© PowerServices, Inc. Presenter: Peter J Rant, PE Vice President, PowerServices 1616 E. Millbrook Road, Suite 210 Raleigh, NC 27609 Phone: (919) 256-5900 Branch Offices: Clemson, SC Maitland, FL A Current Perspective on Solar
©PowerServices, Inc. December 2014
Presenter:
Peter J Rant, PE
Vice President, PowerServices
1616 E. Millbrook Road, Suite 210Raleigh, NC 27609Phone: (919) 256-5900Branch Offices: Clemson, SC Maitland, FL
A Current Perspective on Solar
©PowerServices, Inc. December 2014
PowerServices, Inc.
©PowerServices, Inc. December 2014
3
Strong Ties With Public Power
• 2001 PowerSecure becomes an ESP Partner with ElectriCities of NC as the endorsed provider of distributed generation. Fourteen years later the partnership is still strong with over 120 MW of generation installed at over 200 sites
• Hometown Connections partner since 2013
©PowerServices, Inc. December 2014
Topics
1. Overview
2. Interconnection Issues
3. Impact
4. Financial Issues
5. Case Studies
6. Conclusion
4
©PowerServices, Inc. December 2014
Looking at Both Sides
• Interconnection applicants
• Utilities
5
©PowerServices, Inc. December 2014
How to Think About Solar
• DG – Distributed Generation
• DER/DR – Distributed Energy Resource
6
©PowerServices, Inc. December 2014
Solar Building Blocks
• Panels – Around 300 watts each• Racks
Roof or Ground Fixed or Tracking
• Inverters String Micro
7
©PowerServices, Inc. December 2014
Solar Building Blocks
• Cabling• Combiners• Grounding• Switchgear• Transformers• Protective
Devices/Interconnection• Metering
8
©PowerServices, Inc. December 2014
Solar Building Blocks
9
©PowerServices, Inc. December 2014
Solar Building Blocks
10
©PowerServices, Inc. December 2014
Solar Building Blocks
11
©PowerServices, Inc. December 2014
Solar Building Blocks
12
©PowerServices, Inc. December 2014
Solar Building Blocks
13
©PowerServices, Inc. December 2014
10 kW Demonstration Project
14
©PowerServices, Inc. December 2014
OVERVIEW
©PowerServices, Inc. December 2014
Perspective on DG/DER
©PowerServices, Inc. December 2014
Why Solar? Why Now?
©PowerServices, Inc. December 2014
18
Solar Setting Growth Records
• From now until the end of 2016 “an unprecedented boom”
• July 2015 – Dec. 2016 Forecasts up 18 GW, more than the cumulative capacity built as of June 2015
• 2017 – 2019 Uncertainty over growth
• After 2020 Installed costs reach new lows “driving a new era of growth”
Source: Q2 2015 US Solar Market Insight Report
©PowerServices, Inc. December 2014 1
9
Overview
How to?• Design• Construct
What to?• Consider• Evaluate• Focus Upon
©PowerServices, Inc. December 2014 2
0
Overview
Dynamic Environment• Regulatory Mandates• Subsidies• Risk• Venture Capitalist• Ratepayers
©PowerServices, Inc. December 2014 2
1
Overview
Renewable Type• Wind• Solar• Biomass• Hydro
• Solar is attainable where others are not
©PowerServices, Inc. December 2014
INTERCONNECTION
©PowerServices, Inc. December 2014 2
3
InterconnectionUtility Concerns• Electric power distribution
systems designed for one-way operation
• Personnel safety and grid stability are dominant concerns
• Utilities reluctant to rely on customer-supplied protective relaying schemes that are not well-known
©PowerServices, Inc. December 2014 2
4
InterconnectionCustomer Concerns• Interconnection costs (e.g.,
engineering and system impact studies, system upgrades) can be disincentive for smaller-sized projects
• Most requirements not understood by customer, may appear restrictive
• Manufacturer, customer, and utility DG activities not frequently coordinated
©PowerServices, Inc. December 2014 2
5
InterconnectionPrimary Safety Concerns
• Utility protection scheme Impact on circuit breakers, reclosers,
and fuses Can impact clearing of faults
• Creation of unintentional island Lineman sees grid supply open, and
believes feeder is de-energized
©PowerServices, Inc. December 2014 2
6
InterconnectionThe Application Process
• Steps to operate in parallel with the distribution utility
• Location, technical and design parameters
• Operational and maintenance procedures
• Systemic approach of study
©PowerServices, Inc. December 2014 2
7
InterconnectionQueue
• Why?
• Impact to Municipality
• Purpose
• Have a process
©PowerServices, Inc. December 2014 2
8
InterconnectionApplication Process
©PowerServices, Inc. December 2014 2
9
InterconnectionScreening Process
©PowerServices, Inc. December 2014 3
0
InterconnectionStudy Process • To be used when DG project:
Is larger than __ MW but no larger than __ MW
Is not certified, or Did not pass the Screening Process
• Consists of: Minimum engineering review System Impact Study Facilities Study
©PowerServices, Inc. December 2014 3
1
InterconnectionStudy Process
©PowerServices, Inc. December 2014 3
2
InterconnectionInformation Requirements and Study Fees• Equipment is “pre-certified”• Capacity is 500 kW or less• Equipment is designed to export
no more than 15% of total load on feeder (based on most recent peak load demand) and
• Equipment will contribute not more than 25% of maximum potential short circuit current of feeder
©PowerServices, Inc. December 2014 3
3
InterconnectionUnintentional Islanding• DR is certified to pass applicable non-
islanding test
• DR installation contains reverse or minimum power flow protection
• DR contains other non-islanding means: Forced frequency or voltage shifting Transfer trip
©PowerServices, Inc. December 2014 3
4
InterconnectionIslanding
©PowerServices, Inc. December 2014 3
5
InterconnectionGrid Abnormalities• Four types:
Underfrequency – below 59 Hz Overfrequency – above 61.5 Hz Undervoltage – below ANSI Range B
< 88% PU Overvoltage – above ANSI Range B
>110% PU• During underfrequency events
Essential for DER assets to remain connected to support bulk system
Support of distribution system important, but secondary
©PowerServices, Inc. December 2014 3
6
InterconnectionGrid Abnormalities
• During overvoltage and overfrequency events:
DER should self regulate and attempt to reduce voltage or frequency
©PowerServices, Inc. December 2014 3
7
InterconnectionWhy is Ride Through Needed?
• Ride through to avoid cascade failure during severe underfrequency events and undervoltage events
• DER should remain online until local load shedding schemes have activated
• If DER is lost ahead of load, grid instability may quickly worsen and possibly lead to cascade failure
©PowerServices, Inc. December 2014 3
8
InterconnectionHigh Voltage Ride Through
• Reduce generation quickly Limit magnitude and duration
without tripping
• Bring DER back online quickly to minimize grid disruptions
©PowerServices, Inc. December 2014 3
9
InterconnectionLow Voltage Ride Through
• Improve system stability
Minimize sudden loss of DER during short duration low voltage events
Avoid desensitization of overcurrent protection during feeder faults
©PowerServices, Inc. December 2014 4
0
InterconnectionHigh Frequency Ride Through
• Reduce generation
Quickly to limit magnitude and duration
Bring DER back only quickly following short duration high frequency events to minimize disruptions
©PowerServices, Inc. December 2014 4
1
InterconnectionLow Frequency Ride Through
• Reduce Chances of Cascade Failures of Bulk System
Miminize sudden loss of DER during low frequency event
Coordinate frequency trip behavior of DER with utility frequency load shedding schemes
©PowerServices, Inc. December 2014 4
2
InterconnectionOperating Modes
• Historically, inverter based DER has operated only in one of two modes Normal Operation – full available
current Tripped – offline
• Ride through requirements new mode – “Momentary Cessation” Mode in which DER has ceased to
energize grid but has not tripped
©PowerServices, Inc. December 2014 4
3
InterconnectionOperating Modes
• Difference between momentary cessation and tripped determined by: Duration of excursion Criteria for “Return to Service” Ramp rated limitations during
“Return to Service”
©PowerServices, Inc. December 2014 4
4
InterconnectionReal & Reactive Power Control Functions• Real Power Control
Commanded Max Power Volt/Watt Frequency/Watt
• Reactive Power Control Commanded VAR Fixed PF
©PowerServices, Inc. December 2014 4
5
InterconnectionRegulatory Issues• IEEE 1547 / 1547.1 revision
considers ride through 1547 currently under revision, and
adding ride through requirements When 1547 revision complete,
1547.1 test procedures to be developed
• UL 1741 to address ride through, real / reactive power functions, and new advanced islanding as optional tests Continuing updates
©PowerServices, Inc. December 2014 4
6
Interconnection
NERC/RF/PJM
BES
©PowerServices, Inc. December 2014
IMPACT
©PowerServices, Inc. December 2014 4
8
Impact
©PowerServices, Inc. December 2014 5
0
Impact
©PowerServices, Inc. December 2014 5
1
Impact
©PowerServices, Inc. December 2014 5
2
ImpactOverall Trends
• Residential systems accounted for 94% of individual installations
• Residential systems accounted for only 19% of PV capacity installed
©PowerServices, Inc. December 2014 5
3
Impact
©PowerServices, Inc. December 2014 5
4
Impact
©PowerServices, Inc. December 2014
FINANCIALISSUES
©PowerServices, Inc. December 2014 5
6
Financial Issues
©PowerServices, Inc. December 2014
Financial Issues
Before De-regulation• Customer Charge• Energy/Demand• Facilities
After De-regulation• Customer Charge• Wires Charge• Commodity
Charge, etc. (provider last resort)
• Facilities
57
Previously…
Retail Rate Determinants
©PowerServices, Inc. December 2014
Financial Issues
Renewables Impact
All previously included Before and After De-regulation, Plus:• Backstand• Net Metering• Buy All, Sell All• Avoided Cost• On Peak/Off Peak
58
Now…
Retail Rate Determinants
©PowerServices, Inc. December 2014 5
9
Financial IssuesNet Meter• Generate own needs and serve
grid (retail)• Bank credits
Costs / Rate Recovery
Buy All / Sell All Retail Rate Avoided Cost
©PowerServices, Inc. December 2014 6
0
Financial Issues
Plans to install solar on 1,000 retail stores by 2020 (25%)
Average Annual Increase $185.00
Wal-Mart
California Utility Customer
©PowerServices, Inc. December 2014 6
1
Financial Issues
Distribution System
1/0 ACSR – 3Ø
(POD)
©PowerServices, Inc. December 2014 6
2
Financial Issues
Generation Added
1/0 ACSR – 3Ø
(POD)
©PowerServices, Inc. December 2014 6
3
Financial Issues
Facilities Charge
Facilities Charge
1/0 ACSR – 3Ø
(POD)
©PowerServices, Inc. December 2014 6
4
Financial Issues
Electric System Impact Fee
Facilities Charge
Electric System Impact Fee
1/0 ACSR – 3Ø
(POD)
©PowerServices, Inc. December 2014 6
5
Financial Issues
Total Fees???
Facilities Charge
Electric System Impact Fee
3,000,000kWh x $0.005/kWh = $15,000/yr.
$75,000 – Capital Cost@1% = $750/month= $9,000/yr.
1/0 ACSR – 3Ø
(POD)
©PowerServices, Inc. December 2014 6
6
Financial Issues
“We don’t have to pay this fee to the IOU”
©PowerServices, Inc. December 2014 6
7
Financial Issues
Inverter Cost and Reliability Impacts
©PowerServices, Inc. December 2014
CASE STUDIES
©PowerServices, Inc. December 2014 6
9
Case StudiesLoad Shapes
©PowerServices, Inc. December 2014 7
0
Case StudiesLoad Shapes
18,690,872
18,031,518
24,126,526
Annual kWh
©PowerServices, Inc. December 2014
Case Studies
• Duke Energy Carolinas Background
• N.C. Senate Bill 3 (SB3)• Established renewable energy goals
for N.C. utilities• Included service areas of Duke
Energy• Starting at 3% in 2012 and leveling
off at 12.5% in 2020• Encouraged utilities to meet goal
using energy from variety of renewable resources
• Solar photovoltaic projects have dominated Duke Energy’s efforts to comply7
1
©PowerServices, Inc. December 2014
Case Studies
• Duke Energy Carolinas Goal to determine impacts of solar
PV on ancillary services, generation production cost, and power flows and losses
Three scenarios simulated• Compliance solely with goals and
schedules of SB3• Modest increases over SB3 goals• More rapid penetration of PV
Penetration evaluated ranged from 673 MW to 6800 MW (2% to 20% of peak load)7
2
©PowerServices, Inc. December 2014
Case Studies
• Duke Energy Carolinas Findings
• Net load (load minus PV production) variability increases with PV penetration
• PV penetration increasing to 20% of peak load, system day-ahead planning reserve requirements increase 30% compared to values without PV
• Regulation reserve requirements increase to 140%
73
©PowerServices, Inc. December 2014
Case Studies
• Duke Energy Carolinas Findings
Transmission• PV supplies, real and reactive power, result
in an increase in voltage magnitude proportional to amount of PV output at sub-transmission buses
• Most affected areas in Duke Energy system in 44 kV systems – violated upper limit in spring and fall during light-load conditions
• Amount of energy loss reduction in transmission network due to distributed PV dependent upon many factors
• Transmission loss reduction due to PV between 2.6 and 5.7% as percentage of PV output
74
©PowerServices, Inc. December 2014
Case Studies
• Duke Energy Carolinas Findings
Distribution• On average, feeders show reduction in
losses, particularly during summer season• Equipment overloads tended to decrease
due to offset of local power flow by local generation
• A few cases experienced additional overloads mainly due to reverse power flows
• Feeders servicing PV installations experienced greater voltage fluctuations, and consequently more control actions voltage regulation devices
• Increased regulator operations reduce asset life
75
©PowerServices, Inc. December 2014
Case Studies
• California DG Goal Governor’s goal of adding 12,000
MW of DG to grid by 2020 creates technical challenge
At this scale, Distributed Energy Resource systems have potential to provide significant environmental and financial benefits
Achieving goal will require fundamental paradigm shift in technical operation of distribution system
76
©PowerServices, Inc. December 2014
Case Studies
• California DG Goal Core technical challenge:
• DER systems interconnected to distribution grids designed for one-way flow of power
• DG requires two-way power flows dispersed throughout system
• Source is renewable energy, where generation is intermittent
77
©PowerServices, Inc. December 2014
Case Studies
• California DG Goal Anti-islanding protection
• Current Rule 21 identifies anti-islanding protection requirements in IEEE 1547, including clearing times
• IEEE 1547 does not permit voltage ride-through and frequency ride-through functions
• While Rule 21 requirement remain the same, SIWG proposes islanding settings be changed
• Proposed expansion of high and low voltage and frequency protection limits permit I-DER systems to ride-through temporary voltage or frequency anomalies
78
©PowerServices, Inc. December 2014
Case Studies
• California DG Goal
79
©PowerServices, Inc. December 2014
Case Studies
• California DG Goal
80
©PowerServices, Inc. December 2014
Case Studies• Massachusetts DG Goal
Governor and Energy and Environmental Affairs Secretary celebrate 250 MW of solar energy installed
Reached Patrick-Murray Administration goal 4 years early
Announced new goal of 1,600 MW by 2020
81
©PowerServices, Inc. December 2014
Case Studies• Massachusetts DG Goal
Utility proposed smart inverter technology program to Massachusetts DPU• 20 MW at approx. $100M from
ratepayers• Three categories
• 60-200 kW• 201-500 kW• 501-1,000 kW
82
©PowerServices, Inc. December 2014
Case Studies• Massachusetts DG Goal
DC Rating: 1,000 kW DC Rating: 1,000 kW Array Azimuth: 180.0 Array Azimuth: 225.0
83
AC Energy (kWh) AC Energy (kWh)Month from 1 MW Month from 1 MW
1 83583 1 683702 98004 2 852333 114805 3 1028944 111403 4 1060835 119033 5 1155056 112682 6 1130687 120227 7 1164138 122071 8 1172019 110201 9 9883610 107035 10 9261111 72354 11 6085012 72282 12 72282
Year 1243680 Year 1149346
©PowerServices, Inc. December 2014
Case Studies• Massachusetts DG Goal
84
©PowerServices, Inc. December 2014
Case Studies• Massachusetts DG Goal
85
©PowerServices, Inc. December 2014
Case Studies• Massachusetts DG Goal
86
©PowerServices, Inc. December 2014
Case Studies• Massachusetts DG Goal
87
©PowerServices, Inc. December 2014
CONCLUSION
©PowerServices, Inc. December 2014
ConclusionDER– It’s Coming-It’s Here, Be Prepared• DG presents opportunities and risks for
electric utilities• Environmental benefits• May help utilities avoid ancillary
service costs• May help customers reduce electric
bills and over long term save money• Challenges
Under-recovery of costs Increased difficulties in operating electric
grid Safety issues Cross-class subsidization
89
©PowerServices, Inc. December 2014
ConclusionDER– It’s Coming-It’s Here, Be Prepared• Municipalities situated to deal with DG
Independence of utilities offers opportunity to develop more equitable rates
Do not stifle development of resources or unduly burden non-DG customers
May face pressure to encourage development of DG resources at expense of revenue and operational stability
Fully understand impact of distributed resources on your systems and explain impacts to your communities
Public outreach essential90
©PowerServices, Inc. December 2014
Conclusion
91
Municipalities should prepare
for potential outcomes from DG/DER integration
©PowerServices, Inc. December 2014
1616 E. Millbrook Road, Suite 210Raleigh, North Carolina 27609Toll-Free: (866) 231-6610Phone: (919) 256-5900Fax: (919) 256-5939