SWOT Ground System IGARSS – August 2011

Post on 23-Feb-2016

52 Views

Category:

Documents

0 Downloads

Preview:

Click to see full reader

DESCRIPTION

http://swot.jpl.nasa.gov. SWOT Ground System IGARSS – August 2011 . Helene Vadon (CNES, Toulouse) Phil Callahan (Jet Propulsion Lab, California Institute of Technology) . SWOT Ground System Outline . Introduction SWOT mission Mission phases Ground segment overview - PowerPoint PPT Presentation

Transcript

SWOTJet Propulsion Laboratory California Institute of Technology

SWOT Ground System

IGARSS – August 2011

Helene Vadon (CNES, Toulouse) Phil Callahan (Jet Propulsion Lab, California Institute of

Technology)

http://swot.jpl.nasa.gov

SWOTJet Propulsion Laboratory California Institute of Technology

SWOT Ground System Outline

• Introduction– SWOT mission– Mission phases – Ground segment overview

• KaRIN Data Acquisition and Products– Acquisition characteristics– KaRIN processing – Data Products– Sizing estimates

• Joint Ground System Development – Commonality levels and approach for the processing development

2011/07/25 s3 psc 2IGARSS11 - SWOT Ground System

SWOTJet Propulsion Laboratory California Institute of Technology

IGARSS11 - SWOT Ground System 3

SWOT Mission

• Mission – Extraction of water surface heights over ocean and continental water

bodies– The principal instrument is KaRIN, a Ka-band interferometric SAR

system – Other instruments are a nadir altimeter, radiometer, and precision tracking

systems (classical Jason Altimeter suite)

• Main scientific requirements– Oceanography: Global coverage (< 78°) of oceans, sea surface height

precision < 2 cm at approximately 1 km resolution LR mode

– Hydrology: Global inventory of rivers > 100 m (50 m) and lakes > (250 m)2, water surface height precision of the order of 10 cm (averaged over 1 km2), slope precision 1 cm/km (averaged over 10 km); average posting 50 m HR mode

2011/07/25 s3 psc

SWOTJet Propulsion Laboratory California Institute of Technology

IGARSS11 - SWOT Ground System 4

Mission Phases

• Launch and Early Orbit Operations (~ 3 days) – Launch planned for late 2019

• Checkout / Commissioning (~ 30 - 45 days)

• Fast repeat orbit at 3 (or 1) days for ~90 (or 30) days – For ocean sub-mesoscale

• Calibration / Validation (Cal/Val) (3 – 6 months, covering Fast Repeat and Science Operations)

• Transition to Science Orbit, Operations (~ 15 days) – Non-sun-synchronous, 22 day exact repeat, 970 km altitude, 78 deg inclination

• Science Observations (Requirement = 3 years; starts ~4.5 months after launch)

• Disposal and Ground System Closeout (= 3 months)

2011/07/25 s3 psc

SWOTJet Propulsion Laboratory California Institute of Technology

IGARSS11 - SWOT Ground System 5

SWOT Ground System Challenges

• High precision for both ocean (1-2 cm) and hydrology (~10 cm) – Complete, accurate algorithms – Use of instrument and spacecraft calibration data – External corrections; Ancillary information

• Large Data Volume – both telemetry and data products – Raw data downlink for land data. Requires >~ 600 Mbps X-band

downlink – Data products posted at fine resolution: LR = 500 m, HR = 50 m (~100

giga-samples per cycle for LR+HR)

• Likely Near Real Time requirements – Ocean from Jason suite similar to Jason series – Hydrology (floods, reservoirs) from KaRIN

2011/07/25 s3 psc

SWOTJet Propulsion Laboratory California Institute of Technology

IGARSS11 - SWOT Ground System 6

Architecture Diagram

2011/07/25 s3 psc

CNES

CNES X-band Network(also has S-band Uplink)

Science Processing Archive & Distribution

CNES ElementsNASA ElementsJoint Elements

S/C Control Center (SCC) (Contractor)

CNES S-band Network

KaRIN Science Data

Data exchangeJPL

Science Data Processing

Science Data Center

To CNES: Ack. successful downlink Payload commands

Karin

Radiometer

Nadir AltimeterPayload module

X bandTM

S/C Bus

UPLINK: S/C & P/L Cmd. DOWNLINK: Jason Suite Sci Data (Nadir Alt, Rad, GPS) and All Eng Telem

TBD Additional X-band Sta

JPL Science Data Archiving

& Distribution

X-band Network Center

Payload Operations Center

JPL Payload

Operations Center

To JPL: X-band data, S-band Sci, s/c Telemetry, TBD[KaRIN Eng]

To JPL: Jason Suite L2. Cal/val. To CNES: KaRIN TBD[L1b]. POD. Cal/val.

Ancillary Data: Tropo model(s), Iono info, Tide

model(s), DEM, SSH

To JPL: X-band data, TBD[KaRIN Eng]

SWOTJet Propulsion Laboratory California Institute of Technology

IGARSS11 - SWOT Ground System 7

Ground System Elements (1 of 2)

• Tracking Stations – CNES S-band stations: Downlink for Nadir Alt, Radiometer, DORIS,

GPS (“Jason Altimeter Suite”, JAS); Engineering. Uplink commanding

– X-band network (620 Mbps (nominal, min)): Downlink for high rate science (KaRIN), and associated Engineering data

• Front End Networks – Network from X-band Data Center(s) to JPL and CNES operation

centers. Minimum data rate to return all downlink within approximately 20 mins is >~ 300 Mbps (similar to downlink)

– Network from CNES to JPL for S-band science and engineering data

• Spacecraft Control Center (SCC, CNES/Contractor) – Real time monitoring of s/c and p/l via S-band housekeeping telemetry

2011/07/25 s3 psc

SWOTJet Propulsion Laboratory California Institute of Technology

IGARSS11 - SWOT Ground System 8

Ground System Elements (2 of 2)

• Payload Operations Centers (POC) – JPL: Near Real Time health monitoring of KaRIN, GPS, Radiometer.

Determine X-band data quality, need for replay.– CNES: Near Real Time health monitoring of Jason Altimeter Suite

• Science Processing Centers – JPL: Processing of KaRIN, POD – CNES: Jason Suite, POD

• Data Archiving and Distribution Centers – JPL: PODAAC – CNES: AVISO

• Project Data Distribution Networks – JPL-CNES link – Science Processing Centers to Archiving/Distribution Centers

2011/07/25 s3 psc

SWOTJet Propulsion Laboratory California Institute of Technology

SWOT Ground System Outline

• Introduction– SWOT mission– Mission phases – Ground segment overview

• KaRIN Data Acquisition and Products– Acquisition characteristics– KaRIN processing – Data Products– Sizing estimates

• Joint Ground System Development – Commonality levels and approach for the processing development

2011/07/25 s3 psc 9IGARSS11 - SWOT Ground System

SWOTJet Propulsion Laboratory California Institute of Technology

IGARSS11 - SWOT Ground System 10

KaRIN Data Acquisition

2011/07/25 s3 psc

Vsat

KaRIN altimetry Resolution << Swath : (2.5m x 10m to 70m) << ~100km Almost full coverage

2.5 m70m max

20 km120 km

50km

50km

6 -10 km

Vsat

Classical Nadir Altimetry Resolution = Swath ( ~ 10km) Inter-track at equator ~ 100km

A few km

SWOTJet Propulsion Laboratory California Institute of Technology

IGARSS11 - SWOT Ground System 11

KaRIN Processing Steps

• SAR processing (range and azimuth compression)

• Interferometric processing (co-registration, computation of interferometric phase and coherence)

• Application of acquisition geometry: geolocation, precise orbit determination, correction of roll, baseline variations

• Propagation corrections: tropospheric, ionospheric delay

• Interferogram flattening/correction, land phase unwrapping

• Estimation of geophysical parameters: water surface detection (HR only), computation of water surface heights, slopes etc.

• Establish/refine floodplain DEM (annually (goal) or mission)

• High-level and multi-temporal processing is a Science Team activity

2011/07/25 s3 psc

SWOTJet Propulsion Laboratory California Institute of Technology

IGARSS11 - SWOT Ground System 12

Data Products (1 of 4)

• Level 0 ( ~ 1 TB/day) – Ocean KaRIN: partial interferograms (Raw to partial interferograms

processing onboard)– Hydro KaRIN: raw data– Nadir altimeter and Radiometer data: instrument raw data– GPSP and DORIS data: POD raw data

• Level 1: Nadir Alt, Radiometer, KaRIN ( ~ 10-12 TB/day) – L1a: Engineering unit conversion, calibration data separated for

additional processing – L1b: Final instrument level data with calibrations appended

• Ocean: 9-11 onboard interferograms (1km x 1 km), correlations, amplitudes with instrument calibrations and phase variations corrected combined

• Hydro (HR): KaRIN phase flattened Interferograms• Altimeter, radiometer compliant with Jason-2 Science Data record

processing (SGDR)

2011/07/25 s3 psc

SWOTJet Propulsion Laboratory California Institute of Technology

IGARSS11 - SWOT Ground System 13

High Level Data Products (2 of 4)

• L2A– Ocean KaRIN : As L1B + Geophysical corrections. Nadir data

merged for cross calibration. – Ocean Crossover Attitude Correction: Estimate attitude errors

from ocean crossovers for correcting both ocean and land data. – Intermediate Hydro: L1B + water mask detection; rain, snow,

ice/frozen detections

• L2B (standard distributed products)Remark: Every field will be associated with an uncertainty estimate– Ocean (LR, fixed swath grid, 500 m; ~ 3 G-samples/day):

• Sea surface (SS) heights in latitude/longitude grid• SS slope at each point of the grid • Sigma 0• Wind speed• Ocean Sea Wave Height on same grid (goal)

2011/07/25 s3 psc

SWOTJet Propulsion Laboratory California Institute of Technology

IGARSS11 - SWOT Ground System 14

High Level Data Products (3 of 4)

• L2B (standard distributed products) (continued) – Hydrology (HR, regions, network, 50 m; TBD[80] GB/day):

• Geo-localized water mask (lakes > (250 m)^2, rivers >100 (50) m)• Estimated water elevations (same sampling as mask) -> Triangular

interpolated network (+ uncertainties)• Topographic map of the flood plain surrounding the water surface

and channel cross sections (requirement to be produced by the end of the mission; goal - annually)

– Ocean Nadir: Similar to current Jason-2 SGDR

• NRT (goal)– Ocean: as Level 2 products but with lower accuracy (quick-look orbit and

calibration using past cross-overs)– Hydro: Level 1 products (SLC + interferogram), no calibration data, use of

ancillary DEM for phase flattening– Nadir products: OGDR/ IGDR products (see Jason-2 OSS)

2011/07/25 s3 psc

SWOTJet Propulsion Laboratory California Institute of Technology

IGARSS11 - SWOT Ground System 15

High Level Data Products (4 of 4)

• POD – determined from GPS and DORIS

• Ancillary Data – updated daily – Atmospheric models: Dry Tropo (surface pressure), Wet Tropo (water

vapor) – Input to ionospheric model

• Geophysical Models – updated infrequently – Mean Sea Surface, Geoid – DEM, Water mask (a priori, then self derived) – Elastic Ocean Tides, Earth Tides, “Pole Tide”

2011/07/25 s3 psc

SWOTJet Propulsion Laboratory California Institute of Technology

IGARSS11 - SWOT Ground System 16

Sizing Considerations

• Global coverage, continuous acquisition• Acquisition hypothesis

– Sea 70%, Land 30% => In the average orbit, KaRIN will acquire 67 GB of data to be transmitted to

ground=> ~1 TB /day (~ 99% HR data)

• Archive Plan – Nominal mission duration: 3 years– Long term archive of (main contributors in terms of volume) Raw HR, SLC

(L1A), Interferograms + masks (L2A), Geo-localized hydro products (L2B) => ~10 000TBytes

• Comparison to other missions – CNES: more than 5 times Pleiades satellite archive (dual civilian/defense

optical imagery, to be launched soon)– NASA: similar to proposed DESDynI (Earth deformation and sea ice from L-

band Radar repeat pass interferometer)

2011/07/25 s3 psc

SWOTJet Propulsion Laboratory California Institute of Technology

SWOT Ground System Outline

• Introduction– SWOT mission– Mission phases – Ground segment overview

• KaRIN Data Acquisition and Products– Acquisition characteristics– KaRIN processing – Data Products– Sizing estimates

• Joint Ground System Development – Commonality levels and approach for the processing development

2011/07/25 s3 psc 17IGARSS11 - SWOT Ground System

SWOTJet Propulsion Laboratory California Institute of Technology

IGARSS11 - SWOT Ground System 18

General Levels of Commonality

• Commonality between two processing systems may be achieved at different levels

– Commonality of the full production system (clone, e.g. Jason)• Prevents existing systems reuse. Not necessary for SWOT development

– Commonality of the algorithms, software, and products• Products are guaranteed 100% similar. May be the right level.

– Commonality of specification and reference data• Independent developments. Risky because reference data does not cover

all cases so products will not be 100% similar.

2011/07/25 s3 psc

SWOTJet Propulsion Laboratory California Institute of Technology

IGARSS11 - SWOT Ground System 19

General Algorithm Development Approach

• Science processing algorithms will be developed primarily by supplier of each instrument

• Algorithm flow will be iterated within entire development team

• Data product definitions will be iterated with Science Team • Algorithm testbed will be set up and prototype processing

developed – Testbed will read and write specified products – Test data will be (or emulate) specified products

• After initial development cycle, algorithm specifications will be written for review by System Engineering team and selected subset of Science Team

2011/07/25 s3 psc

SWOTJet Propulsion Laboratory California Institute of Technology

IGARSS11 - SWOT Ground System 20

CNES Usual Development Approach

• Algorithms prototyping activities and operational chain development are relatively independent The scope of prototype development may be larger than scope of operational

system development But not true the other way: prototypes are needed to build the reference data

for the validation of the operational chain

2011/07/25 s3 psc

Algorithmic prototyping

Operational chain development

GS Infrastructure development

SWOTJet Propulsion Laboratory California Institute of Technology

IGARSS11 - SWOT Ground System 21

JPL Usual Development Approach

• Testbed prototype will incorporate as much of the processing framework as possible

• Notes: • NRT processing will be based on standard algorithms but may not use the

processing framework • Existing POD processing will be implemented in project environment

2011/07/25 s3 psc

Algorithmic prototyping

Operational chain development

GS Infrastructure development

Processing framework from previous projects will be leveraged

Algorithm and framework developers will agree on interfaces and control mechanisms

SWOTJet Propulsion Laboratory California Institute of Technology

IGARSS11 - SWOT Ground System 22

Commonality Approach for SWOT

• Complementary prototyping activities will be conducted by JPL and CNES

• The order and nature of the processing steps of the operational LR and HR processing chains will be discussed and agreed on by JPL/NASA and CNES

• The detailed work share is not yet defined, but the operational algorithms and related binary code will be common

2011/07/25 s3 psc

SWOTJet Propulsion Laboratory California Institute of Technology

23

BACKUP

2011/07/25 s3 psc IGARSS11 - SWOT Ground System

SWOTJet Propulsion Laboratory California Institute of Technology

24

SWOT 40 month Mission Timeline

2011/07/25 s3 psc IGARSS11 - SWOT Ground System

Mission PhaseLaunch(02 Dec 2019)

2020 2021 2022 2019

EOM (Mar 2023)

Checkout / Commissioning (up to L + ~65 days)

LEOP ~3 days: nominal s/c state

Calibration/ Validation Period

OrbitInjection

ScienceDisposal

Calendar Years

22-day repeat, 78 deg, 970 km (non-sun-sync)

2023

Decommissioning( ~ 30 days)

Cal/Val

Eclipse Season (illustration only)

Fast Repeat

Science Observation (36 months)

TBD[3, 1 day; near 22 day]Science Processing Closeout

Fast sampling orbit acq 4 weeks

In-Flight Assessment Meeting

In-Flight Assessment Meeting

Operational Phase

Initial Phase

First Verification Workshop

~ 2-4 weeks Nominal Orbit Acquisition

Final Verification workshop (Sci Team meeting at L + 12 months

Backup or here ?

SWOTJet Propulsion Laboratory California Institute of Technology

IGARSS11 - SWOT Ground System 25

Science Operations (1 of 1)

• Science data collection phase starts ~ 4.5 months after launch. Collect data for 3 full years in observational orbit

• Full validation period: 6 months of data in science orbit + 2 months processing, internal review

– Science Team meeting to assess initial data products ~ 12 months after launch – Processing update based on Science Team assessment implemented ~ 2 months after

meeting • Ready to reprocess all data with updated system ~ 16 months after launch. • Science Requirements on Reprocessing (assume “caught up” at 24 months)

puts requirements on total Processing Center throughput (Suggest project aggregate > 5x). Budget/scenario:

– Cal/val data (~3 months) – as science phase starts – Initial science phase data (~12 months +3 months cal/val) – within TBD [< 3] months.

Result: at ~20 months after launch version 2 of all usable data available. Support Science Team meeting at ~24 months to validate data

– End of nominal mission: Reprocess all data a second time with SDS update done from ~ 30 – 36 months after launch; takes 6 – 8 months (runs until 3 months after end of mission [assumes no extended mission])

2011/07/25 s3 psc

top related