Transcript
W O R K S H O PP r o j e c t M A N A G E M E N T Shop Drawings
08.28.2008
1
W O R K S H O P
P r o j e c t M A N A G E M E N T
S H O P D R A W I N G S
W O R K S H O PP r o j e c t M A N A G E M E N T Shop Drawings
08.28.2008
2
P r e s e n t a t i o n O u t l i n e
• Shop Drawings 101
• A201 – 1997
• Section 013300
• Shop Drawing Example
• Do’s and Don’ts
W O R K S H O PP r o j e c t M A N A G E M E N T Shop Drawings
08.28.2008
3
Shop Drawings 101
W O R K S H O PP r o j e c t M A N A G E M E N T Shop Drawings
08.28.2008
4
What are “submittals” ?A201
General Conditions of the Contract for Construction
Paragraph 3.12.1 “… drawings, diagrams, schedules, and other data
specially prepared for the Work by the Contractor, or a Subcontractor, Sub-subcontractor,
manufacturer, supplier or distributor to illustrate some portion of the Work.“
W O R K S H O PP r o j e c t M A N A G E M E N T Shop Drawings
08.28.2008
5
Why are “shop drawings” created ?
A201General Conditions of the Contract
for Construction
Paragraph 3.12.4 “… to demonstrate … the way by which the
Contractor proposes to conform to the information given and the design concept expressed in the Contract Documents.”
W O R K S H O PP r o j e c t M A N A G E M E N T Shop Drawings
08.28.2008
6
Why do architects review submittals?
• to determine if the GC "understands" the CD’s
• correct GC’s “misunderstandings” of the CD’s
• NOT to determine GC “meets the requirements" of the CD’s
W O R K S H O PP r o j e c t M A N A G E M E N T Shop Drawings
08.28.2008
7
Which submittals should the architect request?
Professional Standard of Care
• Structural Stability• Appearance
• Function• Building Code Compliance
W O R K S H O PP r o j e c t M A N A G E M E N T Shop Drawings
08.28.2008
8
A201 - 1997General Conditions of the Contract
for Construction
W O R K S H O PP r o j e c t M A N A G E M E N T Shop Drawings
08.28.2008
9
Contractor's Role A201-1997 : Subparagraph 3.1.3
• The Contractor shall not be relieved of obligations to perform the Work in accordance to the Contract Documents either by activities or duties of the
Architect in the Architect's administration of the Contract...
W O R K S H O PP r o j e c t M A N A G E M E N T Shop Drawings
08.28.2008
10
Contractor's Role A201-1997 : Subparagraph 3.2.1
• ... before starting each portion of Work, the Contractor shall carefully study and compare the
various drawings ... not for the purpose of discovering errors, omissions, or inconsistencies in the Contract
Documents ...
W O R K S H O PP r o j e c t M A N A G E M E N T Shop Drawings
08.28.2008
11
Contractor's Role A201-1997 : Subparagraph 3.7.3
• It is not the Contractor's responsibility to ascertain that the Contract Documents are in accordance with applicable laws, statutes, ordinances, building codes,
and rules and regulations.
W O R K S H O PP r o j e c t M A N A G E M E N T Shop Drawings
08.28.2008
12
Contractor's Role A201-1997 : Subparagraph 3.3.1
• The Contractor shall be solely responsible for and have control over means, methods, techniques,
sequences and procedures ...
W O R K S H O PP r o j e c t M A N A G E M E N T Shop Drawings
08.28.2008
13
Contractor's Role A201-1997 : Subparagraph 3.5.1
• The Contractor warrants to the Owner and Architect ... that the Work will conform to the
requirements of the Contract Documents.
• Work not conforming to these requirements, including substitutions not properly approved or authorized,
may be considered defective.
W O R K S H O PP r o j e c t M A N A G E M E N T Shop Drawings
08.28.2008
14
Contractor's Role A201-1997 : Subparagraph 3.10.2
• The Contractor shall prepare and keep current, for the Architect's approval, a schedule of submittals ...
W O R K S H O PP r o j e c t M A N A G E M E N T Shop Drawings
08.28.2008
15
Contractor's Role A201-1997 : Subparagraph 3.10.3
• The Contractor shall perform the Work in general accordance with the most recent schedules submitted
to the Owner and Architect.
W O R K S H O PP r o j e c t M A N A G E M E N T Shop Drawings
08.28.2008
16
Contractor's Role A201-1997 : Subparagraph 3.12.4
• Submittals not required by the Contract Documents may be returned by the Architect without action.
W O R K S H O PP r o j e c t M A N A G E M E N T Shop Drawings
08.28.2008
17
Contractor's Role A201-1997 : Subparagraph 3.12.5
• The Contractor shall review ... approve and submit to the Architect Shop Drawings ... in such sequence as
to cause no delay in the Work...
• Submittals (shop drawings) ... not marked as reviewed ... and approved by the Contractor may be
returned by the Architect without action.
W O R K S H O PP r o j e c t M A N A G E M E N T Shop Drawings
08.28.2008
18
Contractor's Role A201-1997 : Subparagraph 3.12.6
• By approving and submitting shop drawings ... the Contractor represents that the Contractor
has ... checked and coordinated the information contained within such submittals with the Work and
requirements of the Contract Documents.
W O R K S H O PP r o j e c t M A N A G E M E N T Shop Drawings
08.28.2008
19
Contractor's Role A201-1997 : Subparagraph 3.12.8
• The Contractor shall not be relieved of responsibility for errors or omissions in the Shop Drawings ... by the
Architect's approval thereof.
• ... the Contractor shall not be relieved of responsibility for deviations from ... the Contract Documents by the Architect's approval of Shop Drawings ... unless the Contractor has specifically informed the Architect in
writing of such deviation at the time of submittal …
W O R K S H O PP r o j e c t M A N A G E M E N T Shop Drawings
08.28.2008
20
Contractor's Role A201-1997 : Subparagraph 3.12.9
• The Contractor shall direct specific attention ... to revisions other than those requested by the Architect
on previous submittals.
• In the absence of such written notice, the Architect's approval of a resubmission shall not apply to such
revisions.
W O R K S H O PP r o j e c t M A N A G E M E N T Shop Drawings
08.28.2008
21
Contractor's Role A201-1997 : Subparagraph 3.12.10
• The Contractor shall cause such services or certifications to be provided by a properly licensed design professional,
whose signature and seal shall appear on all ... submittals prepared by such professional.
• Shop Drawings ... designed or certified by such professional ... shall bear such professional's written
approval ...
• The Architect will review ... only for the limited purpose of checking for conformance with information given and the
design concept expressed.
W O R K S H O PP r o j e c t M A N A G E M E N T Shop Drawings
08.28.2008
22
Architect's Role A201-1997 : Subparagraph 4.2.7
• The Architect will review and approve or take appropriate action upon... Shop Drawings... for the limited purpose of checking for
conformance with information given and the design concept expressed.
• Review... is not conducted for the purpose of determining the accuracy and completeness of other details such as dimensions and
quantities...
• The Architect's review shall not constitute approval of safety precautions or... any construction means, methods, ...
• The Architect's approval of a specific item shall not indicate approval of an assembly of which the item is a component.
W O R K S H O PP r o j e c t M A N A G E M E N T Shop Drawings
08.28.2008
23
Architect's Role B151-1997 : Subparagraph 2.6.2
• The Architect shall provide administration of the Contract for Construction as set forth ... in AIA
Document A201, General Conditions.
• Modifications made to the General Condition ... shall be enforceable ... to the extent that they are
consistent with this Agreement or approved in writing by the Architect.
W O R K S H O PP r o j e c t M A N A G E M E N T Shop Drawings
08.28.2008
24
013300 : Submittal Procedures
W O R K S H O PP r o j e c t M A N A G E M E N T Shop Drawings
08.28.2008
25
013300 : Submittal Procedures
Part I : General• 1.1 Related
Documents• 1.2 Summary• 1.3 Definitions• 1.4 Submittal
Procedures• 1.5 GC’s Use of
Cad Files
Part II : Products• 2.1 Action Submittals• 2.2 Info Submittals• 2.3 Delegated Design
Part III : Execution• 3.1 Contractor's
Review• 3.2 Architect's Action
W O R K S H O PP r o j e c t M A N A G E M E N T Shop Drawings
08.28.2008
26
013300 : Related Sections"Payment Procedures"
Applications for Payment & Schedule of Values.
"Project Management and Coordination"
meeting and conference minutes and for submitting Coordination Drawings
"Construction Progress Documentation"
GC's Construction & Submittals Schedule
"Photographic Documentation"
construction photographs & videotapes
"Quality Requirements“
test & inspection reports and mockup req’t
"Closeout Procedures“
warranties
"Project Record Documents“
Record Drawings, Record Specifications, & Record Product Data
"Operation and Maintenance Data“
operation & maintenance manuals
"Demonstration and Training“videotapes of demonstration of equipment & training of Owner's
personnel
Divisions 02 through 49 Sections
specific requirements for submittals in those Sections.
W O R K S H O PP r o j e c t M A N A G E M E N T Shop Drawings
08.28.2008
28
013300 : Submittal Procedures
General• CAD drawings of the CD’s will or will not be provided for
preparing submittals (?)
GC’s use of CAD Drawings• Architect
– makes no representation on compatibility– reserves right to remove all indications of ownership
– makes no warranties
• Data used without any liability to architect• Differences may exist with latest site conditions
W O R K S H O PP r o j e c t M A N A G E M E N T Shop Drawings
08.28.2008
29
013300 : Submittal Procedures
Coordination• Coordinate submittals requiring sequential activity
• Architect reserves the right to withhold action on a submittal requiring coordination with other submittals until related submittals are received
Processing Time• Allow enough time for Initial Review (X days) & Resubmittal Review (X
days)• X = 5 days? 10 days? 15 days?
Deviations• Highlight deviations from CD’s on submittals
W O R K S H O PP r o j e c t M A N A G E M E N T Shop Drawings
08.28.2008
30
013300 : Submittal Procedures
Identification• Permanent label or title block
• Submittal numbering• Specification Section number + decimal point +
sequential number• 061000.01
• Resubmittals : alphabetic suffix after decimal point• 061000.01.A
Transmittals• Architect will “return submittals without review” received
from sources other than the GC
W O R K S H O PP r o j e c t M A N A G E M E N T Shop Drawings
08.28.2008
31
013300 : Submittal ProceduresNumber of Copies
(1) electronic copy, in PDF format
W O R K S H O PP r o j e c t M A N A G E M E N T Shop Drawings
08.28.2008
32
013300 : ExecutionContractor’s Review
• Check for compliance with the Contract Documents• Note corrections & field dimensions
• Submittals are NOT a way to suggest substitutions
• … Mark with Approval Stamp before submitting to Architect– project name + location + specification section title & number
– name of reviewer + date of GC’s approval– statement certifying submittal has been reviewed, checked, &
complies with CD’s
W O R K S H O PP r o j e c t M A N A G E M E N T Shop Drawings
08.28.2008
33
013300 : ExecutionArchitect’s Action
• Architect will not review submittals w/o GC’s Approval Stamp
• Partial submittals are not acceptable & will be returned w/o review
• Submittals not req’d by CD’s … not reviewed and be discarded
• Do NOT rethink, refine, or revise design• Do NOT clarify design (e.g. change scope)
W O R K S H O PP r o j e c t M A N A G E M E N T Shop Drawings
08.28.2008
34
013300 : ExecutionArchitect’s Action Stamp
AIA 201• 4.2.7 : The Architect will review and “approve”…
• 3.12.7 : The GC shall perform no portion of the Work for which... Shop Drawings (are required)... until the...
submittal has been “approved” by the Architect.
AIA B151 • 2.6.11 : The Architect will review and “approve”…
W O R K S H O PP r o j e c t M A N A G E M E N T Shop Drawings
08.28.2008
35
013300 : ExecutionEUA’s Action Stamp
Architect’s review is for the limited purpose of checking for general
conformity with the design concept expressed in the CD’s
The term “approved” is not allowed by most insurance companies.
W O R K S H O PP r o j e c t M A N A G E M E N T Shop Drawings
08.28.2008
36
Submittal Example
W O R K S H O PP r o j e c t M A N A G E M E N T Shop Drawings
08.28.2008
37
Submittal Review ProcessWhat are the steps prior to submittals ?
1. Contractor : Submittal Schedule : submitted & approved by the Architect ?
2. Reviewer : read the A201 and 013300 Submittal Procedures
What are the steps in reviewing submittals ?3. Contractor : stamped & reviewed submittal ?
4. Reviewer : read the specific Spec Section5. Compare what is submitted to what is req’d.6. Review & redline, sign & stamp, and transmit
7. Track submittal info with Newforma & Info Exchange
W O R K S H O PP r o j e c t M A N A G E M E N T Shop Drawings
08.28.2008
38
1. Contractor : Submittal Schedule
Submitted & Approved by the Architect ? A201 - 1997
• Submittal Schedule : recognizes that submittals affect the progress of the project
Contractor’s Standpoint• No excuse for overlooking critical submittal items
Architect Standpoint• No excuse for not providing enough staff to review submittals
• Has the right to approve or disapprove GC’s planned schedule of submittals.
W O R K S H O PP r o j e c t M A N A G E M E N T Shop Drawings
08.28.2008
39
1. Contractor : Submittal Schedule
Submitted & Approved by the Architect ? A201 - 2007
W O R K S H O PP r o j e c t M A N A G E M E N T Shop Drawings
08.28.2008
40
2. Reviewer : read the A201 and 013300 Submittal
ProceduresRead the whole +40 page A201 General
Conditions ?
N OSearch terms : “Submittals” and “Shop
Drawings”
W O R K S H O PP r o j e c t M A N A G E M E N T Shop Drawings
08.28.2008
41
What about projects without an A201 ?
B141 & B151 references the A201 (in absentia)(B141 & B151 : Standard Agreement between Owner & Architect)
Paragraph 1.1.5 When the services under this Agreement include contract administration services, the General Conditions of the Contract for Construction shall be
the A201 …(This document assumes that AIA Document A201 will be used.)
Paragraph 1.3.7.2 Terms in this Agreement shall have the same meaning as those in the
A201 …(By this cross-reference, the parties agree to adopt the terminology found in A201)
W O R K S H O PP r o j e c t M A N A G E M E N T Shop Drawings
08.28.2008
42
3.Contractor : stamped & reviewed submittal?
N O ? • Return it stamped “Rejected” - explain WHY
LOOSE TIGHTMORE
CLAIMSLESS
CLAIMS
W O R K S H O PP r o j e c t M A N A G E M E N T Shop Drawings
08.28.2008
43
4. Read the specific Spec Section
Focus on 1.4 Submittals• Reference related info : other spec sections,
standards & tests
Quality Standard : • … comply with AWI's "Architectural Woodwork Quality
Standards" for grades of interior architectural woodwork indicated for construction, finishes, installation, and other
requirements
W O R K S H O PP r o j e c t M A N A G E M E N T Shop Drawings
08.28.2008
44
5. Compare what is submitted to what is req’d
N O ? • Return it stamped “Revise & Resubmit”
• Note : “Partial submittals are not allowed.”
Submittal Review Sequence Policy• Do not review any submittal until GC submits ALL required info
W H Y ?• Reviewer won’t have to withdraw “approval” of a partially
“approved” item
W O R K S H O PP r o j e c t M A N A G E M E N T Shop Drawings
08.28.2008
45
5.Compare what is submitted to what is req’d
Section 064023 - Interior Architectural Woodwork
1.4 SUBMITTALS• Product Data
• Shop Drawings• Samples for Initial Selection
• Samples for Verification• LEED Submittals
• Product Certificates• Woodwork Quality Standard Compliance Certificates
• Qualification Data
W O R K S H O PP r o j e c t M A N A G E M E N T Shop Drawings
08.28.2008
46
5.Compare what is submitted to what is req’d
Section 064023 - Interior Architectural Woodwork
1.4 SUBMITTALS
C. Shop Drawings: Show location of each item, dimensioned plans and elevations, large-scale details, attachment devices, and other components.1. Show details full size.2. Show locations and sizes of furring, blocking, and hanging strips, including
concealed blocking and reinforcement specified in other Sections.3. Show locations and sizes of cutouts and holes for [plumbing fixtures]
[faucets] [soap dispensers] [and other items] installed in architectural woodwork.
4. Show veneer leaves with dimensions, grain direction, exposed face, and identification numbers indicating the flitch and sequence within the flitch for each leaf.
5. Apply WI-certified compliance label to first page of Shop Drawings.
W O R K S H O PP r o j e c t M A N A G E M E N T Shop Drawings
08.28.2008
47
W O R K S H O PP r o j e c t M A N A G E M E N T Shop Drawings
08.28.2008
48
W O R K S H O PP r o j e c t M A N A G E M E N T Shop Drawings
08.28.2008
49
W O R K S H O PP r o j e c t M A N A G E M E N T Shop Drawings
08.28.2008
50
W O R K S H O PP r o j e c t M A N A G E M E N T Shop Drawings
08.28.2008
51
Show locations and sizes of furring, blocking, and hanging strips, including concealed blocking and reinforcement specified in other Sections.
W O R K S H O PP r o j e c t M A N A G E M E N T Shop Drawings
08.28.2008
52
6. Review & redline, sign & stamp, and transmit
W O R K S H O PP r o j e c t M A N A G E M E N T Shop Drawings
08.28.2008
53
7. Track submittals with Newforma
Use Newforma’s Project Submittals Activity Center :Submittal Tasks
• Log an Incoming Submittal• Create a Submittal Log Report
• Submittal Utilities : Import Spreadsheet
• Go to Info Exchange Activity Center
Selected Submittal Tasks• Create a Submittal Form Report
• Delete the Submittal• Forward for Review
• Identify an Action Item• Modify Submittal Dialog box
• Record a Reviewer’s Response• Respond to Submittal Sender
Resubmittal Tasks• View original submittal’s detail &
history
Send email about Submittal• To the Recipients• To all Reviewers
• To all Participants
Info Exchange Transfer Tasks• View transfer history
• Add or remove recipients• Change access level
• Expiration & reminder settings• Remove content (expire)
• Repost content
W O R K S H O PP r o j e c t M A N A G E M E N T Shop Drawings
08.28.2008
54
W O R K S H O PP r o j e c t M A N A G E M E N T Shop Drawings
08.28.2008
55
W O R K S H O PP r o j e c t M A N A G E M E N T Shop Drawings
08.28.2008
56
Submittal Workflow thru InfoExchange
CONTRACTOR sends Submittal to ARCH via Info Exchange
ARCH logs in Submittal
ARCH logs in Submittal & records CONSULTANT’S response
ARCH stamps/sign Submittal & returns it to the CONTRACTOR
ARCH forwards to CONSULTANT
Info Exchange Newforma Project Center
CONSULTANT reviews & returns Submittal to ARCH via Info Exchange
CONTRACTOR receives Submittal & forwards to SUBCONTRACTOR
W O R K S H O PP r o j e c t M A N A G E M E N T Shop Drawings
08.28.2008
57
Do's and Don'ts
W O R K S H O PP r o j e c t M A N A G E M E N T Shop Drawings
08.28.2008
58
Do's and Don'tsQuestion : True or False ?
• To save time, it's okay to pick colors/textures from printed charts.
Answer : False • Insist on actual material samples
• Review them in similar lighting conditions to the proposed project
• Be careful of wood grain direction/patterns and veneer quality in millwork
• Request mock-ups whenever possible
W O R K S H O PP r o j e c t M A N A G E M E N T Shop Drawings
08.28.2008
59
Do's and Don'tsQuestion : True or False ?
Always refer to EUA issued CD's when reviewing and verifying quantities.
Answer : False• Stay away from verifying quantities.
• If you see an apparent error that is beyond your scope of review, point it out to the GC, but do NOT
attempt to correct it.
W O R K S H O PP r o j e c t M A N A G E M E N T Shop Drawings
08.28.2008
60
Do's and Don'tsQuestion : True or False ?
In the essence of time, submittal reviews may be used to make changes to the contract documents.
Answer : False• Submittal are not contract documents.
• Don't make changes by using the submittals. • Any change of scope should be issued separately by
addendum or CB. • Any changes should be accomplished by Change Order
W O R K S H O PP r o j e c t M A N A G E M E N T Shop Drawings
08.28.2008
61
Do's and Don'tsQuestion : True or False ?
The GC may use submittals as a means for substitutions.
Answer : False• Do not be pressured into accepting substitutions in the submittal
review process. • Instruct the GC to use the substitution process outlined in the
General Conditions.
W O R K S H O PP r o j e c t M A N A G E M E N T Shop Drawings
08.28.2008
62
Do's and Don'tsQuestion :
What can you do if the GC refuses to provide a submittal schedule?
Answer :• It is advisable to document the event by sending
correspondence to the Owner noting the issue and advising that all previously agreed-upon review times
are suspended until an acceptable submittal schedule is provided.
• You may also elect to an RFI requesting such from the GC and tracking the delay in the RFI log.
W O R K S H O PP r o j e c t M A N A G E M E N T Shop Drawings
08.28.2008
63
Do's and Don'tsQuestion :
What can you do when the GC is not adhering to the submittal schedule?
Answer :• Document notification to the GC that they are not in
compliance with the requirements of the contract documents.
• Advise owner in writing that, until the GC adheres to the accepted submittal schedule, you cannot comply with your previously agreed-upon review time, and additional costs
may be incurred as a result.
W O R K S H O PP r o j e c t M A N A G E M E N T Shop Drawings
08.28.2008
64
Do's and Don'tsQuestion : True or False ?
Only revise dimensions that are clearly wrong, don't try to fix them all.
Answer : False• Don't revise dimensions.
• If you see a dimension that is wrong, circle it and suggest the correct dimension be reviewed & verified.
• If there are any other dimensions related to the wrong dimension, make a general statement that associated dimensions be
reviewed. • If you revise (1) dimension, GC may assume you'll review & revise
ALL dimensions.
W O R K S H O PP r o j e c t M A N A G E M E N T Shop Drawings
08.28.2008
65
Do's and Don'tsQuestion : True or False ?
If we receive submittals before CD's have been completed and bid, we should indicate such in our approval.
Answer : False• Return the submittals.
• Respond that we can't process them until the design is complete.
• Not doing so could be putting ourselves under unnecessary risk.
W O R K S H O PP r o j e c t M A N A G E M E N T Shop Drawings
08.28.2008
66
Do's and Don'tsQuestion : True or False ?
It's okay to review & stamp submittals for design-build systems as long as we're the Architect of Record.
Answer : False• Do not extend our responsibility (liability) beyond that what your
contracted for. • If you do, be ready to share the blame once something goes
wrong.
W O R K S H O PP r o j e c t M A N A G E M E N T Shop Drawings
08.28.2008
67
Do's and Don'tsQuestion : True or False ?
Only accept submittals from a GC that are NOT approved & stamped unless you can trust him.
Answer : False• Do not accept unstamped submittals from a GC no matter your
relationship. • It may appear that the architect's is taking on the GC's
responsibility.
W O R K S H O PP r o j e c t M A N A G E M E N T Shop Drawings
08.28.2008
68
Do's and Don'tsQuestion : True or False ?
It's okay to review/stamp submittals issued directly from the Subcontractor only if the GC and Owner are okay
with it.
Answer : False• This would not allow the GC to review, approve and
stamp the submittals prior to issuing them to the architect.
• It may appear that the architect's is taking on the GC's responsibility.
W O R K S H O PP r o j e c t M A N A G E M E N T Shop Drawings
08.28.2008
69
Do's and Don'tsQuestion : True or False ?
We should ignore submittals that we did not request as long as they're approved/stamped by the GC.
Answer : False• Return "not requested/not reviewed".
• To accept or take affirmative action on them would merely create the duty to review them.
• To take affirmative action on them would not only increase the architect’s uncompensated workload but would likely be construed as 'approval' in the eyes of
the law.
W O R K S H O PP r o j e c t M A N A G E M E N T Shop Drawings
08.28.2008
70
Do's and Don'tsQuestion : True or False ?
We do not need to review/stamp technical submittals that are reviewed/stamped by our engineering consultants.
Answer : False• Architect : prime responsibility to the owner for
processing submittals• Architect : review & stamp the submittals only after the
consultant has reviewed and stamped them. • It is doubtful that we can avoid responsibility to the
owner by not stamping the drawings.
W O R K S H O PP r o j e c t M A N A G E M E N T Shop Drawings
08.28.2008
71
Do's and Don'tsQuestion :
What if requested submittals were not submitted by the GC and therefore not reviewed by the Architect?
Answer :• Architects : verify all specified submittals are actually received
from the GC. • Good Idea : prepare a checklist of all specified submittals at the
beginning of the construction period so that each may be checked off as received.
• The GC should then be reminded to submit any missing submittals.
W O R K S H O PP r o j e c t M A N A G E M E N T Shop Drawings
08.28.2008
72
Q u e s t i o n s ?
W O R K S H O PP r o j e c t M A N A G E M E N T Shop Drawings
08.28.2008
73
W O R K S H O PP r o j e c t M A N A G E M E N T Shop Drawings
08.28.2008
74
W O R K S H O PP r o j e c t M A N A G E M E N T Shop Drawings
08.28.2008
75
W O R K S H O PP r o j e c t M A N A G E M E N T Shop Drawings
08.28.2008
76
top related