PROPOSED EXPANSION OF SILICA SAND PRODUCTION (GLASS …
Post on 03-Jun-2022
12 Views
Preview:
Transcript
1
PRE-FEASIBILITY REPORT
for
PROPOSED EXPANSION OF SILICA SAND
PRODUCTION (GLASS GRADE) & LPG STORAGE
CAPACITY FOR GLASS MANUFACTURING UNIT
of
M/s. GUJARAT GUARDIAN LIMITED
VILLAGE: KONDH, VALIA ROAD,
TAL: ANKLESHWAR - 393001, DIST: BHARUCH (GUJ.)
NABL Accredited Testing Laboratory
ISO 9001:2008 Certified Company
Aqua-Air Environmental Engineers P. Ltd.
403, Centre Point, Nr. Kadiwala School, Ring
Road, Surat - 395002
Prepared By:
NABL Accredited Testing Laboratory
ISO 9001:2008 Certified Company
Aqua-Air Environmental Engineers P. Ltd.
403, Centre Point, Nr. Kadiwala School, Ring
Road, Surat - 395002
NABL Accredited Testing Laboratory
ISO 9001:2008 Certified Company
Aqua-Air Environmental Engineers P. Ltd.
403, Centre Point, Nr. Kadiwala School, Ring
Road, Surat - 395002
Prepared By:
2
CONTENTS
Sr.
No.
Description Page No.
1. Executive Summary 3
2. Introduction of the Project/Background information 10
3. Project Description 12
4. Site Analysis 19
5. Planning Brief 20
6. Proposed Infrastructure 21
7. Rehabilitation and resettlement (R & R) Plan 22
8. Project Schedule & Cost Estimates 22
9. Analysis of Proposal (Final Recommendations) 23
3
1.0 EXECUTIVE SUMMARY
1.1 Company Profile
M/s. Gujarat Guardian Limited proposes expansion of Silica Sand production (Glass Grade)
& LPG Storage capacity in Existing Glass Manufacturing Unit at Village: Kondh, Valia Road,
Tal: Ankleshwar - 393001, Dist: Bharuch (Guj.). Total Cost of the Project is Rs. 624 Crores
(Existing = Rs. 584 Crores + Additional Proposed = Rs. 40 Crores). Total Plot Area is
6,55,990.4 m2
.
1.2 Project Details
1.2.1 Products along with Production Capacity
Float Plant Details:
Quantity in Square Meter/Annum S. No. Product
Permitted Additional Total
1 Float Glass
2 Mirror
3 Lacquered Glass
4 Coater Glass
2,50,00,000
- 2,50,00,000
Proposed Expansion Details:
SR.
NO.
PRODUCT NAME EXISTING CAPACITY
(MT/MONTH)
PROPOSED CAPACITY
(MT/MONTH)
1 Silica Sand (Glass Grade) 13,500 56,225
2 By-Products (Coarse, Fines and rejects) 19,620 30,275
3 Total 33,120 86,500
LPG Storage Tank Details
Existing Capacity:
LPG Tanks = 4 Nos. (Capacity = 56.25 MT each)
SR.
NO.
Storage Material No. of Tanks Capacity Total Capacity Tank Dimensions
1 LPG 4 56.25 MT (each) 225 MT Length = 16.2 m
Diameter = 3200 mm
4
Total Proposed Capacity:
LPG Tanks = 6 Nos. (Capacity = 120 MT each)
Proposed combine capacity: 720 MT
SR.
NO.
Storage
Material
No. of Tanks Capacity Total Capacity Tank Dimensions
1 LPG 6 120 MT
(each)
720 MT Design Pressure : 21 Kg/cm2
Overall Length = 24000 mm,
Tank ID = 4010 mm,
Tank Shell = 28 mm thick
Dished End = 18 mm Thick
Note: M/s. Gujarat Guardian Limited is exploring the option to merge the existing and
proposed LPG storage yard for future so that the new LPG yard would be (existing +
proposed) with 720 MT capacity. By proposing this we are also proposing that existing yard
be demolished and merged with new LPG storage yard in case above is the decision.
Existing LPG storage yard: 225 MT
Additional Proposed LPG storage: 495 MT
Total Storage of LPG onsite: 720 MT
1.2.2 Raw Material Requirement
Consumption Quantity Per Month Sr.
No. Raw Material
UOM Permitted Proposed
Additions Total
Float Glass
1 Sand MT 14,000 0 14,000
2 Soda Ash MT 4,500 0 4,500
3 Dolomite MT 3,800 0 3,800
4 Limestone MT 1,400 0 1,400
5 Feldspar MT 850 0 850
6 Salt Cake MT 215 0 215
7 Carbon MT 21 0 21
8 Cullet MT 6000 0 6000
Wet Coater
1 Raw Glass Sq. Meter 5,83,000 0 5,83,000
2 Washing & Polishing Chemicals Kg 2,062 0 2,062
3 Tin Sensitizer Litre 119 0 119
4 Palladium Sensitizer Litre 45 0 45
5 Silver Solution
Silver Nitrate
Litre
Kg
2,600
1,088 0
2,600
1,088
6 Reducer/
Silver less solution
Litre
Litre
4,830
2,920 0
4,830
2,920
7 GMPA & GMPB Litre 1,190 0 1,190
5
Consumption Quantity Per Month Sr.
No. Raw Material
UOM Permitted Proposed
Additions Total
8 Paint MT 68 0 68
9 Ortho-Xylene Litre 9,971 0 9,971
10 HCL-32% Litre 11,393 0 11,393
11 Caustic-32% Litre 13,508 0 13,508
12 Ferric Sulfate kg 256 0 256
Lacquered Glass
1 Raw Glass Sq. Meter 1,50,000 0 1,50,000
2 Washing and polishing chemical Kg 200 0 200
3 Adhesion Promoter Litre 50 0 50
4 Paint MT 10 0 10
A GLASSOLUX NG 9003 PURE WHITE Kg 2,500 0 2,500
B GLASSOLUX NG 2105 Sapphire Kg 2,500 0 2,500
C GLASSOLUX NG 3004 Burgundy Kg 2,500 0 2,500
D GLASSOLUX NG 6113 Fluo green Kg 2,500 0 2,500
E GLASSOLUX NG 9005 Black Kg 2,500 0 2,500
F Ivory Kg 2,500 0 2,500
G Red Kg 2,500 0 2,500
5 Ortho-Xylene Litre 1,000 0 1,000
Sand Beneficiation Plant
1 Raw Silica Sand MT 33,120 53,380 86,500
1.3 Water Requirement, Waste Water Generation and Treatment
Total water requirement is 1650 KL/Day at present which is met through Valia Water Supply
System (Canal Water). The wastewater generation is 921 KL/Day at present. There will be no
increase in Water Consumption as well as Wastewater Generation after proposed
expansion. Out of 921 KL/Day of wastewater, 205 KL/day of domestic wastewater is treated
in STP and then reused for land irrigation/gardening. 716 KL/day of Industrial waste water
(i.e. 150 + 566) is recycled back to Sand Plant for Sand Washing and also is used for
irrigation. Ultimately it is a Zero Liquid Discharge Unit and after proposed expansion it will
remain ZLD.
6
1.4 Air Pollution Source and Control Management
There is no addition or changes in the Flue Gas Stacks & Process Vents
Flue Gas Stacks
Sr.
No.
Stack Attached
To
No. of
Stacks
Height From
Ground (m)
Fuel Used Air Pollution
Control System
Expected
Pollutants
1. Melting Furnace 1 91 Natural Gas,
LPG
Low NOx Burner,
Stack height
PM,TF
2. DG Set
(2.5 MW)
1 30 Diesel NA PM, NOx,
NMHC, CO
3. DG Set
(2.5 MW)
1 30 Diesel NA PM, NOx,
NMHC, CO
4. DG Set
(500 KVA)
1 14 Diesel NA PM, NOx,
NMHC, CO
5. LPG Hot water
generator
exhaust
1 12 LPG NA PM, SO2, NOx
6. Diesel Engine 1
(155 KVA)
1 12 Diesel NA PM, NOx, CO
7. Diesel engine 2
(155 KVA)
1 12 Diesel NA PM, NOx, CO
8. Diesel engine 3
(155 KVA)
1 11 Diesel NA PM, NOx, CO
9. Diesel engine 4
(155 KVA)
1 11 Diesel NA PM, NOx, CO
10. Glass Edge
Burner
1 16 Natural Gas,
LPG
NA PM, SO2, NOx
Process Vents
S.
No.
Stack attached to No. of
Stacks
Stack
height (m)
Pollutant
Emitted
Air Pollution Control
Measures Attached
1. Main Melting Furnace 1 91 PM, TF Stack
2. Ammonia Cracking Plant 1 21 PM,
Ammonia
Stack, Nitrogen
Purging
3. Mirror Line Plant 7 12 VOC,
Ammonia
Stack
4. SO2 Vent 2 17 SO2 Stack
5. Batch House Raw 9 36.5 PM Dust Collector
7
Materials DCF Vents
6. Batch House Raw
Materials DCF Vents at
Basement
2 5.5 PM Dust Collector
7. Batch House Unloading
DCF Vent
1 6 PM Dust Collector
8. Cullet Return System DCF
Vent
1 3 PM Dust Collector
9. Hot Air Exhaust 5 16 PM Not Required
1.5 Hazardous Waste Management
S. No. Items Category Existing Additional Total Treatment and Disposal
Method
1 Used Oil 5.1 25
KL/Year
- 25
KL/Year
Collection, Storage,
Transportation & Sending to
Registered Refiners for recycle
/ reuse
2 Chemical Sludge
from Wastewater
Treatment
35.3 5
MT/Year
- 5
MT/Year
Collection, Storage,
Transportation & Disposal by
landfill at authorized TSDF
3 Waste residue
containing oil
5.2 20
MT/Year
- 20
MT/Year
Collection, Storage,
Transportation & Sent to GPCB
registered TSDF for land Filling
or Incineration
4 Process wastes,
residues & debris
from production
and/or industrial use
of paints, pigments,
lacquers, varnishes,
plastics and inks
21.1 20
MT/Year
- 20
MT/Year
Collection, Storage,
Transportation & Sent to
licensed disposal company
Recycle as a fuel or
Incineration
5 Spent solvents from
the production
and/or industrial use
of solvents
20.2 5
MT/Year
- 5
MT/Year
Collection, Storage,
Transportation & Sent to
licensed disposal company
Recycle as a fuel or
Incineration
7 Discarded Containers
& barrels
contaminated with
hazardous
wastes/chemicals
33.3
240
MT/Year
- 240
MT/Year
Collection, Storage,
Transportation & Disposal by
selling to Registered Vendors
8
8 Furnace/reactor
residue and debris
from pyrolytic
operations
D1 60
MT/Year
- 60
MT/Year
Collection, Storage,
Transportation & Disposal by
landfill at authorized TSDF
9 Inorganic Tin
compounds
B 7 1
MT/Year
- 1
MT/Year
Collection, Storage,
Transportation & Sent to
licensed disposal company for
Recycling
10 Spent catalyst and
molecular sieves
1.7 4
MT/Year
- 4
MT/Year
Collection, Storage,
Transportation & Sent to
licensed disposal company for
Recycling
11 Spent ion exchange
resin containing toxic
metal
34.2 15
MT/Year
- 15
MT/Year
Collection, Storage,
Transportation & Disposal by
landfill at authorized TSDF
Solid (Non-Hazardous) Wastes:
S.No Waste Type Permitted Additional Total Disposal Method
1. Mirror Cullet 100
MT/Month
0 100
MT/Month
Collection, Storage,
Transportation & Sold as
non-hazardous waste for
recycling / reuse
2. Bad Batch, Gcore, other NH
organic chemicals
100
MT/Month
0 100
MT/Month
Collection, Storage,
Transportation &
Recycling/Reuse/Landfill
3. G-Core 100
Kg/Month
0 100
Kg/Month
Collection, Storage,
Transportation & Reuse in-
house for water
neutralization
4. Waste sand 9200
MT/Month
5800
MT/Month 15000
MT/Month
Collection, Storage,
Transportation & Recycling in
house / Landfill & Recycled in
house
5. Cullet 2500
MT/Month
0 2500
MT/Month
Collection, Storage,
Transportation & Recycling
in house / Landfill
6. Sludge Generation from STP 1
MT/Month
0 1
MT/Month
Collection, Storage,
Transportation & Using as
manure in-house
7. Furnace refractory waste, 10 MT/ 0 10 MT/ Collection, Storage,
9
Kwool, Mud, Cement etc. Year Year Transportation & Sent for
Construction earth-filling
8. Cullet Dust 40
MT/Month
0 40
MT/Month
Collection, Storage,
Transportation & Sold To
GPCB approved recycler
9. E-waste 250
Kg / Month
0 250
Kg /
Month
Collection, Storage,
Transportation & Sold to
scrap vendor
10. Trash and Packaging
material waste
20
MT/Month
0 20
MT/Month
Collection, Storage,
Transportation & Sold to
scrap vendor
11. Metal Scrap 10
MT/Month
15
MT/Month 25
MT/Month
Collection, Storage,
Transportation & Sold as
non-hazardous waste for
recycling / reuse (increase in
scrape would be because of
demolish of existing sand
beneficiation plant)
1.6 Green Belt
Company has developed an effective green belt within the factory and on periphery of the
factory. Total Plot Area is 6,55,990.4 m2 out of which 80,936.51 m
2 is Green Belt Area.
1.7 Power & Fuel Requirements
TOTAL POWER REQUIREMENT & SOURCE OF POWER
Power requirement will be 6.5 MW which will be taken from GEB. 4 Nos. of (155 KVA each)
& 3 Nos. of (2.5 MW, 2.5 MW & 500 KVA) DG Sets will be kept for emergency power back
up.
FUEL REQUIREMENT
Quantity S.No Fuel
Existing Proposed Total
1 Natural Gas 6600 m3/hr - 6600 m
3/hr
10
2 LPG 4 MT/hr* - 4 MT/hr*
3 Diesel 1515 Ltrs /Hr 60 Ltrs/Hr 1575 Ltrs /Hr
2.0 INTRODUCTION OF THE PROJECT/BACKGROUND INFORMATION
2.1 Identification of the project and project proponent. In case of mining project, a copy
of mining lease/letter of intent should be given.
Identification of the project
M/s. Gujarat Guardian Limited proposes expansion of Silica Sand production (Glass Grade)
& LPG Storage capacity in Existing Glass Manufacturing Unit at Village: Kondh, Valia Road,
Tal: Ankleshwar - 393001, Dist: Bharuch (Guj.).
Identification of the project proponent
Sr.
No.
Name of
the
Director
Designation Date of
Birth
Address PAN
1 Mr. Vinay
Kumar
Modi
Chairman 13/06/1943 Gujarat Guardian Ltd.,
4/7C DDA Shopping
Centre, New Friends
Colony, New Delhi-
110065
AAEPM1414A
2 Mr. Kevin
William
Baird
Director 09/12/1961 Guardian Industries
Corpn., 2300 Harmon
Road, Auburn Hills,
Michigan, USA
Non-resident
3 Mr. Emad
Al Ebrahim
Director 05/11/1964 10-C Al Khazan Street, Al
HazmSafwa 31892, Saudi
Arabia
Non-resident
4 Mr. Alok Joint 18/06/1966 Gujarat Guardian Ltd., ADQPM0674F
11
K. Modi Managing
Director
4/7C DDA Shopping
Centre, New Friends
Colony, New Delhi-
110065
5 Mr. A. M.
Surana
Finance
Director
02/08/1950 Gujarat Guardian Ltd.,
Valia Road, Village:
Konth, Ankleshwar, Guj.-
393001
AGBPS5137R
6 Mr. P. K.
Gera, IAS
Nominee
Director
26/11/1959 Gujarat Alkalies &
Chemicals Ltd., PO:
Petrochemicals, Baroda-
391346
AATPG0400D
7 Mr. Arun
Kumar
Solanki,
IAS
Additional
Director
14/02/1967 Gujarat Min.
Development Corp. Ltd.,
Khanij Bhavan, 132 ft.
Ring Road, University
Ground, Ahmedabad-52
AGEPS0663H
8 Mr.
Vincent
Pringiers
Director 31/12/1964 189, Kohlenberg, L-1870,
Luxembourg-1870
Non-resident
9 Mr.
Thomas V
Jacobs
Director 04/06/1961 Guardian Industries
Corpn., 2300 Harmon
Road, Auburn Hills,
Michigan, USA
Non-resident
10 Mr.
Douglas
Alan
Girdier
Director 29/09/1966 Guardian Industries
Corpn., 2300 Harmon
Road, Auburn Hills,
Michigan, USA
Non-resident
11 Mr. Independent 01/07/1960 Flat 1102, Tower 1, AABPA1222F
12
Govind
Agrawal
Director Sumer Trinity Towers,
New Prabhadevi Road,
Mumbai-400025
12 Ms.
Bhavna
Doshi
Independent
Director
26/06/1953 C-191, Grand Paradi,
Kemps Corner, Mumbai-
400036
AACPD4427C
2.2 Brief description of nature of the Project
Proposed expansion of Silica Sand production (Glass Grade) & LPG Storage capacity in
Existing Glass Manufacturing Unit
2.3 Need for the project and its importance to the country and or region
The demand for products intended to be manufacture is increasing in the country by
expanding this; M/s Gujarat Guardian Limited will be able to meet the demand of the
product locally. This will also generate direct and indirect employment opportunity for
various levels of people.
2.4 Demands-Supply Gap
Based on our informal survey of the market with our current customers and various traders,
we have found that there is a big potential for the range of the products we are planning.
2.5 Imports vs. Indigenous production
Shall be envisaged.
2.6 Export possibility
Shall be envisaged.
2.7 Domestic/Export Markets
Major portion of the product will be used for domestic market and some portion of the
product may be exported depending on the international market.
13
2.8 Employment Generation (Direct and Indirect) due to project.
M/s Gujarat Guardian Limited will give direct employment to local people based on
qualification and requirement. In addition to direct employment, indirect employment shall
generate ancillary business to some extent for the local population.
3.0 Project Description
3.1 Type of Project including interlinked and interdependent projects, if any.
Proposed expansion of Silica Sand production (Glass Grade) & LPG Storage capacity in
Existing Glass Manufacturing Unit Category: A-2(b) & 6(b)
No interlinked project has been submitted.
3.2 Location (map showing general location, specific location and project boundary &
project site layout) with coordinates.
Map showing general location
(Courtesy: Environmental Information Center, New Delhi)
14
Project Site (Google Map)
15
Plot Layout
16
LPG STORAGE LAYOUT (EXISTING)
17
LPG STORAGE LAYOUT (PROPOSED)
18
3.3 Details of alternate sites considered and the basis of selecting the proposed site,
particularly the environmental considerations gone into should be highlighted.
It is expansion within existing premises. No alternate site is considered.
Major factors involved in the selection of site are listed below:
• Minor site clearance activities shall be carried out to clear shrubs and weed.
• The project site is located on level ground, which does not require any major land filling
for area grading work.
• Proximity to Raw Material suppliers.
• Site is very well connected by road and railway.
• Availability of Power, Water, etc.
Modern infrastructure support and amenities at par in other global markets, including:
� Efficient transport facilities.
� Environment-friendly zone.
� Uninterrupted power supply.
3.4 Size or Magnitude of Operation
Please refer Section-1.2.1, Page No. 1 to 2.
3.5 Project Description with process details (a schematic diagram/flow chart showing the
project layout, components of the project, etc. should be given)
Please refer Please refer Form-I, Annexure-III.
3.6 Raw Material required along with estimated quantity, likely source, marketing area of
final product/s, mode of transport of raw material and Finished product.
For raw material required along with quantity; Please refer Section-1.2.2, Page No. 4
3.7 Resource optimization/recycling and reuse envisaged in the project, if any, should be
briefly outlined.
It is a Zero Liquid Discharge Unit.
19
3.8 Availability of water its source, energy/power requirement and source should be
given.
Water Source
Total water requirement is met through Valia Water Supply System (canal water).
Power & Fuel Requirement
For Power & Fuel Requirement; Please refer Section-1.7, Page No. 9.
3.9 Quantity of wastes to be generated (liquid and solid) and scheme for their
management/disposal.
Please refer Please refer Form-I, Annexure-V & VI.
3.10 Schematic representations of the feasibility drawing which give information of EIA
purpose.
RECONNAISSANCE SURVEY OF EXISTING PLANT ANNUAL REPORT
MARKET ASSESSMENT
FINANCIAL REPORT
PROJECT REPORT
INTRODUCTION
MONITORING OF AIR, WATER & SOIL QUALITY & NOISE
LEVELS. DATA ON METEOROLOGY SOCIO-ECONOMIC STATUS
& BASIC AMENITIES. SITE VISITS BY AND INTERVIEWS WITH
LOCALS
BASELINE
ENVIRONMENTAL
STATUS
ENVIRONMENTAL INFORMATION CENTRE
CENTRAL GROUND WATER BOARD
GUJARAT POLLUTION CONTROL BOARD (GPCB)
PUBLIC HEALTH ENGINEERING DEPT.
AGRICULTURE DEPARTMENT
FOREST DEPARTMENT
IRRIGATION DEPARTMENT
EMPLOYMENT EXCHANGE
HEALTH CENTER
CENSUS DEPT.
INDIAN METEOROLOGICAL DEPT.
SOCIOECONOMIC
STATUS &
INFRASTRUCTURE
PROPOSED
PLANT
FACILITY DESCRIPTION
IMPACTS
METHODOLOGY OF
IMPACT
ASSESSMENT
IDENTIFICATION & ASSESSMENT OF IMPACTS
EVALUATION OF IMPACTS BY MATRIX METHOD
SOURCE OF INFORMATION OVERVIEW OF
E. I. A. STUDIES
ACTIVITIES
ENVIRONMENTAL
MANAGEMENT PLAN
DESCRIPTION OF EFFLUENT TREATMENT PLAN, AIR
POLLUTION CONTROL, HAZARDOUS WASTE MANAGEMENT,
GREEN BELT DEVELOPMENT MONITORING PROGRAM
RISK ANALYSIS
STUDIES &
DISASTER
MANAGEMENT PLAN
SAFETY, HEALTH & ENVIRONMENTAL POLICY, GUIDELINES BY
DIRECTOR GENERAL OF FACTORY SAFETY, MINISTRY OF LABOR. CONSEQUENCE ANALYSIS
PREPARATION OF DISASTER MANAGEMENT PLAN
20
4.0 Site Analysis
4.1 Connectivity
• Site is very well connected by road
• Availability of water, power facilities
4.2 Land Form, Land Use and Land Ownership
It will be incorporated in EIA Studies.
4.3 Topography (along with map)
We will be incorporated topography in EIA Studies.
4.4 Existing land use pattern (agriculture, non-agriculture, forest, water bodies (including
area under CRZ)), shortest distances from the periphery of the project to periphery of the
forests, national park, wild life sanctuary, eco sensitive areas, water bodies (distance from
HFL of the river), CRZ. In case of the notified industrial area, a copy of the Gazette
notification should be given.
It will be incorporated in EIA Studies. CRZ Clearance is not applicable.
4.5 Existing Infrastructure
Existing Infrastructures facilities are listed below:
Site is very well connected by road
Proximity to sugar cane growers
Availability of sufficient land free form cultivation
Availability of power evacuation facilities
4.6 Soil Classification
It will be incorporated in EIA Studies.
21
4.7 Climatic data from secondary sources
Primary source: our own weather station & Secondary Sources: Indian Meteorological
Department, Ahmedabad.
4.8 Social infrastructure available
Depending on the growth of the company the required social infrastructure will be
provided.
5.0 Planning Brief
5.1 Planning Concept (type of industries, facilities, transportation, etc) Town and Country
planning/Development authority classification.
Type of Industry: Proposed expansion of Silica Sand production (Glass Grade) & LPG Storage
capacity in Existing Glass Manufacturing Unit.
5.2 Population Projection
It will be incorporated in EIA Studies.
5.3 Land use planning (breakup along with green belt etc.)
Sr. No. Land Use Proposed Area
(m2)
1 Production Plants 113311.1
2 Parking 16187.3
3 Security Building 404.6825
4 Effluent Treatment plant NA
5 Utility + Tank
6 Tank Farm Area
40468.25
7 Raw Material and Finished Products Storage 283277. 8
8 Gas Tonner Storage 40468.25
9 Green Belt 80936.51
10 Road 80936.51
Total 655990.4
22
5.4 Assessment of Infrastructure Demand (Physical & Social)
It will be incorporated in EIA Studies.
5.5 Amenities/Facilities
It will be incorporated in EIA Studies.
6.0 Proposed Infrastructure
6.1 Processing Zone = 5,75,053.89 m2
6.2 Non- Processing Zone = 80,936.51 m2
6.3 Green Belt
Company has developed an effective green belt within the factory and on periphery of the
factory. Total Plot Area is 6,55,990.4 m2 out of which 80,936.51 m
2 is Green Belt Area.
6.4 Social Infrastructure
Depending on the growth of the company the required social infrastructure will be
provided.
6.5 Connectivity (Traffic and Transportation Road/ Rail/Metro/ Water ways, etc.)
Major factors involved in the selection of site are listed below:
• Site is very well connected by road
• Proximity to sugar cane growers
• Availability of sufficient land free from cultivation
• Availability of power facilities
• Availability of water
6.6 Drinking water Management (Source & Supply of water)
Total water requirement is met through Valia Water Supply System (Canal Water).
23
6.7 Sewerage System
Sewage pipes are laid in entire factory for the removal and disposal of mainly non-harmful
liquid wastes from the offices, canteen and domestic waste coming from different sections.
These liquid wastes are treated in STP and reused back in land irrigation/gardening.
6.8 Solid Waste Management
Please refer Section 1.5 (Page No. 7).
7.0 Rehabilitation and Resettlement (R & R) Plan
7.1 Policy to be adopted (central/state) in respect of the project affected including home
oustees, land oustees and landless laborers (a brief outline to be given)
There is no habitation on the proposed expansion project activity area and it is open
industrial land, so R & R policy is not applicable to this project. There shall not be
displacement of any population in project area. Any major activity that may lead to
resettlement of the people is considered as permanent impact. Hence, there is no
permanent impact on this account. The increasing industrial activity will boost the
commercial and economical status of the locality up to some extent.
8. Project Schedule & Cost Estimates
8.1 Likely date of start of construction and likely date of completion (Time schedule for
the project to be given).
We shall start construction of sand beneficiation plant only after getting environmental
clearance and consent to establish. We shall start production of new sand beneficiation
plant upon making application for CCA.
Note: In the existing premises, we already have operational float glass manufacturing unit
and existing old sand beneficiation plant since 1993.
24
8.2 Estimated Project cost along with analysis in terms of economic viability of the
project.
Total Cost of the Project is Rs. 624 Crores (Existing = Rs. 584 Crores + Additional Proposed =
Rs. 40 Crores).
Break up of Additional Project Cost
Sr.No. Particulars Estimated Cost
(Inr In Lakhs)
1 Land and Site Development 500
2 Building
3 Plant and Machineries
2500
4 Environment protection measures (includes cost of ETP, Tree Plantation,
Evaporator System and Rain Water Harvesting etc.)
1000
TOTAL 4000
9. Analysis of Proposal (Final Recommendations)
9.1 Financial and social benefits with special emphasis on the benefit to be local people
including tribal population, if any, in the area.
• Employment would be as per prevailing norms of state government for skilled and
unskilled people for the proposed expansion project.
• Social Welfare shall be done.
• Cordial relation with the industry shall be established and representation shall be made
to villagers for help for creation of facilities related to health, education, etc.
top related