KC WATERFISCAL YEAR 2017 CAPITAL IMPROVEMENT PROGRAM
PAGE 1
TABLE OF CONTENTSKC Water Assets.........................Page 2
Project Manager Directory.......Page 3
Water ...........................................Page 4
Wastewater ...............................Page 14
Stormwater .........................Page 22
Mission StatementKC Water is committed to providing excellent water, wastewater, and stormwater services that ensure the health and safety of our customers while safeguarding our regional water resources for future generations.
Design Professional Services .......... Page 5
Construction .................................... Page 9
Design Professional Services ........ Page 15
Design Build ................................... Page 18
Construction .................................. Page 19
Construction .................................. Page 23
PAGE 2
KC WATER ASSETS
PAGE 3
KC WATER PROJECT MANAGER DIRECTORY
Name Phone EmailBlake Anderson 816-513-0329 Blake.W.Anderson@kcmo.orgCarla Bergman 816-513-0348 Carla.Bergman@kcmo.orgMickey Cruse 816-513-0491 Mickey.Cruse@kcmo.orgKelly Finn 816-513-0351 Kelly.Finn@kcmo.orgDondrea Fisher 816-513-0488 Dondrea.Fisher@kcmo.orgBon Marie Gardner 816-513-0354 Bon.Marie.Gardner@kcmo.orgTerry Godard 816-513-0353 Terry.Godard@kcmo.orgChris Herrera 816-513-0355 Chris.Herrera@kcmo.orgLynda Hoffman 816-513-0489 Lynda.Hoffman@kcmo.orgBrooke Hudlemeyer 816-513-0454 Brooke.Hudlemeyer@kcmo.orgAlex Ivanescu 816-513-0445 Alex.Ivanescu@kcmo.orgPriya Iyengar 816-513-0579 Padmavathi.Iyengar@kcmo.orgJulie Jenson 816-513-0446 Julie.Jenson@kcmo.orgDiana Johnson 816-513-0376 Diana.M.Johnson@kcmo.orgRebecca Mitchell 816-513-0341 Rebecca.Mitchell@kcmo.orgKhoa Nguyen 816-513-0264 Khoa.Nguyen@kcmo.orgKarine Papikian 816-513-0300 Karine.Papikian@kcmo.orgJohn C. Parks 816-513-0461 John.C.Parks@kcmo.orgRichard Parmeter 816-513-0382 Richard.Parmeter@kcmo.orgJohn Reddy 816-513-0377 John.Reddy@kcmo.orgJoe Remmers 816-513-7228 Joe.Remmers@kcmo.orgMorris Ross 816-513-0361 Morris.Ross@kcmo.orgDebra Smith 816-513-0293 Debra.Smith@kcmo.orgPaul South 816-513-0263 Paul.South@kcmo.orgTerry Thomas 816-513-0262 Terry.D.Thomas@kcmo.orgTerry Winbush 816-513-0495 Terry.Winbush@kcmo.orgReza Zonnooz 816-513-0309 Reza.Zonnooz@kcmo.org
PAGE 4
FISCAL YEAR 2017 WATER CIP
Budget Amounts by Project Type
Treatment $22,300,000Pump Station $5,716,000Transmission $10,459,000Storage $2,000,000Distribution $60,759,000
Total $101,234,000
PAGE 5
Risk-Based Asset Management Program for Facilities$175,000 | December 2016
TREATMENT
DESIGN
East Bottoms Pump Station Phase 3$915,000 | July 2016
Risk-Based Asset Management Program for Pump Stations$300,000 | December 2016
PUMP STATION
NW Waukomis Drive from Englewood Rd. to NW 62nd St.$250,000 | May 2016
Transmission Main Improvements: 131st St., Holmes Rd. to Prospect Ave.$435,000 | September 2016
TRANSMISSION
PAGE 6
Elevated Tank: Prospect Rd., Shoal Creek, Downtown, and Blue Ridge$2,000,000 | June 2016
STORAGE DESIGN
Water Main Replacement: Bales Ave. to Belmont Ave.; E. 99th St. to E. 107th St. $420,000 | June 2016
Water Main Replacement: Wyoming Ave. to Flora Ave.; W. 65th St. to W. 78th St.$330,000 | June 2016
Water Main Replacement: College Ave. to James A Reed Rd.; E. 71st St. to E. 80th Ter.$280,000 | June 2016
Water Main Replacement: Northern Ave. to Lee’s Summit Rd.; E. 49th St. to E. 62nd St.$210,000 | June 2016
Water Main Replacement: N. Lister Ave. to N. Sycamore Dr.; NE 47th St. to NE 62nd St.$180,000 | June 2016
DISTRIBUTION
PAGE 7
DISTRIBUTION
Water Main Replacement: Wallace Ave. to Willow Ave.; E. 29th Ter. to E. 39th Ter.$160,000 | June 2016 | SLBE-WSDEPS
Water Main Replacement: E. 139th St. to Peterson Rd. to Sampson Rd. $130,000 | June 2016
Water Main Replacement: Genessee St. to Euclid Ave.; E. 1st St. to E. 23rd St.$130,000 | June 2016 | SLBE-WSDEPS
Water Main Replacement: Monroe Ave. to Hardesty Ave.; E. 43rd St. to E. 47th St.$120,000 | June 2016 | SLBE-WSDEPS
Water Main Replacement: N. Chaumiere Rd. to N. Cleveland Ave.; NE Russell Rd. to NE 43rd St. $80,000 | July 2016 | SLBE-WSDEPS
Water Main Replacement: I-435 to Oxford Ave.; to E. 49th St. to E. 59th St.$130,000 | July 2016 | SLBE-WSDEPS
Water Main Replacement: Glen Arbor Ter. to Virginia Ave.; E. 110th St. to E. 117th St. $160,000 | July 2016
DESIGN
PAGE 8
DISTRIBUTION
Water Main Replacement: Cherry St. to Prospect Ave.; E. 122nd St. to E. 130th St.$180,000 | July 2016
Water Main Replacement: Ward Parkway to Main St.; W. 85th St. to Western Hills Dr.$200,000 | July 2016
Water Main Replacement: Crystal Ave. to Greenwood Rd.; E. 103rd St. to E. 115th St.$220,000 | July 2016 | SLBE-WSDEPS
Water Main Replacement: N. Troost Ave. to N. Cleveland Ave.; NE 46th St. to NE Englewood Rd.$310,000 | July 2016
Water Main Replacement: Jarboe St. to Brooklyn Ave.; W. 79th St. to E. 86th St.$360,000 | July 2016
Water Main Replacement: Norton Ave. to Quincy Ave.; E. 52nd St. to E. 55th St.$120,000 | July 2016 | SLBE-WSDEPS
DESIGN
PAGE 9
Electrical Service Reliability at Wastewater Treatment Plant$5,000,000 | September 2016
Chemical Building (Lime Slakers)$4,000,000 | February 2017
Water Treatment Plant Improvements to Basin Walkways, Launders, Supports, Equipment and Weirs$9,525,000 | March 2017
Valve Replacements at Water Treatment Plant Intake$1,600,000 | March 2017
SCADA System (North System Automation)$500,000 | April 2017
SCADA System (South System Automation)$1,500,000 | April 2017
TREATMENT CONSTRUCTION
PAGE 10
PUMP STATION
Dehumidification at Secondary Pump Station$200,000 | November 2016
Turkey Creek Pump Station Improvements$1,300,000 | January 2017
CONSTRUCTION
TRANSMISSION
Arrowhead Phase III: N. Oak to Englewood Rd.$6,775,000 | May 2016
NW Englewood Rd. from U.S. 169 to NW Waukomis$3,000,000 | May 2016
PAGE 11
Water Main Replacement: Wiedenmann Pl. to Agnes Ave.; W. 42nd St. to E. 67th St.$426,000 | May 2016
Water Main Replacement: Bristol Ave. to Booth Ave.; E. 47th Ter. to E. 73rd St.$2,000,000 | May 2016
Water Main Replacement: Highland Ave. to Hillcrest Rd.; E. 79th St. to E. 100th Ter.$5,745,000 | June 2016
Water Main Replacement: N. Kansas Ave. to N. Cypress Ave.; NE 41st St. to NE 57th Ter.$2,300,000 | June 2016
Water Main Replacement: Hillcrest Rd. to Wallace Ave.; E. 74th St. to E. 86th St.$1,275,000 | July 2016
Water Main Replacement: Raytown Rd., E. 87th St., and E. Bannister Rd.$1,300,000 | July 2016
Water Main Replacement: Askew Ave. to Belmead Rd.; E. 33rd St. to E. 53rd St.$2,250,000 | July 2016
DISTRIBUTION CONSTRUCTION
PAGE 12
Water Main Replacement: N. Park Plaza Dr. to N. Agnes Ave.; NW 65th Pl. to NE 88th St.$2,690,000 | July 2016
Water Main Replacement: Mercier St. to Woodland Ln.; W. 90th Ter. to E. 100th Ter.$2,250,000 | August 2016
Water Main Replacement: Mercier St. to Wayne Ave.; W. 72nd St to W. 87th St.$5,000,000 | August 2016
Water Main Replacement: N. Oak Trfy to N. Tracy Ave.; NE 96th Ter. to NE Cookingham Dr.$1,100,000 | August 2016
Water Main Replacement: Terrace St. to Euclid Ave.; E. 3rd St. to W. 32nd Ter. $1,260,000 | September 2016
Water Main Replacement: N. Oak Trfy to N. Brooklyn Ave.; NE Russell Rd. to NE Englewood Rd.$1,835,000 | September 2016
Water Main Replacement: Manchester Ave. to SW View High Dr.; E. Bannister Rd. to Longview Rd.$2,500,000 | September 2016
DISTRIBUTION CONSTRUCTION
PAGE 13
Water Main Replacement: Washington St. to Prospect Ave.; 108th Ter. to E. 155th St.$2,500,000 | October 2016
Water Main Replacement: Noland Rd. to Rhinehart Rd.; Little Blue Rd. to E. 87th St.$1,400,000 | October 2016
Water Main Replacement: Winchester Ave. to Hardy Ave.; E. Truman Rd. to E. 40th Ter.$1,800,000 | November 2016
Water Main Replacement: Noland Rd. to Emery Ave.; E. 49th St. to Little Blue Rd.$2,500,000 | November 2016
DISTRIBUTION CONSTRUCTION
PAGE 14
FISCAL YEAR 2017 WASTEWATER CIP
Budget Amounts by Project Type
Collection System $141,500,000Storage $25,842,000Pump Station $8,350,000Treatment $31,530,000
Total $207,222,000
PAGE 15
Motor Control Replacement: 15th & Crystal, Round Grove, Blue River$250,000 | July 2016
Relocate Operational Controls to Pump Stationat Pump Station 7 $100,000 | July 2016
Burlington Creek Force Main/Pump Station Improvements$100,000 | July 2016 | SLBE-WSDEPS
KC Water Learning Labs $250,000 | July 2016
Replace External/Internal Lighting at Birmingham, Westside and Todd Creek$200,000 | August 2016
Replace BR Secondary Switchgear$200,000 | August 2016
Study: Nutrient Removal (Westside Wastewater Treatment Plant)$250,000 | September 2016
TREATMENT DESIGN
PAGE 16
Replace Digester Piping and MCC’s for all 3 DAFs$350,000 | October 2016
New Building for Maintenance Shop and Offices$300,000 | January 2017
TREATMENT DESIGN
1720 Wabash Rehabilitation$250,000 | June 2016
WASTEWATER ADMINISTRATION
PAGE 17
Pump Station Upgrade: Round Grove$1,100,000 | May 2016
Neighborhood Sewer Rehabilitation: Northeast Industrial District$1,600,000 | September 2016
Neighborhood Sewer Rehabilitation: Lower Blue River$2,540,000 | September 2016
Blue River Watershed Management Plan: Year 1 Integrated Planning$100,000 | March 2017
Dry Weather Sewer Line: Outfall 056$45,000 | March 2017 | SLBE-WSDEPS
Neighborhood Sewer Rehabilitation: Turkey Creek/Central Industrial District$2,540,000 | April 2017
OVERFLOW CONTROL PROGRAM DESIGN
PAGE 18
Odor Control Improvements Phase II at Blue River$9,000,000 | May 2016
Blue River Solids Management Phase I$5,000,000 | June 2016
3 Vertical Climbing Bar Screens Line Creek$1,900,000 | July 2017
TREATMENT DESIGN-BUILD
City-wide Sewer Manhole Stabilization within Waterways$4,00,000 | May 2015
COLLECTION
PAGE 19
West Lagoon Clean Out and ResealConstruction Phase Services | $120,000 | September 2016Construction |$2,190,000 | September 2016
Birmingham Grit Removal and BlowersConstruction Phase Services | $480,000 | October 2016Construction | $9,600,000 | October 2016
TREATMENT
CONSTRUCTION
Buckeye Pump Station ImprovementsConstruction Phase Services | $360,000 | April 2017 Construction | $6,890,000 | April 2017
PUMP STATION
PAGE 20
Blue River North I/I ReductionConstruction Phase Services | $194,000 | August 2016Construction | $3,880,000 | August 2016
Sewer Separation at Diversion Structure 099Construction Phase Services | $90,000 | August 2016Construction | $1,700,000 | August 2016
Blue River South I/I Reduction Area 3Construction Phase Services | $150,000 | October 2016Construction | $3,070,000 | October 2016
Line Creek/Rock Creek I/I Reduction Area 1 Construction Phase Services | $180,000 | November 2016Construction | $3,690,000 | November 2016
Small Sewer Rehabilitation: Town Fork CreekConstruction Phase Services | $720,000 | November 2016Construction | $14,350,000 | November 2016
Sewer Separation at Outfall 067Construction Phase Services | $1,290,000 | December 2016Construction | $25,700,000 | December 2016
Blue River Central I/I Reduction Area 1Construction Phase Services | $250,000 | December 2016Construction | $4,920,000 | December 2016
OVERFLOW CONTROL PROGRAM CONSTRUCTION
PAGE 21
Relief Sewer at Diversion Structure 068Construction Phase Services | $280,000 | December 2016Construction | $5,650,000 | December 2016
In-Line Storage: OK Creek GatesConstruction Phase Services | $230,000 | February 2017Construction | $4,610,000 | February 2017
Blue River Central I/I Reduction Area 2Construction Phase Services | $260,000 | March 2017Construction | $5,260,000 | March 2017
Line Creek/Rock Creek I/I Reduction Area 2Construction Phase Services | $330,000 | April 2017Construction | $6,600,000 | April 2017
Pump Station & In-line Storage at Gooseneck Arch SewerConstruction Phase Services | $1,000,000 | April 2017Construction | $20,000,000 | April 2017
Blue River South I/I Reduction Area 5Construction Phase Services | $170,000 | April 2017Construction | $3,430,000 | April 2017
OVERFLOW CONTROL PROGRAM CONSTRUCTION
PAGE 22
FISCAL YEAR 2017 STORMWATER CIP
Budget Amounts by Project Type
Conveyance $3,094,000Flood Risk Management $9,700,000Trails $4,000,000Channels $800,000
Total $17,594,000
PAGE 23
KC Levees - Argentine Unit$1,800,000 | September 2016
Swope Park Industrial Area Bank Stabilization/Levee$5,900,000 | September 2016
Blue River Basin - Dodson$2,000,000 | March 2017
Blue River Trails: Seg B - Brush Creek to Stadium Drive$2,000,000 | November 2016
Blue River Trails: Seg C - Stadium Drive to Corrington Park$2,000,000 | April 2017
STORMWATER IMPROVEMENTS CONSTRUCTION