MICE Coupling Coil Testing at Fermilab All Experimenters Meeting Ruben Carcagno March 19, 2012 1R. Carcagno - MICE CC Testing at Fermilab3/19/2012.

Post on 21-Jan-2016

214 Views

Category:

Documents

0 Downloads

Preview:

Click to see full reader

Transcript

R. Carcagno - MICE CC Testing at Fermilab 1

MICE Coupling Coil Testing at Fermilab

All Experimenters MeetingRuben CarcagnoMarch 19, 2012

3/19/2012

R. Carcagno - MICE CC Testing at Fermilab 2

TD/T&I

Muon Ionization Cooling Experiment

3/19/2012

Coupling Coil #1

Coupling Coil #2

Spectrometer Solenoid #1

Spectrometer Solenoid #2

• The MICE Program has an urgent need to test the MICE CC cold mass assembly• Supporting this test is a high Fermilab priority• Organizations involved supporting this test are the Accelerator Physics Center,

Technical Division, Accelerator Division, and Lawrence Berkeley National Lab

R. Carcagno - MICE CC Testing at Fermilab 3

TD/T&ICoupling Coil

3/19/2012

• Provides a magnetic field to a 201 MHz RF cavity• Magnetic field is needed to keep the muon beam

within the iris of the RF cavities

R. Carcagno - MICE CC Testing at Fermilab 4

TD/T&IMICE CC Assembly

3/19/2012

First Coupling Coil has been delivered to LBNL from China

Parameter Value Coil Length (mm) 281 Coil Inner Radius (mm) 750.5 Coil Thickness (mm) 104 Number of Layers 96 No. Turns per Layer 166 Assembly O.D. (without cooling tubes, mm) 1860.00 Assembly O.D. Envelope (with cooling tubes protrusion, mm) 2025.64 Assembly Height (mm) 325 Assembly Weight (tons) 2.2 Maximum Design Current (A) 210 Self-Inductance (H) 596 Stored Energy at 210 Amps (MJ) 13 Coil Temperature Margin (K) 0.77

R. Carcagno - MICE CC Testing at Fermilab 5

TD/T&ITest Objectives

• Train the coil to 210 A– Should not take a large number of training quenches (less

than 10 to 15 quenches)• Hold maximum current for 24 hours• Conduct thermal cycle and verify training holds• Very aggressive schedule: MICE has urgent

programmatic needs, test results needed by end of August 2012

• There will be a total of 4 Coupling Coils to be tested: one for MTA, two for MICE, and one spare

3/19/2012

R. Carcagno - MICE CC Testing at Fermilab 6

TD/T&IMICE CC Assembly Preparation

• To be installed by LBNL:– Cooling Tubes– Coil Quench Protection system. Coil cannot be

tested without cold diodes and cold resistors!– Mechanical Supports– Heater to induce quench– Instrumentation (Temperature sensors, voltage

taps)• Need to be completed by end of April 2012

3/19/2012

R. Carcagno - MICE CC Testing at Fermilab 7

TD/T&ITest Cryostat

3/19/2012

• Built by Meyer Tool in 1997 for SMES, never used • Recently transferred from NHMFL/FSU to Fermilab for this use• Requires several modifications

11.8 ft.

10 ft.

R. Carcagno - MICE CC Testing at Fermilab 8

TD/T&I

Removing Background Coil at NHMFL

• Background coil was removed prior to shipping to Fermilab and it was disposed in Florida

3/19/2012

R. Carcagno - MICE CC Testing at Fermilab 9

TD/T&ICryostat Modifications

3/19/2012

R. Carcagno - MICE CC Testing at Fermilab 10

TD/T&I

Test Site: Central Helium Liquefier

• Locations considered: IB1, CDF, and CHL• CHL (South Annex) was recommended• Fermilab management directed AD and TD to proceed with CHL location

recommendation on February 17, 2012 and make it a high priority

3/19/2012

R. Carcagno - MICE CC Testing at Fermilab 11

TD/T&ICHL Test Area

• Cryostat was already moved to CHL test area location• Preliminary vacuum vessel leak check in progress• Calculation of forces due to fringe magnetic field interaction with building ferromagnetic

elements in progress (V. Kashikhin)

3/19/2012

R. Carcagno - MICE CC Testing at Fermilab 12

TD/T&ISystems

• Cryogenic System– Forced 2-phase

conduction cooling supplied to cryostat from nearby 10,000 gallon CHL LHe dewar, refilled as needed by CHL liquefier

• DAQ and Control– Based on proven

technology in use at the IB1 Magnet Test Facility

• Power– Power supply provided by

LBNL

3/19/2012

R. Carcagno - MICE CC Testing at Fermilab 13

TD/T&IPreliminary Schedule

• Technically driven, attempts to meet MICE urgent programmatic needs• Coil must be received by end of April 2012• Assumes availability of skilled resources (4 FTEs in 6 months!)• This schedule will be very tough to meet!

3/19/2012

R. Carcagno - MICE CC Testing at Fermilab 14

TD/T&I

A “Solenoid Test Facility” at FNAL

• This the first step towards a “Solenoid Test Facility” at Fermilab

• Will provide a much needed capability for testing large bare superconducting solenoids in the United States

• Example of other uses: test of mu2e transport section modules and PS prototype– Must add a large DC power

system and vapor-cooled current leads

3/19/2012

R. Carcagno - MICE CC Testing at Fermilab 15

TD/T&ISummary

• All elements are in place to proceed with a MICE CC Test Stand installation at CHL.

• No technical issues: technology well understood and based on prior experience

• Critical project elements: tight schedule, complex interfaces, and availability of skilled people– Must be given very high priority at LBNL, FNAL/AD, and FNAL/TD– Must make sure scope is kept to a minimum– Still, schedule is very optimistic!

• Substantial additional effort needed to test mu2e Toshiba PS Prototype and TS coils, but most MICE CC setup is directly applicable for testing these other solenoids

• This is the first step in the development of a “Solenoid Test Facility” at Fermilab

3/19/2012

top related