Transcript
8/14/2019 Topcon230 Quick Manual by Al-Fajr
1/15
Technical Support Team E-mail: topcontech@fajerest.ae Fax : 04-2868016
Authors: Jobin & Vishnu, Tech. Support team (Topcon), Al Fajer Establishment, Dubai.
TOPCON (GTS 230 N) QUICK MANUAL CENTERING AND LEVELING:
STEP-1
Set the instrument on thetripod and press the powerbutton.
STEP-2Press the star key for initialsettings.
STEP-3a
Press the up & down arrowfor contrast adjustment of the display.
STEP-3b
Press (F1) for turn on the
backlight of the displayscreen.
STEP-3cPress (F2) for setting thetilt correction
STEP-3dPress (F3) for turn on thelaser pointer. (optional)
8/14/2019 Topcon230 Quick Manual by Al-Fajr
2/15
Technical Support Team E-mail: topcontech@fajerest.ae Fax : 04-2868016
Authors: Jobin & Vishnu Tech. Su ort team To con Al Fa er Establishment Dubai.
********************************************************************
STEP-3e
Press (F4) for adjusting theprism constant, temp&
pressure value etc.Again,
Press F1for (Prism Con.)Press F3for (Temp-Preas)
STEP-3f
Once you are complete theleveling and centering, press(Esc) button for exit.
8/14/2019 Topcon230 Quick Manual by Al-Fajr
3/15
Technical Support Team E-mail: topcontech@fajerest.ae Fax : 04-2868016
Authors: Jobin & Vishnu Tech. Su ort team To con Al Fa er Establishment Dubai.
MAKING A NEW JOB:
STEP-1 Press the menu button.
STEP-2Press (F1) for data collect.Data collect is the detailsurvey menu.
STEP-3
Press [F1] for inputting a new job name or press [F2] forselecting an existing job fromthe list.
STEP-4
If you want to type the alphanumeric characters, againpress [F1] and input that.ThenPress [F4] to accept the job.
NOTE: If you want to do both the topography and setting out exercises, pleaseselect the same jobs in DATA COLLECT menu & LAYOUT menu.
********************************************************************
8/14/2019 Topcon230 Quick Manual by Al-Fajr
4/15
Technical Support Team E-mail: topcontech@fajerest.ae Fax : 04-2868016
Authors: Jobin & Vishnu Tech. Su ort team To con Al Fa er Establishment Dubai.
CO -ORDINATES INPUTTING:
STEP-1Press menu button to get themain menu. Press F3 to selectthe memory manager.
STEP-2 Press F4 for the next page.
STEP-3 Press F1 to input co ordinates.
STEP-4Press F2 for getting thecreated job list (if you knowthe job name, you can type itdirectly).
STEP-5 To select the job with up &down arrow keys.
STEP-6 Then Press F4
STEP-7 Press [F1], for your co-ordinate entry
Continues on NEXT PAGE
8/14/2019 Topcon230 Quick Manual by Al-Fajr
5/15
Technical Support Team E-mail: topcontech@fajerest.ae Fax : 04-2868016
Authors: Jobin & Vishnu Tech. Su ort team To con Al Fa er Establishment Dubai.
NOTE: It is better to make a Control Point data sheet given below. This isvery useful for the surveyors on job handover situations.
JOB NAME Point.ID Northing Easting Elevation Code NameAL FAJER 1 10.000 10.000 10.000 CP1
AL FAJER 4 2787545.098 5037555.088 10.400 DM1
AL FAJER 5 2787523.776 5037560.001 12.333 DM2**************************** ******************************
STEP-8
Type the point IDIf Press F1-Alpha numeric
Press F2-spacePress F3-clear screen
STEP-9After typing you canpress [F4] or [enter]
STEP-10 Input the co-ordinates
STEP-11 You should type yourpoint name here.
STEP-12 After the inputting press[F4] or [Enter]
STEP-13This shows your input isrecorded to the memory.
8/14/2019 Topcon230 Quick Manual by Al-Fajr
6/15
Technical Support Team E-mail: topcontech@fajerest.ae Fax : 04-2868016
Authors: Jobin & Vishnu Tech. Su ort team To con Al Fa er Establishment Dubai.
STATION SETTING
`
STEP-1Press your MENU button andPress (F1) for data collect.(Data collect is the detailsurvey menu.)
STEP-2Press [F2] for selecting your
job from the list. And press[F4] to set the job.
STEP-3
Press [F1]for OCC.PT# INPUT(occupied point is yourinstruments station point )
STEP-4After inputing the stationspoint ID, Instrument hightetc. Then Press [F4]
STEP-5
Check your station co-ordinates. If it is correct
Press [F3] and go to STEP-9 ,else Press [F4]
STEP-6Press [F4] to check the co-ordinates entry.
STEP-7 Check the point Id and
Press [F4]
STEP-8 Check the recorded co-ordinates and Press [F3]
Continues on NEXT PAGE
8/14/2019 Topcon230 Quick Manual by Al-Fajr
7/15
Technical Support Team E-mail: topcontech@fajerest.ae Fax : 04-2868016
Authors: Jobin & Vishnu Tech. Su ort team To con Al Fa er Establishment Dubai.
STEP-9 Press [F3]
STEP-10 Press [F3]
STEP-11This screen displays yourstation is completed.
**************************** ******************************
8/14/2019 Topcon230 Quick Manual by Al-Fajr
8/15
Technical Support Team E-mail: topcontech@fajerest.ae Fax : 04-2868016
Authors: Jobin & Vishnu Tech. Su ort team To con Al Fa er Establishment Dubai.
BACK STATION ORIENTATION: NOTE: For Back orientation you can choose 3 ways.
1. Whole Circle Bearing ZERO SET.2. Known W.C.Bearing SET.3. Back Station Co-ordinate SET.
BACK STATION BY WHOLE CIRCLE BEARING ZERO SET :
STEP-1
After the station set up, orientthe telescope to the Back station point. Then Press [F2]for start the Back sighting.
STEP-2 Press [F2] for ZERO set
STEP-3 Now you should get thismessage on the screen.
STEP-4 Press [F3] for start measuring
STEP-5Press [F3] for startco-ordinate measuring
STEP-6
Once the machine starts the
measuring, quickly press ESCbutton. Because now yourbearing is set as ZERO. Againpress ESC button and start thesurvey works.
NOTE: If you want to know the co-ords of the BS point, wait upto the completemeasurement. For recording that data, Press [F3]
**************************** ******************************
8/14/2019 Topcon230 Quick Manual by Al-Fajr
9/15
8/14/2019 Topcon230 Quick Manual by Al-Fajr
10/15
Technical Support Team E-mail: topcontech@fajerest.ae Fax : 04-2868016
Authors: Jobin & Vishnu Tech. Su ort team To con Al Fa er Establishment Dubai.
STEP-9Press [F3] for start
co-ordinate measuring
STEP-10
Once the machine starts themeasuring, quickly press ESCbutton. Because now yourbearing is set as ZERO. Againpress ESC button and start thesurvey works.
NOTE: If you want to know the co-ords of the BS point, wait upto the completemeasurement. For recording that data, Press [F3] .
**************************** ******************************
8/14/2019 Topcon230 Quick Manual by Al-Fajr
11/15
Technical Support Team E-mail: topcontech@fajerest.ae Fax : 04-2868016
Authors: Jobin & Vishnu Tech. Su ort team To con Al Fa er Establishment Dubai.
BACK STATION BY CO -ORDINATE SET:
STEP-1
After the station set up, orient
the telescope to the Back station point. Then Press [F2]for start the Back sighting.
STEP-2
Press [F1] and input the back station point id, PCODE, andReflector Height. ThenPress [F3] for confirmation.
STEP-3 Press [F3] for starting theco-ordinate measure.
STEP-4Now you should get thismessage on the screen.
STEP-5
After checking the co-ords
Press [F3] for recording theco-ordinate measurement.
STEP-6Now you should get thismessage on the screen.
STEP-7
Now you should get thismessage on the screen. This
shows your Back station is setproperly.
**************************** ******************************
8/14/2019 Topcon230 Quick Manual by Al-Fajr
12/15
Technical Support Team E-mail: topcontech@fajerest.ae Fax : 04-2868016
Authors: Jobin & Vishnu Tech. Su ort team To con Al Fa er Establishment Dubai.
TOPOGRAPHIC SURVEYING
STEP-1 Press [F1] for preparing adetail survey.
STEP-2
After completing the station& B/S set up orient thetelescope to the prism. ThenPress [F3] to start detailsurveying.
STEP-3
Input the starting point no,
code, and reflector height .Then Press [F4]
STEP-4Press [F3] to prepare themeasurement.
STEP-5
Press [F3] to start the co-
ordinate measurement.
STEP-6Then you should see thismessage
STEP-7 Confirm your co- ordinate and
Press [F3] to record this data.
STEP-8After record, your point Idwill be increasingautomatically.
**************************** ******************************
8/14/2019 Topcon230 Quick Manual by Al-Fajr
13/15
Technical Support Team E-mail: topcontech@fajerest.ae Fax : 04-2868016
Authors: Jobin & Vishnu Tech. Su ort team To con Al Fa er Establishment Dubai.
NOTE: If you want to record the data with same code and same reflector height,you have to do shown on below.
STEP-1 Press [F4] to start measuring
STEP-2Then you should see thismessage
STEP-3Confirm your co- ordinate andPress [F3] to record this data.
STEP-4This message shows that yourdata has recorded to thememory.
**************************** ******************************
8/14/2019 Topcon230 Quick Manual by Al-Fajr
14/15
Technical Support Team E-mail: topcontech@fajerest.ae Fax : 04-2868016
Authors: Jobin & Vishnu Tech. Su ort team To con Al Fa er Establishment Dubai.
TOPOGRAPHIC SURVEYING WITH OFFSET MEASUREMENT
STEP-1Input the starting point no,code, and reflector height .Then Press [F3]
STEP-2Press [F4] for choosing nextpage.
STEP-3 Press [F1] for choosingOFFSET menu.
STEP-4Most commonly using offsetsystem is the 2 nd one. So Press[F2]
NOTE: This offset functionis working as per this figure.
Here, the telescopic linebetween building corner andthe instrument is obstructedby a tree. Before inputting,please confirm the offsetlengths from the chainmanside. Now your requiredpoint (Building Corner) is2m forward and 1m left of the actual observed
point (prizm).
STEP-5
Input your Left (-) or Right(+) offset. Here your offset is1m left. So input -1 andPress [F4] for enter.
Continues on NEXT PAGE
8/14/2019 Topcon230 Quick Manual by Al-Fajr
15/15
Technical Support Team E-mail: topcontech@fajerest.ae Fax : 04-2868016
Authors: Jobin & Vishnu Tech. Su ort team To con Al Fa er Establishment Dubai.
STEP-6
Input your forward (+) orBackward (-) offset. Hereyour offset is 1m forward. Soinput 2m and Press [F4] toenter.
STEP-7Press [F3] to start co-ordinatemeasuring
STEP-8This screen shows, themachine is measuring.
STEP-9This is the calculated co-ordinates and if you wantrecord Press [F3].
STEP-10This screen shows your datahas recorded to the memory.
STEP-11This screen shows yourinstrument is ready for nextobservation.
**************************** ******************************
top related