Clark Avenue Middle School 0

Construction Management at Risk

Presentation

Clark Avenue Middle School

City of Chelsea

W.T. Rich Company, Inc.

W.T. Rich Company, Inc. Construction Managers

Agenda

Schedule

Logistics & Mitigation

Questions and Answers

1 Clark Avenue Middle School

Also important …

§  Public Bidder since 1968

§  MGL Ch. 149/149A Experience – Trade Bidders

§  Residential / Abutter Experience

§  Local Ordinances

§  Permitting and Approvals

Safety, Community and Site Logistics OUR COMMITMENT

Assure the health and safety of the school community and general public while minimizing disruption and enabling cost-effective

progression of the work

Clark Avenue Middle School 2

§  Safety and Site Logistics Plans ü Comprehensive, project-specific safety plan ü Mandatory safety orientations

§  Construction Mitigation Plan ü Communication ü Work zone isolation / CORI & SORI ü Delivery blackout periods ü Dust and noise control ü Safeguarding adjacent structures

§  Logistics ü Parking ü Staging / laydown ü Construction offices ü Traffic management ü Site constraints

Clark Avenue Middle School 3

Existing Conditions March 17, 2015

Clark Avenue Middle School 4

Initial Site Setup April 20, 2015 – April Vacation Week

Clark Avenue Middle School 5

Initial Site Setup April 20, 2015 – April Vacation Week Perimeter

construction fence

School access/egress

maintained

Pedestrian sidewalks & crosswalks

Community Information

Board

Construction trailers (TBC)

Construction parking (TBC)

Clark Avenue Middle School 6

Phase 1 Demolition August 2015

Temporary Boiler

Clark Avenue Middle School 7

Phase 1 Foundations September 2015

Clark Avenue Middle School 8

Phase 1 Steel 2015-2016

Clark Avenue Middle School 9

Phase 2 Initial Setup January 2017

Clark Avenue Middle School 10

Phase 2 Initial Setup February 2017 Perimeter

construction fence relocated

TWO School access/egress

paths

Pedestrian sidewalks & crosswalks

Community Information

Board

Construction trailers (TBC)

Construction parking (TBC)

Clark Avenue Middle School 11

Phase 2 Demolition February 2017

Clark Avenue Middle School 12

Phase 2 Foundations July 2017

Clark Avenue Middle School 13

Phase 2 Steel September 2017