Team Project 10.1

•STEPS TO SUCCESS •IE415

•Team members: 1 -Nawaf

2 -Abdul hakim3 -Ali

4 -Sultan5 -Ahmed

Project Network By (POM)

Project Network By (Excel)

Critical Path

CP= 27.5 Weeks

C

Project Time won’t be Changed, Because C Slack was 1, Changed to be Zero also Project will

Be Finish on the right time.

IFrom 5 to 4

( I )have Slack 4.5 so it’s not going to effect theProject Time

F(iii ) F is going to effect on Project Time.

The new Deadline = 29 weeks.

M(iv )it’s going to effect the project time

The new deadline is 28

• •23 Project Time was 27.5 and crashed to

Project Deadline is 24 weeks now, and

Costing now $59,466.