RES. ESTRPLANILLA DE METRADOS (ESTRUCTURAS) RESUMENProy.:
"MEJORAMIENTO DEL SERVICIO EDUCATIVO EN LA I. E. CATOLICO BILINGE
ISOLINA CLOTET DE FERNADINI - SANTA BARBARA"Respon.: SUB GERENCIA
DE ESTUDIOS - EQUIPO TECNICOProvincia: HUANCAVELICAFecha:JULIO -
2009Distrito: HUANCAVELICAFormula: 01 AREA PEDAGOGICA NIVEL
PRIMARIALocalidad: SANTA
BARBARAITEMPARTIDADESCRIPCIONUBICACINCANTLARGOANCHOALTOPARCTOTALUND"01""ESTRUCTURAS"01.01TRABAJOS
PROVICIONALES01.01.01Sealizacin con cinta de
seguridad105.00ML1.00105.00105.0001.02TRABAJOS
PRELIMINARES01.02.01Limpieza de Terreno Manual379.32M2AULASEJE 1 -
3TRAMO A-G1.0025.7012.30316.11ESCALERAEJE 1 - 3'TRAMO
H-I1.004.9012.9063.2101.02.02Trazo, niveles y replanteo
preliminar379.32M2AULASEJE 1 - 3TRAMO
A-G1.0025.7012.30316.11ESCALERAEJE 1 - 3'TRAMO
H-I1.004.9012.9063.2101.02.03Trazo, niveles y replanteo durante el
proceso379.32M2AULASEJE 1 - 3TRAMO
A-G1.0025.7012.30316.11ESCALERAEJE 1 - 3'TRAMO
H-I1.004.9012.9063.2101.02.04Transporte de Equipos y
Herramientas1.00GLB1.001.0001.02.05Corte de
terreno94.82M3ESCALERAEJE 1 - 3'TRAMO
H-I1.004.9012.901.5094.8201.03MOVIMIENTO DE
TIERRAS01.03.01Excavacion de zanjas para cimientos34.63M3AULASCORTE
1 - 1EJE ATRAMO 1- 31.005.300.500.902.39CORTE 1 - 1EJE C y ETRAMO
1-32.005.130.500.904.62CORTE 6 - 6EJE GTRAMO
1-31.005.300.500.902.39CORTE 2 - 2EJE 3TRAMO
A-B1.002.300.400.900.83TRAMO B-C1.002.250.400.900.81TRAMO
C-D1.002.250.400.900.81TRAMO D-E1.002.250.400.900.81TRAMO
E-F1.002.250.400.900.81TRAMO G-H1.001.850.400.900.67CORTE 2 - 2EJE
1-1TRAMO A-B1.001.880.400.900.68TRAMO B-C1.001.800.400.900.65TRAMO
C-D1.001.800.400.900.65TRAMO D-E1.001.800.400.900.65TRAMO
E-F1.001.800.400.900.65TRAMO G-H1.001.630.400.900.59CAJA DE
ESCALERASCORTE 5 - 5EJE H-ITRAMO
1-3'2.002.150.502.405.162.002.700.502.406.48CORTE 5-5EJE 3'-3'TRAMO
H-I1.001.350.500.900.61CORTE 1 - 1EJE ENTRE 2-3TRAMO
H-I1.003.350.500.901.51CORTE 5-5EJE ENTRE 1-2TRAMO
H-I1.003.000.500.901.35CORTE 2-2EJE ENTRE 1-2TRAMO
H-I1.000.930.400.900.33CIMIENTO DE CAJA ESCALERAEJE ENTRE 1-1TRAMO
H-I1.001.680.400.900.60CIMIENTO DE CAJA ESCALERAEJE ENTRE 1-2TRAMO
H-I1.001.930.400.800.6201.03.02Excavacion para zapatas de 1.0m a
1.80m de profundidad135.25M3ZAPATA ( Z - 1 )EJE 3EJE
A1.001.801.501.804.86ZAPATA ( Z - 2 )EJE 1EJE
A1.002.201.901.807.52ZAPATA ( Z - 3 )EJE 3-3EJE
B-C-D-E-F5.001.951.651.8028.96ZAPATA ( Z - 4 )EJE 1 -1EJE
B-C-D-E-F5.002.402.101.8045.36ZAPATA ( Z - 5 )EJE 1 y 3EJE
G2.002.701.351.8013.12FALSA ZAPATAZAPATA ( Z - 5 )EJE 1 y 3EJE
G2.002.701.351.6011.66ESCALERAZAPATA ( Z - 6 )EJE 1-3'EJE
H-I4.001.601.501.8017.28ZAPATA ( Z - 7 )EJE 2- 2EJE
H-I2.001.501.201.806.4801.03.03Excavacion para cunetas hasta
0.45m18.13M3CUNETAS FRONTAL Y POSTERIOREjes 1-1 Y 3-3Entre Ejes
A-G2.0030.000.500.5015.00CUNETA LATERALESEjes A-AEntre Ejes 1-1 AL
3-31.0012.500.500.503.1301.03.04Relleno con material
propio77.27M3CIMIENTOSCORTE 1 - 1EJE ATRAMO 1-
31.005.300.250.100.13CORTE 1 - 1EJE C y ETRAMO
1-32.005.130.250.100.26CORTE 6 - 6EJE GTRAMO
1-31.005.300.250.100.13CORTE 2 - 2EJE 3TRAMO
A-B1.002.300.250.100.06TRAMO B-C1.002.250.250.100.06TRAMO
C-D1.002.250.250.100.06TRAMO D-E1.002.250.250.100.06TRAMO
E-F1.002.250.250.100.06TRAMO G-H1.001.850.250.100.05CORTE 2 - 2EJE
1-1TRAMO A-B1.001.880.250.100.05TRAMO B-C1.001.800.250.100.05TRAMO
C-D1.001.800.250.100.05TRAMO D-E1.001.800.250.100.05TRAMO
E-F1.001.800.250.100.05TRAMO G-H1.001.630.250.100.04CAJA DE
ESCALERASCORTE 5 - 5EJE H-ITRAMO
1-3'2.002.150.250.100.112.003.250.250.100.16CORTE 5-5EJE 3'-3'TRAMO
H-I1.001.350.250.100.03CORTE 1 - 1EJE ENTRE 2-3TRAMO
H-I1.003.350.250.100.08CORTE 5-5EJE ENTRE 1-2TRAMO
H-I1.003.000.250.100.08CORTE 2-2EJE ENTRE 1-2TRAMO
H-I1.000.930.250.100.02CIMIENTO DE CAJA ESCALERAEJE ENTRE 1-1TRAMO
H-I1.001.680.400.100.07CIMIENTO DE CAJA ESCALERAEJE ENTRE 1-2TRAMO
H-I1.001.930.400.100.08ZAPATASZAPATA ( Z - 1 )EJE 3EJE
A1.001.801.501.102.97ZAPATA ( Z - 2 )EJE 1EJE
A1.002.201.901.104.60ZAPATA ( Z - 3 )EJE 3-3EJE
B-C-D-E-F5.001.951.651.1017.70ZAPATA ( Z - 4 )EJE 1 -1EJE
B-C-D-E-F5.002.402.101.1027.72ZAPATA ( Z - 5 )EJE 1 y 3EJE
G2.002.701.351.108.02ESCALERAZAPATA ( Z - 6 )EJE 1-3'EJE
H-I4.001.601.501.1010.56ZAPATA ( Z - 7 )EJE 2- 2EJE
H-I2.001.501.201.103.9601.03.05Nivelacion Interior, apisonado con
equipo339.10M2AULA 01EJE 1-3TRAMO A-B-C1.007.607.5557.38AULA 02EJE
1-3TRAMO C-D-E1.007.607.5557.38AULA 03EJE 1-3TRAMO
E-F-G1.007.607.5557.38PASADIZOEJE 1-1TRAMO
A-G1.0025.202.9073.08VEREDA DE CIRCULACIONEJE A-ATRAMO
1-31.007.801.5011.70VEREDA DE CIRCULACIONEJE 3-3TRAMO
A-G1.0025.201.5037.80CAJA DE ESCALERAEJE 1-2TRAMO
H-I1.003.001.955.85SS.HHEJE ENTRE 2-3'TRAMO
H-I1.003.853.0011.55HALLEJE ENTRE 2-3TRAMO H-I1.003.852.409.24CTO.
DE LIMPIEZAEJE ENTRE 1-2TRAMO H-I1.002.801.784.98VEREDA DE
CIRCULACIONEJE 1TRAMO H-I1.004.402.9012.7601.03.06Acarreo manual de
material excedente hasta una distancia promedio de 30.0
m1.00134.31134.31134.31M301.03.07Eliminacion de material excedente
con equipo pesado1.00134.31134.31134.31M301.04OBRAS DE CONCRETO
SIMPLE01.04.01Solado de concreto C:H 1:12, e=4'', para
zapatas61.37M2ZAPATA ( Z - 1 )EJE 3EJE A1.001.801.502.70ZAPATA ( Z
- 2 )EJE 1EJE A1.002.201.904.18ZAPATA ( Z - 3 )EJE 3-3EJE
B-C-D-E-F5.001.951.6516.09ZAPATA ( Z - 4 )EJE 1 -1EJE
B-C-D-E-F5.002.402.1025.20ESCALERAZAPATA ( Z - 6 )EJE 1-3'EJE
H-I4.001.601.509.60ZAPATA ( Z - 7 )EJE 2- 2EJE
H-I2.001.501.203.6001.04.02Concreto para cimientos corridos C:H
1:10 + 30% P.G.31.07M3CORTE 1 - 1EJE A-ATRAMO 1-
31.007.350.500.802.94CORTE 6 - 6EJE G-GTRAMO 1-
31.007.350.500.802.94CORTE 2 - 2EJE 3-3TRAMO A-B Y
F-G2.003.580.400.802.29CORTE 2 - 2EJE 3-3TRAMO
B-C-D-F4.003.600.400.804.61CORTE 2 - 2EJE 1-1TRAMO A-B Y
F-G2.003.580.400.802.29CORTE 2 - 2EJE 3-3TRAMO
B-C-D-F4.003.600.400.804.61CAJA DE ESCALERASCORTE 5-5EJE H-ITRAMO
1-3'2.007.700.500.806.16CORTE 5-5EJE 3'-3'TRAMO
H-I1.003.850.500.801.54CORTE 1 - 1EJE ENTRE 2-3TRAMO
H-I1.003.350.500.801.34CORTE 5-5EJE ENTRE 1-2TRAMO
H-I1.003.000.500.801.20CIMIENTO DE CAJA ESCALERAEJE ENTRE 1-1TRAMO
H-I1.001.680.400.800.54CIMIENTO DE CAJA ESCALERAEJE ENTRE 1-2TRAMO
H-I1.001.930.400.800.6201.04.03Concreto en sobrecimientos C:H 1:8 +
25% P.M4.82M3CORTE 1 - 1EJE A-ATRAMO 1- 31.006.750.250.450.76CORTE
2 - 2EJE 3-3TRAMO A-B Y F-G2.003.580.150.450.48CORTE 2 - 2EJE
3-3TRAMO B-C-D-F4.003.600.150.450.97CORTE 6 - 6EJE G-GTRAMO
1-31.006.750.250.450.76CORTE 2 - 2EJE 1-1TRAMO A-B Y
F-G2.003.580.150.450.48CORTE 2 - 2EJE 3-3TRAMO
B-C-D-F4.003.600.150.450.97CAJA DE ESCALERASCORTE 1 - 1EJE ENTRE
2-3TRAMO H-I1.002.950.250.450.33CORTE 2-2EJE ENTRE 1-2TRAMO
H-I1.000.930.150.450.0601.04.04Encofrado y desencofrado en
sobrecimientos h=0.45m54.45M2CORTE 1 - 1EJE A-ATRAMO 1-
32.006.750.456.08CORTE 2 - 2EJE 3-3TRAMO A-B Y
F-G4.003.580.456.44CORTE 2 - 2EJE 3-3TRAMO
B-C-D-F8.003.600.4512.96CORTE 6 - 6EJE G-GTRAMO
1-32.006.750.456.08CORTE 2 - 2EJE 1-1TRAMO A-B Y
F-G4.003.580.456.44CORTE 2 - 2EJE 3-3TRAMO
B-C-D-F8.003.600.4512.96CAJA DE ESCALERASCORTE 1 - 1EJE ENTRE
2-3TRAMO H-I2.002.950.452.66CORTE 2-2EJE ENTRE 1-2TRAMO
H-I2.000.930.450.8401.04.05Falso piso de concreto C:H- de
e=4''266.06M2AULAS 01, 02, 03Ejes A-A, C-CEntre Ejes 1-1 AL
3-33.007.557.40167.61PASADIZO3.008.002.5060.00SS.HH.Ejes H-H,
I-IEntre Ejes 1-1 AL
3'-3'1.003.853.0011.55HALL1.003.852.9011.17DEPOSITO1.002.701.804.86PASADIZO1.004.352.5010.8801.04.06VEREDAS01.04.06.01Vereda
de concreto Pulido de 4" sin colorear y bruado13.63M3VEREDA
POSTERIOREjes 3-3Entre Ejes A-G1.0023.702.500.2011.85VEREDAS
LATERALESEjes A-AEntre Ejes 1-1 AL
3-31.008.901.000.201.7801.04.06.02Encofrado y desencofrado de
veredas32.60M2VEREDA POSTERIOREjes 3-3Entre Ejes
A-G1.0023.7023.70VEREDAS LATERALESEjes A-AEntre Ejes 1-1 AL
3-31.008.908.9001.04.07CUNETAS DE CONCRETO01.04.07.01Concreto en
cunetas F'c=140 Kg/cm25.80M3CUNETAS FRONTAL Y POSTERIOREjes 1-1 Y
3-3Entre Ejes A-G2.0030.00AREA CAD0.084.80CUNETA LATERALESEjes
A-AEntre Ejes 1-1 AL 3-31.0012.50AREA
CAD0.081.0001.04.07.02Encofrado y desencofrado34.10M2CUNETAS
FRONTAL Y POSTERIOREjes 1-1 Y 3-3Entre Ejes
A-G4.009.750.3011.704.009.750.207.80CUNETA LATERALESEjes A-AEntre
Ejes 1-1 AL 3-34.007.300.308.764.007.300.205.8401.04.08PODIUM DE
CONCRETO01.04.08.01Concreto en Podium F'c=140 Kg/cm29.19M3AULAS
01-066.00AREA7.660.209.1901.04.08.02Encofrado y desencofrado en
podium44.70M2AULAS 01-066.00AREA7.4544.7001.05OBRAS DE CONCRETO
ARMADO01.05.01ZAPATAS52.86M301.05.01.01Concreto en zapatas F'c=210
Kg/cm2ZAPATA ( Z - 1 )EJE 3EJE A1.001.801.500.601.62ZAPATA ( Z - 2
)EJE 1EJE A1.002.201.900.602.51ZAPATA ( Z - 3 )EJE 3-3EJE
B-C-D-E-F5.001.951.650.609.65ZAPATA ( Z - 4 )EJE 1 -1EJE
B-C-D-E-F5.002.402.100.6015.12ZAPATA ( Z - 5 )EJE 1 y 3EJE
G2.002.701.350.604.37FALSA ZAPATAZAPATA ( Z - 5 )EJE 1 y 3EJE
G2.002.701.351.6011.66ESCALERAZAPATA ( Z - 6 )EJE 1-3'EJE
H-I4.001.601.500.605.76ZAPATA ( Z - 7 )EJE 2- 2EJE
H-I2.001.501.200.602.1601.05.01.02AceroFY=4,200KG/CM2, Grado 60VER
CUADRO DE METRADOS0.00KG01.05.02SOBRECIMIENTO
REFORZADO01.05.02.01Concreto en sobrecimiento reforzado F'c=175
Kg/cm211.85M3CAJA DE ESCALERASCORTE 5-5EJE H-ITRAMO
1-3'2.007.700.251.957.51CORTE 5-5EJE 3'-3'TRAMO
H-I1.003.850.251.951.88CORTE 5-5EJE ENTRE 1-2TRAMO
H-I1.003.000.251.951.46CIMIENTO DE CAJA ESCALERAEJE ENTRE 1-1TRAMO
H-I1.001.680.401.501.0101.05.02.02Encofrado y desencofrado de
sobrecimientos reforzados91.80M2CAJA DE ESCALERASCORTE 5-5EJE
H-ITRAMO 1-3'4.007.701.9560.06CORTE 5-5EJE 3'-3'TRAMO
H-I2.003.851.9515.02CORTE 5-5EJE ENTRE 1-2TRAMO
H-I2.003.001.9511.70CIMIENTO DE CAJA ESCALERAEJE ENTRE 1-1TRAMO
H-I2.001.681.505.0301.05.02.03AceroFY=4,200KG/CM2, Grado 60VER
CUADRO DE METRADOS0.00KG01.05.03COLUMNAS01.05.03.01Concreto en
columnas F'c=210 Kg/cm226.75M31 PISOCOLUMNA ( C - 1 )EJE A Y GTRAMO
32.000.600.304.001.44EJE A Y GTRAMO 12.000.600.304.001.44COLUMNA (
C - 2 )EJE A Y GTRAMO 35.000.600.304.003.60EJE A Y GTRAMO
15.000.600.304.003.60ESCALERACOLUMNA ( C - 3 )EJE H-ITRAMO
1-3'2.000.500.255.601.402.000.500.255.601.40COLUMNA ( C - 4 )EJE
H-IEJE 2-22.000.400.255.601.122 PISOCOLUMNA ( C - 1 )EJE A Y GTRAMO
32.000.600.302.951.06EJE A Y GTRAMO
12.000.600.302.951.062.000.600.301.640.59COLUMNA ( C - 2 )EJE A Y
GTRAMO 35.000.600.303.202.88EJE A Y GEJE
15.000.600.303.202.885.000.600.301.641.48ESCALERACOLUMNA ( C - 3
)EJE H-ITRAMO
1-3'2.000.500.253.000.752.000.500.253.000.751.000.500.253.000.38COLUMNA
( C - 4 )EJE H-IEJE 2-22.000.400.254.600.9201.05.03.02Encofrado y
desencofrado de columnas223.38M21 PISOCOLUMNA ( C - 1 )EJE A Y
GTRAMO 32.001.404.0011.20EJE A Y GTRAMO
11.001.404.005.601.001.554.006.20COLUMNA ( C - 2 )EJE A Y GTRAMO
33.001.504.0018.002.001.304.0010.40EJE A Y GTRAMO
13.001.504.0018.002.001.404.0011.20ESCALERACOLUMNA ( C - 3 )EJE
H-ITRAMO 1-3'2.001.255.6014.002.001.305.6014.56COLUMNA ( C - 4 )EJE
H-IEJE 2-22.000.805.608.962 PISOCOLUMNA ( C - 1 )EJE A Y GTRAMO
32.001.403.008.40EJE A Y GTRAMO
11.001.404.406.161.001.554.406.82COLUMNA ( C - 2 )EJE A Y GTRAMO
33.001.503.0013.502.001.303.007.80EJE A Y GTRAMO
13.001.504.4019.802.001.404.4012.32ESCALERACOLUMNA ( C - 3 )EJE
H-ITRAMO 12.001.253.007.50TRAMO 3'2.001.306.0015.60COLUMNA ( C - 4
)EJE H-IEJE 2-22.000.804.607.3601.05.03.03AceroFY=4,200KG/CM2,
Grado 60VER CUADRO DE METRADOS0.00KG01.05.04COLUMNETAS DE
AMARRE01.05.04.01Concreto en columnetas de amarre F'c=
175Kg/cm26.70M31 PISOCOLUMNA ( C - A1 )EJE 1-1TRAMO
A-G12.000.150.153.000.81COLUMNA ( C - A1 )EJE 3-3TRAMO
A-G12.000.150.153.000.81COLUMNA ( C - A1 )EJE A-C-E-GTRAMO
1-38.000.250.153.000.902 PISOCOLUMNA ( C - A1 )EJE 1-1TRAMO
A-G12.000.150.153.000.81COLUMNA ( C - A1 )EJE 3-3TRAMO
A-G12.000.150.154.651.26COLUMNA ( C - A1 )EJE A-C-E-GTRAMO
1-38.000.250.154.651.40COLUMNETAS SOPORTE PARA BARANDASCOLUMNA ( C
- A1 )EJE 1-1TRAMO A-G8.000.300.251.200.7201.05.04.02Encofrado y
desencofrado de columnetas de Amarre106.53M21 PISOCOLUMNA ( C - A1
)EJE 1-1TRAMO A-G12.000.453.0016.20COLUMNA ( C - A1 )EJE 3-3TRAMO
A-G12.000.453.0016.20COLUMNA ( C - A1 )EJE A-C-E-GTRAMO
1-38.000.453.0010.802 PISOCOLUMNA ( C - A1 )EJE 1-1TRAMO
A-G12.000.453.0016.20COLUMNA ( C - A1 )EJE 3-3TRAMO
A-G12.000.454.6525.11COLUMNA ( C - A1 )EJE A-C-E-GTRAMO
1-38.000.454.6516.74COLUMNETAS SOPORTE PARA BARANDASCOLUMNA ( C -
A1 )EJE 1-1TRAMO A-G8.000.551.205.2801.05.04.03AceroFY=4,200KG/CM2,
Grado 60VER CUADRO DE
METRADOS0.00KG01.05.05VIGAS01.05.05.01Concreto en vigas F'c=210
Kg/cm285.38M31 PISOV P 101 (.30 X .60)EJE A - GTRAMO
1-37.0010.300.300.6012.98V S 101 (.25 X .40)EJE 1 -3TRAMO
A-G2.0023.650.250.404.73V.G. - 101 (.15 X .60)VOLADOTRAMO
A-G1.0023.650.150.602.13Caja de EscaleraVP - 102 (.25 X .50)ENTRE
EJE H-ITRAMO 1-32.0011.250.250.502.81VS - 102 (.25 X .40)ENTRE EJE
1-1TRAMO H-I1.004.350.250.400.44VS - 103 (.25 X .40)ENTRE EJE
3-3TRAMO H-I1.004.350.250.400.44V.G. - 102 (.15 X .60)VOLADOTRAMO
H-I1.004.350.150.600.39EN LOSA DESCANSO Y SS.HH PRIMER PISOVP' -
101 (.25 X .30)ENTRE EJE H-ITRAMO 2-32.005.250.250.300.79VS' - 101
(.25 X .30)ENTRE EJE 2-2TRAMO H-I1.004.350.250.300.33ENTRE EJE
3-3TRAMO H-I1.004.350.250.300.332 PISOV -P 201 (.30 X .45)EJE
A-C-E-GTRAMO 1-34.0010.300.300.455.56V -S 201 (.25 X .40)EJE 1
-3TRAMO A-G2.0024.65AREA0.115.32V.M. (.30 X H=VAR.)VOLADOEJE
B-D-F3.003.00AREA2.2620.34Caja de EscaleraVP - 203 (.25 X .40)ENTRE
EJE H-ITRAMO 1-32.008.500.250.401.70VS - 203 (.25 X .40)ENTRE EJE
1-1TRAMO H-I2.004.350.250.400.87V.B. - 202 (.15 X .45)VOLADOTRAMO
H-I1.004.35AREA0.070.30VM' - (.25 X H= VAR.)EJE
H-IVOLADO1.002.40AREA2.405.76EN LOSA DEPOSITO SEGUNDO PISOVP' - 201
(.25 X .30)ENTRE EJE H-ITRAMO 2-32.005.250.250.300.79VS' - 201 (.25
X .30)ENTRE EJE 2-2TRAMO H-I1.004.350.250.300.33ENTRE EJE 3-3TRAMO
H-I1.004.350.250.300.332 PISO LOSA EN AULASV -P 202 (.30 X .60)EJE
A - GTRAMO 1-37.008.600.300.6010.84V -S 202 (.25 X .30)EJE 1
-3TRAMO A-G2.0024.65AREA0.083.94Caja de EscaleraVP - 204 (.25 X
.50)ENTRE EJE H-ITRAMO 1-32.0011.600.250.502.90VS - 204 (.25 X
.30)EJE 3'TRAMO H-I1.004.35AREA0.080.35VS - 205 (.25 X .30)EJE
2'TRAMO H-I1.004.35AREA0.080.35VS - 206 (.25 X .30)EJE 1'TRAMO
H-I1.004.35AREA0.080.3501.05.05.02Encofrado y desencofrado de
vigas449.26M21 PISOV -P 101 (.30 X .60)friso exteriorEJE A Y GTRAMO
1-32.0010.300.6012.36friso interiorEJE A-GTRAMO
1-312.0010.300.4049.44fondoEJE B-D-FTRAMO
1-33.006.700.306.03fondoVOLADOEJE A-G7.002.400.305.04V - S 101 (.25
X .40)friso exteriorEJE 1 -1TRAMO A-G12.003.650.4017.52friso
interiorEJE 1 -1TRAMO A-G12.003.650.208.76fondoEJE 1 -1TRAMO
A-G12.003.650.2510.95V.G. - 103 (.15 X .60)friso
exteriorVOLADOTRAMO A-G1.0023.650.6014.19friso interiorVOLADOTRAMO
A-G6.003.650.408.76fondoVOLADOTRAMO
C-D-E-F-G-H-I6.003.650.153.29Caja de EscaleraVP - 102 (.25 X
.50)friso exteriorENTRE EJE H-ITRAMO 1-3'2.0011.250.5011.25friso
interiorENTRE EJE H-ITRAMO 1-3'2.0011.250.5011.25VS -103 (.25 X
.40)friso exteriorENTRE EJE 1-3'TRAMO H-I1.004.350.401.74friso
exteriorENTRE EJE 1-3'TRAMO H-I1.004.350.200.87friso interiorENTRE
EJE 1-1TRAMO H-I2.003.850.403.08FondoENTRE EJE 1-1TRAMO
H-I1.003.850.250.96V.G. - 102 (.15 X .60)friso exteriorVOLADOTRAMO
A-G1.004.350.602.61friso interiorVOLADOTRAMO
A-G6.004.350.4010.44fondoVOLADOTRAMO C-D-E-F-G-H-I6.004.350.153.922
PISOV -P 201 (.30 X .45)friso exteriorEJE A Y GTRAMO
1-32.006.700.608.04friso interiorEJE A-C-E-GTRAMO
1-36.006.700.6024.12V -M (.30 X .H=VARIABLE)friso exteriorVOLADOEJE
A-G2.00AREA2.264.52friso interiorVOLADOEJE
A-G12.00AREA1.7621.12fondoVOLADOEJE A-G6.002.400.304.32V - S 201
(.25 X .40)friso exteriorEJE 1 -1TRAMO A-G12.003.650.4017.52friso
interiorEJE 1 -1TRAMO A-G12.003.650.208.76fondoEJE 1 -1TRAMO
A-G12.003.650.2510.95Caja de EscaleraVP - 203 (.25 X .40)friso
exteriorENTRE EJE H-ITRAMO 1-3'2.0011.250.409.00friso interiorENTRE
EJE H-ITRAMO 1-3'2.0011.250.409.00VS -203 (.25 X .40)friso
exteriorENTRE EJE 1-3'TRAMO H-I1.004.350.401.74friso exteriorENTRE
EJE 1-3'TRAMO H-I1.004.350.401.74friso interiorENTRE EJE 1-1TRAMO
H-I2.003.850.403.08FondoENTRE EJE 1-1TRAMO H-I1.003.850.250.96V.B.
- 202 (.15 X .45)friso exteriorVOLADOTRAMO A-G1.004.350.602.61friso
interiorVOLADOTRAMO A-G6.004.350.4010.44fondoVOLADOTRAMO
C-D-E-F-G-H-I6.004.350.153.922 PISO VIGAS LOSA AULASV -P 202 (.30 X
.60)friso exteriorEJE A Y GTRAMO 1-32.008.600.6010.32friso
interiorEJE A-GTRAMO 1-312.008.600.4344.38fondoEJE B-D-FTRAMO
1-33.006.700.306.03fondoVOLADOEJE A-G7.002.400.305.04V - S 202 (.25
X .30)friso exteriorEJE 1 -1TRAMO A-G12.003.650.3013.14friso
interiorEJE 1 -1TRAMO A-G12.003.650.135.69fondoEJE 1 -1TRAMO
A-G12.003.650.2510.95Caja de EscaleraVP - 204 (.25 X .50)friso
exteriorENTRE EJE H-ITRAMO 1-3'2.0011.250.5011.25friso
interiorENTRE EJE H-ITRAMO 1-3'2.0011.250.5011.25VS -204-205-206
(.25 X .30)friso exteriorENTRE EJE 1-3'TRAMO
H-I3.004.350.303.92friso interiorENTRE EJE 1-1TRAMO
H-I6.003.850.133.0001.05.05.03AceroFY=4,200KG/CM2, Grado 60VER
CUADRO DE METRADOS0.00KG01.05.06VIGUETAS DE
AMARRE01.05.06.01Concreto en viguetas de amarre F'c= 175
Kg/cm22.21M31 PISOVIGUET. S/MUROEJE 1 - 1TRAMO A-B, C-D y
E-F3.003.600.150.150.24EJE 1 - 1TRAMO B-C, D-E Y
F-G3.002.500.150.150.17VIGUET. S/MUROEJE 3 - 3TRAMO A-B, C-D y
E-F3.003.600.150.150.24EJE 3 - 3TRAMO B-C, D-E Y
F-G3.003.600.150.150.242 PISOVIGUET. S/MUROEJE 1 - 1TRAMO A-B, C-D
y E-F6.003.600.150.150.49EJE 1 - 1TRAMO B-C, D-E Y
F-G6.002.500.150.150.34VIGUET. S/MUROEJE 3 - 3TRAMO A-B, C-D y
E-F3.003.600.150.150.24EJE 3 - 3TRAMO B-C, D-E Y
F-G3.003.600.150.150.2401.05.06.02Encofrado y desencofrado de
viguetas de amarre29.43M21 PISOVIGUET. S/MUROEJE 1 - 1TRAMO A-B,
C-D y E-F6.003.600.153.24EJE 1 - 1TRAMO B-C, D-E Y
F-G6.002.500.152.25VIGUET. S/MUROEJE 3 - 3TRAMO A-B, C-D y
E-F6.003.600.153.24EJE 3 - 3TRAMO B-C, D-E Y F-G6.003.600.153.242
PISOVIGUET. S/MUROEJE 1 - 1TRAMO A-B, C-D y E-F12.003.600.156.48EJE
1 - 1TRAMO B-C, D-E Y F-G12.002.500.154.50VIGUET. S/MUROEJE 3 -
3TRAMO A-B, C-D y E-F6.003.600.153.24EJE 3 - 3TRAMO B-C, D-E Y
F-G6.003.600.153.2401.05.06.03AceroFY=4,200KG/CM2, Grado 60VER
CUADRO DE METRADOS130.07KG01.05.07VIGA CANAL01.05.07.01Concreto en
viga canal4.14M3Viga CanalEJE 1 Y 3TRAMO
A-G2.0023.70Area0.083.79ESCALERAEJE 1TRAMO
H-I1.004.35Area0.080.3501.05.07.02Encofrado y
desencofrado62.10M2Viga CanalEJE 1 Y 3TRAMO
A-G2.0023.701.2056.88ESCALERAEJE 1TRAMO
H-I1.004.351.205.2201.05.07.03AceroFY=4,200KG/CM2, Grado 60VER
CUADRO DE METRADOS0.00KG01.05.08LOSAS ALIGERADAS01.05.08.01Concreto
en losas Aligeradas F'c = 210Kg/cm250.16M31 PISOAula 01, 02,
03Concreto en losa AligeradaTRAMO A-GTRAMO
1-31.0023.7010.300.0512.21CONCRETO EN VIGUETASTRAMO A-BTRAMO
1-218.003.600.100.150.97TRAMO B-CTRAMO
1-218.003.600.100.150.97TRAMO C-DTRAMO
1-218.003.600.100.150.97TRAMO D-ETRAMO
1-218.003.600.100.150.97TRAMO E-FTRAMO
1-218.003.600.100.150.97TRAMO F-GTRAMO
1-218.003.600.100.150.97PASADIZOTRAMO A-BTRAMO
1-25.003.600.100.150.27TRAMO B-CTRAMO 1-25.003.600.100.150.27TRAMO
C-DTRAMO 1-25.003.600.100.150.27TRAMO D-ETRAMO
1-25.003.600.100.150.27TRAMO E-FTRAMO 1-25.003.600.100.150.27TRAMO
F-GTRAMO 1-25.003.600.100.150.27Concreto en losa
AligeradaPASADIZOESCALERA1.004.352.900.050.63CONCRETO EN
VIGUETASTRAMO H-IVoladizo5.003.850.100.150.292 PISOAulaS
04-05-06Concreto en losa AligeradaTRAMO A-GTRAMO
1-31.0024.708.600.0510.62CONCRETO EN VIGUETASTRAMO A-BTRAMO
1-318.003.600.100.150.97TRAMO B-CTRAMO
1-318.003.600.100.150.97TRAMO C-DTRAMO
1-318.003.600.100.150.97TRAMO D-ETRAMO
1-318.003.600.100.150.97TRAMO E-FTRAMO
1-318.003.600.100.150.97TRAMO F-GTRAMO
1-318.003.600.100.150.97VOLADOTRAMO
1-318.001.000.100.150.27PASADIZOConcreto en losa AligeradaTRAMO
A-GTRAMO 1-31.0024.702.500.053.09CONCRETO EN VIGUETASTRAMO A-BTRAMO
1-36.003.600.100.150.32TRAMO B-CTRAMO 1-36.003.600.100.150.32TRAMO
C-DTRAMO 1-36.003.600.100.150.32TRAMO D-ETRAMO
1-36.003.600.100.150.32TRAMO E-FTRAMO 1-36.003.600.100.150.32TRAMO
F-GTRAMO 1-36.003.600.100.150.32ESCALERASConcreto en losa
AligeradaTRAMO H-ITRAMO 2-31.005.003.850.050.96CONCRETO EN
VIGUETASTRAMO H-ITRAMO 2-312.003.850.100.150.69ESCALERASConcreto en
losa AligeradaTRAMO H-IVOLADO1.003.852.900.050.56CONCRETO EN
VIGUETASTRAMO H-IVOLADO5.003.850.100.150.29ESCALERASConcreto en
losa AligeradaTRAMO H-ITRAMO 2-31.005.253.850.051.01CONCRETO EN
VIGUETASTRAMO H-ITRAMO 2-313.003.850.100.150.75ESCALERASConcreto en
losa AligeradaTRAMO H-ITRAMO 1-3'1.0011.003.850.052.12CONCRETO EN
VIGUETASTRAMO H-ITRAMO
1-3'25.003.850.100.151.4401.05.08.02Encofrado y desencofrado de
losas aligeradas557.19M21 PISOAula 01-02-03FONDO DE LOSA
SUPERIORTRAMO A-BTRAMO 1-31.007.403.6026.64FONDO DE LOSA
SUPERIORTRAMO B-CTRAMO 1-31.007.403.6026.64FONDO DE LOSA
SUPERIORTRAMO C-DTRAMO 1-31.007.403.6026.64FONDO DE LOSA
SUPERIORTRAMO D-ETRAMO 1-31.007.403.6026.64FONDO DE LOSA
SUPERIORTRAMO E-FTRAMO 1-31.007.403.6026.64FONDO DE LOSA
SUPERIORTRAMO F-GTRAMO 1-31.007.403.6026.64Pasadizo en AulasFONDO
DE LOSA SUPERIORTRAMO A-BTRAMO 1-31.003.602.408.64FONDO DE LOSA
SUPERIORTRAMO B-CTRAMO 1-31.003.602.408.64FONDO DE LOSA
SUPERIORTRAMO C-DTRAMO 1-31.003.602.408.64FONDO DE LOSA
SUPERIORTRAMO D-ETRAMO 1-31.003.602.408.64FONDO DE LOSA
SUPERIORTRAMO E-FTRAMO 1-31.003.602.408.64FONDO DE LOSA
SUPERIORTRAMO F-GTRAMO 1-31.003.602.408.64Pasadizo en EscaleraFONDO
DE LOSA SUPERIORTRAMO H - IPAZADIZO1.003.852.509.632 PISOAula
04-05-06FONDO DE LOSA SUPERIORTRAMO A-BTRAMO
1-31.008.303.6029.88FONDO DE LOSA SUPERIORTRAMO B-CTRAMO
1-31.008.303.6029.88FONDO DE LOSA SUPERIORTRAMO C-DTRAMO
1-31.008.303.6029.88FONDO DE LOSA SUPERIORTRAMO D-ETRAMO
1-31.008.303.6029.88FONDO DE LOSA SUPERIORTRAMO E-FTRAMO
1-31.008.303.6029.88FONDO DE LOSA SUPERIORTRAMO F-GTRAMO
1-31.008.303.6029.88Pasadizo en AulasFONDO DE LOSA SUPERIORTRAMO
A-BVOLADO1.003.602.509.00FONDO DE LOSA SUPERIORTRAMO
B-CVOLADO1.003.602.509.00FONDO DE LOSA SUPERIORTRAMO
C-DVOLADO1.003.602.509.00FONDO DE LOSA SUPERIORTRAMO
D-EVOLADO1.003.602.509.00FONDO DE LOSA SUPERIORTRAMO
E-FVOLADO1.003.602.509.00FONDO DE LOSA SUPERIORTRAMO
F-GVOLADO1.003.602.509.00Pasadizo en EscaleraFONDO DE LOSA
SUPERIORTRAMO H - IPAZADIZO1.003.852.509.63ESCALERASFONDO DE LOSA
SUPERIORTRAMO H-ITRAMO 2-31.005.003.8519.25ESCALERASFONDO DE LOSA
SUPERIORTRAMO H-IVOLADO1.003.852.9011.17ESCALERASFONDO DE LOSA
SUPERIORTRAMO H-ITRAMO 2-31.005.253.8520.21ESCALERASFONDO DE LOSA
SUPERIORTRAMO H-ITRAMO
1-3'1.0011.003.8542.3501.05.08.03AceroFY=4,200KG/CM2, Grado 60VER
CUADRO DE METRADOS0.00KG01.05.08.04Ladrillo hueco de arcilla
15x30x30 cm p/techo Alig.2,345.37UND1 PISOAula 01-02-03Und*m2FONDO
DE LOSA SUPERIORTRAMO A-BTRAMO 1-31.007.403.608.33221.91FONDO DE
LOSA SUPERIORTRAMO B-CTRAMO 1-31.007.403.608.33221.91FONDO DE LOSA
SUPERIORTRAMO C-DTRAMO 1-31.007.403.608.33221.91FONDO DE LOSA
SUPERIORTRAMO D-ETRAMO 1-31.007.403.608.33221.91FONDO DE LOSA
SUPERIORTRAMO E-FTRAMO 1-31.007.403.608.33221.91FONDO DE LOSA
SUPERIORTRAMO F-GTRAMO 1-31.007.403.608.33221.91Pasadizo en
AulasFONDO DE LOSA SUPERIORTRAMO A-BTRAMO
1-31.003.602.408.3371.97FONDO DE LOSA SUPERIORTRAMO B-CTRAMO
1-31.003.602.408.3371.97FONDO DE LOSA SUPERIORTRAMO C-DTRAMO
1-31.003.602.408.3371.97FONDO DE LOSA SUPERIORTRAMO D-ETRAMO
1-31.003.602.408.3371.97FONDO DE LOSA SUPERIORTRAMO E-FTRAMO
1-31.003.602.408.3371.97FONDO DE LOSA SUPERIORTRAMO F-GTRAMO
1-31.003.602.408.3371.97Pasadizo en EscaleraFONDO DE LOSA
SUPERIORTRAMO H - IPAZADIZO1.003.852.508.3380.182 PISOPasadizo en
EscaleraFONDO DE LOSA SUPERIORTRAMO H -
IPAZADIZO1.003.852.508.3380.18ESCALERASFONDO DE LOSA SUPERIORTRAMO
H-ITRAMO 2-31.005.003.858.33160.35ESCALERASFONDO DE LOSA
SUPERIORTRAMO H-IVOLADO1.003.852.908.3393.00ESCALERASFONDO DE LOSA
SUPERIORTRAMO H-ITRAMO 2-31.005.253.858.33168.3701.05.08.05Ladrillo
hueco de arcilla 12x30x30 cm p/techo Alig.2,296.00UND2 PISOAula
04-05-06FONDO DE LOSA SUPERIORTRAMO A-BTRAMO
1-31.008.303.608.33248.90FONDO DE LOSA SUPERIORTRAMO B-CTRAMO
1-31.008.303.608.33248.90FONDO DE LOSA SUPERIORTRAMO C-DTRAMO
1-31.008.303.608.33248.90FONDO DE LOSA SUPERIORTRAMO D-ETRAMO
1-31.008.303.608.33248.90FONDO DE LOSA SUPERIORTRAMO E-FTRAMO
1-31.008.303.608.33248.90FONDO DE LOSA SUPERIORTRAMO F-GTRAMO
1-31.008.303.608.33248.90Pasadizo en AulasFONDO DE LOSA
SUPERIORTRAMO A-BVOLADO1.003.602.508.3374.97FONDO DE LOSA
SUPERIORTRAMO B-CVOLADO1.003.602.508.3374.97FONDO DE LOSA
SUPERIORTRAMO C-DVOLADO1.003.602.508.3374.97FONDO DE LOSA
SUPERIORTRAMO D-EVOLADO1.003.602.508.3374.97FONDO DE LOSA
SUPERIORTRAMO E-FVOLADO1.003.602.508.3374.97FONDO DE LOSA
SUPERIORTRAMO F-GVOLADO1.003.602.508.3374.97Pasadizo en
EscaleraESCALERASFONDO DE LOSA SUPERIORTRAMO H-ITRAMO
1-3'1.0011.003.858.33352.7801.05.09ESCALERAS01.05.09.01Concreto en
Escalera F'c= 210Kg/cm27.93M3Cimiento en caja
escalera1.002.050.402.101.72TRAMO 1Losa en Tramo
11.003.051.930.150.88PELDAOS (AREA CAD
TRIANG)10.000.031.930.58TRAMO 2Losa en Tramo
21.003.601.930.151.04PELDAOS (AREA CAD
TRIANG)10.000.031.930.58TRAMO 3Losa en Tramo
31.003.601.930.151.04PELDAOS (AREA CAD
TRIANG)10.000.031.930.58TRAMO 4Losa en Tramo
41.003.251.930.150.94PELDAOS (AREA CAD
TRIANG)10.000.031.930.5801.05.09.02Encofrado y desencofrado de
escalera48.76M2TRAMO 1Fondo de Losa en Tramo
11.003.051.935.87Laterales2.003.050.332.01CONTRAPASOS10.001.930.183.47TRAMO
2Fondo de Losa en Tramo
21.003.601.936.93Laterales2.003.600.332.38CONTRAPASOS10.001.930.183.47TRAMO
3Fondo de Losa en Tramo
31.003.601.936.93Laterales2.003.600.332.38CONTRAPASOS10.001.930.183.47TRAMO
4Fondo de Losa en Tramo
41.003.251.936.26Laterales2.003.250.332.15CONTRAPASOS10.001.930.183.4701.05.09.03AceroFY=4,200KG/CM2,
Grado 60VER CUADRO DE METRADOS0.00KG
ESTRUCTURASPLANILLA DE METRADOS DE ESTRUCTURAS MODULO 01
"ADMINISTRATIVA Y RECURSOS ACADEMICOS"PROYECTO: "MEJORAMIENTO DE LA
CALIDAD DEL SERVICIO EDUCATIVO EN EL NIVEL SECUNDARIO DE LA
INSTITUCION EDUCATIVA SAN JUAN, DISTRITO DE SAN JUAN, PROVINCIA DE
CASTROVIRREYNA-HUANCAVELICA"Respon.: E&R CONTRATISTAS GENERALES
SRLDepartamento: HUANCAVELICAFecha: Abril 2014Provincia:
CASTROVIRREYNADistrito: SAN JUANFormula: 02 - MODULO 01
"ADMINISTRATIVA Y RECURSOS ACADEMICOS"Lugar: SAN
JUANITEMPARTIDADESCRIPCIONUBICACIN DE ELEMENTOCANTLARGO (m)ANCHO
(m)ALTO (m)PARCIALTOTALUND02MODULO 01 "ADMINISTRATIVA Y RECURSOS
ACADEMICOS"02.01ESTRUCTURAS02.01.01TRABAJOS
PRELIMINARES02.01.01.01LIMPIEZA DE TERRENO MANUAL339.08M2Modulo
AArea construida1 piso1.0034.609.80339.0802.01.01.02TRAZO,
NIVELACION Y REPLANTEO PRELIMINAR339.08M2Modulo AArea construida1
piso1.0034.609.80339.0802.01.01.03TRAZO, NIVELACION Y REPLANTEO
DURANTE EL PROCESO339.08M2Area administrativoArea construida1
piso1.0034.609.80339.0802.01.02MOVIMIENTO DE
TIERRAS02.01.02.01EXCAVACION DE ZANJA PARA CIMIENTOS DE 0.25 HASTA
0.65 M DE PROFUNDIDAD EN TERRENO NORMAL20.41M3Modulo 1Corte N-NEje
A-ATramo 1-21.001.280.400.650.33Tramo 2-31.002.450.400.650.64Tramo
3-41.002.370.400.650.62Tramo 4-51.002.430.400.650.63Tramo
9-101.002.450.400.650.64Tramo 10-111.001.270.400.650.33Corte M-MEje
A-ATramo 3-51.006.000.500.651.95Corte N-NEje C-CTramo
1-21.000.950.400.650.25Tramo 2-31.002.100.400.650.55Tramo
3-41.002.020.400.650.53Tramo 4-51.002.080.400.650.54Tramo
9-101.002.080.400.650.54Tramo 10-111.000.950.400.650.25Corte
N-NEntre ejes A y BTramo 3-41.000.270.400.650.07Corte N-NEntre ejes
B y CTramo 7-81.000.930.400.650.24Cimentacion EscaleraEntre ejes B
y CTramo 7-81.002.000.401.000.80Corte M-MEje 1-1Tramo
A-C1.005.150.500.651.67Eje 3-3Tramo A-C1.002.550.500.650.83Eje
4-4Tramo A-C1.002.180.500.650.71Eje 4-4Tramo
A-C1.002.000.500.650.65Eje 5-5Tramo A-C1.002.630.500.650.85Eje
5-5Tramo A-C1.001.100.500.650.36Corte P-PEje 6-6Tramo
A-C1.004.350.500.651.41Eje 9-9Tramo A-C1.004.350.500.651.41Corte
P-PEje 7-7Tramo A-C1.001.570.450.250.18Eje 7-7Tramo
A-C1.001.330.450.250.15Eje 8-8Tramo A-C1.001.570.450.250.18Eje
8-8Tramo A-C1.001.330.450.250.15Corte M-MEje 11-11Tramo
A-C1.005.150.500.651.67Corte M-MEntre ejes 3 y 4Tramo
A-C1.001.930.500.650.63Corte N-NEntre ejes 7 y 8Tramo
A-C1.002.530.400.650.6602.01.02.02EXCAVACION PARA ZAPATAS INC.
SOLADO DE 2.05 M DE PROF. TERR. NORMAL135.45M3Modulo 1Z-01Eje
A-ATramo 1-112.002.601.252.0513.33Z-02Eje A-ATramo
1-113.001.601.502.0514.76Z-03Eje A-ATramo
1-112.001.751.652.0511.84Z-04Eje A-ATramo
1-112.001.001.902.057.79Z-09Eje A-ATramo
1-112.000.801.502.054.92Z-11Eje B-BTramo
1-112.000.901.752.056.46Z-05Eje C-CTramo
1-112.002.851.452.0516.94Z-06Eje C-CTramo
1-113.001.951.852.0522.19Z-07Eje C-CTramo
1-112.002.102.002.0517.22Z-08Eje C-CTramo
1-112.001.202.402.0511.81Z-10Eje C-CTramo
1-112.001.002.002.058.2002.01.02.03RELLENO Y COMPACTADO CON
MATERIAL PROPIO67.67M3Modulo 1 Relleno en zanjas de
cimentacionCorte N-NEje A-ATramo 1-21.001.950.250.050.02Tramo
2-31.003.530.250.050.04Tramo 3-41.003.530.250.050.04Tramo
4-51.003.500.250.050.04Tramo 9-101.003.450.250.050.04Tramo
10-111.002.250.250.050.03Corte M-MEje B-BTramo
3-51.006.000.250.050.08Corte N-NEje C-CTramo
1-21.001.950.250.050.02Tramo 2-31.002.430.250.050.03Tramo
2-31.001.100.400.050.02Tramo 3-41.002.430.250.050.03Tramo
3-41.001.100.400.050.02Tramo 4-51.003.500.250.050.04Tramo
9-101.003.450.250.050.04Tramo 10-111.002.250.250.050.03Corte
N-NEntre ejes A y BTramo 3-41.000.270.250.050.003Corte N-NEntre
ejes B y CTramo 7-81.000.930.250.050.01Corte M-MEje 1-1Tramo
A-C1.005.900.250.050.07Eje 3-3Tramo A-C1.003.080.250.050.04Eje
4-4Tramo A-C1.002.700.250.050.03Eje 4-4Tramo
A-C1.002.700.250.050.03Eje 5-5Tramo A-C1.003.080.250.050.04Eje
5-5Tramo A-C1.001.730.250.050.02Corte P-PEje 6-6Tramo
A-C1.005.900.250.050.07Eje 9-9Tramo A-C1.005.900.250.050.07Corte
M-MEje 11-11Tramo A-C1.005.900.250.050.07Corte M-MEntre ejes 3 y
4Tramo A-C1.001.930.250.050.02Corte N-NEntre ejes 7 y 8Tramo
A-C1.002.530.250.050.03Modulo 1 Relleno en zanjas de zapatasZ-01Eje
A-ATramo 1-112.00Area 010.961.352.592.00Area 021.391.353.75Z-02Eje
A-ATramo 1-113.00Area 011.011.354.093.00Area 020.761.353.08Z-03Eje
A-ATramo 1-112.00Area 010.491.351.322.00Area 020.491.351.322.00Area
030.951.352.57Z-04Eje A-ATramo 1-111.00Area 010.481.350.651.00Area
020.681.350.92Z-04Eje A-ATramo 1-111.00Area 011.371.351.85Z-09Eje
A-ATramo 1-112.00Area 010.411.351.112.00Area 020.401.351.08Z-11Eje
B-BTramo 1-112.00Area 011.141.353.08Z-05Eje C-CTramo 1-112.00Area
011.891.355.102.00Area 021.241.353.35Z-06Eje C-CTramo 1-113.00Area
011.251.355.063.00Area 021.581.356.40Z-07Eje C-CTramo 1-112.00Area
011.491.354.022.00Area 021.881.355.08Z-08Eje C-CTramo 1-111.00Area
011.111.351.501.00Area 020.831.351.12Z-08Eje C-CTramo 1-111.00Area
012.221.353.00Z-10Eje C-CTramo 1-112.00Area
011.691.354.5602.01.02.04NIVELACION INTERIOR Y APISONADO CON
EQUIPO301.34M2Modulo
1Comedor1.00Area52.0652.06Cocina1.00Area12.4812.48Almacen1.00Area9.829.82SS-HH
011.00Area2.372.37Guardiania1.00Area12.4412.44Deposito
011.00Area12.4112.41Deposito 021.00Area14.6014.60Salon de
Musica1.00Area52.0352.03Pasadizofrontal1.0035.201.9066.88posterior1.0035.201.0035.20Hall
de ingreso1.006.904.5031.0502.01.02.05ACARREO DE MATERIAL EXEDENTE
HASTA UNA DISTANCIA PROMEDIO DE 30
M.110.23M31.25vol88.18110.2302.01.02.06ELIMINACIN DE MATERIAL
EXCEDENTE CON EQUIPO PESADO R=120
M3/DIA110.23M31.00110.23110.2302.01.03OBRAS DE CONCRETO
SIMPLE02.01.03.01SOLADO02.01.03.01.01SOLADO DE CONCRETO C:H 1:12
E=4" PARA ZAPATAS66.07M2Modulo 1Z-01Eje A-ATramo
1-112.002.601.256.50Z-02Eje A-ATramo 1-113.001.601.507.20Z-03Eje
A-ATramo 1-112.001.751.655.78Z-04Eje A-ATramo
1-112.001.001.903.80Z-09Eje A-ATramo 1-112.000.801.502.40Z-11Eje
B-BTramo 1-112.000.901.753.15Z-05Eje C-CTramo
1-112.002.851.458.27Z-06Eje C-CTramo 1-113.001.951.8510.82Z-07Eje
C-CTramo 1-112.002.102.008.40Z-08Eje C-CTramo
1-112.001.202.405.76Z-10Eje C-CTramo
1-112.001.002.004.0002.01.03.02CIMIENTOS
CORRIDOS02.01.03.02.01CONCRETO PARA CIMIENTOS CORRIDOS C:H 1:10 +
30% P.G.23.08M3Modulo 1Corte N-NEje A-ATramo
1-21.001.950.400.600.47Tramo 2-31.003.530.400.600.85Tramo
3-41.003.530.400.600.85Tramo 4-51.003.500.400.600.84Tramo
9-101.003.450.400.600.83Tramo 10-111.002.250.400.600.54Corte M-MEje
B-BTramo 3-51.006.000.500.601.80Corte N-NEje C-CTramo
1-21.001.950.400.600.47Tramo 2-31.002.430.400.600.58Tramo
2-31.001.100.400.600.26Tramo 3-41.002.430.400.600.58Tramo
3-41.001.100.400.600.26Tramo 4-51.003.500.400.600.84Tramo
9-101.003.450.400.600.83Tramo 10-111.002.250.400.600.54Corte
N-NEntre ejes A y BTramo 3-41.000.270.400.600.06Corte N-NEntre ejes
B y CTramo 7-81.000.930.400.600.22Corte M-MEje 1-1Tramo
A-C1.005.900.500.601.77Eje 3-3Tramo A-C1.003.080.500.600.92Eje
4-4Tramo A-C1.002.700.500.600.81Eje 4-4Tramo
A-C1.002.700.500.600.81Eje 5-5Tramo A-C1.003.080.500.600.92Eje
5-5Tramo A-C1.001.730.500.600.52Corte P-PEje 6-6Tramo
A-C1.005.900.500.601.77Eje 9-9Tramo A-C1.005.900.500.601.77Corte
M-MEje 11-11Tramo A-C1.005.900.500.601.77Corte M-MEntre ejes 3 y
4Tramo A-C1.001.930.500.600.58Corte N-NEntre ejes 7 y 8Tramo
A-C1.002.530.400.600.6102.01.03.03SOBRECIMIENTOS02.01.03.03.01CONCRETO
PARA SOBRECIMIENTOS C:H 1:8 + 25% P.M8.57M3Modulo 1Corte N-NEje
A-ATramo 1-21.001.950.150.500.15Tramo 2-31.003.530.150.500.26Tramo
3-41.003.530.150.500.26Tramo 4-51.003.500.150.500.26Tramo
9-101.003.450.150.500.26Tramo 10-111.002.250.150.500.17Corte M-MEje
B-BTramo 3-51.006.000.250.500.75Corte N-NEje C-CTramo
1-21.001.950.150.500.15Tramo 2-31.002.430.150.500.18Tramo
3-41.002.430.150.500.18Tramo 4-51.003.500.150.500.26Tramo
9-101.002.350.150.500.18Tramo 10-111.002.250.150.500.17Corte
N-NEntre ejes A y BTramo 3-41.000.400.150.500.03Corte N-NEntre ejes
B y CTramo 7-81.000.930.150.500.07Corte M-MEje 1-1Tramo
A-C1.005.900.250.500.74Eje 3-3Tramo A-C1.003.080.250.500.39Eje
4-4Tramo A-C1.005.900.250.500.74Eje 5-5Tramo
A-C1.003.080.250.500.39Eje 5-5Tramo A-C1.001.730.250.500.22Corte
P-PEje 6-6Tramo A-C1.005.900.250.500.74Eje 9-9Tramo
A-C1.005.900.250.500.74Corte M-MEje 11-11Tramo
A-C1.005.900.250.500.74Corte M-MEntre ejes 3 y 4Tramo
A-C1.001.930.250.500.24Corte N-NEntre ejes 7 y 8Tramo
A-C1.002.530.250.500.3202.01.03.03.02ENCOFRADO Y DESENCOFRADO DE
SOBRECIMIENTOS166.80M2Modulo 1Corte N-NEje A-ATramo
1-22.001.951.003.90Tramo 2-32.003.531.007.06Tramo
3-42.003.531.007.06Tramo 4-52.003.501.007.00Tramo
9-102.003.451.006.90Tramo 10-112.002.251.004.50Corte M-MEje
B-BTramo 3-52.006.001.0012.00Corte N-NEje C-CTramo
1-22.001.951.003.90Tramo 2-32.002.431.004.86Tramo
3-42.002.431.004.86Tramo 4-52.003.501.007.00Tramo
9-102.003.451.006.90Tramo 10-112.002.251.004.50Corte N-NEntre ejes
A y BTramo 3-42.000.401.000.80Corte N-NEntre ejes B y CTramo
7-82.000.931.001.86Corte M-MEje 1-1Tramo A-C2.005.901.0011.80Eje
3-3Tramo A-C2.003.081.006.16Eje 4-4Tramo A-C2.005.901.0011.80Eje
5-5Tramo A-C2.003.081.006.16Eje 5-5Tramo A-C2.001.731.003.46Corte
P-PEje 6-6Tramo A-C2.005.901.0011.80Eje 9-9Tramo
A-C2.005.901.0011.80Corte M-MEje 11-11Tramo
A-C2.005.901.0011.80Corte M-MEntre ejes 3 y 4Tramo
A-C2.001.931.003.86Corte N-NEntre ejes 7 y 8Tramo
A-C2.002.531.005.0602.01.03.04FALSO PISO02.01.03.04.01FALSO PISO DE
CONCRETO 1:12 DE E=4''301.34M2Modulo
1Comedor1.00Area52.0652.06Cocina1.00Area12.4812.48Almacen1.00Area9.829.82SS-HH
011.00Area2.372.37Guardiania1.00Area12.4412.44Deposito
011.00Area12.4112.41Deposito 021.00Area14.6014.60Salon de
Musica1.00Area52.0352.03Pasadizofrontal1.0035.201.9066.88posterior1.0035.201.0035.20Hall
de ingreso1.006.904.5031.0502.01.03.05COLUMNETAS DE PROTECCION
DESAGUE PLUVIAL02.01.03.05.01CONCRETO EN COLUMNETA PLUVIAL F'C=175
KG/CM21.51M3Modulo 1C.P.Eje 1-1 y 11-11Tramo
A-C6.000.250.156.701.5102.01.03.05.02ENCOFRADO Y DESENCOFRADO DE
COLUMNETA PLUVIAL12.06M2Modulo 1C.P.Eje 1-1 y 11-11Tramo
A-C6.000.306.7012.0602.01.03.06VEREDAS DE
CONCRETO02.01.03.06.01VEREDA DE CONCRETO FROTACHADO DE 6" SIN
COLOREAR Y BRUADO35.20M2Modulo 1Veredaeje A-ATramo
01-111.0035.201.0035.2002.01.03.06.02UAS EN VEREDA DE
CONCRETO2.82M3Modulo 1Uas en veredasEje A'-A' y C'-C'Tramo
01-112.00Area0.0435.202.8202.01.03.06.03ENCOFRADO Y DESENCOFRADO EN
VEREDAS18.58M2Modulo 1Lateral de uasEje A'-A' y C'-C'Tramo
01-112.00Area0.040.08Frontal de uasEje A'-A' y C'-C'Tramo
01-112.0035.200.2618.30Lateral de veredasEje 01-01 y 11-11tramo
A-C2.000.900.110.2002.01.04OBRAS DE CONCRETO
ARMADO02.01.04.01ZAPATAS02.01.04.01.01CONCRETO EN ZAPATAS F'C=210
KG/CM239.64M3Modulo 1Z-01Eje A-ATramo
1-112.002.601.250.603.90Z-02Eje A-ATramo
1-113.001.601.500.604.32Z-03Eje A-ATramo
1-112.001.751.650.603.47Z-04Eje A-ATramo
1-112.001.001.900.602.28Z-09Eje A-ATramo
1-112.000.801.500.601.44Z-11Eje B-BTramo
1-112.000.901.750.601.89Z-05Eje C-CTramo
1-112.002.851.450.604.96Z-06Eje C-CTramo
1-113.001.951.850.606.49Z-07Eje C-CTramo
1-112.002.102.000.605.04Z-08Eje C-CTramo
1-112.001.202.400.603.46Z-10Eje C-CTramo
1-112.001.002.000.602.4002.01.04.01.02ACERO FY=4,200KG/CM2, GRADO
60VER CUADRO DE
METRADOS953.15KG02.01.04.02COLUMNAS02.01.04.02.01CONCRETO EN
COLUMNAS F'C=210 KG/CM237.00M3Modulo 1C-1Eje A-ATramo
1-114.00Area0.217.506.30C-2Eje A-ATramo
1-115.00Area0.247.509.00C-3Eje A-ATramo
1-112.00Area0.137.501.95C-4Eje B-BTramo
1-112.000.250.258.241.03C-BEje B-BTramo
1-113.000.250.257.841.47C-1Eje C-CTramo
1-114.00Area0.217.506.30C-2Eje C-CTramo
1-115.00Area0.247.509.00C-3Eje C-CTramo
1-112.00Area0.137.501.9502.01.04.02.02ENCOFRADO Y DESENCOFRADO DE
COLUMNAS370.00M2Modulo 1C-1Eje A-ATramo
1-114.00Perim.2.007.5060.00C-2Eje A-ATramo
1-115.00Perim.2.207.5082.50C-3Eje A-ATramo
1-112.00Perim.1.507.5022.50C-4Eje B-BTramo
1-112.00Perim.1.008.2416.48C-BEje B-BTramo
1-113.00Perim.1.007.8423.52C-1Eje C-CTramo
1-114.00Perim.2.007.5060.00C-2Eje C-CTramo
1-115.00Perim.2.207.5082.50C-3Eje C-CTramo
1-112.00Perim.1.507.5022.5002.01.04.02.03ACERO FY=4,200KG/CM2,
GRADO 60VER CUADRO DE METRADOS7,244.44KG02.01.04.03COLUMNETAS DE
AMARRE02.01.04.03.01CONCRETO EN COLUMNETAS DE AMARRE F'C=
175KG/CM25.90M3Modulo 1C-A 1 PlantaEje A-ATramo
1-22.000.150.152.050.09Tramo 2-32.000.150.152.050.09Tramo
3-42.000.150.152.050.09Tramo 4-52.000.150.152.050.09Tramo
9-102.000.150.152.050.09Tramo 10-112.000.150.152.050.09C-A 1
PlantaEje C-CTramo 1-22.000.150.152.050.09Tramo
2-32.000.150.152.050.09Tramo 3-42.000.150.152.050.09Tramo
4-52.000.150.152.050.09Tramo 9-102.000.150.152.050.09Tramo
10-112.000.150.152.050.09C-A 2 PlantaEje A-ATramo
1-22.000.150.151.550.07Tramo 2-34.000.150.151.550.14Tramo
3-44.000.150.151.550.14Tramo 4-54.000.150.151.550.14Tramo
5-64.000.150.151.000.09Tramo 9-104.000.150.151.550.14Tramo
10-112.000.150.151.550.07C-A 2 PlantaEje C-CTramo
1-22.000.150.152.050.09Tramo 2-32.000.150.152.050.09Tramo
3-42.000.150.152.050.09Tramo 4-54.000.150.152.050.18Tramo
5-62.000.150.152.050.09Tramo 9-102.000.150.152.050.09Tramo
10-112.000.150.152.050.09Columneta P/BarandaEje C'-C'Tramo
1-1111.00Area0.271.103.2702.01.04.03.02ENCOFRADO Y DESENCOFRADO DE
COLUMNETAS DE AMARRE46.44M2Modulo 1C-A 1 PlantaEje A-ATramo
1-22.000.301.751.05Tramo 2-32.000.301.751.05Tramo
3-42.000.301.751.05Tramo 4-52.000.301.751.05Tramo
9-102.000.301.751.05Tramo 10-112.000.301.751.05C-A 1 PlantaEje
C-CTramo 1-22.000.301.751.05Tramo 2-31.000.301.750.53Tramo
2-31.000.451.750.79Tramo 3-41.000.301.750.53Tramo
3-41.000.451.750.79Tramo 4-52.000.301.751.05Tramo
9-101.000.451.750.79Tramo 9-101.000.301.750.53Tramo
10-112.000.301.751.05C-A 2 PlantaEje A-ATramo
1-22.000.301.550.93Tramo 2-34.000.301.551.86Tramo
3-44.000.301.551.86Tramo 4-54.000.301.551.86Tramo
5-64.000.301.001.20Tramo 9-104.000.301.551.86Tramo
10-112.000.301.550.93C-A 2 PlantaEje C-CTramo
1-22.000.302.051.23Tramo 2-31.000.302.050.62Tramo
2-31.000.452.050.92Tramo 3-42.000.302.051.23Tramo
4-53.000.302.051.85Tramo 4-51.000.452.050.92Tramo
5-61.000.302.050.62Tramo 5-61.000.452.050.92Tramo
9-101.000.302.050.62Tramo 9-101.000.452.050.92Tramo
10-112.000.152.050.62Columneta P/BarandaEje C'-C'Tramo
1-1111.001.001.1012.1002.01.04.03.03ACERO FY=4,200KG/CM2, GRADO
60VER CUADRO DE METRADOS448.96KG02.01.04.04PLACA DE
CONCRETO02.01.04.04.01CONCRETO EN PLACA F'C= 210
KG/CM217.46M3Modulo 1P-01Eje A-A y C-CTramo
1-22.001.500.307.506.75P-02Eje A-A y C-CTramo
10-112.001.200.307.505.40PlacaEje A-ATramo
7-81.004.000.252.202.20PlacaEje 7-7 y 8-8Tramo
A-C2.002.830.252.203.1102.01.04.04.02ENCOFRADO Y DESENCOFRADO DE
PLACA289.61M2Modulo 1P-01Eje A-A y C-CTramo
1-24.003.607.50108.00P-02Eje A-A y C-CTramo
10-114.003.007.5090.00PlacaEje A-ATramo
7-82.008.502.2037.40PlacaEje 7-7 y 8-8Tramo
A-C4.006.162.2054.2102.01.04.04.03ACERO FY=4,200KG/CM2, GRADO 60VER
CUADRO DE METRADOS1,832.93KG02.01.04.05VIGAS02.01.04.05.01CONCRETO
EN VIGAS F'C=210 KG/CM248.55M3Modulo 1 Vigas principales 1
pisoVP-100Eje 01-01Tramo A-C1.006.900.300.501.04VP-100 voladoEje
01-01Tramo A-C1.001.850.300.500.28VP-101Eje 02-02 y 05-05Tramo
A-C2.006.900.300.502.07VP-101 voladoEje 02-02 y 05-05Tramo
A-C2.001.850.300.500.56VP-102Eje 03-03 y 04-04Tramo
A-C2.006.900.300.602.48VP-102 voladoEje 03-03 y 04-04Tramo
A-C2.001.850.300.600.67VP-100Eje 06-06Tramo
A-C1.006.900.300.501.04VP-100 voladoEje 06-06Tramo
A-C1.001.850.300.500.28VP-103Eje 07-07 y 08-08Tramo
A-C2.006.900.300.502.07VP-103 voladoEje 07-07 y 08-08Tramo
A-C2.001.850.300.500.56VP-104Eje 09-09 y 11-11Tramo
A-C2.006.900.300.502.07VP-104 voladoEje 09-09 y 11-11Tramo
A-C2.001.850.300.500.56VP-105Eje 10-10Tramo
A-C1.006.900.300.501.04VP-105 voladoEje 10-10Tramo
A-C1.001.850.300.500.28Modulo 1 Vigas principales 2 pisoVP-200Eje
01-01Tramo A-C1.008.870.300.401.06VP-201Eje 02-02 y 05-05Tramo
A-C2.008.870.300.402.13VP-202Eje 03-03 y 04-04Tramo
A-C2.008.870.300.402.13VP-200Eje 06-06Tramo
A-C1.008.870.300.401.06VP-203Eje 07-07 y 08-08Tramo
A-C2.008.870.250.401.77VP-204Eje 09-09 y 11-11Tramo
A-C2.008.870.300.402.13VP-205Eje 10-10Tramo
A-C1.008.870.300.401.06Modulo 1 Vigas secundadrias 1 pisoVS-102Eje
A-ATramo 01-021.003.800.300.400.46Tramo
02-031.003.820.300.400.46Tramo 03-041.003.820.300.400.46Tramo
04-051.003.800.300.400.46Tramo 05-061.004.450.300.400.53Tramo
07-082.004.000.300.400.96Tramo 09-101.003.800.300.400.46Tramo
10-111.003.800.300.400.46VS-102Eje C-CTramo
01-021.003.800.300.400.46Tramo 02-031.003.820.300.400.46Tramo
03-041.003.820.300.400.46Tramo 04-051.003.800.300.400.46Tramo
05-061.004.450.300.400.53Tramo 07-081.004.000.300.400.48Tramo
09-101.003.800.300.400.46Tramo 10-111.003.800.300.400.46Modulo 1
Vigas secundadrias 2 pisoVS-202Eje A-ATramo
01-021.003.800.300.400.46Tramo 02-031.003.820.300.400.46Tramo
03-041.003.820.300.400.46Tramo 04-051.003.800.300.400.46Tramo
05-061.004.450.300.400.53Tramo 07-081.004.000.300.400.48Tramo
09-101.003.800.300.400.46Tramo 10-111.003.800.300.400.46VS-202Eje
C-CTramo 01-021.003.800.300.400.46Tramo
02-031.003.820.300.400.46Tramo 03-041.003.820.300.400.46Tramo
04-051.003.800.300.400.46Tramo 05-061.004.450.300.400.53Tramo
07-081.004.000.300.400.48Tramo 09-101.003.800.300.400.46Tramo
10-111.003.800.300.400.46VS-301Eje B-BTramo
01-021.004.250.300.400.51Tramo 02-031.004.130.300.400.50Tramo
03-041.004.120.300.400.49Tramo 04-051.004.100.300.400.49Tramo
05-061.004.900.300.400.59Tramo 07-081.004.500.300.400.54Tramo
09-101.004.250.300.400.51Tramo 10-111.004.250.300.400.51V.M-100Eje
C-CTramo 01-061.0021.600.150.501.62Tramo
07-081.004.500.150.500.34Tramo
09-111.008.500.150.500.6402.01.04.05.02ENCOFRADO Y DESENCOFRADO DE
VIGAS257.88M2Modulo 1 Vigas principales 1 pisoVP-100Eje 01-01Tramo
A-C1.005.900.905.31VP-100 voladoEje 01-01Tramo
A-C1.001.850.901.67VP-101Eje 02-02 y 05-05Tramo
A-C2.005.900.9010.62VP-101 voladoEje 02-02 y 05-05Tramo
A-C2.001.850.903.33VP-102Eje 03-03 y 04-04Tramo
A-C2.005.901.1012.98VP-102 voladoEje 03-03 y 04-04Tramo
A-C2.001.851.104.07VP-100Eje 06-06Tramo A-C1.005.900.905.31VP-100
voladoEje 06-06Tramo A-C1.001.850.901.67VP-103Eje 07-07 y
08-08Tramo A-C2.005.900.9010.62VP-103 voladoEje 07-07 y 08-08Tramo
A-C2.001.850.903.33VP-104Eje 09-09 y 11-11Tramo
A-C2.005.900.9010.62VP-104 voladoEje 09-09 y 11-11Tramo
A-C2.001.850.903.33VP-105Eje 10-10Tramo A-C1.005.900.905.31VP-105
voladoEje 10-10Tramo A-C1.001.850.901.67Modulo 1 Vigas principales
2 pisoVP-200Eje 01-01Tramo A-C1.006.020.764.58VP-201Eje 02-02 y
05-05Tramo A-C2.006.020.769.15VP-202Eje 03-03 y 04-04Tramo
A-C2.006.020.769.15VP-200Eje 06-06Tramo
A-C1.006.020.764.58VP-203Eje 07-07 y 08-08Tramo
A-C2.006.020.769.15VP-204Eje 09-09 y 11-11Tramo
A-C2.006.020.769.15VP-205Eje 10-10Tramo A-C1.006.020.764.58Modulo 1
Vigas secundadrias 1 pisoVS-102Eje A-ATramo
01-021.003.450.702.42Tramo 02-031.003.530.702.47Tramo
03-041.003.520.702.46Tramo 04-051.003.500.702.45Tramo
05-061.004.100.702.87Tramo 07-082.004.000.705.60Tramo
09-101.003.450.702.42Tramo 10-111.003.450.702.42VS-102Eje C-CTramo
01-021.003.450.702.42Tramo 02-031.003.530.702.47Tramo
03-041.003.520.702.46Tramo 04-051.003.500.702.45Tramo
05-061.004.100.702.87Tramo 07-081.004.000.702.80Tramo
09-101.003.450.702.42Tramo 10-111.003.450.702.42Modulo 1 Vigas
secundadrias 2 pisoVS-202Eje A-ATramo 01-021.003.450.702.42Tramo
02-031.003.530.702.47Tramo 03-041.003.520.702.46Tramo
04-051.003.500.702.45Tramo 05-061.004.100.702.87Tramo
07-081.004.000.702.80Tramo 09-101.003.450.702.42Tramo
10-111.003.450.702.42VS-202Eje C-CTramo 01-021.003.450.702.42Tramo
02-031.003.530.702.47Tramo 03-041.003.520.702.46Tramo
04-051.003.500.702.45Tramo 05-061.004.100.702.87Tramo
07-081.004.000.702.80Tramo 09-101.003.450.702.42Tramo
10-111.003.450.702.42VS-301Eje B-BTramo 01-021.003.450.702.42Tramo
02-031.003.530.702.47Tramo 03-041.003.520.702.46Tramo
04-051.003.500.702.45Tramo 05-061.004.100.702.87Tramo
07-081.004.000.702.80Tramo 09-101.003.450.702.42Tramo
10-111.003.450.702.42V.M-100Eje C-CTramo 01-021.003.800.752.85Tramo
02-031.003.820.752.87Tramo 03-041.003.820.752.87Tramo
04-051.003.800.752.85Tramo 05-061.004.450.753.34Tramo
07-081.003.950.752.96Tramo 09-101.003.800.752.85Tramo
10-111.003.800.752.8502.01.04.05.03ACERO FY=4,200KG/CM2, GRADO
60VER CUADRO DE METRADOS4,617.10KG02.01.04.06VIGUETAS DE
AMARRE02.01.04.06.01CONCRETO EN VIGUETAS DE AMARRE F'C= 175
KG/CM21.61M3Modulo 1V-A 1 PlantaEje A-ATramo
1-21.001.900.150.150.04Tramo 2-31.003.470.150.150.08Tramo
3-41.003.470.150.150.08Tramo 4-51.003.450.150.150.08Tramo
9-101.003.400.150.150.08Tramo 10-111.002.200.150.150.050.00V-A 1
PlantaEje C-CTramo 1-21.001.900.150.150.04Tramo
2-31.002.400.150.150.05Tramo 3-41.002.400.150.150.05Tramo
4-51.003.450.150.150.08Tramo 9-101.002.330.150.150.05Tramo
10-111.002.200.150.150.050.00V-A 2 PlantaEje A-ATramo
1-21.001.900.150.150.04Tramo 2-31.003.470.150.150.08Tramo
3-41.003.470.150.150.08Tramo 4-51.003.450.150.150.08Tramo
5-61.004.110.150.150.09Tramo 9-101.003.400.150.150.08Tramo
10-111.002.200.150.150.050.00V-A 2 PlantaEje C-CTramo
1-21.001.900.150.150.04Tramo 2-31.001.500.150.150.03Tramo
3-41.003.480.150.150.08Tramo 4-51.002.650.150.150.06Tramo
5-61.002.970.150.150.07Tramo 9-101.002.330.150.150.05Tramo
10-111.002.200.150.150.0502.01.04.06.02ENCOFRADO Y DESENCOFRADO DE
VIGUETAS DE AMARRE41.56M2Modulo 1V-A 1 PlantaEje A-ATramo
1-22.001.900.301.14Tramo 2-32.003.470.302.08Tramo
3-42.003.470.302.08Tramo 4-52.003.450.302.07Tramo
9-102.003.400.302.04Tramo 10-112.002.200.301.320.00V-A 1 PlantaEje
C-CTramo 1-22.001.900.301.14Tramo 2-32.002.400.301.44Tramo
3-42.002.400.301.44Tramo 4-52.003.450.302.07Tramo
9-102.002.330.30Tramo 10-112.002.200.301.320.00V-A 2 PlantaEje
A-ATramo 1-22.001.900.301.14Tramo 2-32.003.470.302.08Tramo
3-42.003.470.302.08Tramo 4-52.003.450.302.07Tramo
5-62.004.110.302.47Tramo 9-102.003.400.302.04Tramo
10-112.002.200.301.320.00V-A 2 PlantaEje C-CTramo
1-22.001.900.301.14Tramo 2-32.001.500.300.90Tramo
3-42.003.480.302.09Tramo 4-52.002.650.301.59Tramo
5-62.002.970.301.78Tramo 9-102.002.330.301.40Tramo
10-112.002.200.301.3202.01.04.06.03ACERO FY=4,200KG/CM2, GRADO
60VER CUADRO DE METRADOS225.08KG02.01.04.07VIGA
CANAL02.01.04.07.01CONCRETO EN VIGA CANAL F'C= 210
KG/CM26.95M3Modulo 1V-C 2 Planta horizontalEje A-ATramo
1-111.0034.600.500.111.90V-C 2 Planta verticalEje A-ATramo
1-111.0034.600.100.401.38V-C 2 Planta horizontalEje C-CTramo
1-111.0034.600.600.112.28V-C 2 Planta verticalEje C-CTramo
1-111.0034.600.100.401.3802.01.04.07.02ENCOFRADO Y DESENCOFRADO DE
VIGA CANAL101.80M2Modulo 1V-C baseEje A-ATramo
1-111.0034.600.5017.30V-C frontal ext.Eje A-ATramo
1-111.0034.600.5017.30V-C frontal int.Eje A-ATramo
1-111.0034.400.4013.76V-C lateral ext.Eje 01-01 y 11-11Tramo
A-C2.000.500.500.50V-C lateral int.Eje 01-01 y 11-11Tramo
A-C2.000.400.390.31V-C baseEje C-CTramo 1-111.0034.600.6020.76V-C
frontal ext.Eje C-CTramo 1-111.0034.600.5017.30V-C frontal int.Eje
C-CTramo 1-111.0034.400.4013.76V-C lateral ext.Eje 01-01 y
11-11Tramo A-C2.000.500.500.50V-C lateral int.Eje 01-01 y
11-11Tramo A-C2.000.400.390.3102.01.04.07.03ACERO FY=4,200KG/CM2,
GRADO 60VER CUADRO DE
METRADOS926.89KG02.01.04.08CLOSET02.01.04.08.01CONCRETO EN CLOSET
F'C= 175 KG/CM20.59M3Modulo 1ClosetEje A-ATramo
1-114.002.000.550.100.44ClosetEje A-ATramo
1-111.002.800.550.100.1502.01.04.08.02ENCOFRADO Y DESENCOFRADO DE
CLOSETS5.80M2Modulo 1Closet fondoEje A-ATramo
1-114.002.000.403.20Closet fondoEje A-ATramo
1-111.002.800.401.12Closet frente + lateralesEje A-ATramo
1-114.002.800.101.12Closet frente + lateralesEje A-ATramo
1-111.003.600.100.3602.01.04.08.03ACERO FY=4,200KG/CM2, GRADO 60VER
CUADRO DE METRADOS18.98KG02.01.04.09LOSAS
ALIGERADAS02.01.04.09.01CONCRETO EN LOSAS ALIGERADAS F'C = 210
KG/CM239.64M3Modulo 1 - 1 pisoViguetasPao ATramo
01-0215.003.800.100.150.86LosaPao ATramo
01-021.003.806.300.051.20Viguetas en voladoPao DTramo
01-024.003.800.100.150.23Losa en voladoPao DTramo
01-021.003.801.850.050.35ViguetasPao ATramo
02-0315.003.830.100.150.86LosaPao ATramo
02-031.003.836.300.051.21Viguetas en voladoPao DTramo
02-034.003.830.100.150.23Losa en voladoPao DTramo
02-031.003.831.850.050.35ViguetasPao BTramo
03-0415.003.820.100.150.86LosaPao BTramo
03-041.003.826.300.051.20Viguetas en voladoPao DTramo
03-044.003.820.100.150.23Losa en voladoPao DTramo
03-041.003.821.850.050.35ViguetasPao CTramo
04-0515.003.800.100.150.86LosaPao CTramo
04-051.003.806.300.051.20Viguetas en voladoPao DTramo
04-054.003.800.100.150.23Losa en voladoPao DTramo
04-051.003.801.850.050.35ViguetasPao CTramo
05-0615.004.450.100.151.00LosaPao CTramo
05-061.004.456.300.051.40Viguetas en voladoPao DTramo
05-064.004.450.100.150.27Losa en voladoPao DTramo
05-061.004.451.850.050.41Viguetas en voladoPao ETramo
07-084.003.950.100.150.24Losa en voladoPao ETramo
07-081.003.951.850.050.37ViguetasPao FTramo
09-1015.003.800.100.150.86LosaPao FTramo
09-101.003.806.300.051.20Viguetas en voladoPao GTramo
09-104.003.800.100.150.23Losa en voladoPao GTramo
09-101.003.801.850.050.35ViguetasPao FTramo
10-1115.003.800.100.150.86LosaPao FTramo
10-111.003.806.300.051.20Viguetas en voladoPao GTramo
10-114.003.800.100.150.23Losa en voladoPao GTramo
10-111.003.801.850.050.35Modulo 1 - 2 pisoViguetasPao ATramo A-B;
01-027.003.800.100.120.32LosaPao ATramo A-B;
01-021.003.803.270.050.62ViguetasPao ATramo B-C;
01-027.003.800.100.120.32LosaPao ATramo B-C;
01-021.003.803.280.050.62Viguetas en voladoPao DTramo
01-024.003.800.100.120.18Losa en voladoPao DTramo
01-021.003.802.000.050.38ViguetasPao ATramo A-B;
02-037.003.830.100.120.32LosaPao ATramo A-B;
02-031.003.833.270.050.63ViguetasPao ATramo B-C;
02-037.003.830.100.120.32LosaPao ATramo B-C;
02-031.003.833.280.050.63Viguetas en voladoPao DTramo
02-034.003.830.100.120.18Losa en voladoPao DTramo
02-031.003.832.000.050.38ViguetasPao ATramo A-B;
03-047.003.820.100.120.32LosaPao ATramo A-B;
03-041.003.823.270.050.62ViguetasPao ATramo B-C;
03-047.003.820.100.120.32LosaPao ATramo B-C;
03-041.003.823.280.050.63Viguetas en voladoPao DTramo
03-044.003.820.100.120.18Losa en voladoPao DTramo
03-041.003.822.000.050.38ViguetasPao ATramo A-B;
04-057.003.800.100.120.32LosaPao ATramo A-B;
04-051.003.803.270.050.62ViguetasPao ATramo B-C;
04-057.003.800.100.120.32LosaPao ATramo B-C;
04-051.003.803.280.050.62Viguetas en voladoPao DTramo
04-054.003.800.100.120.18Losa en voladoPao DTramo
04-051.003.802.000.050.38ViguetasPao ATramo A-B;
05-067.004.450.100.120.37LosaPao ATramo A-B;
05-061.004.453.270.050.73ViguetasPao ATramo B-C;
05-067.004.450.100.120.37LosaPao ATramo B-C;
05-061.004.453.280.050.73Viguetas en voladoPao DTramo
05-064.004.450.100.120.21Losa en voladoPao DTramo
05-061.004.452.000.050.45ViguetasPao BTramo A-B;
07-087.004.000.100.120.34LosaPao BTramo A-B;
07-081.004.003.270.050.65ViguetasPao BTramo B-C;
07-087.004.000.100.120.34LosaPao BTramo B-C;
07-081.004.003.280.050.66Viguetas en voladoPao ETramo
07-084.003.950.100.120.19Losa en voladoPao ETramo
07-081.003.952.000.050.40ViguetasPao CTramo A-B;
09-107.003.800.100.120.32LosaPao CTramo A-B;
09-101.003.803.270.050.62ViguetasPao CTramo B-C;
09-107.003.800.100.120.32LosaPao CTramo B-C;
09-101.003.803.280.050.62Viguetas en voladoPao FTramo
09-104.003.800.100.120.18Losa en voladoPao FTramo
09-101.003.802.000.050.38ViguetasPao CTramo A-B;
10-117.003.800.100.120.32LosaPao CTramo A-B;
10-111.003.803.270.050.62ViguetasPao CTramo B-C;
10-117.003.800.100.120.32LosaPao CTramo B-C;
10-111.003.803.280.050.62Viguetas en voladoPao FTramo
10-114.003.800.100.120.18Losa en voladoPao FTramo
10-111.003.802.000.050.3802.01.04.09.02ENCOFRADO Y DESENCOFRADO DE
LOSA ALIGERADA497.32M2Modulo 1 - 1 PisoLosaPao ATramo
01-021.003.806.3023.94Losa en voladoPao DTramo
01-021.003.801.857.03LosaPao ATramo 02-031.003.836.3024.13Losa en
voladoPao DTramo 02-031.003.831.857.09LosaPao BTramo
03-041.003.826.3024.07Losa en voladoPao DTramo
03-041.003.821.857.07LosaPao CTramo 04-051.003.806.3023.94Losa en
voladoPao DTramo 04-051.003.801.857.03LosaPao CTramo
05-061.004.456.3028.04Losa en voladoPao DTramo
05-061.004.451.858.23Losa en voladoPao ETramo
07-081.003.951.857.31LosaPao FTramo 09-101.003.806.3023.94Losa en
voladoPao GTramo 09-101.003.801.857.03LosaPao FTramo
10-111.003.806.3023.94Losa en voladoPao GTramo
10-111.003.801.857.03Modulo 1 - 2 PisoLosaPao ATramo A-B;
01-021.003.803.2712.43LosaPao ATramo B-C;
01-021.003.803.2812.46Losa en voladoPao DTramo
01-021.003.802.007.60LosaPao ATramo A-B;
02-031.003.833.2712.52LosaPao ATramo B-C;
02-031.003.833.2812.56Losa en voladoPao DTramo
02-031.003.832.007.66LosaPao ATramo A-B;
03-041.003.823.2712.49LosaPao ATramo B-C;
03-041.003.823.2812.53Losa en voladoPao DTramo
03-041.003.822.007.64LosaPao ATramo A-B;
04-051.003.803.2712.43LosaPao ATramo B-C;
04-051.003.803.2812.46Losa en voladoPao DTramo
04-051.003.802.007.60LosaPao ATramo A-B;
05-061.004.453.2714.55LosaPao ATramo B-C;
05-061.004.453.2814.60Losa en voladoPao DTramo
05-061.004.452.008.90LosaPao BTramo A-B;
07-081.004.003.2713.08LosaPao BTramo B-C;
07-081.004.003.2813.12Losa en voladoPao ETramo
07-081.003.952.007.90LosaPao CTramo A-B;
09-101.003.803.2712.43LosaPao CTramo B-C;
09-101.003.803.2812.46Losa en voladoPao FTramo
09-101.003.802.007.60LosaPao CTramo A-B;
10-111.003.803.2712.43LosaPao CTramo B-C;
10-111.003.803.2812.46Losa en voladoPao FTramo
10-111.003.802.007.6002.01.04.09.03ACERO FY=4,200KG/CM2, GRADO
60VER CUADRO DE METRADOS3,489.28KG02.01.04.09.04POLIESTIRENO
EXPANDIDO (TEKNOPORT) 1.20 X 0.30 X 0.15445.42UNDPlanchaN
Viget.Modulo 1 - 1 pisoViguetasPao ATramo
01-021.003.801.2015.0047.50Viguetas en voladoPao DTramo
01-021.003.801.204.0012.67ViguetasPao ATramo
02-031.003.831.2015.0047.88Viguetas en voladoPao DTramo
02-031.003.831.204.0012.77ViguetasPao BTramo
03-041.003.821.2015.0047.75Viguetas en voladoPao DTramo
03-041.003.821.204.0012.73ViguetasPao CTramo
04-051.003.801.2015.0047.50Viguetas en voladoPao DTramo
04-051.003.801.204.0012.67ViguetasPao CTramo
05-061.004.451.2015.0055.63Viguetas en voladoPao DTramo
05-061.004.451.204.0014.83Viguetas en voladoPao ETramo
07-081.003.951.204.0013.17ViguetasPao FTramo
09-101.003.801.2015.0047.50Viguetas en voladoPao GTramo
09-101.003.801.204.0012.67ViguetasPao FTramo
10-111.003.801.2015.0047.50Viguetas en voladoPao GTramo
10-111.003.801.204.0012.6702.01.04.09.05POLIESTIRENO EXPANDIDO
(TEKNOPORT) 1.20 X 0.30 X 0.12469.33UNDLOSA INCLINADAPlanchaN
Viget.Modulo 1 - 2 pisoViguetasPao ATramo A-B;
01-021.003.801.207.0022.17ViguetasPao ATramo B-C;
01-021.003.801.207.0022.17Viguetas en voladoPao DTramo
01-021.003.801.204.0012.67ViguetasPao ATramo A-B;
02-031.003.831.207.0022.34ViguetasPao ATramo B-C;
02-031.003.831.207.0022.34Viguetas en voladoPao DTramo
02-031.003.831.204.0012.77ViguetasPao ATramo A-B;
03-041.003.821.207.0022.28ViguetasPao ATramo B-C;
03-041.003.821.207.0022.28Viguetas en voladoPao DTramo
03-041.003.821.204.0012.73ViguetasPao ATramo A-B;
04-051.003.801.207.0022.17ViguetasPao ATramo B-C;
04-051.003.801.207.0022.17Viguetas en voladoPao DTramo
04-051.003.801.204.0012.67ViguetasPao ATramo A-B;
05-061.004.451.207.0025.96ViguetasPao ATramo B-C;
05-061.004.451.207.0025.96Viguetas en voladoPao DTramo
05-061.004.451.204.0014.83ViguetasPao BTramo A-B;
07-081.004.001.207.0023.33ViguetasPao BTramo B-C;
07-081.004.001.207.0023.33Viguetas en voladoPao ETramo
07-081.003.951.204.0013.17ViguetasPao CTramo A-B;
09-101.003.801.207.0022.17ViguetasPao CTramo B-C;
09-101.003.801.207.0022.17Viguetas en voladoPao FTramo
09-101.003.801.204.0012.67ViguetasPao CTramo A-B;
10-111.003.801.207.0022.17ViguetasPao CTramo B-C;
10-111.003.801.207.0022.17Viguetas en voladoPao FTramo
10-111.003.801.204.0012.6702.01.04.10ESCALERAS02.01.04.10.01CONCRETO
EN ESCALERAS F'C=210 KG/CM26.46M3Modulo 1EscaleraTramo
011.00Area1.152.002.30EscaleraTramo
021.00Area0.762.001.52EscaleraDescanso1.00Area0.424.001.68EscaleraLlegada1.00Area0.124.000.48V.S
102Apoyo descanso1.004.000.300.400.4802.01.04.10.02ENCOFRADO Y
DESENCOFRADO EN ESCALERAS56.76M2Modulo 1EscaleraTramo
01Fondo1.003.032.006.06Contrapasos9.002.000.183.15EscaleraTramo
02Fondo1.003.342.006.68Contrapasos10.002.000.183.50EscaleraDescanso1.002.464.009.84EscaleraLlegada10.000.604.0024.00V.S
102Apoyo descanso1.003.720.953.5302.01.04.10.03ACERO
FY=4,200KG/CM2, GRADO 60VER CUADRO DE METRADOS337.62KG
ACER ZAPTASPLANILLA DE NETRADOS ACERO ZAPATAS ( ESTRUCTURAS
)PROYECTO: "MEJORAMIENTO DE LA CALIDAD DEL SERVICIO EDUCATIVO EN EL
NIVEL SECUNDARIO DE LA INSTITUCION EDUCATIVA SAN JUAN, DISTRITO DE
SAN JUAN, PROVINCIA DE CASTROVIRREYNA-HUANCAVELICA"Respon.: E&R
CONTRATISTAS GENERALES SRLDepartamento: HUANCAVELICAFecha: Abril
2014Provincia: CASTROVIRREYNADistrito: SAN JUANFormula: 02 - MODULO
01 "ADMINISTRATIVA Y RECURSOS ACADEMICOS"Lugar: SAN
JUANITEMPARTIDADESCRIPCIONTIPO LONG PARCIALCANT DE ELEMENTOSN DE
VECES 1" 3/4" 5/8" 1/2" 3/8" 1/4"02.01.04.01.02ACERO
FY=4,200KG/CM2, GRADO 60MODULO 01Z-01HORZ.
5/8"2.436.002.000.000.0029.160.000.000.00Z-01VERT.
5/8"1.1411.002.000.000.0025.080.000.000.000.00Z-02HORZ.
5/8"1.467.003.000.000.0030.660.000.000.00Z-02VERT.
5/8"1.368.003.000.000.0032.640.000.000.000.00Z-03HORZ.
5/8"1.618.002.000.000.0025.760.000.000.00Z-03VERT.
5/8"1.518.002.000.000.0024.160.000.000.000.00Z-04HORZ.
5/8"0.869.002.000.000.0015.480.000.000.00Z-04VERT.
5/8"1.785.002.000.000.0017.800.000.000.00Z-05HORZ.
5/8"2.717.002.0037.94Z-05VERT. 5/8"1.3111.002.0028.82Z-06HORZ.
5/8"1.819.003.0048.87Z-06VERT. 5/8"1.719.003.0046.17Z-07HORZ.
5/8"1.9610.002.0039.20Z-07VERT. 5/8"1.8610.002.0037.20Z-08HORZ.
5/8"1.0611.002.0023.32Z-08VERT. 5/8"2.266.002.0027.12Z-09HORZ.
5/8"0.669.002.0011.88Z-09VERT. 5/8"1.365.002.0013.60Z-10HORZ.
5/8"0.865.002.008.60Z-10VERT. 5/8"1.8610.002.0037.20Z-11HORZ.
5/8"0.764.002.006.08Z-11VERT. 5/8"1.619.002.0028.98TOTAL
(ML)0.000.00595.720.000.000.00TOTAL
(KG)4.042.261.601.020.580.250.000.00953.150.000.000.00953.15Kg.
ACER COLUMNAPLANILLA DE METRADOS ACERO COLUMNAS
(ESTRUCTURAS)PROYECTO: "MEJORAMIENTO DE LA CALIDAD DEL SERVICIO
EDUCATIVO EN EL NIVEL SECUNDARIO DE LA INSTITUCION EDUCATIVA SAN
JUAN, DISTRITO DE SAN JUAN, PROVINCIA DE
CASTROVIRREYNA-HUANCAVELICA"Respon.: E&R CONTRATISTAS GENERALES
SRLDepartamento: HUANCAVELICAFecha: Abril 2014Provincia:
CASTROVIRREYNADistrito: SAN JUANFormula: 02 - MODULO 01
"ADMINISTRATIVA Y RECURSOS ACADEMICOS"Lugar: SAN
JUANITEMPARTIDADESCRIPCIONTIPO LONG PARCIALCANT ELEMENTOSN DE VECES
1" 3/4" 5/8" 1/2" 3/8" 1/4"02.01.04.02.03ACERO FY=4,200KG/CM2,
GRADO 600.000.000.000.000.000.00Modulo
010.000.000.000.000.000.00C-01; Portico 01-01Acero long.
5/8"9.618.002.000.000.00153.760.000.000.00Acero long.
1/2"9.614.002.0076.88Traslape en acero long.
5/8"0.808.002.000.000.0012.800.000.000.00Traslape en acero long.
1/2"0.804.002.006.40Estribos horizontal
3/8"1.4853.002.000.000.000.000.00156.880.00Estribo vertical
3/8"1.4853.002.000.000.000.000.00156.880.000.000.000.000.000.000.00C-01;
Portico 06-06Acero long.
5/8"9.618.002.000.000.00153.760.000.000.00Acero long.
1/2"9.614.002.0076.880.00Traslape en acero long.
5/8"0.808.002.000.000.0012.800.000.00Traslape en acero long.
1/2"0.804.002.006.40Estribos long
3/8"1.4853.002.000.000.000.000.00156.88Estribo Transv.
3/8"1.4853.002.000.000.000.000.00156.88C-02; Portico 2-2 y 5-5Acero
long. 5/8"9.6118.004.000.000.00691.920.000.00Traslape en acero
long. 5/8"0.8018.004.000.000.0057.600.000.00Estribos long
3/8"1.4853.004.000.000.000.000.00313.76Estribo Transv.
3/8"1.6853.004.000.000.000.000.00356.16C-02; Portico 3-3 y 4-4Acero
long. 5/8"9.6118.004.000.000.00691.920.000.00Traslape en acero
long. 5/8"0.8018.004.000.000.0057.600.000.00Estribos long
3/8"1.4853.004.000.000.000.000.00313.76Estribo Transv.
3/8"1.6853.004.000.000.000.000.00356.16C-03; Portico 7-7 y 8-8Acero
long. 5/8"9.614.004.000.000.00153.760.000.00Acero long.
1/2"9.614.004.00153.76Traslape en acero long.
5/8"0.804.004.000.000.0012.800.000.00Traslape en acero long.
1/2"0.804.004.0012.80Estribos
3/8"1.3853.004.000.000.000.000.00292.56C-01; Portico 9-9 y
11-11Acero long. 5/8"9.618.004.000.000.00307.520.000.00Acero long.
1/2"9.614.004.00153.76Traslape en acero long.
5/8"0.808.004.000.000.0025.600.000.00Traslape en acero long.
1/2"0.804.004.0012.80Estribos long
3/8"1.4853.004.000.000.000.000.00313.76Estribo Transv.
3/8"1.4853.004.000.000.000.000.00313.76C-02; Portico 10-10Acero
long. 5/8"9.6118.002.000.000.00345.960.000.00Traslape en acero
long. 5/8"0.8018.002.000.000.0028.800.000.00Estribos long
3/8"1.4853.002.000.000.000.000.00156.88Estribo Transv.
3/8"1.6853.002.000.000.000.000.00178.08C.B Portico 01-01Acero long.
1/2"8.864.001.000.000.000.0035.440.00Estribos
3/8"0.9551.001.000.000.000.000.0048.45C.B Portico 06-06Acero long.
1/2"8.864.001.000.000.000.0035.440.00Estribos
3/8"0.9551.001.000.000.000.000.0048.45C.B Portico 03-03 y
04-04Acero long. 1/2"8.864.002.000.000.000.0070.880.00Estribos
3/8"0.9551.002.000.000.000.000.0096.90C.B Portico 09-09 y
11-11Acero long. 1/2"8.864.002.000.000.000.0070.880.00Estribos
3/8"0.9551.002.000.000.000.000.0096.90C-04 Portico 07-07 y
08-08Acero long. 1/2"10.124.002.000.000.000.0080.960.00Traslape en
acero long. 1/2"0.804.002.006.40Estribos
3/8"0.9555.002.000.000.000.000.00104.500.000.000.000.000.000.00TOTAL
(ML)0.000.002,706.60799.683,617.600.00TOTAL
(KG)4.042.261.601.020.580.250.000.004,330.56815.672,098.210.07,244.44Kg.
ACER COLUMNETAPLANILLA DE METRADOS ACERO EN COLUMNETA
(ESTRUCTURAS)PROYECTO: "MEJORAMIENTO DE LA CALIDAD DEL SERVICIO
EDUCATIVO EN EL NIVEL SECUNDARIO DE LA INSTITUCION EDUCATIVA SAN
JUAN, DISTRITO DE SAN JUAN, PROVINCIA DE
CASTROVIRREYNA-HUANCAVELICA"Respon.: E&R CONTRATISTAS GENERALES
SRLDepartamento: HUANCAVELICAFecha: Abril 2014Provincia:
CASTROVIRREYNADistrito: SAN JUANFormula: 02 - MODULO 01
"ADMINISTRATIVA Y RECURSOS ACADEMICOS"Lugar: SAN
JUANITEMPARTIDADESCRIPCIONTIPO LONG PARCIALCANT ELEMENTOSN DE VECES
1" 3/4" 5/8" 1/2" 3/8" 1/4"02.01.04.03.03ACERO FY=4200KG/CM2 GRADO
600.000.000.000.000.000.00Modulo 011
piso0.000.000.000.000.000.00Columnetas eje A-A; tramo 01-11Acero
long. 3/8"2.604.0012.000.000.000.000.00124.800.00Estribos
1/4"0.519.0012.000.000.000.000.000.0055.08Columnetas eje C-C; tramo
01-11Acero long.
3/8"2.604.0012.000.000.000.000.00124.800.00Estribos
1/4"0.519.0012.000.000.000.000.000.0055.08Modulo 012
piso0.000.000.000.000.000.00Columnetas eje A-A; tramo 01-11Acero
long. 3/8"2.374.0014.000.000.000.000.00132.720.00Estribos
1/4"0.518.0014.000.000.000.000.000.0057.12Columnetas eje C-C; tramo
01-11Acero long.
3/8"2.894.0024.000.000.000.000.00277.440.00Estribos
1/4"0.518.0024.000.000.000.000.000.0097.920.000.000.000.000.000.00TOTAL
(ML)0.000.000.000.00659.76265.20TOTAL
(KG)4.042.261.601.020.580.250.000.000.000.00382.6666.30448.96Kg.
ACE PLACAPLANILLA DE METRADOS ACERO EN PLACA
(ESTRUCTURAS)PROYECTO: "MEJORAMIENTO DE LA CALIDAD DEL SERVICIO
EDUCATIVO EN EL NIVEL SECUNDARIO DE LA INSTITUCION EDUCATIVA SAN
JUAN, DISTRITO DE SAN JUAN, PROVINCIA DE
CASTROVIRREYNA-HUANCAVELICA"Respon.: E&R CONTRATISTAS GENERALES
SRLDepartamento: HUANCAVELICAFecha: Abril 2014Provincia:
CASTROVIRREYNADistrito: SAN JUANFormula: 02 - MODULO 01
"ADMINISTRATIVA Y RECURSOS ACADEMICOS"Lugar: SAN
JUANITEMPARTIDADESCRIPCIONTIPO LONG PARCIALCANT ELEMENTOSN DE VECES
1" 3/4" 5/8" 1/2" 3/8" 1/4"02.01.04.04.03ACERO FY=4200KG/CM2 GRADO
600.000.000.000.000.000.00Modulo 010.000.000.000.000.000.00P-02;
Eje A-A;Tramo 01-02Acero long.
1/2"8.2313.002.000.000.000.00213.980.000.00Acero transv.
1/2"0.8492.002.000.000.000.00154.560.000.00Estribos
3/8"1.0092.002.00184.000.00P-02; Eje C-C;Tramo 01-02Acero long.
1/2"8.2313.002.000.000.000.00213.980.00Acero transv.
1/2"0.8492.002.000.000.000.00154.560.00Estribos
3/8"1.0092.002.00184.000.00Tramo 10-110.000.00P-01; Eje A-A;Tramo
01-02Acero long. 1/2"8.2313.002.000.000.000.00213.980.00Acero
transv. 1/2"0.5892.002.000.000.000.00106.720.00Estribos
3/8"1.0092.002.00184.000.00P-01; Eje C-C;Tramo 01-02Acero long.
1/2"8.2313.002.000.000.000.00213.980.00Acero transv.
1/2"0.5892.002.000.000.000.00106.720.00Estribos
3/8"1.0092.002.00184.00Caja de Escaleraeje 7-8 tramo A-CAcero long.
3/8"5.409.002.0097.20Acero transv. 3/8"2.1028.002.00117.60eje A
tramo 7-8Acero long. 3/8"3.909.001.0035.10Acero transv.
3/8"2.1020.001.0042.000.000.000.000.000.000.00TOTAL
(ML)0.000.000.001,378.481,027.900.00TOTAL
(KG)4.042.261.601.020.580.250.000.000.001,406.05596.180.002,002.23Kg.0.0
ACE VIGAPLANILLA DE METRADOS ACERO VIGAS (ESTRUCTURAS)PROYECTO:
"MEJORAMIENTO DE LA CALIDAD DEL SERVICIO EDUCATIVO EN EL NIVEL
SECUNDARIO DE LA INSTITUCION EDUCATIVA SAN JUAN, DISTRITO DE SAN
JUAN, PROVINCIA DE CASTROVIRREYNA-HUANCAVELICA"Respon.: E&R
CONTRATISTAS GENERALES SRLDepartamento: HUANCAVELICAFecha: Abril
2014Provincia: CASTROVIRREYNADistrito: SAN JUANFormula: 02 - MODULO
01 "ADMINISTRATIVA Y RECURSOS ACADEMICOS"Lugar: SAN
JUANITEMPARTIDADESCRIPCIONTIPO LONGITUD PARCIAL (ML)CANTIDAD DE
ELEMENTOSN DE VECES 1" 3/4" 5/8" 1/2" 3/8" 1/4"02.01.04.05.03ACERO
FY= 4200KG/CM2 / GRADO 600.00.00.00.00.00.0Modulo 011
pisoVP-100;Portico 01-01Acero principal superior
5/8"7.322.001.000.000.0014.640.000.000.00Acero principal inferior
1/2"7.142.001.000.000.000.0014.280.000.00Refuerzo central
1/2"7.122.001.000.0014.24Refuerzo negativo
1/2"7.221.001.007.22Estribos
3/8"1.4840.001.000.000.000.000.0059.200.000.00.00.00.00.00.0VP-100;Portico
01-01 voladoAcero principal superior
5/8"2.922.001.000.000.005.840.000.000.00Acero principal inferior
1/2"2.822.001.000.000.000.005.640.000.00Refuerzo central
1/2"2.722.001.000.005.440.00Refuerzo negativo
1/2"2.821.001.002.820.00Estribos
3/8"1.4815.001.000.000.000.000.0022.200.00VP-100;Portico 06-06Acero
principal superior 5/8"9.322.001.000.000.0018.640.000.00Acero
principal inferior 1/2"9.142.001.000.000.000.0018.280.00Refuerzo
central 1/2"9.122.001.000.0018.24Refuerzo negativo
1/2"9.221.001.009.22Estribos
3/8"1.4855.001.000.000.000.000.0081.400.00.00.000.00.0VP-101;Portico
2-2 y 5-5Acero principal superior
3/4"9.422.002.000.0037.680.000.000.00Acero principal inferior
3/4"9.322.002.000.0037.280.000.000.00Refuerzo central
1/2"9.122.002.000.000.000.0036.480.00Refuerzo negativo lateral
3/4"3.101.002.000.006.200.000.000.00Refuerzo negativo lateral
5/8"3.102.002.000.000.0012.400.000.00Refuerzo negativo lateral
5/8"2.272.002.000.000.009.080.000.00Refuerzo negativo lateral
1/2"2.221.002.000.000.000.004.440.00Estribos
3/8"1.4855.002.000.000.000.000.00162.80VP-102;Portico 3-3 y
4-4Acero principal superior
3/4"9.422.002.000.0037.680.000.000.00Acero principal inferior
3/4"9.322.002.000.0037.280.000.000.00Refuerzo central
1/2"9.122.002.000.000.000.0036.480.00Refuerzo negativo lateral
3/4"3.102.002.000.0012.400.000.000.00Refuerzo negativo lateral
3/4"3.102.002.000.0012.400.000.000.00Refuerzo negativo lateral
3/4"2.322.002.000.009.280.000.000.00Refuerzo negativo lateral
3/4"2.321.002.000.004.640.000.000.00Estribos
3/8"1.6855.002.000.000.000.000.00184.80VP-103;Portico 7-7 y
8-8Acero principal superior
1/2"9.222.002.000.000.000.0036.880.00Acero principal inferior
1/2"9.142.002.000.000.000.0036.560.00Refuerzo central
1/2"9.122.002.000.000.000.0036.480.00Refuerzo negativo lateral
1/2"2.702.002.000.000.000.0010.800.00Estribos
3/8"1.4855.002.000.000.000.000.00162.80VP-104;Portico 9-9 y
11-11Acero principal superior
1/2"9.222.002.000.000.000.0036.880.00Acero principal inferior
1/2"9.142.002.000.000.000.0036.560.00Refuerzo central
1/2"9.122.002.000.000.000.0036.480.00Refuerzo negativo lateral
5/8"3.302.002.000.000.0013.200.000.00Estribos
3/8"1.4855.002.000.000.000.000.00162.80VP-105;Portico 10-10Acero
principal superior 3/4"9.422.001.000.0018.840.000.000.00Acero
principal inferior 3/4"9.322.001.000.0018.640.000.000.00Refuerzo
central 1/2"9.122.001.000.000.000.0018.240.00Refuerzo negativo
lateral 3/4"3.101.001.000.003.100.000.000.00Refuerzo negativo
lateral 5/8"3.102.001.000.000.006.200.000.00Refuerzo negativo
lateral 5/8"2.272.001.000.000.004.540.000.00Refuerzo negativo
lateral 1/2"2.221.001.000.000.000.002.220.00Refuerzo positivo
central 1/2"3.301.001.00Estribos
3/8"1.6855.001.000.000.000.000.0092.40Modulo 012 pisoVP-200;Portico
01-01Acero principal superior
1/2"4.902.001.000.000.000.009.800.00Acero principal superior
1/2"6.522.001.000.000.000.0013.04Acero principal inferior
1/2"4.652.001.000.000.000.009.300.00Acero principal inferior
1/2"6.482.001.0012.96Refuerzo negativo
1/2"2.301.001.000.002.30Refuerzo negativo
1/2"3.023.001.009.06Estribos
3/8"1.2361.001.000.000.000.000.0075.030.00.00.00.00.0VP-200;Portico
06-06Acero principal superior
1/2"4.902.001.000.000.000.009.800.00Acero principal superior
1/2"6.522.001.000.000.000.0013.04Acero principal inferior
1/2"4.652.001.000.000.000.009.300.00Acero principal inferior
1/2"6.482.001.0012.96Refuerzo negativo
1/2"2.301.001.000.002.30Refuerzo negativo
1/2"3.023.001.009.06Estribos
3/8"1.2361.001.000.000.000.000.0075.030.00.00.000.00.0VP-201;Portico
2-2 y 5-5Acero principal superior
1/2"4.902.002.000.000.000.0019.600.00Acero principal superior
1/2"6.522.002.000.000.000.0026.08Acero principal inferior
1/2"4.652.002.000.000.000.0018.600.00Acero principal inferior
1/2"6.482.002.0025.92Refuerzo negativo
1/2"2.301.002.000.004.60Refuerzo negativo
5/8"3.022.002.0012.080.00Refuerzo negativo
1/2"3.021.002.006.04Estribos
3/8"1.2361.002.000.000.000.000.00150.06VP-202;Portico 3-3 y
4-4Acero principal superior
1/2"4.902.002.000.000.000.0019.600.00Acero principal superior
1/2"6.522.002.000.000.000.0026.08Acero principal inferior
1/2"4.652.002.000.000.000.0018.600.00Acero principal inferior
1/2"6.482.002.0025.92Refuerzo negativo
1/2"2.301.002.000.004.60Refuerzo negativo
5/8"3.022.002.0012.080.00Refuerzo negativo
1/2"3.022.002.0012.08Estribos
3/8"1.2361.002.000.000.000.000.00150.06VP-203;Portico 7-7 y
8-8Acero principal superior
1/2"4.902.002.000.000.000.0019.600.00Acero principal superior
1/2"6.522.002.000.000.000.0026.080.00Acero principal inferior
1/2"4.652.002.000.000.000.0018.600.00Acero principal inferior
1/2"6.482.002.000.000.000.0025.920.00Refuerzo negativo
1/2"2.301.002.000.000.000.004.600.00Refuerzo negativo
1/2"3.022.002.000.000.000.0012.080.00Estribos
3/8"1.2361.002.000.000.000.000.00150.06VP-104;Portico 9-9 y
11-11Acero principal superior
1/2"4.902.002.000.000.000.0019.600.00Acero principal superior
1/2"6.522.002.000.000.000.0026.080.00Acero principal inferior
1/2"4.652.002.000.000.000.0018.600.00Acero principal inferior
1/2"6.482.002.000.000.000.0025.920.00Refuerzo negativo
1/2"2.301.002.000.000.000.004.600.00Refuerzo negativo
1/2"2.022.002.000.000.000.008.080.00Estribos
3/8"1.2361.002.000.000.000.000.00150.06VP-205;Portico 10-10Acero
principal superior 1/2"4.902.002.000.000.000.0019.600.00Acero
principal superior 1/2"6.522.002.000.000.000.0026.08Acero principal
inferior 1/2"4.652.002.000.000.000.0018.600.00Acero principal
inferior 1/2"6.482.002.0025.92Refuerzo negativo
1/2"2.301.002.000.004.60Refuerzo negativo
5/8"3.022.002.0012.080.00Refuerzo negativo
1/2"3.022.002.0012.08Estribos
3/8"1.2361.002.000.000.000.000.00150.06Modulo 011
pisoVS-102;Portico A-A;tramo 09-11Acero principal superior
5/8"8.922.001.000.000.0017.840.000.00Acero principal inferior
5/8"8.822.001.000.000.0017.640.00Estribos
3/8"1.2350.001.000.000.000.000.0061.50VS-102;Portico A-A;tramo
07-08Acero principal superior
5/8"4.922.001.000.000.009.840.000.00Acero principal inferior
5/8"4.822.001.000.000.009.640.00Estribos
3/8"1.2326.001.000.000.000.000.0031.98VS-102;Portico A-A;tramo
01-06Acero principal superior
5/8"21.922.001.000.000.0043.840.000.00Acero principal inferior
5/8"21.822.001.000.000.0043.640.00Traslape superior
5/8"0.802.001.000.000.001.600.00Traslape inferior
5/8"0.802.001.000.000.001.600.00Estribos
3/8"1.23116.001.000.000.000.000.00142.68VS-102;Portico C-C;tramo
09-11Acero principal superior
1/2"8.822.001.000.000.000.0017.640.00Acero principal inferior
1/2"8.742.001.000.000.000.0017.480.00Refuerzo negativo lateral
1/2"3.001.001.000.000.000.003.000.00Refuerzo negativo lateral
1/2"1.861.001.000.000.000.001.860.00Estribos
3/8"1.2350.001.000.000.000.000.0061.50VS-102;Portico C-C;tramo
07-08Acero principal superior
1/2"4.822.001.000.000.000.009.640.00Acero principal inferior
1/2"4.742.001.000.000.000.009.480.00Refuerzo negativo lateral
1/2"1.861.001.000.000.000.001.860.00Refuerzo negativo lateral
1/2"1.861.001.000.000.000.001.860.00Estribos
3/8"1.2326.001.000.000.000.000.0031.98VS-102;Portico C-C;tramo
01-06Acero principal superior
1/2"21.822.001.000.000.000.0043.640.00Acero principal inferior
1/2"21.742.001.000.000.000.0043.480.00Refuerzo negativo lateral
1/2"1.861.001.000.000.000.001.860.00Refuerzo negativo central
1/2"2.904.001.000.000.000.0011.600.00Traslape superior
1/2"0.802.001.000.000.000.001.60Traslape inferior
1/2"0.802.001.000.000.000.001.60Estribos
3/8"1.23116.001.000.000.000.000.00142.68Modulo 012
pisoVS-202;Portico A-A;tramo 09-11Acero principal superior
1/2"8.823.001.000.000.000.0026.460.00Acero principal inferior
1/2"8.743.001.000.000.000.0026.22Estribos
3/8"1.2350.001.000.000.000.000.0061.50VS-202;Portico A-A;tramo
07-08Acero principal superior
1/2"4.823.001.000.000.000.0014.460.00Acero principal inferior
1/2"4.743.001.000.000.000.0014.22Estribos
3/8"1.2326.001.000.000.000.000.0031.98VS-202;Portico A-A;tramo
01-06Acero principal superior
1/2"21.823.001.000.000.000.0065.460.00Acero principal inferior
1/2"21.743.001.000.000.000.0065.22Traslape superior
1/2"0.803.001.000.000.000.002.40Traslape inferior
1/2"0.803.001.000.000.000.002.40Estribos
3/8"1.23116.001.000.000.000.000.00142.68VS-202;Portico C-C;tramo
09-11Acero principal superior
1/2"8.822.001.000.000.000.0017.640.00Acero principal inferior
1/2"8.742.001.000.000.000.0017.480.00Refuerzo negativo lateral
3/8"1.661.001.000.000.000.000.001.66Refuerzo negativo central
3/8"2.901.001.000.000.000.000.002.90Estribos
3/8"1.2350.001.000.000.000.000.0061.50VS-202;Portico C-C;tramo
07-08Acero principal superior
1/2"4.823.001.000.000.000.0014.460.00Acero principal inferior
1/2"4.743.001.000.000.000.0014.220.00Estribos
3/8"1.2326.001.000.000.000.000.0031.98VS-202;Portico C-C;tramo
01-06Acero principal superior
1/2"21.822.001.000.000.000.0043.640.00Acero principal inferior
1/2"21.742.001.000.000.000.0043.480.00Refuerzo negativo lateral
3/8"1.861.001.000.000.000.000.001.86Refuerzo negativo lateral
3/8"2.461.001.000.000.000.000.002.46Refuerzo negativo central
3/8"2.904.001.000.000.000.000.0011.60Traslape superior
3/8"0.802.001.000.000.000.000.001.60Traslape inferior
3/8"0.802.001.000.000.000.000.001.60Estribos
3/8"1.23116.001.000.000.000.000.00142.68VM-100;Portico C-C;tramo
09-11Acero longitudinal 3/8"8.403.001.000.000.000.000.0025.20Acero
transversal 3/8"0.4254.001.000.000.000.000.0022.68VM-100;Portico
C-C;tramo 07-08Acero longitudinal
3/8"4.383.001.000.000.000.000.0013.14Acero transversal
3/8"0.4227.001.000.000.000.000.0011.34VM-100;Portico C-C;tramo
01-06Acero longitudinal
3/8"21.463.001.000.000.000.000.0064.38Traslape en acero long.
3/8"0.803.002.004.80Acero transversal
3/8"0.42138.001.000.000.000.000.0057.96VS-301 Portico B-BTramo
1-6Acero principal superior 1/2"22.002.001.0044.00Acero principal
inferior 1/2"22.002.001.0044.00Estribos
3/8"1.20132.001.00158.40tramo 7-8Acero principal superior
1/2"4.902.001.009.80Acero principal inferior
1/2"4.902.001.009.80Estribos 3/8"1.2027.001.0032.40tramo 9-11Acero
principal superior 1/2"9.002.001.0018.00Acero principal inferior
1/2"9.002.001.0018.00Estribos
3/8"1.2052.001.0062.400.000.000.000.000.000.00TOTAL
(ML)0.00235.42266.421,739.123,249.780.00TOTAL
(KG)4.042.261.601.020.580.250.00532.05426.271,773.901,884.870.004,617.10Kg.
ACERO VIGUETASPLANILLA DE METRADOS ACERO VIGUETAS
(ESTRUCTURAS)PROYECTO: "MEJORAMIENTO DE LA CALIDAD DEL SERVICIO
EDUCATIVO EN EL NIVEL SECUNDARIO DE LA INSTITUCION EDUCATIVA SAN
JUAN, DISTRITO DE SAN JUAN, PROVINCIA DE
CASTROVIRREYNA-HUANCAVELICA"Respon.: E&R CONTRATISTAS GENERALES
SRLDepartamento: HUANCAVELICAFecha: Abril 2014Provincia:
CASTROVIRREYNADistrito: SAN JUANFormula: 02 - MODULO 01
"ADMINISTRATIVA Y RECURSOS ACADEMICOS"Lugar: SAN
JUANITEMPARTIDADESCRIPCIONTIPO LONGITUD PARCIAL (ML)CANTIDAD DE
ELEMENTOSN DE VECES 1" 3/4" 5/8" 1/2" 3/8" 1/4"02.01.04.06.03ACERO
FY= 4200KG/CM2 / GRADO 600.00.00.00.00.00.0Modulo 011
piso0.00.00.00.00.00.0V.A Portico A-A; Tramo 01-02Acero
longitudinal superior 3/8"2.232.001.000.00.00.00.04.460.00Acero
longitudinal inferior 3/8"2.082.001.000.00.00.00.04.160.00Estribos
1/4"0.519.001.000.000.000.000.000.004.590.00.00.00.00.00.0V.A
Portico A-A; Tramo 02-03Acero longitudinal superior
3/8"3.812.001.000.00.00.00.07.620.00Acero longitudinal inferior
3/8"3.662.001.000.00.00.00.07.320.00Estribos
1/4"0.5117.001.000.000.000.000.000.008.67V.A Portico A-A; Tramo
03-04Acero longitudinal superior
3/8"3.812.001.000.00.00.00.07.620.00Acero longitudinal inferior
3/8"3.662.001.000.00.00.00.07.320.00Estribos
1/4"0.5117.001.000.000.000.000.000.008.67V.A Portico A-A; Tramo
04-05Acero longitudinal superior
3/8"3.782.001.000.00.00.00.07.560.00Acero longitudinal inferior
3/8"3.632.001.000.00.00.00.07.260.00Estribos
1/4"0.5117.001.000.000.000.000.000.008.67V.A Portico A-A; Tramo
09-10Acero longitudinal superior
3/8"3.732.001.000.00.00.00.07.460.00Acero longitudinal inferior
3/8"3.592.001.000.00.00.00.07.180.00Estribos
1/4"0.5117.001.000.000.000.000.000.008.67V.A Portico A-A; Tramo
10-11Acero longitudinal superior
3/8"2.542.001.000.00.00.00.05.080.00Acero longitudinal inferior
3/8"2.392.001.000.00.00.00.04.780.00Estribos
1/4"0.5110.001.000.000.000.000.000.005.10V.A Portico C-C; Tramo
01-02Acero longitudinal superior
3/8"2.242.001.000.00.00.00.04.480.00Acero longitudinal inferior
3/8"2.082.001.000.00.00.00.04.160.00Estribos
1/4"0.518.001.000.000.000.000.000.004.080.00.00.00.00.00.0V.A
Portico C-C; Tramo 02-03Acero longitudinal superior
3/8"2.742.001.000.00.00.00.05.480.00Acero longitudinal inferior
3/8"2.582.001.000.00.00.00.05.160.00Estribos
1/4"0.5111.001.000.000.000.000.000.005.61V.A Portico C-C; Tramo
03-04Acero longitudinal superior
3/8"2.742.001.000.00.00.00.05.480.00Acero longitudinal inferior
3/8"2.582.001.000.00.00.00.05.160.00Estribos
1/4"0.5111.001.000.000.000.000.000.005.61V.A Portico C-C; Tramo
04-05Acero longitudinal superior
3/8"3.782.001.000.00.00.00.07.560.00Acero longitudinal inferior
3/8"3.632.001.000.00.00.00.07.260.00Estribos
1/4"0.5117.001.000.000.000.000.000.008.67V.A Portico C-C; Tramo
09-10Acero longitudinal superior
3/8"2.652.001.000.00.00.00.05.300.00Acero longitudinal inferior
3/8"2.502.001.000.00.00.00.05.000.00Estribos
1/4"0.5110.001.000.000.000.000.000.005.10V.A Portico C-C; Tramo
10-11Acero longitudinal superior
3/8"2.532.001.000.00.00.00.05.060.00Acero longitudinal inferior
3/8"2.372.001.000.00.00.00.04.740.00Estribos
1/4"0.5110.001.000.000.000.000.000.005.10Modulo 012
piso0.00.00.00.00.00.0V.A Portico A-A; Tramo 01-02Acero
longitudinal superior 3/8"2.232.001.000.00.00.00.04.460.00Acero
longitudinal inferior 3/8"2.082.001.000.00.00.00.04.160.00Estribos
1/4"0.519.001.000.000.000.000.000.004.590.00.00.00.00.00.0V.A
Portico A-A; Tramo 02-03Acero longitudinal superior
3/8"3.812.001.000.00.00.00.07.620.00Acero longitudinal inferior
3/8"3.662.001.000.00.00.00.07.320.00Estribos
1/4"0.5117.001.000.000.000.000.000.008.67V.A Portico A-A; Tramo
03-04Acero longitudinal superior
3/8"3.812.001.000.00.00.00.07.620.00Acero longitudinal inferior
3/8"3.662.001.000.00.00.00.07.320.00Estribos
1/4"0.5117.001.000.000.000.000.000.008.67V.A Portico A-A; Tramo
04-05Acero longitudinal superior
3/8"3.782.001.000.00.00.00.07.560.00Acero longitudinal inferior
3/8"3.632.001.000.00.00.00.07.260.00Estribos
1/4"0.5117.001.000.000.000.000.000.008.67V.A Portico A-A; Tramo
05-06Acero longitudinal superior
3/8"4.392.001.000.00.00.00.08.780.00Acero longitudinal inferior
3/8"4.242.001.000.00.00.00.08.480.00Estribos
1/4"0.5120.001.000.000.000.000.000.0010.20V.A Portico A-A; Tramo
09-10Acero longitudinal superior
3/8"3.732.001.000.00.00.00.07.460.00Acero longitudinal inferior
3/8"3.592.001.000.00.00.00.07.180.00Estribos
1/4"0.5117.001.000.000.000.000.000.008.67V.A Portico A-A; Tramo
10-11Acero longitudinal superior
3/8"2.542.001.000.00.00.00.05.080.00Acero longitudinal inferior
3/8"2.392.001.000.00.00.00.04.780.00Estribos
1/4"0.5110.001.000.000.000.000.000.005.10V.A Portico C-C; Tramo
01-02Acero longitudinal superior
3/8"2.242.001.000.00.00.00.04.480.00Acero longitudinal inferior
3/8"2.082.001.000.00.00.00.04.160.00Estribos
1/4"0.518.001.000.000.000.000.000.004.080.00.00.00.00.00.0V.A
Portico C-C; Tramo 02-03Acero longitudinal superior
3/8"1.852.001.000.00.00.00.03.700.00Acero longitudinal inferior
3/8"1.712.001.000.00.00.00.03.420.00Estribos
1/4"0.516.001.000.000.000.000.000.003.06V.A Portico C-C; Tramo
03-04Acero longitudinal superior
3/8"3.812.001.000.00.00.00.07.620.00Acero longitudinal inferior
3/8"3.662.001.000.00.00.00.07.320.00Estribos
1/4"0.5116.001.000.000.000.000.000.008.16V.A Portico C-C; Tramo
04-05Acero longitudinal superior
3/8"2.142.001.000.00.00.00.04.280.00Acero longitudinal inferior
3/8"2.002.001.000.00.00.00.04.000.00Estribos
1/4"0.518.001.000.000.000.000.000.004.08V.A Portico C-C; Tramo
04-05Acero longitudinal superior
3/8"1.172.001.000.00.00.00.02.340.00Acero longitudinal inferior
3/8"1.032.001.000.00.00.00.02.060.00Estribos
1/4"0.513.001.000.000.000.000.000.001.53V.A Portico C-C; Tramo
05-06Acero longitudinal superior
3/8"3.342.001.000.00.00.00.06.680.00Acero longitudinal inferior
3/8"3.152.001.000.00.00.00.06.300.00Estribos
1/4"0.5114.001.000.000.000.000.000.007.14V.A Portico C-C; Tramo
09-10Acero longitudinal superior
3/8"2.652.001.000.00.00.00.05.300.00Acero longitudinal inferior
3/8"2.502.001.000.00.00.00.05.000.00Estribos
1/4"0.5110.001.000.000.000.000.000.005.10V.A Portico C-C; Tramo
10-11Acero longitudinal superior
3/8"2.532.001.000.00.00.00.05.060.00Acero longitudinal inferior
3/8"2.372.001.000.00.00.00.04.740.00Estribos
1/4"0.5110.001.000.000.000.000.000.005.100.000.000.000.000.000.00TOTAL
(ML)0.000.000.000.00314.20171.36TOTAL
(KG)4.042.261.601.020.580.250.000.000.000.00182.2442.84225.08Kg.
ACERO VIGA CANAL PLANILLA DE METRADOS ACERO VIGA CANAL
(ESTRUCTURAS)PROYECTO: "MEJORAMIENTO DE LA CALIDAD DEL SERVICIO
EDUCATIVO EN EL NIVEL SECUNDARIO DE LA INSTITUCION EDUCATIVA SAN
JUAN, DISTRITO DE SAN JUAN, PROVINCIA DE
CASTROVIRREYNA-HUANCAVELICA"Respon.: E&R CONTRATISTAS GENERALES
SRLDepartamento: HUANCAVELICAFecha: Abril 2014Provincia:
CASTROVIRREYNADistrito: SAN JUANFormula: 02 - MODULO 01
"ADMINISTRATIVA Y RECURSOS ACADEMICOS"Lugar: SAN
JUANITEMPARTIDADESCRIPCIONTIPO LONGITUD PARCIAL (ML)CANTIDAD DE
ELEMENTOSN DE VECES 1" 3/4" 5/8" 1/2" 3/8" 1/4"02.01.04.07.03ACERO
FY= 4200KG/CM2 / GRADO 600.00.00.00.00.00.0Modulo 011
piso0.00.00.00.00.00.0Viga canal; eje A-A; tramo 01-11Acero
longitudinal fondo 3/8"35.443.001.000.00.00.00.0106.320.00Acero
longitudinal frontal 3/8"34.584.001.000.00.00.00.0138.320.00Acero
transversal
1/2"1.45231.001.000.00.00.0334.950.000.000.00.00.00.00.00.0Viga
canal; eje C-C; tramo 01-11Acero longitudinal fondo
3/8"35.443.001.000.00.00.00.0106.320.00Acero longitudinal frontal
3/8"34.584.001.000.00.00.00.0138.320.00Acero transversal
3/8"2.25231.001.000.00.00.00.0519.750.000.000.000.000.000.000.00TOTAL
(ML)0.000.000.00334.951009.030.00TOTAL
(KG)4.042.261.601.020.580.250.000.000.00341.65585.240.00926.89Kg.
ACERO closetPLANILLA DE METRADOS ACERO CLOSET
(ESTRUCTURAS)PROYECTO: "MEJORAMIENTO DE LA CALIDAD DEL SERVICIO
EDUCATIVO EN EL NIVEL SECUNDARIO DE LA INSTITUCION EDUCATIVA SAN
JUAN, DISTRITO DE SAN JUAN, PROVINCIA DE
CASTROVIRREYNA-HUANCAVELICA"Respon.: E&R CONTRATISTAS GENERALES
SRLDepartamento: HUANCAVELICAFecha: Abril 2014Provincia:
CASTROVIRREYNADistrito: SAN JUANFormula: 02 - MODULO 01
"ADMINISTRATIVA Y RECURSOS ACADEMICOS"Lugar: SAN
JUANITEMPARTIDADESCRIPCIONTIPO LONGITUD PARCIAL (ML)CANTIDAD DE
ELEMENTOSN DE VECES 1" 3/4" 5/8" 1/2" 3/8" 1/4"02.01.04.08.03ACERO
FY= 4200KG/CM2 / GRADO 600.00.00.00.00.00.0Modulo 011
piso0.00.00.00.00.00.0ClosetAcero longitudinal
3/8"2.004.001.000.00.00.00.08.000.00Acero transversal
3/8"0.5211.001.000.00.00.00.05.720.000.00.00.00.00.00.0ClosetAcero
longitudinal 3/8"2.804.001.000.00.00.00.011.200.00Acero transversal
3/8"0.5215.001.000.00.00.00.07.800.000.000.000.000.000.000.00TOTAL
(ML)0.000.000.000.0032.720.00TOTAL
(KG)4.042.261.601.020.580.250.000.000.000.0018.980.0018.98Kg.
ACE ALIGPLANILLA DE METRADOS ACERO ALIGERADO
(ESTRUCTURAS)PROYECTO: "MEJORAMIENTO DE LA CALIDAD DEL SERVICIO
EDUCATIVO EN EL NIVEL SECUNDARIO DE LA INSTITUCION EDUCATIVA SAN
JUAN, DISTRITO DE SAN JUAN, PROVINCIA DE
CASTROVIRREYNA-HUANCAVELICA"Respon.: E&R CONTRATISTAS GENERALES
SRLDepartamento: HUANCAVELICAFecha: Abril 2014Provincia:
CASTROVIRREYNADistrito: SAN JUANFormula: 02 - MODULO 01
"ADMINISTRATIVA Y RECURSOS ACADEMICOS"Lugar: SAN
JUANITEMPARTIDADESCRIPCIONTIPO LONGITUD PARCIAL (ML)CANTIDAD DE
ELEMENTOSN DE VECES 1" 3/4" 5/8" 1/2" 3/8" 1/4"02.01.04.09.03ACERO
FY=4200KG/CM2,GRADO 600.00.00.00.00.00.0Modulo 011 PisoViguetas,
pao A,B,CAcero Longitudinal
1/2"21.751.0015.000.00.00.0326.250.00.0Traslape en acero
longitudinal 1/2"0.802.0015.000.00.00.024.00Refuerzo negativo
lateral 5/8"1.631.0015.000.00.024.450.00.00.0Refuerzo negativo
lateral 5/8"1.831.0015.000.00.027.450.00.00.0Refuerzo negativo
central 5/8"2.704.0015.000.00.0162.000.00.00.0Refuerzo positivo
central 1/2"2.252.0015.000.00.00.067.500.00.00.0Viguetas, pao
DAcero Longitudinal 5/8"21.751.004.000.00.087.000.00.00.0Traslape
en acero longitudinal 5/8"0.802.004.000.00.06.400.0Refuerzo
negativo lateral 5/8"1.631.004.000.00.06.520.00.00.0Refuerzo
negativo lateral 5/8"1.831.004.000.00.07.320.00.00.0Refuerzo
negativo central
5/8"2.704.004.000.00.043.200.00.00.00.00.00.0Viguetas, pao EAcero
Longitudinal 1/2"4.751.004.000.00.00.019.000.00.0Refuerzo negativo
lateral 3/8"1.631.004.000.00.00.00.06.520.0Refuerzo negativo
lateral 3/8"1.631.004.000.00.00.00.06.520.0Viguetas, pao FAcero
Longitudinal 1/2"8.751.0015.000.00.00.0131.250.00.0Refuerzo
negativo lateral 5/8"1.631.0015.000.00.024.450.00.00.0Refuerzo
negativo lateral 5/8"1.631.0015.000.00.024.450.00.00.0Refuerzo
negativo central 5/8"2.704.0015.000.00.0162.000.00.00.0Viguetas,
pao GAcero Longitudinal
5/8"8.751.004.000.00.035.000.00.00.0Refuerzo negativo lateral
5/8"1.631.004.000.00.06.520.00.00.0Refuerzo negativo lateral
5/8"1.631.004.000.00.06.520.00.00.0Refuerzo negativo central
5/8"2.704.004.000.00.043.200.00.00.0Acero de temperatura
1/4"9.03138.401.000.00.00.00.00.01,249.06Modulo 012 PisoViguetas,
pao A,DAcero Longitudinal
1/2"21.751.0016.000.00.00.0348.000.00.0Traslape en acero
longitudinal 1/2"0.802.0016.000.00.00.025.60Refuerzo negativo
lateral 1/2"1.631.0016.000.00.00.026.080.00.0Refuerzo negativo
lateral 1/2"1.831.0016.000.00.00.029.280.00.0Refuerzo negativo
central 1/2"2.704.0016.000.00.00.0172.800.00.0Refuerzo positivo
central 1/2"2.252.0016.000.00.00.072.000.00.00.0Viguetas, pao
B,EAcero Longitudinal 1/2"4.751.0016.000.00.00.076.000.00.0Refuerzo
negativo lateral 1/2"1.632.0016.000.00.00.052.16Refuerzo negativo
lateral 1/2"1.631.0016.000.00.00.026.080.00.00.00.00.0Viguetas, pao
C,FAcero Longitudinal
1/2"8.751.0016.000.00.00.0140.000.00.0Refuerzo negativo lateral
1/2"1.631.0016.000.00.00.026.080.00.0Refuerzo negativo lateral
1/2"1.631.0016.000.00.00.026.080.00.0Refuerzo negativo central
1/2"2.704.0016.000.00.00.0172.800.00.0Acero de temperatura
1/4"8.87138.401.000.00.00.00.00.01,227.610.00.00.00.00.00.0TOTAL
(ML)0.00.0666.481,760.9613.042,476.67TOTAL
(KG)4.042.261.601.020.580.250.00.01,066.371,796.187.56619.173,489.28Kg.
ESCALERAPLANILLA DE METRADOS ACERO EN ESCALERAS
(ESTRUCTURAS)PROYECTO: "MEJORAMIENTO DE LA CALIDAD DEL SERVICIO
EDUCATIVO EN EL NIVEL SECUNDARIO DE LA INSTITUCION EDUCATIVA SAN
JUAN, DISTRITO DE SAN JUAN, PROVINCIA DE
CASTROVIRREYNA-HUANCAVELICA"Respon.: E&R CONTRATISTAS GENERALES
SRLDepartamento: HUANCAVELICAFecha: Abril 2014Provincia:
CASTROVIRREYNADistrito: SAN JUANFormula: 02 - MODULO 01
"ADMINISTRATIVA Y RECURSOS ACADEMICOS"Lugar: SAN
JUANITEMPARTIDADESCRIPCIONTIPO LONGITUD PARCIAL (ML)CANTIDAD DE
ELEMENTOSN DE VECES 1" 3/4" 5/8" 1/2" 3/8" 1/4"02.01.04.10.03ACERO
FY=4200KG/CM2,GRADO 60Modulo 01Escalera tramo 01Aceros Long.
negativos 3/8"2.4010.001.0024.00Aceros Long. negativos
3/8"1.8010.001.0018.00Aceros Long. negativos
3/8"4.1010.001.0041.00Aceros Long. positivos
3/8"5.0010.001.0050.00Aceros Long. positivos
3/8"3.2510.001.0032.50Acero tranversales
3/8"1.9564.001.00124.80Modulo 01Escalera tramo 02Aceros Long.
negativos 3/8"4.6510.001.0046.50Aceros Long. negativos
3/8"2.3510.001.0023.50Aceros Long. positivos
3/8"1.6010.001.0016.00Aceros Long. positivos
3/8"4.5510.001.0045.50Aceros Long. positivos
3/8"3.5510.001.0035.50Acero tranversales
3/8"1.9564.001.00124.800.00.00.00.00.0TOTAL
(ML)0.00.00.00.0582.100.0TOTAL
(KG)4.042.261.601.020.580.250.00.00.00.0337.620.0337.62Kg.