Introduction The Ulva Ferry Community Background USCA/ School Closure Threat Local Development Officers Community Consultation/ Community Plan Initial Housing Proposals Current Scheme Housing Need Funding Design and Development Advice and Support Allocations Maintenance and Governance Challenges and Obstacles Ulva Ferry Housing Project
14
Embed
Introduction The Ulva Ferry Community Background USCA/ School Closure Threat Local Development Officers Community Consultation/ Community Plan Initial.
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Introduction The Ulva Ferry Community
Background USCA/ School Closure Threat
Local Development Officers Community Consultation/ Community Plan Initial Housing Proposals
Current SchemeHousing NeedFundingDesign and DevelopmentAdvice and SupportAllocationsMaintenance and GovernanceChallenges and Obstacles
Ulva Ferry Housing Project
The Ulva Ferry Community
Ulva Ferry Housing Project
Ulva School
Ulva Ferry Housing ProjectThe Ulva Ferry Community
Achleck
Ulva Ferry Housing Project
Ulva Ferry Housing ProjectHousing Need
USCA Housing List:
Familes 15Couples 8Individuals 7Total 76
Ulva Ferry Housing ProjectFunding
Land Purchase
Scottish Land Fund
Capital (includes all professional fees) £96,760Revenue (part time project manager for 2 years) £45,000
Total £141,760
Ulva Ferry Housing ProjectFunding
Ulva Ferry Housing ProjectFundingProject funding
Argyll and Bute Council RHDF - £180,000Bank/ Building Society Loan - £95,000Sale of Gifted Plot - £35,000Local Fundraising - >£1,005
Ulva Ferry Housing ProjectDesign and Development
Ulva Ferry Housing ProjectDesign and Development
Ulva Ferry Housing ProjectExperience and Advice
Rural Housing ServiceHighland Small Communities Housing TrustKnoydart FoundationIona Housing Partnership
Highlands and Islands EnterpriseArgyll and Bute Council WHHA
MICT
Ulva Ferry Housing ProjectOngoing Maintenance and Governance
Maintenance Fund Included as part of the budget
Governance by Ulva Ferry Housing Partnership-
2 Directors of MICT2 USCA members1 Tenant representative
Day to day management supported by WHHA
Ulva Ferry Housing ProjectChallenges
Collapse of initial refurbishment schemeRequirement for Constituted legal entityUp front Funding Need for paid management due to complexities and workload