SPC Division
RESTORING JAMAICA’S POWER AFTER A NATURAL DISASTER
PRESENTED BY
RICARDO CASE PMP, P.E.SCADA/EMS MANAGER
JPSCO
SPC DivisionAbout JPSCo
Island utility located in the CaribbeanInstalled Capacity ~830 MWPeak Demand 644 MW September 2009Transmission: 69 kV and 138 kV ~ 1184 kmDistribution: 12 kV, 13.8 kV and 24kV ~ 11000 km55 Substations, 28 Generating PlantsTotal Customers: 595,000Staff: ~ 1500 employees Regulator: Office of Utilities Regulation (OUR)Ownership: Marubeni (Japan) 40%, Korea East West Power (EWP) 40% GOJ ~ 20%
2
SPC Division
3
Power Generation and Delivery
SPC Division
4
Generating Plants - Jamaica
HydroMaggotty 6.0 LW River 4.8UW River 3.8Roaring Rvr 3.5Rio Bueno A 2.5Rio Bueno B 1.1Const Spr. 0.8Rams Horn 0.4Munro 3.0
HydroMaggotty 6.0 LW River 4.8UW River 3.8Roaring Rvr 3.5Rio Bueno A 2.5Rio Bueno B 1.1Const Spr. 0.8Rams Horn 0.4Munro 3.0
Old HarbourUnit 1 30 SteamUnit 2 60 SteamUnit 3 65 SteamUnit4 68.5 Steam
Old HarbourUnit 1 30 SteamUnit 2 60 SteamUnit 3 65 SteamUnit4 68.5 Steam
BogueGT 3 21.5 Frame 5GT 6 14 FT 4AGT 7 14 FT 4AGT 8 14 FT 4AGT 9 20 FT 4CGT11 20CCycle 120
BogueGT 3 21.5 Frame 5GT 6 14 FT 4AGT 7 14 FT 4AGT 8 14 FT 4AGT 9 20 FT 4CGT11 20CCycle 120
RockfortUnit 1 18 DieselUnit 2 18 Diesel
RockfortUnit 1 18 DieselUnit 2 18 DieselHunts Bay
Unit B6 68.5 SteamGT 10 32.5 Frame 6GT 4 21.5 Frame 5GT 5 21.5 Frame 5
Hunts BayUnit B6 68.5 SteamGT 10 32.5 Frame 6GT 4 21.5 Frame 5GT 5 21.5 Frame 5
Private ProducersJEP 124 MS DieselJPPC 60 SS DieselBroilers 12 MSD CogenJamalco 11 Steam CogenWigton 38 Windpower
Private ProducersJEP 124 MS DieselJPPC 60 SS DieselBroilers 12 MSD CogenJamalco 11 Steam CogenWigton 38 Windpower
SPC Division
5
24 kV13.8 kV12 kV
LOAD CENTRE
GENERATION STATIONS
138 KV
69 KV
Electricity from the generating stations is transported via the transmission and distribution network to our customers.Customer Operations manage and maintain these networks as well as managing the day to day relationship with the customers.
SPC DivisionEmergency Power System Operations
Source : National Hurricane Center
SPC DivisionOrganizational Chart – Emergency Operations
7
Jamaica Public Service Company (Disaster Preparedness) 2012 EOC Organization Chart - April 2012
CEO Kelly Tomblin
Director EOC/Customer Operations Ricardo Rennalls
Gov. & Reg. Agencies Samuel Davis
Generation Herve Perrin
Communications & IT Sylvia Brown
System Control Dwight Dacosta
Distribution Engineering/Maintenance Steve Dixon
Regional Operations Ferris Stewart
St. James Marlon McKenzie
Trelawny Winston Bansie
Regional Operations. Roger Kennedy
Hanover Norval Bullock
Regional Operations. David Archer
Westmoreland Leighton Barnes
St. Elizabeth David Lewis
St. Catherine Michael Davis
Clarendon Donovan Moore
Manchester Shelton Thomas
Transmission Blaine Jarrett
Losses Sangeet Dutta
ODPEM/Special Projects Desmond Jones
Regional Operations Horace Tulloch
Substation East Raymond Logan
Reporting & Records Dionne Nugent
CEOC Radio Room Ricardo Case
IPPs
St. Mary Cliton Henry
Portland Simon Jackson St. Thomas Andrew McIntosh
Regional Operations Craig Francis
KSAN Omar Brown
Transmission Steve Windross
P & C East & West Lenbern Hopkins
Communication System - Clive Wright
Voice Michael Henlin
KSAS Edward Miller
Substation Projects Nadrae Waugh
Lines & Substation West – Hugh Garvey
Contractors - Claudia Davis/Ann-maria Bennett
Old Harbour Ray Sinclair
Hunts Bay Joseph Williams
Inventory Mgmt Peter Brown/Lorrise Higgins
IT Systems Karlene Haye - Williams
Transport Patricia Walker/Jennifer Foster
Rockfort Glenroy Leslie
Bogue Rueben Thomas
HSSE – George Kates/ Michelle Dunn/Allson Thompson
Facilities Rohan Lindsay
Carrilec/Overseas Assistance S. Dixon/S. Davis/C. Davis
Human Resource Alicia Lyle
Renewables Desmond Fagan
Secretary/Co-ordinator Claudia Davis
Corporate Communication – Winsome Callum
Dispatch Luke Brown
Customer Service Jay McCoskey
St. Ann Wayne Jackson
SPC DivisionHow JPS Prepares
As part of our normal operating procedure, we take steps to ensure that all relevant operational areas of the Company are ready to respond in the event of an emergency.
Our hurricane preparation begins early in the year before the start of the hurricane season. This preparation involves our core operational areas of Generation, Power Delivery, and Region Operations, as well as support areas such as Materials Management and Information Systems.
8
SPC DivisionHow JPS Prepares
STRUCTURAL INTEGRITY PROGRAMME: An important element of our preparation is the ongoing structural integrity programme, which involves the replacement of old wooden poles with concrete poles to reduce the likelihood of displacement or damage by flooding and strong winds.
MATERIAL & EQUIPMENT: We also ensure that adequate material and other resources are in place to facilitate speedy repair and replacement of damaged equipment. To this end, we maintain an inventory of over $300 million disaster preparedness supplies.
9
SPC DivisionHow JPS Prepares
EMPLOYEE TRAINING: Employee preparedness is an important part of our emergency plan. That’s why each year we carry out refresher training and disaster simulation to ensure employee readiness.
10
SPC DivisionDTS Operator Training Session
SPC DivisionPOWER RESTORATION
Electricity restoration after a hurricane involves a number of critical steps that must be followed for maximum efficiency and the safe return of service to customers. To expedite the restoration process, where possible, we carry out several of these steps simultaneously, but it is essential that we observe the restoration protocol. Hastening the process without following these steps could significantly compromise the integrity of the power system, your safety, and our restoration efforts in the long run.
12
SPC DivisionEmergency Power System Operations
Emergency Shutdown and Restoration
Disaster management policy dictates that for category 4 hurricanes and greater the system should be shutdown to protect life and property and restored as soon as the storm has passed and it is safe to do so.
SPC Division
14
Restoration Drivers
1. Critical Loads2. Critical Distribution Circuits3. Critical Substations4. Critical Transmission Circuits5. Critical Generators
Critical loads include: Communication Towers (for JPS and Media Operation), Airports, Hospitals, Main Water Pumps, System Control Center, Morgues, Main Prisons.
SPC DivisionPOWER RESTORATION
Step 1: Checking and Repairing Power Plants and
Main Transmission Lines
Step 2: Getting Power to Essential Services
Step 3: Repair main lines that restore power to the
Largest Numbers of Customers
Step 4: Repair minor lines that restore power to the
Smallest Numbers of Customers
Step 5: Address individual customer needs
15
SPC DivisionFlow of System Restoration
LEGEND138 KV LINE
69 KV LINEDISTRIBUTION
SUBSTATION
GENERATION
SPC DivisionEmergency Power System Operations
Jamaica’s recent storm history
STORM NAME YEARCUSTOMERS
AFFECTED (%)RESTORATION TIME (Days)
Hurricane Gilbert 1988 100 120
Hurricane Ivan 2004 100 43
Hurricane Dean 2007 100 38
Tropical Storm Gustav
2008 70 18
Tropical Storm Nicole
2010 48 7