Transcript
8/14/2019 KSPC Newsletter Vol14 May09
1/101
KSPCS CHIMNEY TO RISE 110 METERS HIGH INTO THE SKY
ebu Power Plants tall chimney will soon rise into the sky as the
astounding erection of this important feature of the project has already
commenced.
Concrete pouring work has started and will continue until the height of 110
meters from the ground of the structure is achieved. The slip-forming
equipment used was imported from Sweden. The technology was introduced in
the country by a Hungarian. This is now being enjoyed by both the Filipinos
and the Korean nationals who are implementing the construction work.
KSPCS Chimney to Rise 110m High
EDITION NO. 14, May 20, 2009The Cebu CFBC Plant Chronicle
KSPCs chimney that will soon be a new landmark of Naga,Cebu (May 18, 2009)
CCCC
8/14/2019 KSPC Newsletter Vol14 May09
2/102
Into the Sky (Cont.)
eanwhile, the rate of concrete casting is 600 mm high every 4 hours.
The cement to be poured is being monitored and the temperature is being
controlled in order to stabilize the concrete before the forms slip up to the next
elevation. The rebar preparation and installation are done in advance so that
they will not be caught up by the advancing pouring of concrete.
The chimney has strong foundation that can withstand the forces of nature
and carry the load of the structure itself. The foundation alone can consume
770 cubic meters of ready mix concrete with strength of 30 megapascals
reinforced by 231 tons of rebar. Once completed, the new skyscraper, which
has a fascinating dome figure on its top, will be a new landmark in Naga, Cebu.
MMMM
The swift work progress in the erection of chimney
(Left Photo, May 5, 2009/ Right Photo, May 18, 2009)
8/14/2019 KSPC Newsletter Vol14 May09
3/103
MMTS 1st Quarterly Meeting
SPCs Multi-Partite Monitoring Team (MMT) held its first quarter meeting
last April 21, 2009 at the Cebu Construction Office. Majority of the members
representing the concerned stakeholders of the project, namely, DENR-EMB 7,
CENRO, LGUs, NGOs, academe and rural health units attended the whole-day
activity.
The highlights of the affair included the updating of the official listing of MMT
members, presentation of the current KSPC project status, review and
discussion of the MMT Manual of Operations (MOO), and the planning of
future activities and meetings.
The MMT members during the CY 2009 1st QuarterlyMeeting (April 21, 2009)
KKKK
8/14/2019 KSPC Newsletter Vol14 May09
4/104
MMT Meeting (Cont)
he MOO defines how the MMT should operate with regards to monitoring
activities, rules and regulations, trainings, sampling methods, and all other
areas of concern. With the development of this manual, the different activities
of the group can be done smoothly and in line with their goals.
There was a site visit in the afternoon to provide a visual compliment of the
project status. The whole event created a benchmark for the committees goals
in formulating the yearly work and financial plan. Furthermore, this marked
the beginning of the groups adherence to their Mission and Vision for the year
2009: Our Environment, Our People, Our Concern.
MMT members given updates on the project status as theytour the project site (April 21, 2009)
TTTT
8/14/2019 KSPC Newsletter Vol14 May09
5/105
KSPC Joins Barangay Colons Fiesta
iving up to its commitment of community involvement, KSPC has
organized a basketball team to participate in Barangay Colons Summer
League Basketball Tournament, as part of the activities for the fiesta
celebration on May 28, 2009.
Aside from the direct involvement of its employees to the sports activity of its
host barangay, KSPC also provided financial donation to ensure the success of
the lined up socio-cultural events, such as variety show, drama, dance and
singing contest, for the feast of San Vicente Ferrer.
KSPCs Basketball Team joins the opening of Barangay
Colons Summer Basketball League (May 10, 2009)
LLLL
8/14/2019 KSPC Newsletter Vol14 May09
6/106
Project Progress
View of the Unit 1 HP Turbine Assembly
View of the Unit 1 IP & LP Turbine Assembly
8/14/2019 KSPC Newsletter Vol14 May09
7/10
8/14/2019 KSPC Newsletter Vol14 May09
8/108
Project Progress
Rebar and form works for the discharge tunnel(May 18, 2009)
On-going fabrication of Coal Silo Shell for Unit No. 1 Boiler(May 18, 2009)
8/14/2019 KSPC Newsletter Vol14 May09
9/109
Project Progress
Rebar and form works for Unit No. 1 Turbine GeneratorPedestal (May 18, 2009)
On-going work for the Administration Building(May 18, 2009)
8/14/2019 KSPC Newsletter Vol14 May09
10/1010
PROJECT PROPONENT : KEPCO SPC Power Corporation (KSPC) CAPACITY : 100 MW x 2 Units PLANT TECHNOLOGY : CFBC (Circulating Fluidized Bed Combustion) LOCATION : Colon, City of Naga (20 Km from Cebu City) TARGET COMPLETION : Unit No. 1: February 2011; Unit No. 2: May 2011
Project Information
Contact us
Mr. Bag Woon ChoiMs. Jasmin Suma-oy
Tel. No. (032) 272 6290~91, 93Fax No. (032) 489 7010
top related