Seattle-Tacoma International Arrivals Facility
Pre-Proposal Informational MeetingTrade Packages
DESIGN BUILD ENJOY
•21 – Doors, Frames & Hardware
•22 – Fireproofing•23 – Drywall / Framing•26 – Asphalt Paving•27 – Misc. Metals
(1 of 2)•30 – Millwork•31 – Interior Wall
Panels•32 – Flooring
•33 – Painting•37 – Ceilings•38 – Landscaping•40 – Ornamental Metals•42 – Interior Glass•43.5 – Fall Arrest•55 – Bridge Dampening
International Arrivals Facility
Page 2
Project Team
• Lou Palandrani – Senior VP/Project Director
• Greg Seldon – Procurement Manager
• Nelson Cook – Sr. Estimating Manager
• Tina Smith – Procurement Coordinator
International Arrivals Facility
Page 3
Subcontractors & Suppliers& Design Team
Progressive Design Build Delivery – Partnership with Port of Seattle
International Arrivals Facility
Page 4
• Key to the growth of our Great Northwest• Growth in international traffic – 13% year-over-year• Federal Inspection Services (FIS) facility built in 1970’s• Currently built to accommodate approximately 800 passengers – current demand is
as high as 2,000 passengers.
WHY?
WHAT?• New modern state-of-the-art facility for enhanced passenger experience.• Improve the airlines’ abilities to operate efficiently. • Provide for the 2025 demand of 2,600 passengers/hour. • Passenger connection times between international and domestic flights.
International Arrivals Facility
Page 5
• Bring the project in below budget• Open new facility on-time in the fall of 2019.• Encourage robust SCS/SBE participation• A modern and efficient international passenger processing facility using latest technology.
Goals
International Arrivals Facility
Page 6
Overall Schedule
• Project Award July 20th, 2015
• Design Development – Finalization 2016 / 2017
• Procurement Trade Packages July 2016– December 2017
• Construction Start 2nd Quarter 2017
• Open New Facilities Fall 2019 / Mid 2020
International Arrivals Facility
Page 7
International Arrivals Facility
Page 8
International Arrivals Facility —Document Verification Officers
Sterile Corridor—Typical Gate Pod
Passenger Walkway —Moving Walkway, View over Airfield
Page 12
International Arrivals Facility
Page 13
International Arrivals Facility
Page 14
International Arrivals Facility
Page 15
International Arrivals Facility
International Arrivals Facility
Page 16
• RFP Submittal Checklist• Bid Form• Unit Price/Alternates Form
(if applicable)• Letter from Surety• SCS/SBE Summary Form• Signed PLA Letter of Assent• Subcontractor Suggested
Opportunities Form
• Subcontract Agreement
• Exhibit A – Contract Documents
• Exhibit B – Scope of Work –Per Package
• Exhibit C – Payment & Performance Bonds
.
RFP Package Contents• Exhibit D – Supplementary
Conditions
• Exhibit D-1 – Letter of Assent to PLA
• Exhibit E – Insurance Requirements
• Exhibit J – Owner Flow Down Provisions
• Exhibit R – Release of Lien
• Logistics Plan – Parking & Access Points
International Arrivals Facility
Page 17
RFP From Website Here
International Arrivals Facility
Page 18
Small/Diverse Business Participation – Scoring Factor
• Clark Construction Group & Port of Seattle o History of Commitment and Core Valueso Community Development > Small Business Development
• Overall Project Goal -- 12% SCS Participation / SBE Participation 17.5%o Includes SBE/MBE/WBE/DBE/DVBE or Small and Diverse firmso Small/Diverse Business Participation involves All Tierso Participation will be part of the Best Value Evaluation in proposals
• Clark SeaTac IAF Website Resource
o www.clarkseataciaf.com under the small business page. o King County SCS Directory
Page 19
International Arrivals Facility
Completing & Submitting ProposalsEach trade package shall include the following:
• Fully completed and executed Proposal Form• Proposal value.• Letter from Surety confirming bondability• Insurance Verification Letter• PLA Letter of Assent (see subcontract Exhibit D-1)• Completed “Proposers SCS/SBE Participation Summary”• Acknowledgement of receipt of issued Addenda.• Detailed Proposal Analysis • Subcontractor Suggested Opportunities From
International Arrivals Facility
Page 20
Subcontractor Suggested Opportunities – Scoring Factor
o Provide Innovative & Creative Ideas
o Support Performance & Quality Standards
o Result in Cost, Schedule & Operational Savings
Page 21
What’s Next for Proposal Process
International Arrivals Facility
• RFIs – Last Day June 22, 2017
• RFP Bid Due Date June 29, 2017
• One on One Proposal Reviews Week of July 10, 2017
• Anticipated Contract Award Late July
www.clarkseataciaf.com
Page 22