Treating Our Water…Right! Winnipegs Water Treatment Program.
Post on 28-Mar-2015
221 Views
Preview:
Transcript
Treating Our Water…Right!Treating Our Water…Right!Winnipeg’sWinnipeg’s
Water Treatment ProgramWater Treatment Program
2
AgendaAgenda
Introduction History of Winnipeg’s Water Supply Council’s Decision to Treat Winnipeg’s Water Why treat our water? What have we done so far? What will the new water treatment plant be
like? What challenges remain?
Environmental Issues Organizational Issues Market Conditions Schedule Finances Risk Management
Questions
3
HistoryHistory
Red River
MainAqueduct
McPhillips Reservoirand Pumping Station
Wilkes Reservoir andHurst Pumping Station
MacLean Reservoir and Pumping Station
TacheBoosterStation
Branch II
Deacon Reservoirand Booster Station
Winnipeg
Deacon Reservoir
SHOAL LAKE(Indian Bay)
Falcon Lake
Winnipeg River
MANITOBA
ONTARIO
MINNESOTA
Kenora
Ross
Pinawa
AssiniboineRiver
Main Aqueduct
Intake
exsys2bw0512_cgs
Natalie Lake
Shoal LakeWatershedBoundary
Existing Water Supply SystemFigure 3-1
4
HistoryHistory
0 10 20 30 40 50 60 70 80 90 100
DISTANCE (STATION) IN MILES
700
800
900
1000
1100
Ele
vati
on A
bov
eS
ea L
evel
in F
eet
700
800
900
1000
1100
RE
D R
IVE
RS
EIN
E R
IVE
R BR
OK
EN
HE
AD
RIV
ER
WH
ITE
MO
UTH
RIV
ER
BIR
CH
RIV
ER
BO
GG
Y R
IVE
R
BO
GG
Y R
IVE
R
IND
IAN
BAY
SH
OA
L LA
KE
INVERT OF AQUEDUCT
GROUNDLINE
WINNIPEG
SHOALLAKE
FALC
ON
RIV
ER
5
HistoryHistory
6
HistoryHistory
Dugald
Trans Canada Highway
WINNIPEG
1
City Limits
15R
edR
iver
Assiniboine River
100
Perimeter Highway
Perimeter H
ighway
207
Red Rive
r Floodway
206
101
Shoal Lake Aqueduct
Branch II
Branch IMacLean
Res.Wilkes Res.
McPhillips Res.
Shoal Lake96 km to
Cell 1
Cell 4Cell 3
(1919)
(1972)Cell 2
(1978)
(1997)
7
HistoryHistory
The GWWD Railway was constructed between 1913 and 1915Aqueduct construction was completed in March, 1919 – 2500 workers at peakSince 1919, Winnipeg has enjoyed a high quality reliable water supply from Shoal Lake- minimal treatment (chlorine for disinfection prior to 1937, and fluoride for dental protection since 1956)Recently, fluoride was relocated to Deacon, and orthophosphate was added for lead control
8
Council’s DecisionCouncil’s Decision
In 1993 Council - Accepted the recommendation to undertake water treatment within a ten year time frame - And established a Water Treatment Reserve
Between 1995 and 1999 a comprehensive program of monitoring, pilot testing and engineering studies was undertakenIn 2000, Council adopted a recommendation that Winnipeg proceed with a water treatment programThis decision was supported by public consultation, public health officials and the opinion of an “expert panel” (low risk – high consequence)
9
Why Treat Our Water?Why Treat Our Water?
Water treatment is about protecting Public Health
“The rationale for construction of a water treatment plant is based primarily on health concerns” …. Dr. Margaret Fast
“Providing water that is safe and healthy to drink” received the highest priority …. March 1999 Customer Survey
10
Specific ObjectivesSpecific Objectives
Reduce the risk of a waterborne disease outbreak caused by chlorine-resistant microorganisms
Reduce chlorine disinfection by-products
Meet the Canadian Drinking Water Quality Guidelines
11
Waterborne Pathogens - “Da Waterborne Pathogens - “Da Bugs…”Bugs…”
Chlorine is effective against bacteria and viruses
Chlorine is relatively ineffective against Giardia and requires high doses and long contact times
Chlorine is not effective against Cryptosporiduim
12
Our New Water Treatment Our New Water Treatment PlantPlant
A new Water Treatment Plant is being built at the Deacon Reservoir Site.The plant will be a state-of-the-art, modern facility designed for performance, safety, and environmental sustainability.
13
AERIAL VIEW FROM SOUTH WESTAERIAL VIEW FROM SOUTH WEST
14
VIEW FROM SOUTH EASTVIEW FROM SOUTH EAST
15
Plant Design Life and CapacityPlant Design Life and Capacity
Water Treatment Plant Design Life projected to be 2040Maximum Finished Water Production – 400 ML/dAverage Finished Water Production – 254 ML/dMinimum Finished Water Production – 100 ML/d
16
Location of the Water Treatment Location of the Water Treatment PlantPlant
17
What’s New at Deacon?What’s New at Deacon?
Ultraviolet light disinfectionNew treatment facility, clearwell and ancillary buildings (Stand-by power, chemical storage and on-site sodium hypochlorite generation)Settling ponds and a new pipe to transport wastewater from the plant to the City’s sewer system24-hour monitoring and security
18
What We Have Done So FarWhat We Have Done So Far
Tested a number of water treatment technologies and found the combination that works best for Winnipeg’s water
Completed Concept and Preliminary design for the water treatment plant
Detailed Design is underway, concurrent with construction
19
Early Ultraviolet Light DisinfectionEarly Ultraviolet Light Disinfection
The water will pass through large pipes containing ultraviolet lamps.
The ultraviolet light will make water- borne parasites, such as Cryptosporidium, harmless
20
Ultraviolet Light DisinfectionUltraviolet Light Disinfection
21
Ultraviolet Light DisinfectionUltraviolet Light Disinfection
22
Need for Multiple BarriersNeed for Multiple Barriers
“What the experts and the industry recommend with respect to the treatment of all surface water is a multi-barrier approach. The first barrier is watershed protection to ensure the best possible raw water source. The next barrier is optimization of the plant processes designed to achieve settlement of particulates and sediment in the raw water. The third barrier is maximization of the efficiency and monitoring of the filtration process which follows sedimentation. The final barrier is to ensure the water is adequately disinfected.”[1]
[1] Justice Robert D. Laing, Commissioner, Report of the Commission of the Inquiry into matters relating to the safety of the public drinking water in the City of North Battleford, Saskatchewan. March 28, 2002
23
The Water Treatment ProcessThe Water Treatment Process
24
Settling PondsSettling Ponds
Algae and other solid material will be removed from the water and put in the ponds.The water will be separated from the solid material.The solids will be removed from the ponds every year and hauled to Brady Road Landfill.We do not expect any odour from the ponds.
25
Location of Settling PondsLocation of Settling Ponds
New Water Treatment Plant
1 2
3 4
26
What are the Challenges?What are the Challenges?
Environmental Issues Organizational Issues Market Conditions Schedule Finances Risk Management
27
Environmental Effects Environmental Effects AssessmentAssessment
An Environmental Effects Assessment study of the effects the water treatment plant on the environment and surrounding community identified no adverse effects.The study was voluntary – it is not required by our regulators.The results were shared with stakeholders and Manitoba Conservation.The facility will be a zero discharge operation - it will not discharge to the environment.Two Public Open Houses have been held in Springfield;All substantive issues have been addressed.
28
Organizational IssuesOrganizational Issues
This is a large complex project with four major consulting firms working from geographically diverse locationsCoordination/communication through “ERoom”Construction Management and “Fast Tracking” leads to risks and cultural issues for City and ConsultantsHiring and training of certified operators in time for commissioning and start-up (2008 by Council mandate) will be challenging
29
Market ConditionsMarket Conditions
Many large new projects will be going to market over the scheduled construction periodA period of high inflation within the construction industry is forecast (time = money)A shortage of qualified contractors and personnel is anticipatedWe must make this an attractive project for contractors
30
ScheduleSchedule
April 2005 Finish preliminary designand environmental
effectsstudy
Spring 2005 Started building the water treatment plant
Fall 2008 Start testing the plant
End of 2008 Begin operating the plant
31
Construction ActivitiesConstruction Activities
Progress to date:
• Long Delivery Valves and process equipment have been prepurchased
• Some piling has been prepurchased• Bulk Excavation for the WTP and the Clearwell has been completed• Construction of Yard piping, Clearwell and Raw Water Pumping
Station are underway.• About $40 Million in work awarded• Overall, we have committed about $78 Million to date
Upcoming Work:
• WTP Concrete and Piling (Construction) - $55.9M• Freeze Thaw Ponds and related infrastructure - $6.9M• Mechanical and Electrical - $38.5 Million• Miscellaneous equipment, piping and infrastructure - $10
M
32
FinancesFinances
The original water treatment program budget was $214 million to build the WTP and $12.75 million/yr to operateCouncil has approved an additional $13.3 million for risk mitigation initiatives and $2.8 million for shops/staff consolidationThe current rate model will provide about of $117 Million in cash financingOnce the plant is up and operating, revenues from water sales are sufficient to cover operating and debt servicing without extraordinary increases to water rates
33
Risk ManagementRisk Management
This project conforms to new civic policies on Risk ManagementA two-day Risk Management Workshop was undertaken, using a specialist consultant120 risk items were identified by workshop attendeesThese were synthesized into 44 project issues and 33 design issues by the Risk Consultant. Some of the risks are “Serious” to “Critical”Further refinement; mitigation and monitoring protocols have been developed; risks are monitored on an ongoing basis and reviewed at monthly meetings
34
Questions?Questions?