© 1997 Prentice-Hall, © 1997 Prentice-Hall, Inc. Inc. 12 - 12 - 1 1 Principles of Principles of Operations Management Operations Management Aggregate Scheduling Aggregate Scheduling Chapter 12 Chapter 12
© 1997 Prentice-Hall, Inc.© 1997 Prentice-Hall, Inc.
12 - 12 - 11
Principles of Principles of Operations ManagementOperations Management
Principles of Principles of Operations ManagementOperations Management
Aggregate SchedulingAggregate SchedulingChapter 12Chapter 12
© 1997 Prentice-Hall, Inc.© 1997 Prentice-Hall, Inc.
12 - 12 - 22
Learning ObjectivesLearning ObjectivesLearning ObjectivesLearning Objectives
Describe planningDescribe planning Distinguish the types of plansDistinguish the types of plans Define aggregate schedulingDefine aggregate scheduling Relate aggregate scheduling to the Relate aggregate scheduling to the
overall planning processoverall planning process Explain aggregate scheduling optionsExplain aggregate scheduling options Develop aggregate schedulesDevelop aggregate schedules
© 1997 Prentice-Hall, Inc.© 1997 Prentice-Hall, Inc.
12 - 12 - 33
Thinking ChallengeThinking ChallengeThinking ChallengeThinking Challenge
You’ve started a You’ve started a newnew company. You’ve company. You’ve developed 2 production plans:developed 2 production plans:
MonthMonth ForecastForecast Plan 1Plan 1 Plan 2Plan 2JanJan 900 900 900900 800800FebFeb 700 700 700700 800800MarMar 800800 800800 800800
You estimate You estimate 1 worker 1 worker can make can make 100 units100 units per monthper month. Which plan do you use? How . Which plan do you use? How many workers do you hire? How do you many workers do you hire? How do you meet demand? meet demand?
AloneAlone GroupGroup Class Class
© 1997 Prentice-Hall, Inc.© 1997 Prentice-Hall, Inc.
12 - 12 - 44
PlanningPlanningPlanningPlanning
Setting goals & objectivesSetting goals & objectives Example: Meet demand within the limits Example: Meet demand within the limits
of available resources at the least costof available resources at the least cost
Determining steps to achieve goalsDetermining steps to achieve goals Example: Hire more workersExample: Hire more workers
Setting start & completion datesSetting start & completion dates Example: Begin hiring in Jan.; finish, Mar.Example: Begin hiring in Jan.; finish, Mar.
Assigning responsibility Assigning responsibility
© 1997 Prentice-Hall, Inc.© 1997 Prentice-Hall, Inc.
12 - 12 - 55
Types of PlansTypes of PlansTypes of PlansTypes of Plans
TodayToday 3 months3 months 1 year1 year 5 years5 years
Long-Range Facility location
Long-Range Facility location
Intermediate-Range Aggregate plans
Intermediate-Range Aggregate plans
Short-Range Dispatching
Short-Range Dispatching
Mgt LevelMgt Level
HighHigh
LowLow
Top Top ExecutivesExecutives
SupervisorsSupervisors
Operations Operations ManagersManagers
18 months18 months
© 1997 Prentice-Hall, Inc.© 1997 Prentice-Hall, Inc.
12 - 12 - 66
Aggregate Scheduling Aggregate Scheduling Aggregate Scheduling Aggregate Scheduling
Provides the quantity & timing of Provides the quantity & timing of production for intermediate futureproduction for intermediate future Usually 3 to 18 months into futureUsually 3 to 18 months into future
Combines (‘aggregates’) productionCombines (‘aggregates’) production Often expressed in common unitsOften expressed in common units
Example: Hours, dollars, equivalents Example: Hours, dollars, equivalents (e.g., FTE students)(e.g., FTE students)
Involves capacity & demand variablesInvolves capacity & demand variables
© 1997 Prentice-Hall, Inc.© 1997 Prentice-Hall, Inc.
12 - 12 - 77
Relationships of Relationships of Aggregate ScheduleAggregate Schedule
Relationships of Relationships of Aggregate ScheduleAggregate Schedule
Forecast &Firm Orders
MaterialRequirements
Planning
AggregateProduction
Planning
ResourceAvailability
MasterProductionScheduling
ShopFloor
Schedules
CapacityRequirements
PlanningRealistic?
Yes
No, modify CRP, MRP, or MPS
Work forceInventorySubcontractors
Forecast &Firm Orders
MaterialRequirements
Planning
AggregateProduction
Planning
ResourceAvailability
MasterProductionScheduling
ShopFloor
Schedules
CapacityRequirements
PlanningRealistic?
Yes
No, modify CRP, MRP, or MPS
Work forceInventorySubcontractors
© 1997 Prentice-Hall, Inc.© 1997 Prentice-Hall, Inc.
12 - 12 - 88
Aggregate Schedule Aggregate Schedule ExampleExample
Aggregate Schedule Aggregate Schedule ExampleExample
Aggregate Schedule:Aggregate Schedule:MonthMonth JanJan FebFeb MarMar AprApr MayMayNo. of ChipsNo. of Chips 600600 650650 620620 630630 640640
Master Production Schedule:Master Production Schedule:MonthMonth JanJan FebFeb MarMar AprApr MayMayPentiumPentium 300300 200200 310310 300300 340340486DX2486DX2 300300 450450 310310 330330 300300
© 1997 Prentice-Hall, Inc.© 1997 Prentice-Hall, Inc.
12 - 12 - 99
Aggregate Scheduling Aggregate Scheduling GoalsGoals
Aggregate Scheduling Aggregate Scheduling GoalsGoals
Meet demandMeet demand Use capacity efficientlyUse capacity efficiently Meet inventory policyMeet inventory policy Minimize costMinimize cost
LaborLabor InventoryInventory Plant & equipmentPlant & equipment SubcontractSubcontract
© 1997 Prentice-Hall, Inc.© 1997 Prentice-Hall, Inc.
12 - 12 - 1010
Promotion & pricePromotion & price Back orderingBack ordering Counterseasonal Counterseasonal
product mixingproduct mixing
Aggregate Scheduling Aggregate Scheduling OptionsOptions
Aggregate Scheduling Aggregate Scheduling OptionsOptions
CapacityCapacity DemandDemand InventoryInventory Hire or layoffHire or layoff Overtime or idle Overtime or idle
timetime SubcontractSubcontract Part-time workersPart-time workers
© 1997 Prentice-Hall, Inc.© 1997 Prentice-Hall, Inc.
12 - 12 - 1111
Aggregate Scheduling Aggregate Scheduling StrategiesStrategies
Aggregate Scheduling Aggregate Scheduling StrategiesStrategies
Mixed strategyMixed strategy Combines 2 or more aggregate scheduling Combines 2 or more aggregate scheduling
optionsoptions
OvertimeOvertime
Sub-Sub-contractcontract
InventoryInventory
PricePrice
Mixed Strategy
© 1997 Prentice-Hall, Inc.© 1997 Prentice-Hall, Inc.
12 - 12 - 1212
Aggregate Scheduling Aggregate Scheduling StrategiesStrategies
Aggregate Scheduling Aggregate Scheduling StrategiesStrategies
Mixed strategyMixed strategy Combines 2 or more aggregate scheduling Combines 2 or more aggregate scheduling
optionsoptions
Level scheduling strategyLevel scheduling strategy Produce same amount every Produce same amount every dayday Keep work force level constant Keep work force level constant Vary non-work force capacity or demand Vary non-work force capacity or demand
optionsoptions Often results in lowest production costsOften results in lowest production costs
© 1997 Prentice-Hall, Inc.© 1997 Prentice-Hall, Inc.
12 - 12 - 1313
Aggregate Scheduling Example Aggregate Scheduling Example 1 (Level with Overtime)1 (Level with Overtime)
Aggregate Scheduling Example Aggregate Scheduling Example 1 (Level with Overtime)1 (Level with Overtime)
You’re an aggregate planner You’re an aggregate planner for GE. You want to develop for GE. You want to develop a plan that meets a plan that meets average average daily demand daily demand with a with a constant constant work forcework force. Each worker . Each worker produces produces 5 units per day5 units per day. . There is There is no beginning no beginning inventoryinventory. Besides regular . Besides regular production, you decide to use production, you decide to use inventoryinventory & & overtimeovertime..
© 1997 Prentice-Hall, Inc.© 1997 Prentice-Hall, Inc.
12 - 12 - 1414
Plan 1 SolutionPlan 1 SolutionPlan 1 SolutionPlan 1 Solution
Production/day: Production/day: No. workers: No. workers:
Month Days Units Produced InventoryReg OT Subcn Held Chg
JanJan 2222 900900
FebFeb 1818 700700
MarMar 2020 800800
TotalTotal
$/Unit$/Unit $8.00$8.00 $11.20$11.20 $5.00$5.00
Tot $Tot $
Forc
$10.00$10.00
Given informationGiven information
© 1997 Prentice-Hall, Inc.© 1997 Prentice-Hall, Inc.
12 - 12 - 1515
Plan 1 SolutionPlan 1 SolutionPlan 1 SolutionPlan 1 Solution
Month Days Forc Units Produced InventoryReg OT Subcn Held Chg
Jan 22 900 880 20 0
Feb 18 700 720 20 20
Mar 20 800 800 20
Total 60 2400 2400 20 40
$/Unit $8.00 $11.20 $10.00 $5.00
Tot $ 19200 $224 $200
Month Days Forc Units Produced InventoryReg OT Subcn Held Chg
Jan 22 900 880 20 0
Feb 18 700 720 20 20
Mar 20 800 800 20
Total 60 2400 2400 20 40
$/Unit $8.00 $11.20 $10.00 $5.00
Tot $ 19200 $224 $200
Production/day: 40Production/day: 40 No. workers: 8.0No. workers: 8.0
Total cost = 19200 + 224 + 200 = $19,624Total cost = 19200 + 224 + 200 = $19,624
00
00
© 1997 Prentice-Hall, Inc.© 1997 Prentice-Hall, Inc.
12 - 12 - 1616
Aggregate Scheduling Thinking Aggregate Scheduling Thinking Challenge 2 (Level with Challenge 2 (Level with
Subcontracting)Subcontracting)
Aggregate Scheduling Thinking Aggregate Scheduling Thinking Challenge 2 (Level with Challenge 2 (Level with
Subcontracting)Subcontracting)
You’re an aggregate planner You’re an aggregate planner for GE. You want to develop for GE. You want to develop a plan that meets lowest daily a plan that meets lowest daily demand (March), about demand (March), about 38/day38/day, with a , with a constant work constant work forceforce. All other demand will . All other demand will be met by be met by subcontractingsubcontracting. . Each worker produces Each worker produces 5 units 5 units per dayper day. There is . There is no no beginning inventorybeginning inventory. .
AloneAlone GroupGroup Class Class
© 1997 Prentice-Hall, Inc.© 1997 Prentice-Hall, Inc.
12 - 12 - 1717
Plan 2 Solution*Plan 2 Solution*Plan 2 Solution*Plan 2 Solution*
Production/day: 38 Production/day: 38 No. workers: No. workers:
Month Days Units Produced InventoryReg OT Subcn Held Chg
JanJan 2222 900900
FebFeb 1818 700700
MarMar 2020 800800
TotalTotal
$/Unit$/Unit $8.00$8.00 $11.20$11.20 $5.00$5.00
Tot $Tot $
Forc
$10.00$10.00
Given informationGiven information
© 1997 Prentice-Hall, Inc.© 1997 Prentice-Hall, Inc.
12 - 12 - 1818
Plan 2 Solution*Plan 2 Solution*Plan 2 Solution*Plan 2 Solution*
Month Days Forc Units Produced InventoryReg OT Subcn Held Chg
Jan 22 900 836 64
Feb 18 700 684 16
Mar 20 800 760 40
Total 60 2400 2280 120
$/Unit $8.00 $11.20 $10.00 $5.00
Tot $ 18240 $1200
Month Days Forc Units Produced InventoryReg OT Subcn Held Chg
Jan 22 900 836 64
Feb 18 700 684 16
Mar 20 800 760 40
Total 60 2400 2280 120
$/Unit $8.00 $11.20 $10.00 $5.00
Tot $ 18240 $1200
Production/day: 38Production/day: 38 No. workers: 7.6No. workers: 7.6
Total cost = 18240 + 1200 = $19,440Total cost = 18240 + 1200 = $19,440
00
00
00
00
00
00
© 1997 Prentice-Hall, Inc.© 1997 Prentice-Hall, Inc.
12 - 12 - 1919
Aggregate Scheduling Example Aggregate Scheduling Example 3 (Chase with Hiring and 3 (Chase with Hiring and
Layoffs)Layoffs)
Aggregate Scheduling Example Aggregate Scheduling Example 3 (Chase with Hiring and 3 (Chase with Hiring and
Layoffs)Layoffs)
You’re an aggregate planner You’re an aggregate planner for GE. You want to develop a for GE. You want to develop a plan that meets exactly plan that meets exactly monthly demandmonthly demand. To do this, . To do this, you decide to you decide to hirehire & & layofflayoff workers. The number of workers. The number of workers will vary each month. workers will vary each month. Each worker produces Each worker produces 5 5 units per dayunits per day. There is . There is no no beginning inventorybeginning inventory. .
© 1997 Prentice-Hall, Inc.© 1997 Prentice-Hall, Inc.
12 - 12 - 2020
Plan 3 SolutionPlan 3 SolutionPlan 3 SolutionPlan 3 Solution
Production/day: Production/day: No. workers: No. workers:
Month Days Forc Units Produced InventoryReg Inc Dec Held Chg
TotalTotal
$/Unit$/Unit
Tot $Tot $
JanJan 2222 900900
FebFeb 1818 700700
MarMar 2020 800800
$8.00$8.00 $10.00$10.00 $15.00$15.00 $5.00$5.00
Given informationGiven information
© 1997 Prentice-Hall, Inc.© 1997 Prentice-Hall, Inc.
12 - 12 - 2121
Plan 3 SolutionPlan 3 SolutionPlan 3 SolutionPlan 3 Solution
Production/day: Production/day: No. workers:No. workers:
Month Days Forc Units Produced InventoryReg Inc Dec Held Chg
TotalTotal
$/Unit$/Unit
Tot $Tot $
JanJan 2222 900900
FebFeb 1818 700700
MarMar 2020 800800
$8.00$8.00 $10.00$10.00 $15.00$15.00 $5.00$5.00
6060 24002400
909000 0000
707000
Production matchesforecast demand
Production matchesforecast demand
© 1997 Prentice-Hall, Inc.© 1997 Prentice-Hall, Inc.
12 - 12 - 2222
Plan 3 SolutionPlan 3 SolutionPlan 3 SolutionPlan 3 Solution
Production/day: Varies Production/day: Varies No. workers: No. workers:
Month Days Forc Units Produced InventoryReg Inc Dec Held Chg
TotalTotal
$/Unit$/Unit
Tot $Tot $
JanJan 2222 900900
FebFeb 1818 700700
MarMar 2020 800800
$8.00$8.00 $10.00$10.00 $15.00$15.00 $5.00$5.00
6060 24002400
909000 0000
707000
Production per day varies.Jan: 900/22 = 40.9 units/dayFeb: 700/18 = 38.9 units/day
Production per day varies.Jan: 900/22 = 40.9 units/dayFeb: 700/18 = 38.9 units/day
© 1997 Prentice-Hall, Inc.© 1997 Prentice-Hall, Inc.
12 - 12 - 2323
Plan 3 SolutionPlan 3 SolutionPlan 3 SolutionPlan 3 Solution
Production/day: VariesProduction/day: Varies No. workers: VariesNo. workers: Varies
Month Days Forc Units Produced InventoryReg Inc Dec Held Chg
TotalTotal
$/Unit$/Unit
Tot $Tot $
JanJan 2222 900900
FebFeb 1818 700700
MarMar 2020 800800
$8.00$8.00 $10.00$10.00 $15.00$15.00 $5.00$5.00
6060 24002400
909000 0000
707000
Workers per day varies.Jan: (40.9 units/day)/(5 units/worker/day) = 8.2 Feb: (38.9 units/day)/(5 units/worker/day) = 7.8
Workers per day varies.Jan: (40.9 units/day)/(5 units/worker/day) = 8.2 Feb: (38.9 units/day)/(5 units/worker/day) = 7.8
© 1997 Prentice-Hall, Inc.© 1997 Prentice-Hall, Inc.
12 - 12 - 2424
Plan 3 SolutionPlan 3 SolutionPlan 3 SolutionPlan 3 Solution
Production/day: VariesProduction/day: Varies No. workers: VariesNo. workers: Varies
Month Days Forc Units Produced InventoryReg Inc Dec Held Chg
TotalTotal
$/Unit$/Unit
Tot $Tot $
JanJan 2222 900900
FebFeb 1818 700700
MarMar 2020 800800
$8.00$8.00 $10.00$10.00 $15.00$15.00 $5.00$5.00
6060 24002400
909000 0000
707000 200200
200 = 900 - 700: decrease in production due to layoffs
200 = 900 - 700: decrease in production due to layoffs
© 1997 Prentice-Hall, Inc.© 1997 Prentice-Hall, Inc.
12 - 12 - 2525
Plan 3 SolutionPlan 3 SolutionPlan 3 SolutionPlan 3 Solution
Month Days Forc Units Produced InventoryReg Inc Dec Held Chg
Jan 22 900 900 0 0
Feb 18 700 700 200 0 0
Mar 20 800 800 100 0 0
Total 60 2400 2400 100 200
$/Unit $8.00 $10.00 $15.00 $5.00
Tot $ 19200 $1000 $3000
Month Days Forc Units Produced InventoryReg Inc Dec Held Chg
Jan 22 900 900 0 0
Feb 18 700 700 200 0 0
Mar 20 800 800 100 0 0
Total 60 2400 2400 100 200
$/Unit $8.00 $10.00 $15.00 $5.00
Tot $ 19200 $1000 $3000
Production/day: VariesProduction/day: Varies No. workers: VariesNo. workers: Varies
Total cost = 19200 + 1000 + 3000 = $23,200Total cost = 19200 + 1000 + 3000 = $23,200
© 1997 Prentice-Hall, Inc.© 1997 Prentice-Hall, Inc.
12 - 12 - 2626
Thinking Challenge:Thinking Challenge:Compare & ContrastCompare & ContrastThinking Challenge:Thinking Challenge:Compare & ContrastCompare & Contrast
Basis of PlanComparison Inv/OT Subcontract Hire/Layoff
Basis of PlanComparison Inv/OT Subcontract Hire/Layoff
AloneAlone GroupGroup Class Class
© 1997 Prentice-Hall, Inc.© 1997 Prentice-Hall, Inc.
12 - 12 - 2727
ConclusionConclusionConclusionConclusion
Described planningDescribed planning Distinguished the types of plansDistinguished the types of plans Defined aggregate schedulingDefined aggregate scheduling Related aggregate scheduling to the Related aggregate scheduling to the
overall planning processoverall planning process Explained aggregate scheduling optionsExplained aggregate scheduling options Developed aggregate schedulesDeveloped aggregate schedules