ABEINSA 3-Mar-14 Abeinsa Business Development Rev.00 S# Description Unit Unit rate Amount # (SAR/unit) (SAR) 1.00 Clearing of the soil 1.01 Site clearance Clearing and grubbing of site upto 300 mm depth including uprooting vegetation, grass, bushes, shrubs, saplings and trees girth up to 300 mm, removal of stumps of trees of all girth size, stacking of serviceable material and disposal of unserviceable materials at a designated dumping yard within a lead of 10 km. The quoted rate shall include all local permits and fees as applicable. 2.00 Site Grading 2.01 Hill cutting 2.01.01 Excavation in Hill Area in Soil by Mechanical Means (Excavation in soil in hilly area by mechanical means including cutting and trimming of side slopes and disposing of excavated earth with all lifts and lead upto 1000 metres) m 3 777,900.00 2.01.02 Excavation in Hilly Area in Ordinary Rock by Mechanical Means not Requiring Blasting. (Excavation in hilly area in ordinary rock not requiring ballasting by mechanical means including cutting and trimming of slopes and disposal of cut material with all lift and lead upto 1000 metres ) m 3 466,800.00 2.01.03 Excavation in Hilly Areas in Hard Rock Requiring control Blasting (Excavation in hilly areas in hard rock requiring blasting,by drilling, blasting and breaking,trimming of bottom and side slopes as per the approved drawings and disposal of cut material with all lifts and lead upto 1000 metres including labour,blasting material & permits.) m 3 311,200.00 2.01.04 Breaking of boulders into suitable size as required as per specifications and seggregating the same for Area filling . m 3 200,000.00 2.01.05 stabilization of quarry faces to prevent landslides and rock fall during & after the hill cutting . m 2 30,000.00 2.01.06 construction of temporary earthen storm water drain at top & bottom of the hill to make dry during the hill cutting m 3 1,000.00 2.02 Area Filling for Rock fill Embankment ( Raising of Land from MSL +7m to MSL +1 3.0m) 2.02.01 Area filling for Rockfill embankment in suitable thickness of layers with selected rock fill of suitable size obtained directly from hill cutting for above lifts including clearing of areas of filling spreading, grading for required level and slope, dressing of filled up area, watering and rolling/compacting with the aid of mechanical means, carrying outfield compaction tests , plate load bearing tests and achieving 25 Ton/m 2 bearing capacity at MSL +13 m Lvl, as per sultanate of Oman standard specifications and direction of the Engineer. m 3 300,000.00 Appendix-5, Exhibit-0 Project: 100 MW CCCP or Engine based Power Plant at Musandam, Oman Bill of Quantities for Civil & Structural works Quantity - m2 - 52,500.00
24

05 Appendix 5 BOQ-Rev.00

Nov 23, 2015

Download

Documents

Landon Mitchell

specufucations of materials
Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
  • ABEINSA 3-Mar-14Abeinsa Business Development Rev.00

    S# Description Unit Unit rate Amount # (SAR/unit) (SAR)

    1.00 Clearing of the soil 1.01 Site clearance

    Clearing and grubbing of site upto 300 mm depth including uprooting vegetation, grass, bushes, shrubs, saplings and trees girth up to 300 mm, removal of stumps of trees of all girth size, stacking of serviceable material and disposal of unserviceable materials at a designated dumping yard within a lead of 10 km. The quoted rate shall include all local permits and fees as applicable.

    2.00 Site Grading2.01 Hill cutting

    2.01.01Excavation in Hill Area in Soil by Mechanical Means (Excavation in soil in hilly area bymechanical means including cutting and trimming of side slopes and disposing of excavatedearth with all lifts and lead upto 1000 metres)

    m3 777,900.00

    2.01.02

    Excavation in Hilly Area in Ordinary Rock by Mechanical Means not RequiringBlasting. (Excavation in hilly area in ordinary rock not requiring ballasting by mechanicalmeans including cutting and trimming of slopes and disposal of cut material with all lift andlead upto 1000 metres )

    m3 466,800.00

    2.01.03

    Excavation in Hilly Areas in Hard Rock Requiring control Blasting (Excavation in hilly areas inhard rock requiring blasting,by drilling, blasting and breaking,trimming of bottom and side slopes as per the approved drawings and disposal of cut material with all lifts and lead upto 1000 metres including labour,blasting material & permits.)

    m3 311,200.00

    2.01.04Breaking of boulders into suitable size as required as per specifications and seggregating the same for Area filling . m

    3 200,000.00

    2.01.05 stabilization of quarry faces to prevent landslides and rock fall during & after the hill cutting . m2 30,000.00

    2.01.06construction of temporary earthen storm water drain at top & bottom of the hill to make dry during the hill cutting m

    3 1,000.00

    2.02 Area Filling for Rock fill Embankment ( Raising of Land from MSL +7m to MSL +1 3.0m)

    2.02.01

    Area filling for Rockfill embankment in suitable thickness of layers with selected rock fill of suitable size obtained directly from hill cutting for above lifts including clearing of areas of filling spreading, grading for required level and slope, dressing of filled up area, watering and rolling/compacting with the aid of mechanical means, carrying outfield compaction tests , plate load bearing tests and achieving 25 Ton/m2 bearing capacity at MSL +13 m Lvl, as per sultanate of Oman standard specifications and direction of the Engineer.

    m3 300,000.00

    Appendix-5, Exhibit-0Project: 100 MW CCCP or Engine based Power Plant at Musandam, Oman

    Bill of Quantities for Civil & Structural works

    Quantity

    - m2 - 52,500.00

  • S# Description Unit Unit rate Amount # (SAR/unit) (SAR)

    Quantity

    Area Filling for soil Embankment ( Raising of Land from MSL +13m to MSL +15.0m)

    2.02.02

    Area filling in suitable thickness of layers not exceeding 250 mm with selected soil/rock of size 0-100mm, obtained directly from hill cutting for above lifts including clearing of areas of filling spreading, grading for required level and slope, dressing of filled up area, watering and rolling/compacting with the aid of mechanical means, carrying outfield compaction tests etc. all as per sultanate of oman standard specification and direction of the Engineer.

    m3 110,000.00

    3.00 Earthworks for Foundations

    3.01 Excavation in soft soil / disintegrated rock - Depth 0 to 2.00 meters below ground

    Excavation at depth 0.00 to 2.00 meter below ground by mechanical means for foundations of equipment,buildings, drain, pit, trenches, manholes etc. in ordinary soils including Soft/Disntegrated rock, in both Dry an Wet conditions, including setting out works, pumping and bailing out surface and subsoil water, Shoring, Strutting, Slush removal, as per Drawing and Specifications.The bed of the excavation shall be made level and firm by watering and ramming.

    3.02 Excavation in soft soil / disintegrated rock - Depth 2.00 to 4.00 meters below ground

    Excavation at depth 2.00 to 4.00 meter below ground by mechanical means for foundations of equipment,buildings, drain, pit, trenches, manholes etc. in ordinary soils including Soft/Disntegrated rock, in both Dry an Wet conditions, including setting out works, pumping and bailing out surface and subsoil water, Shoring, Strutting, Slush removal, as per Drawing and Specifications.The bed of the excavation shall be made level and firm by watering and ramming.

    3.03 Excavation in soft soil / disintegrated rock - Depth 0.00 to 2.00 meters below groundExcavation at depth 0.00 to 2.00 meter below ground by manual means for foundations of equipment, drain, pit, trenches, manholes etc. in ordinary soils including Soft/Disntegrated rock, in both Dry an Wet conditions, including setting out works, pumping and bailing out surface and subsoil water, Shoring, Strutting, Slush removal, as per Drawing and Specifications.The bed of the excavation shall be made level and firm by watering and ramming.

    4.01 Backfilling of soil and disposal4.02 Backfilling with excavated soil

    Backfilling with excavated soil from the excavation at site, compacted in layers about 20 cm thick at least up to 95% of the maximum dry density as determined by the standard Proctor test (ASTM D 698, AASHTO T 180).

    4.03 Filling with clean sandFilling with clean sand, including transport, placing, compacted and all the necessary for the correct execution.

    4.04 Filling with imported earthFilling with imported and selected proper ground, compacted in layers about 8 inches thick at least up to 95% of the maximum dry density as determined by the standard Proctor test (ASTM D 698, AASHTO T 99).

    -

    -

    -

    -

    -

    -

    2,000.00 m3 -

    m3 - 1,000.00

    m3 - 2,000.00

    m3 - 7,500.00

    m3 500.00 -

    m3 - 15,000.00

  • S# Description Unit Unit rate Amount # (SAR/unit) (SAR)

    Quantity

    4.05 Compacted coarse stone 32-65 mm (Sub - Base)Supply and placing of compacted coarse stone 32-65 mm size for sub-base compacted to 95% Proctor Modified.

    4.06 Compacted stone grit 4-32 mm (Base)Supply and placing of compacted stone grit 4-32 mm size for base compacted to 95% Proctor Modified.

    4.07 Filling with gravelSupply, spreading & levelling with gravel of size 30-70 mm size at transformer yard, switchyard area and other area as directed by EPC contractor in layer of 100 mm. etc all complete.

    4.08 Disposal of surplus excavated soilLoading, transporting and disposal of surplus excavated soil at a designated location within a lead of 10 Kms. from site. The disposal shall be carried out as per local regulation. The quoted price shall include dust control measures, transportation, housekeeping etc. all complete.

    5.00 Concrete

    5.01Provision and placing of mass concrete of grade C15 (28th day cube strength 15 N/mm2) under the foundations

    Provision and placing of mass concrete (characteristic resistance of 15 N/mm2) under the foundations. Cement shall be Type I Ordinary portland cement, minimum cement content shall be 200 Kg/m3 and maximum water-cement ratio shall be 0.6 and nominal size of20 mm aggregate,as per the drawings, specifications and directions of Engineer, excluding the cost of shuttering and reinforcement but inclussive of all other materials, tools, plant, labour curing, dewatering, taking cubes and its testing and provided test results complete.

    5.02Provision and placing of concrete of grade C40 (28th day cube strength 40 N/mm2) for all sub-structures & super-structures

    Provision and placing of concrete (characteristic resistance of 40 N/mm2) for varous sub-structures & super-structures as listed below including compaction, cure and protection of concrete. Cement shall be Type I Ordinary portland cement, minimum cement content shall be 375 Kg/m3 and maximum water-cement ratio shall be 0.42,.as per the drawings, specifications and directions of Engineer excluding the cost of shuttering and reinforcement but inclussive of all other materials, tools, plant, labour curing, dewatering, taking cubes and its testing and provided test results complete

    5.02.01 Foundation m3 2,000.00 - - 5.02.02 Slabs m3 1,500.00 - - 5.02.03 Walls m3 750.00 - - 5.02.04 Columns m3 750.00 - - 5.02.05 Beams m3 1,500.00 - -

    5.03 Extra over items nos. 5.01 & 5.02 for concrete with Sulphate Resistant portland cement.5.03.01 For mass concrete - 15N/mm2 m3 500.00 - - 5.03.02 For structural concrete - 40 N/mm2 m3 500.00 - -

    -

    -

    -

    -

    -

    -

    m3 - 500.00

    m3 - 10,000.00

    m3 - 500.00

    m3 - 500.00

    m3 - 500.00

  • S# Description Unit Unit rate Amount # (SAR/unit) (SAR)

    Quantity

    5.04Provision and placing of concrete of grade C25 (28th day cube strength 25 N/mm2) under steps & basesProvision and placing of concrete (characteristic resistance of 25 N/mm2)for steps & bases . Cement shall be Type I Ordinary portland cement, minimum cement content shall be 250 Kg/m3 and maximum water-cement ratio shall be 0.45 and nominal size of20 mm aggregate,as per the drawings, specifications and directions of Engineer excluding the cost of shuttering and reinforcement but inclussive of all other materials, tools, plant, labour curing, dewatering, taking cubes and its testing and provided test results complete

    m3 300.00

    5.05Provision and placing of concrete of grade C10 (28th day cube strength 10 N/mm2) under floor screedProvision and placing of concrete (characteristic resistance of 10 N/mm2)for screed concrete . Cement shall be Type I Ordinary portland cement, minimum cement content shall be 180 Kg/m3 and maximum water-cement ratio shall be 0.6 and nominal size of10 mm aggregate,as per the drawings, specifications and directions of Engineer excluding the cost of shuttering and reinforcement but inclussive of all other materials, tools, plant, labour curing, dewatering, taking cubes and its testing and provided test results complete

    m3 100.00

    5.06 Grouting

    Provision and placing of non shrinking and chloride free grout under base platesas per the drawings, specifications and directions of Engineer inclussive of all other materials, tools, plant, labour curing, dewatering, taking cubes and its testing and provided test results complete, The grout shall have the following minimum characteristicsCompressive strength (BS 1881 part 1, 1983) 26 MPa @ 1 day 55 MPa @ 7 days and66 MPa @ 28 daysExpansion characteristics (ASTM C940 -98a): Up to 2% @ 24 hours

    6.00 Formwork6.01 Formwork - Straight in profile

    Providing, centering, fixing & stripping of good quality formwork straight in profile at all heights & depths including centering & steel Scaffolding all complete as per drawings, specifications and direction of the EPC Contractor/Client.

    6.01.01 Foundation m2 6,000.00 - 6.01.02 Slabs m2 7,000.00 - 6.01.03 Staircase m2 500.00 - 6.01.04 Walls m2 2,500.00 - 6.01.05 Columns m2 750.00 - 6.01.06 Beams m2 1,500.00 -

    -

    m2

    m3 - 5.00

  • S# Description Unit Unit rate Amount # (SAR/unit) (SAR)

    Quantity

    6.02 Formwork - Curved in profileProviding, centering, fixing & stripping of good quality formwork curved in profile at all heights & depths including centering & steel Scaffolding all complete as per drawings, specifications and direction of the EPC Contractor/Client.

    6.02.01 Walls m2 250.00 - 6.02.02 Columns m2 250.00 - 6.02.03 Beams m2 250.00 -

    6.03 Extra-over item nos. 6.01 & 6.02 for providing fair finish6.03.01 For walls straight in profile m2 500.00 - 6.03.02 For columns straight in profile m2 500.00 - 6.03.03 For beams straight in profile m2 500.00 - 6.03.04 For walls curved in profile m2 500.00 - 6.03.05 For columns curved in profile m2 500.00 - 6.03.06 For beams curved in profile m2 500.00 -

    7.00 Reinforcement Bars7.01 Reinforcement bars for concrete (Uncoated)

    Supplying of reinforcing steel,Preparation of bar bending shedules,placing & positioning of HYSD reinforcement bars with characteristic strength of fy = 460 N/mm2 and compliant with BS-4449,including welding joints at all levels above and below ground level for reinforced cement concrete and precast reinforced cement concrete works including cutting, bending, cranking, binding, tack welding, spot welding as necessary, binding wire(1.5mm annealedwire), spacerblocks, electrodes etc, straightening and decoiling wherever necessary all as per drawings, specifications and directions of the engineer, all materials,tools, plant, labour etc, complete. ( authentically accepted laps and chairs will be paid in this item ).

    7.02 Reinforcement bars for concrete (corossion resistant)

    Provision and placing of corrosion resistant HYSD reinforcement bars (CRS bars) with characteristic strength of fy = 460 N/mm2 and compliant with BS-4449, including overlap lengths and tied with wires.including welding joints at all levels above and below ground level for reinforced cement concrete and precast reinforced cement concrete works including cutting, bending, cranking, binding, tack welding, spot welding as necessary, binding wire(1.5mm annealedwire), spacerblocks, electrodes etc, straightening and decoiling wherever necessary all as per drawings, specifications and directions of the engineer, all materials,tools, plant, labour etc, complete. ( authentically accepted laps and chairs will be paid in this item ).

    -

    -

    M.Tons - 400.00

    M.Tons - 150.00

  • S# Description Unit Unit rate Amount # (SAR/unit) (SAR)

    Quantity

    8.00 Structural steel & Ancillaries8.01 Structural steel

    Supply, fabrication & erection of structural steel including loading, unloadig, shifting to work location, preparation of fabrication drawings, surface preparation painting as per specification & drawings.Structural steel conforming to BS-EN-10025 -S355 (Grade-50) at all elevations involving rolled Sections (including mild steel rounds), built up Sections fabricated out of plates, rolled Sections and combination of plates and rolled Sections, in columns, beams, gantry girders, bunkers, silos, hoppers, roof trusses, portals, laced purlins, space frames, shear connectors, hangers, struts, monorails, galleries, stiffeners, wall beams, sheeting runners, brackets, stub columns, bracings, cleats, trestles, base plates, splice plates, chequered plate flooring, decking and seal plates, diaphragm, steel frame grid over false ceiling, walkway platforms, ladders, stairs, stringers, treads, landings, toeplates, MS Rungs, insert plates, edge angles, embedments, lugs, posts,stays, louvers, lacings, gusset plates, safety chains for walkways adjacent to crane girders etc; for Engine hall and other buildings.Surface Preparation- Blast clean for ferrous metals shall be according to S3.21/EP160/2-FE Sa2.5 according to EN ISO- 8501 Painting- shop Primer -two coats of epoxy zinc rich DFT- 75 microns Mid coat - High build miceous iron oxide pigmented epoxy coating DFT-150 microns Finish coat - Polyurethene top coat as approved colour DFT -75 microns

    8.01.01

    Extra over item nos. 8.01 for using Intumescent painting system to provide 2 hrs protection to steel structures according to BS:476-1987Surface Preparation- Blast clean as per Fe Sa2.5 according to EN ISO- 8501 Painting- shop Primer -two coats of epoxy zinc rich DFT- 75 microns Mid coat - Intumescent paint with suitable thickness to suit 2 hrs fire protection Finish coat - Polyurethene top coat as approved colour DFT -50 microns

    m2 1,000.00

    8.02 Handrails and railingsProviding & fabricating steel tube handrails of Nominal bore dia. of 38mm of top rail of 1.1 m height with 38mm dia middle tube and vertical post at every 1.0m c/c with necessary toe guards of 100m high x 4mm thick steel plate including chain links of 6mm wide at openings, providing and fabrications as per the detail designs and drawings or as directed including cutting, fabricating, ransporting erecting, fixing in postion,grouting of post with cement mortar, making welded connection, including galvanised coating.Hand railings shall be steel pipe and shall be constructed pipe conforming to BS1387Steel Tubes and Tubulars Suitable for Screwing to BS21 Pipe Threads" Medium class

    Mtons 6.00

    8.03 LaddersProviding & fixing of steel ladders of width 450mm conforming to BS- 4211 with stringers made of flat sections of 65 mm x 13 mm spaced 380 mm apart, rungs made of 25 mm dia solid rods spaced at 250 mm centres,inluding galvanised coating .

    MTons 5.00

    - M.Tons - 500.00

  • S# Description Unit Unit rate Amount # (SAR/unit) (SAR)

    Quantity

    8.04 Gratingproviding & fixing Galvanised gratingof 25 mm thick, made up of flat bars and rods with seat angles,anchors and supports of Galvanized steel including welding and as per details drawings.

    MTons 20.00

    8.05 chequered plateProviding & fixing 6 o/p chequered plate of weight not less than 53.2 kg/sq.m with all fasteners etc complete as per the drawing

    Mtons 20.00

    8.06 Galvanized steel structureSupply ,fabrication and erection of galvanized steel structure in frames, columns and beams, as well as provision, fabrication and erection at site with bolted connections.

    8.07 Anchor bolts M-20 to M-24

    Supply & fixing of MS anchor bolts including nuts and washers from M-20 to M-24 according to BS 3692 grade 8.8 upto 0.75 meter of length and washers conforming to BS 4320, embedded in the concrete including providing templates, consumables, labour, housekeeping etc. all complete.

    8.08 Anchor bolts M-27 to M-36

    Supply & fixing of MS anchor bolts including nuts and washers from M-27 to M-36 according to BS 3692 grade 8.8 upto 1.0 meter of length and washers conforming to BS 4320, embedded in the concrete including providing templates, consumables, labour, housekeeping etc. all complete.

    8.09 Anchor bolts M-30 to M-36

    Supply & fixing of MS anchor bolts including nuts and washers from M-30 to M-36 according to BS 3692 grade 8.8 upto 1.25 meter of lengthand washers conforming to BS 4320, embedded in the concrete including providing templates, consumables, labour, housekeeping etc. all complete.

    8.10 Field connection bolts M-20 to M-24 (BS 3692 Grade 8.8)

    Supply & fixing of galvanized field connection bolts including nuts and washers from M-20 to M-24 according to BS 3692 Grade 8.8,and washers conforming to BS 4320 including providing templates, consumables, labour, housekeeping etc. all complete.

    9.00 Metal cladding & ventilators9.01 Insulated metal cladding system for roof and walls

    Cladding for roofs and walls fabricated with insulated acoustic sandwich panels comprising of two 0.85 mm thick aluminium sheets of profile colour coated with 80 mm thk polyurethane insulation of Kingspan Panel make or approved equivalent to achieve U value of 0.25 W/m2k including provision of all fasteners, sealant, labour, scaffolding, housekeeping, erection,all necessary accessories, power tools and devices to complete a proper and RAECOure erection.

    9.01.01 For roof m2 800.00 - - 9.01.02 For walls m2 2,500.00 - -

    -

    -

    -

    -

    -

    M.Tons - 100.00

    Kgs - 2,000.00

    Kgs - 2,000.00

    Kgs - 2,000.00

    Kgs 2,000.00 -

  • S# Description Unit Unit rate Amount # (SAR/unit) (SAR)

    Quantity

    9.02 Single skin metal cladding for roof and wallsCladding for roof and walls in aluminium sheet of 0.7 mm thick profile colour coated with sandwich panel of 80mm thick polyurethane insulation of of U -value 0.25W/m2k, including provision of all fasteners, sealant, labour, scaffolding, housekeeping, erection,all necessary accessories, power tools and devices to complete a proper and RAECOure erection.

    9.03 Flashing & Trim

    Supply & installation of flashing & trim of 0.45 mm thick galvanized steel sheet to eaves, corners, bases, frame openings, fascias and fillers including all material, fasteners, sealant, etc. all complete.

    9.04 Roof kerb

    Supply & installation of roof kerbs fabricated from 1.2 mm thick, zinc-coated (galvanized) steel sheet or aluminium-zinc alloy-coated steel sheet pre-painted with coil coating; with welded top box and bottom skirt, and integral full-length cricket. Fabricate curb sub-framing of minimum 1.5 mm thick, angle-, C-, or Z-shaped steel sheet. Fabricate curb and sub-framing to withstand indicated loads, of size and height indicated. Finish roof curbs to match metal roof panels. The Contractor shall insulate all roof curbs with 75 mm thick, rigid insulation.The quoted rate shall include all materials, tools, labour, consumables, scaffolding etc. all complete.

    9.05 Galvanized steel ridgeGalvanized steel ridge of 0.6 mm thick, placed in metallic building, with minimum development of 300 mm, even fixation accesories and waterproof joints. Measured in true magnitude.

    9.06 Roof ventilatorSupply and installation of non-power turbine ventilator including all accessories, sealants, fasteners, labour, scaffolding, consumables etc. all complete.

    9.07 Roof &side wall GlazingSupplying & fixing of 4mm thick Polycarbonate sheets transparent and smoke tinted,including alumnimum frames on the roofs & side walls and sealing joints as per the specifications & drawings including cutting of metal sheet, all fixtures & fasterns, labour complete.

    m2 50.00

    -

    -

    -

    -

    - Each - 50.00

    m - 1,500.00

    m2 - 650.00

    m - 50.00

    m 1,500.00 -

  • S# Description Unit Unit rate Amount # (SAR/unit) (SAR)

    Quantity

    10.00 Masonry and Finishes10.01 Concrete block wall (39 x 19 x 14 cm) with minimum compressive stength of 10.5 N/mm2

    Supply & laying of 200 mm thick concrete masonry unit in cement lime mortar 1:1:6 (1 part cement: 1 part of lime:3 parts coarse sand) for external walls upto 3.00 m height including raking out joints, curing, scaffolding etc. all complete excluding plastering and painting.Every fourth course of brick works shall be provided with reinforcement steel.The quote rate shall include all materials, scaffolding, tools, labour etc. all items necessary for satisfactory completion of works.

    10.02 Concrete block wall (39 x 19 x 9cm)with minimum compressive stength of 10.5 N/mm2Supply & laying of 100 mm thick concrete masonry unit in cement mortar 1:1:6 (1 part cement:1 part lime: 3 parts coarse sand) for internal walls including raking out joints, curing, scaffolding etc. all complete excluding plastering and painting.Every fourth course of brick works shall be provided with reinforcement steel.The quote rate shall include all materials, scaffolding, tools, labour etc. all items necessary for satisfactory completion of works.

    10.03 External plasterProviding 20 mm thick plaster in three layers (base, browning & finish coat) on external surfaces with cement mortar 1:3 to a smooth finish including making grooves, all materials, scaffolding, curing etc. all complete as per specifications and drawings.Approved waterproof agent and plasticizer shall be added to the mix. Top coat shall be in "Tyrolean" finish of uniform thickness and texture.The quote rate shall include all materials, scaffolding, tools, labour etc. all items necessary for satisfactory completion of works.

    m2 2,500.00 -

    10.04 Internal plaster (Vertical surface)Providing 12 mm thick plaster in three layers (base, browning & finish coat) on internal surfaces with cement sand mortar in 1:3 ratio and applied to a smooth finish including making grooves, all materials, scaffolding, curing etc. all complete as per specifications and drawings.The quote rate shall include all materials, scaffolding, tools, labour etc. all items necessary for satisfactory completion of works.

    m2 2,500.00 -

    -

    - m2 - 2,500.00

    m2 - 2,500.00

  • S# Description Unit Unit rate Amount # (SAR/unit) (SAR)

    Quantity

    10.05 Ceiling plaster

    Providing 6 mm thick plaster on ceiling with cement mortar 1:3 to a smooth finish including making grooves, all materials, scaffolding, curing etc. all complete as per specifications and drawings.

    m2 1,500.00 -

    10.06 Alkali Resistant Tiles on wallsSupply and fixing of Alkali resistant tiles on walls upto height of 3.00 meters of size 200 mm x 200 mm x 20 mm thk on 15 mm thk bedding of cement mortar of ratio 1:3, joint width of 2 mm, including grouting of joints, housekeeping, scaffolding etc. all complete

    m2 500.00 -

    10.07 Alkali Resistant Tiles on floorSupply and fixing of anti-skid Alkali resistant tiles of size 200 mm x 200 mm x 20 mm thk on 25 mm thk bedding of cement mortar of ratio 1:3, joint width of 6 mm including grouting of joints, housekeeping etc. all complete

    m2 500.00 -

    10.08 Glazed Ceramic Tiles on wallsSupply and fixing of glazed ceramic tiles of size 200 mm x 200 mm x 7 mm thk on 15 mm thk bedding of cement mortar of ratio 1:3, joint width of 2 mm including grouting of joints, housekeeping etc. all complete

    m2 500.00 -

    10.09 Unglazed Ceramic Tiles on floor

    Supply and fixing of unglazed antislip ceramic tiles of size 600 mm x 600 mm x 7 mm thk on 25 mm thk bedding of cement mortar of ratio 1:3, joint width of 2 mm including grouting of joints, housekeeping etc. all complete

    m2 500.00 -

    10.10 Concrete hardner floor finsih

    Supply and application of polyurethere based coating system on concrete surfaces in specified areas including provision of tools, sealing, housekeeping etc. all complete.The primed surface shall be coverd with a polyurethene based hard wearing flexible base coat consisting of two component self smoothing compound with a nonslip finish.The top finishing coat shall be a 2 pack- polyurethene based ocating giving a flexible wearingsurface suitable for mechanical workshops.

    10.11 CarpetSupply and installation of carpet for office & prayer area procured locally of reputed or approved equivalent make including adhesive, consumables, tools etc all complete.

    -

    -

    m2 250.00

    m2 50.00 -

  • S# Description Unit Unit rate Amount # (SAR/unit) (SAR)

    Quantity

    10.12 Suspended ceilings

    Suspended ceiling with acoustic gypsum tile:Providing and fixing 20 mm thick gypsum fibre board false ceiling tiled false ceiling of approved materials of size 1200X600 mm in true horizontal level suspended on inter locking metal grid of powder coated aluminum frames consisting of main "T" runner with suitably spaced joints to get requird length and of size 24X38mm made from 0.30mm thick (minimun) sheet spaced at 1200mm center to center and cross "T" of size 24X25mm made of 0.30mm thick (minimun) sheet, 1200mm long spaced between main "T" at 600mm center to center to form a grid of 1200X600 mm and secondary cross "T" of length 600mm and size 24X25mm made of 0.30mm thick (minimun) sheet,To be interlocked at middle of the 1200X600 panel to form grids of 600X600mm and wall angle of size 21X21X0.3 mm and laying false ceiling tiles of approved texture in the grid including, wherever, required, cutting/making, opening of services like diffusers, grills, light fittings, fixtures, smoke detectors etc. Main "T" runner to be suspended from ceiling using GI sloted cleats fixed to ceiling with 6mm dia and 50mm long dash fastener , 4mm GI adjustable rod with galvanised level clips spaced at 1200mm center to center along main "T" bottom exposed width of 24mm of all T-sections shall be pre-painted with polyester paint, all complete at all heights as per specifications, drawings and as directed by engineer in charge. Texture, colour, shape, finish, type, brand to be approved by engineer in charge.

    m2 500.00 - -

    10.13 Flase Flooring

    Providing and fixing of raised flooring system 600 mm high comprising of 600 x 600 x 32 mm cement fill metallic false flooring panel with 1.2 mm antistatic high pressure laminate tile on top. The supporting arrangement for cement fill metallic panels false flooring shall consist of seamless pipe 25 mm. outer dia and 12 mm thick base plates. The pipes shall be fixed on the floor @ 600 mm c/c with 50x6 mm metal screw with nilon rowal plug. The pipe heads will have MS check nut and M18x 100 long studs with jackhead zinc plated of size 90x90x4 mm thick over which GI stringer 30x20x1.5 thk having pre punched holes 6 mm dia for the fixing of panels,Base plate size - 100 x 100 x 10 mm;The rate shall include panel, supporting arrangement, submission & approval of samples, tools, labour, housekeeping etc. all complete.

    m2 500.00 -

    10.14 Expansion joint 12 mmProvision and placing of expansion joints 12 mm thick between surfaces of concrete, formed by polyurethane expanded and sealed with resistant bicomponent to frictions and heavy traffic. Measurement according to the theoretical length in planes.

    10.15 SkirtingCeramic tile skirting shall be 200 x 150 mmx 7 mm with a bullnosed top to plastered walls with CM1:6, the skirting standing 5mm proud of the walls finish and with a square top to tiled walls, the skirting finishing flush with the tilling, the cove radius not less than 15mm. The bases shall be of the same quality as the above-specified ceramic tiles.

    m2 100.00

    - m - 1,500.00

  • S# Description Unit Unit rate Amount # (SAR/unit) (SAR)

    Quantity

    11.00 Miscellaneous steel11.01 Galvanized Standard Steel Doors

    Standard steel doors and frames made of cold-rolled steel, door faces will be made of cold-rolled sheet steel too 0,8mm of thickness, including welding, painting and all necessary accesories to complete a RAECOure erection.

    11.02 Steel stairs Supply and erction of steel stairs with 1,2 meter of wide, made of hot-rolled steel, including welding, painting and all necessary accesories to complete a RAECOure placement.

    12.00 Woodwork12.01 Timber wall panels

    Supply and fixing of timber wall panels upto height of 2.15 meters in prayer room including all fixtures, fasteners, adhesives, sealants etc. all complete.

    13.00 Painting13.01 External Painting

    Providing and applying to exterior surfaces at all elevations two coats of exterior weather and oil resistant emulsion paint over POP of approved manufacture, colour and shade(as per manufacturers instructions over a coat of primer,) and all as per specifications, drawings, and directions of the engineer, including surface preparation, scaffolding, all materials, labour etc, complete ( (including the cost of primer).

    13.02 Internal PaintingProviding and painting interior surfaces at all elevations with two coats of acrylic emulsion paint of approved manufacture, colour and shade over a coat of primer as per manufactures recommendations and including surface preparation, scaffolding, all materials, labour etc, complete. (including the cost of primer).

    13.03 Painting on ceilingsproviding & painting on all interior ceiling/soffits at all elevations with two coats of approved emuslion paint @ 12-14 m2/ltr, applied over two coats of putty, applied over primer@ 7-9 m2/ltr. Include all scafffolding, labour etc.

    13.04 Painting above flase ceiling

    Providing and painting all block walls above the false ceiling with 3 coats of silane- siloxane coating @ 0.25 lits/m2 for each coat.

    13.05Painting on internal surfaces of buried structures (like Cable trenchs, culverts, ductbanks & lifting stations)All internal surface of concrete structures buried below ground, shall be provided a heavy duty coating to provide long term protection against carbonation, chloride ingress & surface abrassion.The coating shall be solvent free coal tar extended epoxy resin of two coats with minimum DFT of 400 micron each coat.The coating shall be suitable for direct application on concrete surfacs without use of primer.

    -

    -

    -

    m2 - 50.00

    m2 250.00

    m2 250.00

    m2 - 150.00

    m - 50.00

    m2 1,200.00

    m2 500.00

    m2 1,000.00

  • S# Description Unit Unit rate Amount # (SAR/unit) (SAR)

    Quantity

    13.06 Bitumen coating for Below ground concrete structures incontact with soil/water

    Supply and application of 2 coats of high build bitumen coating which shall vbe flexible,damp & vapour proof surface applied liquid memebrane to underground concrete surfaces having the solid content 50% by weight and zero percent water permeability. The quoted rate shall include all necessary application of primer, tools, scaffolding etc. all complete.

    14.00 Vapour barrier, waterproofing & thermal insulation14.01 Tanking membrane

    Supply and application of tanking membrane Fosroc Proofex or equivalent in two layers on underground concrete surface of approve make. The quoted rate shall include all necessary application of adhesive, tools, scaffolding etc. all complete.

    14.02 Roof waterproofingSupply and application of roof waterproofing system comprising of the following:1. Concrete screedof minimum 50 mm thick with 10mm size agreegates;2. Polyethylene-sheet vapour retarder 1.5 mm thick solar reflective roof cold applied,flexible, preformed water proofing membrane comprising a 4 layer cross laminated HDPE carrierfilm with a solar reflective & self adhesive rubber/bitumen compound conforming to ASTM D638 , with a maximum moisture vapour transmission rate of 0.2g/m2/24 hrs3. Extruded High density polystyrene rijid foam board 600x1200x100 thick, compressive strength 280kPA, water absoprtion

  • S# Description Unit Unit rate Amount # (SAR/unit) (SAR)

    Quantity

    14.05 Geotextile MembraneSupply and laying of geotextile membrane of thickness 2.3 mm and weight 0.27 kg/cm2 including cutting, overlaps, adhesives, housekeeping etc. all complete. The lining materials shall be warranted against manufacturing defects and material degradation for a period of 30 years from the date of official acceptance by the Company/Engineer. Materials that fail within the warranty period shall be replaced at no cost to the Company.

    14.06 WaterstopSupply and installation of 225 mm wide, 6 mm thick PVC waterstop of Fosroc or equivalent make at slab-wall joints of underground tanks.

    14.07 Joint SealantSupply and installation of closed cell expanded polyethylenefoam of size 25 mm x 25 mm including backing strip of polysulphide compound, cleaning the joint etc. all complete.

    14.08 Damp proof courseSupply and application of 2 coat of water repellent silicone sealer, film-forming, polymerized, silicone-resin water repellent for dense substrates. It shall be a solvent or water-based solution containing not less than 3% and up to 5% solids by weight, and shall comply with FS SS-W-110C. Such a course shall be applied below concrete masonry units.

    15.00 Downspouts and Gutters15.01 Gutters in galvanized mild steel steel

    Provision and placing of gutters in buildings, including all necessary accesories to complete as per specifications & drawings

    15.02 Downspouts galvanized diameter 150 mmDownspouts pipes diam. 150 mm, made of galvanized mild steel medium gauge, including joints and all necessaries to complete as per specifications & drawings.

    15.03 Downspouts PVC diameter 150 mmDownspouts pipes diam. 150 mm, made of PVC, including joints and all necessaries to complete as per specifications & drawings

    16.00 Supply and laying of GI Pipes

    Supply and laying of GI pipes including joining, pressure testing etc. all complete for various diameters.

    16.01 25 mm dia m 25.00 16.02 40 mm dia m 25.00 16.03 60 mm dia m 25.00

    -

    -

    -

    -

    -

    -

    -

    m - 250.00

    m 500.00

    m - 250.00

    m 500.00

    m2 650.00

    m2 500.00

    m - 250.00

  • S# Description Unit Unit rate Amount # (SAR/unit) (SAR)

    Quantity

    17.00 Supply and laying of drainage pipes

    17.01Supply and laying of cast iron pipes including joining, pressure testing etc. all complete for various diameters.

    17.01.01 90 mm dia. m 25.00 17.01.02 200 mm dia. m 25.00 17.01.03 315 mm dia. m 25.00 17.01.04 400 mm dia. m 25.00 17.01.05 600 mm dia. m 25.00

    17.02Supply and laying of RCC pipes including joining, pressure testing etc. all complete for various diameters.

    17.02.01 300 mm dia. m 25.00 17.02.02 400 mm dia. m 25.00 17.02.03 600 mm dia. m 25.00 17.02.04 900 mm dia. m 25.00

    17.03 Concrete manholeProvision, placing and levelling of concrete manhole with forged iron cover (diameter of the manhole 1.10 m minimum and 2.50 m depth), with 150 mm minimum thickness for floor slab and 150 mm minimum thickness for walls, including excavation, soil improvement and compaction, placing of the manhole and final refilling (where necessary) around the manhole.

    17.04 Precast concrete pit 63x63cm and 1m depth for connectionsProvision, placing and levelling of precast concrete pit for conections with forged iron cover (square RAECOtion of 63x63 cm width minimum), with 100 mm minimum thickness for floor slab and 150 mm minimum thickness for walls, including excavation, soil improvement and compaction, placing of the pit and final refilling (where necessary) around the pit.

    17.05 Collecting pits (culvert) 51x34cm, 60cm depthCollecting pits of concrete (culvert) 51x34cm RAECOtion and 60cm depth, with forged iron cover, including excavation, backfilling and transport of the leftover ground to a licensed suitable site.

    17.06 Separating fat pitInspection box separator fat, made with walls of 20 cm of solid brick, flattened and polished inwardly with cement mortar, on concrete floor of 15 cm of thickness and fences with ductile iron covers, class c (250 KN), with a total length of 3 m and a width of 1.5 m with a depth of the existing collector include also; excavation, fill, compaction and transport of waste to landfill.

    17.07Supply and laying of PVC pipes including joining, pressure testing etc. all complete for various diameters.

    17.07.01 100 mm dia. m 25.00 17.07.02 150 mm dia. m 25.00

    -

    -

    -

    - m - 5.00

    Each - 5.00

    Each - 5.00

    Each - 5.00

  • S# Description Unit Unit rate Amount # (SAR/unit) (SAR)

    Quantity

    17.08Supply and laying of HDPE pipes including joining, pressure testing etc. all complete for various diameters.

    17.08.01 100 mm dia. m 25.00 17.08.02 150 mm dia. m 25.00

    18.00 Roads18.01 Asphalt Road

    18.01.01 Preparation of subgrade as per Oman General specification of roads section 300Excavation upto required depth, watering and rolling of the subgrade with rollers to achieve maximum density of 95%, irregularities or depressions that develop during the compaction shall be corrected to the specified grade by loosening the material at these places and adding, removing, or replacing the material.

    18.01.02 Sub-base courseas per Oman General specification of roads section 300Supply and laying of sub-base course with well-graded materials of the class or classes shown on the drawings or specifications. All materials shall be free from organic matter, shale or other deleterious matter and shall be of such quality that it will bind readily to form a firm stable base for placement of flexible pavement.

    18.01.03 Base course as per Oman General specification of roads section 300Supply and laying of base course with well-graded materials of the class or classes shown on the drawings or specifications. All materials shall be free from organic matter, shale or other deleterious matter and shall be of such quality that it will bind readily to form a firm stable base for placement of flexible pavement.

    18.01.04 Prime coat as per Oman General specification of roads section 400Supply and application of prime coat uniformly to the sub-base course using a pressure distributor at a rate between 1.0 to 1.75 litres per square metre.The primer shall be applied to a width of at least 300 mm greater on each side of the specified width of the finished surface. The prime coat shall be of medium-curing type cutback asphalt consisting of asphaltic base fluxed with suitable petroleum distillates. The product shall be free of water, show no separation prior to use, shall not foam when heated to application temperature and shall conform to the requirements of Grade MC-70 or MC-250 of ASTM D2027.

    -

    -

    -

    -

    m3

    m3

    1,500.00

    500.00

    500.00

    m2

    m2 1,500.00

  • S# Description Unit Unit rate Amount # (SAR/unit) (SAR)

    Quantity

    18.01.05 Binder course - 100 mm thk as per Oman General specification of roads section 400Supply and laying of asphaltic concrete comprising of Asphalt Cement of homogenous, penetration grade 60-70, 85-100 or 150-200, free of water, shall not foam when heated to 177C, and conforming to the requirements of ASTM D946. Mineral aggregates shall consist of coarse aggregates, fine aggregates, and filler material. Asphalt concrete shall be a combination of mineral aggregates and asphalt cement in such proportion as to produce a mixture conforming to the composition limits by weight per table below:1. Total Mineral Aggregate : 93-96 % 2. Asphalt Cement : 4 - 7%

    18.01.06 Tack coat as per Oman General specification of roads section 400Supply and application of tack coat with of rapid-curing type cutback asphalt consisting of asphalt base fluxed with suitable petroleum distillates. The product shall be free of water, show no separation prior to use, shall not foam when heated to application temperature and shall conform to the requirements of Grade RC-800 of ASTM D2028. The tack coat shall be uniformly applied over the entire surface of the area to be covered, when the temperature of the tack coat material is between 95C to 120C.

    18.01.07 Wearing course - 80 mm thk as per Oman General specification of roads section 400Supply and laying of asphaltic concrete comprising of Asphalt Cement of homogenous, penetration grade 60-70, 85-100 or 150-200, free of water, shall not foam when heated to 177C, and conforming to the requirements of ASTM D946. Mineral aggregates shall consist of coarse aggregates, fine aggregates, and filler material. Asphalt concrete shall be a combination of mineral aggregates and asphalt cement in such proportion as to produce a mixture conforming to the composition limits by weight per table below:1. Total Mineral Aggregate : 93-96 % 2. Asphalt Cement : 4 - 7%

    18.01.08 Seal coatSupply and application of asphalt seal coat.

    18.01.09 Precast Concrete KerbsSupply and installation of precast concrete kerbs of size 600 mm x 200 mm x 450 mm founded on concrete bedding along the edge of the road. The precast kerb shall be laid on minimum of 400mm wide & 300mm high plain concrete grade C20 and joined with cement-sand mortar of 1:3 ratio.

    18.02 Car park shedSupply and installation of car park shelter of size 6.00 m x 3.00 m. Each 3.00

    1,500.00 -

    1,500.00

    -

    -

    -

    m2

    m2

    m

    m2

    m2

    1,500.00

    500.00

    - 1,500.00

  • S# Description Unit Unit rate Amount # (SAR/unit) (SAR)

    Quantity

    19.00 Others19.01 Anti Termite Treatment

    Providing and injecting approved quality chemical emulsions as specified for pre-constructional Anti-termite Treatment chemicals such as Malathion, Dursban 4TC, K-Othrine EC, Ficam, Dieldren, Tergram (Gamma BHC Isomer) and Permethrin (Dragent FT),and creating a chemical barrier under and around column pits, wall trenches, basement excavation, top surfaces of plinth filling, junction of wall and floor, along the external perimeter of building, expansion joints, surrounding of pipes and conduits etc. as specified, complete with all labour, tools, tackles, consumables as per direction of the Engineer-in-charge. (Only ground floor plinth area of all building will be measured for payment). However, area requiring treatment but not covered in plinth area shall be measured for the areas actually treated for payment purposes. Material to be approved by engineer in charge

    19.02 Warning tapesSupply and laying of RAECO approved warning tapes 150 mm wide in trenches for cables.

    19.03 Cable Protection tilesSupply and laying of RAECO approved cable protection tiles of size 40 cm x 20 cm x 5 cm in trenches for cables.

    19.04 Vehicle access barrierSupply and installation of vehicle access barrier - 5.00 m wide

    19.05 Aluminium Windows

    Supplying, fitting and fixing minimum 20 micron Bronze colour anodised aluminium windows of various sizes made with All extrusions shall be of AlMgSi, designation 6060, or 6063, temper T5, heattreatable, and shall be in accordance with BS 1474 : 1987, 50 mm thick box frames.windows shall be delivered to site complete with all fittings. All windows and their components shall conform to B.S.4873 and shall be designedto resist the severe (b) exposure test pressure of 2800 N/m2 when tested inaccordance with BS 4315: Part 1, and test certificates shall be submitted to thesupervising Engineer confirming this requirements.All frames and casements shall be fully weather stripped with continuous neoprenestrips and shall be designed for internal glazing with snap-on Aluminium beads. Thosewindows shown on the schedules or drawings to be openable shall open inwards andshall be secured in the closed position by means of budget locks.All aluminium surfaces in contract with steel, concrete, masonry or mortar shall beprotected by painting with bituminous paint or taping with PVC before fixing in position.The windows shall be fixed-in with stainless steel lugs, or with screws supplied by themanufacturer, in accordance with the details shown on the Drawings.After fixing and where shown on the Drawings, the frames shall be pointed inpolysulphide or equal and approved non-hardening pointing sealant recommended bythe window manufacturer.Frames shall conform to the above specifications and glazing shall be 24mm overall bronze tinted tempered 8mm (external) and 8mm clear tempered glass ( internal) with 8mm airgap in middle.

    -

    -

    -

    -

    -

    - 250.00

    Each - 2.00

    m2 - 300.00

    m2 - 15,000.00

    m - 500.00

    m2

  • S# Description Unit Unit rate Amount # (SAR/unit) (SAR)

    Quantity

    19.06 Aluminium LouversThe louvers shall be of 18-gauge Aluminium, of fixed pitch at 45mm, complete withframes, sills, and mullions as detailed on the Drawings. The louvers shall bepreformed for site assembly, and shall be anodized to match the windows inaccordance with B.S 3987. The back of the louvers shall be fitted with bird meshscreens or blank sheet Aluminium panels where indicated on the Drawings.

    19.07 Metal Doors & frames

    Metal Door (Scientific Door): Providing & Fixing of Metal Door frames and door shutters made upof Galvanize steel (base steel of 0.58 mm thick D quality, galvanized with Zinc of 120 GSM) Pure polyester powder upto 50-60 microns thick . Outer frame section should be of 100x 58mm x 1.2mm thick. Shutter section should be of 0.80 mm thick galvanized steel sheet pressed (roll formed) to provide a 46mm thick fully flush, double skin door shell Seam joints at stile edges. In-fill of Honeycomb Kraft paper is used to give the required rigidity and effective acoustic insulation. 6 Tower bolt 1 No., 6 D handles 2 Nos., 10 Aldrop 1 No., Butt Hinges 3 Nos, Mortise Lock of approved quality 1 No. The above frames should be fixed to the concrete/masonry wall by means of self expanding screws complete for finished item of work.

    19.07.01 Single leaf doors - 1200 mm x 2100 mm Each 25.00 - 19.07.02 Double leaf doors - 2100 mm x 2100 mm Each 25.00 -

    19.08 wooden Louvred Doorssupply & installation of louvred doors manufactured with hardwood. The top rail shall be 148x50mm, with middle & bottom rails 246x50mm. The top & bottom panels shall be formed with hardwood louvre blades each side 70x10 set at 450 to throw rainwater at the external face.

    19.09 Fire Resistant Steel DoorsSupply and installation of fire resistant steel doors made of steel profiles & stel sheet plates as per specifications of 19.07 insulated with mineral wool, surface treatment and painting similar to steel structures. The fire rating shall be 2 hours. All doors shall be complete with ironmongery including locking arrangements with masterkey system handles & fastens, hinges etc.

    19.09.01 Door size - 2000 mm x 2100 mm Each 4.00 19.09.02 Door size - 1000 mm x 2100 mm Each 4.00

    25.00 -

    -

    m2

    m2 - 1,500.00

    m2 30.00

  • S# Description Unit Unit rate Amount # (SAR/unit) (SAR)

    Quantity

    19.10 Toilet doors (UPVC)

    Providing and fixing to existing door frames 30 mm thick factory made Polyvinyle Chloride (PVC) door shutter made of styles and rails of a UPVC hollow section of size 60x30mm and wall thichness of 2mm +0.2 mm with inbuilt decorative moulding edging on one side.Thestyles and rails mitred and joined at the corners by means of M.S. galvanised/plastic brackets of size 75x220mm having wall thickness 1.0mm and stainless steel screws. the styles of the shutter reinforced by inserting galvanised M.S. tube of size 25x20 mmand 1mm+/- 0.1mm wall thicknes. the lock rail made up of H section,a UPVC hollow section of size 100x30 mmand 2mm +/-0.2 mm wallthickness fixed to the shutter styles by means of plastic/ galvanised M.S. `U`cleats .The shutter frame filled with a UPVC multi chambered single panel of size not less than 620mm,having overall thickness of 20 mm and 1mm+/-- 0.1mm wall thickness. The panels filled vertically and tie bar at two places by inserting horizontally 6mm galvanised M.S. rod and fastened with nuts and washers,complete as per manufacturer`s specification and direction of Engineer -in -charge

    m2 50.00

    19.11 wooden doors

    supply & installation of 40 mm thick solid flush doors made from solid cores of hardwood . stiles & toprail of minimum width 80mm, bottom rail of minimum width 200mm. With 6mm plywood on both sides,10mm thick lipping alround and shall confirm to half hour fire resisitant doors in accordance to BS 4787.Complete with all necessary fixtures, ironmongery, handles, locks, hinges and labour.

    10.00

    19.12 Rolling ShuttersSupplying and fixing in position approved make electrically operated steel rolling shutters conforming to relevant british standards, (with wicket gate where necessary) including all fittings, fixtures (including guide channels and hood cover etc), motor, all as per drawings, specifications and instuctions of engineer(M.S rolling shutters shall be made of interlocking lath section formed from bright cold rolled, annealed M.S strips not less than 0.90mm thick for shutters up to 3.5m width & not less than 1.20mm thick for shutters above 3.50m width, with weather seals and wind lock and shall have grills for ventilation where necessary. Its components shall be factory galvanized, primed and field painted as specified). of size 3000 mm W x 4000 mm H

    - Each 4.00

    m2

  • S# Description Unit Unit rate Amount # (SAR/unit) (SAR)

    Quantity

    19.13 Rolling ShuttersSupplying and fixing in position approved makemanually operated steel rolling shutters conforming to relevant british standards, (with wicket gate where necessary) including all fittings, fixtures (including guide channels and hood cover etc), motor, all as per drawings, specifications and instuctions of engineer(M.S rolling shutters shall be made of interlocking lath section formed from bright cold rolled, annealed M.S strips not less than 0.90mm thick for shutters up to 3.5m width & not less than 1.20mm thick for shutters above 3.50m width, with weather seals and wind lock and shall have grills for ventilation where necessary. Its components shall be factory galvanized, primed and field painted as specified).size 1500 mm W x 2500 mm H

    19.14 Fence

    Supply and installation of chain link fence with following specifications:2.4 m height PVC coated chain link fence of gauge 8, on 50 mm dia GI pipes,planted at 3.0 m intervals with top and bottom and intermediate horizontal GIpipes. Inclusive of PVC coated tension wire (4 rows length wise) strut poles andrubble curb wall 300 mm wide and 450 mm below ground (minimum), 300 mmabove ground (minimum dimension) with plastered surface. Top of GI poles tobe covered with PVC riveted capsChain link fencing wire mesh shall be 3.5mm overall diameter olive green plastic coated to BS 4102 of standard mesh size 50mm and height 1800mm as specified and shall have a galvanized core diameter of 2.50mm as BS 4102 table-3Support tension wires to bottom, middle and top of wire mesh shall be 4mm diameter galvanized steel cold tension wires as specified in BS 4102.Tying wire finished with galvanized coating shall be 2.5mm galvanized tying wire as specified in BS 4102.Barbed wire where specified shall comply with the requirements of BS 4102.Steel intermediate posts shall be to BS 6328. Parts 1 to 8 and be 50mm nominal bore Medium / Low Speed galvanized steel tube with three 10mm diameter holes fir wires and length 2.6m or 2. 0m.The ends of the posts to be set in concrete shall be sprigged.Steel corner posts and straining posts shall be 60mm nominal and fitted with two 50mm nominal bore Medium / Low Speed galvanized steel tube strut braces fixed at 45 degrees to level ground. The struts shall be fitted in the direction of each line of fencing secured to them. All works to be as per design requirements, final approved drawings & specifications.

    19.12 Compound wall fenceSupply and installation of chain link fence with UPVC coat steel security barbed wire for 1m height

    -

    -

    Each 4.00 -

    m 900.00 -

    m - 600.00

  • S# Description Unit Unit rate Amount # (SAR/unit) (SAR)

    Quantity

    19.13 Gates

    19.13.01

    Sliding gates: Providing & fixing GI framed gate with minimum 7.0 m clear width x 2.4 Height with colour bond cladding double sashed, side hung door inclusive of bottom rails, guide wheelswith self lubricated heavy duty ball bearings & inclusive of gate columns andlocking arrangements.Steel posts shall be galvanised in accordance with the specification.Access gates shall be both single and double entrance gates shall be fabricatedtubular steel and galvanised after manufacture. They shall comply with BS 1722 Part 1Supplement No. 1 Sockets for casting into the roadway shall also be provided. Thesockets shall be designed to provide secure and robust support for drop bolts whengates are in both open and closed positions.Each gate shall be supplied with a padlock and three keys all to the Engineer's

    Each 3.00 -

    19.13.02Supply and installation of man entry swing gates of size 1000 mm wide x 2400 mm height with the same material specifications of sliding gates

    Each 3.00 -

    19.14 Limestone claustraSupply and installation of limestone claustra of size 300mm x 240mm x 115mm 5DF of approved color on transformer yard fire wall

    19.15 Septic tank

    Construction of septic tank of capacities for 50 users as per approved drawing with Brick walls and RCC slab including two 560 mm dia. R.C.C. manhole cover of approved make supplied,fitted, & fixed in the top slab with necessary fittings , 15mm thick cement plaster (4:1) with neat cement finish to the internal surfaces and 15 mm thick cemnt plaster (4:1) to outside wall upto 200 mm below G.L. floor finished with 25 mm thick grey artificial stone including supplied,fitted, and fixedS.W. tees C.I. foot rest etc. including excavating earth in all sorts of soil shoring bailing and pumping out water as necessary , ramming, dressing the bed and refilling the sides of the tank with earth , removing spoils filling up the chamber with clear water, removing foreign materials from the chamber & including constructing attached inspection pit as per approved drawing and connecting all necessary pipes , joints, etc. with internal plaster work and artificial stone flooring is to be done with admixture compound @ 5% weight of cement ,complete in all respect .

    Lumpsum 1.00

    19.16 soak PitConstruction of brick lined soak pit of required diameters, depth of the for 50 users and SW drain pipe 100 mm dia. 1.8m long and including connection from septic tank to soakpit etc., complete as per standard design

    Lumpsum 1.00

    - Each 50.00 -

  • S# Description Unit Unit rate Amount # (SAR/unit) (SAR)

    Quantity

    20.00 Furniture20.01 Curved desk - 5 persons

    Supply and installation of curved desk unit suitable for 5 persons in arc shape.20.02 Straight console desk - 2 persons

    Supply and installation of Straight console desk unit for 2 Operator cum Engineering station.20.03 Printer Tables

    Supply and installation of tables for printers from reputed local make.20.04 Executive Chairs

    Supply and installation of executive chairs of reputed make.20.05 Steel racks

    Supply and installation of steel racks for workshop.20.06 Steel cupboard

    Supply and installation of steel cupboard for workshop.21.00 Sanitary Fixtures

    Supply & fixing of sanitary fixture including complete accessories, bolts etc.21.01 Wash-Basin - Pedestal type Each 10 - 21.02 Mirror - 600 mm x 450 mm x 6 mm thk Each 4 - 21.03 Kitchen sink - stainless steel make Each 2 - 21.04 European type WC Each 2 - 21.05 Asian type WC Each 4 - 21.06 Urinals with partition Each 4 - 21.07 Shelves Each 2 - 21.08 Towel holder - 600 mm long Each 6 - 21.09 Toilet paper holder Each 2 - 21.10 Liquid soap holder Each 4 - 21.11 Handspray Each 6 - 21.12 Faucet Each 6 - 21.13 Shower Each 6 - 21.14 Soap holder Each 6 - 21.15 PVC Floor drains Each 20 -

    2.00 - -

    Each 12.00 - -

    -

    - 2.00 -

    Each 2.00 - -

    Each 2.00 - -

    Each 2.00 -

    Each

    Each

  • S# Description Unit Unit rate Amount # (SAR/unit) (SAR)

    Quantity

    22.00 Landscaping22.01 soft Landscaping

    Green Landscaping:Landscaping includes removing of top soil upto 250 mm below FGL, preparation of ground, cultivation of ground, supplying of imported soil,sand, manure ,Supply and planting of trees, shrubs and grass(Bermuda grass) conforming to BS 3936 from the approved source , supplying and laying of gravel(28 mm size), with all necessary pegs & wires in the space as shown in the drawings.

    22.02 Interlock paving - 60 mm thk for pedestrain walkwaysSupply and laying of heavy duty interlocking precast concrete flags of 60 mm thickness with a minimum compressive strength of 40 N/mm2 including sand bedding , coloured throughout . The concrete paving shall be sealed with a premium quality,durable, water based, approved clear sealer@ 7-10m2/ltr. TheQuoted rate shall include supply of interlock tiles, sand , compaction,tools, labour etc. all complete.

    22.03 Interlock paving - 80 mm thk for Roads & parking areas

    Supply and laying of heavy duty interlock precast concrete flags of 80 mm thickness with a minimum compressive strength of 40 N/mm2 including sand bedding and coloured throughout.The concrete paving shall be sealed with a premium quality,durable, water based, approved clear sealer@ 7-10m2/ltr Quoted rate shall include supply of interlock tiles, sand , compaction,tools, labour etc. all complete.

    23.00 Temporary Site facilities to Client23.01 site office for owner's representatitives

    Supply & install temporary portacabin offices with power, telephone, broadband internet,computers, laptop,A3 colour laser printer, xerox machine, fax machine, A/C and well ventilated housing for 2 persons with Toilets

    No's 4.00

    m2 200.00 -

    m2 200.00 -

    m2 1,000.00 -