Page 1: © 2008 Eventure Events. All rights reserved. Capital Costing Using the PM, CS, IM and BI Modules Jared MartinRon Wagner.

© 2008 Eventure Events. All rights reserved.

Capital Costing Using the PM, CS,IM and BI Modules

Jared Martin Ron Wagner

Page 2: © 2008 Eventure Events. All rights reserved. Capital Costing Using the PM, CS, IM and BI Modules Jared MartinRon Wagner.

Agenda

• Introductions

• Corporate and Project Background

• Business Process Overview

• Solution Overview

• Key Lessons Learned

Page 3: © 2008 Eventure Events. All rights reserved. Capital Costing Using the PM, CS, IM and BI Modules Jared MartinRon Wagner.

Consumers Energy and Michigan

LudingtonLudingtonPumpedPumpedStorageStorage

B C CobbB C Cobb

J H CampbellJ H Campbell

D E KarnD E KarnJ C WeadockJ C Weadock

J R WhitingJ R Whiting

MioMioAlconaAlcona

CookeCooke

FooteFooteLoudLoud

5 Channels5 ChannelsHodenpylHodenpylTippyTippy

RogersRogersHardyHardy

CrotonCroton

WebberWebber

AlleganAllegan

Electric

Gas

Combination

Storage field

Dams

Generation

Pumped storage

ZeelandZeeland

• Serving Michigan families and businesses since 1886

• We provide electric and natural gas service to 6.5 million people

• 8,000 employees

• Serving all 68 Lower Peninsula counties

• Company motto: “Count on Us”

Page 4: © 2008 Eventure Events. All rights reserved. Capital Costing Using the PM, CS, IM and BI Modules Jared MartinRon Wagner.

CEA Project at a Glance

• Comprehensive legacy platform replacement project (over 112 legacy systems retired)

• Included SAP IS-U (CCS, CS, FERC), FI, CO, MM, SD, HR, PM, IM and PS

• All modules all business units “big-bang” deployment approach

• Included “downgrade” of latest SAP functionality – compatible unit design estimating for mass plant and mobile device integration

• Live with ECC 6.0 on July 1, 2008

Page 5: © 2008 Eventure Events. All rights reserved. Capital Costing Using the PM, CS, IM and BI Modules Jared MartinRon Wagner.

Systems Interfaced

• Fleet Fuel Management System

• File Index Routing and Management (FIRM)

• FRS

• GEM/CAP

• Lan File Manager

• MISSDIG

• Neptune

• PCCMS – Detail/Pac

• PCCMS – ICAD

• PCCMS – CAD

• PowerPlant

• SIMS Data Extract for OMAR

• SIMS WEB

Page 6: © 2008 Eventure Events. All rights reserved. Capital Costing Using the PM, CS, IM and BI Modules Jared MartinRon Wagner.

Capital Business Process Scope

• Scope of implementation included all aspects of capital costing and management

– Annual budgeting, program planning and actual cost tracking

– Work order setup, charging and settlement

– Asset unitization

• Strategic Enterprise Management (SEM) and other advanced functionality not in scope for initial rollout

• Limited use of Investment Management (IM), no appropriation requests – maintained legacy functionality for this area

Page 7: © 2008 Eventure Events. All rights reserved. Capital Costing Using the PM, CS, IM and BI Modules Jared MartinRon Wagner.

Design Requirements and Challenges

Varied Requirements with Conflicting Goals

• Work order setup and charging process must be tailored to the way work is performed and managed in the field, not to satisfy accountants’ needs to split CAP, COR and O&M

• Need to satisfy internal “program” management buckets and FERC accounting rules at same time

• Need monthly forecasting at a detailed cost element level – IM has forecasting capability but at a higher level

– For the scope of the project, monthly cash flows were not available

Page 8: © 2008 Eventure Events. All rights reserved. Capital Costing Using the PM, CS, IM and BI Modules Jared MartinRon Wagner.

Design Overview

Investment Management (IM) Module

Project Systems (PS) Module

Controlling (CO) Module for Internal Orders

Plant Maintenance (PM) Module for EAM Work Orders

PSPIP-AAA-XXXX

PSPIP-AAA-XXXX-XX

PSPIP-AAA-XXXX-XX

PSPIP-AAA-XXXX-XX

Program Shadow Project

Program IPAAA-XXXX

Program PositionIPAAA-XXXX-XX

Program PositionIPAAA-XXXX-XX

Program PositionIPAAA-XXXX-XX

WBSEAA-XXXXX-X

WBSEAA-XXXXX-X-XX

WBSE AA-XXXXX-X-XX

WBSEAA-XXXXX-X

Superior Order

Subordinate orderSubordinate order

Program Definition

Work Orders, Superior &

Subordinate

Project Definition: AA-XXXXX

Order

- Operations- tasks

Page 9: © 2008 Eventure Events. All rights reserved. Capital Costing Using the PM, CS, IM and BI Modules Jared MartinRon Wagner.

Detailed Design Flow Diagram:Focus on Order Creation and Management

PS: Example ProjectPS: T&D Program Shadow Project

CAP COR O&M

New Construction

Reliability Capacity

Distribution Lines Cap

DS DT

O&MAssociated

with Construction

Blanket Project

Field Manager #1

Field Manager #2

A% Budget

B% Budget

C% Budget

Work Order 1 Contr

Work Order 2

In House

WO Assignment

WO AssignmentAsset

Accounting

WO Actual Costs and Asset Info w/

Allocation to CAP, COR, O&M by

Functional Class

WO costs broken down by CAP, COR, and O&M by cost element.

The Program Structure is

duplicated in PS where Monthly

Planning occurs using versions

such as 200, 300, and 408.

IM: ProgramsAnnual Budget

O&M 606

COR 605

CAP 604

Plan version“Actuals”

O&M 603

COR 602

CAP 601

Plan versionPlan costs

BI: All Projs plans version 604, 605, & 606 (“Actual”

COR, CAP, O&M) are aggregated as

a Plan in the shadow program

project

Allows Plan vs. “Actual” Comparison at the lowest Level WBS Element.

HQ HQ

OH UG

Page 10: © 2008 Eventure Events. All rights reserved. Capital Costing Using the PM, CS, IM and BI Modules Jared MartinRon Wagner.

• Order types segregated by major work type and business unit, e.g. Electric, Gas, Generation, Fleet, and Facilities– Order types further broken down into Capital and O&M

– Example: ECNC – Electric capital construction

CORR – Generation corrective maintenance

• Use of maintenance activity types and priority codes to drive assignment to proper program budgets– MAT example: NLU – New Lines Underground

– Priority example: Residential Line

• Two major processing types – one process for orders with design documents (CUs for mass property) and another process for non-CU orders for location specific plant

Order Creation and Management

Page 11: © 2008 Eventure Events. All rights reserved. Capital Costing Using the PM, CS, IM and BI Modules Jared MartinRon Wagner.

Order Creation and Management: Compatible Units Orders

Page 12: © 2008 Eventure Events. All rights reserved. Capital Costing Using the PM, CS, IM and BI Modules Jared MartinRon Wagner.

Order Creation and Management: Non Compatible Units Orders

Page 13: © 2008 Eventure Events. All rights reserved. Capital Costing Using the PM, CS, IM and BI Modules Jared MartinRon Wagner.

Order Creation and Management

• Orders determine Cap/COR/O&M splits

• Program structures in IM and PS are used to manage capital “functional” budgets

• Assignment of orders to proper program WBS for actual to budget comparison, is automatic and driven by order type, MAT, priority code and plant

• At order creation, the job estimates determine the split between capital, removal and expense

Page 14: © 2008 Eventure Events. All rights reserved. Capital Costing Using the PM, CS, IM and BI Modules Jared MartinRon Wagner.

Order Creation and Management: Work Order Life Cycle

• After creation, orders are worked and completed in the field (many are updated via mobile device)

• For CU orders, as-built documents are created when there are changes between estimated and installed assets

• Similar as-built process for non-CU orders, but data is maintained directly on PM order instead of CU as-built document

• Costs are charged only to the PM/CS order and settled to asset G/L accounts or cost centers

• Process is flexible enough to allow for changes to expenditure type distribution changes and asset information changes

– Allows for total transfer of actuals from one order to another if corrections are required. This has the result of changing the entire costing distribution among Capital, COR and O&M

Page 15: © 2008 Eventure Events. All rights reserved. Capital Costing Using the PM, CS, IM and BI Modules Jared MartinRon Wagner.

Detailed Design Flow Diagram:Focus on Projects and Programs

PS: Example ProjectPS: T&D Program Shadow Project

CAP COR O&M

New Construction

Reliability Capacity

Distribution Lines Cap

DS DT

O&MAssociated

with Construction

Blanket Project

Field Manager #1

Field Manager #2

A% Budget

B% Budget

C% Budget

Work Order 1 Contr

Work Order 2

In House

WO Assignment

WO AssignmentAsset

Accounting

WO Actual Costs and Asset Info w/

Allocation to CAP, COR, O&M by

Functional Class

WO costs broken down by CAP, COR, and O&M by cost element.

The Program Structure is

duplicated in PS where Monthly

Planning occurs using versions

such as 200, 300, and 408.

IM: ProgramsAnnual Budget

O&M 606

COR 605

CAP 604

Plan version“Actuals”

O&M 603

COR 602

CAP 601

Plan versionPlan costs

BI: All Projs plans version 604, 605,

& 606 (PP “Actual” COR, CAP, O&M) are aggregated as

a Plan in the shadow program

project

Allows Plan vs. “Actual” Comparison at the lowest Level WBS Element.

HQ HQ

OH UG

Page 16: © 2008 Eventure Events. All rights reserved. Capital Costing Using the PM, CS, IM and BI Modules Jared MartinRon Wagner.

Projects and Programs:Rollup of Capital and O&M Costs

• PS Project blanket structures are setup according to a hierarchy driven by the business needs, rather than accounting or FERC requirements

– Geography, Org Structure and work activity

• Bottom Level: Work activity (e.g. UG New Business Con)

• Next Level: Geography (e.g. West Region)

• Next Level: Field Manager

• Non-blanket (specific) project structures are setup according to individual project management needs, usually project phases

• Orders are always assigned to lowest level in PS structure

Page 17: © 2008 Eventure Events. All rights reserved. Capital Costing Using the PM, CS, IM and BI Modules Jared MartinRon Wagner.

Projects and Programs: Budgeting

• All projects, whether blanket or specific, are attached by the highest level WBS element to a lowest level IM program position

• IM structure is driven by overall program budgets, and contain buckets of dollars for activities across the corporation

• IM is primarily a rollup structure, as budget life-cycle features such as appropriation requests have not been implemented as of yet

• Limited use of budget distribution functionality– Budget entered at highest level WBS element of projects

• Encountered challenges using IM for forecasting, due to CMS detail requirements

– Monthly cash flows, cost elements/accounts, etc.

Page 18: © 2008 Eventure Events. All rights reserved. Capital Costing Using the PM, CS, IM and BI Modules Jared MartinRon Wagner.

Detailed Design Flow Diagram:Focus on Program Shadow Projects

PS: Example ProjectPS: T&D Program Shadow Project

CAP COR O&M

New Construction

Reliability Capacity

Distribution Lines Cap

DS DT

O&MAssociated

with Construction

Blanket Project

Field Manager #1

Field Manager #2

A% Budget

B% Budget

C% Budget

Work Order 1 Contr

Work Order 2

In House

WO Assignment

WO AssignmentAsset

Accounting

WO Actual Costs and Asset Info w/

Allocation to CAP, COR, O&M by

Functional Class

WO costs broken down by CAP, COR, and O&M by cost element.

The Program Structure is

duplicated in PS where Monthly

Planning occurs using versions

such as 200, 300, and 408.

IM: ProgramsAnnual Budget

O&M 606

COR 605

CAP 604

Plan version“Actuals”

O&M 603

COR 602

CAP 601

Plan versionPlan costs

BI: All Projs plans version 604, 605,

& 606 (PP “Actual” COR, CAP, O&M) are aggregated as

a Plan in the shadow program

project

Allows Plan vs. “Actual” Comparison at the lowest Level WBS Element.

HQ HQ

OH UG

`

Page 19: © 2008 Eventure Events. All rights reserved. Capital Costing Using the PM, CS, IM and BI Modules Jared MartinRon Wagner.

Shadow Project Approach PSPSP’s

• Solution to meet detailed forecasting requirements – use of a “shadow project” in PS

• Shadows used to simulate programs for monthly forecasting and reporting

• Shadow projects also allowed CMS to capture all actuals on a single order, but split them into component parts required for management reporting – Capital, Cost of Removal, O&M

Page 20: © 2008 Eventure Events. All rights reserved. Capital Costing Using the PM, CS, IM and BI Modules Jared MartinRon Wagner.

Detailed Design Flow Diagram:Focus on Rollups for Plan and Actual

PS: Example ProjectPS: T&D Program Shadow Project

CAP COR O&M

New Construction

Reliability Capacity

Distribution Lines Cap

DS DT

O&MAssociated

with Construction

Blanket Project

Field Manager #1

Field Manager #2

A% Budget

B% Budget

C% Budget

Work Order 1 Contr

Work Order 2

In House

WO Assignment

WO AssignmentAsset

Accounting

WO Actual Costs and Asset Info w/

Allocation to CAP, COR, O&M by

Functional Class

WO costs broken down by CAP, COR, and O&M by cost element.

The Program Structure is

duplicated in PS where Monthly

Planning occurs using versions

such as 200, 300, and 408.

IM: ProgramsAnnual Budget

O&M 606

COR 605

CAP 604

Plan version“Actuals”

O&M 603

COR 602

CAP 601

Plan versionPlan costs

BI: All Projs plans version 604, 605,

& 606 (PP “Actual” COR, CAP, O&M) are aggregated as

a Plan in the shadow program

project

Allows Plan vs. “Actual” Comparison at the lowest Level WBS Element.

HQ HQ

OH UG

`

Page 21: © 2008 Eventure Events. All rights reserved. Capital Costing Using the PM, CS, IM and BI Modules Jared MartinRon Wagner.

Versions and Relationships

• Used three plan versions for tracking planned/budgeted costs – one each for Capital, Cost of Removal, and Expense

• Used three plan versions to compare to the plan – in which “actual” costs were populated

• Available for Program Shadow Projects and functional projects

Page 22: © 2008 Eventure Events. All rights reserved. Capital Costing Using the PM, CS, IM and BI Modules Jared MartinRon Wagner.

Detailed Design Flow Diagram:Recap

PS: Example ProjectPS: T&D Program Shadow Project

CAP COR O&M

New Construction

Reliability Capacity

Distribution Lines Cap

DS DT

O&MAssociated

with Construction

Blanket Project

Field Manager #1

Field Manager #2

A% Budget

B% Budget

C% Budget

Work Order 1 Contr

Work Order 2

In House

WO Assignment

WO AssignmentAsset

Accounting

WO Actual Costs and Asset Info w/

Allocation to CAP, COR, O&M by

Functional Class

WO costs broken down by CAP, COR, and O&M by cost element.

The Program Structure is

duplicated in PS where Monthly

Planning occurs using versions

such as 200, 300, and 408.

IM: ProgramsAnnual Budget

O&M 606

COR 605

CAP 604

Plan version“Actuals” from PP

O&M 603

COR 602

CAP 601

Plan versionPlan costs from PP

BI: All Projs plans version 604, 605,

& 606 (PP “Actual” COR, CAP, O&M) are aggregated as

a Plan in the shadow program

project

Allows Plan vs. PP “Actual” Comparison at the lowest Level WBS Element.

HQ HQ

OH UG

Page 23: © 2008 Eventure Events. All rights reserved. Capital Costing Using the PM, CS, IM and BI Modules Jared MartinRon Wagner.

Reporting: Bringing it all Together in BI

• BI queries were necessary to bring together actuals on orders and PS investment measures, with plans and actuals on shadow projects

• Standard PS reporting is used by supervisors and project managers for actual cost tracking and project management

• Budget analysts use IM and BI reports for overall program picture and forecasting reports

Page 24: © 2008 Eventure Events. All rights reserved. Capital Costing Using the PM, CS, IM and BI Modules Jared MartinRon Wagner.

Reporting: BI Query Selection Screen

Page 25: © 2008 Eventure Events. All rights reserved. Capital Costing Using the PM, CS, IM and BI Modules Jared MartinRon Wagner.

Reporting: BI Query Sample Output

Page 26: © 2008 Eventure Events. All rights reserved. Capital Costing Using the PM, CS, IM and BI Modules Jared MartinRon Wagner.

Lessons Learned

• You CAN satisfy the needs of all:– Field workers able to manage entire job on a single order

– Budget analysts can use a single report to analyze all costs at a detail/monthly level

– Management can control and manage costs at a program or specific project level

• Some minor enhancements are necessary but NO custom code (SAP modifications) was used anywhere

• Include all of the stakeholders in the design process up front, and then heavily involve them in the testing phase

• Future goals are to expand use of IM functionality and take advantage of more standard SAP overhead costing

Page 27: © 2008 Eventure Events. All rights reserved. Capital Costing Using the PM, CS, IM and BI Modules Jared MartinRon Wagner.