Top Banner

of 6

00141707

Jun 01, 2018

Download

Documents

wvargas926
Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
  • 8/9/2019 00141707

    1/6

    222

    Transactions on Power

    Systems,

    Vol

    7

    No I , February

    1992

    VOLTAGE CONTROL IMPROVEMENT THROUGH CAPACITOR AND

    TRANSFORMER TAP OPTIMIZATION

    C.J. Bridenbaugh D.A. DiMascio

    Ohio Edison Company

    Akron, Ohio 44308-1890

    Advanced Engineering Planning Department

    Abstract

    -

    A PCB ubstation capacitor replacement program provides

    an opportunity to review a system's overall reactive compensation

    requirements. These requirements can be coordinated with other

    voltage control elements, such as transformer ap settings, n order to

    improve overall transmission operating conditions. A voltage

    improvement and var allocation study utilizing an Optimal Power

    Flow program provides an effective means of coordinating these

    voltage control elements. The control movement required

    to

    improve

    voltage control is minimized while active and reactive system losses

    and reactive importsare reduced.

    Key wor ds Optimal Power Flow, Voltage Control, Reactive

    Allocation, Transformer Tap Optimization.

    INTRODUCTION

    Ohio Edison (OE) is completing a program which eliminates all

    PCB

    substation capacitors

    on

    the transmission and subtransmission

    system. One approach to implementing such a program would be to

    replace existing

    PCB

    apacitor

    banks

    on a one-for-one basis with new

    non-PCB banks [l] A potentid disadvantage in this approach is that it

    presupposes that all the existing banks are still required in the

    locations and at the MVAr ratings that were determined under different

    system conditions than exist today. The early planning for the

    replacement program recognized an opportunity to review and more

    optimally locate and size the reactive compensation needs of the

    system. This planning also recognized that capacitive correction

    should be coordinated with other voltage control elements, such as

    transformer tap settings, n order to improve the overall operation of

    the transmission system.

    The primary objectives of this study were to improve the voltage

    regulation between light load and on-peak load periods and minimize

    losses while determining an appropriate level of reactive

    compensation. The voltage regulation problem generally consists of

    limiting high voltages during light load periods and low voltages

    during on-peak periods. Voltage variation between light load and on-

    peak periods should be minimized. On-peak and light load system

    models were established as the basis for the studies. Considerable

    attention was placed on verifying that these base models were realistic

    representationsof system performance.

    A voltage control evaluation can be accomplished using a

    conventional power flow program. However, for a major system

    evaluation this method requires the running of numerous trial and

    error cases and engineering judgment to find the "optimal" solution.

    This type of evaluation can be performed more efficiently and

    effectively

    with

    the use of an Optimal Power Flow (OPF) program.

    An OPF will help determine t h e minimum amount of control

    movement and capital cost necessary to optimize power system

    quantitiesby optimizing specified control variables.

    The work described in this paper involved the study of all existing

    and currently planned voltage control devices on the

    OE

    transmission

    and subtransmission system. These devices included 104

    91

    SM

    4 3 6 6

    PWRS A

    paper recommended and approved

    by the IEEE Power System Engineering Committee

    of the IEEE Power Engineering Society

    for

    presentat-

    ion at the IEEE/PES 1991 Summer Meeting, San Diego,

    California, July 28 August 1, 1991. Manuscript

    submitted January

    30

    1991; made available

    for

    printing May 29, 1991.

    R D'Aquila

    GE Industrial 8i Power Systems

    Power Systems Engineering Department

    Schenectady, New York 12345

    transformers, most of which are fixed tap, and over 100 sites for new

    or additional capacitor bank installations. The intent of this work was

    to determine the transformer tap settings and reactive allocation to

    provide the best possible voltage profile for all foreseeable system

    conditions while minimizing losses and reactive iniports. Due to the

    large number of voltage control devices being studied, an optimal

    power flow (OPF) was used for most of the analysis. The use of an

    OPF eliminated a significant amount of the trial and error work

    normally associated with this type of study. This study demonstrates

    the benefit of an OPF or transmission planning studies in addition to

    previously demonstrated system operation benefits.

    ANALYTICAL APPROACH

    A. Optimal Power Flow

    A conventional power flow solves a set of equations representing

    the elements of the power system and yields the voltage magnitude

    and angle at each node

    in

    the system.[2] From the voltage and angle,

    other system conditions such as power flows and reactive generation

    can

    be

    calculated. The starting point

    is

    a set of data representing the

    physical values of the transmission system, generation system and the

    customer demand. The system of equations

    are

    solved for one

    specific set of equipment settings.

    If the solution does not yield acceptable results, the equipment

    settings must be adjusted and the equations e-solved. For example,

    if

    the solution shows an unacceptablevoltage at a bus, transformer taps

    or shunt compensation can be adjusted to relieve the problem.

    Through experience and skill, the power flow can be

    an

    effective tool

    in determining equipment settings for localized control. However,

    when a large number of control adjustments must be made to satisfy

    several desirable system wide criteria this becomes an enormous trial

    and error process.

    This is where the value of an OPF can be realized. An OPF is a

    power flow program which not only solves the power flow equations

    but optimally adjusts system control variables to achieve desired

    results. Its input data requirements are essentially the same as for a

    conventional power flow. The same generation, transmission and

    load data are used. Additional data is required

    to

    specify an

    optimization objective, controls which can be adjusted, equipment

    limits and system constraints. The OPF will adjust the available

    control devices to minimize the objective function and satisfy the

    system constraints.

    The optimization objective is a function which the OPF minimizes.

    It can include active or reactive power losses, fuel costs and added

    reactive compensation. It can be calculated for the entire modeled

    system or, more commonly, for a portion of the modeled system

    representing a utility's operating region.

    The control variables are transformer tap positions, phase shifter

    angles, allocation of reactive compensation, generator terminal

    voltages and power generation. Depending

    on

    the optimization

    objective and the user's intent, any of these control variables can be

    fixed (not available for adjustment). The available controls are then

    adjusted to minimize the objective function and satisfyalllimits.

    Equipment limits such

    as

    generator reactive limits and transformer

    tap ranges are actual physical constraints and are strictly enforced

    during the optimization process. System limits can include upper and

    lower bus voltage limits, line

    flow

    limits, and area interchange imits.

    In cases where the system limits cannot be satisfied with the available

    controls the OPF will find the solution which minimizes the

    violations. In this instance, minimizing the violations will drive the

    control adjustment and the optimization objective will force a solution

    as

    close to optimal as feasible.

    0885-8950/92 03.0001992

    I

  • 8/9/2019 00141707

    2/6

    223

    Many of the power system control variables are discrete devices.

    For

    example, there are a limited number of discrete tap positions

    available for a transformer. Similarly, a capacitor bank must be

    switched in or out as one unit. To represent this discrete operation

    with an optimal power flow, control variables are first optimized as if

    they were continuous elements. When the optimal solution is found

    the discrete elements

    are

    reset to their nearest actual setting and the

    remaining continuous controls

    are

    re-optimized. The results from

    both the continuous and discrete portions of the optimization can be

    reported by the OPF.

    This discretization of transformer tap settings and capacitor bank

    sizes

    can

    result in a suboptimal solution with the established voltage

    constraints being violated. To avoid this problem, both the discrete

    and continuous solution should be carefully reviewed. If the specified

    voltage constraints are violated through the discretization process,

    more restrictive voltage constraints should be established to ensure the

    required voltage constraints

    are

    met.

    An OPF, like a conventional power flow, solves the system

    equations for a single set of conditions. The user must simulate

    various system conditions and determine the final control settings

    based on all results. Nevertheless, the engineering time is

    economized.

    For a description of the OPF package and methodology used for

    this study. refer

    to

    [3],

    141

    and [SI

    B. Constraints

    Two key constraints were utilized in defining the optimization

    function for th is study. These constraints were the upper and ower

    bus voltage limitsand the elative capacitor installation cost ratios.

    The original specified voltage constraints were

    a

    maximum of

    1.05p.u. for

    345

    kV,

    138

    kV,

    69

    kV and

    34.5

    kV networks and

    1.07 U

    for

    23

    kV networks. The minimum voltage level specified

    was 0.95 p.u. for all voltage classes. The upper voltage level

    corresponds to the maximum steady-state design voltage currently

    considered for each voltage class. The lower voltage was chosen to

    limit the variation

    in

    voltageon the transmiSsion and subtransmission

    systems between light load and peak loading periods. Some specific

    bus voltage limits were specified during the study to avoid extensive

    voltage control adjustments for an isolated area.

    Voltage limits had

    the

    single largest impact on the results of both

    the transformer tap and capacitor optimization. An increase of as little

    as

    0.01

    p.u. in the low voltage limit would cause a substantial increase

    in the required capacitor additions. Correspondingly, a decrease of

    0.01

    p.u. for the upper voltage limit on the

    23

    kV system required

    transformer tap setting adjustments which caused a substantial

    increase

    in

    the requ redcapacitive additions.

    When bus voltages could not be held within the specified

    constraints for the given system conditions and available voltage

    control elements, the magnitude of all voltage violations was

    minimized

    General comparative inslallation and replacement costs were

    specified for capacitor additions. The relative costs used reflect higher

    installation costs at higher voltage classes. The cost for replacement

    installations represents nstallingnew capacitors at

    sites

    where existing

    banks will

    be

    removed.

    This

    cost was set to

    75

    of the cost for new

    installations to account for utilization of existing controls, structural

    steel, and switching devices. Capacitor bank increment additions for

    the various voltage classes were also defined.

    The size of the

    increment additions were larger for the higher voltage classes. These

    relative cost ratios and increment addition sizes are indicated in

    Table

    1. 

    Table 1

    General Installation Sizes and Costs

    sizeWVArS) Relative Cost (P.u.)

    B u s I k y l M u L n B l p E k m I i s z h m a

    138

    12.6

    2.0

    1S O

    69

    84 8.4 1.0

    .75

    34.5

    80 8.0

    1.0

    .75

    23

    45 4.5 1.0 .75

    Data was also input to reflect limitations and cost differences at

    specific stations. For example, some stations were excluded from

    capacitor additions due to site specific limitations.

    Generator voltage schedules were specified as fixed for the

    purpose of

    this

    study. These schedulesrepresent the current operating

    practice for each generator base on unit and system loading. A

    separatestudy is currently in progress to verify the active and reactive

    power capabilities of each generator in the system. Therefore, it was

    decided to defer detailed study of generator voltage schedules to a

    future date. Since most of the native generating capacity is remote

    from the transmission system load centers, it was concluded that the

    impact of deferring optimization of these voltage schedules would

    have a minimal impact on the transformer tap setting and capacitor

    recommendations necessary to meet the primary objective of improved

    voltage control.

    C Study Procedure

    All existing and planned substation capacitors are switched either

    by automatic voltage control or by operator control voltage ovemde

    via SCADA. They are switched on and off as system requirements

    change. However, most of the transformers on the system are fmed

    tap. Although some fned taps are changed seasonally, the desired

    operation is

    to

    set the taps at a position which would be acceptable

    year round while using capacitors for daily and seasonal voltage

    control. To achieve this desired mode of voltage control the

    transformer aps were fr st optimizedto satisfy voltage constraints for

    the light load system conditions. The new tap settings were then

    incorporated in the peak load case, where the capacitor optimization

    was performed.

    The light load system case represents the maximum expected

    voltage levels on the system while the peak load case represents the

    minimum expected voltage levels. For light load conditions it is

    assumed that the generators will

    be

    at their current light loadoperating

    level and that all shunt capacitors will be switched off. Therefore,

    transformer tap setting changes are the most economic and effective

    means for reducing the light load voltage levels. For peak load

    conditions the generators are assumed to

    be

    at their current peak load

    operating leveland all shunt capacitor banks are available for voltage

    control. The transformer tap settings are also assumed available for

    voltage control for the peak load case, but are limited by the maximum

    setting

    permitted

    to ensure voltage constraints are met for the light load

    system case.

    The transformer and capacitor optimizationswere

    performed

    in an

    iterative process, requiring passes between the peak and light load

    cases. An iterative process was required to ensure a practical

    implementation of the transformer tap and capacitor optimization

    results. If extensive transformer tap setting changes or capacitive

    additions were required to correct isolated voltage violations, the

    voltage constraints at these buses were modified. Figure

    shows a

    flow chart of the study process.

    The first step is to prepare the on-peak and light load data sets.

    h i s

    involves specifying he initial load and generation schedules and

    initial voltage constraintsfor both load levels. Major system additions

    currently planned are

    also

    included in

    the

    study data sets.

    Transformer tap settings are optimized for light load conditions.

    The objective of

    each

    optimization is to determine tap settings for all

    fne

    tap transformers which keep bus voltages within their limits and

    minimize system losses. Bus voltages are reviewed after each

    optimization. If the results

    are

    not acceptable or practical, voltage

    limits can be changed and the process repeated. For each transformer

    tap optimization

    run

    a preliminary capacitor optimization is p e r f o d

    for the on-peak load case. This ensures the feasibility of the

    transformer tap recommendations or on-peak capacitor optimization.

    This process continues until all tap settings are determined and

    acceptable voltages are achieved. These tap settings

    are then

    set in the

    on-peak case.

    When a tentative transforiner tap schedule has been established,

    the optimum substation capacitor bank allocationis determined using

    the on-peak load model. All existing PCB capacitor banks are

    removed from the data base and the associated buses are identified as

    possible replacement locations. All non-PCB capacitor banks

    normally used for voltage control under peak load conditions are left

    on. Existing non-PCB capacitors used for contingency voltage

    suppor~re

    assumed

    available at a zero nstallation cost All Company

    substations are initially designated as candidate buses for either new or

    additional capacitors. At each candidate bus the maximum bank size,

    switching block size and relative cost per installed MVAr are specified

    as input to the OPF.

  • 8/9/2019 00141707

    3/6

    224

    Initial Data

    Set Preparation

    1

    Set Voltage Limits

    Light Load

    Optimize Taps

    Set Voltage Limits

    and Cap Data -

    Peak

    Load

    Optimize Caps

    Figure

    1 . Flow

    chart

    of

    stu y process.

    The objective of each optimization is to find the minimum added

    compensation required to satisfy the voltage constraints while

    minimizing active power losses. The

    OPF

    recommended capacitor

    additions and resulting

    area

    voltage profiles

    are

    reviewed to evaluate

    the feasibility of implementing the recommendations. If the results are

    found to be unacceptable, changes can be made to modify the

    solution. Depending on the required changes, iterations between the

    light load and on-peak load case may be necessary.

    For example, if a capacitor is assigned by the

    OPF

    o a bus which

    physically can not accommodate the bank, that bus is removed from

    the candidate bus list and the capacitor optimization was repeated.

    Other problems include proposed tap changes from

    the

    light load case

    which cause too arge a voltage reduction in the

    peak

    oad case. This

    would cause a significant increase in the amount of compensation

    required in the affected

    area

    solely for voltage control minimal impact

    on

    losses). In

    these instances, the proposed tap changes addressed

    isolated bus voltage violations. Therefore, a compromise ap setting

    was specified and

    the

    capacitor optimization

    repeated.

    This process is repeated until the voltage criteria is satisfied for

    both the on-peak and light load cases with a reasonable amount of

    added compensation and transformer tap changes.

    RESULTS

    A. Transformer Tap Optimization

    The transformer tap optimization was performed for a light load

    system case. The active system load was 1,740 MW, or 42% of the

    peak load. The actual generator operating levels for light load

    conditions were used and all shunt reactive compensation was

    assumed off. The reactive

    load

    was varied to model the actual

    maximum voltage levels which had been experienced for light load

    system conditions.

    During these projected light load conditions some bus voltages

    exceeded 1.05 P U on the subtransmission system. Voltages on the

    345 kV and 138 kV transmission system were within the specified

    acceptable range. The main objective of the fixed tap transformer

    optimization was to bring the subtransmission voltages below the

    maximum acceptable voltage level

    of

    1.05 p.u. (1.07 p.u. for

    the

    23 kV system) while minimizing the voltage reduction on the 138 kV

    transmission system.

    A total of 104 transmission and subtransmission transformers

    were included in the optimization. The number, voltage rating and

    type

    of tap changing were:

    18 345-138 kV transformers no LTC's

    48 138-69 kV transformers no LTC's

    11

    138-34.5 kV transformers

    -

    all LTC's

    2

    138-23kVtransformers

    -

    l L T C

    104 Total

    Most of the 138-69 kV and 138-23 kV transformen were already

    set at their highest tap positionin the base case all taps

    are

    on the high

    side). Therefore, the most effective way to reduce the

    subtransmission voltages was to adjust the 345-138 kV transformers.

    Since all 138-34.5 kV transformers are equipped with LTC's, the

    34.5

    kV bus voltages were not affected.

    In

    the

    first iteration through the tr ansfmer tap optimization

    all

    the

    345-138 kV taps were adjusted to their highest settings. While these

    changes brought the subtransmission voltages to within their upper

    limits,

    hey also lowered the 138 kV bus voltages to levels just above

    their lower limits. Although

    this

    was acceptable for the light load

    condition, it was anticipated hat it would require significantcapacitor

    additions for on-peakload conditions. The first iteration through the

    capacitor optimization confimKd this. A large number of capacitor

    additions were required to bring the 138 kV voltages within their

    lower limits.

    After several iterations between the transformer and capacitor

    optimization a final tap schedule was selected. The resulting tap

    settings provided reduced voltages for the light load system case while

    limiting the amount of added compensation required for the on-peak

    load case. This schedule included adjusting several 345-138 kV

    transformer tap settings up one tap position to reduce the 138 kV

    system voltage. Some 138-23 kV and 138-69 kV transformers were

    also adjusted to correct local

    area

    high voltage concems. While t h i s

    did not reduce the high voltage problems during light load conditions

    to the extent of the first iteration (a two step adjustment on the 345

    138 kV transformers), it kept most subtransmission voltages below

    the upper limits for the light load case without requiring excessive

    capacitor

    bank

    additions

    to

    raise

    voltages for the on-peak case. A total

    of 25 ransformer taps were changed, with only three aps adjusted to

    increase suhs mi ss io nvoltages.

    Examples of the voltage reduction achieved through transformer

    tap optimization for the light load case are shown in Figures 2, 3 and

    4. These are graphical comparisons for the light load case showing

    the original transformer settings compared with the new

    settings.

    Figure 2 is a ranked voltage profile for 69 kV buses in one

    operating division. This type of plot provides a statistical picture

    of

    the bus voltages.

    For each curve, bus voltages were sorted i n

    descending order, with each case being sorted independently. The top

    solid curve labeled "ORIG TAPS" represents the bus voltages

    associated with the original transformer tap settings. The curve

    labeled "NEWTAPS hows the voltage reduction achieved through

    the tap optimization. The original system had approximately

    90

    uses

    with voltages above the 1.05 p.u. limit in this division. With the

    recommended tap settings nearly all bus voltages were below this

    limit.

    Figure 3 shows a similar plot for all 138 kV buses. These graphs

    demonstrate that high subtransmission voltages were reduced by

    lowering the 138 kV bus voltages via 345-138 kV transformer tap

    adjustments.

    Figure 4 is a plot of the 345 kV bus voltages. The voltages in this

    plot are plotted against individual buses, not sorted as in the previous

    ranked profile plot. While the. previous figures showed the reduction

    in voltages on the 138 kV and 69 kV systems, this figure shows that

    most 345 kV bus voltages were increased by 345-138 kV

  • 8/9/2019 00141707

    4/6

    1.15,

    , ORl G

    TAPS

    1 1

    -

    n

    1

    -05

    2I

    ?

    1 -

    225

    ...........................................................................................

    3

    .........................

    I L

    ------ -A-- j

    .............. ;. ............

    .:.

    ..... .-.-p--.--

    w

    a 1

    ...................

    . . . .

    . .

    .

    . . .

    . . .

    . .

    ..

    ....

    , ..

    ..

    .........................

    . . .

    . . . . . . .

    . .

    . . .

    ; ....... ....... ; ........................................

    . . . . . . .

    . . . . .

    ............... _

    ........................................................................

    . .

    . . .

    . . . . .

    . . .

    . . .

    . . . . . . .

    . . . . . . .

    . . . . . . . .

    . . .

    . . .

    , .

    . .

    0

    20

    40 60 80

    100

    N U M B E R O F B U S E S

    Figure 2. 69

    kV

    division light

    lo d

    voltage profile.

    ORl G

    TAPS

    NEWTAPS-

    0.95 1

    0 20

    40 60 80 100 120

    N U M B E R O F B U S E S

    Figure 3. 138

    kV

    light

    lo d

    voltage profile.

    1.06 O R l G TAPS

    1.04

    2

    1.02

    n

    -

    -1

    a 1

    =-

    0.98

    0.96

    0.94

    A B C O E F G H I J K L

    BUS NAME

    Figure 4 . 345

    kV

    light

    lo d bus

    voltages.

    transformer tap changes. The buses with increased voltages

    correspond to the high side buses of the adjusted transformers. The

    increase in high side voltage can be best understood by looking at a pi

    equivalent model of the transformer.

    Figure

    5

    shows the pi equivalent circuit for a typical fixed tap

    transformerwith high side taps.[3,4] VH and VL are the high and low

    side voltages, respectively.YT s the transformer admittance and n is

    the off nominal tums ratio. The shunt elements, BH and BL. will

    t

    B

    = ( ) Y T 1

    L

    Y T

    w i l l h a v e t h e f o r m

    - j B T ,

    w h e r e

    BT>O

    Figure

    5.

    Pi eq uivalent transformer circuit.

    always be of opposite sign. When one is positive, representing a

    capacitor, the other will be negative, representing an inductor. In the

    case of the 345-138 kV transformer, where the tap positions were

    moved up one step, BH will be moxecapacitivethanoriginally

    and

    the

    345 kV voltage wll rise

    The transformer tap changes had a positive impact on the total

    reactive imports into the OE system in that the net import was reduced.

    The imports were reduced by 238 MVAr (38 ) on the 345 kV tie

    lines and increased by 84 MVAr (31 ) on the 138 kV ties, for a net

    reduction of 164 MVAr (20 ). The reduced imports on the 345 kV

    ties was due to the increased voltage level on the

    345 kV

    system,

    while the increased impor ts on the 138 kV ties is a consequenceof the

    reduced voltage levels on the 138 kV system.

    B. Capacitor Optimization

    The substation capacitor replacement needs were studied using a

    load case with 4140 M W of load in the OE system. A total of

    587 MVAr of capacitors were in this case, representing the existing

    reactive compensation. One hundred sixty-five (165) MVAr of this

    total represented PCB banks to

    be

    removed.

    The first task in determining a capacitor replacement plan is to

    implement the previously determined fixed tap transformer changes.

    Initially the original capacitor banks are left in place to simulate the

    results of a one-for-one or

    MVAr-for-MVAr

    type eplacement scheme

    with the new tap settings.

    This

    un is not an optimization,but rather a

    conventional power flow solution intended to serve as a reference for

    later comparison.

    The results of t h i s simulation

    confii

    hat with the present reactive

    allocation and the proposed transformer tap changes, a large number

    of bus voltages will fall below their lower limits of

    .95

    p.u. during

    on-peak load conditions. There was an increase in the voltage levels

    on the

    345 kV

    system, but nearly all other bus voltages were reduced.

    The cause of the voltage level increase on the 345 kV system was

    discussed in the transformer tap optimization section. These results

    clearly demonstrated that some change in the shunt compensation on

    the system wouldbe needed to accommodate the new transformer ap

    settings during on-peak load conditions.

    A new replacement schedule was formulated which would

    improve upon a one-for-one replacement of capacitors. This schedule

    represents the optimum shunt compensation scheme for the base

    system satisfying all voltage requirements and minimizingOE system

    losses. It is a practical and attainable plan which accounts for the

    specific costs and physical limitations of adding compensation at

    particular substations.

    The finalcapacitorreplacement schedule consisted of replacing the

    165 MVArs of capacitorbanks at 26 locations planned for removal

    with 388 MVArs at 35 locations. This increases the total shunt

    compensation for this study system from 587

    MVArs

    o 810 MVArs.

    As an example of the voltage changes attained for the on-peak

    case, Figure 6 shows bus voltages for one operating division

    (69 kV of the system. This is a ranked voltage p f d e plot (similar

    to that of Figure 3). By implementing the tap changes without my

    changes in shunt compensation (curve NEW APS"), the voltages

    were reduced by approximately0.03 p.u. throughout this

    area.

    This

  • 8/9/2019 00141707

    5/6

    226

    1 1

    1.05

    n

    U

    5

    l

    0.95

    0.9

    3000.-

    2000-

    1000

    B A S E

    N E W T A P S

    0-

    -

    1 1

    0

    10

    20 30 40

    NUMBER

    OF

    B U S E S

    -.._

    ,

    ----*

    -- -

    ,

    A

    ---+--

    ............................................

    .,....

    .....................................

    Figure 6 . 69 kV division peak lo d voltage

    profile

    voltage reduction was expected, since the main intent of the

    transformer optimization was to lower subtransmission voltages for

    light load conditions. After implementing he capacitor optimization

    the bus voltages in

    th i s

    area were brought back o their original on-

    peak voltage levels (curve “FINAL“). Therefore, the effect of the

    capacitor optimization in

    t h i s

    area was to offset the transformer tap

    changesrequired o lower light load voltage levels.

    C. Summary

    Figure 7 

    summarizes the supply of reactive compensation on the

    OE system comparing the components for the original study system

    with the study recommendations. The MVArs supplied from

    generation. line charging and distribution line capacitors remains

    essentially unchanged. The MVArs supplied from substation

    capacitors increased by approximately

    38%

    while the system net

    MVAr ipterchangedemead by appmximately34%.

    Although net reactive import reduction could not be specified

    as

    a

    constraint in the optimization, t was a study objective and monitored

    for all cases in the study. The net reduction in reactive imports was

    viewed

    as

    a positive benefit resulting from the optimized transformer

    tap settings and reactive allocation.

    The above reactive additions combined with the recommended tap

    setting changes results in a transmission system voltage profile within

    the specified criteria. Figure 8 globally demonstrates the tighter

    operating voltage band achieved by implementing the study

    recommendations. The horizontal axis ndicates the operating division

    and voltage class while the vertical axis indicates the per unit voltage

    level based on nominal voltage for each area. The maximum light load

    and minimum on-peak voltage in each

    area

    are

    shown with the

    “0‘s”

    corresponding to the levels without the study recommendations and

    the “x’s’’ corresponding o the evels with the study recommendations.

    In general, light load voltages were reduced while on-peak voltages

    wereraised

    to

    establish the desired tighter operating voltage band.

    The sensitivity of the study objectives to increasing the reactive

    compensation beyond the recommended level was also evaluated.

    Figure 9 summarizes he effect of the transformer tap setting changes

    and various levels of reactive additions on losses and reactive imports.

    The horizontal axis ndicates the specific study case with respect to tap

    changes and amount of reactive compensation on the system. The

    verticalaxis on the left indicates the percent change

    in

    losses from the

    original base case while the vertical axis on the right indicates the

    percent change in reactive imports. Along the horizontal axis, the

    second “0”point demonstrates the effect of no change

    in

    the amount

    or placement of reactive compensation with the recommended

    transformer tap changes. Active and reactive losses changed slightly

    and reactive

    imports

    were reduced. However, the voltage profile for

    this case does not meet the specified criteria. The next point (-57)

    represents a reduced level of reactive compensation

    -57 MVAr ,

    although the compensation was optimally sized and located. The

    active and reactive losses. reactive imports and voltage profile were all

    essentially unchanged from the previous case. These two simulations

    confirmed the need for

    additional

    eactive compensation o meet the

    voltage requirements for the peak oad system.

    4 0 0 0 ~

    RECOMMENDED

    Figure 7 Component of MVArs.

    AREA VOLTAGE RANGES

    BEFORE AND AFTER STUDY RECOMMENDATIONS

    H I G H E S T A N D L O W E ST

    OFF

    AND ON-PEAK VOLTAGES

    l T-------

    A23 B23 C23 A69 869 C69 D69

    E69

    F69 G69 H69

    69 J69

    D I V I S I O N A ND V O LT A GE L E V E L

    ,g

    ______~

    +-O r i g i n a l R a n g e +-

    x N e w R a n g e *

    Figure

    8 .

    Area voltage ranges.

    ON-PEAK SYSTEM CASE SUMMARY

    D E V I A T I O N

    FROM

    O R I G I N A L

    I

    I

    -8J ‘ 50

    0 0

    -57

    1

    NEW

    TAPS

    RIGINAL

    TAPS

    A P P R O X I M A T E A D D E D C O M P E N S A T IO N M V A R S )

    Figure 9. On peak system case

    summary

  • 8/9/2019 00141707

    6/6

    227

    The next point (223) represents the effect of the recommended

    reactive allocations. The active and reactive losses and reactive

    imports were all reduced and the voltage profile was within the

    specifed

    criteria.

    The last point (388) represents anincreased evel of

    optimally located capacitors. Active andreactive losses and reactive

    imports

    are

    further reduced whilethe voltage profile r e d s imilar

    to

    the recommended

    case

    Thewresults indicate hat

    additional

    increases

    in reactive compensation would have little effect on voltage control,

    however active and reactive losses and reactive imports would

    be

    redUCed.

    The final study recommendations for transformer tap setting

    changes and capacitor bank additions result in

    a

    number of

    improvements to overall system performance including:

    The transmission system voltage profile has generally been

    Improvement in quality of service to transmission and

    ultimately distribution customers because of improved voltage

    control and reduced range.

    Active power losses reduced by 1.3% (approximately

    8Ooo

    M w h annually).

    Reactive power losses reduced by 4.3%.

    Reactive power imports reduced by 34.3%.

    impr~ved a n p e a koadingand light loadperiods

    The estimated capital equiyalent savings of the reduction in active

    power losses represents approximately 80%

    of

    the capital cost of

    implementing the shdy recommendati ons

    The study also identified several issues for further review and an

    additionalfollow

    on

    study:

    A review of voltage

    limits s

    to be made for

    three

    isolated 23 kV

    systems in order to finalize he associated ransformer tap

    settings

    and

    capacitor bank recommendations. Optimization of the voltage

    schedules for localized generation and synchronous condenser

    facilities may enhance voltage control in

    some

    areas of the

    23

    kV

    system. This could eiiminate the need for some of the associated

    preliminary transformer tap setting and capacitor bank

    recommendations.

    Some of the 69 kV capacitor bank recommendations at

    distribution substations exclusively serving radial load may be

    implemented more cost effectivelywith distribution line capacitorson

    the distribution circuits. Equivalent levels of compensation can be

    installed more economically at the distribution level because of the

    lower voltage rating and the lower distribution substation ransformer

    losses.

    When generator operating capabilities have been finalized, the

    system voltage schedules can then be reviewedwthrespect to further

    optimization and loss reduction.

    C O N C L U S I O N S

    This

    study has effectively denNied ms fo rmer tap changes and a

    capacitor replacement and addition program whichwill improve the

    overall transmission and subtransmission voltage profile, reduce

    system losses and reduce the net reactive system imports. The

    recommendations have been limited to the

    areas

    of transformer taps

    and capacitors, which can readily be implemented for improving

    system performance.

    The recommendations include several areas that require fur ther

    review to ensure the most effective and economic implementation or

    the needed system improvement in this area. Some distribution

    substation capacitor banks are under review to determine if a

    comparable level of compensation

    to

    the transmission system can be

    more economically and effectively implemented by applying the

    compensation on the distribution lines. Several of the 138-23 kV

    transformer tap and 23 kV capacitor bank recommendationsare also

    being studied further.

    The study was conducted in such a way that later optimization of

    the generator terminal voltage schedule may be an effective option for

    further controlling voltage and reducing the net reactive system

    imports. When the capabilities of the generating units have been

    verified k u g h ield tests,

    their

    voltage schedules will bereviewed to

    determine if further improvements

    in

    voltage control, system losses

    and net reactive mports can be achieved.

    REFER

    ENC

    S.A. Miske, Jr., W. Neugebauer, D.J. Ward, “A Systems

    Approach

    t

    the Replacement of Older Substation Capacitors,”

    mesented at the 1988 American Power Conference, Chicago

    r ~

    Illinois, April 1

    R.C. Degeneff, W. Neugebauer, C.H. Saylor, S.L. Corey,

    “Security-Constrained Optimization: An Added Dimension in

    Utility Systems Optimal Power Flow,” IEEE Computer

    Applications n Power, October 1988.

    R.C. Burchett, H.H. Happ, R.E. Palmer, D.R. Vierath,

    “Quadratically Convergent Optimal Power Flow,” IEEE

    Transactions Power Amaratus and Systems, Volume 103, NO.

    .~~

    11,

    1984, pp. 3267-3f3 .

    W.C. Merritt, C.H. Saylor, R.C. Burchett , H.H. Happ,

    “Security Constrained Optimization A Case Study,” IEEE

    Transactions on Power Systems, Volume 3, No. 3, 1988, pp.

    970-977.

    P.E: Gil , W. Murray, and M.H. Wright,

    h W . i d

    - Academic Press, 1981.

    P.M. Anderson, ted Power S y w n s , The Iowa

    State University-73 pp. 262-264.

    W.D. Stevenson, Jr., Elements of Power S u e m s hdYdS

    McGraw-Hill, Inc., 1982, pp. 216-218.

    Robert D’Aquilo was bom in Queens, New York in 1962. He

    received his B.S. and

    M S

    degrees from Clarkson University in

    Electrical Engineering in 1984 and 1985, respectively.

    In

    1986Mr D’Aquila joined the GE Power Systems E n g h d g

    Department in Schenectady, N.Y. He has been involved in

    transmission planning and design projects and the development of

    power system analysis software. He is currently involved in the

    analysis of reactive power control and voltage stability. Before

    joining GE, he was employed by Consolidated Edison Company,

    New York, N.Y. where he worked in the areas of transmission

    planning and system operation.

    Dennis A. DiMascio is a Senior Transmission Planning Engineer

    in the Transmission Planning Section of the Advanced Engineering

    and Planning Department at Ohio Edison Company. He received

    his

    BSEE

    and BA in Mathematics rom the University of Akron n 1965.

    He is also a 1972 graduateof the WestinghouseAdvanced School of

    Power System Engineering. Before his present job assignment, he

    worked

    as

    a substation design engineer and in equipment application

    engineering of power circuit preakers and synchronous motors. He

    has been a member of IEEE since 1966 and served as Chairman of

    Akron Section Power Group and as a member of the Synchronous

    Machinery Subcommittee. He is a registeredProfessional Engineer n

    the Stateof Ohio.

    Carl Bridenbaugh was bom in Port Huron, Michigan

    in

    1960. He

    received his BSEE from the University of Derroit in 1983and his MS

    in Electrical Engineering from Union College

    in

    1985. He also

    graduatedfirom the GE Power Systems EngineeringCourse n 1985.

    In 1983,Mr.Bridenbaugh joined the GE Systems Development

    and Engineering Departmentin Schenectady,N.Y. as an Engineer on

    Rotation involved in all aspects of power system engineering and

    economic studies.

    In

    1986 he became

    an

    Application Engineer,

    performing power system dynamic studies and developing computer

    models of power system components for

    use

    in dynamic performance

    analysis. In 1989 he joined the Ohio Edison Companyin Akron,

    Ohio as a Planning Engineer in the Transmission Planning Section

    of

    the Advanced Engineering and Planning Department. He is currently

    involved in both long and short range studies of the transmission and

    subtransmission system.

    Mr Bridenbaugh is a member of I and is Treasurer of the

    Akron

    Chapter of the

    I

    Power Engineering Society. He holds a

    ProfessionalEngineering Licehse in the states of New York and Ohio.