Activity ID Activity Name Original Duration Early Start Early Finish Late Start Late Finish Total Float Al Muraqqabat Mixed Use Development 537 02-Jan-12 02-Oct-13 31-Dec-11 02-Oct-13 0 General 537 02-Jan-12 02-Oct-13 31-Dec-11 02-Oct-13 0 Contractual Milestones 537 02-Jan-12 02-Oct-13 31-Dec-11 02-Oct-13 0 A1000 Project Commencement Date 0 02-Jan-12 31-Dec-11 0 A1030 Completion Date of Phase 1 0 04-Jul-13 04-Jul-13 0 A1050 Overall Duration of Phase 1 550 02-Jan-12 04-Jul-13 01-Apr-12 02-Oct-13 90 A1010 Completion Date of Phase 2 0 02-Oct-13 02-Oct-13 0 A1020 Overall Duration of Phase 2 640 02-Jan-12 02-Oct-13 02-Jan-12 02-Oct-13 0 Control Milestones 367 24-Apr-12 08-Jul-13 15-Dec-12 02-Oct-13 74 Civil Works Completion Milestones 158 08-May-12 14-Nov-12 02-Oct-13 02-Oct-13 270 A9066 Completion of Raft Slab (Block A,B,C) 0 08-May-12 02-Oct-13 428 A9067 Completion of Ground Floor Slab (Block A,B,C) 0 23-Jun-12 02-Oct-13 390 A9068 Completion of the Skeleton for Block A 0 17-Sep-12 02-Oct-13 318 A9089 Completion of the Skeleton for Block C 0 30-Oct-12 02-Oct-13 283 A9069 Completion of the Skeleton for Block B 0 14-Nov-12 02-Oct-13 270 Architectural Works Milestones 81 24-Apr-12 29-Jul-12 15-Dec-12 16-Dec-12 114 A9182 Start of Block Works @ Basements 0 24-Apr-12 16-Dec-12 195 A9183 Start of Block Works @ 1st Floor 0 29-Jul-12 15-Dec-12 113 Fit Out and FF&E Milestones 78 06-Apr-13 08-Jul-13 16-Apr-13 02-Oct-13 74 Fit Out Milestones 15 06-Apr-13 23-Apr-13 16-Apr-13 28-Apr-13 4 A9360 Completion of Fit Out for Block C 0 06-Apr-13 16-Apr-13 9 A9340 Completion of Fit Out for Block A 0 17-Apr-13 25-Apr-13 7 A9350 Completion of Fit Out for Block B 0 23-Apr-13 28-Apr-13 4 FF & E Milestones 2 06-Jul-13 08-Jul-13 02-Oct-13 02-Oct-13 74 A9370 Commencement of FF&E @ Block A 0 06-Jul-13 02-Oct-13 76 A1232 Commencement of FF&E @ Block B 0 06-Jul-13 02-Oct-13 76 A1222 Commencement of FF&E @ Block C 0 08-Jul-13 02-Oct-13 74 MEP Works Milestones 67 26-Jan-13 14-Apr-13 05-Mar-13 24-Apr-13 9 A9226 Completion of LPG System 0 26-Jan-13 10-Apr-13 64 A9256 Completion of MEP Works ( Related to Temporary Power) 0 21-Feb-13 05-Mar-13 10 A9196 Completion of Elevators 0 14-Mar-13 23-Mar-13 7 A9216 Completion of Garbage & Linen Chute 0 14-Apr-13 24-Apr-13 9 Facade Works Milestones 69 02-Apr-13 23-Jun-13 04-Jul-13 04-Jul-13 10 A9236 Completion of Facade Cleaning System 0 02-Apr-13 04-Jul-13 79 A9206 Completion of Facade Glazing 0 22-Jun-13 04-Jul-13 11 A9246 Completion of Facade Lighting System 0 23-Jun-13 04-Jul-13 10 Authorities Approvals 338 30-Jan-12 11-Mar-13 17-Mar-12 23-Mar-13 10 Swimmimng Pool 86 08-Jul-12 17-Oct-12 17-Jul-12 01-Nov-12 11 A1435 EHS Approval for Pouring Pools Slab - Block B 10 08-Jul-12 18-Jul-12 17-Jul-12 28-Jul-12 8 A1436 EHS Approval for Pouring Pools Slab - Block A 10 27-Aug-12 06-Sep-12 10-Sep-12 20-Sep-12 12 A1438 EHS Approval for Pouring Pools Slab - Block C 10 07-Oct-12 17-Oct-12 20-Oct-12 01-Nov-12 11 Temporary Power Connection 338 30-Jan-12 11-Mar-13 17-Mar-12 23-Mar-13 10 A1348 Receipt of Design NOC for Electrical Drawings 0 30-Jan-12 17-Mar-12 39 A1358 Confirmation of RMU & Transformers Rooms Layout 0 30-Jan-12 17-Jul-12 143 A1368 Submission & Approval of Electrical Drawings 25 02-Jun-12 01-Jul-12 18-Jul-12 15-Aug-12 39 A1408 Application for Fee Estimation 11 21-Jul-12 01-Aug-12 13-Oct-12 24-Oct-12 70 A1418 Fee Payment by Client to DEWA 12 02-Aug-12 15-Aug-12 28-Oct-12 10-Nov-12 70 A1378 Substation Inspection Invitation to DEWA 6 01-Oct-12 07-Oct-12 09-Mar-13 14-Mar-13 130 A1388 Civil Work Inspection by DEWA 6 08-Oct-12 14-Oct-12 16-Mar-13 21-Mar-13 130 A1398 Approval & Handover Substations to DEWA 0 14-Oct-12 21-Mar-13 130 A1428 Delivery- Installation - Termination of Transformers - RMU 0 27-Dec-12 21-Mar-13 70 A1458 Invitation to DEWA for MEP Work Inspection 2 23-Feb-13 24-Feb-13 06-Mar-13 07-Mar-13 10 A1468 1st MEP Inspection & Comments by DEWA 2 25-Feb-13 26-Feb-13 09-Mar-13 10-Mar-13 10 A1478 Attend DEWA Comments 10 27-Feb-13 10-Mar-13 11-Mar-13 21-Mar-13 10 A1488 Final MEP Inspection & Approval By DEWA 1 11-Mar-13 11-Mar-13 23-Mar-13 23-Mar-13 10 A1518 Release DEWA Temporary Power for T & C 0 11-Mar-13 23-Mar-13 10 Utilities Connection 118 16-Feb-13 04-Jul-13 26-Mar-13 04-Jul-13 0 Gas Connection 0 28-Feb-13 28-Feb-13 26-Mar-13 26-Mar-13 22 A2970 Gas Supply Connection 0 28-Feb-13 26-Mar-13 22 Water Supply Connection 0 07-Mar-13 07-Mar-13 01-May-13 01-May-13 47 A2950 Water Supply Connection 0 07-Mar-13 01-May-13 47 Sewage Connection 0 16-Feb-13 16-Feb-13 16-Apr-13 16-Apr-13 51 A2960 Sewage Connection 0 16-Feb-13 16-Apr-13 51 Permenanet Power Connection 0 04-Jul-13 04-Jul-13 04-Jul-13 04-Jul-13 0 A1528 Release of Permanent Power By DEWA 0 04-Jul-13 04-Jul-13 0 Client Submissions 215 15-Apr-12 30-Dec-12 29-Apr-12 20-Feb-13 43 Awarding of Provisional Sum Packages 215 15-Apr-12 30-Dec-12 29-Apr-12 20-Feb-13 43 A1456 Awarding of Kitchen Equipments Package to ASGC 0 15-Apr-12 30-Apr-12 13 A1466 Awarding of Laundry Equipments Package to ASGC 0 15-Apr-12 29-Apr-12 12 A1476 Awarding of Facade Lighting Package to ASGC 0 21-Apr-12 14-May-12 20 A1489 Awarding of Cooking StationPackage to ASGC 0 30-Apr-12 14-Aug-12 90 A1486 Awarding of Gymnasium Equipments Package to ASGC 0 30-Dec-12 20-Feb-13 43 Technical Data for Prime Cost Items 134 23-May-12 31-Oct-12 23-Sep-12 02-Feb-13 76 A1257 Submit the Techincal Data for Porcalin Tiles 7 23-May-12 30-May-12 23-Sep-12 30-Sep-12 102 A1247 Submit the Techincal Data for Ironmongery 7 24-Jul-12 31-Jul-12 10-Jan-13 17-Jan-13 139 A1277 Submit the Techincal Data for Wooden Parquet 7 24-Jul-12 31-Jul-12 19-Dec-12 26-Dec-12 121 A1267 Submit the Techincal Data for Carpet 7 23-Sep-12 30-Sep-12 15-Dec-12 22-Dec-12 67 A1287 Submit the Techincal Data for Kitchen Appliances 7 22-Oct-12 31-Oct-12 26-Jan-13 02-Feb-13 76 Mobilization 121 02-Jan-12 22-May-12 22-Jan-12 06-Jun-12 13 Project Site 15 02-Jan-12 18-Jan-12 22-Jan-12 08-Feb-12 17 A8950 Installation of Site Gate 5 02-Jan-12 07-Jan-12 02-Feb-12 08-Feb-12 27 A5490 Installation of Project Signboard 6 02-Jan-12 08-Jan-12 01-Feb-12 08-Feb-12 26 A5460 Installation of Generator 7 02-Jan-12 09-Jan-12 23-Jan-12 30-Jan-12 18 A5410 Installation of Fence 8 02-Jan-12 10-Jan-12 30-Jan-12 08-Feb-12 24 A5480 Installation of Store Yard 10 02-Jan-12 12-Jan-12 28-Jan-12 08-Feb-12 22 A8920 Installation of Workshop 10 02-Jan-12 12-Jan-12 28-Jan-12 08-Feb-12 22 A5470 Installation of Septic Tank & Water Tank 7 10-Jan-12 17-Jan-12 31-Jan-12 08-Feb-12 18 A5450 Installation of Site Offices 15 02-Jan-12 18-Jan-12 22-Jan-12 08-Feb-12 17 Tower Cranes 85 14-Feb-12 22-May-12 05-Mar-12 06-Jun-12 13 A5420 Installation of Tower Crane 1 12 14-Feb-12 27-Feb-12 05-Mar-12 18-Mar-12 17 A5467 Installation of Tower Crane 4 12 22-Feb-12 06-Mar-12 28-Apr-12 10-May-12 56 A5430 Installation of Tower Crane 2 12 28-Apr-12 10-May-12 24-May-12 06-Jun-12 23 A5440 Installation of Tower Crane 3 12 09-May-12 22-May-12 24-May-12 06-Jun-12 13 Engineering 463 02-Jan-12 07-Jul-13 02-Jan-12 29-Jul-13 19 Shop Drawings 463 02-Jan-12 07-Jul-13 02-Jan-12 29-Jul-13 19 Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec 2012 2013 Project Commencement Date Completion Date of Phase 1 Overall Duration of Phase 1 Completion Date Overall Duration Completion of Raft Slab (Block A,B,C) Completion of Ground Floor Slab (Block A,B,C) Completion of the Skeleton for Block A Completion of the Skeleton for Block C Completion of the Skeleton for Block B Start of Block Works @ Basements Start of Block Works @ 1st Floor Completion of Fit Out for Block C Completion of Fit Out for Block A Completion of Fit Out for Block B Commencement of FF&E @ Block Commencement of FF&E @ Block Commencement of FF&E @ Block Completion of LPG System Completion of MEP Works ( Related to Temporary Power) Completion of Elevators Completion of Garbage & Linen Chute Completion of Facade Cleaning System Completion of Facade Glazing Completion of Facade Lighting Syste EHS Approval for Pouring Pools Slab - Block B EHS Approval for Pouring Pools Slab - Block A EHS Approval for Pouring Pools Slab - Block C Receipt of Design NOC for Electrical Drawings Confirmation of RMU & Transformers Rooms Layout Submission & Approval of Electrical Drawings Application for Fee Estimation Fee Payment by Client to DEWA Substation Inspection Invitation to DEWA Civil Work Inspection by DEWA Approval & Handover Substations to DEWA Delivery- Installation - Termination of Transformers - RMU Invitation to DEWA for MEP Work Inspection 1st MEP Inspection & Comments by DEWA Attend DEWA Comments Final MEP Inspection & Approval By DEWA Release DEWA Temporary Power for T & C Gas Supply Connection Water Supply Connection Sewage Connection Release of Permanent Power By D Awarding of Kitchen Equipments Package to ASGC Awarding of Laundry Equipments Package to ASGC Awarding of Facade Lighting Package to ASGC Awarding of Cooking StationPackage to ASGC Awarding of Gymnasium Equipments Package to ASGC Submit the Techincal Data for Porcalin Tiles Submit the Techincal Data for Ironmongery Submit the Techincal Data for Wooden Parquet Submit the Techincal Data for Carpet Submit the Techincal Data for Kitchen Appliances Installation of Site Gate Installation of Project Signboard Installation of Generator Installation of Fence Installation of Store Yard Installation of Workshop Installation of Septic Tank & Water Tank Installation of Site Offices Installation of Tower Crane 1 Installation of Tower Crane 4 Installation of Tower Crane 2 Installation of Tower Crane 3 Asset Management Group (Wasl) Al Muraqqabat Mixed Use Development Data Date : 01-Jan-12 Page : 1 of 114 Printed On : 02-Feb-12 Actual Work Remaining Work Critical Remaining Work Milestone Critical Milestones Project Implementation Schedule Overall Schedule Date Revision Chec... Approved 25-Jan-12 Project Implementation Schedule - Rev 00