NORSOK Z standards for Technical Information (Z-TI)ROLV WERNER ERICHSEN/ROBERT SKREDEBJØRN BERLI

23rd and 24th May 2018

2

The NORSOK Z-TI initiative addresses the challenge that current documentation requirements and way of working with standards drive cost on NCS

• Oil and Gas operators pay 20%-30% more for the same products, compared to other industries

• A significant share of this difference is related to specifications and documentation requirements

• The additional cost on NCS was NOK 50 billion in 2016

• Several examples also show that requirements does not sufficiently improve safety

3

Opportunities to improve quality and efficiency in existing work processes and cooperation through digitalization has not been captured widely in the industry

“This initiative is important for achieving lasting improvements. I would urge the industry to support the project.”

Terje Søviknes Oil and Energy Minister, Norway

Recommendations for Digital field development process

• Purpose full collaboration to harvest effects of digitalisation

• Standardised digital plant information

• …accelerating the current digitalisation of the NORSOK standards – particularly NORSOK Z-TI

4

NORSOK Z-TI – Current status• Current NORSOK Z-TI standards are basically outdated (from the late 90'ies)− Revision of these standards recommended as high priority in the NORSOK analysis

• NORSOK Z-TI revision objective: Enabling requirements distribution and information flow through the value chain, over the life cycle of installations

• Initial scoping has identified an opportunity to fully digitalize these standards to create a competitive advantage for the Norwegian oil & gas industry

• The project will be demanding and the funding requirements will exceed the Sector Board of Petroleum Standardization's budgetary limits

• Work is in progress to establish a JIP with broad industry participation and DNV-GL as the project manager− JIP funding approx. 20 – 30 mill NOK in cash with equivalent in-kind amounts for a two year duration− DNV-GL very experience in managing JIP's and will also participate in this JIP

• Targeting Sector Board of Petroleum Standardization endorsement of the JIP in the March 2018 meeting− Governance− Participant fees− IP− etc

• JIP launch May 2018

5

Owners & Operators

The problems are……

• Requirements are analogue and company specific

• Documentation is company specific

• Software solutions are proprietary

• Verification of requirements are manual

• Re-use of concepts and solutions are analogue

EPCs

Vendors & Suppliers

Authorities, public, society Requirements InformationReview/Verification

DocumentationReview/Verification

DocumentationReview/Verification

Documentation

Exploration Feed Detailed engineering

Procurement and const. Operation Modification Decom

DNV GL ©

From document centric to data centric requirements management

6

Requirements and standards are available as text in documents, hence only understandable to humans not computers.

Requirements are translated manually into systems and software to make them understandable to computers.

Requirements represented in a language understandable to computers and humans.

Individual requirements are uniquely referable and identifiable.

Complete consistency checks using automated reasoning.

Systematic support for automated verification.

Current Practice Desired future state

DNV GL ©

Solution: Common digital requirements for Technical Information

Requirements represented in a language understandable to computers and humans.

Individual requirements are uniquely referable and identifiable.

Digital Information can be linked directly to digital requirements

Complete consistency checks using automated reasoning.

Enable automated verification

7

Operators

Contractors

SuppliersDigital

requirements

8

NORSOK Z-TI: Digital requirements and exchange of technical information through the value chain

• Reduced and standardized requirements, enabling automation of knowledge work and being an opportunity for increased value creation through digital services.

• Competitive advantage for Norwegian industry, removal of established, but undocumented requirements, and establishing methodology and tools for traceability and consistency in requirements.

• Addressing digital requirements will also include requirements for information management and information transfer. This digitalization will be important elements in automation of work processes and decision support.

9

Company Specs

Steps from company specific requirements to international standards(Definitions alone is not sufficiently precise, and requirements must be based on discipline knowledge)

NORSOK

IOGPJIP 33

ISO/API

10

NORSOK Z-TI provides a common foundation for change

It’s up to the participants and the industry to realise the potential values

• A common language for digital requirements and asset vocabularies

• A scalable way of capturing and structuring true digital requirements

• Information sharing in line with Konkraft’s recommendations for the digital field development process

• Updated and digitalised NORSOK requirements to Technical Information(Z-TI standards)

• Relevant parts of the deliverables will be fed into international standards like ISO/IEC

11

Z-TI Q4-2017

Z-TI GAP1

JIPZ-TISektorstyre Petroleum

Z-TI stafettpinne fra GAP1 (1.1.2018-1.5.2018) til JIPZ-TI

12

Q1/2018 Q1/2019 Q4/2019

2017 2018 2019

20.09.2017Milestone #1 Milestone #3 Milestone #4

Q2/2018Milestone #2

NORSOK Z-TI timeline acording to decition in Sector Board Petroleum September 2017

EPIM STANDARDIZATION PROJECT (STI)

#1: Requirements methodology for technical information

#2: Requirements governance and

distribution

#4: Z-001 Establishing requirements for asset information

#3: Z-018 Requirements for equipment specific information

#0: Project Definition

Milestone #0

#5: Final structure for Z-TI (Z-001, Z-018, Z-003, Z-DP-002 and Z-CR-002)

Why Standardize?

Concept for STI (Standardization Initiative) delivering to Z-TI: Standard information and documentation for equipment

www.epim.no 13

Supplier 1

Supplier 2

Supplier 3

Common Industry

Requirementsfor Supplier Equipment

Oil&GasOperator

1

Oil&GasOperator

2

Oil&GasOperator

3

Supplier 1

Supplier 2

Supplier 3

Oil&GasOperator

1

Oil&GasOperator

2

Oil&GasOperator

3

Eng. Contr. 1

Eng. Contr. 2

Eng. Contr. 3

WG1-Instrument WG2-Electro WG3-Valves

14www.epim.no

ConocoPhillipsStatoilAibelAker SolutionsEmersonABBSiemens

ConocoPhillipsShellStatoilAker SolutionsAibelSiemensABB

ConocoPhillipsAkerBPStatoilAibelAker SolutionsScoreMRC Solberg & Andersen

ConocoPhillipsStatoilRepsolAker SolutionsAibelIntelecomJotron

ConocoPhillipsStatoilAibelAker SolutionsNOV Kran og løftAir Products

WG5-Telecom WG6-Mechanical

STI working method: Working group participants from the whole value chain

STI WG3-ValvesRequirements matrix

15www.epim.no

16

Z-TI deliverables: Digital framvwork for requirements management and requirements distributionEksempel på selskapspesifikk løsning:

• Digitalt rammeverk for kravforvaltning

• Katalogbasert

• Søkbart innhold

• All informasjon om ett produkt tilgjengelig på en plass

• Kravdistribusjon i form av brukergrensesnitt, eksport av krav og generering av kravdokument (PDFs)

• Hvert selskap kan ha sine egne verktøy for presentasjon og integrering av felles krav.

17

Q1/2018 Q1/2019 Q4/2019

2017 2018 2019

20.09.2017Milestone #1 Milestone #3 Milestone #4

Q2/2018Milestone #2

NORSOK Z-TI timeline acording to decition in Sector Board Petroleum September 2017

EPIM STANDARDIZATION PROJECT (STI)

#1: Requirements methodology for technical information

#2: Requirements governance and

distribution

#4: Z-001 Establishing requirements for asset information

#3: Z-018 Requirements for equipment specific information

#0: Project Definition

Milestone #0

#5: Final structure for Z-TI (Z-001, Z-018, Z-003, Z-DP-002 and Z-CR-002)