KICK-OFF MEETING - Brindisi 21 July 2011
EcoPlasBrick
KICK-OFF MEETING
Brindisi, 21 July 2011
AGREEMENT NUMBER: ECO/10/277233/SI2.596954
EcoPlasBrick
Innovative recycled plastic based panels for building field
KICK-OFF MEETING - Brindisi 21 July 2011
EcoPlasBrick
Agenda
• Welcome and introduction of partners
• Partners presentation
• Project objectives, results and technical description
• Coffee break
• Financial and Administrative Issues
• Work programme and role of each partner• Lunch
• Visit to laboratories
• Planning of first 6 Months Activities
• Meeting closure
KICK-OFF MEETING - Brindisi 21 July 2011
EcoPlasBrick
Agenda
• Welcome and introduction of partners
• Partners presentation
• Project objectives, results and technical description
• Coffee break
• Financial and Administrative Issues
• Work programme and role of each partner• Lunch
• Visit to laboratories
• Planning of first 6 Months Activities
• Meeting closure
KICK-OFF MEETING - Brindisi 21 July 2011
EcoPlasBrick
Partners presentation
1. Consorzio CETMA
2. Consorzio TRE
3. PANDORA GROUP
4. MOTULAB
5. ACCIONA
6. Albanian Constructor Association
KICK-OFF MEETING - Brindisi 21 July 2011
EcoPlasBrick
• It’s a nonpolitical and non profit voluntary organization
• Established the 12th October 2001
• Covers all the Republic of Albania territory
• It counts more than
400 members
Albanian Constructors Association
KICK-OFF MEETING - Brindisi 21 July 2011
EcoPlasBrick
• To protect and represent the interests and rights of:
constructors construction companies companies of construction materials’ production companies of installationdesign companies and also protect the urban environment
ACA’s TARGET
KICK-OFF MEETING - Brindisi 21 July 2011
EcoPlasBrick
Albanian Construction Association serve encouragement in:
development of constructioncontemporaneous techniques of application construction materials production
ACA’s TARGET
KICK-OFF MEETING - Brindisi 21 July 2011
EcoPlasBrick
• to carry out the activities related to: dissemination and promotion of contacts for the creation of European
partnerships; • it will facilitate the spreading of ECOPLASBRICK
particularly in the Balkans and in East Europe. • to favour the introduction in the building market of
new, innovative and more environmental friendly products.
ACA’s Involvement
KICK-OFF MEETING - Brindisi 21 July 2011
EcoPlasBrick
• Allowing a proper market replication in the building sector in Albania.
• Responsible for disseminating the project results in other European countries.
• Crucial for the European partnership promotion.
ACA’s Involvement
KICK-OFF MEETING - Brindisi 21 July 2011
EcoPlasBrick
• Disseminating information and project application through workshops, in Tirana and ACA’s branches.
• Informing designers through workshops for alternative constructions materials.
• Advising Constructors Association in Macedonia, Kosovo etc, regarding the project results.
ACA’s Role
KICK-OFF MEETING - Brindisi 21 July 2011
EcoPlasBrick
Agenda
• Welcome and introduction of partners
• Partners presentation
• Project objectives, results and technical description
• Coffee break
• Financial and Administrative Issues
• Work programme and role of each partner• Lunch
• Visit to laboratories
• Planning of first 6 Months Activities
• Meeting closure
KICK-OFF MEETING - Brindisi 21 July 2011
EcoPlasBrick
Project objectives, results and technical description
Title: Innovative recycled plastic based panels for building field
Acronym: EcoPlasBrick
Agreement number: ECO/10/277233/SI2.596954
Start: 1 July 2011
End: 30 June 2014
KICK-OFF MEETING - Brindisi 21 July 2011
EcoPlasBrick
Plastic waste
•Products: PET, PP, PE
•By-products: Mixed plastic waste
Separate collection,
sorting
The need
•Landfill
•Incineration
•Aggregates, Plastic lumbers
KICK-OFF MEETING - Brindisi 21 July 2011
EcoPlasBrick
DIRECTIVE 2008/98/EC OF THE EUROPEAN PARLIAMENT AND OF THE COUNCIL
of 19 November 2008on waste and repealing certain Directives
Article 4
Waste hierarchy
The need
KICK-OFF MEETING - Brindisi 21 July 2011
EcoPlasBrick
EcoPlasBrick objectives
- To promote an innovative, eco-sustainable and more environmentally friendly recycled plastic-based panel for the building industry, using as raw material scrap resulting from sorting plastic waste, coming from both solid urban and industrial/agricultural/commercial waste.
- To develop a sizeable European market for this new, eco-sustainable building product, initially focusing on the segments of elevated floors and ventilated facades.
KICK-OFF MEETING - Brindisi 21 July 2011
EcoPlasBrick
- Availability to building market of environmentally friendly recycled products able to compete with the traditional ones in terms of mechanical and aesthetical properties
EcoPlasBrick expected results
- A reduction in the unsorted plastic wastes destined to landfill and incineration and a corresponding increase in the volume sent to mechanical recycling
- Creation of partnerships among European industries
Raw material suppliers
Panel producers
Builders End users
Product chain
KICK-OFF MEETING - Brindisi 21 July 2011
EcoPlasBrick
Potential market
Given the ETS (EU Emissions Trading Scheme) proposal for a 20% abatement of CO2 emissions by 2020, growth opportunities for industries in the following areas will arise:- Use of renewable resources in construction and manufacturing - high market potential;-Resource saving and waste minimizing production processes, involving technologies for process measurement and control - very high market potential.
The production capacity of the new production line of MOTULAB will be 12,000 panels/year. However, the aim is to reach a production of 250.000 tons/year (by the involvement of other plastic panel producers not part of the project) at the end of the project, that represents approximately a 2% market share in EU27
EcoPlasBrick technical description
KICK-OFF MEETING - Brindisi 21 July 2011
EcoPlasBrick
EcoPlasBrick technical description
The innovative idea promoted by this project, is to use mixed plastic waste as the core of a sandwich panel with a gres face-
sheet (skins) on both sides.The panel will be obtained using the
compression moulding process tested during the preparatory research activities already
carried out. The process foresees only a rough grinding of non-washed plastic waste (2/3 cm sized against the 4/8 mm normally
requested by other processes).
Method for the manufacturing of ECOPLASBRICK Panel
KICK-OFF MEETING - Brindisi 21 July 2011
EcoPlasBrick
EcoPlasBrick technical description
Advantages introduced by EcoPlasBrick solution
Compared to its competitors, building products made of recycled plastic panels using the “ECOPLASBRICK” technology have several advantages:
- the core of the panels is made of mixed plastic waste, a zero cost raw material,
- the process does not foresee the presence of resins or glues, - easy to handle,- resistant and durable,- Recycled and recyclable
KICK-OFF MEETING - Brindisi 21 July 2011
EcoPlasBrick
Preparatory research
Technical description
KICK-OFF MEETING - Brindisi 21 July 2011
EcoPlasBrick
Agenda
• Welcome and introduction of partners
• Partners presentation
• Project objectives, results and technical description
• Coffee break
• Financial and Administrative Issues
• Work programme and role of each partner• Lunch
• Visit to laboratories
• Planning of first 6 Months Activities
• Meeting closure
KICK-OFF MEETING - Brindisi 21 July 2011
EcoPlasBrick
Financial & Administrative Issues
Budget:
Total eligible costs of the action are estimated at 1.832.066 €.
KICK-OFF MEETING - Brindisi 21 July 2011
EcoPlasBrick
Financial & Administrative Issues
Duration of the project:
• Starting date – 01/07/2011• Duration – 36 months
• Reporting periods: Month 1 – Month 10 – First technical progress report Month 1 – Month 20 – Interim technical implementation report and Interim financial statements Month 21 – Month 28 – Second technical progress report Month 1 – Month 36 – Final technical implementation report and Final financial statements + where required, Certificates on the financial statements
KICK-OFF MEETING - Brindisi 21 July 2011
EcoPlasBrick
Financial & Administrative Issues
Eligibility criteria:
• Costs must relate to the action and be necessary• Costs must be reasonable and justified• Costs must have been budgeted• Costs must be generated during the period of the action,
i.e. from contract start (exception of costs relating to final reports and audit certificates -> Max. + 2 months)
• Costs must abide by the relevant general accounting principles and participant’s internal rules + comply with sound financial management
• Costs must be identifiable and verifiable in particular being recorded in the accounting records of the beneficiary and determined according to the applicable accounting standards of the country where the beneficiary is established and according to the usual cost-accounting practices of the beneficiary
• Costs claimed during project must actually be incurred
KICK-OFF MEETING - Brindisi 21 July 2011
EcoPlasBrick
Ineligible costs (see grant agreement):
• Return on capital• Debt and debt service charges• Provisions for losses or potential future liabilities• Interest owed• Doubtful debts• Exchange losses• VAT, unless the beneficiary can show that he is unable to
recover it• Costs covered by another action receiving a Community
grant• Excessive or reckless expenditure
Financial & Administrative Issues
KICK-OFF MEETING - Brindisi 21 July 2011
EcoPlasBrick
• All costs should be budgeted in whole Euros• Round the figures, do not just hide the decimals
• All costs should be budgeted net of value added tax (VAT)
• The proposer may only budget gross amounts (incl. VAT) if he provides a certificate from his tax authority stating he can not recover VAT
Some formal principles in establishing the budget
will ease everybody's life
Financial & Administrative Issues
KICK-OFF MEETING - Brindisi 21 July 2011
EcoPlasBrick
Direct costs:
The eligible direct costs for the action are those costs which are identifiable as specific costs directly linked to performance of the action and which can therefore be booked to it direct.
In particular, the following direct costs are eligible:• Direct staff costs assigned to the action• Travel and subsistence allowances for staff taking part
in the action,• Subcontracting costs entailed by other contracts
awarded by the beneficiary for the purposes of carrying out the action
• The purchase cost of equipment (new or second-hand)• Other specific costs, these are costs arising directly
from requirements imposed by the agreement (dissemination of information, specific evaluation of the action, audits, translations, reproduction, etc.)
Financial & Administrative Issues
KICK-OFF MEETING - Brindisi 21 July 2011
EcoPlasBrick
Direct staff costs:
• Only technical and specialised staff may be declared• Costs for administrative support staff belong to the indirect
cost category• Identify each category of staff in a clear and unambiguous
mannerExamples of staff categories: project manager, expert, senior expert, junior expert, senior engineer, technician, etc
• The inclusion of freelance ‘staff’ (=inhouse consultants) depends on their contractual terms and conditions of work:
• They work in the premises of the beneficiary using its infrastructure
• They take directions from the beneficiary• The outcome of the work belongs to the beneficiary• Teleworking only if standard working conditions are
applicable to the teleworker
Financial & Administrative Issues
KICK-OFF MEETING - Brindisi 21 July 2011
EcoPlasBrick
Staff cost per hour:Only the cost of staff assigned to the action may be declared: comprising actual salaries plus social security charges and other statutory costs included in the remuneration.
Real costs = direct labour costsi.e. wages and salaries plus related obligatory social security charges and other statutory costs (numerator).
The denominator is the average number of productive hours :• Productive hours are the hours worked, whether for a
commercial or project purpose or for internal matters• The average number of productive hours observed is 147
hours per month, with a lower limit of 130 hours per month• The EACI will review rate calculations on this basis
The number of hours declared must reflect the work that has been done. The labour rate reflects the economic conditions prevailing forthe beneficiary.
Financial & Administrative Issues
KICK-OFF MEETING - Brindisi 21 July 2011
EcoPlasBrick
Travel & subsistence costs:
Only for staff taking part in the action (travel costs of subcontractors should be included in the subcontracts)
The travel costs should be based on the beneficiary’s usual practices and reflect the most economical options
Keep track of trips (e.g. keep flight boarding passes)
Check if the amount of trips is reasonable
Financial & Administrative Issues
KICK-OFF MEETING - Brindisi 21 July 2011
EcoPlasBrick
Subcontracting: Relates to purchase of services, not of goods!
Subcontracting may only cover the execution of a limited part of the action:
• Limited tasks outsourced by the beneficiary, and for hiring special expertise
• Does not include services ancillary to the main work, e.g. printing of documents, which should be declared under "Other specific costs"
• Subcontractors should be selected on transparent grounds, to the best offer, taking into consideration price and quality (best value for money)
• In a very simplified procedure, three different offers should be obtained and evaluated against common established criteria
• Beneficiaries can not subcontract services or sell equipment to one another or internally (e.g. between departments or affiliates)!
< 35% of total eligible costs, unless justified in Annex I A clear description of the service should be given with the name of
the provider
Financial & Administrative Issues
KICK-OFF MEETING - Brindisi 21 July 2011
EcoPlasBrick
Equipment:
The purchase cost of equipment (new or second-hand) must be written off in accordance with the tax and accounting rules applicable to the beneficiary and generally accepted for items of the same kind.
Only the portion of the equipment’s depreciation corresponding to the duration of the action and the rate of actual use for the purposes of the action may be taken into, except where the nature and/or the context of its use justifies different treatment.
Financial & Administrative Issues
KICK-OFF MEETING - Brindisi 21 July 2011
EcoPlasBrick
Other specific costs:
These are costs arising directly from requirements imposed by the agreement. Such costs include all the other direct costs that cannot be included under the previous cost categories for direct costs. Examples:
Costs of financial guarantees Costs of certificates on financial statements Printing of dissemination material, subscription fees to
conferences Specific evaluation of the action Travel costs for people who are neither members of staff nor
subcontractors (for instance experts) Translations, reproduction, etc. Specific costs incurred by the coordinator for fulfilling his
responsibilities in his capability of the body responsible for the overall management of the action and the co-ordination of the beneficiaries
!! Electricity & Gas are do not belong to “Other Specific Costs”. They are part of overhead.
Financial & Administrative Issues
KICK-OFF MEETING - Brindisi 21 July 2011
EcoPlasBrick
Indirect costs:
The eligible indirect costs for the action are those costs which are not identifiable as specific costs directly linked to performance of the action which can be booked to it direct, but which can be identified and justified by the beneficiaries using their accounting system as having been incurred in connection with the eligible direct costs for the action. They may not include any eligible direct costs.
Indirect costs are eligible for flat-rate funding fixed at 7% of the beneficiaries total eligible direct costs.
Indirect costs need not be supported by accounting documents.
Financial & Administrative Issues
KICK-OFF MEETING - Brindisi 21 July 2011
EcoPlasBrick
Non-eligible costs:
• Return on capital• Debt and debt service charges• Provisions for losses or potential future liabilities• Interest owed• Doubtful debts• Exchange losses• VAT, unless the beneficiary can show that he is unable to
recover it;• Costs declared by a beneficiary and covered by another
action or work programme receiving a Community grant• Excessive or reckless expenditure
Financial & Administrative Issues
KICK-OFF MEETING - Brindisi 21 July 2011
EcoPlasBrick
VAT issue:
As a general rule - all costs should be declared net of value added tax (VAT)
BUT! - The beneficiary may declare gross amounts (incl. VAT) if he/she provides a certificate from his tax authority stating he can not recover VAT
Financial & Administrative Issues
KICK-OFF MEETING - Brindisi 21 July 2011
EcoPlasBrick
Budget transfers:
A beneficiary may, when carrying out the action, adjust the estimated budget by transfers between items of eligible costs, provided that this adjustment of expenditure does not affect the implementation of the action and the transfer between items does not exceed 20% of the total costs of the action.
Beneficiaries may, when carrying out the action, transfer between themselves the estimated budget set out in Annex II, provided that thisadjustment of expenditure does not affect the implementation of the action and the transfer does not exceed 20% of the total eligible costs of the recipient beneficiary and the transfer does not exceed 50% of the total costs of the giving beneficiary.
Financial & Administrative Issues
KICK-OFF MEETING - Brindisi 21 July 2011
EcoPlasBrick
Funding rates:
The Agency will contribute a maximum of 916.033 € for the project.
Name Status % EC funding
CETMA Other 50
Consorzio TRE Other 50
Pandora Small 50
Motulab Small 50
Acciona Large 50
ACA Other 50
Financial & Administrative Issues
KICK-OFF MEETING - Brindisi 21 July 2011
EcoPlasBrickPayments:
First pre-financingThe first pre-financing is intended to provide the beneficiaries with a float.The Agency will transfer the First pre-financing to the coordinator within 45 calendar days from the date when the signed agreement and all the mandates are officially received.The first pre-financing is equal to 30% of the maximum EC funding specified in the agreement, i.e. 30% * 916.033 € = 274.809,90€
Second pre-financingThe coordinator may request a second pre-financing payment provided that 100% of the first pre-financing payment has been used up.The amount of the second pre-financing shall be paid to the coordinator upon approval by the Agency of the interim technical implementation report of the action and the interim financial statements.The aggregate amount of the pre-financing payments shall represent 60% of the maximum amount of the grant.
Payment of the balance (the final payment)• Payment of the balance, which may not be repeated, is made after the end of
the action on the basis of the costs actually incurred by the beneficiaries in carrying out the action, and deducting the amount of any pre-financing previously paid to the beneficiary.
• The payment of balance shall be effected on approval by the Agency of the final technical implementation report of the action and the final financial statements.
Financial & Administrative Issues
KICK-OFF MEETING - Brindisi 21 July 2011
EcoPlasBrick
Payments (2):
* Provided that 100% of the first pre-financing payment has been used up** Based on the eligible costs actually incurred, and considering the amount of
any pre-financing previously paid to the beneficiary
Financial & Administrative Issues
KICK-OFF MEETING - Brindisi 21 July 2011
EcoPlasBrick
Certificate on financial statements:
Each beneficiary for whom the amount of Community funding exceeds 150.000 € shall provide an external audit report on the action’s accounts at the time of the Final payment.
Financial & Administrative Issues
KICK-OFF MEETING - Brindisi 21 July 2011
EcoPlasBrick
Consortium Agreement
KICK-OFF MEETING - Brindisi 21 July 2011
EcoPlasBrick
Consortium Agreement
Structure:1. Definitions2. Purpose3. Entry into force, duration and termination4. Responsibilities of Parties5. Liability towards each other6. Governance structure7. Financial provisions8. Action results9. Access rights10. Non-disclosure of information11. Misellaneous12. Signatures13. Attachments
Financial & Administrative Issues
KICK-OFF MEETING - Brindisi 21 July 2011
EcoPlasBrick
Consortium Agreement
6.Governance structure
The Steering Committee is the decision-making body of the Consortium.The PSC consists of 6 members, i.e. one representative of each partner. Each representative in the PSC will be authorised to act on behalf of the partner who appointed him. The PSC will be chaired by the Project Co-ordinator.
The PSC will be established during the kick-off meeting.
It is in charge of monitoring and supervising the progress of the project according to the agreed workplan and in the respect of the contract obligations.
It is responsible for pointing out any evidence of mishandling or wrongdoing of the partners of the Consortium and requesting immediate remedial actions.
Financial & Administrative Issues
KICK-OFF MEETING - Brindisi 21 July 2011
EcoPlasBrick
Consortium Agreement
Structure:1. Definitions2. Purpose3. Entry into force, duration and termination4. Responsibilities of Parties5. Liability towards each other6. Governance structure7. Financial provisions8. Action results9. Access rights10. Non-disclosure of information11. Misellaneous12. Signatures13. Attachments
Financial & Administrative Issues
KICK-OFF MEETING - Brindisi 21 July 2011
EcoPlasBrick
Consortium Agreement
7. Financial provisions
1. Principles of financial contribution distributionThe Project will be co-financed by the Agency at the following funding rates:
Financial & Administrative Issues
KICK-OFF MEETING - Brindisi 21 July 2011
EcoPlasBrick
2. Funding principles
Each party will be funded in accordance with its actual duly justified eligible costs only.If a Party spends more than its allocated share of the Consortium Budget will be funded only in respect of duly justified eligible costs up to an amount not exceeding that share.
3. Payment schedule
Two separate instalments for pre-financingFirst pre-financingSecond pre-financing
The Final payment
Financial & Administrative Issues
KICK-OFF MEETING - Brindisi 21 July 2011
EcoPlasBrick Management
support to the CO• D’Appolonia S.p.A., based on its long experience in the coordination of EC-funded projects (including projects under programmes managed by the EACI), will support the Coordinator (CO) CETMA in its management role for all the project duration
• Activities of the Company will include administrative, contractual and financial assistance
• D’Appolonia will also provide support to CETMA concerning market analysis and road-mapping activities
KICK-OFF MEETING - Brindisi 21 July 2011
EcoPlasBrick
Management structure and procedures
KICK-OFF MEETING - Brindisi 21 July 2011
EcoPlasBrick
Management structureOrganisational structure and decision-making mechanisms
KICK-OFF MEETING - Brindisi 21 July 2011
EcoPlasBrick
General Structure
• The Steering Committee, SC, is the decision-making body of the Consortium
• The CO is the legal entity acting as the intermediary between the Parties (CBs) and the Agency. The Coordinator shall, in addition to its responsibilities as a Party, perform the tasks assigned to it as described in the EACI-GA and the CA
• The WP Leaders assist the SC and the CO throughout the different phases of the Project (technical implementation, market replication, dissemination)
KICK-OFF MEETING - Brindisi 21 July 2011
EcoPlasBrick
Members of the SC
• SC shall consist of one representativeMember of each Party
• Each Member shall be deemed to be duly authorised to deliberate, negotiate and decide on all matters listed in Article 6.3.6 of the CA
• The CO shall chair all meetings of the SC, unless decided otherwise by the panel itself
• The Parties agree to abide by all decisions of the SC
KICK-OFF MEETING - Brindisi 21 July 2011
EcoPlasBrick
Operational Procedures for the SC
In order to ensure democratic representation in meetings, any Member:
• should be present or represented at any meeting
• may appoint a substitute or a proxy to attend and vote at any meeting
• shall participate in a cooperative manner in the meetings
KICK-OFF MEETING - Brindisi 21 July 2011
EcoPlasBrick
SC Representatives Election
TitleRepresentative First
and Family name Partner NOTE
Dr/Mr/Ms CETMA (Co)
Dr/Mr/Ms Consorzio TRE
Dr/Mr/Ms Pandora
Dr/Mr/Ms Motulab
Dr/Mr/Ms Acciona
Dr/Mr/Ms ACA
KICK-OFF MEETING - Brindisi 21 July 2011
EcoPlasBrick
Voting Rules and Quorum
• The SC will not deliberate and decide validly unless three-fifths (3/5) of its Members are present or represented (quorum)
• Each Member has only one vote
• Defaulting Parties may not vote
• Decisions shall be taken by a majority of three-fifths (3/5) of the votes
KICK-OFF MEETING - Brindisi 21 July 2011
EcoPlasBrick
Project reports and documents
Practical procedures and deadlines
KICK-OFF MEETING - Brindisi 21 July 2011
EcoPlasBrick
Reporting requirements
• Using inputs from the co-beneficiaries (CBs) in the GA, the coordinator (CO) is required to put together each report as a single document in English language and to ensure that it is submitted to the EACI by the agreed deadline
KICK-OFF MEETING - Brindisi 21 July 2011
EcoPlasBrick
Overview of reporting to the EACI
• The CBs shall submit, through the CO, the following documents:– 1 project information sheet– 2 technical progress reports– 1 interim technical implementation report + 1 interim financial
statement– 1 final technical implementation report + 1 final financial statement
• Additionally, all partners have to provide to the realization of a dedicated project web site
KICK-OFF MEETING - Brindisi 21 July 2011
EcoPlasBrick
The Project web site
• Has to provide:– outline of the project– project activities progressions– important medium to
disseminate all electronic deliverables of the project
• Set up either as:– own website or – at the premises of the CO – or at one of the CBs’ Internet
site
• Reachable by private (all project partners) & public sections
• Must be:– easily accessible at the latest 6
months after the starting date, 01/01/2012
– available until at least 2 (two) years after the end of the project duration, July 2016 (Art. I.2.2 of the GA)
– updated according guidance, recommendations and other best practice guides provided on the CIP Eco-innovation website
– proactively promoted and carefully monitoring its use
KICK-OFF MEETING - Brindisi 21 July 2011
EcoPlasBrick
Technical Progress Reports
• Through the CO and in the format provided by the Agency, the Co-beneficiaries shall submit:– 1st technical progress report, covering M1-M10, within 31/05/2012
– an interim technical implementation report (and interim financial statements), covering M1-M20, within 31/03/2013
– 2nd technical progress report, covering M21-M28, within 30/11/2013
– a final technical implementation report (and final financial statements), within 60 days from end of project activities, 31/08/2014
KICK-OFF MEETING - Brindisi 21 July 2011
EcoPlasBrick
Other Project Templates
You can find Eco-Innovation logos and other templates for financial and contractual documents at:
http://ec.europa.eu/environment/eco-innovation/implementation_en.htm
http://ec.europa.eu/environment/eco- innovation/docs/call09/template_timesheet_financial.xls
http://ec.europa.eu/environment/eco-innovation/contract_en.htm
http://ec.europa.eu/environment/eco- innovation/docs/contract/mandate_model09.doc
http://ec.europa.eu/environment/eco-innovation/docs/impl/graphical_charter.pdf
KICK-OFF MEETING - Brindisi 21 July 2011
EcoPlasBrick Final Technical Implementation
Report
• Together with the final financial statements and a cover letter in which the coordinator requests the payment of the balance, these documents must be submitted by the CO in one consolidated package (Art I.5.3 and I.6.4 of GA)
• The final technical implementation report must: – follow the template (provided on the website)– integrate the contribution from each CBs– contain in an annex:
• the Layman’s report• the final version of the project information sheet• copies of the deliverables produced during the reporting period
KICK-OFF MEETING - Brindisi 21 July 2011
EcoPlasBrick
Confidentiality & Publicity
ARTICLE II.5 of the Grant Agreement
• The Agency and the beneficiaries undertake to preserve the confidentiality of any document, information or other material directly related to the subject of the agreement that is duly classed as confidential, if disclosure could cause prejudice to the other party. The parties shall remain bound by this obligation beyond the closing date of the action.
ARTICLE II.5 of the Grant Agreement
• II.5.1 Unless the Agency requests otherwise, any communication or publication by the beneficiaries collectively or any one of the beneficiaries individually about the action, including at a conference or seminar, shall indicate that the action has received funding from the Community.
• Any communication or publication by the beneficiaries collectively or any one of the beneficiaries individually, in any form and medium, shall indicate that sole responsibility lies with the author and that the Agency is not responsible for any use that may be made of the information contained therein.
KICK-OFF MEETING - Brindisi 21 July 2011
EcoPlasBrick
Practical remarks
KICK-OFF MEETING - Brindisi 21 July 2011
EcoPlasBrick Specific Document Format
Requests
• Documents must be submitted in English
• Indicate clearly the project number and acronym in the subject line: 277233 EcoPlasBrick
• Logo of Eco-Innovation – Pilot and market replication projects has to be included in all communication or publication by the CBs collectively or individually about the action, including conferences or seminars (Art. II.5.1 of the GC)
• All public documents will be published by the EACI on the programme website at, as previously indicated:
http://ec.europa.eu/environment/etap/ecoinnovation
KICK-OFF MEETING - Brindisi 21 July 2011
EcoPlasBrick
Thank you for your attention
Sara Parodi
+39 010 3628148
sara.parodi@dappolonia.it
KICK-OFF MEETING - Brindisi 21 July 2011
EcoPlasBrick
Agenda
• Welcome and introduction of partners
• Partners presentation
• Project objectives, results and technical description
• Coffee break
• Financial and Administrative Issues
• Work programme and role of each partner• Lunch
• Visit to laboratories
• Planning of first 6 Months Activities
• Meeting closure
KICK-OFF MEETING - Brindisi 21 July 2011
EcoPlasBrick
Work programme
WP nr. WP description WP leader
WP1 Management CETMA
WP2 Industrialization activities MOTULAB
WP3 Product design and validation ACCIONA
WP4 Environmental compatibility analysis TRE
WP5 Exploitation and Business Plan CETMA
WP6 Dissemination activities ACA
WP
1 M
anag
emen
t
WP
6 D
isse
min
atio
n ac
tiviti
es
WP5 Exploitation and business plan
WP4 Environmental compatibility analysis
WP2 Industrialization activities
WP3 Product design and validation
WP
1 M
anag
emen
t
WP
6 D
isse
min
atio
n ac
tiviti
es
WP5 Exploitation and business plan
WP4 Environmental compatibility analysis
WP2 Industrialization activities
WP3 Product design and validation
KICK-OFF MEETING - Brindisi 21 July 2011
EcoPlasBrick
Work programme
Hours distribution
CETMA TRE Pandora MOTULAB ACCIONA ACA Tot.
WP1 Management 1500 120 120 120 120 120 2100
WP2 Industrialization activities
2500 800 580 4700 8580
WP3 Product design and validation
320 2200 580 1340 3320 7760
WP4 Environmental compatibility analysis
200 2890 100 3190
WP5 Exploitation and Business Plan
2800 120 200 120 120 120 3480
WP6 Dissemination activities 700 120 120 120 240 2010 3310
8020 6250 1600 6500 3800 2250 28420
KICK-OFF MEETING - Brindisi 21 July 2011
EcoPlasBrick
Work programme: schedule
Project phase / Duration of the project (in months)
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 60
WP1: Management
WP2: Industrialization activities
WP3: Product design and validation
WP4: Environmental compatibility analysis
WP5: Exploitation and Business Plan
WP6: Dissemination Activities
Project meetings
x x x x x x x
Project reports to EACI
PR1 IR PR2 LR FR
Project Information Sheet to EACI
X X X X X
Project Webpage/site creation and update
X
Project deliverables
1.1 5.2.1 1.2 2.1 5.1 6.6
1.4 6.1
1.2 1.3 2.2 2.3 4.1
5.2.2
1.2 1.7 3.1 3.3
4.2.1 5.3
1.5 6.1
1.2 1.3 2.4 3.2
4.2.2 5.3
1.4 6.1
1.2 3.2.1 3.4.2 4.3 5.4 6.1 6.4
1.2 1.3 1.6 3.5 4.4
5.2.2 5.3 5.4 6.1 6.9
6.5
KICK-OFF MEETING - Brindisi 21 July 2011
EcoPlasBrick
WP 1: Management
WP leader: CETMA
Duration: 1 to 36 months
Aims:
- timely and cost-efficient implementation of proposed activities
- attainment of expected results and fulfillment of project objectives
- communication of project progress to the EC.
CETMATRE
PANDORA
MOTULAB
ACCIONA
ACA
KICK-OFF MEETING - Brindisi 21 July 2011
EcoPlasBrick
WP 1: Management
WP leader: CETMADuration: 1 to 36 months
Tasks:
1.1 – Inception phase
1.2 – Project meetings
1.3 – Indicators monitoring
Team responsible for implementation and internal management of the project. The Team responsible will be the reference person for the communications with the coordinator and/or the other project partners.
Project Steering Committee SC functions:• to supervise the progress of the project,• to verify that the objectives and expected results are being met,• to control whether the project is implemented timely and cost-
efficiently,• to highlight the problems and indicate what remedial actions
need to be put in place.
KICK-OFF MEETING - Brindisi 21 July 2011
EcoPlasBrick
WP 1: Management
Partner Team responsible / Steering Committee e-mail
CETMA Alessandro Marseglia alessandro.marseglia@cetma.it
TRE Carmine Pascale
PANDORA Alessia Guarnaccia
MOTULAB
ACCIONA
ACA
Team responsible – Steering committee establishment:
…within 22 July
KICK-OFF MEETING - Brindisi 21 July 2011
EcoPlasBrick
Role and contribution (tasks) of each partner
WP 1: Management
Participant no. and short name
Contributions of this participant Hours foreseen
1. CETMA 1.1: Overall project management and co-ordination 1.2: Organisation and management of kick-off meeting, 6-monthly Team meetings and annual SC meetings1.3: Progress monitoring
1.500
2. TRE3. PANDORA4. MOTULAB5. ACCIONA6. ACA
1.1: Participation in kick-off meeting1.2: Participation in all other project meetings
120 hours for each partner, total 600 hours
Total staff costs in €: 93.566
KICK-OFF MEETING - Brindisi 21 July 2011
EcoPlasBrick
Deliverables
WP 1: Management
Deliverable N°
DELIVERABLE NAME Responsible Month of completion
D1.1 Kick-off minutes CETMA 1
D1.2 Project meeting minutes CETMA 6, 12, 18, 24, 30,36
D1.3 Steering committee minutes CETMA 12, 24, 36
D1.4 Progress Report (including performance indicators)
CETMA 10, 28
D1.5 Interim Report – Technical and financial (including performance indicators)
CETMA 20
D1.6 Final Report (including performance indicators)
CETMA 36
KICK-OFF MEETING - Brindisi 21 July 2011
EcoPlasBrick
WP 2: Industrialization activities
WP leader: MOTULAB
Duration: 1 to 24 months
Aim: The industrial partner MOTULAB will become able to produce the innovative recycled plastic panel. MOTULAB will purchase the complete industrial line for panel manufacturing.
KICK-OFF MEETING - Brindisi 21 July 2011
EcoPlasBrick
TASKS
2.1 Requirements definition Analysis of current regulations and technical standards requirements, properties of interest for the market and identification of characterisation tests for the different possible applications:
2.2: Identification of most suitable face-sheets and optimization of panel properties ... the most suitable types of face-sheets, or skins (i.e.: commercial gres, aluminium, wood sheets) will be identified, aiming at the maximization of bonding resistance between the skins and the plastic core.
2.3: Purchase, installation, and start-up of a new industrial lineThe line, complete with the new foreseen equipment, will be purchased, installed and started-up by MOTULAB, to begin producing recycled plastic panels
2.4 Scaling up of the manufacturing process ..in order to optimize process parameters, minimise costs , minimise the environmental impact of the process
WP 2: Industrialization activities
KICK-OFF MEETING - Brindisi 21 July 2011
EcoPlasBrick
WP 2: Industrialization activities
2.1 – 2.4 CETMA
2.2 TRE
2.3 MOTULAB
2.3 PANDORA
2.4 MOTULAB
Face sheets suppliers, datasheets
Acquisition of face sheets, characterization tests
Supplier identification ,
testing, purchase
Installation, start up
Production of samples
Characterisation test on panel obtained with
different process parameters (CETMA)
Analysis of the productivity and plastic panel properties (MOTULAB/CETMA)
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24
2.1 Requirements definition
2.2Identification of most suitable face sheets and optimisation of panel properties
2.3Purchase, installation, and start-up of a new industrial line
2.4 Scaling up
Project phase / Months
KICK-OFF MEETING - Brindisi 21 July 2011
EcoPlasBrick
Role and contribution (tasks) of each partner
WP 2: Industrialization activities
Role and contribution of each participant in this work package:
Participant no. and short name
Contributions of this participant Hours foreseen
1. CETMA 2.1 Requirements definition
CETMA will carry out this task, including the analysis of the current regulations and technical standards requirements and of the properties of interest for the market at European level. The necessary characterisation tests will also be identified.
2.4 Characterization tests on the recycled plastic panel obtained with different process conditions
2,500
2. TRE 2.2 Identification of the most suitable face-sheets (skins) and optimization of panel properties
800
3. PANDORA 2.3 Technical support to MOTULAB for the technical specifications of the new industrial line
580
4. MOTULAB 2.3 Purchase, installation, testing and start-up of a new industrial moulding line
2.4 Scaling-up of the manufacturing process
4,700
Total staff cost in € 344,390
KICK-OFF MEETING - Brindisi 21 July 2011
EcoPlasBrick
Deliverables
WP 2: Industrialization activities
Delive rable N°
Deliverable name (self-explanatory)
Type of deliverable
Quantifi cation
Locations/ Language(s)
Accessibility of delive rable
Month of comple tion
D2.1 Requirements definition N° 1 Technical report
Max 20 pages
English PU 6
D2.2 Identification of most suitable types of face sheets (skins) and optimization of panel properties
N° 1 Technical report
Max. 40 pages
English CO 12
D2.3 Purchase, installation, and start-up of a new industrial line
Industrial production line
1 MOTULAB PU 12
D2.4 Scaling-up of the manufacturing process
N° 1 Technical report
Max. 30 pages
English CO 24
KICK-OFF MEETING - Brindisi 21 July 2011
EcoPlasBrick
Innovative recycled plastic based panels for building field
WP3: PRODUCT DESIGN AND VALIDATIONWP3: PRODUCT DESIGN AND VALIDATION
ACA
KICK-OFF MEETING - Brindisi 21 July 2011
EcoPlasBrick
WP3: Product design and validation
Work Package DescriptionWork Package Description
1. Vertical solutions (ventilated façades, self-standing walls)
The main objective of the WP3 is the design of different solutions and applications of the panels as environmentally friendly construction components.
ACTIVITIES
2. Horizontal solutions (raised floors)
KICK-OFF MEETING - Brindisi 21 July 2011
EcoPlasBrick
• TASKS
3.1. Design of vertical solutions
3.2. Validation of vertical solutions
WP3: Product design and validation
Work package no: 3 Start date: MONTH 12 End date: MONTH 36
Work package title PRODUCT DESIGN AND VALIDATION
Partner Number 1 2 3 4 5 6
Partner Shortname CETMA TRE PANDORA MOTULAB ACCIONA ACA
Task ParticipationTechnicalsupport
3.13.2
3.13.3
3.23.4
3.33.43.5
Work Package DescriptionWork Package Description
TRE
ACCIONA
3.3. Design of horizontal solutions
3.4. Validation of horizontal solutions
3.5. Technical-commercial schedules
KICK-OFF MEETING - Brindisi 21 July 2011
EcoPlasBrick
WP3: Product design and validation
• Task 3.1 “Design of vertical solutions” • Task 3.3 “Design of horizontal solutions”
Tasks DescriptionTasks Description
Defining the optimal size of the panels for different applications
Optimization of panel properties
T 2.2 Product DesignT 3.1, T 3.3
Production of panelsT 3.2, T 3.4
Validation T 3.2, T 3.4
TREACCIONA
WP2 WP3
(TRE)
TREACCIONA
MOTULAB
KICK-OFF MEETING - Brindisi 21 July 2011
EcoPlasBrick
Tasks DescriptionTasks Description
WP3: Product design and validation
• Task 3.2 “Validation of vertical solutions” • Task 3.4 “Validation of horizontal solutions”
Testing the mechanical and thermal/fire properties of full scale elements
Mechanical PropertiesThermal and Fire properties
ValidationT 3.2, T 3.4
Manufacture and Test of full scale Elements
for different solutionsTREACCIONA
WP3 WP6
DisseminationActivities
(ACA)
KICK-OFF MEETING - Brindisi 21 July 2011
EcoPlasBrick
WP3: Product design and validation
Tasks DescriptionTasks Description
• Task 3.5 “Technical-commercial schedules”
Description of applications, technical data, environmental and economic aspects, etc.
Test resultsT 3.2, T 3.4
Technical-commercialSchedules
T 3.5
ACCIONA
WP3
(TRE, ACCIONA)
EnvironmentalCompatibility
analysis
WP4
(CETMA, TRE, MOTULAB)
KICK-OFF MEETING - Brindisi 21 July 2011
EcoPlasBrick
• Steps:
1.DesignDesign of the panels: optimal dimensions for different applications.
2.ProductionProduction of the panels.
3.ManufactureManufacture of full scale elements.
4.ValidationValidation: testing the mechanical and thermal/fire properties,
depending on the application.
5.EvaluationEvaluation of the results. Analysis of the advantages and
disadvantages of the different designs to select the best option for
each application.
6.DescriptionDescription of technical-commercial schedules for each product.
WP3: Product design and validation
MethodologyMethodology
KICK-OFF MEETING - Brindisi 21 July 2011
EcoPlasBrick
WP3 Product design and validation
TASK
2011 2012 2013 2014
III IV I II III IV I II III IV I II
TASK 3.1 D 3.1
TASK 3.2 D
3.2.1D
3.2.2
TASK 3.3 D 3.3
TASK 3.4 D
3.4.1 D
3.4.2
TASK 3.5 D 3.5
PlanningPlanning
DELIVERABLE DELIVERABLE NAMEDELIVERY
DATEPARTNERS INVOLVED
D 3.1 Design of vertical solutions Month 18 TRE
D 3.2.1D 3.2.2
Validation of vertical solutionsFull scale example of vertical solution for demonstration purposes
Month 30Month 36 TRE
D 3.3 Design of horizontal solutions Month 18 ACCIONA
D 3.4.1D 3.4.2
Validation of horizontal solutionsFull scale example of horizontal solution for demonstration purposes
Month 30Month 36 ACCIONA
D 3.5 Technical-commercial schedules Month 36 ACCIONA
KICK-OFF MEETING - Brindisi 21 July 2011
EcoPlasBrick
Work Package 4
Environmental compatibility analysis
The environmental compatibility analysis, based on an LCA analysis, will aim at assessing the entire product/process.
Overall objective of the work package is to evaluate the applicability for the Eco-label and/or for an Environmental Product Declaration (EPD).
Activities will begin from an up-to-date analysis of the current Product Groups and related Criteria for the award of the Eco-label and of Product Categories and related Product Category Rules (PCR) for EPD.
The LCA analysis will then be conducted keeping in mind both the product group criteria and the PCR, for the definition of the goals and scope and for the impact assessment and interpretation of the analysis’s results. The last step will be the production of technical documents needed to support the application for the ECO-label certification and/or for the Environmental Product Declaration (EPD), sub-contractors (to be identified) will be hired to support the WP leader in these tasks.
Duration: month 1 to month 36
Partners involved: TRE (WP leader), CETMA, MOTULAB
Work Package 4 Environmental compatibility analysis
KICK-OFF MEETING - Brindisi 21 July 2011
EcoPlasBrick
Work Package 4 Environmental compatibility analysis
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36
WP1: Management
WP2: Industrialization activities
WP3: Product design and validation
WP4: Environmental compatibility analysis
4.1
4.2
4.3
4.4
WP5: Exploitation and Business Plan
WP6: Dissemination Activities
KICK-OFF MEETING - Brindisi 21 July 2011
EcoPlasBrick
Work Package 4 Environmental compatibility analysis
4.1 Requirements analysis for Eco-Label and
Environmental Product Declaration (Type I and III).
Analysis of the existing Product Categories and related Product Category Rules (PCR) for Environmental Product Declaration and of Product Groups and related Criteria for the award of the ECO-label certification. The aim is to support and address the definition of the goals and scope for LCA-Analysis.
Duration: month 1 to month 12
Partners involved: TRE
Subcontractor: TBD (TRE)
Deliverable: D4.1 Requirements for Environmental Product Declaration (report)
KICK-OFF MEETING - Brindisi 21 July 2011
EcoPlasBrick
Work Package 4: Environmental compatibility analysis
4.2 LCA
Phase I: Definition of the Goal and Scope for the case and Data Inventory.
These activities will be conducted on the basis of the results of task 4.1 and according to ISO standards, in particular: ISO 14041 Environmental management. Life-cycle assessment. Goal and scope definition and inventory analysis
Phase II: Impact assessment
Impact will be assessed through the evaluation of the selected indicators and according to ISO standards, in particular: ISO 14042 Environmental management. Life-cycle assessment. Life-cycle impact assessment
Duration: month 12 to month 24
Partners involved: TRE, MOTULAB (Support the data collection for the LCA inventory)
Deliverables: D4.2.1 LCA phase I: Definition of goal and scope, Data inventory
D4.2.2 LCA phase II: Impact assessment
(reports)
KICK-OFF MEETING - Brindisi 21 July 2011
EcoPlasBrick
Work Package 4 Environmental compatibility analysis
4.3 LCA - phase III: Interpretation
The interpretation of the results will be conducted according to ISO standards, in particular:
ISO 14043 Environmental management. Life-cycle assessment. Life-cycle Interpretation
Duration: month 18 to month 30
Partners involved: TRE
Deliverable: D4.3 LCA phase III: Interpretation of results (report)
KICK-OFF MEETING - Brindisi 21 July 2011
EcoPlasBrick
Work Package 4 Environmental compatibility analysis
4.4 Environmental Product Declaration Documentation
The aim of this task is to produce the requested technical documentation to support the application for the award of the Eco-label and/or for the production of Environmental Product Declaration. Such documentation will be in accordance with the results of the previous tasks, and based on the existing Product Categories for the EPD and Product Groups for Eco-label.
The results of the present task will be the:Product related information;Environmental performance related information;Additional environmental information.
The activities will be carried out complying to the ISO standards, in particular:- ISO 14024 Type I environmental labelling – Principles and procedures for the Eco-label ;- ISO 14025 Environmental labels and declarations – Type III - ISO 21930 Sustainability in building construction - Environmental declaration of
building products for the Environmental Product Declaration .
In case the proposed solution should not fit the existing Product Categories for the Environmental Product Declaration (Type III) or the Product Groups for Eco-label (Type I), activities will focus on the production of a Type II Environmental Label according to the standard:
ISO 14021 Environmental labels and declarations – Self-declared environmental claims (Type
II environmental labelling).
KICK-OFF MEETING - Brindisi 21 July 2011
EcoPlasBrick
Work Package 4 Environmental compatibility analysis
4.4 Environmental Product Declaration Documentation
Duration: month 24 to month 36
Partners involved: TRE
Subcontractor: TBD (TRE)
Deliverable: D4.4 Technical documentation for Environmental Product Declaration (report eng/ita )
KICK-OFF MEETING - Brindisi 21 July 2011
EcoPlasBrick
WP 5: Exploitation and business plan
WP leader: CETMA
Duration: 1 to 36 months
5.1 Market
analysis and roadmapping
5.2 Exploitation
plan
5.3 Business
plan
Market uptake of
EPB panels at European
level
Possibility for the partners to enter the market and generate revenue during
the project!!
KICK-OFF MEETING - Brindisi 21 July 2011
EcoPlasBrick
Revenue possibilities
EPB partner
product
Motulab panels
Acciona •ventilated façades•elevated floors
Pandora patent
time
EP
B p
rod
ucts
m
ark
et
market replication
through new
stakeholders
involvement
ACACETMATRE
EBP project
WP 5: Exploitation and business plan
KICK-OFF MEETING - Brindisi 21 July 2011
EcoPlasBrick
Revenue possibilities
WP 5: Exploitation and business plan
Motulab:total budget: 647 k€EC contribution: 324 k€max income from selling ECB panels before the end of the project: 324k€
Acciona:total budget: 188 k€EC contribution: 94 k€max income from selling ECB final product before the end of the project: 94k€
Pandora:total budget: 99 k€EC contribution: 50 k€max income from selling the ECB patent before the end of the project: 50 k€
time
EP
B p
rod
ucts
m
ark
et
EBP project
KICK-OFF MEETING - Brindisi 21 July 2011
EcoPlasBrick
• Assess the European construction market for the introduction of EcoPlasBrick products (ventilated facades and elevated floors markets)
• Conduct a Lead Market Analysis to identify a shortlist of countries with favorable market conditions for the uptake of EPB products
• Develop a road-map for the market uptake of EPB products within Europe thanks to the identification of potential end-users
CETMA will be supported by DAPP
WP 5: Exploitation and business plan
5.1 Market analysis and roadmapping
KICK-OFF MEETING - Brindisi 21 July 2011
EcoPlasBrick
WP 5: Exploitation and business plan
5.2 Exploitation plan
•Strategy for an appropriate management of the knowledge generated in the project and IPR (Consortium Agreement)
•European extension of the patent “Procedure for making an eco-sustainable building component”
•Strategy for maximising the exploitation potential of the project results, evaluating exploitation routes, target groups and markets, competitors, exploring marketing options
•Strategy for mobilising a wide market uptake, reaching a critical mass during and after the project
•Pre-series manufacture to be used to show the innovative solution to potential customers
KICK-OFF MEETING - Brindisi 21 July 2011
EcoPlasBrick
WP 5: Exploitation and business plan
•Identification of the economic and environmental benefits of the promoted products
•The definition of products’ key features, to make these more appealing for potential customers
•Market barriers
•A detailed description of the potential customers
•Economic and financial projections
5.3 Business plan
KICK-OFF MEETING - Brindisi 21 July 2011
EcoPlasBrick
Schedule
Deliverable N°
Deliverable name (self-explanatory) Responsible Month of completion
D5.1 Market Analysis and road-mapping CETMA 6
D5.2.1 Consortium Agreement CETMA 3
D5.2.2 Exploitation Plan CETMA 12, 36
D5.3 Business plan CETMA 24, 36
WP 5: Exploitation and business plan
2011 2012 2013 2014
1-3 4-6 7-910-12
13-15
16-18 19-21 22-24 25-2728-30
31-33 34-36
5.1Market Analysis and road-mapping
5.2.1 Consortium Agreement
5.2.2 Exploitation Plan
5.3 Business plan
Deliverables
KICK-OFF MEETING - Brindisi 21 July 2011
EcoPlasBrick
Role and contribution (tasks) of each partner
Participant no. and short name
Contributions of this participant Hours foreseen
1. CETMA 5.1: Market Analysis and road-mapping5.2: Exploitation Plan5.3: Business Plan
2,800
2. TRE4. MOTULAB5. ACCIONA6. ACA
5.2: Support CETMA in developing the Exploitation Plan 120 hours for each partner, total 480 hours
3. PANDORA 5.2: Support CETMA in developing the Exploitation Plan; European extension of the patent “Procedure for making an eco-sustainable building component”
200
Total staff costs in €: 152,825
WP 5: Exploitation and business plan
KICK-OFF MEETING - Brindisi 21 July 2011
EcoPlasBrick
WP 6: Dissemination activities
WP leader: ACA
Duration: 1 to 36 months
Work Package 6
The work package covers resources to contribute, upon request by the EACI, to common dissemination activities and a final evaluation with the aim to increase synergies between projects supported by the eco-innovation initiative and to increase their visibility. In addition, this work package includes project specific dissemination activities.
KICK-OFF MEETING - Brindisi 21 July 2011
EcoPlasBrick
Work Package 6
TASKS
Pre-defined tasks–Project Information Sheets: Creation and regular update of project information for
EACI/DG ENV online information systems (adapted to your reporting schedule).
–Contribution, upon request by the EACI, to the development of additional information material (News Flash, videos, images etc.) in the quality and form specified by the EACI.
–Upon request, participation and/or contribution, to information and dissemination events (contractors’ workshops, conferences, briefing days, exhibitions, etc.) related to eco-innovation or other relevant EU programmes.
–Producing a layman's report before the end of the project that summarises the project objectives, actions and tangible results and is intended for the general public (5-10 pages long, in English and, optionally, in the main project languages).
–Evaluation of project impacts after the project duration: completing a questionnaire on economic and environmental impacts two years after the project has finished.
KICK-OFF MEETING - Brindisi 21 July 2011
EcoPlasBrick
Work Package 6
TASKS
Project-specific tasks:
• 6.6: Setting up of project web portal.
• 6.7: Presentation of project’s results at workshops and conferences
• 6.8 demonstration of EPB products
• 6.9: Promotion of contacts in view of the establishment of business
partnerships.
KICK-OFF MEETING - Brindisi 21 July 2011
EcoPlasBrick
Work Package 6
Deli vera ble N°
Deliverable name (self-explanatory)
Type of deliverable
Quantifi cation
Locations/ Language(s)
Accessibility of delive rable
Month of com pletion
D6.1 Project information updates
text, ppt 5 times EN PU (together with reports)
D6.2 Inputs to additional common information material related to eco-innovation actions
input to posters, articles for newsletters, visuals, interviews
on request by EACI
EN(or local, as appropriate
PU upon request
D6.3 Project presentations ppt presentation, participation in events
max 2 times EN(or local, as appropriate)
PU upon request
D6.4 Layman's report Brochure 5-10 pages EN (optional: others)
PU 30
D6.5 Evaluation report Report max. 5 pages
EN to be agreed
2 years after project
DELIVERABLES
KICK-OFF MEETING - Brindisi 21 July 2011
EcoPlasBrick
Work Package 6DELIVERABLES
D6.6 Project web portal
Web portal Non quantifiable
English PU 6
D6.7 Presentation of project’s results at workshops and conferences
Technical description and PowerPoint presentation
Max. 20 pages
English PU To be defined
D6.8 Demonstration of the ECOPLASBRICK products
Presentation of project’s results at specialised trade fairs and exhibitions
At least 1 PU To be defined
D6.9 Promotion of contacts
text Non quantifiable
English, national
To be agreed
36
KICK-OFF MEETING - Brindisi 21 July 2011
EcoPlasBrick
Work Package 6Role and contribution (tasks) of
each partner Participant no. and short name Contributions of this participant Hours foreseen
1. CETMA All pre-defined dissemination activities 6.1, 6.2, 6.3, 6.4, 6.56.6: Project web portal set-up6.7: Project’s results presentation at workshops and conferences6.8: Participation in specialised trade fairs and exhibitions6.9: Support in making contacts
700
2. TRE Contribution for writing reports (6.1, 6.2, 6.3, 6.4, 6.5)6.7: Project’s results presentation at workshops and conferences6.8: Participation in specialised trade fairs and exhibitions6.9: Support in making contacts
120
3. PANDORA Contribution for writing reports (6.1, 6.2, 6.3, 6.4, 6.5)6.7: Project’s results presentation at workshops and conferences6.8: Participation in specialised trade fairs and exhibitions6.9: Support in making contacts
120
4. MOTULAB Contribution for writing reports (6.1, 6.2, 6.3, 6.4, 6.5)6.7: Project’s results presentation at workshops and conferences6.8: Participation in specialised trade fairs and exhibitions6.9: Support in making contacts
120
6. ACCIONA Contribution for writing reports (6.1, 6.2, 6.3, 6.4, 6.5)6.7: Project’s results presentation at workshops and conferences 6.8: Participation in specialised trade fairs and exhibitions6.9: Support in making contacts particularly in Spain
240
7. ACA Periodical reporting on WP progress to the Coordinator.6.7: Project’s results presentation at workshops and conferences 6.8: Participation in specialised trade fairs and exhibitions6.9: Promotion of contacts in view of the establishment of business partnerships focusing initially on Albania, Balkans and Central&Eastern European CountriesContribution for writing reports (6.1, 6.2, 6.3, 6.4, 6.5)
2,010
Total staff cost in €: 98,620
KICK-OFF MEETING - Brindisi 21 July 2011
EcoPlasBrick
• The Albanian Constructors Association will reflect its dissemination activities with:
WorkshopsConferences, mainly technical Brochures, Fairs
Work Package 6
KICK-OFF MEETING - Brindisi 21 July 2011
EcoPlasBrick
In its annual working plan ACA foresee the arrangement possibility of workshops regarding technical achievements:
• ACA’s branches
• ACA’s collaborative association in:• Kosovo
• Macedonia, etc
• Technical workshops organized in Albania
Work Package 6
KICK-OFF MEETING - Brindisi 21 July 2011
EcoPlasBrick
• ACA organizes technical conferences that can be seen as a focal point in the dissemination activity.
• ACA participates in technical conferences in Albania and abroad
These participation can be seen as a good reference for the dissemination activities planned.
Work Package 6
KICK-OFF MEETING - Brindisi 21 July 2011
EcoPlasBrick
• Brochures publishing takes a considerable part of ACA’s budget
• Technical brochures
• Informative brochures
• Thematically brochures
Work Package 6
KICK-OFF MEETING - Brindisi 21 July 2011
EcoPlasBrick
• ACA participate twice a year in fairs
Spring fair an international fair
Autumn fair an international fair also
Work Package 6
KICK-OFF MEETING - Brindisi 21 July 2011
EcoPlasBrick
• Welcome and introduction of partners
• Implementing your project, content and requirements
• Partners presentation
• Coffee break
• Project objectives, results and technical description
• Financial and Administrative Issues
• Work programme and role of each partner
• Lunch
• Visit to CETMA laboratories
• Planning of first 6 Months Activities
• Meeting closure
Agenda
KICK-OFF MEETING - Brindisi 21 July 2011
EcoPlasBrick
• Welcome and introduction of partners
• Implementing your project, content and requirements
• Partners presentation
• Coffee break
• Project objectives, results and technical description
• Financial and Administrative Issues
• Work programme and role of each partner
• Lunch
• Visit to CETMA laboratories
• Planning of first 6 Months Activities
• Meeting closure
Agenda
KICK-OFF MEETING - Brindisi 21 July 2011
EcoPlasBrick
Planning of first 6 Months Activities
First six months schedule
1 2 3 4 5 6CETMA
2.1 Requirements definition CETMA2.2 Identification of most suitable faces sheets and optimisation of panel TRE2.3 Purchase, installation, and start-up of a new “intrusion” line Motulab/Pandora
WP4 Environmental compatibility analysis4.1 Requirements analysis for Eco-label and EPD declaration TRE
5.1 Market Analysis and road-mapping CETMA5.2.1 Consortium agreement CETMA+all
6.6 Setting up of project web portal. CETMA6.7 Presentation of project’s results at workshops and conferences ACA+all6.8 Promotion of contacts ACA+all
Project meetings x xProject reports to EACI
Project Information Sheet to EACI xProject Webpage/site creation and update X
Project deliverables 2.16.6
Project phase / Duration of the project (in months)WP1: ManagementWP2: Industrialization activities
WP5: Exploitation and Business Plan
WP6: Dissemination Activities
1.15.2.
1
KICK-OFF MEETING - Brindisi 21 July 2011
EcoPlasBrick
Planning of first 6 Months Activities
WP2: Industrialization activities
WP leader: Motulab
Task Responsible ResultsDelivery month
2.1 Requirements definition CETMA Deliverable 2.1 6
2.2Identification of most suitable
face sheets TRE
Face sheets suppliers, datasheets
6
2.3Purchase, installation, and
start-up of a new industrial line MOTULAB
Supplier identification, testing, purchase
6
KICK-OFF MEETING - Brindisi 21 July 2011
EcoPlasBrick
Planning of first 6 Months Activities
Recapitulation: first 6 month activities for each partners
Task Result Deadline
1.1 Inception phase kick off minute 30 July 2011
5.2.1 Exploitation Plan Consortium Agreement 30 September 2010
2.1 Requirement definition Deliverable 2.1 30 December 2011
5.1 Market analysis and road-mapping
Deliverable 5.1 30 December 2011
6.1 Project information updates
Deliverable 6.1 30 July 2011
6.6 Setting of the project web portal
Web portal 30 December 2011
CETMA
KICK-OFF MEETING - Brindisi 21 July 2011
EcoPlasBrick
Planning of first 6 Months Activities
Recapitulation: first 6 month activities for each partners
Task/sub-task Result Deadline
2.2 Identification of most suitable faces sheets
First results on suppliers, datasheets
30 December 2011
4.1 Requirement analysis for Eco label and EPD
First analysis results 30 December 2011
6.7 Project’s result presentation
6.8 Support in making contact
TRE
KICK-OFF MEETING - Brindisi 21 July 2011
EcoPlasBrick
Planning of first 6 Months Activities
Recapitulation: first 6 month activities for each partners
PANDORA
Task/sub-task Result Deadline
2.3 Purchase, installation and start up of the new
industrial line
Support to Motulab for the technical specification of
the new industrial line
30 December
2011
6.7 Project’s result presentation
6.8 Support in making contact
Project Logo within the end of October
KICK-OFF MEETING - Brindisi 21 July 2011
EcoPlasBrick
Planning of first 6 Months Activities
Recapitulation: first 6 month activities for each partnersMotulab
Task/sub-task Result Deadline
2.3 Purchase, installation, and start-up of a new
industrial line
Supplier identification, testing and purchasing
purchasing within the
end of September
2011 – installation and start up
within December
2011
6.7 Project’s result presentation
6.8 Support in making contact
Remember : The Eu co-funding will be proportional to the period of months used for the action!!!
KICK-OFF MEETING - Brindisi 21 July 2011
EcoPlasBrick
Planning of first 6 Months Activities
Recapitulation: first 6 month activities for each partners
Acciona
Task/sub-task Result Deadline
6.7 Project’s result presentation
6.8 Support in making contact
KICK-OFF MEETING - Brindisi 21 July 2011
EcoPlasBrick
Recapitulation: first 6 month activities for each partners
ACA
Task/sub-task Result Deadline
6.7 Project’s result presentation
First results
6.8 Promotion of contacts in view of the establishment of business partnerships
First results
Planning of first 6 Months Activities
KICK-OFF MEETING - Brindisi 21 July 2011
EcoPlasBrick
MUSTS
! Keep the track of all the activities you carry on within the project (photos, reports, …)
! Use all the opportunities you have to show the solution promoted by the project (conferences, fairs, contacts with other industries, …)
! Respect the deadlines
! Keep the coordinator informed about any kind of unexpected event you would face with
KICK-OFF MEETING - Brindisi 21 July 2011
EcoPlasBrick
Doubts
KICK-OFF MEETING - Brindisi 21 July 2011
EcoPlasBrick
When…
Where…
TRE Naples
31 January 2012
6 MONTH MEETING
KICK-OFF MEETING - Brindisi 21 July 2011
EcoPlasBrick
Meeting closure
Thank you for your attention and cooperation
See you at the next meeting…