Minutes of 3 rd meeng of Southern Regional Power Commiee (Transmission Planning) भारत सरकार Government of India ुत म ं ालय Ministry of Power क ीय ु त ाकरण Central Electricity Authority ु त णाली योजना ए ं मूया ं कन भाग -I Power System Planning & Appraisal Division-I सेा म / To, स ं लन सूची के अनुसार As per enclosed list षय : दण े ुत समत (पारेषण योजना) की तीसरी बैठक का काय&ृत। Subject: Minutes of 3 rd meeting of Southern Regional Power Committee (Transmission Planning) [SRPC(TP)]. महोदया(Madam) / महोदय(Sir) The 3 rd meeting of Southern Regional Power Committee (Transmission Planning) [SRPC(TP)] was held on 24.08.2021 through VC (Microsoft Teams). Minutes of the meeting are attached for kind information. भदीय/Yours faithfully, (ईशान शरण / Ishan Sharan) मुय अभय ं ता / Chief Engineer Copy for kind information to: 1) PPS to Member (Power System), CEA 1 File No.CEA-PS-12-14(12)/1/2018-PSPA-II Division I/18213/2021 1006
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Minutes of 3rd meeting of Southern Regional Power Committee (Transmission Planning)
वि� द्य ुत प्र णाली योजना ए� ं म ू ल् या ंकन प्र भाग -I
Power System Planning & Appraisal Division-I
से�ा में / To,
संलग्न सचूी के अनसुार As per enclosed list
वि�षय : दवि ण ेत्र वि�द्युत सविमवित (पारेषण योजना) की तीसरी बैठक का काय&�ृत।Subject: Minutes of 3rd meeting of Southern Regional Power Committee (Transmission
Planning) [SRPC(TP)].
महोदया(Madam) / महोदय(Sir)
The 3rd meeting of Southern Regional Power Committee (Transmission Planning)[SRPC(TP)] was held on 24.08.2021 through VC (Microsoft Teams).
Minutes of the meeting are attached for kind information.
भ�दीय/Yours faithfully,
(ईशान शरण / Ishan Sharan)
मुख्य अविभयंता / Chief Engineer
Copy for kind information to:1) PPS to Member (Power System), CEA
Minutes of 3rd meeting of Southern Regional Power Committee (Transmission Planning)
Minutes of 3rd meetging of Southern Regional Power Committee (Transmission
Planning)
Date: 24.08.2021 Time: 10:30AM
List of participants is enclosed at Annex-A.
Member (Power System), CEA, and Chairman of RPC (TP) welcomed the participants andstated that the meeting could not be scheduled on time due to prevailing conditions ofCOVID-19 pandemic.
Chief Engineer (PSPA-I), CEA, stated that most of the proposals of transmission systemaugmentation as received from the SR constituents had already been discussed in the jointstudy meetings held on 04.02.2021 and 19.05.2021. He requested Director (PSPA-I), CEA, totake up the agenda items for discussion.
1. Confirmation of the Minutes of 2nd Meeting of Southern Regional Power Committee(Transmission Planning) [SRPC(TP)]
1.1. Director (PSPA-I), CEA informed that minutes of 2nd Southern Regional Power Committee
(Transmission Planning) [SRPC (TP)] meeting held on 01.10.2020 through VC, were
circulated vide letter No. CEA-PS-12-14(12)/1/2018-PSPA-II Division-Part (2) I/12514/2020
dated 03.12.2020.
1.2. As no comments/observations on the minutes were received from the constituents, the
minutes of 2nd SRPC(TP) meeting issued vide CEA letter no. CEA-PS-12-14(12)/1/2018-
PSPA-II Division-Part (2) I/12514/2020 dated 03.12.2020 were confirmed.
A. ToR 2(i) – QUARTERLY REVIEW AND STRENGTHNING OF INTER-REGIONALTRANSMISSION SYSTEM
2. Quarterly Review of transmission lines and substations
2.1. List of transmission lines and substations/ICTs commissioned in Southern Region during FY
2020-21 and Q1 of FY 2021-22 are attached as Annex-2.
Gist of transmission lines and substation/ICTs commissioned in Southern Region in FY
Minutes of 3rd meeting of Southern Regional Power Committee (Transmission Planning)
Sl.No.
ICTSeason/ Antecedent Conditions
Description of theconstraints
Deliberations in 3rd SRPC (TP) meeting
1.400/220 kV 2x500 MVAICTs at Kolar
Whole Year
'N-1' not satisfied for1% in Jan, 14 % in Feb, 27% in March.
1x500 MVA, 400/220 kV ICTaugmentation agreed at Kolar. Referitem-15.
2.400/220 kV 2x500 MVAICTs at Kaiga
Whole Year
'N-1' not satisfied for18% in Jan, 16% inFeb, 14% in March.The 2x220 MWUnits at Kaiga,Kadra (150 MW)and Kodasalli (120MW) generation iscompletely injectedinto the 400 kVsystem through theseICTs due to openingof 220 kV Kodasalli– Nagjheri D/C inview of 220 kVsystem overload.
In 1st SRSCT meeting, re-conductoringof following lines with HTLSconductor had been agreed: 220 kV Nagjheri – Ambewadi DC
line, 220 kV Ambewadi – Narendra D/C
line, 220 kV Kaiga – Kodasally S/C line 220 kV Kadra – Kodasally S/C line
With reconductoring of the lines,loading capability & availability oflines will increase. Accordingly loadingon ICTs was expected to be reduced.
Representative of KPTCL informed thatreconductoring works were delayedbecause of RoW issues as the linecorridor is falling under Western ghatarea. He added that the reconductoringwork is in tendering stage and the workis expected to be completed by March,2024. CGM, SRLDC added that KPTCL hasto implement SPS to avoid the trippingof ICTs at Kaiga S/s and subsequenttripping of generating units at Kaigaduring contingencies. However, SPS hasnot yet been implemented. Theimplementation of modified SPS hadbeen agreed in January, 2019.Member (Power System), CEA, advisedKPTCL to complete the reconductoringwork at the earliest. He advised MemberSecretary (I/c), SRPC, to discuss andresolve the issues in implementation ofSPS with KPTCL.
3. 400/220 kV 3x500 MVAICTs at Nelamangala
Whole Year
‘N-1’ not satisfiedfor 2% in Jan, 10%in Feb, 28 % inMarch.
KPTCL informed that the followingsubstations are under implementaionstage which would reduce the loadingon ICTs at Nelamangala S/s: 2x500 MVA, 400/220 kV Peenya S/
s: LOI is issued on 26.07.2021 andtarget date of implementation isJanuary, 2024.
3rd 500 MVA ICT at Devanhalli S/s: LOI is issued on 26.07.2021 and
Minutes of 3rd meeting of Southern Regional Power Committee (Transmission Planning)
Sl.No.
ICTSeason/ Antecedent Conditions
Description of theconstraints
Deliberations in 3rd SRPC (TP) meeting
target date of implementation isMarch 2023.
Establishing 400/220 kV S/s atHuliyurdurga, Tumakuru District:Land has been acquired and targetdate of implementation is March,2024.
4.
400/220 kV 2x315 + 1x500 MVAICTs at Mysore
Whole Year
'N-1' not satisfied for24% in Jan, 44% inFeb, 69% in March.
KPTCL informed that 3rd ICT is notrequired as the loading on Mysore ICTswould reduce after commissioning ofKadakola S/s in Mysore district. Targetdate of implementation of Kadakola S/sis March 2024. Refer item no 15.
5.
400/220 kV 2x315 MVA ICTsat Cochin
Whole Year
'N-1' not satisfied for2 % in March.
Issue will resolve with transformationcapacity augmentation by 1x500 MVA,400/220 kV ICT (3rd), alreadydiscussed and agreed in 2nd SRPC(TP)and 4th NCT.
It was informed that the 3rd ICT hasalready awarded to POWERGRID forimplementation under RTM vide MoPOM dated 16th July, 2021.
6.400/220 kV 3x315 MVA ICTs at Vemagiri
High demand Scenario of SR
'N-1' not satisfied for7% in Jan, 12% inFeb, 38 % in March.
APTRANSCO informed that 4th ICT of500 MVA at Vemagiri has beencommissioned on 30.04.2021 and now ,loading on ICTs is normal.
7.400/220 kV 2x315 MVA ICTs at Narnoor
High demandScenario of SR
'N-1' not satisfied for16% in Jan, 22% in Feb, 1% in March.
Proposal of 3rd ICT is under discussionin APTRANSCO and the observationswill be furnished to CEA shortly.However, an alternate arrangement hasbeen made in the 1st week of March,2021 in 220 kV Bus at 400 kV GhaniSS.With this arrangement, loading on ICTsat Narnoor would be reduced. Thesame is expected to be commissionedby April, 2022.
8.400/230 kV 3x315 MVA ICTs at Hosur
High demandScenario of SR
'N-1' not satisfied for1 % in March.
As per TANTRANSCO, ICTaugmentation may not be required asthe ‘N-1’ violation is very meagre.Further, after commissioning ofUthanapalli – Palavadi 230 kV D/cline, the load will be diverted fromHosur S/S and there will not be anyconstraint in future.
9. 400/220 kV 2x500 MVA ICTs at Narendra
High demandScenario of SR
'N-1' not satisfied for8 % in March.
KPTCL informed that loading wouldbe reduced on Narendra S/s aftercommissioning of planned 400/220 kVLokapur S/s. Lokapur S/s is under planning stage.
Minutes of 3rd meeting of Southern Regional Power Committee (Transmission Planning)
Sl.No.
ICTSeason/ Antecedent Conditions
Description of theconstraints
Deliberations in 3rd SRPC (TP) meeting
Refer item 27.
10.400/230 kV 2x250 MVA ICTs at NeyveliII TPS
High demand Scenario of SR
'N-1' not satisfied for39 % in Mar.
It was decided that Neyveli TS-II -Cuddalore 400 kV D/c line would beimplemented by TANTRANSCO toreduce the loading on ICTs at NeyveliII TPS. Refer item no. 7 of the minutes.TANTRANSCO suggested that shiftingof the NLC TS II Unit-IV connectivityfrom 400 kV side to 230 kV side wouldmitigate the overloading issue of 2x250MVA ICTs at NLC TS-II. It wasdecided that the same would bediscussed in next SRPC (TP) meeting.
11.400/220 kV 2x315 MVA ICTs at Hassan
High demandScenario of SR
'N-1' not satisfied for5% in Feb, 7% in March.
KPTCL informed that loading on ICTsat Hassan is expected to reduce withcommissioning of planned 400/220 kVHampapura S/s. The substation wouldbe implemented by 2025.
12.
765/400 kV 2x1500 MVAICTs at Nizamabad
High demand Scenario of SR
'N-1' not satisfied for1% in January.
Augmentation of 1x1500 MVA, 765/400 kV ICT (3rd) at Nizamabad hasbeen approved. Refer item No. 15.
13.
400/220 kV 2x315 + 2x250 MVA ICTs at Ramagundam STPS
High demandScenario of SR
'N-1' not satisfied for5% in Jan, 12% in Feb, 34% in March.
TSTRANSCO informed that load of140 MW would be shifted to othersubstation, so the loading onRamagundam S/s would be relieved.
14.
400/220 kV 2x315 MVA ICTs at Suryapet
High demandScenario of SR
'N-1' not satisfied for1% in February.
With implementation of Yadadrigeneration linked scheme, loading onSuryapet ICT is expected to bereduced. Tentative schedule ofimplementation is one year.
15.
400/220 kV 3x500 MVA ICTs at Somanahalli
High demand Scenario ofSR
'N-1' not satisfied for1% in Jan, 1% in Feb, 5 % in March.
KPTCL to expedite implementation of: 2x500 MVA, 400/220 kV
Domasandra S/s 220 kV line terminating at 3x500
MVA, 400 /220 kV Mylasandra S/sWith above, loading on ICTs onSomanhalli is expected to be reduced.
KPTCL informed that: 2x500 MVA, 400/220 kV
Domasandra S/s is expected to becommissioned within 22 months.
220 kV line terminating at 3x500MVA, 400 /220 kV Mylasandra S/shas been commissioned along withMylasandra S/s.
16.400/230 kV 2x315 MVA
High demand 'N-1' not satisfied for
With implementation of 2x200 MVA,400/110 kV ICTs and 1x500 MVA,
Minutes of 3rd meeting of Southern Regional Power Committee (Transmission Planning)
Sl.No.
ICTSeason/ Antecedent Conditions
Description of theconstraints
Deliberations in 3rd SRPC (TP) meeting
ICTs at Thiruvalam
Scenario ofSR
3% in March.
400/230 kV 3rd ICT at Tiruvalam,loading on ICTs will be reduced.
TANTRANSCO informed that 1x500MVA, 400/230 kV, 3rd ICT atThiruvalam has been already approvedin the 42nd meeting of SCPSPSR.
17.400/220 kV 2x315 MVA ICTs at UPCL
High demandScenario in SR
'N-1' not satisfied for9% in Jan, 31% in Feb, 29 % in March.
KPTCL informed that they areplanning to implement 2x500 MVA,400/220 kV Arasapadavu S/s. Theloading on UPCL would be reducedafter commissioning of Arasapadavu S/s by December, 2024.
18.
400/132 kV, 250 MVA ICT atRamagundam STPS
-
Limiting constraint for State Drawl capability. N-1 of 400/220 kV ICT would result in over loading.
TSTRANSCO informed that part of load would be shifted to other substation.
19.
400/110 kV, 2x200 MVA ICTs at Salem SS
Whole year
Limiting constraint forState Drawl capability. 'N-1' of ICTs would result in over loading.
TANTRANSCO informed that 1x200MVA, 400/110 kV ICT (3rd) at Salem400/230 kV SS was commissioned on23.07.2021.
In addition to the above, following ICT Constraints reported by SRLDC in Q1 of 2021-22 (April, 21 – June, 21) were also discussed:
Sl.No.
ICT Season/AntecedentConditions
Description of theconstraints
Deliberations in 3rd SRPC (TP)meeting
1.
400/230 kV 2x315+1x500 MVA ICTs at Allundur S/s
Whole year
Limiting constraint for S1-S2 drawl capability.‘N-1’ not satisfied for11% in April and 1% in May
As per TANTRANSCO, ICTaugmentation may not berequired as ‘N-1’ violation isvery meagre. Further, aftercommissioning of Vellaviduthi400/230 kV S/s, the N-1 violationat Alundur will be resolved.
2.
400/220 kV 2x315 MVA ICTs at Jindal S/S
High demand andpeak solar scenario SR
‘N-1’ not satisfied for80% in April, 5% in May, 4% in June
It was informed that KPTCL isdrawing additional power fromJindal S/S through 220 kV line. Committee advised KPTCL totake appropriate action tominimize the loading on the ICTsat Jindal S/s.
Minutes of 3rd meeting of Southern Regional Power Committee (Transmission Planning)
5.2. Transmission Line Constraints
Transmission line constraints reported by SRLDC in Q4 of 2020-21 (Jan’21 – March’21):
Sl.No
Corridor
Season/ Antecedent Conditions
Description of the transmission line constraints
Deliberations in 3rd SRPC (TP)meeting
TamilNadu230 kVSystem
WholeYear
230 kV NLCTS 2 – KadalangudiS/C
TANTRANSCO informed thatthere would not be any constraintafter commissioning of 2nd circuitfrom Neyveli (TNEB) – Kadalagudi230 kV SC line.
230 kV NLCTS 2 - STCMS
TANTRANSCO informed thatthere is no constraint observed aftersplit bus arrangement at Cuddalore& Neyveli 230 kV SS and openingof NNTPS-Neyveli 230 kV DCline.
230 kV Kalivendapattu –Tharamani S/C
TANTRANSCO informed thatupgradation of Tharamani 400 kVSS, construction of Sholinganallur –KITs park 230 kV SC line andSholinganallur -Omega 230 kV DCline.
TANTRANSCO informed that high loading is only during high wind generation season
230 kV Othakalmandapam-Coimbatoor S/C
TANTRANSCO informed that high loading is only during high wind generation season
230 kV Othakalmandapam – Thudialur S/C
TANTRANSCO informed that high loading is only during high wind generation season
230 kV Othakalmandapam –Mywadi S/C
TANTRANSCO informed thathigh loading is only during highwind generation season and linestrengthening work is underprogress.
230 kV Madurai - Sembatty S/C
TANTRANSCO informed thatthere is no constraint aftercommissioning of Karaikudi-Sembatty 230 kV SC line.
230 kV Pugalur – Pugalur(PG) D/C
TANTRANSCO informed thatloading issues will be resolvedafter making LILO of Alundur-Pugalur (PG) 230 kV feeder atValayapatty 230 kV SS.
230 kV Pugalur-Karukathi S/C TANTRANSCO informed thatloading issues will be addressedafter making LILO of Alundur-Pugalur (PG) 230 kV feeder atValayapatty 230 kV SS and LILO
Minutes of 3rd meeting of Southern Regional Power Committee (Transmission Planning)
Sl.No
Corridor
Season/ Antecedent Conditions
Description of the transmission line constraints
Deliberations in 3rd SRPC (TP)meeting
of Ingur –Palladam line atKurukathi.
230 kV Pudanchandai-Pugalur S/C
TANTRANSCO informed thatloading issues will be addressedafter making LILO of Alundur-Pugalur (PG) 230 kV feeder atValayapatty 230 kV SS.
230 kV Trichy (PG) – Allundur(TN) D/C
TANTRANSCO informed thatloading issues would be resolvedafter commissioning ofVellaviduthi 400 kV SS.
230 kV TTPS-TSIPCOT S/CTANTRANSCO informed thatloading issues would be resolvedafter commissioning of Ottapidaram400 kV SS
230 kV Kariakudi – Karmbayam
TANTRANSCO informed that aftercommissioning of Karaikudi –Karambiyam 230 kV 2nd circuitwhich is under construction, theloading issue will be resolved.
2 220 kVBangalore MetroNetwork
WholeYear
Most of the 220 kV network inBengaluru is radialised duringpeak season to prevent overloading of lines. The radialisationof lines decreases the reliabilityof supply & thus resulting in LowVoltage situation during peakperiod and High Voltage duringOff-Peak period of the day at 400kV Somanahalli/Nelamangala/Hoody.There is no sufficient CapacitorCompensation at distributionlevel in BESCOM area also.
KPTCL informed that the followingsubstations are being established toprevent the overloading of 220 kVlines in Bengaluru:a. 2 x 500 MVA,
400/220 kV Dommasandra GIS- Target by March, 2024,
b. 2x150 MVA,220/66 kV Kumbalagodu S/s -Target by November, 2021.
c. 2x150 MVA,220/66 kV Exora S/s- Target byNovember, 2021.
d. 2x150 MVA,220/66 kV HBR Layout S/s -Target by January, 2022.
e. 2x150 MVA,220/66 kV Sahakari Nagar S/s -Target by December, 2022.
f. 2 x 150 MVA,220/66 kV GIS sub-station atSobha Dreams - Target bySeptember 2021
g. 2 x 150 MVA,220/66 kV GIS sub-station atWhitefiled (Hagadur) - Targetby March 2024
Minutes of 3rd meeting of Southern Regional Power Committee (Transmission Planning)
Sl.No
Corridor
Season/ Antecedent Conditions
Description of the transmission line constraints
Deliberations in 3rd SRPC (TP)meeting
Target by March 2024i. 2x100 MVA,
220/66 kV Nelamangala S/s -Target by March 2024
j. 2 x 150 MVA,220/66 kV GIS in the premises ofexisting 66/11kV Keonics(Electronic City) S/s - Target byMarch 2024
k. 2 x 150 MVA,220/66 kV GIS near 66/11kVMathikere S/s - Target by January2024
l. 2x150 MVA, 220/66kV and 1x31.5 MVA, 66/11 kVsubstation at Banashankari 6thstage - Target by March 2024
m. 2x150MVA,220/66kV and 31.5MVA,66/11kV substation at Medahalli -Target by March 2024
n. 220 kV GIS near toexisting 220 kV VrishabhavathiValley S/s along withstrenghthening of 220kVSomanahalli-Tataguni-VV ValleySC line. - Target by March 2023
o. 220 kV GIS atBBMP park near to existing220/66/11 kV Khodays GlassFactory S/s - Target by March2023
p. 220 kV Multi circuit(4 circuits) line from 400/220KVNelamangala-220 kV SRSPeenya- 220 kV NRSRajajinagara-220 kV BrindavanaS/s - proposed 220 kVSahakarinagra S/s - Target byOctober 2022
q. Strengthening ofexisting 220 kV Kolar HVDC-Kolar DC line using HTLSconductor - Target by March2024
r. Strengthening ofexisting 220 kV Bidadi PGCIL-Bidadi DC line using HTLSconductor - Target by March2024
meeting of Southern RegionalPower Committee (TransmissionPlanning) held on 16.12.2019recommended for Re-conductoring of the lines withHTLS conductor. KPTCL has toexpedite the same.
KPTCL informed that estimate isunder preparation for thereconductoring work with HTLSconductor and the work is expectedto be completed by March, 2024.
4
AndhraPradesh220kVNetwork
WholeYear
The following lines are heavily loaded: 220 kV Lower Sileru –
Bommuru S/CAPTRANSCO informed thatloading will be reduced with thecompletion of works for revival of220 kV Lower Sileru – BommuruDC abandoned line, which areunder progress. The work isexpected to be completed by
220 kV UpperSileru-Pendurthi S/C
220 kV LowerSileru-KTSV S/C
220 kV Maradam-Garividi D/CAPTRANSCO informed that 220kV Maradam – Pydibhimavaramline was commissioned on14.05.2021 and 220/132 kV 100MVA PTR at Pydibhimavaram wasloaded on 02-08-2021. Hence,loadings on 220 kV Maradam –Garividi and Maradam – Bobbilifeeders were reduced.
Minutes of 3rd meeting of Southern Regional Power Committee (Transmission Planning)
Sl.No
Corridor
Season/ Antecedent Conditions
Description of the transmission line constraints
Deliberations in 3rd SRPC (TP)meeting
220 kV Kalpaka-Brandix D/C
APTRANSCO informed that theland acquisition for construction of400/220 kV Atchutapuram SS is infinal stage. With theimplementation of the proposed400 kV Atchutapuram S/s, loadingon 220 kV Kalpaka – Brandix willbe reduced. 400 kV AtchutapuramS/s would be commissioned by2024-25. However, an interim alternateproposal to reduce overloading on220 kV Kalpaka – Brandix is understudy. The interim arrangement is
220 kV Gazuwaka-Parvada
APTRANSCO informed that 220KV Gajuwaka (VSS) – Kakinadawas proposed to be LILO’ed at 220KV SS Parawada. Tendering is inprogress. The work is expected tobe completed by May’2022.
220 kV Vemagiri-Bommuru D/C
APTRANSCO informed that LILOof 220 kV Bommuru – VijjeswaramStage-1 & 220 kV Bommuru –Vijjeswaram Stage-2 lines at440/220 kV Vemagiri S/s is alreadyplanned. Tendering is in progress.The work is expected to be
220 kV Gudivada-Nunna D/C
APTRANSCO informed that withthe implementation of proposed400/220 kV Gudiwada S/S, loadingon 220 kV Gudivada-Nunna D/Cline will be reduced. Proposal wasfurnished to CEA on 13.07.2021.Works will be awarded after gettingapproval from CEA. It is expectedto be completed in 2023-24.
220 kV Gunadala-Nunna S/CLine
APTRANSCO informed that bridgejumpers were connected between220 kV VTS and 220 kV Gunadalafeeders at 220 kV Nunna S/s toform 2nd 220 kV VTS – GunadalaLine on 22.01.2021. Another 220kV Nunna-Gunadala DC line is alsounder construction. 220 kV VTPS-Tadikonda D/C APTRANSCO informed that loadsof 132 kV SS Guntur were shiftedfrom 220 kV S/S Tadikonda SS to220 kV Prathipadu S/s on30.04.2021. With this, loading on220 kV VTPS - Tadikonda Lineswas reduced.
Minutes of 3rd meeting of Southern Regional Power Committee (Transmission Planning)
Sl.No
Corridor
Season/ Antecedent Conditions
Description of the transmission line constraints
Deliberations in 3rd SRPC (TP)meeting
220 kV Chinakampalli-Rajampet S/C
APTRANSCO informed that 220kV Chinakampalli – Rajampet lineis passing through forest area due towhich replacement with HTLSconductor is difficult. New 220 kVSS in the same area is under study.Expected time frame for new 220kV S/s is 2024-25.
5
Downstream network of Mysore400/220 kV SS
Peakdemandscenario
of SR
The following lines are heavily loaded: 220 kV Mysore-Hootagalli D/
C 220 kV Mysore-Kadakola D/C 220 kV Mysore-Tubinekare S/
KPTCL informed that strengtheningof 220 kV Mysore-Hootagalli D/Cby replacing existing Drake byHTLS conductor is expected to becompleted by March 2024.Conversion of 220 kV Hootagalli-Vajamangala SC line by DC line isapproved and it will beimplemented by March, 2024.
KPTCL added that with theproposed 400 kV Kadakola S/s, theloading of following 220kV lineswould be reduced:
KPTCL informed that 2x500 MVA,400/220 kV Arasapadavu S/s is plannedto reduce the loading on 220 kV UPCL-Kemar D/c line. Arasapadavu S/s isexpected to be implemented by March,2024.
Minutes of 3rd meeting of Southern Regional Power Committee (Transmission Planning)
5.3. Over Voltage Constraints
5.3.1 Director, CEA, informed that SRLDC in its report for the period Q4 of 2020-21 (Jan’21 –March’21) has mentioned that 57 nos. of nodes are experiencing high voltage, out of which24 nodes are experiencing high voltage almost throughout the year. To control the overvoltage, 114 nos. of 765 kV and 400 kV lines had to be opened 549 times.
Further, SRLDC in its report for the period Q1 of 2021-22 (April’21 – June’21) hasreported that about 74 nodes are experiencing high voltage (above 420 kV) during off peakperiod / whole year. To control the overvoltage, about 98 nos. of 765kV and 400 kVelements had to be opened 282 times.
5.3.2 To mitigate the over/ low voltage issues, reactive compensation studies have been carriedregularly with augmentation of new transmission system or operator feedback and put upfor deliberation in the SRPC(TP) meetings. On basis of study analysis, 27 nos. of reactorsat different ISTS and STU nodes were agreed for implementation in Southern RegionalGrid in 1st SRSCT meeting held on 07.09.2018.
Matter regarding persisting high voltage in Southern Region was also discussed in 2nd
SRPC(TP) meeting held on 01.10.2020, wherein STUs were asked to expedite theimplementation of reactors agreed in various standing committees. Details of the reactors andtheir implementation status as informed during the 2nd SRPC(TP) meeting are as tabulatedbelow.
Sl.No.
Bus NameVoltage
(kV)ISTS /State
Existing /UC
Reactor(MVAr)
TypeReactorAgreed(MVAr)
Status as per 3rd SRPC(TP)meeting
1. Hosur 400 ISTS 63 Bus 125Expected to be commissionedby September, 2021.
2. Madhugiri 400 ISTS 63 Bus 125Major works completed,Expected to be commissionedby September, 2021.
3. Dharampuri 400 ISTS - Bus 125Expected to be commissionedby September, 2021.
4. Hiriyur 400 ISTS - Bus 125Major civil works completed,Expected to be commissionedby October, 2021.
5. Pugalur 400 ISTS - Bus 125Major civil work completed,expected to be commissionedby October, 2021
6.Pugalur HVDC STN
400 ISTS - Bus 2x125Major civil work completed,expected to be commissionedby October, 2021
7. Rachagunneri 400 AP - Bus 125Commissioned in November,2020
8. Hindupur 400 AP 80 Bus 125
80MVAr was commissionedon 21.11.2020.Works are yet to be awardedfor the 125 MVAr Bus
Reactor would beimplemented along withWayand Sub-station. Thesame is yet to be ordered.
14. Velalividu 400 TN - Bus 125
1x80 MVAr bus reactor isunder erection stage and it isexpected to be commissionedby December 2021. Thesuggested 1x125 MVArreactor is not required.
15. Uddandapur 400 TEL Bus 125 Tendering is under progress
16. KTPP SS 400 TEL Bus 125
Works are taken up along withconstruction of 400/220/132kV KTPP SS. At present,foundation & structureerection works are underprogress. It is expected to becommissioned in March, 2022.
17. Raidurg 400 TEL Bus 125
Works are taken up against theongoing contract of RayadurgGIS sub-station and works arenearing completion. It isexpected to be commissionedin November, 2021.
18. Narlapur 400 TEL Bus 125 Contract has been awarded forthe erection pf 400 kV LI SSat Narlapur, Vattem, andYedula along with supply &erection of 1x125 MVArreactor at each substation.Narlapur work is likely to becompleted in May’2022 andYedula & Vattem works islikely to be completed inMarch, 2022.
19. Yedula 400 TEL Bus 125
20. Vattem 400 TEL Bus 125
21. Narsapur 400 TEL Bus 125 Grant from PSDF wassanctioned by MoP on31.03.2021. Works will betaken up shortly. The work is
Minutes of 3rd meeting of Southern Regional Power Committee (Transmission Planning)
Sl.No.
Bus NameVoltage
(kV)ISTS /State
Existing /UC
Reactor(MVAr)
TypeReactorAgreed(MVAr)
Status as per 3rd SRPC(TP)meeting
expected to be completed by
23. Kamalapuram 400 TEL Bus 125
Works are taken up against theongoing contract ofKamalapuram LI sub-stationand works are nearingcompletion. The work isexpected to be completed bySeptember, 2021.
24. Tippapur 400 TEL Bus 125 Reactor commissioning worksare under progress. The workis expected to be completed byOctober, 2021.
25.Sundilla (Yellampalli)
400 TEL Bus 125
26. Chandulapur 400 TEL Bus 125Works are completed and itwas commissioned on06.09.2019.
27. Chouttuppal 400 TEL Bus 125
Works are taken up along withconstruction of 400/220/132kV Choutuppal SS. At present,tower erection works are underprogress. The work is expectedto be completed by February,2022.
28. Dindi 400 TEL Bus 2x125 PSDF grant was sanctioned byMoP on 31.03.2021. Contractwas awarded by Bay extensionworks on dtd. 04.06.2021. Atpresent, works are underprogress. The work is expectedto be completed by June, 2022.
29. Janagaon 400 TEL Bus 12530. Suryapet 400 TEL Bus 125
31.Maheshwaram-TS
400 TEL Bus 80
32.Asupaka
400 TEL Bus 12533. 400 TEL Line 63
5.3.3 Subsequently, to analyze the high / low voltage issue in Southern Grid, in time frame of2024-25 (August-night), detailed study has been carried out by CTU. Maximum andminimum demand observed by SRLDC for 2020-21 and the demand considered for studyanalysis in time frame of 2024-25 and are as given below.
Minutes of 3rd meeting of Southern Regional Power Committee (Transmission Planning)
Nadu6. Puducherr
y421 - 650 570 314
7. SouthernRegion
58400 27486 74650 74200 37700
5.3.4 From study results, voltage above than 1.05 pu has been observed at Muddunur, Karaikudiand Velalividu S/s. Further, 1x125 MVAR, 420 kV bus reactor proposed by APTRANSCOat Kalikiri 400/220 kV S/s along with 6100 MW solar generation scheme, has beenconsidered in study analysis.
5.3.5 It may be noted that due to space constraint, it is not possible to implement 420 kV busreactor at Karakudi 400/230 kV S/s. To control the grid voltage following is proposed forMuddunur and Velalividu S/s.
Installation of 1x125 MVAR, 420 kV bus reactor is proposed at Muddunur generationend– Under the scope of Generator. (Presently there is no bus reactor at generatorswitchyard).
Installation of 1x125 MVAR, 420kV bus reactor is proposed at Velalivedu S/s – Underthe scope of TANTRANSCO.
5.3.6 From study analysis it may be observed that voltage at all 765 kV substations is within theoperational limit for 765 kV level i.e. 800 kV.
Further, it may be noted that in study analysis, generators in Southern Region haveabsorbed reactive power of the order of about 7700 MVAR. If generators are not operatedin under excited conditions, more reactors shall be required at different nodes to control thegrid voltage.
Deliberations in 3 rd SRPC(TP) Meeting
5.3.7 Sr. DGM (CTUIL) stated that considering all the planned and approved Bus/Line reactors,the total reactive compensation provided at 400 kV and 765 kV is 61% and 84%respectively. If generators will absorb reactive power as per their capability curve thenadditional reactors may not be required to control Bus voltages. However, with the injectionof more RE power in the grid, some generating units may have to back down and capabilityof the grid to absorb reactive power will reduce. In such case, additional reactors may haveto be planned based on the feedback of POSOCO.
5.3.8 POSOCO mentioned that as per CEA’s Manual on Transmission Planning Criteria, reactivepower capability from generating units is to be considered as (-)10% Pmax for thermalgenerators. However, in present study analysis, reactive support from the generators isconsidered as more than 10%.
5.3.9 CTU clarified that detailed study analysis has been carried out in line with discussion held on1st SRSCT meeting, held on 07.09.2018, wherein 27 nos. of 125 MVAR, 420 kV bus
Minutes of 3rd meeting of Southern Regional Power Committee (Transmission Planning)
reactors were agreed after detailed deliberation. He reiterated that generally thermalgenerators have about reactive support capability of about (-)30-35% of Pmax. Therefore,planning bus reactors considering only (-)10% Pmax as reactive support capability of thegenerators will create huge margin into the system and it will be along with cost implicationto beneficiaries.
5.3.10 SRLDC informed that generators are absorbing reactive power from the grid as per theircapability on the directions of SRLDC. SRLDC also presented the P-Q capability curvealong with reactive power absorbed by 500 MW generating unit at RamagundamGenerating station. As per curve, 500 MW generating units is absorbing about 150 MVARat rated capacity.
5.3.11 Director, POSOCO, suggested to include the number of 400 kV & 765 kV transmissionlines to be opened on voltage regulation and the dispatch of generating unit during high/lowRE period in the reactive power compensation studies.
5.3.12 Sr. DGM (CTUIL) informed that, considering all the above reactors in operation, they arenot envisaging opening of any ISTS line for voltage regulation provided that theconventional generators absorbing the reactive power as per their capability curve.Regarding reactive power absorption capability of generating units, he opined that thereactive power absorption capability of generating units should not be restricted to 10% ofPmax. It should be adjusted depending on the margin available as per their capability curve,otherwise additional reactors may have to be planned. He also explained that generatorswith dispatch above the technical minimum were considered in service and all othergenerators are considered as out of service.
5.3.13 After deliberations, it was decided that the proposal of implementation of following BusReactors would be discussed in a joint study meeting to be conveyed for discussing reactivepower compensation issues of Southern Region:
Installation of 1x125 MVAR, 420 kV bus reactor proposed at Muddunur generation end.Presently there is no bus reactor at generator switchyard – Under the scope of Generator
Installation of 1x125 MVAR, 420kV bus reactor proposed at Velalivedu S/s – Under thescope of TANTRANSCO
The same would be discussed in the next SRPC(TP) meeting.
5.4. Requirement of ‘N-1’ Reliability for ICTs at RE Pooling Grid stations:
5.4.1. Director, CEA, stated that as per the Manual on Transmission Planning Criteria,“para 16.2 The ‘N-1’ criteria may not be applied to the immediate connectivity ofwind/solar farms with the ISTS/Intra-STS grid i.e. the line connecting the farm to the gridand the step-up transformers at the grid station”.
5.4.2. CTUIL stated that there is need to have ‘N-1’ security for step-up transformers atthe grid sub-stations, else loss of one ICT may lead to loss of total RE pooled at the
Minutes of 3rd meeting of Southern Regional Power Committee (Transmission Planning)
station. SRLDC in its quarterly report Q1 for the time period April’21-June’21 reportedsuch incident at Tuticorin-II GIS S/s and same is reproduced below.
“Presently 888 MW wind generation is getting evacuated at 400/230 kV TuticorinGIS through 2x500MVA 400/230 kV ICT#1 and ICT#2 from 4 numbers of WindStations namely 230/33 kV Betam, 230/33kV Mytrah, 230/33kV Orange and230/33/11kV Green Infra (Chandragiri). On 14-07-2021, 400/230kV ICT#1 at TTGSgot tripped due to suspected maloperation of Buchholz protection. After the trippingof ICT#1, entire power (735 MW generation prior to incident) got shifted to ICT#2and over current stage-1 protection operated as the current increased to max RMScurrent of 2300 A. Due to tripping of both ICTs, there was loss of wind evacuation of735MW. Similarly, N-1 condition is not satisfied at all the RE generation poolingstations”
5.4.3. Presently in Southern Region, large RE generation projects are under operation viz.Tumkur Solar Park (2050 MW commissioned), N P Kunta (1500 MW out of which 1300MW is commissioned), Tuticorin-II GIS (LTA granted for about 1100 MW + 540 MWagreed for grant) etc. In case of outage of large capacity RE generation, the possibility ofgrid eventuality may not be ruled out. In view of safety, security and reliability of grid, atleast from ‘N-1’ security point of view, for step-up transformers at ISTS pooling stationfor RE generators, it is proposed that ‘N-1’ contingency criteria may be considered forstep-up transformers at the grid stations (ISTS) and implementation of ICTs may be takenup accordingly.
Deliberations in 3 rd SRPC(TP) Meeting
5.4.4. Director, POSOCO, opined that installation of additional ICT should be consideredat ISTS RE generation pooling stations so that ‘N-1’ criterion is compiled and cascadetripping of ICTs could be avoided in case of any contingency. He added that loosing largequantum of RE power due to cascade tripping of transformers will affect the grid stability.
5.4.5. KPTCL opined that considering reliability of grid, N-1 reliability criterion forICT’s at RE pooling station shall be applied for RE generators connected at 220 kV andabove voltage class.
5.4.6. Representative from TANGEDCO opined that ‘N-1’ compliance for step uptransformers at RE pooling stations alone cannot prevent the loss of large quantum of REpower. ‘N-1’ compliance of the line connecting RE generation to the grid is also required.However, complying ‘N-1’ of transformers and line will add tariff burden to thebeneficiaries.
5.4.7. Member (Power System), CEA, stated that cascade tripping of ICTs at RE poolingstation would affect all the downstream network. However, during outage of thetransmission line connecting RE generation to the grid, the demand would be met throughother generating sources. Regarding tariff burden, he stated that as per new CERC tariffregulation, the tariff burden will be shared by all the states. As per the Manual on
Minutes of 3rd meeting of Southern Regional Power Committee (Transmission Planning)
Transmission Planning Criteria 2013, “para 16.2 The ‘N-1’ criteria may not be applied tothe immediate connectivity of wind/solar farms with the ISTS/Intra-STS grid i.e. the lineconnecting the farm to the grid and the step up transformers at the grid station”. Themanual is under revision and the issue is being deliberated by the committee constitutedfor revision of the Manual. Once the Manual is revised, the same would be adopted fortransmission planning.
B. ToR 2(ii) – ASSESSMENT OF TRANSMISSION SYSTEM REQUIREMENTS IN NEAR,MEDIUM AND LONG TERM AND FORMULATE TRANSMISSION SCHEME
6. Proposal for grant of connectivity to NLC India Ltd for TPS-II 2nd Expansion (2x660
MW) in Cuddalore, Tamil Nadu, and to control high short circuit fault level in Neyveli
Generation complex.
6.1. Proposal for grant of connectivity to M/s NLC India Ltd for Neyveli TPS-II 2nd Expansion
thermal power plant was discussed and agreed in the 2nd SRSCT meeting held on 10.06.2019
and subsequently in the 1st meeting of Southern Regional Power Committee (Transmission
Planning) held on 16.12.2019. In view of the connectivity requirements of Neyveli TPS-II 2nd
expansion from April, 2021, and commissioning of Manalmedu (TANTRANSCO) substation
by December, 2021, it was agreed in 1st SRPC(TP) meeting that LILO of 2nd circuit of
Neyveli TS-II / Neyveli TS-I Expn – Trichy 400 kV D/c line at Nagapattinam, shall be
restored only after commissioning of Manalmedu S/s, Neyveli TPSII 2nd Expn – Manalmedu
400 kV D/c (Quad) line and Manalmedu – Ariyalur 400 kV D/c line by TANTRANSCO.
6.2. Accordingly, following was agreed in the 2nd SRSCT/1st SRPC(TP) meeting(s):
Transmission System for providing connectivity to Neyveli TS-II 2nd Expn (2x660 MW):
i. Re-storation of Neyveli TS-II/Neyveli TS-I Expn - Trichy 400 kV D/c lines throughsuitable arrangement of bypassing the LILOs at Nagapattinam– to be implementedunder ISTS.
ii. Utilization of LILO sections for making Neyveli TPS-II 2nd Expn – Nagapattinam 400kV, 2xD/c lines upto Neyveli TPS-II 2nd Expn swithchyard - to be implemented underISTS.
iii. LILO of 2nd circuit of Neyveli TS-II / Neyveli TS-I Expn – Trichy 400 kV D/c line atNagapattinam shall be restored only after commissioning of Manalmedu S/s, NeyveliTPSII 2nd Expn – Manalmedu 400 kV D/c (Quad) line and Manalmedu – Ariyalur 400kV D/c line by TANTRANSCO.
iv. 2x125 MVAr bus reactors at generation switchyard (Neyveli TPS-II 2nd Expn) – byNLC India Ltd.
v. The line bays at generation switchyard would be implemented by NLC India Ltd. vi. Generation Switchyard to be designed with 50 kA short circuit level.
Additional System Strengthening for control of short circuit levels in Neyveligeneration complex and re-arrangement of network configuration to controloverloading of ICTs / 230 kV lines from Neyveli generation complex:
Minutes of 3rd meeting of Southern Regional Power Committee (Transmission Planning)
i. Neyveli TS-II – Cuddalore 400 kV D/c (Quad) line – under the scope of TANGEDCOas agreed in 1st SRSCT.
ii. Manalmedu – Neyveli TPS-II 2nd Expn 400 kV D/c (Quad) line (in place of Cuddalore– Manalmedu 400 kV D/c line agreed in 1st SRSCT) – under the scope ofTANGEDCO.
iii. Bypassing of one ckt. of Neyveli TS-II- Salem 400 kV D/c line of PGCIL and NeyveliTSII- NNTPS 400 kV S/c line of PGCIL, to form NNTPS-Salem 400 kV S/c line(agreed in 42nd SCPSPSR) – to be implemented under ISTS.
6.3. Subsequently, CTU vide email dated 12.03.2020 sought confirmation of start date of
connectivity and expected commissioning schedule of both the units of Neyveli TPS-II 2nd
Expansion. In reply to the email, M/s NLC India Ltd. has furnished the following information
towards start date of connectivity and expected commissioning schedule:
Date from which connectivity is required : Year 2024-25 (Tentative) Date of commissioning of Unit 1 : Year 2025-26 (Tentative) Date of commissioning of Unit 2 : Year 2025-26 (Tentative)
6.4. M/s NLC India Ltd. has revised the start date of connectivity from April, 2021, to the year
2024-25 (tentative). In view of the delayed schedule of commissioning of Neyveli TPS-II 2nd
Expansion, implementation of the associated transmission scheme may be required to be
phased by Tamil Nadu. Further, as per the revised schedule of commissioning of the
generating units, Manalmedu S/S shall be connected radially to Ariyalur till the
implementation of Manalmedu – Neyveli TPS-II 2nd Expn 400 kV D/c (Quad) line, which
shall be implemented matching with schedule of commissioning of generating units of
Neyveli TPS-II 2nd Expansion. Further LILO of 2nd circuit of Neyveli TS-II / Neyveli TS-I
Expn – Trichy 400 kV D/c line at Nagapattinam, shall be restored only after commissioning
of Manalmedu S/s, Neyveli TPS II 2nd Expn – Manalmedu 400 kV D/c (Quad) line and
Manalmedu - Ariyalur 400 kV D/c line by TANTRANSCO as agreed in the 1 st SRPC(TP)
meeting.
6.5. For transmission system augmentation and re-arrangement of network configuration, as
mentioned in para 6.2, firm commissioning schedule of Neyveli TS-II 2nd Expn (2x660 MW)
is required. As such, the augmentation/re-arrangement work would be taken up upon receipt
of firm commissioning schedule of Neyveli TS-II 2nd Expn (2x660 MW) from NLC India
Ltd.
6.6. In the 2nd SRPC (TP) meeting, representative of NLC informed that start date of connectivity
for Neyveli TPS-II 2nd Expn may be considered as 2025-26 (tentative). TANTRANSCO
representative informed that works for Manalmedu S/s is likely to start by January/February,
2021, and the substation is expected to be commissioned by 2022-23.
Minutes of 3rd meeting of Southern Regional Power Committee (Transmission Planning)
6.9. In the joint study meeting, it was agreed that the transmission system and its phasing would
be put up in the forthcoming meeting of SRPC(TP). Subsequently, revised connectivity for
Manalmedu has been proposed by TANTRANSCO. Hence, part of the scheme proposed
above would change depending upon the connectivity agreed for Manalmedu.
Deliberations in 3 rd SRPC(TP) meeting
6.10. TANTRANCO informed that NLCIL vide letter dated 09.12.2020 addressed to
CMD/TANGEDCO has stated that CoD of Neyveli TPS-II 2nd Expansion (2x660 MW) is
expected to be in the year 2026-27.
6.11. NLCIL informed that there are uncertainties in PPAs, except PPA (547 MW) with Tamil
Nadu and investment decision for this project is yet to be taken.
6.12. TANTRANSCO informed that in view of the delayed schedule of commissioning of Neyveli
TPS-II 2nd Expansion, implementation of the associated transmission scheme may be required
to be phased by Tamil Nadu.
6.13. After deliberations, it was agreed that the proposal for grant of connectivity to NLC India Ltdfor TPS-II 2nd Expansion (2x660 MW) will be discussed when commissioning schedule ofNeyveli TPS-II 2nd Expansion (2x660 MW) gets finalized. The connectivity application ofNLC India Ltd for Neyveli TPS-II 2nd Expansion (2x660 MW) would be closed and NLCILmay apply for connectivity after availability of firm commissioning schedule of thegeneration project.
7. Manalmedu 400/230-110 kV substation:
7.1. Establishment of Manalmedu 400/230-110 kV substation was approved in the 41st meeting of
SCPSPSR (held on 22.09.2017) with the following transmission schemes:
400 kV transmission lines:
i. Ariyalur (proposed 765/400kV SS) - Manalmedu 400 kV D/C link ii. Neyveli (TNEB)-Manalmedu 400 kV D/C link.
230 kV transmission lines:
i. LILO of Neyveli TS-II - Kadalangudi 230 kV SC line at Manalmedu.ii. Kumbakonam- Manalmedu 230 kV S/C line
iii. Narimanam- Manalmedu 230 kV S/C line.ICTs:
i. 2x500 MVA, 400/230 kV ICT ii. 2x200 MVA, 400/110 kV ICT
Bus reactor: 2x80 MVAr Bus reactors.
7.2. Due to constraints in land acquisition for the establishment of 400 kV S/S at Neyveli,
upgradation of the existing Cuddalore 230/110 kV substation into 400/230-110 kV SS instead
Thus the 400 kV connectivity for Manalmedu SS was modified as given below:
(i) Ariyalur 765/400 kV SS - Manalmedu 400 kV DC line.(ii) Cuddalore - Manalmedu 400 kV D/C line.
7.3. Further, in the 2nd SRSCT meeting held on 10.06.2019, as an additional system strengthening
scheme for control of short circuit levels in Neyveli generation complex and rearrangement
of network configuration to control overloading of ICTs/230 kV lines from Neyveli
generation complex, transmission schemes of the already proposed Manalmedu & Cuddalore
400 kV substations were modified as follows:
(i) Neyveli TS II - Cuddalore 400 kV D/c (Quad) line - under the scope of TANGEDCOas agreed in 1st SRSCT meeting.
(ii) Manalmedu - Neyveli TPS II 2nd Expansion 400 kV D/c (Quad) line (in place of Cuddalore – Manalmedu 400kV D/c line as agreed in 1st SRSCT) – under the scope of TANGEDCO
7.4. In the 2nd SRPC(TP) meeting, TANTRANSCO had proposed to revise the transmission
scheme for the establishment of 400/230-110 kV Manalmedu substation as given below:
Manalmedu 400/230-110 kV SS – original connectivity:
400 kV transmission lines:
i. Erection of 400 kV DC line from Ariyalur 765/400 kV SS to Manalmedu 400 kV SS.
ii. Erection of 400 kV DC line from the proposed Neyveli TS II 2nd Expansion TPP to
Minutes of 3rd meeting of Southern Regional Power Committee (Transmission Planning)
i. Erection of DC line to make LILO of Neyveli TS-II to Kadalangudi 230 kV feeder atManalmedu 400 kV SS.
ii. Erection of SC line to Kumbakonam 230 kV SS from Manalmedu 400 kV SSiii. Erection of SC line to Poyyur 230 kV SS from Manalmedu 400 kV SS.iv. Erection of DC line to the proposed Chidambaram 230 kV SS from Manalmedu 400
kV SS.v. Erection of DC line to the proposed Virudhachalam 230 kV SS from Manalmedu 400
kV SS.110 kV transmission lines
i. LILO of existing Kadalangudy-LTPCL-Manalmedu 110 kV feeder between LTPCLand Manalmedu substation.
ii. SC line to Kattumannar Koil 110 kV SS.iii. SC line to Sethiyathoppu 110 kV SS.iv. DC line to Pappakudi 110 kV SS.v. SC line to the sanctioned Naduvalur 110 kV SS.
Minutes of 3rd meeting of Southern Regional Power Committee (Transmission Planning)
230 kV transmission lines:i. Erection of D/C line to make LILO of Neyveli TS-II to Kadalangudi 230 kV feeder at
Manalmedu 400 kV SS.ii. Erection of S/C line to Kumbakonam 230 kV S/S from Manalmedu 400 kV S/S
iii. Erection of S/C line to Poyyur 230 kV S/S from Manalmedu 400 kV S/S.iv. Erection of D/C line to the proposed Chidambaram 230 kV S/S from Manalmedu 400
kV S/S.v. Erection of D/C line to the proposed Virudhachalam 230 kV SS from Manalmedu 400
kV S/S.110 kV connectivity
i. LILO of existing Kadalangudy-LTPCL-Manalmedu 110 kV feeder between LTPCL and Manalmedu substation.
ii. S/C line to Kattumannar koil 110kV S/S.iii. S/C line to Sethiyathoppu 110kV SS.iv. D/C line to Pappakudi 110kV S/S.
v. S/C line to the sanctioned Naduvalur 110kV SS.
Deliberations in 3 rd SRPC(TP) Meeting
7.12. TANTRANSCO informed that they had proposed Neyveli TS-II – Cuddalore 400kV (quad)
D/c line for connectivity to Cuddalore and LILO of one ckt of Neyveli TS-II – Cuddalore
400kV (quad) D/c line at Manalmedu. Once the Neyveli TS-II 2nd Expn is available, they will
Minutes of 3rd meeting of Southern Regional Power Committee (Transmission Planning)
towards sharing of charges of these reactors, it was informed that the same would be under
the scope of generator and shall not be part of ISTS transmission charges.
12.13. After detailed deliberations, it was agreed that connectivity application may be closed in case
of NPCIL does not respond as agreed above. However, upon receipt of confirmation from
NPCIL within stipulated time as agreed, connectivity may be granted to NPCIL for KKNPP-
3&4 through the following transmission system:
i. Bus extension of Kudankulam NPP Unit-1&2 generation switchyard with suitable bus
sectionalizer arrangement (under the scope of NPCIL);
or
Interconnection between KKNPP-1&2 and KKNPP-3&4 generation switchyards
through laying of 400 kV overhead transmission line or cable.
ii. 2x125 MVAR bus reactor at KKNPP-3&4 – under the scope of NPCIL
13. Implementation of bays at ISTS Substation under the scope of ISTS for termination of
dedicated line of RE generators:
13.1 1 no. of 230 kV bays at 400/230 kV Tuticorin Substation
13.1.1Director, CEA informed that in the 48th & 54th Southern Region constituents meetingregarding Connectivity/LTA applications held on 27.11.2020 & 28.05.2021 respectively,Stage-II Connectivity to M/s JSW Renew Energy Ltd. & M/s JSW Future Energy Ltd wasagreed for grant as per the following details:
13.1.2 In meeting, M/s JSW Future Energy Ltd had requested that implementation of bays at ISTSsubstation may be kept under the scope of ISTS licensee. As per clause 5.3 of the RevisedDetailed Procedure for Grant of connectivity to projects based on renewable sources toISTS,
Minutes of 3rd meeting of Southern Regional Power Committee (Transmission Planning)
“For Connectivity, the dedicated transmission line including line bay(s) at generatorpooling station shall be under the scope of the Applicant and the associated bay(s) atthe ISTS sub-station shall be under the scope of transmission licensee owning theISTS sub-station subject to compliance of relevant provisions of Tariff Policy.Provided that the Applicant may, if it so chooses, construct the associated bay(s) atits own cost, subject to approval of the CTU and agreement with the transmissionlicensee owning the ISTS sub-station.”
Accordingly, in 54th Southern Region constituents meeting, one 230 kV bay at Tuticorin-IIGIS PS was agreed for implementation under the scope of ISTS licensee in line with clause5.3 of the Revised Detailed Procedure for Grant of connectivity to projects based onrenewable sources to ISTS.
13.1.3CTUIL iformed that M/s JSWFEL vide letter dated 27.08.2021 has requested forimplementation of 230kV bay at Tuticorin-II substation by JSW Future Energy Ltd.Accordingly, the bays would not be required to be implemented under ISTS scope.
13.1.4Members noted the same.
13.2 1 no. 400 kV bay at 765/400 kV Kurnool (New) Substation
13.2.1Director, CEA informed that in the 46th Southern Region constituents meeting of CTUregarding Connectivity/LTA applications held on 28.09.2020, M/s Greenko AP01 IREP PvtLtd was granted 900 MW Stage-II Connectivity at Kurnool (New) substation as per thefollowing details:
Applicant
Nature ofapplicant
Location Stage-IConnecti
vityQuantum
(MW)
Stage-IIConnectivi
tyQuantum
(MW)
Startdateof
Stage-II
Connectivi
ty
locationfor Grantof Stage-
IIConnecti
vity
Dedicated TransmissionSystem
(Under scope of applicant)
Greenko AP01 IREP Pvt. Ltd.
Generator (Hybrid)Solar with storage
Kurnool, AP
900 900 04.02.22
Kurnool (New) 765/400 kV Substation
Greenko AP01 IREPPvt. Ltd – Kurnool New400 kV S/c line strungon D/c tower (with highcapacity conductorenabling at least 900MW power transfer atnominal voltage likequad moose conductoretc.) along with bay(s) atgenerator and Kurnool(New) end
13.2.2Subsequently, M/s Greenko AP01 IREP Pvt Ltd vide letter dated 25.11.2020, had requestedthat implementation of 400kV bay at Kurnool (new) end for termination of their dedicated
Minutes of 3rd meeting of Southern Regional Power Committee (Transmission Planning)
line may be kept under the scope of ISTS licensee. The matter regarding implementation ofbay under the ISTS was taken up for discussion in the 49 th Southern Region constituentsmeeting regarding Connectivity/LTA applications held on 29.12.2020. In the meeting, it wasagreed that 400 kV bay at Kurnool (New) substation may be implemented under the scopeof ISTS licensee in line with the clause 5.3 of the Revised Detailed Procedure for Grant ofconnectivity to projects based on renewable sources to ISTS.
13.2.3After deliberations, it was agreed to take up implementation of 400kV bay at Kurnool(New)substation under ISTS for grant of connectivity to Greenko AP01 IREP Pvt. Ltd.
14. Use of switchable line reactors as bus reactors at Kurnool Sub-Station:
14.1. Director, CEA, informed that in 37th SCPSPSR meeting held on 31st July 2014, the scheme
“Additional inter‐Regional AC link for import into Southern Region i.e. Warora – Warangal
and Chilakaluripeta ‐ Hyderabad ‐ Kurnool 765 kV link” was agreed as part of the System for
increasing capacity of Inter‐State Transmission system for import of power into SR up to
2018‐19. Scheme was awarded to M/s Essel Infra projects Ltd, through TBCB route. The
scheme includes Hyderabad– Kurnool 765 kV D/c line with 240 MVAR switchable line
reactor at Kurnool end. As per Gazette notification, POWERGRID to provide bays at
Kurnool 765kV S/s for termination of Hyderabad– Kurnool 765 kV D/c line with 240 MVAR
switchable line reactor at Kurnool end.
14.2. In 35th SRPC meeting held on 02.02.2019, following is noted.
“the nodes at Maheswaram and Kurnool were experiencing high voltages and foreffective management of the system, POSOCO was instructing closing and opening ofthe lines on a daily basis. For the TBCB line coming from Warora, PGCIL was carryingout the works of bay extension at Warangal, Maheswaram and Kurnool. The contractualschedule was around February/March 2019 while the lines were expected by November2019. However, PGCIL was ready with bays at Kurnool with two reactors (2 x 240MVAR) which could be energized by end of February 2019 or first week of March 2019.The reactors were likely to reduce the voltages of 765 kV node by 10 – 11 kV and about4-5 kV of 400 kV node at Kurnool, if the reactors are permitted to be commissioned bythe forum.”
After deliberation it was agreed for early commissioning (end of February 2019/first week ofMarch 2019) of the line reactors at Kurnool for voltage management.
14.3. As per latest status on 31.05.2021, the Hyderabad– Kurnool 765 kV D/c line got stuck in
severe RoW issue and also got impacted due to COVID-19. The anticipated CoD of the
scheme is October, 22. Further, SRLDC in its quarterly report for quarter-III & quarter -IV of
2020-21 has mentioned that voltage remains very high most of the time of whole year at
Minutes of 3rd meeting of Southern Regional Power Committee (Transmission Planning)
3. Karnataka 14367 16700 163004. Kerala 4284 6000 58005. Tamil Nadu 16481 24200 228006. Puducherry 421 650 570
Southern Region 58400 74650 74200
Detailed System Study results with ICTs flows at various substations in Southern Region aregiven at Annex-15. From the study results it is observed that loading on the ICTs at some ofthe substations are on higher side and the ICT augmentation is required at these sub-stations.
The list of substations under ISTS and STUs where transformation capacity augmentation isrequired are tabulated below:
Minutes of 3rd meeting of Southern Regional Power Committee (Transmission Planning)
informed that for augmentation of 1x500 MVA, 400/220 kV ICT at Kolar, cables will be
required for interconnection between ICT and 220 kV bus.
15.3. Towards augmentation of transformation capacity at Hosur S/s, POWERGRID informed that
ICT bays are not available for augmentation of transformation capacity. However, space is
available for future 400 kV line bays, however, due to severe RoW issues, these line bays
cannot be utilized for termination of line. Further, 1x63 MVAr bus reactor is installed
adjacent to 3x315 MVA ICTs and 220 kV switchyard. The 400/230kV, 1x500 MVA 4th ICT
may be accommodated by shifting of 63 MVAr bus reactor to available 400 kV line bays.
Accordingly, it is proposed that transformation capacity with 1x500 MVA, 400/230 kV ICT(4th) may be augmented at Hosur substation by shifting of 1x63 MVAR bus reactor toavailable 400 kV line bays with suitable arrangement.
15.4. Regarding, Narendra and Cochin substation, POWERGRID has informed that space is not
available for augmentation of 3rd and 4th ICT respectively.
15.5. In view of above, augmentation of transformation capacity is proposed at following locations.
Sl. No.
Transmission License
Substation
Voltage Level(kV)
Existing & UC ICTCapacity(MVA)
ExpectedICT loadings
(MW)
Proposed ICT augmentation Capacity (MVA)
Remarks
All ICTs inservice
With ‘N-1’
1. KPTCL Guttur 400/220
2x315 2x225 1x287 1x500
2. KPTCL Peenya 400/220
2x500 2x317 1x452 1x500
3. APTRANSCO
Kurnool400/220
3x315 2x228 2x288 1x500
APTRANSCO informedthat detailed study is beingcarried out on the proposalof 3rd ICT and theobservations will befurnished to CEA withstudy results. However, analternate arrangementmade in the 1st week ofMarch-2021 in 220 kVBus at 400 kV Ghani S/s.With this arrangement,loading on ICTs atKurnool were reduced.
4. APTRANSCO
Rachagunneri400/220
2x315 2x230 1x306 1x500
APTRANSCO informedthat 3rd 315 MVA ICT wasproposed to feed industrialloads and it is under study.Proposal along with studyresults will be furnished toCEA shortly.
5. APTRANSCO
Kakinadasez400/220
2x500 2x445 ----- 1x500APTRANSCO informedthat they will study andinform to CEA.
Minutes of 3rd meeting of Southern Regional Power Committee (Transmission Planning)
15.7. SRLDC in its operational feedback also mentioned that ISTS substation at Mysore is not
complying with 'N-1' contingency criteria of ICTs.
15.8. In this regard it may be pointed out that KPTCL has planned 2x500 MVA, 400/220 kV S/s at
Kadakola for relieving loading on ICTs at Mysore and meeting the increasing demand of the
area. The same was discussed and agreed in 2nd SRSCT meeting held on 10th June 2019.
However, it may be noted that Kadakola substation is yet to be awarded and can be expected
in 24 - 36 months.
However, loading of more than 100% may cause failure of entire Mysore S/s and may resultin blackout of large area in and around Mysore city. Till the commissioning of Kadkola S/s,loadings on ICTs at Mysore S/s shall remain critical.
15.9. In view of delayed commissioning of Kadkola S/s and critical loadings of ICTs at Mysore, it
was proposed that Mysore substation may be augmented with 1x500 MVA, 400/220 kV (4 th
ICT) transformation capacity. POWERGRID has informed availability of space for
Nizamabad(1x1500MVA), and 400/220 kV Kolar (1x500MVA)were agreed.
16. Short Circuit studies for Southern Region
16.1. Director, CEA, informed that in the 1st SRPC(TP) meeting held on 16.12.2019, CTU had
informed about the likely locations where high short circuit level could be observed for 2023-
24-time frame. In the meeting, it was decided that STUs may also carry out detailed studies
for identification of locations where fault levels were expected to cross the design limits and
suggest necessary measures for control of fault level. Details of short circuit current and
switchyard rating of ISTS and STU substations as informed are tabulated below.
Sl.No.
SubstationVoltage
level (kV)3-Ph
SC (kA)1-Ph
SC (kA)Ownership
Switchyard rating (kA) / Remarks
1. Maheshwaram-TS 400 63.7 45.5 TSTRANSCO 50
2. Maheshwaram 400 63.5 45.6 POWERGRID 63
3. Udumalpet 400 51.8 37.1 POWERGRID 40
4. Yadadri 400 49.3 49.9 TSTRANSCO 50
5. Chittor 400 47.4 33.5 APTRANSCO
APTRANSCO informed thatexisting switchyard rating is40 kA. The fault level isexpected to remain withindesign limits with the controlfault level at Thiruvalam S/s
Minutes of 3rd meeting of Southern Regional Power Committee (Transmission Planning)
Sl.No.
SubstationVoltage
level (kV)3-Ph
SC (kA)1-Ph
SC (kA)Ownership
Switchyard rating (kA) / Remarks
6. Dindi 400 46.9 33.2 TSTRANSCO 50
7. Edayarpalayam 400 46.7 33.3 TANTRANSCO 63
8. Tirunelveli 400 45.7 35.0 POWERGRID 40
9. Hyderabad-TS 400 45.5 31.0 TSTRANSCO 40
10. Kurnool 400 45.1 33.3 APTRANSCO
APTRANSCO informed thatexisting switchyard rating is40 kA. Rating of theSwitchgear of 400 kVGhani-Kurnool D/C linesand 400 kVJammalamadugu- KurnoolD/C lines is 50 kA (atKurnool S/s).
A study may be carried outto reduce the short circuitlevels at Kurnool S/s.
11. Kurnool 765 40.5 27.5 POWERGRID 40
16.1.1. In the 2nd SRPC(TP) meeting, it was decided that the scheme to control the fault level at
Maheshwaram-TS may be evolved through joint system study with participation from CEA,
SRPC, CTU, TSTRANSCO and POSOCO/SRLDC. It was also decided that scheme for
controlling fault level at Kurnool (APTRANSCO), Hyderabad-TS (TSTRANSCO),
Tirunelveli (POWERGRID) may be put-up for discussions in subsequent SRPC(TP)
meetings.
16.1.2. Accordingly, the proposal was discussed in the joint study meeting held on 04.02.2021. In the
meeting, Sr. GM (CTU) gave presentation on uprating of existing substation on increasing
short circuit current. He informed that following can inter-alia be implemented for mitigating
the short circuit fault level:
i. Up gradation of substation equipments
ii. Splitting of Bus bar
iii. Higher impedance transformer/ICTs for the proposed substation
16.2. Scheme to control fault level at Udumalpet S/s: The scheme to control fault level at
Udumalpet S/s was discussed in 2nd SRPC(TP) meeting. From the system studies for 2023-
24-time frame, the 3-phase short circuit levels at 400 kV bus of Udumalpet S/s were observed
to be of the order of about 49 kA, whereas the substation has been designed for 40 kA fault
Minutes of 3rd meeting of Southern Regional Power Committee (Transmission Planning)
17. Phasing of transmission system for evacuation of power from potential REZ in Karur &
Gadag
17.1. Transmission Scheme for Evacuation of power from RE sources in Karur/ Tiruppur
Wind Energy Zone (Tamil Nadu) (2500 MW):
Director (PSPA-I), CEA informed that the “Transmission Scheme for Evacuation of powerfrom RE sources in Karur/ Tiruppur Wind Energy Zone (Tamil Nadu) (2500 MW)” wastaken-up for discussion in the 4th NCT meeting held on 20.01.2021 and 28.01.2021, whereinphasing of the scheme was decided. Subsequently, MoP vide Gazette notification dated19.07.2021, has notified Phase I of the Scheme as given below:
Transmission Scheme for Evacuation of power from RE sources in Karur/ TiruppurWind Energy Zone (Tamil Nadu) (1000 MW) under Phase-I :
Establishment of 2x500 MVA, 400/230 kV Karur Pooling Station
LILO of both circuits of Pugalur – Pugalur (HVDC) 400 kV D/c line (with Quad MooseACSR Conductor) at Karur PS
4 Nos. of 230 kV line bays at Karur PS (to be implemented as part of ISTS)
2x125 MVAr, 400 kV Bus reactors at Karur PS
Space provision for Phase-II:o 400/230 kV ICTs along with bays: 3 nos.
o 230 kV line bays: 5 nos.
o 230 kV bus sectionalizer bays: 2 nos.
Adequate space provision for future expansion for: o 400/230 kV ICTs along with bays: 3 nos.
o 400 kV line bays: 6 nos.
o 230 kV line bays: 7 nos
The schedule of implementation would be matching with schedule of RE developers or 18months from the date of transfer of SPV, whichever is later.
Transmission Scheme for Evacuation of power from RE sources in Karur/ TiruppurWind Energy Zone (Tamil Nadu) (1500MW) under Phase-II :
Augmentation of 3x500 MVA, 400/230 kV at Karur PS
5 Nos. of 230 kV line bays at Karur PS (to be implemented as part of ISTS)
Phase-II scheme to be taken up only after receipt of Connectivity/LTA applications beyond1000 MW at Karur.
Deliberations in 3 rd SRPC(TP) Meeting
17.2. Representative of TANGEDCO opined that “Transmission Scheme for Evacuation of power
from RE sources in Karur/ Tiruppur Wind Energy Zone (Tamil Nadu) (1000 MW) under
Phase-I” should be implemented with 1x500 MVA, 400/230 kV ICT at Karur PS in place of
Minutes of 3rd meeting of Southern Regional Power Committee (Transmission Planning)
2x500 MVA, 400/230 kV ICT at Karur PS since LTA of only 100 MW has been granted at
Karur PS. Further he stated that during the special SRPC meeting, it has been recorded that
the proposal for phasing of transmission scheme was directly discussed in the NCT meeting
and should have been first discussed and agreed in the SRPC(TP) meeting with the
constituents.
17.3. Chief Engineer (PSPA-I), CEA, informed that phasing of the transmission scheme was
deliberated and agreed in the 4th NCT meeting and based on the recommendation of NCT,
MOP, has already issued gazette notification for the phasing of the scheme viz. 2x500 MVA
ICT in Phase-I and 3x500 MVA ICT in Phase-II.
17.4. Representative from SECI stated that all the issues pertaining to phasing of “Transmission
Scheme for Evacuation of power from RE sources in Karur/ Tiruppur Wind Energy Zone
(Tamil Nadu) (1000 MW)” were discussed in totality and agreed in the 4th NCT meeting.
17.5. Regarding interconnection of Pugalur HVDC with RE generators at Karur, CGM,
POWERGRID gave a brief presentation on the risk of commutation failure at Pugalur HVDC
due to its interconnection with nearby RE generations. The presentation is attached at Annex-
17. He stated that the following criteria needs to be met at 400 kV RE injection point for
smooth operation of HVDC at Pugalur terminal:
Harmonic limits shall be within the grid code defined limits
Voltage fluctuations shall be within the grid code defined limits
Frequency variations shall be within the grid code defined limits
Voltage unbalance shall be less than 1%
At any point, the RE connected feeder shall not be the only inter-connection to theRaigarh-Pugalur HVDC at Pugalur bus.
In future, in case any issues arises during RE integration, necessary control & protectionstudy and validation may be carried out.
17.6. Members noted.
17.7. Transmission scheme for evacuation of power from Gadag SEZ (2500 MW) - Part A:
Director (PSPA-I), CEA informed that the phasing of the scheme “Transmission scheme forevacuation of power from Gadag SEZ (2500 MW) - Part A” was discussed in the 4th NCTmeeting held on 20.01.2021 and 28.01.2021and subsequently, MoP vide Gazette notificationdated 19.07.2021, has notified Phase I of the Scheme as given below:
Transmission scheme for evacuation of 1000 MW from Gadag SEZ under Phase-I
Establishment of 400/220 kV, 2x500 MVA Gadag Pooling Station
Minutes of 3rd meeting of Southern Regional Power Committee (Transmission Planning)
220 kV line bays for interconnection of solar projects (4 nos)
1x125 MVAr (400 kV) bus reactor at Gadag PS
Future provisions:o Space for 400 kV Line bay with switchable line reactor: 8 nos.
o 400/220 kV ICT along with associated bay: 4 nos.
220 kV:o Bus sectionalizer bay: 2 nos. (One no. bay for each Main Bus)
o Bus coupler bay: 2 nos.
o Transfer Bus coupler bay: 2 nos.
o Space for future 400/220kV ICT bay: 4 nos.
o Space for future line bay: 8 nos.
The schedule of implementation would be matching with schedule of RE developers or 18months from the date of transfer of SPV, whichever is later.
Transmission scheme for evacuation of 1500 MW from Gadag SEZ under Phase-II
Augmentation of 400/220 kV, 3x500 MVA Gadag Pooling Station
Gadag PS - Koppal PS 400 kV (high capacity equivalent to quad moose) D/C Line
400 kV line bays at Koppal PS for Gadag PS- Koppal PS 400 kV D/c line
220 kV line bays for interconnection of solar projects (4 nos)
The Phase I as agreed would be adequate to evacuate power of 2500 MW Gadak andKoppal. However, the additional transformer system and Gadak-Koppal 400 kV line alongwith associated bays under Phase-II scheme to be taken up only after receipt ofConnectivity/LTA applications beyond 1000 MW at Gadag or beyond 1500 MW at KoppalP.S. The schedule of implementation of Phase-II of the scheme would be matching withschedule of RE developers or 18 months from the date of transfer of SPV, whichever islater.
17.8. Members noted the same.
18. Phase-I & Phase-II Solar & Wind Energy Zone Transmission Schemes
18.1. Transmission scheme for integration and evacuation of 18.5 GW REZ was discussed and
agreed in the 1st SRSCT meeting held on 07.09.2018 and 2nd SRSCT meeting held on
10.06.2019. Further, various issues related to availability of land, bidding, identification of
potential and All-India Studies were raised by TANGEDGO in various forums including
proceedings before CERC in the petition no. 200/MP/2019, which were deliberated in the 1st
SRPC(TP) meeting held on 16.12.2019. Status of availability of land, bidding and
applications in various REZ were further informed in the 2nd SRPC(TP) meeting held on
01.10.2020, however, due to paucity of time, the agenda could not be discussed completely
and it was decided that same may be taken up in the next SRPC(TP) meeting.
h) Common transmission system strengthening in Southern Region for enablingevacuation and export of power from Solar & Wind Energy Zones in Southern Region
18.3. As per discussions in 2nd SRSCT meeting, the above transmission system is a broad master
plan to serve integration of RE generation potential assessed in Tamil Nadu, Karnataka and
Andhra Pradesh for period upto 2021-22. As such, it was agreed that the scheme would be
implemented as ISTS, consequent to grant of LTA by CTU. The transformation capacity at
various sub-stations and certain elements may be required to be reviewed based on LTA
applications. Accordingly, this broad master plan would be implemented in stages to serve
RE integration.
18.4. As per information furnished by SECI, status of land availability for setting up of RE
generation projects (18.5 GW) in Southern Region is detailed below:
Land is available in Gadag (2500 MW SEZ) and Koppal (2500 MW WEZ) andGovernment of Karnataka has already identified the land. However, Koppal wasoriginally envisaged as Wind Energy Zone but SECI has now proposed to developKoppal as a SEZ/Hybrid.
Regarding Bidar (2500 MW SEZ), Karnataka, land is yet to be firmed up.
Land is available in Ananthpuram (2,500 MW SEZ) and Kurnool (2,500 MW SEZ,3,000 MW WEZ) Andhra Pradesh.
Regarding Karur WEZ (2,500 MW), Tamil Nadu Government has raised specificconcerns about the availability of land for the identified potential of 2500 MW.Regarding Tirunelveli WEZ (500 MW), Tamil Nadu Government has not confirmed theavailability of land.
18.5. Further, the following were also decided in the 1st SRPC(TP) meeting:
i. SECI would share the RE potential assessment study/report for 18.5 GW of envisagedRE potential in states of Andhra Pradesh, Karnataka and Tamil Nadu with CEA/CTU/SRPC and with STU’s of SR.
ii. SRPC would co-ordinate with states to find out the RE potential already developed
Minutes of 3rd meeting of Southern Regional Power Committee (Transmission Planning)
and the balance RE potential which could be developed in different locations(connected to ISTS as well as intra-state network), based on availability of land andother infrastructure within two months and forward their findings to CEA.
iii. SECI/MNRE to confirm whether the assessed RE potential at different locations inSouthern Region includes the potential being developed in intra-state system orexcludes the same. For example, whether the RE potential (2.5 GW) at Koppal,Karnataka, is the total potential of Koppal area and includes the RE potential (of about1 GW) being developed by KPTCL in Koppal or is over and above the potential beingdeveloped by KPTCL.
iv. SECI was requested to expedite the bidding process of planned RE capacity inSouthern region so as to avoid mismatch between commissioning of RE capacity andassociated transmission system.
v. Accordingly, CEA/CTU may review the transmission plans/schemes based on theabove.
18.6. SECI along with NIWE, made a presentation on assessment of 18.5 GW RE Potential in
states of Andhra Pradesh, Karnataka and Tamil Nadu at TNEB Headquarters Chennai
on 11th February 2020.The meeting was attended by SR constituents.
18.7. In the 2nd SRPC(TP) meeting, Director (PSPA-I), CEA, stated that out of 18.5 GW of RE
potential, land availability corresponding to 5.5 GW of RE (Karur - 2.5 GW, Tirunelveli – 0.5
GW and Bidar – 2.5 GW) is yet to be finalized. Chief Engineer (PSPA-I), CEA, requested
SECI to furnish the details of land availability in Koppal, Gadag, Kurnool and
Ananthapuram. Towards this, representative of SECI stated that land has been finalized by
A.P. government for setting up RE generation projects in Ananthpuram and Kurnool and the
same will be formalized within two months. He also informed that SECI has invited bidders
to set up solar park of 2,500 MW capacity in Koppal. He further clarified that SECI has not
identified Koppal as SEZ only, Koppal may be developed as a hybrid zone and has the
potential for both solar and wind power. Regarding Gadag, land is available corresponding to
2,100 MW of solar power.
18.8. Representative from TANGEDCO stated that as per the directions of CERC, SECI has been
asked to file an affidavit for the following for each RE location in Southern Region:
Firm availability of land.
Status of bidding.
Status of LTA application.
Whether RE power can be evacuated through existing transmission system or augmentation is required.
Whether the proposed transmission network for evacuation of RE power can be taken up independently and in phased manner
Subsequently, SECI has filed an affidavit informing that land is available in Koppal todevelop 2.5 GW of solar park. However, as per TANGEDCO, SECI, has not provided any
D/c line has been agreed for reconductoring with twin HTLS in the 3rd WRPC(TP) meeting
held on 14.06.2021 as regional system strengthening scheme. The same shall be required for
evacuation of surplus power from generation projects in above prioritized REZ. In addition,
deliberations are going on in Western Region for identification of additional strengthening
beyond Kolhapur for export of surplus power from SR under high RE generation scenario.
18.19.Representative from KPTCL & TANGEDCO enquired about the dispatches considered at
prioritized REZ and whether the nature of generation i.e. Solar, wind & hybrid REZ has been
considered in the studies. Towards this, CTU stated that the transmission system has been
planned for evacuation of power commensurate to the LTA at these REZ. It has been
observed that RE developers install generation more than the LTA quantum so as to honour
the provisions of PPA for supply of LTA quantum to the identified beneficiary. Accordingly,
full potential of 2.5 GW has been considered in the studies each for Koppal, Gadag and Karur
REZ and 0.5 GW at Tuticorin REZ. It was requested that CTUIL may share the study files
with constituents for their analysis. CTU agreed for the same.
18.20.Accordingly, the following transmission system was proposed to be taken-up for
implementation as given below:
a) Transmission Scheme for Evacuation of power from RE sources in Karur/Tiruppur Wind Energy Zone (Tamil Nadu) (2500 MW) – with phasing asdiscussed in para 17.1.
b) Transmission scheme for evacuation of power from Gadag SEZ (2500 MW) -Part A- with phasing as discussed in para 17.7.
c) Transmission scheme for Evacuation of power from RE sources in Koppal REZ(Karnataka) (2500MW)
18.21.Representative of SECI informed that out of 1200 MW Stage-II connectivity granted at
Koppal P.S., LTA for 600 MW has already been granted. Discussions for PSA signing with
Rajasthan for additional 600 MW was expected to be concluded shortly and LTA application
for the same shall be submitted to CTU shortly. Further, several location (Koppal) specific
Minutes of 3rd meeting of Southern Regional Power Committee (Transmission Planning)
conductor having minimum capacity of 2100MVA per circuit at nominal voltage
Augmentation of Narendra (New) by 1x1500 MVA, 765/400 kV ICTs
19.12.Further, in the 3rd meeting of NCT held on 20th & 28th January, 2021, it was agreed that
Strengthening of Kolhapur (PG) - Kolhapur (MSETCL) 400 kV section may be taken in
RPC(TP) based on the operational constraint reported by POSOCO. Subsequently, POSOCO
vide letter dated 02.02.2021 has intimated that during December, 20 – January,21 period,
power flow in the Kolhapur (PG) - Kolhapur(MSETCL) 400 kV D/c line has been observed
very high with ‘n-1’ non-compliance. NLDC and RLDCs are taking various measures in
operations such as reduction in power order of HVDCs toward southern region (Talcher –
Kolar, Bhadravati, Raigarh – Pugalur) to relive the loading of Kolhapur (PG) – Kolhapur
(MSETCL) 400 kV D/c line. The issue shall be aggravated with the injection of power at
Narendra (New), from the identified REZ potential in Koppal and Gadag together with
generation from Kudgi TPS.
19.13.Transmission system requirement for export of power from Southern Region to Western
Region has been deliberated with WR constituents in the 3rd WRPC(TP) meeting wherein the
following was agreed:
Re-conductoring of Kolhapur (PG) – Kolhapur 400 kV D/c line with conductor ofminimum capacity of 2100 MVA/Ckt at nominal voltage along with bay upgradationwork at Kolhapur (MSETCL).
The strengthening requirement beyond Kolhapur other than re-conductoring ofKolhapur (PG) – Kolhapur 400 kV D/c line would be studied in separate joint studymeeting with CEA, CTU, WRPC & POSOCO.
19.14. Due to paucity of time this agenda could not be discussed and the same would be discussed
in the next SRPC(TP) meeting.
20. Assessment of online Dynamic Line Rating
20.1. As per the directions of CERC regarding implementation of assessment of Dynamic Line
Loadings in real time / day ahead for optimal utilization of transmission lines, the matter was
discussed in 37th SRPC and 167th OCC meetings held on 01.02.2020 and 13.03.2020
respectively. In the OCC meeting it was decided that SRPC may take up the matter with
POSOCO/CTU to have a pilot project on any critical line in Southern Region. Member
Secretary, SRPC vide letter dated 16.03.2020 had requested to have a pilot project on any
critical line in Southern Region. KSEB has proposed installation of the system for dynamic
loadings on Udumalpet–Palakad 400 kV D/c line.
20.2. In view of above, Udumalpet – Palakad 400 kV D/c line (line length 95 km.), Tuticorin PS –
Madurai 400 kV D/c (quad) line (line length 95 km), N. P. Kunta – Kolar 400 kV S/c line
(line length 130 km) or any other transmission line may also be considered as potential
Minutes of 3rd meeting of Southern Regional Power Committee (Transmission Planning)
Sl.No.
Application No.
Applicant Location Stage-IIConnectivity (MW)
Start Dateof Stage-II
connectivity
Location forgrant ofStage-II
Connectivity
DedicatedTransmission
System
1 1200002672
GreenkoAP01 IREPPvt Ltd
BrahmanPalle,Kurnool,AP
900 04-Feb-22Kurnool(New)
Greenko AP01 IREPPvt. Ltd. – KurnoolNew 400kV S/c linestrung on D/c towers(with high capacityconductor enabling atleast 900 MW powertransfer at nominalvoltage like QuadMoose conductor etc.)along with line bay atgeneration end underthe scope of applicantand one bay atKurnool New S/sunder the scope ofISTS.
48th Conn/LTA meeting held on 27.10.2020
21200002868
JSW RenewEnergy Ltd.
Tiruppur,Tamil Nadu
310(reduced to270 MW in
55th
meeting)
31-Oct-22 oravailabilityof commontransmissionsystem forConnectivity, whicheveris later
Karur (PS)
JSW Renew EnergyLtd – Karur PS230kV S/c line (withequivalent conductorenabling at least 310MW power transfer atnominal voltage)
31200002869
JSW RenewEnergy Ltd.
Tuticorin,Tamil Nadu
500 31-Oct-22Tuticorin-IIGIS
JSW Renew EnergyLtd – Tuticorin-II230kV D/c line withbay at generator endunder the scope ofapplicant and bays atISTS end under thescope of ISTSlicensee
41200002872
VenaEnergyVidyuth PvtLtd
Koppal,Karnataka
160
31-May-22oravailabilityof commontransmissionsystem forConnectivity, whicheveris later
Gadag PSVena Energy VidyuthPvt Ltd – Gadag PS220kV S/c line
51st Conn/LTA meeting held on 26.02.2021
51200003011
BoreasRenewableEnergy PvtLtd
Nimbalagiri,Bellary,Karnataka
175 01.04.2022 Hiriyur
Boreas RenewableEnergy Pvt Ltd –Hiriyur 220kV S/cline along with baysat both ends under thescope of applicant
Minutes of 3rd meeting of Southern Regional Power Committee (Transmission Planning)
Sl.No.
Application No.
Applicant Location Stage-IIConnectivity (MW)
Start Dateof Stage-II
connectivity
Location forgrant ofStage-II
Connectivity
DedicatedTransmission
System
52nd Conn/LTA meeting held on 31.03.2021
61200003076
VientoRenewablesPvt Ltd
Thoothukudi, TamilNadu
79.80 15.03.2022 Tuticorin-II
Through dedicatedline of GRT Jewellers(India) Pvt LtdGRT – Tuticorin-II230kV S/c line
53rd Conn/LTA meeting held on 28.04.2021
71200003181
AyanaRenewablePower SixPvt Ltd
Gadag,Karnataka
300 01.08.2022 Koppal PS
Ayana RenewablePower Six Pvt Ltd –Koppal 220kV S/cline along with 220kVbay at generation endunder the scope ofapplicant and bay atKoppal PS under thescope of ISTS
54th Conn/LTA meeting held on 28.05.2021
81200003212
JSW FutureEnergy Ltd
Tiruppur,Dindigul,Tamil Nadu
150 31.10.2022 Karur PS
JSW Future EnergyLtd – Karur 230kV S/c line along with230kV bay atgeneration end underthe scope of applicantand bay at Karur PSunder the scope ofISTS
91200003214
JSW FutureEnergy Ltd
Tuticorin,Tamil Nadu
300 31.10.2022 Tuticorin-IIJSW Future EnergyLtd – Tuticorin-II230kV S/c line
101200003221
AdaniRenewableEnergyHoldingFifteen Ltd
Gadag, Karnataka
300 30.12.2022 Koppal PS
Adani RenewableEnergy HoldingFifteen Ltd - Koppal220kV S/c line alongwith 220kV bay atgeneration end underthe scope of applicantand bay at Koppal PSunder the scope ofISTS
111200003242
Renew SolarPower PvtLtd
Gadag,Bagalkote,Koppal,Karnataka
300 31.10.2022 Gadag PS
Renew Solar PowerPvt Ltd – Gadag PS220kV S/c line alongwith 220kV bay atgeneration end underthe scope of applicantand bay at Koppal PSunder the scope ofISTS.
Minutes of 3rd meeting of Southern Regional Power Committee (Transmission Planning)
Sl.No.
Application No.
Applicant Location Stage-IIConnectivity (MW)
Start Dateof Stage-II
connectivity
Location forgrant ofStage-II
Connectivity
DedicatedTransmission
System
55th Conn/LTA meeting held on 28.06.2021
121200003254
Renew SolarPower PvtLtd
Gadag,Bagalkote,Koppal,Karnataka
300 31.12.2022 Koppal PS
Renew Solar PowerPvt Ltd – Koppal PS220kV S/c line on D/ctower along with220kV bay atgeneration end underthe scope of applicantand 220kV bay atKoppal PS under thescope of ISTS
56th Conn/LTA meeting held on 27.07.2021
131200003300
ZenatarisRenewableEnergy PvtLtd
Nimbalagiri,Bellary,Karnataka
125 30.07.2022 Hiriyur
Through sharing ofdedicatedtransmission line ofM/s BoreasRenewable EnergyPvt Ltd (BREPL) i.e.Boreas RenewableEnergy Pvt Ltd –Hiriyur 220kV S/cline along with baysat both ends under thescope of M/s BREPL
21.2. Further, following Connectivity application of NTPC for proposed solar plants at
Kayamkulam within premises of the existing NTPC Kayamkulam plant was agreed for grant
Minutes of 3rd meeting of Southern Regional Power Committee (Transmission Planning)
Sl.No.
Name ofExisting
Substation
MVACapacit
y
Total220kV
Bays
Total Un-
utilizedbays
Remarks Deliberations in 3rd SRPC(TP)meeting
242. Yelahank
a2x500MVA
10 4 ConstructionofdownstreamT/L for 4Nos 220 kVbays to beexpedited byKPTCL.
220 kV Yelahanka – DGPlant 2000sq mm UG cable 2runs – Commissioned
Proposal for strengthening ofBengaluru transmissionnetwork to utilize theremaining bays at Yelahankais under planning.
KPTCL informed that fullcapacity of 2x500 MVAtransformer may be utilizedthrough 220 kV Yelahanka –DG Plant 2x2000 sq mm UGcable.
3. Bidadi 2x500MVA
6 4 ConstructionofdownstreamT/L for 4Nos 220 kVbays to beexpedited byKPTCL.
220 kV D/c line betweenBidadi (PG)- Bidadi(KPTCL) – Commissioned
220 kV D/c line Bidadi –Magadi – Commissioned
220 kV Bidadi – Kumbalgod– 1200 sq mm UG cable S/cline – under execution.
220 kV S/c line identified toKampagada layout – 220 kVbay with UG Cable isproposed for utilization ofconstructing 220 kV line toproposed switching station atV. Valley. Target by April,2024.
4. Hiriyur 2x315MVA
6 2 ConstructionofdownstreamT/L for 2Nos 220 kVbays to beexpedited byKPTCL.
220 kV Hiriyur – Chitradurgavia Thallak to Hiriyur –Commissioned.
Minutes of 3rd meeting of Southern Regional Power Committee (Transmission Planning)
Sl.No.
Name ofExisting
Substation
MVACapacit
y
Total220kV
Bays
Total Un-
utilizedbays
Remarks Deliberations in 3rd SRPC(TP)meeting
220 kV Hiriyur (PGCIL) –Chitradurga. – underexecution, target by Nov’21
5. Hassan 2x315MVA
6 2 ConstructionofdownstreamT/L for 2Nos 220 kVbays to beexpedited byKPTCL.
LILO of B4 circuit ofShimoga – Bangalore 220kVat Hassan – underexecution, target by March,2022.
6. Kolar 2x500MVA
6 2 ConstructionofdownstreamT/L for 2Nos 220 kVbays to beexpedited byKPTCL.
220 kV D/c line Kolar(PG) –Kolar(KPTCL)Commissioned.
220 kV D/c line Kolar –Chintamani –Commissioned.
2 Nos 220 kV downstream T/L to Gollahalli – 220 kVGollahalli S/s along with 220kV lines were commissionedon 15.03.2021. 66 kV lineswould be commissioned bySeptember, 2021.
7. Kozhikode
2×315+
1x500MVA
4 1 ConstructionofdownstreamT/L for 1Nos 220 kVbay to beexpedited byKSEB.
KSEB is enhancing thecapacity of existing 3 nos. of220 kV feeders from 400kVKozikode (PGCIL) S/s to 220kV Areekode (KSEB) S/s bychanging from single mooseconductor to double mooseconductor. With theupgradation of existing 3 nos.of feeders, the power transfercapacity at 400 kV Kozikodesubstation would be fullyutilized. Accordingly, KSEBis not planning to constructthe 4th 220 kV feeder between400 kV Kozikode (PGCIL) S/
Minutes of 3rd meeting of Southern Regional Power Committee (Transmission Planning)
Proposed Connectivity:
`
25.4. The proposal was discussed in the joint study meeting held on 04.02.2021 and after
deliberations, KPTCL was requested to carry out following additional studies:
Line loading considering full generation of about 3000 MW at Sharavathy existingand Sharavathy Pumped Storage Project.
Line loading when Sharavathy Pumped Storage Project would be operating inpumping mode (during off peak load hours or during high RE generation period).
To review the ICT requirement at Talaguppa, if required. And it was decided to discuss the matter subsequently in separate meeting with KPTCL,CTU, CEA and SRLDC and the scheme would be subsequently put up in the forthcomingSRPC(TP) meeting.
25.5. Accordingly, matter was discussed in the meeting held on 19.05.2021. KPTCL carried out
study for the above scenarios and proposed following additional connectivity:
i. Establishing 400 kV Switching station at Sirsi with Double circuit LILO of 400 kV
Kaiga-Guttur DC line.
ii. Construction of 400/220 kV MC/MV Double circuit line with Quad Moose
conductor/Twin equivalent HPC from proposed Sharavathy Pumped Storage Station to
proposed 400 kV Switching station at Sirsi limits in existing 220 kV DC Sharavathy-
Sirsi line corridor.
iii. Provision for 1x125 MVAr Bus Reactor at proposed 2000 MW Sharavathy Pumped
Storage Plant.
iv. Strengthening of 400kV S/C Twin Moose line between Dhoni-Guttur by DC line with
1.3. APTRANSCO had carried out system studies for the following scenarios considering an
annual peak electricity demand of 14,611 MW by the year 2022-23. A maximum capacity
factor of 75% has been taken for wind and solar power as per Transmission Planning Criteria.
Scenario 1: Full Solar Full Wind (75% Solar, 75% wind)Scenario 2: Full Solar Full Wind (75% Solar, 75% wind, RTPP NIL)Scenario 3: Full Solar Less wind (75% Solar, 40% wind)Scenario 4: Full Solar, No wind (75% Solar, 0% wind)Scenario 5: Less Solar, Full wind (40% Solar, 75% wind)Scenario 6: No Solar, Full wind (0% Solar, 75% wind)Scenario 7: Less Solar, Less wind (40% Solar, 40% wind)Scenario 8: No Solar, No wind (0% Solar, 0% wind)
1.4. Based on the system studies for the 6,100 MW Solar Power, the following evacuation lines
are proposed for evacuation of 6,100 MW of Solar Power in Prakasam, YSR Kadapa and
Minutes of 3rd meeting of Southern Regional Power Committee (Transmission Planning)
Sl.No. Description
RevisedSolarPower
Capacity
Revised Network for evacuation andDeletion of earlier proposed Lines
1 C.S. Puram PoolingStations-1&2 to
Pamur SubstationPrakasam Dist.
600 MW 1) 220 kV TMSC Line (4 km) from PS-1 toCommon Tower, 220 kV TMSC Line (4km) from PS-2 to Common Tower and 220kV TMDC Line (15 km) from commonTower to Pamur SS.2) Upgradation of existing 132 kVSS/Pamur into 220 kV SS.3) Double LILO of existing 220 kV SMDCLine from 400 kV SS/Podili to Atmakur toPamur SS (13.5 km).
600 MW 220 kV TMSC Line (8 km) from PS-1 toCommon Tower, 220 kV TMSC Line (4km) from PS-2 to Common Tower and 220kV TMDC Line (38 km) from commonTower to 220 kV SS/Podili.
3 Pendlimarri PoolingStations-1&2 to
proposed PendlimarriSw. Station,
YSR Kadapa Dist.
500 MW 1) 220 kV TMSC Line (3 km) from PS-1 toCommon Tower, 220 kV TMSC Line (4km) from PS-2 to Common Tower and 220kV TMDC Line (6 km) from commonTower to proposed 220 kV Sw. Station atPendlimarri.2) Double LILO of existing 220 kVMuddnuru(RTPP)-Chinakampalli SMDCLine to Pendlimarri Sw. Station dulyconverting it as TMDC. Towers are suitablefor Twin Moose DC.
Minutes of 3rd meeting of Southern Regional Power Committee (Transmission Planning)
Sl.No. Description
RevisedSolarPower
Capacity
Revised Network for evacuation andDeletion of earlier proposed Lines
4 M. KambaladinnePooling Stations-1&2
to 400KVSS/Jammalamadugu,
YSR Kadapa Dist.
500 MW 220 kV TMSC Line (2 km) from PS-1 toCommon Tower, 220 kV TMSC Line (5km) from PS-2 to Common Tower and 220kV TMDC Line (20 km) from commonTower to the existing 400 kV/SSJammalamadugu.
5 Urichinthala PoolingStations-1&2 to
400KVSS/Talaricheruvu,Anantapur Dist.
600 MW 220 kV TMSC Line (4 km) from PS-1 toCommon Tower, 220 kV TMSC Line (1km) from PS-2 to Common Tower and 220kV TMDC Line (6 km) from commonTower to the existing 400 kV/SSTalaricheruvu.
6 Mudigubba PoolingStations-1&2 to the
proposed Sw. Stationat Mudigubba,
Anantapur Dist.
500 MW 1) 220 kV TMSC Line (4 km) from PS-1 toCommon Tower, 220 kV TMSC Line (3km) from PS-2 to Common Tower and 220kV TMDC Line (7 km) from commonTower to the proposed Sw. Station atMudigubba2) Making Double LILO of 220 kVPulivendula-Mutyalacheruvu SMDC Line(5 km) which is (under construction) to theproposed Mudigubba Sw. Station.
7 Chakrayapeta PoolingStations-1&2 to theexisting 220KV SS/Chakrayapeta, YSR
Kadapa Dist.
500 MW 1) 220 kV TMSC Line (2 km) from PS-1 toCommon Tower, 220 kV TMSC Line (2km) from PS-2 to Common Tower and 220kV TMDC Line (8 km) from commonTower to the existing 220 kVSS/Chakrayapeta2)220 kV TMDC line from the existing 220kV SS/ Chakrayapeta to the existing 400kV SS/ Kalikiri (80 km).
400 MW 1) 220 kV SMDC line (30 km) from PS-1to the existing 220 kV SS/Kondapuram
2) 220 kV SMDC line (35 km) from PS-2to the existing 220 kV SS/Yerraguntla
9 Pampanur TandaPooling Stations-
1,2,3&4 to proposedSw. Station at
Pampanur Tanda,Anantapur Dist.
1300 MW 1) 220 kV TMSC Line (3 km) from PS-1 toCommon Tower, 220KV TMSC Line(3KM) from PS-2 to Common Tower and220KV TMDC Line (4 km) from commonTower to the proposed Sw. Station atPampanur Tanda.
Minutes of 3rd meeting of Southern Regional Power Committee (Transmission Planning)
Sl.No. Description
RevisedSolarPower
Capacity
Revised Network for evacuation andDeletion of earlier proposed Lines
2) 220 kV TMSC Line (3 km) from PS-3 toCommon Tower, 220KV TMSC Line (3km) from PS-4 to Common Tower and220KV TMDC Line (4 km) from commonTower to the proposed Sw. Station atPampanur Tanda.
10 Kolimigundla PoolingStations-1&2 to
400KVSS/Talaricheruvu,Anantapur Dist.
600 MW 220 kV TMSC Line (2 km) from PS-1 toCommon Tower, 220KV TMSC Line (2km) from PS-2 to Common Tower and 220kV TMDC Line (15 km) from commonTower to the existing 400 kV SS atTalaricheruvu
Total Capacity 6100 MW
1.5. In addition, the following transmission schemes had also been proposed by APTRANSCO.
1 Proposal for extension of Power Supply for a CMD of 400 MVA to the proposed Industrial Park at Guttapadu by APIIC:i. Laying 220 kV TMDC Line from 400 kV Ghani SS to the proposed
Switching Station at Guttapadu (14 km length) and ii. Making Double LILO of the 220 kV Narnur-Somayajulu Palli DC line at the
proposed Switching Station at Guttapadu (7 km)
The already approved transmission schemes in AP and changes proposed by APTRANSCO
are given below:
Sl. No. Schemes approved earlier Revised Proposals/Remarks1 400 kV Jammalamadugu
(Kondapuram) - Ghani QMDC line as per 38th SCPSPSR
Dropped.
Proposed Lines:a) 400 kV QMDC line fromTakaricheruvu to Podili b) 400 kV TMDC Line fromJammalamadugu (Kondapuram) to RTPP
2 400KV SS Uravakonda:a) 2x315 + 2x500 MVA ICTs
b) 220 kV DC line from 220 kVVajrakarur SS to 220 kV AnanthapurSS
as per 40th Standing CommitteeMeeting.
a) Proposed 4x500 MVA ICT to meet theN-1 contingency.
b) Dropped.
3 400kV Talarichervu SS: 3x315 MVA ICT as per 40th StandingCommittee Meeting.
Minutes of 3rd meeting of Southern Regional Power Committee (Transmission Planning)
Sl. No. Schemes approved earlier Revised Proposals/Remarks4 400/220kV SS at Mylavaram
3x315 MVA ICTs and 1x125 MVARBus reactor and 400kV QMDC linefrom 400kV Jammalmadugu–Mylavaram SS (2 km) for evacuationof 1000 MW of Solar Power atMylavaram (1000MW Solar Powerof Kadapa Ultra Mega Solar Park ofAPSPCL) as per 40th StandingCommittee Meeting.
Dropped.
1000MW will be evacuated to 400 kV Jammalamadugu (Kondapuram) Substation:a) PS-1 to Jammalamadugu SS: 220kV
TMDC/SC line: 12.5 km b) PS-2 to Jammalamadugu SS: 220kV
TMDC/SC line: 10.0 km c) PS-3 to Jammalamadugu SS: 220kV
SMDC line: 8.0 km d) PS-4 to Jammalamadugu SS: 220kV
SMDC Line: 9.8 km (Alreadycommissioned)
5 400 kV Jammalamadugu SS (Kondapuram): 3x315 MVA ICTs as per 40th
Standing Committee Meeting.
Proposed 2x500 +2x315 MVA ICTs
6 220 kV Single Moose DC line from 400/220 kV Hindupur SS to 220 kVPampanur Tanda SS as per 40th
Standing Committee Meeting.
Proposed 220 kV Twin Moose DC line from 400/220 kV Hindupur SS to 220 kVPampanur Tanda SS.
1.6. In the 2nd SRPC(TP) meeting, it was decided that the transmission scheme proposed by
APTRANSCO would be studied in detail in a joint meeting of CEA, SRPC, CTU, POSOCO/
SRLDC and APTRANSCO and the scheme would be put up in the next SRPC(TP) meeting
for discussion.
1.7. Accordingly, the proposal was discussed in the joint study meeting on 04.02.2021. After
detailed deliberation, it was decided that APTRANSCO will carry out studies on the all-India
study file prepared in consultation with SR constituents, for the following nine scenarios:
June- afternoon, evening, late nightAugust- afternoon, evening, late nightFebruary- afternoon, evening, late night
and the study results will be discussed in the separate meeting with CEA, CTU and SRLDC
and the transmission system emerged from the study would be discussed in the forthcoming
Minutes of 3rd meeting of Southern Regional Power Committee (Transmission Planning)
iii. In case, any constraints / congestion are observed in the ISTS grid due to injection of
power from the proposed solar generators or non-backing down of thermal generators
during high RE generation, APTRANSCO would apply for LTA so that suitable system
strengthening of ISTS could be identified and implemented as per requirements.
iv. The transmission system would be put up for discussion/ratification in the next
SRPC(TP) meeting.
Deliberations in 3 rd SRPC(TP) Meeting
30.3. The following transmission system was agreed for evacuation of 6100 MW Solar Power:
Sl.No.
DescriptionSolarPower
CapacityTransmission Scheme
1
C.S. Puram PoolingStations-1&2 to
Pamur SubstationPrakasam Dist.
600 MW
1) 220 kV TMSC Line (4 km) from PS-1 toCommon Tower, 220 kV TMSC Line (4km) from PS-2 to Common Tower and 220kV TMDC Line (15 km) from commonTower to Pamur SS.2) Upgradation of existing 132 kVSS/Pamur into 220 kV SS.3) Double LILO of existing 220 kV SMDCLine from 400 kV SS/Podili to Atmakur toPamur SS (13.5 km).
220 kV TMSC Line (8 km) from PS-1 toCommon Tower, 220 kV TMSC Line (4km) from PS-2 to Common Tower and 220kV TMDC Line (38 km) from commonTower to 220 kV SS/Podili.
3
Pendlimarri PoolingStations-1&2 to
proposed PendlimarriSw. Station,
YSR Kadapa Dist.
500 MW
1) 220 kV TMSC Line (3 km) from PS-1 toCommon Tower, 220 kV TMSC Line (4km) from PS-2 to Common Tower and 220kV TMDC Line (6 km) from commonTower to proposed 220 kV Sw. Station atPendlimarri.2) Double LILO of existing 220 kVMuddnuru(RTPP)-Chinakampalli SMDCLine to Pendlimarri Sw. Station dulyconverting it as TMDC. Towers are suitablefor Twin Moose DC.
4
M. KambaladinnePooling Stations-1&2
to 400KVSS/Jammalamadugu,
YSR Kadapa Dist.
500 MW
220 kV TMSC Line (2 km) from PS-1 toCommon Tower, 220 kV TMSC Line (5km) from PS-2 to Common Tower and 220kV TMDC Line (20 km) from commonTower to the existing 400 kV/SSJammalamadugu.
5 Urichinthala PoolingStations-1&2 to
600 MW 220 kV TMSC Line (4 km) from PS-1 toCommon Tower, 220 kV TMSC Line (1
Minutes of 3rd meeting of Southern Regional Power Committee (Transmission Planning)
Sl.No.
DescriptionSolarPower
CapacityTransmission Scheme
400KVSS/Talaricheruvu,Anantapur Dist.
km) from PS-2 to Common Tower and 220kV TMDC Line (6 km) from commonTower to the existing 400 kV/SSTalaricheruvu.
6
Mudigubba PoolingStations-1&2 to the
proposed Sw. Stationat Mudigubba,
Anantapur Dist.
500 MW
1) 220 kV TMSC Line (4 km) from PS-1 toCommon Tower, 220 kV TMSC Line (3km) from PS-2 to Common Tower and 220kV TMDC Line (7 km) from commonTower to the proposed Sw. Station atMudigubba2) Making Double LILO of 220 kVPulivendula-Mutyalacheruvu SMDC Line(5 km) which is (under construction) to theproposed Mudigubba Sw. Station.
7
Chakrayapeta PoolingStations-1&2 to theexisting 220KV SS/Chakrayapeta, YSR
Kadapa Dist.
500 MW
1) 220 kV TMSC Line (2 km) from PS-1 toCommon Tower, 220 kV TMSC Line (2km) from PS-2 to Common Tower and 220kV TMDC Line (8 km) from commonTower to the existing 220 kVSS/Chakrayapeta2)220 kV TMDC line from the existing 220kV SS/ Chakrayapeta to the existing 400kV SS/ Kalikiri (80 km).
1) 220 kV SMDC line (30 km) from PS-1to the existing 220 kV SS/Kondapuram
2) 220 kV SMDC line (35 km) from PS-2to the existing 220 kV SS/Yerraguntla
9
Pampanur TandaPooling Stations-
1,2,3&4 to proposedSw. Station at
Pampanur Tanda,Anantapur Dist.
1300 MW
1) 220 kV TMSC Line (3 km) from PS-1 toCommon Tower, 220KV TMSC Line(3KM) from PS-2 to Common Tower and220KV TMDC Line (4 km) from commonTower to the proposed Sw. Station atPampanur Tanda.2) 220 kV TMSC Line (3 km) from PS-3 toCommon Tower, 220KV TMSC Line (3km) from PS-4 to Common Tower and220KV TMDC Line (4 km) from commonTower to the proposed Sw. Station atPampanur Tanda.
10 Kolimigundla PoolingStations-1&2 to
400KV
600 MW 220 kV TMSC Line (2 km) from PS-1 toCommon Tower, 220KV TMSC Line (2km) from PS-2 to Common Tower and 220
3 400kV Talarichervu SS: 3x315 MVA ICT as per 40th
Standing Committee Meeting.
Proposed 1x315 + 3x500 MVA ICTs
4 400/220kV SS at Mylavaram 3x315 MVA ICTs and 1x125MVAR Bus reactor and 400kVQMDC line from 400kVJammalmadugu–Mylavaram SS(2 km) for evacuation of 1000MW of Solar Power atMylavaram (1000MW SolarPower of Kadapa Ultra MegaSolar Park of APSPCL) as per40th Standing CommitteeMeeting.
Dropped.
1000MW will be evacuated to 400 kV Jammalamadugu (Kondapuram) Substation:a) PS-1 to Jammalamadugu SS: 220kV
TMDC/SC line: 12.5 km b) PS-2 to Jammalamadugu SS: 220kV
TMDC/SC line: 10.0 km c) PS-3 to Jammalamadugu SS: 220kV
SMDC line: 8.0 km d) PS-4 to Jammalamadugu SS: 220kV
SMDC Line: 9.8 km (Alreadycommissioned)
5 400 kV Jammalamadugu SS (Kondapuram): 3x315 MVA ICTs as per 40th
Standing Committee Meeting.
Proposed 2x500 +2x315 MVA ICTs
6 220 kV Single Moose DC line from 400/220 kV Hindupur SS to 220 kVPampanur Tanda SS as per 40th
Standing Committee Meeting.
Proposed 220 kV Twin Moose DC line from 400/220 kV Hindupur SS to 220 kV PampanurTanda SS.
31. Proposal for removing LILO arrangement of 400 kV Vemagiri – Sattenapalli Line at
400/220 kV SS (PGCIL)/Nunna to make 2nd circuit of 400 kV Vemagiri – Sattenapalli
Line.
31.1. APTRANSCO vide letter dated 30.03.2021 had informed that in the special meeting on grid
related issues held on 20th October 2015 at SRPC, Bengaluru, it was recorded that LILO of
one circuit from existing 400 kV Vemagiri – Nunna TMDC line at 400 kV SS Sattenapalli
was agreed due to non-availability of sufficient load at 400 kV Sattenapalli SS.
APTRANSCO has now proposed to remove the LILO arrangement of 400 kV Vemagiri –
Sattenapalli Line at 400/220 kV SS Nunna (PGCIL) SS to make 2nd circuit of 400 kV
Minutes of 3rd meeting of Southern Regional Power Committee (Transmission Planning)
Transmission planning proposals by TSTRANSCO
33. Relocation of 125 MVAR Reactors from proposed 400/11kV Veljipur SS, 400/11 kV
Yellaipally SS and 400/11 kV Tukkapur (New) SS
33.1. The proposal for extending power supply to meet the load requirement for lifting additional 1
TMC of water from Godavari Basin in Link-I, Link-II & Link-IV of Kaleshwaram Lift
Irrigation Scheme was approved in 2nd meeting of Southern Regional Power Committee
(Transmission Planning) [SRPC(TP)].
33.2. TSTRANSCO vide letter dated 08.02.2021 has informed that they have accorded approval
for providing only Consumer Bus at new 400/11kV Veljipur, 400/11kV Yellaipally &
400/11kV Tukkapur (New) Lift irrigation(LI) substations under Link – IV due to near
vicinity to the corresponding existing Link IV substations. At the new proposed 400/11kV
Veljipur, 400/11kV Yellaipally & 400/11kV Tukkapur (New) LI substations, only Metering
Bay and Consumer Bus with Bus Sectionaliser is proposed and there is no 400kV Double
Bus System. Therefore, 125MVAR Reactors cannot be connected at the new proposed 400kV
substations.
In view of the above, TSTRANSCO has proposed the relocation of 125MVAR Reactors asfollows:
Sl. No.Earlier approved 125 MVARReactor at Substations of Link –IV
Now Proposed Substations to relocateReactors
1 400/11 kV Veljipur LI SS 400/13.8/11 kV Ramadugu LI SS
2 400/11 kV Yellaipalli LI SS 400 kV Kachapur Swiching Station
3 400/11 kV Tukkapur (New) LI SS Tukkapur 400/11 kV LI SS (Existing)
33.3. Relocating 125 MVAR Reactor from Veljipur 400/11 kV LI Substation to 400 kV
Ramadugu LI Substation:
The Veljipur 400/11kV LI Substation is around 5 km from existing 400/11kV Tippapur LISubstation where 1No. 400kV 125 MVAR Reactor is already provided. The Ramadugu400/220/11kV LI Substation is in Link – II of the Kaleshwaram Lift irrigation project and isconnected to two major Power Sources NTPC and STPP Jaipur (Singareni) and there is noReactor at Ramadugu LI Substation. Hence it is proposed to relocate 125 MVAR Reactorfrom Veljipur LI Substation to Ramadugu LI Substation.
33.4. Relocating 125 MVAR Reactor from Yellaipalli 400/11 kV LI Substation to 400 kV
Kachapur Switching Station:
The Yellaipally 400 kV Switchyard is around 8 km from existing 400/13.8/11kV ChandlapurLI Substation where 1 No. 400kV 125 MVAR Reactor is already provided.
In the 2nd SRPC(TP) meeting, 400 kV Kachapur Switching Station was approved with bussectionaliser arrangement along with 1 No. 400kV, 125 MVAR Reactor. Now it is proposed
Minutes of 3rd meeting of Southern Regional Power Committee (Transmission Planning)
to relocate 125MVAR Reactor from Yellaipalli LI Substation to Kachapur Switching Stationand with this relocation, 400kV Kachapur Switching Station will have 125 MVAR Reactorson both the sections.
33.5. Relocating 125 MVAR Reactor from Tukkapur (New) 400/11 kV LI Substation to 400
kV Tukkapur (Existing) LI Substation:
The Tukkapur (New) 400/11kV LI Substation is around 0.5 km from existing 400/11 kVTukkapur (Existing) LI Substation and there is no reactor at Tukkapur (Existing) Substationand hence, it is proposed to relocate 125 MVAR Reactor from Tukkapur (New) 400/11kV LISubstation to 400 kV Tukkapur (Existing) LI Substation.
Minutes of 3rd meeting of Southern Regional Power Committee (Transmission Planning)
33.6. Due to paucity of time, the agenda item could not be discussed in the 3rd SRPC(TP) meeting
and it was decided that same may be taken up in the next meeting of 3rd SRPC(TP).
Transmission Planning proposals by KSEB
34. Modification in 400 kV Edamon substation
34.1. 400 kV substation at Edamon was agreed at 39th SCPSPSR held on 28-29 December, 2015.
The following scheme was agreed upon:
Six 400 kV line bays
Four spare 400 kV line bay
Two transformer bays with 2x315 MVA 400/220 kV ICT’s.
The 400 kV connectivity would be established by charging existing 220 kVTirunelveli – Edamon Twin Moose D/c feeder, constructed in 400 kV parameters, at400 kV, and by LILO-ing both circuits of under construction 400 kV Tirunelveli –Cochin East Quad Moose D/c feeder.
Additional connectivity to 400 kV substation, Trivandrum North is planned later byLILO of existing 400 kV Tirunelveli – Trivandrum (North) Twin Moose D/c feeder.
Downstream 220kV connectivity: -
a. 220 kV connectivity will be directly to existing 220 kV switchyard of Edamon andfurther to following stations
b. 220 kV D/c feeder to Pothencode
c. 220 kV D/c and 220 kV S/c feeders to Sabarigiri
d. 220 kV feeders to Kundara and Edappon.
34.2. In the 2nd SRPC(TP) meeting. KSEB informed that as per studies carried out by KSEB, only
six circuits need to be connected to the new 400/220 kV substation at Edamon, Nagamala
Estate. The following revised transmission scheme has been proposed by KSEB:
i. Tirunelveli - Edamon I & II Twin Moose feeders constructed in 400 kV parameters andnow charged at 220 kV level will be terminated at 400 kV Edamon substation.
ii. One of the 400 kV Quad Moose Tirunelveli- Cochin East I & II feeders will beLILO’ed at 400 kV Edamon substation.
iii. One of the 400 kV Twin Moose Tirunelveli - Trivandrum I & II feeders will beLILO’ed at 400 kV Edamon substation.
iv. The 220 kV connectivity to 220 kV Edamon (KSEBL) existing substation will beestablished by using the balance portion of Twin Moose feeder to Edamon (KSEB)substation.
62 Kudlici /Badeladaku) SiS 220i66 KPTCL 200 Mav-20 Total of State Sector 12162
-
No.1 §/3/2018-Tra,ns-Pl(S) Government of India
Ministry of Power Shram Shakti Bhawan. Rafi Marg. New Delhi
Dated. the 20th May 2021 OFFICE ORDER
Annex-4
Subject: - National Committee on Transmission (NC,T)- amendment thereof.
In continuation of this Ministris Office order no. 15/312017-Trans dated 04.11.2019 regarding constltlltion of the National Com.mittee on Transmission (NCT). following amendments are hereby ordered with immediate effect
a) CMO, POSOCO will be a member of NCT.b) The following functions would be added to the Terms of Reference of NCT:
(i) To formulate the packages for the transmission schemes for theirimplementation and to recommend their mode of implementation i.e.Tariff Based Competitive Bidding (TBCB) / Regulated Tariff Mechanism(RTM), as per the existing Tariff Policy, to Ministry of Power.
(ii) To examine the cost of the transmission schemes .. (iii) To altocate the task of carrying out survey amongst CTU, RECTPCL and
PFCCL by maintaining a roster.
2. Further, NCT, while considering the Transmission Planning shall also keep inmind the following aspeets:
(i) ,:he Regional Power Committees (Transmission Planning) caw makemeaningful recommendations only regarding their own Region. They cannofoecide on transfers across region. '. _,..
(ii) For enabling growth of Renewable Energy (RE) capacity areas which have highsolar/ wind energy potential, will need to be identified and connected to bulkpower evacuation systems sp that capacity can come up there. This is anational mission as a part of our energy transition goal.
3. This issues with the approval of the Hon'ble Minister of State (IndependentCharge) for Power and New & Renewable Energy and Minister of State for SkfflDevelopment and Entrepreneurship ..
fti) Secretary. Ministry of New & Renewable Energy, Govt of India. (iii) Chaiq:,erson, CEA. New Delhi.(iv) CMD, POSOCO, New Oelhi(v) CMOs of all CPSEs under the Ministry of Power. Govt of India.
11111
(Vi) (vii) (Viii) (ix). (x)
-�-
H8cld$ of all autonomous bodies under the Ministry of Power. Finance/ Section. Ministry of
.
Chief Exect.flwes of all State Power Transmission Utilities. CEO. NITt Aayog, New Deihl.
Copy to;
of India.
(I) PS to Hon'ble MoSP(lC}I Sr PPS/ PP$/ PS to Secretaty(Power}I AS&FN AS{SKGR)I A.S(VKO)I au Jomt Secretaries/ Sr. A<trisOr/ Chief Engineer(Th)/ alt Directors/ Dy. Seaetaries, Ministry of Power.
(ii) Technical Director, NIC. Mio Power, for publishing this order on ttte website ofMio Power.
PTI INTERACTIVE POWER SYSTEM SIMULATOR--PSS(R)E MON, MAY 31 2021 14:40 Of ZONE TOTALS
IN MW/MVAR FROM ------AT ZONE BUSES------- TO -NET INTERCHANGE-
GENE- FROM IND TO IND TO TO BUS GNE BUS TO LINE FROM TO TO TIE TO TIES X-- ZONE --X RATION GENERATN MOTORS LOAD SHUNT DEVICES SHUNT CHARGING LOSSES LINES + LOADS
PTI INTERACTIVE POWER SYSTEM SIMULATOR--PSS(R)E MON, MAY 31 2021 13:39
OUTPUT FOR AREA 5 [SOUTH ] ZONE 52 [KARNATKA ] SUBSYSTEM LOADING CHECK (INCLUDED: TRANSFORMERS) (EXCLUDED: LINES; BREAKERS AND SWITCHES) MVA LOADINGS ABOVE 40.0 % OF RATING SET A:
X--------- FROM BUS ----------X X---------- TO BUS -----------X BUS# X-- NAME --X BASKV AREA BUS# X-- NAME --X BASKV AREA CKT LOADING RATING PERCENT
PTI INTERACTIVE POWER SYSTEM SIMULATOR--PSS(R)E MON, MAY 31 2021 13:46
OUTPUT FOR AREA 5 [SOUTH ] ZONE 50 [ANDHRA ] SUBSYSTEM LOADING CHECK (INCLUDED: TRANSFORMERS) (EXCLUDED: LINES; BREAKERS AND SWITCHES) MVA LOADINGS ABOVE 40.0 % OF RATING SET A:
X--------- FROM BUS ----------X X---------- TO BUS -----------X
PTI INTERACTIVE POWER SYSTEM SIMULATOR--PSS(R)E MON, MAY 31 2021 14:17
OUTPUT FOR AREA 5 [SOUTH ] ZONE 51 [TELANGANA ] SUBSYSTEM LOADING CHECK (INCLUDED: TRANSFORMERS) (EXCLUDED: LINES; BREAKERS AND SWITCHES) MVA LOADINGS ABOVE 40.0 % OF RATING SET B:
X--------- FROM BUS ----------X X---------- TO BUS -----------X
PTI INTERACTIVE POWER SYSTEM SIMULATOR--PSS(R)E MON, MAY 31 2021 14:35
OUTPUT FOR AREA 5 [SOUTH ] ZONE 53 [KERALA ] SUBSYSTEM LOADING CHECK (INCLUDED: TRANSFORMERS) (EXCLUDED: LINES; BREAKERS AND SWITCHES) MVA LOADINGS ABOVE 40.0 % OF RATING SET A:
Discussion on probability of Commutation failures at Pugalur HVDC
with direct injection of RE power
aigarhA
R .
Consists of '3' Schemes Scheme-3
Scheme-1
6oooMW DC Power +BookV )
OH Line
$JI$ ine
�11� OH
!Jl! -BookV - -
,,,..- ,,I
,-' �
4ookV D/C Line
Arasur (60 Km)
OH Line
OH Line.
LILO of 4ookV D/C Line
Trichur AC Bus
4ookV D/C Line /4- :, Thiruvallam (390 Km)
4ookV D/C Line I �ugalur (Existing) (50 Km)
Scheme-2 (Total 1294 . Cid. Km)
I 4ookV D/C Line
• r� Edayarpalayam (57 Km)
400kV DIC line
Pugalur AC Bus
Udumalapet (90 Km)
Risk of Commutation Failure
• When RP800 HVDC link operates in forward power direction i.e. , Pugalur is actingas Inverter, the probability of commutation failure at Pugalur is high when the busvoltage dips by 10% to 15% of the nominal voltage, however HVDC will recoverfrom this commutation failures if the voltage dips are temporary (5 -10 Cycles).
Hence after connection of RE power the voltage limits at Pugalur bus shall be
maintained as per grid code.
• When RP800 HVDC link operates in reverse power direction i.e. , Pugalur acting asrectifier, the probability of commutation failure at Pugalur is very less due tohigher commutation margin.
• From the literature/case studies, it is found that connection of Pugalur-TrichurVSC link at Pugalur bus helps in reducing the number of commutation failures andbetter recovery from commutation failure. Also VSC HVDC is immune tocommutation failures for both the direction of VSC operation.
Commutation margin Rectifier operation
With firing angle (a) range of 12° to 17° , Rectifier has higher commutation margin
a+u+ Y=180 deg
Inverter operation
With typical value of extinction angle (Y) of 17° , Inverter has lower commutation margin ,
p
Other Technical Issues
• The following issues need to be taken care at the 400 kV RE injectionpoint for smooth operation of HVDC at Pugalur terminal:
• Harmonic limits shall be within the grid code defined limits
• Voltage fluctuations shall be within the grid code defined limits
• Frequency variations shall be within the grid code defined limits
• Voltage unbalance shall be less than 1 %
• At any point, the RE connected feeder shall not be the only inter-connectionto the Raigarh-Pugalur HVDC at Pugalur bus
• In future, in case any issues arises during RE integration, necessarycontrol & protection study and validation may be carried out.
Southern Regional Power Committee
Bengaluru
Minutes of the Special Meeting of SRPC
(held on 14th July 2021 through VC)
1. Introduction
1. 1 Central Transmission Utility of India Limited (CTUIL) vide letter dated O 1st
July 2021 has intimated that CERC vide Record of Proceeding (date of
hearing: 25.06.2021) in Petition No.200/MP/2019 has directed CTU to
coordinate with Secretariat of SRPC to hold the RPC meeting within 15 days
from the date of issuance of Record of Proceeding to discuss the
developments and implementation of the transmission scheme in phase-wise
manner with the constituents of Southern Region. CTU has also been directed
to file the minutes of the meeting within a week thereafter.
1.2 CTUIL has requested recommendation of SRPC to take up the
implementation of the transmission schemes in phase- wise manner for
integration of potential renewable capacity of Koppal (Karnataka ), Gadag
(Karnataka) and Karur (Tamil Nadu) REZs considering already granted
Stage-II connectivity/LTAs to various RE developers in Koppal, Gadag and
Karur REZs so that regulatory requirement can be fulfilled in a time bound
manner.
1.3 Accordingly, a Special Meeting of the Southern Regional Power Committee
(SRPC) was held on 14th
July 2021to discuss the developments and
implementation of Transmission scheme for integration of potential
Renewable energy zone of 18.5 GW Solar & Wind Energy Zones in Southern
Region (SR).
The meeting was chaired by Shri Rajesh Lakhoni Chairperson, SRPC
&CMD, T ANGEDCO. The list of participants is at Annexure-1.3.
2. Transmission scheme for integration of potential REZ of 18.5
GW in Southern Region
2.1 Central Transmission Utility of India Limited (CTUIL) vide letter dated 01 st
July 2021 (Annexure-2.1)has furnished agenda on the developments and
implementation of the transmission scheme in phase-wise manner for
discussion with the constituents of Southern Region as per the direction of
CERC vide Record of Proceeding (Date of hearing: 25.06.2021& Date of
issuance ofRoP: 29.06.2021) in Petition No.200/MP/2019.
Annex-18.1
2.2 The transmission scheme for integration of 18.5 GW REZ in Southern Region
was discussed in the 36th SPRC held on 12.07.2019 and 37th SPRC held on
01.02.2020 and 38th SPRC held on 23.12.2020.The details of prioritized SEZs
and WEZs in Southern region (totaling to 18,500 MW) considered by SRPC
IJ Transmission system proposed is only for immediate integration with ISTS Grid and
margins available in the existing/under implementation transmission system shall
be utilized for further transfer of power
IJ Even the immediate transmission system is proposed for implementation in phased
manner associated with the grant of LTA
IJ From the system studies, it is found that line loadings are generally in order as per
the guidelines under the transmission planning criteria
IJ With the phased implementation of the transmission system matching with LTA,
upgradation of Narendra-Kolhapur line at its rated 765 kV level has been
deferred
IJ Further, to address overloading beyond Kolhapur, Kolhapur - Kolhapur (PG) 400
kV D/c lines has been agreed for reconductoring with twin HTLS in the 3rd
WRPCTP held on 14.06.2021.
Indicative Impact on the transmission charges
S.NO Scheme Proiect Cost of the
Levelized
Potential (MW) scheme (Cr.) (@15%
) cost(Crs.)
1 Tirunelveli and Tuticorin Wind Energy
500 37 5.55 Zone {Tamil Nadu) (500MW):
2 Karur / Tiruppur Wind Energy Zone
2500 344 51.6 {Tamil Nadu) (2500MW):
3 Koppal Wind Energy Zone (Karnataka)
2500 647 97.05 (2500MW):
Gadag SEZ Part-A(2500 MW) 2500 600 90
Total 8000 1628 244.2
Present total all India LTA quantum (A) = 101904 MW
RE LTA under waiver (B) = 9800 MW
Tariff payable by LTA beneficiaries = A- B = 92104 MW
Indicative Impact on transmission charges = Rs. 244.2/(92104x12) crs. = about Rs. 2210 per MW LTA/month
Phase-I transmission system
Phase-II transmission system is to be taken up only after receipt of Connectivity/LTA applications beyond1000 MW at Gadag or beyond 1500 MW at Koppal PS
Phase-I transmission system
Phase-II transmission system is to be taken up only after receipt of Connectivity/LTA applications beyond1000 MW at Karur
Bidar PS
Madhugiri(PG)
Maheshwaram
Gadag PSS2 : 2.5 GW
Koppal PS
Narendra(New)
Dharmapuri
Tuticorin PS
Tamil Nadu - REZ : 3 GW (WEZ)
Raigarh '
.-N. Trissur
' ' ' '
Madhugiri
Somanah�i
Total REZ in SR
, - - - - Phase-I: 5.5 GW (Dec'21 )
- - - - Phase-II: 5 GW (Dec'21)
- - - - Phase-Ill: 8 GW (Beyond
Dec'21)
Andhra Pradesh - REZ : 8 GW (SEZ-5GW & WEZ-3 GW)
Kurno�
l-111 PSW1: 25GW W2:05G S1: 1 5 G
Maheshwaram (PG)
► J
.r--� ...
,,,� J°7JJI
'! , ... ......
' ..,,. ...... Anantap"\tt=yf
S � \ c.--.....c.. S2 : 3.5 G Cuddap�h(PG)
.,, � \ J ..,_
.r....,...._ -\r-J t., •• .J t\
t--.A
\ \.,_ \
Nellore(PG)
-'>,.... ...... t....,..,.
,,,,,...r-
}.,
<:'.J
j\ "-"' ..\,,,, J).
\..I' �
Total REZ in SR •---- Phase-I: 5.5 GW (Dec'21) ---- Phase-II: 5 GW (Dec'21) ---- Phase-Ill: 8 GW (Beyond Dec'21)
भा�रत सरका�रGovernment of India
वि�द्युत मं�त्रा�लयMinistry of Powerका� न्द्री�य वि�द्युत प्रा�वि�कारण
Central Electricity Authorityवि�द्युत प्राण�ल� य�जना� ए�� मं�ल्य��काना - । प्राभा�ग
3. Shri Shailesh Kumar Mishra, Director (Power System), SECI, 1st Floor, PRIUSPlatinum, D-3, District Centre, Saket, New Delhi – 110017.
वि�षय / Subject: Minutes of the meeting held on 11th August' 2021 to deliberate over the
issues raised by SECI/MNRE/CTU in the 5th meeting of the sub-committee on cross cuttingissues for setting up of transmission lines in RE rich areas held on 28.07.2021.
महोदय / Sir,
A meeting to deliberate over the issues raised by SECI/MNRE/CTU in the 5th meeting of thesub-committee on cross cutting issues for setting up of transmission lines in RE rich areaswas convened by CEA on 11th August' 2021 through VC under the chairmanship of Member(Power System).
The minutes of the meeting are enclosed herewith.
संलग्न / Encl. - उपरोक्त / as above
भवदीय / Yours faithfully,
(प्रि�यम श्रीवास्तव/Priyam Srivastava)
उप प्रिनदशेक /Deputy Director
�प्रित प्रिलप्रिप / CC: Director (Trans), MoP, Shram Shakti Bhawan
Minutes of the meeting held on 11th August, 2021 to deliberate over the issues raised byMNRE and CTUIL in the 5th meeting of the sub-committee on cross cutting issues forsetting up of transmission lines in RE rich areas held on 28.07.2021.
List of participants is attached as Annexure-I.
Member (Power System), CEA, welcomed the participants and stated that in the 5th meetingof the sub-committee on cross cutting issues of setting up of transmission lines in RenewableEnergy (RE) Rich areas convened by MoP on 28.07.2021, CEA had been directed to convenea meeting with SECI, MNRE and CTUIL to discuss/resolve the issues raised by MNRE andCTUIL within 15 days. Accordingly, based on the agenda received from SECI and CTU, thismeeting has been convened.
The issues discussed in the meeting are as follows:
1. Issue: Status of approval and award for 20 GW Transmission system for locations inFatehgarh, Bhadla & Ramgarh and their timelines for availability for evacuation of REgeneration.
CEA’s views: The transmission system for evacuation of 20 GW RE in Rajasthan underPhase-III has already been discussed and approved in the NRPC (TP) meeting held on19.02.2021. The planned system would be discussed in the upcoming NCT meetingscheduled on 25.08.2021 and NCT would recommend the scheme to Government for itsimplementation.
Further, MoP vide letter dated 02.08.2021, has directed CEA/CTUIL to explore differentoptions for maximizing transmission capacity utilization including Battery Energy StorageSystem (BESS).
The transmission system for evacuation of 20 GW RE in Rajasthan under Phase-III inter aliaincludes 6000 MW, + 800 kV HVDC system from Bhadla-III – Fatehpur. The estimated costof HVDC scheme alongwith AC interconnections would be about 12000 Cr and wouldrequire an implementation timeframe of 3-4 years. In lieu of this scheme, SECI/MNRE mayplan Battery Energy Storage System for optimization as well as increased utilization of thebalance transmission system proposed under Phase-III as well as transmission system underPhase-I & II which are under implementation.
CTUIL’s views: Implementation of Battery Energy Storage System against the proposedHVDC scheme would certainly facilitate increase in the utilization of the proposed/underimplementation transmission schemes. However, implementation of the 20 GW transmissionsystem in phased manner as per the quantum of LTA applications from various REdevelopers at the planned Pooling Stations under Phase-III would avoid under-utilisation ofthe planned transmission system. Therefore, the transmission system for evacuation of 20GW RE in Rajasthan under Phase-III needs to be implemented in phases based on LTAapplications.
MNRE/ SECI’s views: The transmission system for evacuation of 20 GW RE in Rajasthanunder Phase-III may be taken up for implementation on priority basis as most of the solarcapacity addition has happened in Rajasthan and this would continue in future also. In the
meantime, SECI is exploring the suitable business model for Battery and Energy Storagesystem so as to achieve maximum utilization of the 37 GW ( 8.9 GW + 8.1 GW + 20 GW)transmission system already planned/under implementation in Rajasthan. As this involvesresolution of certain regulatory issues which would take time, accordingly, implementation ofBESS should not be linked with the 20 GW RE system already planned in Rajasthan. Further,substantial RE potential is available in Rajasthan (in addition to the potential alreadydeveloped/under development), which would be developed in the coming years andBattery/energy storage system would be planned with further development of RE potential.
The following was agreed:
(i) Planning of Battery/ Energy Storage System for optimization as well as increasedutilization of the transmission system associated with RE generation projects inRajasthan would be done for RE capacity addition beyond 37 GW under ISTS inRajasthan.
(ii) SECI/MNRE may finalise the suitable business model for implementation of Battery/Energy Storage System along with associated Regulatory issues.
(iii) Based on the decision taken in the upcoming NCT meeting, the transmission systemfor evacuation of 20 GW RE generation in Rajasthan under Phase-III needs to betaken up for implementation in phased manner based on the quantum of LTAapplications.
2. Issue: Delay in signing of PPA/PSA for Manufacturing linked LoA
CEA’s views: RE generators with manufacturing based LoAs have been granted Stage-IIconnectivity at various under construction/planned pooling stations for 8500 MW capacity(Bhadla-II PS: 1500MW, Fatehgarh-II PS: 1000MW, Fatehgarh-III PS: 4000MW & RamgarhPS: 2000 MW). However, as informed by CTU, no LTA applications has been received fromsuch RE developers as PPA/PSA have not been signed. This has resulted in grant ofconnectivity & LTA to other RE applicants (who have won other LOAs) at newsubstations/sections (Fatehgarh-III new section) which will take more time for developmentas part of Phase-III scheme.
CTUIL’s views: If clarity is obtained with respect to the materialization of LTA for thesemanufacturing based LoAs, then capacity in Phase-II system already blocked by thesemanufacturing linked RE applicants can be allocated to other RE applicants with firmtimeline. This would also ensure that the transmission system under Phase-II which is alreadyunder implementation is fully utilized.
MNRE/ SECI’s views: PPA/PSA of manufacturing based LoAs for 800 MW has alreadybeen signed and signing of additional PPA/PSA for 1000 MW is in pipeline. Regarding statusof signing of PPA/PSA for the balanced capacity, deliberations/negotiation are already goingon and SECI may be in position to convey the outcome by end of August, 2021.
The following was agreed:
(i) SECI to furnish the details of pooling station wise RE developers for the 1800 MWmanufacturing based LoAs whose PPA/PSA are likely to be signed.
(ii) SECI in coordination with MNRE would review the status of PPA/PSA of balancemanufacturing based LOAs. The updated status would be conveyed to CEA/CTU bySeptember, 2021.
3. Issue: Award of balance transmission scheme of Northern Region of 8.1 GW scheme
Background: Seven number of Transmission schemes for evacuation of 8.1 GW RE powerin Northern Region under Phase-II were notified by MoP vide Gazette Notification dated27.10.2020. Five out of these seven transmission schemes are presently underimplementation, one is under bidding and the balance one i.e Phase-II Part E schemecomprising of Bhadla-II PS – Sikar-II 765kV D/c line (2nd) has been kept on hold. Further,few ICT augmentations under RTM (Bhadla-II ICTs) have also been kept on hold.
CTUIL’s views: LTA for about 4.4 GW RE capacity has been received on transmissionsystem for SEZ Ph-II RE in Rajasthan (8.1GW). Lack of additional LTA applications againstRajasthan SEZ Phase-II scheme has resulted in holding the bid process of Package-E (TBCB)& Part of B1-Bhadla-II ICTs (RTM).
MNRE/ SECI’s views: The scheme may not be kept on hold and as per the informationavailable with them, higher quantum of LTA applications are there for the Phase-II scheme asagainst 4.4 GW LTA indicated by CTU. SECI raised concern that some RE generators havebeen commissioned without the commissioning of associated transmission system and as aresult these RE generators have to sell power in short term through the interim arrangementmade for power evacuation. Hence, implementation of the transmission schemes needs totaken up in advance.
The following was agreed:
(i) SECI and CTU to reconcile the LTA quantum available for Phase-II scheme.(ii) Based on reconciliation of LTA quantum and clarity on the LTA applications from
manufacturing linked LoAs, decision regarding bidding of Package-E (TBCB) & Partof B1(Bhadla-II ICTs under RTM) may be taken up.
4. Issue: Whether the Transmission Scheme for evacuation of 2500 MW from KoppalREZ needs to be implemented in phased manner or as a single scheme.
Background:Transmission Scheme for evacuation of 2500 MW from Koppal REZ was notified by MoPvide Gazette Notification dated 09.10.2019. The same is under bidding. However, Regulatoryapproval for the scheme is awaited. CTU vide its letter dated 07.07.2021 has communicatedto CEA that ReNew Surya Ojas Pvt Ltd (RSOPL) has been identified as LTTC for theKoppal scheme. In the letter, it was also mentioned that RSOPL has been granted LTA for300 MW with 1x500 MVA, 400/220 kV ICT out of total 5x500MVA 400/220 kV ICTsplanned at Koppal. The communication received from CTU was forwarded to BPC.Subsequently, BPC vide letter dated 30.07.2021 has requested CEA to advise for signing ofTSA by M/s ReNew Surya Ojas Pvt Ltd for the complete transmission scheme as per originalscope ( i.e for 5x500 MVA, 400/220 kV Koppal P.S.).
Further, in view of receipt of Stage-II Connectivity and LTA application of 1200 MW and600 MW respectively at Koppal P.S., CTU has proposed phasing of Koppal scheme into 2
phases with implementation of 3x500 MVA, 400/220 kV ICT under Phase-I and balance2x500 MVA, 400/220 kV ICT under Phase-II.
CTUIL’s views: i) Regulatory approval of Transmission schemes associated with evacuation of RE potential
zones in Southern Region is under consideration by CERC. CERC vide RoP dated25.06.2021 had directed SRPC to hold the RPC meeting to discuss the developments andimplementation of the transmission schemes in phase-wise manner with the constituentsof the Southern Region and submit the minutes of the meeting.
ii) On the direction of CERC, a special meeting of SRPC was held on 14.07.2021 whereinSRPC has concluded that revised studies may be carried out and a fresh proposal may besubmitted before SRPC(TP) and transmission system would be implemented in a phasedmanner strictly based on the LTA.
iii) CTU, vide affidavit dated 27.07.2021, has already submitted in CERC the Minutes of themeeting of Special SRPC meeting alongwith details of Connectivity / LTA granted to REdevelopers by wherein CTU has submitted phased implementation of the TransmissionSystem for Koppal REZ as per the details below:Transmission scheme for evacuation of 1500 MW from Koppal REZ under Phase-I
Establishment of 3x500 MVA, 400/220 kV pooling station near Munirabad /suitable location in Koppal distt.
Pooling station (near Munirabad /suitable location in Koppal distt.) - Narendra(New) 400 kV D/c Line (with Quad Moose ACSR conductor)
5 Nos of 220kV line bays for interconnection of wind projects 2x125 MVAr,400kV bus reactor at Pooling station (near Munirabad /suitable
location in Koppal distt.) Space provision for Phase-II
o 400/220 kV ICTs along with bays : 3 nos.o 220 kV line bays : 4 nos.
Adequate space provision for further expansion :o 400/220 kV ICTs along with bays : 3 nos.o 400 kV line bays : 6 nos.o 220 kV line bays : 7 nos.
Transmission scheme for evacuation of 1000 MW from Koppal REZ under Phase-II Augmentation of 400/220 kV, 2x500 MVA Koppal Pooling Station 4 Nos of 220 kV line bays for interconnection of wind projects
iv) LTA and Stage-II Connectivity has been granted at Koppal PS for 600 MW and 1200MWrespectively. However, LTA Agreement has been signed & CBG has been submitted for300MW only and same has been informed to CEA as part of details of LTTC for the parttransmission system at Koppal REZ. The LTA grantee (granted on 03.08.2021) foradditional 300 MW is required to sign LTA Agreement by 02.09.2021 and to submitCBG of Rs. 15 Crs. within 3 months thereafter.
MNRE/ SECI’s views: SECI informed that out of 1200 MW Stage-II connectivity granted atKoppal P.S., LTA for 600 MW has already been granted. Discussions for PSA signing withRajasthan for additional 600 MW is expected to be concluded (by 13.08.2021) and LTAapplication for the same shall be submitted to CTU shortly. In addition, the following bids arein pipeline:
(i) 1200 MW Hybrid pan-India tender whose e-RA was scheduled in third week ofAugust’2021.
(ii) 1200 MW SECI-XI Wind ISTS location specific tender (Gadag, Koppal, Kallamand Rajgarh) whose e-RA would be scheduled after 1200 MW Hybrid pan-Indiatender.
(iii) 600 MW Solar Park tender for Koppal.(iv) 600 MW Solar park tender for Gadag.
It is expected that conclusion of above bids would result in LTA of more than 1500 MW atKoppal P.S. Accordingly, the bidding may be carried out for Transmission Scheme forevacuation of total identified potential of 2500 MW for Koppal REZ instead of phasing thescheme.
CEA’s views: The scheme includes establishment of 400/220 kV, 5x 500 MVA Poolingstation and a 400 kV D/c line. Phasing of the ICTs at the Pooling station has been suggestedby CTU. However, as per SECI, conclusion of location specific and other bids in pipelinewould result in LTA of more than 1500 MW at Koppal P.S. Therefore, instead of phasing ofthe transmission scheme for Koppal and implementing it into two phases, the implementationtimeframe of the 400/220 kV, 5x500 MVA ICTs at Koppal P.S. may be staggered.
The following was agreed:
(i) Transmission Scheme for evacuation of 2500 MW power from Koppal REZ would beimplemented with establishment of 5x500 MVA, 400/220 kV Koppal P.S. However,the commissioning schedule would be staggered with time gap of six months i.e,commissioning schedule of 18 months for 3x500 MVA, 400/220 kV ICTs andcommissioning schedule of 24 months for balance 2x500 MVA, 400/220 kV ICTs.BPC to go ahead with bidding process with signing of TSA by the identified LTTCfor the complete scheme.
(ii) To facilitate the Regulatory Approval of the scheme, SECI to file affidavit in CERCjustifying the implementation of complete transmission scheme at Koppal REZ (2500MW), instead of phasing the scheme.
(iii) SECI to pursue with M/s ReNew Power Pvt Ltd for signing of the LTA Agreementwith CTU. SECI to pursue with RE developers who have already been granted Stage-II Connectivity at Koppal P.S, to apply for LTA with signing of PSA.
5. Issue: Status of LTA granted, signing of TSA and submission of bids for Gadag , Karur,Kallam, Pachora & Khavda.
5.1 Transmission Scheme for evacuation of 1000 MW from Gadag REZ under Phase-I:
Background: MoP vide Gazette notification dated 19th July, 2021, has notified theTransmission Scheme for evacuation of 1000 MW from Gadag REZ under Phase-I withimplementation timeframe of 18 months. The bid process for the same has been initiated bythe BPC. However, the Regulatory approval for the scheme is awaited.
CTUIL’s views: LTA for 460 MW (M/s ReNew -300 MW) and M/s Veena Energy-
160MW) has been granted at Gadag P.S. However, the signing of LTA agreement andsubmission of CBG by the applicant is pending. M/s ReNew and M/s Veena Energy havesought LTA with start date of 31.12.2022 and 31.03.2023 respectively. The grantees arerequired to sign LTA Agreement by 02.09.2021 and submit applicable CBG within threemonths thereafter. In absence of LTA agreement and completion of the other formalities,CTUIL is not in a position to share LTTC details.
5.2 Transmission Scheme for evacuation of 1000 MW from Karur REZ under Phase-I :
Background: MoP vide Gazette notification dated 19th July, 2021 has notified theTransmission Scheme for evacuation of 1000 MW from Karur REZ under Phase-I withimplementation timeframe of 18 months. The bid process for the same is to be initiated by theBPC. However, the Regulatory approval for the scheme is awaited.
CTUIL’s views: 420 MW Stage-II Connectivity and 100 MW LTA has been granted atKarur P.S. The LTA agreement for 100 MW has been signed and the LTTC for the schemehas already been intimated to BPC.
5.3 Transmission scheme for evacuation of 3 GW from Khavda under Phase-I:
Background: MoP vide Gazette notification dated 23.09.2020 has notified the scheme. Thesame is under bidding by the BPC. However, the Regulatory approval for the scheme isawaited.
CTUIL’s views: 3500 MW Stage-II Connectivity and 1000 MW LTA has been granted atKhavda P.S. The LTA agreement for 1000 MW has already been signed and the LTTCsidentified for the scheme has been intimated to the BPC.
5.4 Transmission Scheme for evacuation of 1000 MW from Osmanabad (Kallam):
Background: MoP vide Gazette notification dated 24.01.20 has notified the scheme. Thesame is under bidding by the BPC. Regulatory approval for the scheme is available.
CTUIL’s views: 1000 MW Stage-II Connectivity and 300 MW LTA has been granted atKallam P.S. However, signing of LTA agreement and submission of CBG by the applicant ispending. Subsequent to signing of LTA agreement, the LTTC’s for the scheme would beintimated to CEA and BPC.
5.5 Transmission Scheme for evacuation of 1500 MW from Rajgarh (Pachora)- Phase-I:
Background: MoP vide Gazette notification dated 19th July, 2021 has notified theTransmission Scheme for evacuation of 1500 MW from Rajgarh (Pachora) under Phase-Iwith implementation timeframe of 18 months.
CTUIL’s views: Stage-II Connectivity and LTA of 1000 MW has been granted at PachoraP.S. However, signing of LTA agreement and submission of CBG by the applicant ispending.
In respect of the above five issues, following was agreed:
SECI to pursue with LTA grantees to sign the LTA Agreement and submit CBGimmediately, wherever applicable.
SECI to pursue with Stage - II Connectivity grantees regarding application for LTA.
6. Issue: Award for transmission scheme for evacuation of power from Indore PS for 324.4MW project of SBESS and its scheduled completion date.
SECI raised the concern that with interim arrangement for evacuation of power through intra-state system of MP, only about 200 MW power could be evacuated.
It was informed that the scheme has already been awarded to POWERGRID under RTM on13.04.2021 with completion schedule of 12 months (April 2022). As per the 32nd JCCMeeting held on 29.06.2021, efforts are being made to complete the works well within thescheduled timeframe of April, 2022.
7. Issue: Expedite award for transmission scheme for evacuation of power from Hiryurand its scheduled completion date.
SECI’s view: ReNew Power has been granted LTA for 300 MW at Hiriyur with start date of31.12.2021 or commissioning of ICT at Hiriyur, whichever is later. RE developer hasinformed that they will be ready to commission about 150 MW capacity shortly and 3rd ICT isrequired to be commissioned before commissioning of the project by M/s ReNew Power.
CTUIL’s view:
3rd ICT (500MVA) at Hiriyur was proposed as part of Regional System Strengtheningscheme in Southern Region in the 2nd SRPC(TP) meeting held on 01.10.2020. MoPvide OM dated 16.07.2021 has already allocated the implementation work toPOWERGRID under RTM with commissioning schedule of 15 months.
As constraints were observed in the existing transmission system, augmentation ofICT was agreed and with the same ICT, LTA was granted to M/s ReNew Power Pvt.Ltd. for 300 MW. However, upto the commissioning of ICT, existing margins ofabout 100-150 MW may be utilised for evacuation of power from RE generations atHiriyur.
8. Issue: Expedite award for transmission scheme for evacuation of power from Tuticorinand its scheduled completion date.
SECI’s views: SECI raised the issue that LTA application for 540 MW has been submittedby RE generation developers for Tuticorin II GIS PS in June, 2021, thereby the total LTAquantum has become 1640 MW (1100 MW + 540 MW). For evacuation of power from theRE generation projects, ICT augmentation at Tuticorin II GIS PS needs to be taken up onpriority.
CTUIL’s views: LTA of 540 MW to JSW has been agreed for grant with 1x500 MVA 400/230 kV ICT
(4th ICT) at Tuticorin-II PS. Tuticorin-II GIS PS has been commissioned as part of GreenEnergy Corridor with 2x500 MVA, 400/230kV ICTs. In addition, 1x500 MVA,400/230kV 3rd ICT is under advanced stage of completion.
Presently, LTA of 1100 MW has been granted, out of which 950 MW is under operation.For effectiveness of present 540 MW LTA, implementation of 1x500 MVA 4th ICT needsto be taken up with the grant of LTA beyond 1500 MW. Accordingly, implementation of4th ICT at Tuticorin-II GIS PS is to be taken up. The ICT has been allocated toPOWERGRID under RTM, however Regulatory Approval for the same is awaited.
With the 3 nos. of 500 MVA ICTs, about 1400 MW power can be evacuated. Lookinginto the already granted LTA for 1100 MW, LTA of about 300 MW can be partoperationalized out of agreed 540 MW grant of LTA to M/s JSW.
List of Participants of meeting held 11th August' 2021 to deliberate over the issuesraised by SECI/MNRE/CTU in the 5th meeting of the sub-committee on cross cuttingissues for setting up of transmission lines in RE rich areas
Assumptions considered for preparation of load generation scenarios for RE integration in 2024-25
1. Time frame Considered: Transmission studies carried out for 2024-25 timeframe.
2. Scenarios : The study carried out for Summer (June), Winter (February) andMonsoon(August) season. To study the variation in generation required to meet the load, studyhas been carried out for three conditions, Morning Solar Peak, Evening Peak and night offpeak. During morning Solar generation is at its peak and thermal generation requirement isat minimal and by evening the solar is zero and the thermal contribution is maximum. Thescenario is tested for any constraints like generation maximum and minimum limit
3. Load Demand : While the Coona-19 has had a devastating impact on the economyIndian economy has been slowly bouncing back. In the studies load has beenconsidered as per as per the 19th EPS. (All India 266751 MW)
4. Demand factors : Calculated as per data received from POSOCO (enclosed inAnnexure)
5. Generation: In order to meet the required demand of a region, RE has been consideredas must-run. Total RE generation has been apportioned as per RE RPO to all regionsas per their projected EPS demand.
6. For accounting the availability of solar roof-top generation, equivalent load is reducedfrom respective regions.
7. Nuclear, gas and hydro have been considered as per the scenario and the balancedemand is met by thermal generation.
8. Evening peak scenario of each month was setup first as the number of thermal unitsrequired shall be maximum in this scenario. Total thermal generation requirement ofthis scenario is apportioned between state and central sector thermal generation as
Annex-19
per their installed capacity in each region. Further, state thermal generation requirement is divided among the states as per their maximum demand in each month of 2019-20.
9. After obtaining state thermal generation requirement, thermal units were switched onat technical maximum (85/90%) in merit order for each state.
10.To meet central thermal requirement, ISGS & IPP thermal plants with lower variablecost have been identified by dispatching them at technical maximum (85%) regionwise progressively. Demand of any region (like NR, SR) not met by thermal generationwithin that region is balanced by plants from other region (like WR, ER) consideringall India merit order for evening peak scenario.
11.For preparing night off peak scenario of the month, as discussed above state andcentral generation requirement was identified and economic dispatch was carried outby considering same number of units. These generating plants were scaled downproportionately.
12.While preparing the solar max scenario it was observed that even after running all theon-bar plants at technical minimum, surplus thermal generation was available, whichindicated that some plants needs to be switched off to balance the load generation.Accordingly, thermal plants with higher cost are switched off region wise progressivelytill the LGB is balanced.
Central State IPP Reqd Hydro Nuclear Solar Solar Wind RE RPO Diesel Gas Total Demand Surplus/ Net Net 111 C Thermal rooftop availabili Factor Deficit Availabih Demand
,f N NER 0% 0% 0% 0% 90% 80% 0% 0% 0% 0% 0% 85% 93% 88%
N
-� <(
39% 54% 51% 49% 89% 237491
Thermal Thermal Thermal Reqd Hydro Nuclear Solar Solar Wind RE RPO Diesel Gas Total Demand Surplus/ Net Net 111 C Central State Private Thermal rooftop availabili Factor Deficit Availabili Demand