, penetration
grade 60-70, 85-100 or 150-200, free of water, shall not foam when
heated to 177C, and conforming to the requirements of ASTM D946.
Mineral aggregates shall consist of coarse aggregates, fine
aggregates, and filler material. Asphalt concrete shall be a
combination of mineral aggregates and asphalt cement in such
proportion as to produce a mixture conforming to the composition
limits by weight per table below:1. Total Mineral Aggregate : 93-96
% 2. Asphalt Cement : 4 - 7%
18.01.06 Tack coat as per Oman General specification of roads
section 400Supply and application of tack coat with of rapid-curing
type cutback asphalt consisting of asphalt base fluxed with
suitable petroleum distillates. The product shall be free of water,
show no separation prior to use, shall not foam when heated to
application temperature and shall conform to the requirements of
Grade RC-800 of ASTM D2028. The tack coat shall be uniformly
applied over the entire surface of the area to be covered, when the
temperature of the tack coat material is between 95C to 120C.
18.01.07 Wearing course - 80 mm thk as per Oman General
specification of roads section 400Supply and laying of asphaltic
concrete comprising of Asphalt Cement of homogenous, penetration
grade 60-70, 85-100 or 150-200, free of water, shall not foam when
heated to 177C, and conforming to the requirements of ASTM D946.
Mineral aggregates shall consist of coarse aggregates, fine
aggregates, and filler material. Asphalt concrete shall be a
combination of mineral aggregates and asphalt cement in such
proportion as to produce a mixture conforming to the composition
limits by weight per table below:1. Total Mineral Aggregate : 93-96
% 2. Asphalt Cement : 4 - 7%
18.01.08 Seal coatSupply and application of asphalt seal
coat.
18.01.09 Precast Concrete KerbsSupply and installation of
precast concrete kerbs of size 600 mm x 200 mm x 450 mm founded on
concrete bedding along the edge of the road. The precast kerb shall
be laid on minimum of 400mm wide & 300mm high plain concrete
grade C20 and joined with cement-sand mortar of 1:3 ratio.
18.02 Car park shedSupply and installation of car park shelter
of size 6.00 m x 3.00 m. Each 3.00
1,500.00 -
1,500.00
-
-
-
m2
m2
m
m2
m2
1,500.00
500.00
- 1,500.00
-
S# Description Unit Unit rate Amount # (SAR/unit) (SAR)
Quantity
19.00 Others19.01 Anti Termite Treatment
Providing and injecting approved quality chemical emulsions as
specified for pre-constructional Anti-termite Treatment chemicals
such as Malathion, Dursban 4TC, K-Othrine EC, Ficam, Dieldren,
Tergram (Gamma BHC Isomer) and Permethrin (Dragent FT),and creating
a chemical barrier under and around column pits, wall trenches,
basement excavation, top surfaces of plinth filling, junction of
wall and floor, along the external perimeter of building, expansion
joints, surrounding of pipes and conduits etc. as specified,
complete with all labour, tools, tackles, consumables as per
direction of the Engineer-in-charge. (Only ground floor plinth area
of all building will be measured for payment). However, area
requiring treatment but not covered in plinth area shall be
measured for the areas actually treated for payment purposes.
Material to be approved by engineer in charge
19.02 Warning tapesSupply and laying of RAECO approved warning
tapes 150 mm wide in trenches for cables.
19.03 Cable Protection tilesSupply and laying of RAECO approved
cable protection tiles of size 40 cm x 20 cm x 5 cm in trenches for
cables.
19.04 Vehicle access barrierSupply and installation of vehicle
access barrier - 5.00 m wide
19.05 Aluminium Windows
Supplying, fitting and fixing minimum 20 micron Bronze colour
anodised aluminium windows of various sizes made with All
extrusions shall be of AlMgSi, designation 6060, or 6063, temper
T5, heattreatable, and shall be in accordance with BS 1474 : 1987,
50 mm thick box frames.windows shall be delivered to site complete
with all fittings. All windows and their components shall conform
to B.S.4873 and shall be designedto resist the severe (b) exposure
test pressure of 2800 N/m2 when tested inaccordance with BS 4315:
Part 1, and test certificates shall be submitted to thesupervising
Engineer confirming this requirements.All frames and casements
shall be fully weather stripped with continuous neoprenestrips and
shall be designed for internal glazing with snap-on Aluminium
beads. Thosewindows shown on the schedules or drawings to be
openable shall open inwards andshall be secured in the closed
position by means of budget locks.All aluminium surfaces in
contract with steel, concrete, masonry or mortar shall beprotected
by painting with bituminous paint or taping with PVC before fixing
in position.The windows shall be fixed-in with stainless steel
lugs, or with screws supplied by themanufacturer, in accordance
with the details shown on the Drawings.After fixing and where shown
on the Drawings, the frames shall be pointed inpolysulphide or
equal and approved non-hardening pointing sealant recommended bythe
window manufacturer.Frames shall conform to the above
specifications and glazing shall be 24mm overall bronze tinted
tempered 8mm (external) and 8mm clear tempered glass ( internal)
with 8mm airgap in middle.
-
-
-
-
-
- 250.00
Each - 2.00
m2 - 300.00
m2 - 15,000.00
m - 500.00
m2
-
S# Description Unit Unit rate Amount # (SAR/unit) (SAR)
Quantity
19.06 Aluminium LouversThe louvers shall be of 18-gauge
Aluminium, of fixed pitch at 45mm, complete withframes, sills, and
mullions as detailed on the Drawings. The louvers shall bepreformed
for site assembly, and shall be anodized to match the windows
inaccordance with B.S 3987. The back of the louvers shall be fitted
with bird meshscreens or blank sheet Aluminium panels where
indicated on the Drawings.
19.07 Metal Doors & frames
Metal Door (Scientific Door): Providing & Fixing of Metal
Door frames and door shutters made upof Galvanize steel (base steel
of 0.58 mm thick D quality, galvanized with Zinc of 120 GSM) Pure
polyester powder upto 50-60 microns thick . Outer frame section
should be of 100x 58mm x 1.2mm thick. Shutter section should be of
0.80 mm thick galvanized steel sheet pressed (roll formed) to
provide a 46mm thick fully flush, double skin door shell Seam
joints at stile edges. In-fill of Honeycomb Kraft paper is used to
give the required rigidity and effective acoustic insulation. 6
Tower bolt 1 No., 6 D handles 2 Nos., 10 Aldrop 1 No., Butt Hinges
3 Nos, Mortise Lock of approved quality 1 No. The above frames
should be fixed to the concrete/masonry wall by means of self
expanding screws complete for finished item of work.
19.07.01 Single leaf doors - 1200 mm x 2100 mm Each 25.00 -
19.07.02 Double leaf doors - 2100 mm x 2100 mm Each 25.00 -
19.08 wooden Louvred Doorssupply & installation of louvred
doors manufactured with hardwood. The top rail shall be 148x50mm,
with middle & bottom rails 246x50mm. The top & bottom
panels shall be formed with hardwood louvre blades each side 70x10
set at 450 to throw rainwater at the external face.
19.09 Fire Resistant Steel DoorsSupply and installation of fire
resistant steel doors made of steel profiles & stel sheet
plates as per specifications of 19.07 insulated with mineral wool,
surface treatment and painting similar to steel structures. The
fire rating shall be 2 hours. All doors shall be complete with
ironmongery including locking arrangements with masterkey system
handles & fastens, hinges etc.
19.09.01 Door size - 2000 mm x 2100 mm Each 4.00 19.09.02 Door
size - 1000 mm x 2100 mm Each 4.00
25.00 -
-
m2
m2 - 1,500.00
m2 30.00
-
S# Description Unit Unit rate Amount # (SAR/unit) (SAR)
Quantity
19.10 Toilet doors (UPVC)
Providing and fixing to existing door frames 30 mm thick factory
made Polyvinyle Chloride (PVC) door shutter made of styles and
rails of a UPVC hollow section of size 60x30mm and wall thichness
of 2mm +0.2 mm with inbuilt decorative moulding edging on one
side.Thestyles and rails mitred and joined at the corners by means
of M.S. galvanised/plastic brackets of size 75x220mm having wall
thickness 1.0mm and stainless steel screws. the styles of the
shutter reinforced by inserting galvanised M.S. tube of size 25x20
mmand 1mm+/- 0.1mm wall thicknes. the lock rail made up of H
section,a UPVC hollow section of size 100x30 mmand 2mm +/-0.2 mm
wallthickness fixed to the shutter styles by means of plastic/
galvanised M.S. `U`cleats .The shutter frame filled with a UPVC
multi chambered single panel of size not less than 620mm,having
overall thickness of 20 mm and 1mm+/-- 0.1mm wall thickness. The
panels filled vertically and tie bar at two places by inserting
horizontally 6mm galvanised M.S. rod and fastened with nuts and
washers,complete as per manufacturer`s specification and direction
of Engineer -in -charge
m2 50.00
19.11 wooden doors
supply & installation of 40 mm thick solid flush doors made
from solid cores of hardwood . stiles & toprail of minimum
width 80mm, bottom rail of minimum width 200mm. With 6mm plywood on
both sides,10mm thick lipping alround and shall confirm to half
hour fire resisitant doors in accordance to BS 4787.Complete with
all necessary fixtures, ironmongery, handles, locks, hinges and
labour.
10.00
19.12 Rolling ShuttersSupplying and fixing in position approved
make electrically operated steel rolling shutters conforming to
relevant british standards, (with wicket gate where necessary)
including all fittings, fixtures (including guide channels and hood
cover etc), motor, all as per drawings, specifications and
instuctions of engineer(M.S rolling shutters shall be made of
interlocking lath section formed from bright cold rolled, annealed
M.S strips not less than 0.90mm thick for shutters up to 3.5m width
& not less than 1.20mm thick for shutters above 3.50m width,
with weather seals and wind lock and shall have grills for
ventilation where necessary. Its components shall be factory
galvanized, primed and field painted as specified). of size 3000 mm
W x 4000 mm H
- Each 4.00
m2
-
S# Description Unit Unit rate Amount # (SAR/unit) (SAR)
Quantity
19.13 Rolling ShuttersSupplying and fixing in position approved
makemanually operated steel rolling shutters conforming to relevant
british standards, (with wicket gate where necessary) including all
fittings, fixtures (including guide channels and hood cover etc),
motor, all as per drawings, specifications and instuctions of
engineer(M.S rolling shutters shall be made of interlocking lath
section formed from bright cold rolled, annealed M.S strips not
less than 0.90mm thick for shutters up to 3.5m width & not less
than 1.20mm thick for shutters above 3.50m width, with weather
seals and wind lock and shall have grills for ventilation where
necessary. Its components shall be factory galvanized, primed and
field painted as specified).size 1500 mm W x 2500 mm H
19.14 Fence
Supply and installation of chain link fence with following
specifications:2.4 m height PVC coated chain link fence of gauge 8,
on 50 mm dia GI pipes,planted at 3.0 m intervals with top and
bottom and intermediate horizontal GIpipes. Inclusive of PVC coated
tension wire (4 rows length wise) strut poles andrubble curb wall
300 mm wide and 450 mm below ground (minimum), 300 mmabove ground
(minimum dimension) with plastered surface. Top of GI poles tobe
covered with PVC riveted capsChain link fencing wire mesh shall be
3.5mm overall diameter olive green plastic coated to BS 4102 of
standard mesh size 50mm and height 1800mm as specified and shall
have a galvanized core diameter of 2.50mm as BS 4102 table-3Support
tension wires to bottom, middle and top of wire mesh shall be 4mm
diameter galvanized steel cold tension wires as specified in BS
4102.Tying wire finished with galvanized coating shall be 2.5mm
galvanized tying wire as specified in BS 4102.Barbed wire where
specified shall comply with the requirements of BS 4102.Steel
intermediate posts shall be to BS 6328. Parts 1 to 8 and be 50mm
nominal bore Medium / Low Speed galvanized steel tube with three
10mm diameter holes fir wires and length 2.6m or 2. 0m.The ends of
the posts to be set in concrete shall be sprigged.Steel corner
posts and straining posts shall be 60mm nominal and fitted with two
50mm nominal bore Medium / Low Speed galvanized steel tube strut
braces fixed at 45 degrees to level ground. The struts shall be
fitted in the direction of each line of fencing secured to them.
All works to be as per design requirements, final approved drawings
& specifications.
19.12 Compound wall fenceSupply and installation of chain link
fence with UPVC coat steel security barbed wire for 1m height
-
-
Each 4.00 -
m 900.00 -
m - 600.00
-
S# Description Unit Unit rate Amount # (SAR/unit) (SAR)
Quantity
19.13 Gates
19.13.01
Sliding gates: Providing & fixing GI framed gate with
minimum 7.0 m clear width x 2.4 Height with colour bond cladding
double sashed, side hung door inclusive of bottom rails, guide
wheelswith self lubricated heavy duty ball bearings & inclusive
of gate columns andlocking arrangements.Steel posts shall be
galvanised in accordance with the specification.Access gates shall
be both single and double entrance gates shall be fabricatedtubular
steel and galvanised after manufacture. They shall comply with BS
1722 Part 1Supplement No. 1 Sockets for casting into the roadway
shall also be provided. Thesockets shall be designed to provide
secure and robust support for drop bolts whengates are in both open
and closed positions.Each gate shall be supplied with a padlock and
three keys all to the Engineer's
Each 3.00 -
19.13.02Supply and installation of man entry swing gates of size
1000 mm wide x 2400 mm height with the same material specifications
of sliding gates
Each 3.00 -
19.14 Limestone claustraSupply and installation of limestone
claustra of size 300mm x 240mm x 115mm 5DF of approved color on
transformer yard fire wall
19.15 Septic tank
Construction of septic tank of capacities for 50 users as per
approved drawing with Brick walls and RCC slab including two 560 mm
dia. R.C.C. manhole cover of approved make supplied,fitted, &
fixed in the top slab with necessary fittings , 15mm thick cement
plaster (4:1) with neat cement finish to the internal surfaces and
15 mm thick cemnt plaster (4:1) to outside wall upto 200 mm below
G.L. floor finished with 25 mm thick grey artificial stone
including supplied,fitted, and fixedS.W. tees C.I. foot rest etc.
including excavating earth in all sorts of soil shoring bailing and
pumping out water as necessary , ramming, dressing the bed and
refilling the sides of the tank with earth , removing spoils
filling up the chamber with clear water, removing foreign materials
from the chamber & including constructing attached inspection
pit as per approved drawing and connecting all necessary pipes ,
joints, etc. with internal plaster work and artificial stone
flooring is to be done with admixture compound @ 5% weight of
cement ,complete in all respect .
Lumpsum 1.00
19.16 soak PitConstruction of brick lined soak pit of required
diameters, depth of the for 50 users and SW drain pipe 100 mm dia.
1.8m long and including connection from septic tank to soakpit
etc., complete as per standard design
Lumpsum 1.00
- Each 50.00 -
-
S# Description Unit Unit rate Amount # (SAR/unit) (SAR)
Quantity
20.00 Furniture20.01 Curved desk - 5 persons
Supply and installation of curved desk unit suitable for 5
persons in arc shape.20.02 Straight console desk - 2 persons
Supply and installation of Straight console desk unit for 2
Operator cum Engineering station.20.03 Printer Tables
Supply and installation of tables for printers from reputed
local make.20.04 Executive Chairs
Supply and installation of executive chairs of reputed
make.20.05 Steel racks
Supply and installation of steel racks for workshop.20.06 Steel
cupboard
Supply and installation of steel cupboard for workshop.21.00
Sanitary Fixtures
Supply & fixing of sanitary fixture including complete
accessories, bolts etc.21.01 Wash-Basin - Pedestal type Each 10 -
21.02 Mirror - 600 mm x 450 mm x 6 mm thk Each 4 - 21.03 Kitchen
sink - stainless steel make Each 2 - 21.04 European type WC Each 2
- 21.05 Asian type WC Each 4 - 21.06 Urinals with partition Each 4
- 21.07 Shelves Each 2 - 21.08 Towel holder - 600 mm long Each 6 -
21.09 Toilet paper holder Each 2 - 21.10 Liquid soap holder Each 4
- 21.11 Handspray Each 6 - 21.12 Faucet Each 6 - 21.13 Shower Each
6 - 21.14 Soap holder Each 6 - 21.15 PVC Floor drains Each 20 -
2.00 - -
Each 12.00 - -
-
- 2.00 -
Each 2.00 - -
Each 2.00 - -
Each 2.00 -
Each
Each
-
S# Description Unit Unit rate Amount # (SAR/unit) (SAR)
Quantity
22.00 Landscaping22.01 soft Landscaping
Green Landscaping:Landscaping includes removing of top soil upto
250 mm below FGL, preparation of ground, cultivation of ground,
supplying of imported soil,sand, manure ,Supply and planting of
trees, shrubs and grass(Bermuda grass) conforming to BS 3936 from
the approved source , supplying and laying of gravel(28 mm size),
with all necessary pegs & wires in the space as shown in the
drawings.
22.02 Interlock paving - 60 mm thk for pedestrain walkwaysSupply
and laying of heavy duty interlocking precast concrete flags of 60
mm thickness with a minimum compressive strength of 40 N/mm2
including sand bedding , coloured throughout . The concrete paving
shall be sealed with a premium quality,durable, water based,
approved clear sealer@ 7-10m2/ltr. TheQuoted rate shall include
supply of interlock tiles, sand , compaction,tools, labour etc. all
complete.
22.03 Interlock paving - 80 mm thk for Roads & parking
areas
Supply and laying of heavy duty interlock precast concrete flags
of 80 mm thickness with a minimum compressive strength of 40 N/mm2
including sand bedding and coloured throughout.The concrete paving
shall be sealed with a premium quality,durable, water based,
approved clear sealer@ 7-10m2/ltr Quoted rate shall include supply
of interlock tiles, sand , compaction,tools, labour etc. all
complete.
23.00 Temporary Site facilities to Client23.01 site office for
owner's representatitives
Supply & install temporary portacabin offices with power,
telephone, broadband internet,computers, laptop,A3 colour laser
printer, xerox machine, fax machine, A/C and well ventilated
housing for 2 persons with Toilets
No's 4.00
m2 200.00 -
m2 200.00 -
m2 1,000.00 -