Page 1: (02) Price AdjustmentsPrice adjustment

PRICE ADJUSTMENT IN PRICE ADJUSTMENT IN CONSTRUCTION & CONSTRUCTION &

CONSULTANCY CONTRACTCONSULTANCY CONTRACT

ByEngr. M. Mazhar-ul-IslamConvener

PEC Act & Byelaws Committee

1

Page 2: (02) Price AdjustmentsPrice adjustment

Terms – Escalation, Price Adjustments & Increase / Decrease. Meaning – Adjustment of Contract Price for increase or decrease of prices of

adjustable materials / services. It is compensation and not extra benefit to Contractor. Adjusted periodically during contract period. Basic formula: Price Adjustment = Quantity x (current rate – base rate). FIDIC formula: Pn=A+b Ln + c Mn + d En + ……

Lo Mo Eo

To be built in the Bidding Documents.

2

Page 3: (02) Price AdjustmentsPrice adjustment

Bidders quote price on prevailing market rates. Cost of basic construction materials fluctuate unpredictably

in Pakistan. Unlimited cost increase not foreseeable & cannot be built in

competitive bidding process. Contractors can execute work only at right costs. Legal contract not necessarily be executable unless

conductive mechanism equitable to the parties are included.

3

Page 4: (02) Price AdjustmentsPrice adjustment

Results of non-adjustments: Project delay, disputes,

cancellation of contracts – resulting more cost for the

Employer. Exclusions: Variation Orders Claims Subsequent Legislation Measurement of Quantities

4

Page 5: (02) Price AdjustmentsPrice adjustment

Standard Bidding Documents for Civil Works: Clause 70.1 of PCC. Standard Bidding Documents for E&M Works: Clause 47.1 of PCC. Standard Form of Bidding Documents (Smaller Contractor):

Preamble. Standard Contract for Consultancy (Time Based): Clause 6.2(a)

SC. Standard Procedure & Formula for Price Adjustments.

5

Page 6: (02) Price AdjustmentsPrice adjustment

Below Rs 30 million contract (below C-5

Ceiling)not covered for Price Adjustment. Procedure for Price Adjustments deemed to be

notified. Mistakes in formulating contract specific formula.

6

Page 7: (02) Price AdjustmentsPrice adjustment

7

FORMULA FORMULA FOR FOR

ESCALATIONESCALATION

Page 8: (02) Price AdjustmentsPrice adjustment

Undertake rate analysis of rightly prepared BOQ’s Consider all members of a family of escalatable items Consider 5% & more weightages as escalatable elements POL & labor shall always be considered even below 5% Maximum adjustable portion shall not exceed 65% and

fixed portion not less than 35% Sum of all weightages plus fixed portion must be unity

8

Page 9: (02) Price AdjustmentsPrice adjustment

Cost Element

Description Weightage Applicable Index

1 2 3 4

(i) Fixed Portion 0.350

(ii) Local Labor PICC

(iii) Cement – in bags PICC

(iv) Reinforcing Steel PICC

(v) High Speed Diesel (HSD)

PICC

(vi) Bricks PICC

(vii) Bitumen PICC

(viii)

Total 1.000

9

Page 10: (02) Price AdjustmentsPrice adjustment

Employers using this price adjustment provisions may

add or delete any elements as deemed appropriate to

the project.

10

Page 11: (02) Price AdjustmentsPrice adjustment

Indices for “(ii)” to “(vii)” are taken from FBS. The base cost indices or prices shall be those applying 28 days prior to the latest day for submission of bids. Current indices or prices shall be those applying 28 days prior to the last day of the billing period.

11

Page 12: (02) Price AdjustmentsPrice adjustment

Any fluctuation in the indices or prices of materials other than those given above shall not be subject to adjustment of the Contract Price.

12

Page 13: (02) Price AdjustmentsPrice adjustment

Fixed portion shown here is for typical road project, Employer to determine the weightage of Fixed Portion considering only those cost elements having cost impact of seven (7) revised to five (5) percent or more on his specific project.

13

Page 14: (02) Price AdjustmentsPrice adjustment

Pn = A + b Ln + c Mn + d En + ……

Lo Mo Eo

14

Page 15: (02) Price AdjustmentsPrice adjustment

Pn is Price Adjustment Factor A is constant, representing the nonadjustable portion b, c, d, etc. are coefficients / weightages representing

portion of each cost element Ln, Mn, En, etc. are the current cost indices of cost

elements for month “n” Lo, Mo, Eo, etc. are base cost indices corresponding to

above cost elements

15

Page 16: (02) Price AdjustmentsPrice adjustment

Source of indices shall be those listed in Appendix-C as

approved by Engineer. As the basis of Price adjustment, Contractor shall have

submitted the tabulation of Weightages & Source of

Indices if different than Appendix – C.

16

Page 17: (02) Price AdjustmentsPrice adjustment

Base cost indices or prices shall be those prevailing on

the day 28 days prior to the latest date of bid

submission. Current indices or prices shall be those prevailing on

the day 28 days prior to the last day of the period to

which a particular monthly statement is related.

17

Page 18: (02) Price AdjustmentsPrice adjustment

If at any time, current indices are not available,

provisional indices are determined by the Engineer will

be used subject to subsequent adjustments.

If an element is not used, ratio between base and current

rates should be considered unity

18

Page 19: (02) Price AdjustmentsPrice adjustment

Clause 43 GC: Time for Completion – within Schedule or

extended Schedule pursuant to Clause 44 GC. Clause 44 GC: Extension of Time for Completion – not

for fault of Contractor. Clause 48GC: Taking over Certificate – by the Engineer.

19

Page 20: (02) Price AdjustmentsPrice adjustment

Price adjustments admissible even for the extended

completion period. If extension due to Contractor's fault, PA will be using

indices before or after the completion, favorable to the

Employer. If extension pursuant to Clause 44 (No fault of Contractor),

PA as usual is allowed.

20

Page 21: (02) Price AdjustmentsPrice adjustment

The Weightages of each of the cost factors shall be

adjusted at any stage of the project, if it is found

unreasonable, unbalanced or inapplicable in review of

the Engineer. Weightages change for Instruction under clause 51(v.o.). Such adjustments shall have to be agreed in such v.o.

21

Page 22: (02) Price AdjustmentsPrice adjustment

““PRICE ADJUSTMENT IN

CONSULTANCY CONTRACT””

BY:Engr. M. Mazhar-ul Islam

ConvenerPEC Act & Bye-laws Committee

22

Page 23: (02) Price AdjustmentsPrice adjustment

Applicable to Time Based assignment Contract only. Generally increase in cost for services. Exclusions: Increase in ceiling Cost of Additional work Subsequent Legislation for other provisions Modification of Contract under Clause 2.5 SC

Payment to be adjusted under Clause 6.2(a) SC. Applicable for both Foreign & Local currency adjustments.

23

Page 24: (02) Price AdjustmentsPrice adjustment

Option – 1

Billing rates for each person shall be adjusted in each July. First adjustment in July following submission of final

proposal. Revision Elements: Annual increment Increase due to promotion Salary revision to Clause 5.3 SC or otherwise

24

Page 25: (02) Price AdjustmentsPrice adjustment

Option – 2 Using the formula:

RI = RIo x II/IIoWhere: RI is the adjusted billing rate RIo is the billing rate payable II is the combined consumer Price Index (CPI) General for

Govt. employees IIo is CPI in July of the year Consultant submitted its

proposal

25

Page 26: (02) Price AdjustmentsPrice adjustment

To be adjusted every 12 months using formula: Rf = Rfo x If / Ifo

Where: Rf is adjusted remuneration Rfo is the remuneration payable If is the official salary index in foreign country for the first

month for which adjustment is suppose to have effect Ifo is the official salary index for the monthly date of

contract

26

Page 27: (02) Price AdjustmentsPrice adjustment

27