Transcript
The Pipeline Services Professionals
Trans-Asia Story
2
1994 2000 2002 2009
Incorporated as Narmada Offshore in Mumbai, India
1994
Preferred Pipeline Subcontractor with ONGC, GAIL, etc
2000
Focus on Pipeline Precommissioning – The Sole Business Activity
1998
- Successfully executed contracts in Oman, Qatar, Iran, UAE ISO 9k, 14k and 18k Preferred pre-commissioning subcontractor with various State owned petroleum companies
2006-08
2008
First Overseas Contract in UAE
2002
1998 20072004 2010
Commence Operations in South East Asia with an Office in SingaporePrecom Projects in Indonesia, Brunei, Malaysia
2010-11
Trans-Asia Pipelines has successfully evolved as preferred precommissioning subcon within 2 decades throughout Asia
Trans-Asia Pipeline Services FZC incorporated in Sharjah, UAE
2004
Greene’s Energy Story • The Company’s predecessor, Greene’s Pressure Testing and Rentals, Inc. was
founded in Lafayette, Louisiana in 1953 to provide rental tool and testing services for the oil and gas market
•In the late 60’s and early 70’s, Greene’s added a line of rental equipment to accompany BOP testing. In the mid 70’s, it started performing production tests, and testing of heaters, separators, flow lines and pipelines. •Hydraulic torque wrench services were added in 1982. •In the 80’s it expanded into the testing, flushing and reinstatement of piping, flanges and valves for construction of offshore drilling rigs, barges, structural components of fixed platforms, production modules, floating MOPU’s and topside production decks for platforms. •Over the years GEG has been successful in extending its geographic footprint and expanding its services lines through the acquisitions of an array of Oil & Gas service groups. •2008 GEG Expands Pipeline services into Brazil •2010 GEG open Asian Pacific Office to service both the Middle East and Asian Pipeline markets. •GEG Positioning of an Asian based asset pool. •Most recently GEG has added Water Treatment Services and expanded operations into Brazil. •Bob Vilyus – Chief Executive Officer has held numerous leadership positions at companies within the energy services industry and prior to joining GEG he served as President and CEO of PII North America, President of Weatherford Compression and President of Gemoco. He has been directly involved in 22 acquisitions and has extensive international business experience.
Joint Service Competencies
Similar Projects in Past Year Client/
Contractor
Dia LengthProject Title Scope of Work Location(Inches
) km
2012Daewoo/MOGE/HHI 32” 132 km SHWE Project
Flooding, Cleaning, Gauging, Hydrotesting, Dewatering, Drying and Nitrogen PurgingMFL Run
Myanmar
2012 IOEC 32” x 3 lines
160 km each
South Pars Ph 12
Flooding, Cleaning, Gauging, Hydrotesting, Dewatering, Drying and Nitrogen Purging
Middle East
2011 GAIL/ Fernas Constructions 48" 290 DVPL-II
Bulk Dewatering, Swabbing, Drying, Calliper Survey and Vacuum Drying
Onshore, India
2009 Dulam Subsea 30” 146Salman Infield
Pipeline Project ((Total 26 pipelines)
Flooding, Cleaning, Gauging, Hydrostatic Testing, Dewatering, Swabbing , Drying and Nitrogen Packing
Salman Field, Middle East
2008/2009 IOEC 32” 87 South Pars
Phases 9 and 10
Flooding, Cleaning, Gauging, Hydrostatic Testing, Dewatering, Swabbing & Drying
Middle East
32” 95
2005
Oil and Natural Gas Corporation (ONGC) / Hyundai Heavy Industries
30” 203Mubai-Uran
Trunk Pipeline Project
Flooding, Cleaning, Gauging , Hydrostatic Testing , Dewatering and Commissioning
Bombay High Field, INDIA 28” 203
Our Clients/Contractors Over 20000 km of
Pipelines pre-commissioned collectively.
Over 500 dedicated and skilled pipeline employees.
Worked with almost all Oil Companies in Middles East, India, South East Asia & North and South America.
Worked with all major Pipeline contractors operating in Asia.
Preferred precommissioning subcontractor in India, Middle East and other locations
Major Assets
FCG HYDROTESTING BULK DE-WATERING/DRYING
VACUUM DRYING NITROGEN PURGING
Pressure Pump
CI Pumps
Air Driven Pressure Pumps
Drying Instrumentation
Air Dryes
CompressorsWater Winning Pump
Filling Pumps
Break Tank
Vacuum Pumps
Vacuum Instrumentation
Oxygen Analyzer
ISO Tank
Vaporizer
Nitrogen Pump
Our Assets as a Glance
QHSE
The TRANS ASIA & Greene’s Energy Group QHSE Management systems are based on the guidelines set forth by the ISO 9001, ISO 14001 and ISO 18001 Management systems
QHSE Management System
Key Features:
Quality Management System Manual
Safety Management System Manual
HSE Procedures Manual
QHSE Certs
PIPELINE PRE-COMMISSIONING
Ruby Field Development Project
Sr. No. Pipeline Service Pipeline OD Wall
Thickness Length
1 Kp 300.59 to kp o.oo
Multi phase Gas 355.6 mm
11.1 /12.7/14.3
mm300.59 km
Rigid Pipeline Summary
Pipeline Details From(KP)
To(KP)
Length
(km)
Dia(mm)
Grade
ServiceDesign
Pressure(Bar)
14” P/LKp
000+000Kp 312+322 Senipah Pig Receiver
312 355.6 API 5Lx65
Multiphase Gas (Non
sour) 90
Pipeline Thickness
Project Introduction Location: Pearloil (Sebeku) Limited is developing Ruby Field of
Sulewasi, Indonesia located in Sebuku PSC which lies in Makasar Straits, east of Kalimantan
Water Depth: Min 20 mtr, Max 60 mtr
Pre-Commissioning Scope of Work :• Gauging of Expansion spool on vessel • Flooding, Cleaning, Gauging of 14” Offshore Pipeline• Riser Tie In • Hydrotesting of pipeline• Dewatering of Pipeline• Vacuum Drying • Nitrogen Purging
Sequence of Operation • Flooding, Cleaning and Gauging of Pipeline from
subsea start up head near Ruby PQP to Senipah Terminal permanent pig receiver
• SSIV Installation and Riser Tie In (by Swiber) • Hydrotesting of Pipeline from PQP riser top to
Senipah pig receiver • Dewatering of Pipeline from Senipah Terminal pig
launcher to temporary pig receiver at PQP riser top • Vacuum Drying at Senipah Terminal pig receiver • Nitrogen Purging from Senipah Pig launcher to Ruby
PQP Riser Isolation Valve
Flooding
Length
(km)
Dia(mm
)
ID
(mm)
Volume
m3
Volume per mtr
m3
Pig Speedm/s
Req Pump
Capacitym3/hr
14” P/L
312 355.6 11.1 27,237.
75 0.0873 0.5-1.0 300
Equipment Setup on Vessel
Flooding, Cleaning and Gauging 250 mtr filtered sea water Pig # 1 bi-di magnetic
brush pig 500 mtr filtered sea water Pig # 2 bi-di magnetic
brush pig 500 mtr filtered sea water Pig # 3 bi-di magnetic
brush pig 500 mtr filtered sea water Pig#4 bi-di gauge pig with
2 gauge plates (95% of minimum ID) fitted with pinger
Line Volume of filtered and chemically treated sea water
Sea Water Treatment
• Seawater filtered through 100 micron filters
• Flooding Chemicals @ 200 ppm – Clariant Make Multi-Treat 5549R
• Florescent Sea dye @ 15 ppm
• Chemical approved by MIGAS
Gauging of Pipeline • Maximum Pipeline thickness – 14.3 mm in Zone 4,
Onshore Section• Selection of Gauge Plate: 95% of Minimum Pipeline
ID (at zone 4) i.e. 95% of 327 mm = 310.65 • To be confirmed: Pipewall thickness of onshore
pipeline/bends
• Further possibilities » EGP Survey » MFL Inspection
• Client to advise on Pipeline Internal Inspection
Geometry Inspection Calliper Inspection will
typically gives data on dents and ovality in Pipeline
Change in internal dia of pipeline
Will be run while dewatering in case its required
MFL Inspection High Resolution ILI – Hall Sensors
MFL Inspection
• Each Sensor is analyzed• Gives changes in
internal dia with respect to corrosion
Hydrotesting of Pipeline
• After installation of SSIV and Riser Tie Ins • Limits: Ruby PQP Riser Top to Senipah
Terminal
Hydrotest Spread/Instruments
Hydrotest – Stages
Pressurize to 35 bar – Air content check Pressurize to 50% of Test Pressure – Leak
Check Pressurize to 95% of Test Pressure – Leak
Check and stabilization Pressurize to Test Pressure Isolate, monitor stabilization24 hr Hold period After successful hydrotest, depressurize to
static head
Bulk Dewatering & Drying
• Proposed from Senipah Terminal so as water can be discharged to sea
• Dewatering Pig Train(s) from permanent pig launcher at Senipah Terminal to temporary (permanent) pig receiver at Ruby PQP
• Vacuum Drying – proposed drying method due to high length of pipeline
Dewatering Stages Desalination & Dewatering Pig # 1 bi-di magnetic high
seal pig Slug of fresh water
equivalent to 350 m3
Pig # 2 bi-di magnetic high seal pig
Slug of fresh water equivalent to 300 m3
Pig # 3 bi-di magnetic high seal pig
Slug of dry air equivalent to 1000 mtr of line volume
Pig#4 bi-di magnetic high seal pig
Line Volume of compressed dry air
Vacuum Drying
Principle: Water boils at -20 deg C at 1 mbar pressure. So reduction in pressure in system to saturated vapour pressure can cause water to boil which can be removed as gas with a vacuum pump
Stages Initial Draw Down Phase: Pressure in pipeline will be brought down to
23 mbar so that water will boil at 20 deg C (ambient temperature) Vaporization Phase: Vacuum pump will continue pumping water
vapours out of system Final Draw down phase – depressurize to 1 mbar Soak Test – Monitoring for 12 hrs
Acceptance: maintaining the pressure of 1 mbar for over a continuous period of 12 hrs.
Nitrogen Purging
• Limits of Operation: from permanent pig launcher at Senipah terminal to permanent pig receiver at Ruby PQP
• Due to very high quantity, Nitrogen generated at Site using membrane units
Responsibilities Trans Asia-Greene’s
Engineering, Procedure Project Procurement for Pigs, Chemicals, Fabrication of
Launchers/Receivers, Flanges Equipment and Instrumentation certificates Experience and skilled manpower Reports
Swiber Subsea Operations Diving Support Logistics support Support inside Senipah Terminal Environmental clearances for discharge of test water to sea
Swiber Support: Safety Issues
HSE Management Plan Permit to work Safety Office/Medical Support Inductions at Senipah Terminal Tool box talk/pre-start meetings Emergency response plan
General Medical/Environmental
Reporting DPR LTIs/Incidents/Accidents/Spills etc
Contingencies/Areas of Concerns Environmental Issues
Discharge of chemically treated water to sea – approx 30k m3 of fluids Aesthetics/visual issues while discharging treated (green colour) water
to sea Environmental clearances
Chemical storage and handling Interface issues:
offshore and at Senipah Terminal Free span correction
Stuck pig contingencies Dislodging of pig/location of stuck pig
Damage to gauge plate EGP Survey/IP inspection – Client to advise
Hydrotest Failures Leak Detection/Leak Test
Equipment Failures Communication Failures
HAZID Mobilization Activities
Lifting Working near/over water Working inside terminal Chemical handling Hot work
Water winning activities Flooding activities (high volume/low pressure) Hydrotesting Diving Support
Subsea Tie ins/Pig launching/Equipment connections Leak detection Pinger detection General visuals
The Complete Pipeline Solution Thank You