Kashmir rail project

Post on 03-Sep-2014

6223 Views

Category:

Technology

8 Downloads

Preview:

Click to see full reader

DESCRIPTION

 

Transcript

Kashmir Rail ProjectChallenges solutions and current status

Presented ByMeenakshi Gupta

Mahesh JainRitu Dubey

Kashmir Railway Project (KRP)bull To provide an alternative and reliable transportation system to

JampK

bull 345 km long railway line for linking the Kashmir Valley

bull Biggest project to be undertaken by IR since independence

bull Officially called Jammu-Udhampur-Katra-Quazigund-Baramulla link (JUSBRL)

bull Under construction since 1994 was given the status of a national project in 2002 under the Vajpayee government

bull The initial deadline was for 2009 Various delays pushed it to 2012 and now extended to 2017

Project Detailsbull There will be 30 stations and they will be served by 10 to 12

trains a day

bull Being built to the Indian standard gauge of 1676mm gauge laid on concrete sleepers with continuous welded rail and with a minimum curve radius of 676m

bull A ruling gradient of 1 has been set to provide a safe smooth and reliable journey

bull Maximum line speed is 100kmh (60mph)

bull Cross a total of over 750 bridges and pass through over 100 kilometres (62 mi) of tunnels

Challengesbull There are various constraints such as allowable

maximum speed high gradients sharp curves stations to be kept for optimum utilization safety and minimum maintenance need in future in addition to the basic need for providing the link with the rest of the network

bull Projects in mountainous regions are associated with special features such as deep cuttings high embankments tall piers and long span bridges across deep gorges and fast flowing flash flood rivers with big boulders and unusually long tunnels etc

Challenges

bull 345km route crosses major earthquake zones and is subjected to extreme temperatures of cold and heat as well as inhospitable terrain

bull Extreme winters with heavy snowfalls

bull Kashmir is an electricity scarce region at present

bull Young Himalayas where geology is poor and changes occur frequently

Challengesbull Katra-Quazigund leg is the most difficult stretch of this project

In this leg Salal to Quazigund stretch lies in the territory where virtually no habitation road or tracking path existed

bull In Katra-Quazigund a significant part of the project lies in tunnels with the longest being about 1096 km

bull There will be several bridges The tallest bridge is about 359 m above bed level and is over 13 km in length over river Chenab

bull Water ingress problems have been seen in the Udhampur to Katra section This has required some drastic solutions using steel arches and several feet of shotcrete

Security Challenges

bull the regions the line passes through are continuing to face terrorist challenges

bull The train will pass through some of the most vulnerable areas in the Valley such as Budgam Pulwama Srinagar and Anantnag districts to which militants have clear and easy access in the absence of security

bull The presence of the international border with Pakistan close by aggravates these challenges

bull Plans for close circuit cameras at all major bridges tunnels and railway stations have been made Lighting is provided on all major bridges and inside tunnels

Project Sub sectionsbull Jammu-Udhampur Rail Link Project (53 km) ndash Leg 0

ndash sub-mountainous region ndash It is 53 km long and has 10 km length of tunnels 36 major bridges and 122 minor bridgesndash his stretch has already been completed and commissioned in April 2005ndash The completion cost of this stretch is Rs 522 crore

bull Udhampur-Srinagar-Baramulla Rail Link (USBRL) Project (202 km)

ndash Leg-1 ndash Udhampur-Katra section (25 km )bull involves about 109 km of tunneling Nine major bridges 29 minor bridges and 10

ROBRUBs in addition to about 3886 lac cum of earthworkbull approximate cost of this stretch is Rs 640 cr bull tallest bridge in this section is 90 m high (Br No 20) and the longest tunnel (T-80) is

315 km long

Project Sub sectionsbull Leg-2 ndash Katra-Quazigund (148 km)

ndash toughest sector ever been constructed on the Indian Railwaysndash full of tunnels and bridgesviaducts Terrain in this region is full of poor geology and

faults ndash On this section a bridge is being constructed across river Chenab which will have an

arched span of 465 m and a total length of the bridge is around 13 km This will be about 359 m above the bed level of the river

ndash The stretch between river Chenab and Banihal is through a virgin territory and requires construction of approximately 300 km of access roads of which about 110 km has already been constructed

ndash At Quazigund end of this stretch the longest tunnel on Indian Railways is being constructed (Pir Panjal Tunnel) This tunnel is 1095 km long and will pierce through the Pir Panjal range below the snow line

bull Leg 3-Quazigund-Baramulla (119 km)

ndash falls in the Kashmir Valley which is a natural bowl surrounded by the mountain rangesndash there are no tunnels heavy bridging is required across rivers canals and roadsndash 64 major bridges and 640 minor bridges in this sectionndash completed in October 2009

Rolling Stockbull Freight services conveying grain and petroleum products will run

in between 10- 12 passengers services that are planned to operate daily

bull An eight-coach DEMU will run on the Quazigund-Baramulla section of line Each coach will carry 90 passengers It will run twice a day in both directions

bull The train has been fixed with a snow cutter system for clearing snow on the track The temperature in coaches can also be maintained at 20degC during winter

bull Passenger services will be provided by the new aerodynamic High Power diesel multiple units with special features

Rolling Stock (contdhellip)bull The air-conditioned coaches have wide windows for a panoramic view

anti-skid flooring sliding doorways heating facilities an attractive colour scheme and executive class reclining seats inside

bull The drivers cabin has a heating and defogging unit to take care of cold climatic conditions and is fitted with single lookout glass windows to give a wider view

bull A snow-cutting type cattle guard has been attached at the driving end of the train for clearing snow from the tracks during winter In view of the peculiar climate of the valley the 1400-horsepower diesel engine for the train has been provided with a heating system for a quick and trouble-free start in the winters A public information system with display and announcement facilities are included in the coaches which have pneumatic suspension for better riding comfort There is also a compartment for physically challenged people with wider doors

bull Maintenance of all rolling stock and locomotives will be at the newly built Budgam workshop just north of Srinagar

Responsibilitybull Indian Railways is in charge of the Udhampur-Katra Section (25 km)

bull Konkan Railway Corporation Limited is in charge of the Katra-Laole Section (90 km) This is arguably the toughest portion of the railway with over 92 of the line either inside a tunnel or on a bridge The bridges comprise of 12 km the tunnels of 72 km and only a minuscule part of this tortuous stretch ie 6 km is on normal ground

bull IRCON a Public Sector railway construction company is in charge of the Laole-Baramulla Section (175 km) Another tough but less brutal section

bull HCC has won the tender to construct both the North and South Section of the 11 km Banihal tunnel across the Pir Panjal range for approx US$120 million Work is completed

bull AFCONS with Ultra Engineering (South Korea) will design and construct the Chenab Bridge for US$130 million

bull Gammon India with Archirodon Construction (South Africa) will build the Anji Khad Bridge for US$100 million

Financials

bull Till April 2011 7165 crore had already been spent While the budget for last year was 1000 crore it has been marginally raised to 1100 crore for current fiscal

bull Delay in the completion of the project led to an increase in the cost of requiring additional funds The Indian Government previously increased the projected cost of the railway line in 2007 upping the initial estimate of Rs307bn ($5693m) to Rs112bn ($21bn)

bull The Indian Government has cleared a proposal to earmark Rs190bn ($35bn) of additional funds (Jan 2012)

Infrastructure and constructionbull Total of over 750 bridges and over 100

kilometres (62 mi) of tunnels the longest of which is about 11 kilometres (68 mi) in length

bull The greatest engineering challenges involve the crossing of the Chenab river which involves building a 1315-metre-long (4314 ft) bridge 359 metres (1178 ft) above the river bed and the crossing of the Anji Khad which involves building a 657-metre-long (2156 ft) bridge 186 metres (610 ft) above the river bed

Pir Panjal Tunnel(T-80)

Pir Panjal Tunnel(T-80)bull At 1096km long the Pir Panjal Railway Tunnel is Indias longest and Asias 2nd

longest tunnel

bull passes through the Pir Panjal mountain range in Jammu and Kashmir in India

bull aimed at reducing the travel distance between Quazigund and Banihal to only 11 km

bull cover the distance from the south to the north side of the mountain in 66 minutes

bull Completed in October 2011

bull cost of Rs10bn ($2018m)

bull Construction of the tunnel was carried out by Hindustan Construction Company and took over six years

Pir Panjal Tunnel(T-80)bull 84m-wide and 73m-high tunnel and is up to 1 100 m below the surface

bull construction of a 3m-wide road that runs alongside the railway tunnel for maintenance and emergency evacuation

bull 100 percent water-proof and is also equipped with fire fighting system throughout its entire length

bull construction of the tunnel started in November 2005 and was complete in 2011

bull The fascinating fact about the tunnel excavation is that the total excavated quantity was equal to one mountain

bull It runs 440m below the existing Jawahar Tunnel which is the only road link from the region to the rest of India meant for vehicular traffic only- which usually gets blocked during winters owing to heavy snowfall in the region

bull due to the changing geological strata of the young Himalayan rock New Australian Tunneling Methodology (NATM) was adopted for the construction

Chenab Bridgebull The Chenab Bridge will be the highest railway structure of its kind in the world

35 m higher than the tip of the Eiffel Tower in Paris

bull The Chenab bridge is 13 km long and has the third largest arch span in the world At 1178 feet it will be the highest bridge in the world once completed

bull Located near the Salal Hydro Power Dam the bridge was originally planned as a 1315 metre-long bridge having 17 spans

bull Afcons Infrastructure Limited was awarded the contract for the bridge

bull While deciding to stop all construction works on the Katra-Qazigund section in 2008 the Railway Ministry had proposed a change in the location of the bridge from the gorge to a wide valley two to three kilometers upstream of the original location Since the newly proposed location had a higher bed level the height of the bridge had it been constructed there would have come down to about 120-150 meters from river bed

bull The Railways decided to stick to the location it had originally chosen to construct the Chenab Bridge mdash billed as the highest in the world at a height of 359 metres from the river bed At 343 metres Millau Viaduct in France is the tallest bridge in the world

Operational Accidents amp Casualitiesbull June 2004 mdash Sudhir Kumar Pundir an IRCON Engineer and his brother Sanjay

were kidnapped and murdered by terrorists in the valley

bull June 2005 mdash Altaf Hussain A laborer working in a Tunnel at Tathyar (HCC) was killed by a collapse Two others were injured

bull May 16 2007 mdashdaughter of Mushtaq Ahmad Wagay and daughter of Mohammad Ayub Wani (9 amp 7 yrs)drowned in a ditch constructed by Railway Company

bull Feb 14 2008 mdash A Nepali labourer Tika Ram Balwari son of Tuya Narayan was killed after a boulder hit him in at Uri Varmul presumably on the Kashmir rail project for HCC

bull Apr 18 2008 mdash Six labourers of a private company engaged with the Katra-Qazigund railway line project were killed and two others received injuries when a tipper carrying them rolled down into a deep gorge in Lower Juda Morh near Kouri in Reasi district late at night

bull Mar 27 2011 mdash Two workers were killed at an under-construction railway bridge over the Chenab in Reasi district as a basket attached to a crane carrying them unhooked and fell from a height of more than 100 metres

Current Status

bull The USBRL project is divided into four sections

bull Leg 0 extending 53 kilometres (33 mi) from Jammu to Udhampur completed in April 2005

bull Leg 1 extending 25 kilometres (16 mi) from Udhampur to Katra Under construction may open in 2013

bull Leg 2 extending 148 kilometres (92 mi) from Katra to Qazigund Under construction may open in 2017

bull Leg 3 extending 119 kilometres (74 mi) from Qazigund to Baramulla completed in October 2009

Inauguration of Kashmir rail linkDate Section Length km

April 2005 Jammu - Udhampur Current Status

53

October 2008 Anantnag - Mazhom 66

February 2009 Mazhom - Baramulla 35

October 2009 Quazigund - Anantnag 18

Delayed owing to construction difficulties

Udhampur - Quazigund 167

Inauguration of Final section KVRbull Prime Minister Dr Manmohan

Singh flagged off a train from Anantnag to Quazigund to inaugurate the final 18 km of the railway through the Kashmir Valley on October 28 2009

bull The currently isolated line will eventually be joined to the Indian rail network at Udhampur providing an all -weather transport link between the state of Jammu amp Kashmir and the rest of India which has been designated as a national priority

Thanks

  • Kashmir Rail Project Challenges solutions and current status
  • Kashmir Railway Project (KRP)
  • Project Details
  • Slide 4
  • Challenges
  • Slide 6
  • Slide 7
  • Security Challenges
  • Project Sub sections
  • Slide 10
  • Rolling Stock
  • Rolling Stock (contdhellip)
  • Responsibility
  • Financials
  • Infrastructure and construction
  • Pir Panjal Tunnel(T-80)
  • Slide 17
  • Slide 18
  • Slide 19
  • Chenab Bridge
  • Slide 21
  • Operational Accidents amp Casualities
  • Slide 23
  • Current Status
  • Slide 25
  • Inauguration of Final section KVR
  • Thanks

    Kashmir Railway Project (KRP)bull To provide an alternative and reliable transportation system to

    JampK

    bull 345 km long railway line for linking the Kashmir Valley

    bull Biggest project to be undertaken by IR since independence

    bull Officially called Jammu-Udhampur-Katra-Quazigund-Baramulla link (JUSBRL)

    bull Under construction since 1994 was given the status of a national project in 2002 under the Vajpayee government

    bull The initial deadline was for 2009 Various delays pushed it to 2012 and now extended to 2017

    Project Detailsbull There will be 30 stations and they will be served by 10 to 12

    trains a day

    bull Being built to the Indian standard gauge of 1676mm gauge laid on concrete sleepers with continuous welded rail and with a minimum curve radius of 676m

    bull A ruling gradient of 1 has been set to provide a safe smooth and reliable journey

    bull Maximum line speed is 100kmh (60mph)

    bull Cross a total of over 750 bridges and pass through over 100 kilometres (62 mi) of tunnels

    Challengesbull There are various constraints such as allowable

    maximum speed high gradients sharp curves stations to be kept for optimum utilization safety and minimum maintenance need in future in addition to the basic need for providing the link with the rest of the network

    bull Projects in mountainous regions are associated with special features such as deep cuttings high embankments tall piers and long span bridges across deep gorges and fast flowing flash flood rivers with big boulders and unusually long tunnels etc

    Challenges

    bull 345km route crosses major earthquake zones and is subjected to extreme temperatures of cold and heat as well as inhospitable terrain

    bull Extreme winters with heavy snowfalls

    bull Kashmir is an electricity scarce region at present

    bull Young Himalayas where geology is poor and changes occur frequently

    Challengesbull Katra-Quazigund leg is the most difficult stretch of this project

    In this leg Salal to Quazigund stretch lies in the territory where virtually no habitation road or tracking path existed

    bull In Katra-Quazigund a significant part of the project lies in tunnels with the longest being about 1096 km

    bull There will be several bridges The tallest bridge is about 359 m above bed level and is over 13 km in length over river Chenab

    bull Water ingress problems have been seen in the Udhampur to Katra section This has required some drastic solutions using steel arches and several feet of shotcrete

    Security Challenges

    bull the regions the line passes through are continuing to face terrorist challenges

    bull The train will pass through some of the most vulnerable areas in the Valley such as Budgam Pulwama Srinagar and Anantnag districts to which militants have clear and easy access in the absence of security

    bull The presence of the international border with Pakistan close by aggravates these challenges

    bull Plans for close circuit cameras at all major bridges tunnels and railway stations have been made Lighting is provided on all major bridges and inside tunnels

    Project Sub sectionsbull Jammu-Udhampur Rail Link Project (53 km) ndash Leg 0

    ndash sub-mountainous region ndash It is 53 km long and has 10 km length of tunnels 36 major bridges and 122 minor bridgesndash his stretch has already been completed and commissioned in April 2005ndash The completion cost of this stretch is Rs 522 crore

    bull Udhampur-Srinagar-Baramulla Rail Link (USBRL) Project (202 km)

    ndash Leg-1 ndash Udhampur-Katra section (25 km )bull involves about 109 km of tunneling Nine major bridges 29 minor bridges and 10

    ROBRUBs in addition to about 3886 lac cum of earthworkbull approximate cost of this stretch is Rs 640 cr bull tallest bridge in this section is 90 m high (Br No 20) and the longest tunnel (T-80) is

    315 km long

    Project Sub sectionsbull Leg-2 ndash Katra-Quazigund (148 km)

    ndash toughest sector ever been constructed on the Indian Railwaysndash full of tunnels and bridgesviaducts Terrain in this region is full of poor geology and

    faults ndash On this section a bridge is being constructed across river Chenab which will have an

    arched span of 465 m and a total length of the bridge is around 13 km This will be about 359 m above the bed level of the river

    ndash The stretch between river Chenab and Banihal is through a virgin territory and requires construction of approximately 300 km of access roads of which about 110 km has already been constructed

    ndash At Quazigund end of this stretch the longest tunnel on Indian Railways is being constructed (Pir Panjal Tunnel) This tunnel is 1095 km long and will pierce through the Pir Panjal range below the snow line

    bull Leg 3-Quazigund-Baramulla (119 km)

    ndash falls in the Kashmir Valley which is a natural bowl surrounded by the mountain rangesndash there are no tunnels heavy bridging is required across rivers canals and roadsndash 64 major bridges and 640 minor bridges in this sectionndash completed in October 2009

    Rolling Stockbull Freight services conveying grain and petroleum products will run

    in between 10- 12 passengers services that are planned to operate daily

    bull An eight-coach DEMU will run on the Quazigund-Baramulla section of line Each coach will carry 90 passengers It will run twice a day in both directions

    bull The train has been fixed with a snow cutter system for clearing snow on the track The temperature in coaches can also be maintained at 20degC during winter

    bull Passenger services will be provided by the new aerodynamic High Power diesel multiple units with special features

    Rolling Stock (contdhellip)bull The air-conditioned coaches have wide windows for a panoramic view

    anti-skid flooring sliding doorways heating facilities an attractive colour scheme and executive class reclining seats inside

    bull The drivers cabin has a heating and defogging unit to take care of cold climatic conditions and is fitted with single lookout glass windows to give a wider view

    bull A snow-cutting type cattle guard has been attached at the driving end of the train for clearing snow from the tracks during winter In view of the peculiar climate of the valley the 1400-horsepower diesel engine for the train has been provided with a heating system for a quick and trouble-free start in the winters A public information system with display and announcement facilities are included in the coaches which have pneumatic suspension for better riding comfort There is also a compartment for physically challenged people with wider doors

    bull Maintenance of all rolling stock and locomotives will be at the newly built Budgam workshop just north of Srinagar

    Responsibilitybull Indian Railways is in charge of the Udhampur-Katra Section (25 km)

    bull Konkan Railway Corporation Limited is in charge of the Katra-Laole Section (90 km) This is arguably the toughest portion of the railway with over 92 of the line either inside a tunnel or on a bridge The bridges comprise of 12 km the tunnels of 72 km and only a minuscule part of this tortuous stretch ie 6 km is on normal ground

    bull IRCON a Public Sector railway construction company is in charge of the Laole-Baramulla Section (175 km) Another tough but less brutal section

    bull HCC has won the tender to construct both the North and South Section of the 11 km Banihal tunnel across the Pir Panjal range for approx US$120 million Work is completed

    bull AFCONS with Ultra Engineering (South Korea) will design and construct the Chenab Bridge for US$130 million

    bull Gammon India with Archirodon Construction (South Africa) will build the Anji Khad Bridge for US$100 million

    Financials

    bull Till April 2011 7165 crore had already been spent While the budget for last year was 1000 crore it has been marginally raised to 1100 crore for current fiscal

    bull Delay in the completion of the project led to an increase in the cost of requiring additional funds The Indian Government previously increased the projected cost of the railway line in 2007 upping the initial estimate of Rs307bn ($5693m) to Rs112bn ($21bn)

    bull The Indian Government has cleared a proposal to earmark Rs190bn ($35bn) of additional funds (Jan 2012)

    Infrastructure and constructionbull Total of over 750 bridges and over 100

    kilometres (62 mi) of tunnels the longest of which is about 11 kilometres (68 mi) in length

    bull The greatest engineering challenges involve the crossing of the Chenab river which involves building a 1315-metre-long (4314 ft) bridge 359 metres (1178 ft) above the river bed and the crossing of the Anji Khad which involves building a 657-metre-long (2156 ft) bridge 186 metres (610 ft) above the river bed

    Pir Panjal Tunnel(T-80)

    Pir Panjal Tunnel(T-80)bull At 1096km long the Pir Panjal Railway Tunnel is Indias longest and Asias 2nd

    longest tunnel

    bull passes through the Pir Panjal mountain range in Jammu and Kashmir in India

    bull aimed at reducing the travel distance between Quazigund and Banihal to only 11 km

    bull cover the distance from the south to the north side of the mountain in 66 minutes

    bull Completed in October 2011

    bull cost of Rs10bn ($2018m)

    bull Construction of the tunnel was carried out by Hindustan Construction Company and took over six years

    Pir Panjal Tunnel(T-80)bull 84m-wide and 73m-high tunnel and is up to 1 100 m below the surface

    bull construction of a 3m-wide road that runs alongside the railway tunnel for maintenance and emergency evacuation

    bull 100 percent water-proof and is also equipped with fire fighting system throughout its entire length

    bull construction of the tunnel started in November 2005 and was complete in 2011

    bull The fascinating fact about the tunnel excavation is that the total excavated quantity was equal to one mountain

    bull It runs 440m below the existing Jawahar Tunnel which is the only road link from the region to the rest of India meant for vehicular traffic only- which usually gets blocked during winters owing to heavy snowfall in the region

    bull due to the changing geological strata of the young Himalayan rock New Australian Tunneling Methodology (NATM) was adopted for the construction

    Chenab Bridgebull The Chenab Bridge will be the highest railway structure of its kind in the world

    35 m higher than the tip of the Eiffel Tower in Paris

    bull The Chenab bridge is 13 km long and has the third largest arch span in the world At 1178 feet it will be the highest bridge in the world once completed

    bull Located near the Salal Hydro Power Dam the bridge was originally planned as a 1315 metre-long bridge having 17 spans

    bull Afcons Infrastructure Limited was awarded the contract for the bridge

    bull While deciding to stop all construction works on the Katra-Qazigund section in 2008 the Railway Ministry had proposed a change in the location of the bridge from the gorge to a wide valley two to three kilometers upstream of the original location Since the newly proposed location had a higher bed level the height of the bridge had it been constructed there would have come down to about 120-150 meters from river bed

    bull The Railways decided to stick to the location it had originally chosen to construct the Chenab Bridge mdash billed as the highest in the world at a height of 359 metres from the river bed At 343 metres Millau Viaduct in France is the tallest bridge in the world

    Operational Accidents amp Casualitiesbull June 2004 mdash Sudhir Kumar Pundir an IRCON Engineer and his brother Sanjay

    were kidnapped and murdered by terrorists in the valley

    bull June 2005 mdash Altaf Hussain A laborer working in a Tunnel at Tathyar (HCC) was killed by a collapse Two others were injured

    bull May 16 2007 mdashdaughter of Mushtaq Ahmad Wagay and daughter of Mohammad Ayub Wani (9 amp 7 yrs)drowned in a ditch constructed by Railway Company

    bull Feb 14 2008 mdash A Nepali labourer Tika Ram Balwari son of Tuya Narayan was killed after a boulder hit him in at Uri Varmul presumably on the Kashmir rail project for HCC

    bull Apr 18 2008 mdash Six labourers of a private company engaged with the Katra-Qazigund railway line project were killed and two others received injuries when a tipper carrying them rolled down into a deep gorge in Lower Juda Morh near Kouri in Reasi district late at night

    bull Mar 27 2011 mdash Two workers were killed at an under-construction railway bridge over the Chenab in Reasi district as a basket attached to a crane carrying them unhooked and fell from a height of more than 100 metres

    Current Status

    bull The USBRL project is divided into four sections

    bull Leg 0 extending 53 kilometres (33 mi) from Jammu to Udhampur completed in April 2005

    bull Leg 1 extending 25 kilometres (16 mi) from Udhampur to Katra Under construction may open in 2013

    bull Leg 2 extending 148 kilometres (92 mi) from Katra to Qazigund Under construction may open in 2017

    bull Leg 3 extending 119 kilometres (74 mi) from Qazigund to Baramulla completed in October 2009

    Inauguration of Kashmir rail linkDate Section Length km

    April 2005 Jammu - Udhampur Current Status

    53

    October 2008 Anantnag - Mazhom 66

    February 2009 Mazhom - Baramulla 35

    October 2009 Quazigund - Anantnag 18

    Delayed owing to construction difficulties

    Udhampur - Quazigund 167

    Inauguration of Final section KVRbull Prime Minister Dr Manmohan

    Singh flagged off a train from Anantnag to Quazigund to inaugurate the final 18 km of the railway through the Kashmir Valley on October 28 2009

    bull The currently isolated line will eventually be joined to the Indian rail network at Udhampur providing an all -weather transport link between the state of Jammu amp Kashmir and the rest of India which has been designated as a national priority

    Thanks

    • Kashmir Rail Project Challenges solutions and current status
    • Kashmir Railway Project (KRP)
    • Project Details
    • Slide 4
    • Challenges
    • Slide 6
    • Slide 7
    • Security Challenges
    • Project Sub sections
    • Slide 10
    • Rolling Stock
    • Rolling Stock (contdhellip)
    • Responsibility
    • Financials
    • Infrastructure and construction
    • Pir Panjal Tunnel(T-80)
    • Slide 17
    • Slide 18
    • Slide 19
    • Chenab Bridge
    • Slide 21
    • Operational Accidents amp Casualities
    • Slide 23
    • Current Status
    • Slide 25
    • Inauguration of Final section KVR
    • Thanks

      Project Detailsbull There will be 30 stations and they will be served by 10 to 12

      trains a day

      bull Being built to the Indian standard gauge of 1676mm gauge laid on concrete sleepers with continuous welded rail and with a minimum curve radius of 676m

      bull A ruling gradient of 1 has been set to provide a safe smooth and reliable journey

      bull Maximum line speed is 100kmh (60mph)

      bull Cross a total of over 750 bridges and pass through over 100 kilometres (62 mi) of tunnels

      Challengesbull There are various constraints such as allowable

      maximum speed high gradients sharp curves stations to be kept for optimum utilization safety and minimum maintenance need in future in addition to the basic need for providing the link with the rest of the network

      bull Projects in mountainous regions are associated with special features such as deep cuttings high embankments tall piers and long span bridges across deep gorges and fast flowing flash flood rivers with big boulders and unusually long tunnels etc

      Challenges

      bull 345km route crosses major earthquake zones and is subjected to extreme temperatures of cold and heat as well as inhospitable terrain

      bull Extreme winters with heavy snowfalls

      bull Kashmir is an electricity scarce region at present

      bull Young Himalayas where geology is poor and changes occur frequently

      Challengesbull Katra-Quazigund leg is the most difficult stretch of this project

      In this leg Salal to Quazigund stretch lies in the territory where virtually no habitation road or tracking path existed

      bull In Katra-Quazigund a significant part of the project lies in tunnels with the longest being about 1096 km

      bull There will be several bridges The tallest bridge is about 359 m above bed level and is over 13 km in length over river Chenab

      bull Water ingress problems have been seen in the Udhampur to Katra section This has required some drastic solutions using steel arches and several feet of shotcrete

      Security Challenges

      bull the regions the line passes through are continuing to face terrorist challenges

      bull The train will pass through some of the most vulnerable areas in the Valley such as Budgam Pulwama Srinagar and Anantnag districts to which militants have clear and easy access in the absence of security

      bull The presence of the international border with Pakistan close by aggravates these challenges

      bull Plans for close circuit cameras at all major bridges tunnels and railway stations have been made Lighting is provided on all major bridges and inside tunnels

      Project Sub sectionsbull Jammu-Udhampur Rail Link Project (53 km) ndash Leg 0

      ndash sub-mountainous region ndash It is 53 km long and has 10 km length of tunnels 36 major bridges and 122 minor bridgesndash his stretch has already been completed and commissioned in April 2005ndash The completion cost of this stretch is Rs 522 crore

      bull Udhampur-Srinagar-Baramulla Rail Link (USBRL) Project (202 km)

      ndash Leg-1 ndash Udhampur-Katra section (25 km )bull involves about 109 km of tunneling Nine major bridges 29 minor bridges and 10

      ROBRUBs in addition to about 3886 lac cum of earthworkbull approximate cost of this stretch is Rs 640 cr bull tallest bridge in this section is 90 m high (Br No 20) and the longest tunnel (T-80) is

      315 km long

      Project Sub sectionsbull Leg-2 ndash Katra-Quazigund (148 km)

      ndash toughest sector ever been constructed on the Indian Railwaysndash full of tunnels and bridgesviaducts Terrain in this region is full of poor geology and

      faults ndash On this section a bridge is being constructed across river Chenab which will have an

      arched span of 465 m and a total length of the bridge is around 13 km This will be about 359 m above the bed level of the river

      ndash The stretch between river Chenab and Banihal is through a virgin territory and requires construction of approximately 300 km of access roads of which about 110 km has already been constructed

      ndash At Quazigund end of this stretch the longest tunnel on Indian Railways is being constructed (Pir Panjal Tunnel) This tunnel is 1095 km long and will pierce through the Pir Panjal range below the snow line

      bull Leg 3-Quazigund-Baramulla (119 km)

      ndash falls in the Kashmir Valley which is a natural bowl surrounded by the mountain rangesndash there are no tunnels heavy bridging is required across rivers canals and roadsndash 64 major bridges and 640 minor bridges in this sectionndash completed in October 2009

      Rolling Stockbull Freight services conveying grain and petroleum products will run

      in between 10- 12 passengers services that are planned to operate daily

      bull An eight-coach DEMU will run on the Quazigund-Baramulla section of line Each coach will carry 90 passengers It will run twice a day in both directions

      bull The train has been fixed with a snow cutter system for clearing snow on the track The temperature in coaches can also be maintained at 20degC during winter

      bull Passenger services will be provided by the new aerodynamic High Power diesel multiple units with special features

      Rolling Stock (contdhellip)bull The air-conditioned coaches have wide windows for a panoramic view

      anti-skid flooring sliding doorways heating facilities an attractive colour scheme and executive class reclining seats inside

      bull The drivers cabin has a heating and defogging unit to take care of cold climatic conditions and is fitted with single lookout glass windows to give a wider view

      bull A snow-cutting type cattle guard has been attached at the driving end of the train for clearing snow from the tracks during winter In view of the peculiar climate of the valley the 1400-horsepower diesel engine for the train has been provided with a heating system for a quick and trouble-free start in the winters A public information system with display and announcement facilities are included in the coaches which have pneumatic suspension for better riding comfort There is also a compartment for physically challenged people with wider doors

      bull Maintenance of all rolling stock and locomotives will be at the newly built Budgam workshop just north of Srinagar

      Responsibilitybull Indian Railways is in charge of the Udhampur-Katra Section (25 km)

      bull Konkan Railway Corporation Limited is in charge of the Katra-Laole Section (90 km) This is arguably the toughest portion of the railway with over 92 of the line either inside a tunnel or on a bridge The bridges comprise of 12 km the tunnels of 72 km and only a minuscule part of this tortuous stretch ie 6 km is on normal ground

      bull IRCON a Public Sector railway construction company is in charge of the Laole-Baramulla Section (175 km) Another tough but less brutal section

      bull HCC has won the tender to construct both the North and South Section of the 11 km Banihal tunnel across the Pir Panjal range for approx US$120 million Work is completed

      bull AFCONS with Ultra Engineering (South Korea) will design and construct the Chenab Bridge for US$130 million

      bull Gammon India with Archirodon Construction (South Africa) will build the Anji Khad Bridge for US$100 million

      Financials

      bull Till April 2011 7165 crore had already been spent While the budget for last year was 1000 crore it has been marginally raised to 1100 crore for current fiscal

      bull Delay in the completion of the project led to an increase in the cost of requiring additional funds The Indian Government previously increased the projected cost of the railway line in 2007 upping the initial estimate of Rs307bn ($5693m) to Rs112bn ($21bn)

      bull The Indian Government has cleared a proposal to earmark Rs190bn ($35bn) of additional funds (Jan 2012)

      Infrastructure and constructionbull Total of over 750 bridges and over 100

      kilometres (62 mi) of tunnels the longest of which is about 11 kilometres (68 mi) in length

      bull The greatest engineering challenges involve the crossing of the Chenab river which involves building a 1315-metre-long (4314 ft) bridge 359 metres (1178 ft) above the river bed and the crossing of the Anji Khad which involves building a 657-metre-long (2156 ft) bridge 186 metres (610 ft) above the river bed

      Pir Panjal Tunnel(T-80)

      Pir Panjal Tunnel(T-80)bull At 1096km long the Pir Panjal Railway Tunnel is Indias longest and Asias 2nd

      longest tunnel

      bull passes through the Pir Panjal mountain range in Jammu and Kashmir in India

      bull aimed at reducing the travel distance between Quazigund and Banihal to only 11 km

      bull cover the distance from the south to the north side of the mountain in 66 minutes

      bull Completed in October 2011

      bull cost of Rs10bn ($2018m)

      bull Construction of the tunnel was carried out by Hindustan Construction Company and took over six years

      Pir Panjal Tunnel(T-80)bull 84m-wide and 73m-high tunnel and is up to 1 100 m below the surface

      bull construction of a 3m-wide road that runs alongside the railway tunnel for maintenance and emergency evacuation

      bull 100 percent water-proof and is also equipped with fire fighting system throughout its entire length

      bull construction of the tunnel started in November 2005 and was complete in 2011

      bull The fascinating fact about the tunnel excavation is that the total excavated quantity was equal to one mountain

      bull It runs 440m below the existing Jawahar Tunnel which is the only road link from the region to the rest of India meant for vehicular traffic only- which usually gets blocked during winters owing to heavy snowfall in the region

      bull due to the changing geological strata of the young Himalayan rock New Australian Tunneling Methodology (NATM) was adopted for the construction

      Chenab Bridgebull The Chenab Bridge will be the highest railway structure of its kind in the world

      35 m higher than the tip of the Eiffel Tower in Paris

      bull The Chenab bridge is 13 km long and has the third largest arch span in the world At 1178 feet it will be the highest bridge in the world once completed

      bull Located near the Salal Hydro Power Dam the bridge was originally planned as a 1315 metre-long bridge having 17 spans

      bull Afcons Infrastructure Limited was awarded the contract for the bridge

      bull While deciding to stop all construction works on the Katra-Qazigund section in 2008 the Railway Ministry had proposed a change in the location of the bridge from the gorge to a wide valley two to three kilometers upstream of the original location Since the newly proposed location had a higher bed level the height of the bridge had it been constructed there would have come down to about 120-150 meters from river bed

      bull The Railways decided to stick to the location it had originally chosen to construct the Chenab Bridge mdash billed as the highest in the world at a height of 359 metres from the river bed At 343 metres Millau Viaduct in France is the tallest bridge in the world

      Operational Accidents amp Casualitiesbull June 2004 mdash Sudhir Kumar Pundir an IRCON Engineer and his brother Sanjay

      were kidnapped and murdered by terrorists in the valley

      bull June 2005 mdash Altaf Hussain A laborer working in a Tunnel at Tathyar (HCC) was killed by a collapse Two others were injured

      bull May 16 2007 mdashdaughter of Mushtaq Ahmad Wagay and daughter of Mohammad Ayub Wani (9 amp 7 yrs)drowned in a ditch constructed by Railway Company

      bull Feb 14 2008 mdash A Nepali labourer Tika Ram Balwari son of Tuya Narayan was killed after a boulder hit him in at Uri Varmul presumably on the Kashmir rail project for HCC

      bull Apr 18 2008 mdash Six labourers of a private company engaged with the Katra-Qazigund railway line project were killed and two others received injuries when a tipper carrying them rolled down into a deep gorge in Lower Juda Morh near Kouri in Reasi district late at night

      bull Mar 27 2011 mdash Two workers were killed at an under-construction railway bridge over the Chenab in Reasi district as a basket attached to a crane carrying them unhooked and fell from a height of more than 100 metres

      Current Status

      bull The USBRL project is divided into four sections

      bull Leg 0 extending 53 kilometres (33 mi) from Jammu to Udhampur completed in April 2005

      bull Leg 1 extending 25 kilometres (16 mi) from Udhampur to Katra Under construction may open in 2013

      bull Leg 2 extending 148 kilometres (92 mi) from Katra to Qazigund Under construction may open in 2017

      bull Leg 3 extending 119 kilometres (74 mi) from Qazigund to Baramulla completed in October 2009

      Inauguration of Kashmir rail linkDate Section Length km

      April 2005 Jammu - Udhampur Current Status

      53

      October 2008 Anantnag - Mazhom 66

      February 2009 Mazhom - Baramulla 35

      October 2009 Quazigund - Anantnag 18

      Delayed owing to construction difficulties

      Udhampur - Quazigund 167

      Inauguration of Final section KVRbull Prime Minister Dr Manmohan

      Singh flagged off a train from Anantnag to Quazigund to inaugurate the final 18 km of the railway through the Kashmir Valley on October 28 2009

      bull The currently isolated line will eventually be joined to the Indian rail network at Udhampur providing an all -weather transport link between the state of Jammu amp Kashmir and the rest of India which has been designated as a national priority

      Thanks

      • Kashmir Rail Project Challenges solutions and current status
      • Kashmir Railway Project (KRP)
      • Project Details
      • Slide 4
      • Challenges
      • Slide 6
      • Slide 7
      • Security Challenges
      • Project Sub sections
      • Slide 10
      • Rolling Stock
      • Rolling Stock (contdhellip)
      • Responsibility
      • Financials
      • Infrastructure and construction
      • Pir Panjal Tunnel(T-80)
      • Slide 17
      • Slide 18
      • Slide 19
      • Chenab Bridge
      • Slide 21
      • Operational Accidents amp Casualities
      • Slide 23
      • Current Status
      • Slide 25
      • Inauguration of Final section KVR
      • Thanks

        Challengesbull There are various constraints such as allowable

        maximum speed high gradients sharp curves stations to be kept for optimum utilization safety and minimum maintenance need in future in addition to the basic need for providing the link with the rest of the network

        bull Projects in mountainous regions are associated with special features such as deep cuttings high embankments tall piers and long span bridges across deep gorges and fast flowing flash flood rivers with big boulders and unusually long tunnels etc

        Challenges

        bull 345km route crosses major earthquake zones and is subjected to extreme temperatures of cold and heat as well as inhospitable terrain

        bull Extreme winters with heavy snowfalls

        bull Kashmir is an electricity scarce region at present

        bull Young Himalayas where geology is poor and changes occur frequently

        Challengesbull Katra-Quazigund leg is the most difficult stretch of this project

        In this leg Salal to Quazigund stretch lies in the territory where virtually no habitation road or tracking path existed

        bull In Katra-Quazigund a significant part of the project lies in tunnels with the longest being about 1096 km

        bull There will be several bridges The tallest bridge is about 359 m above bed level and is over 13 km in length over river Chenab

        bull Water ingress problems have been seen in the Udhampur to Katra section This has required some drastic solutions using steel arches and several feet of shotcrete

        Security Challenges

        bull the regions the line passes through are continuing to face terrorist challenges

        bull The train will pass through some of the most vulnerable areas in the Valley such as Budgam Pulwama Srinagar and Anantnag districts to which militants have clear and easy access in the absence of security

        bull The presence of the international border with Pakistan close by aggravates these challenges

        bull Plans for close circuit cameras at all major bridges tunnels and railway stations have been made Lighting is provided on all major bridges and inside tunnels

        Project Sub sectionsbull Jammu-Udhampur Rail Link Project (53 km) ndash Leg 0

        ndash sub-mountainous region ndash It is 53 km long and has 10 km length of tunnels 36 major bridges and 122 minor bridgesndash his stretch has already been completed and commissioned in April 2005ndash The completion cost of this stretch is Rs 522 crore

        bull Udhampur-Srinagar-Baramulla Rail Link (USBRL) Project (202 km)

        ndash Leg-1 ndash Udhampur-Katra section (25 km )bull involves about 109 km of tunneling Nine major bridges 29 minor bridges and 10

        ROBRUBs in addition to about 3886 lac cum of earthworkbull approximate cost of this stretch is Rs 640 cr bull tallest bridge in this section is 90 m high (Br No 20) and the longest tunnel (T-80) is

        315 km long

        Project Sub sectionsbull Leg-2 ndash Katra-Quazigund (148 km)

        ndash toughest sector ever been constructed on the Indian Railwaysndash full of tunnels and bridgesviaducts Terrain in this region is full of poor geology and

        faults ndash On this section a bridge is being constructed across river Chenab which will have an

        arched span of 465 m and a total length of the bridge is around 13 km This will be about 359 m above the bed level of the river

        ndash The stretch between river Chenab and Banihal is through a virgin territory and requires construction of approximately 300 km of access roads of which about 110 km has already been constructed

        ndash At Quazigund end of this stretch the longest tunnel on Indian Railways is being constructed (Pir Panjal Tunnel) This tunnel is 1095 km long and will pierce through the Pir Panjal range below the snow line

        bull Leg 3-Quazigund-Baramulla (119 km)

        ndash falls in the Kashmir Valley which is a natural bowl surrounded by the mountain rangesndash there are no tunnels heavy bridging is required across rivers canals and roadsndash 64 major bridges and 640 minor bridges in this sectionndash completed in October 2009

        Rolling Stockbull Freight services conveying grain and petroleum products will run

        in between 10- 12 passengers services that are planned to operate daily

        bull An eight-coach DEMU will run on the Quazigund-Baramulla section of line Each coach will carry 90 passengers It will run twice a day in both directions

        bull The train has been fixed with a snow cutter system for clearing snow on the track The temperature in coaches can also be maintained at 20degC during winter

        bull Passenger services will be provided by the new aerodynamic High Power diesel multiple units with special features

        Rolling Stock (contdhellip)bull The air-conditioned coaches have wide windows for a panoramic view

        anti-skid flooring sliding doorways heating facilities an attractive colour scheme and executive class reclining seats inside

        bull The drivers cabin has a heating and defogging unit to take care of cold climatic conditions and is fitted with single lookout glass windows to give a wider view

        bull A snow-cutting type cattle guard has been attached at the driving end of the train for clearing snow from the tracks during winter In view of the peculiar climate of the valley the 1400-horsepower diesel engine for the train has been provided with a heating system for a quick and trouble-free start in the winters A public information system with display and announcement facilities are included in the coaches which have pneumatic suspension for better riding comfort There is also a compartment for physically challenged people with wider doors

        bull Maintenance of all rolling stock and locomotives will be at the newly built Budgam workshop just north of Srinagar

        Responsibilitybull Indian Railways is in charge of the Udhampur-Katra Section (25 km)

        bull Konkan Railway Corporation Limited is in charge of the Katra-Laole Section (90 km) This is arguably the toughest portion of the railway with over 92 of the line either inside a tunnel or on a bridge The bridges comprise of 12 km the tunnels of 72 km and only a minuscule part of this tortuous stretch ie 6 km is on normal ground

        bull IRCON a Public Sector railway construction company is in charge of the Laole-Baramulla Section (175 km) Another tough but less brutal section

        bull HCC has won the tender to construct both the North and South Section of the 11 km Banihal tunnel across the Pir Panjal range for approx US$120 million Work is completed

        bull AFCONS with Ultra Engineering (South Korea) will design and construct the Chenab Bridge for US$130 million

        bull Gammon India with Archirodon Construction (South Africa) will build the Anji Khad Bridge for US$100 million

        Financials

        bull Till April 2011 7165 crore had already been spent While the budget for last year was 1000 crore it has been marginally raised to 1100 crore for current fiscal

        bull Delay in the completion of the project led to an increase in the cost of requiring additional funds The Indian Government previously increased the projected cost of the railway line in 2007 upping the initial estimate of Rs307bn ($5693m) to Rs112bn ($21bn)

        bull The Indian Government has cleared a proposal to earmark Rs190bn ($35bn) of additional funds (Jan 2012)

        Infrastructure and constructionbull Total of over 750 bridges and over 100

        kilometres (62 mi) of tunnels the longest of which is about 11 kilometres (68 mi) in length

        bull The greatest engineering challenges involve the crossing of the Chenab river which involves building a 1315-metre-long (4314 ft) bridge 359 metres (1178 ft) above the river bed and the crossing of the Anji Khad which involves building a 657-metre-long (2156 ft) bridge 186 metres (610 ft) above the river bed

        Pir Panjal Tunnel(T-80)

        Pir Panjal Tunnel(T-80)bull At 1096km long the Pir Panjal Railway Tunnel is Indias longest and Asias 2nd

        longest tunnel

        bull passes through the Pir Panjal mountain range in Jammu and Kashmir in India

        bull aimed at reducing the travel distance between Quazigund and Banihal to only 11 km

        bull cover the distance from the south to the north side of the mountain in 66 minutes

        bull Completed in October 2011

        bull cost of Rs10bn ($2018m)

        bull Construction of the tunnel was carried out by Hindustan Construction Company and took over six years

        Pir Panjal Tunnel(T-80)bull 84m-wide and 73m-high tunnel and is up to 1 100 m below the surface

        bull construction of a 3m-wide road that runs alongside the railway tunnel for maintenance and emergency evacuation

        bull 100 percent water-proof and is also equipped with fire fighting system throughout its entire length

        bull construction of the tunnel started in November 2005 and was complete in 2011

        bull The fascinating fact about the tunnel excavation is that the total excavated quantity was equal to one mountain

        bull It runs 440m below the existing Jawahar Tunnel which is the only road link from the region to the rest of India meant for vehicular traffic only- which usually gets blocked during winters owing to heavy snowfall in the region

        bull due to the changing geological strata of the young Himalayan rock New Australian Tunneling Methodology (NATM) was adopted for the construction

        Chenab Bridgebull The Chenab Bridge will be the highest railway structure of its kind in the world

        35 m higher than the tip of the Eiffel Tower in Paris

        bull The Chenab bridge is 13 km long and has the third largest arch span in the world At 1178 feet it will be the highest bridge in the world once completed

        bull Located near the Salal Hydro Power Dam the bridge was originally planned as a 1315 metre-long bridge having 17 spans

        bull Afcons Infrastructure Limited was awarded the contract for the bridge

        bull While deciding to stop all construction works on the Katra-Qazigund section in 2008 the Railway Ministry had proposed a change in the location of the bridge from the gorge to a wide valley two to three kilometers upstream of the original location Since the newly proposed location had a higher bed level the height of the bridge had it been constructed there would have come down to about 120-150 meters from river bed

        bull The Railways decided to stick to the location it had originally chosen to construct the Chenab Bridge mdash billed as the highest in the world at a height of 359 metres from the river bed At 343 metres Millau Viaduct in France is the tallest bridge in the world

        Operational Accidents amp Casualitiesbull June 2004 mdash Sudhir Kumar Pundir an IRCON Engineer and his brother Sanjay

        were kidnapped and murdered by terrorists in the valley

        bull June 2005 mdash Altaf Hussain A laborer working in a Tunnel at Tathyar (HCC) was killed by a collapse Two others were injured

        bull May 16 2007 mdashdaughter of Mushtaq Ahmad Wagay and daughter of Mohammad Ayub Wani (9 amp 7 yrs)drowned in a ditch constructed by Railway Company

        bull Feb 14 2008 mdash A Nepali labourer Tika Ram Balwari son of Tuya Narayan was killed after a boulder hit him in at Uri Varmul presumably on the Kashmir rail project for HCC

        bull Apr 18 2008 mdash Six labourers of a private company engaged with the Katra-Qazigund railway line project were killed and two others received injuries when a tipper carrying them rolled down into a deep gorge in Lower Juda Morh near Kouri in Reasi district late at night

        bull Mar 27 2011 mdash Two workers were killed at an under-construction railway bridge over the Chenab in Reasi district as a basket attached to a crane carrying them unhooked and fell from a height of more than 100 metres

        Current Status

        bull The USBRL project is divided into four sections

        bull Leg 0 extending 53 kilometres (33 mi) from Jammu to Udhampur completed in April 2005

        bull Leg 1 extending 25 kilometres (16 mi) from Udhampur to Katra Under construction may open in 2013

        bull Leg 2 extending 148 kilometres (92 mi) from Katra to Qazigund Under construction may open in 2017

        bull Leg 3 extending 119 kilometres (74 mi) from Qazigund to Baramulla completed in October 2009

        Inauguration of Kashmir rail linkDate Section Length km

        April 2005 Jammu - Udhampur Current Status

        53

        October 2008 Anantnag - Mazhom 66

        February 2009 Mazhom - Baramulla 35

        October 2009 Quazigund - Anantnag 18

        Delayed owing to construction difficulties

        Udhampur - Quazigund 167

        Inauguration of Final section KVRbull Prime Minister Dr Manmohan

        Singh flagged off a train from Anantnag to Quazigund to inaugurate the final 18 km of the railway through the Kashmir Valley on October 28 2009

        bull The currently isolated line will eventually be joined to the Indian rail network at Udhampur providing an all -weather transport link between the state of Jammu amp Kashmir and the rest of India which has been designated as a national priority

        Thanks

        • Kashmir Rail Project Challenges solutions and current status
        • Kashmir Railway Project (KRP)
        • Project Details
        • Slide 4
        • Challenges
        • Slide 6
        • Slide 7
        • Security Challenges
        • Project Sub sections
        • Slide 10
        • Rolling Stock
        • Rolling Stock (contdhellip)
        • Responsibility
        • Financials
        • Infrastructure and construction
        • Pir Panjal Tunnel(T-80)
        • Slide 17
        • Slide 18
        • Slide 19
        • Chenab Bridge
        • Slide 21
        • Operational Accidents amp Casualities
        • Slide 23
        • Current Status
        • Slide 25
        • Inauguration of Final section KVR
        • Thanks

          Challenges

          bull 345km route crosses major earthquake zones and is subjected to extreme temperatures of cold and heat as well as inhospitable terrain

          bull Extreme winters with heavy snowfalls

          bull Kashmir is an electricity scarce region at present

          bull Young Himalayas where geology is poor and changes occur frequently

          Challengesbull Katra-Quazigund leg is the most difficult stretch of this project

          In this leg Salal to Quazigund stretch lies in the territory where virtually no habitation road or tracking path existed

          bull In Katra-Quazigund a significant part of the project lies in tunnels with the longest being about 1096 km

          bull There will be several bridges The tallest bridge is about 359 m above bed level and is over 13 km in length over river Chenab

          bull Water ingress problems have been seen in the Udhampur to Katra section This has required some drastic solutions using steel arches and several feet of shotcrete

          Security Challenges

          bull the regions the line passes through are continuing to face terrorist challenges

          bull The train will pass through some of the most vulnerable areas in the Valley such as Budgam Pulwama Srinagar and Anantnag districts to which militants have clear and easy access in the absence of security

          bull The presence of the international border with Pakistan close by aggravates these challenges

          bull Plans for close circuit cameras at all major bridges tunnels and railway stations have been made Lighting is provided on all major bridges and inside tunnels

          Project Sub sectionsbull Jammu-Udhampur Rail Link Project (53 km) ndash Leg 0

          ndash sub-mountainous region ndash It is 53 km long and has 10 km length of tunnels 36 major bridges and 122 minor bridgesndash his stretch has already been completed and commissioned in April 2005ndash The completion cost of this stretch is Rs 522 crore

          bull Udhampur-Srinagar-Baramulla Rail Link (USBRL) Project (202 km)

          ndash Leg-1 ndash Udhampur-Katra section (25 km )bull involves about 109 km of tunneling Nine major bridges 29 minor bridges and 10

          ROBRUBs in addition to about 3886 lac cum of earthworkbull approximate cost of this stretch is Rs 640 cr bull tallest bridge in this section is 90 m high (Br No 20) and the longest tunnel (T-80) is

          315 km long

          Project Sub sectionsbull Leg-2 ndash Katra-Quazigund (148 km)

          ndash toughest sector ever been constructed on the Indian Railwaysndash full of tunnels and bridgesviaducts Terrain in this region is full of poor geology and

          faults ndash On this section a bridge is being constructed across river Chenab which will have an

          arched span of 465 m and a total length of the bridge is around 13 km This will be about 359 m above the bed level of the river

          ndash The stretch between river Chenab and Banihal is through a virgin territory and requires construction of approximately 300 km of access roads of which about 110 km has already been constructed

          ndash At Quazigund end of this stretch the longest tunnel on Indian Railways is being constructed (Pir Panjal Tunnel) This tunnel is 1095 km long and will pierce through the Pir Panjal range below the snow line

          bull Leg 3-Quazigund-Baramulla (119 km)

          ndash falls in the Kashmir Valley which is a natural bowl surrounded by the mountain rangesndash there are no tunnels heavy bridging is required across rivers canals and roadsndash 64 major bridges and 640 minor bridges in this sectionndash completed in October 2009

          Rolling Stockbull Freight services conveying grain and petroleum products will run

          in between 10- 12 passengers services that are planned to operate daily

          bull An eight-coach DEMU will run on the Quazigund-Baramulla section of line Each coach will carry 90 passengers It will run twice a day in both directions

          bull The train has been fixed with a snow cutter system for clearing snow on the track The temperature in coaches can also be maintained at 20degC during winter

          bull Passenger services will be provided by the new aerodynamic High Power diesel multiple units with special features

          Rolling Stock (contdhellip)bull The air-conditioned coaches have wide windows for a panoramic view

          anti-skid flooring sliding doorways heating facilities an attractive colour scheme and executive class reclining seats inside

          bull The drivers cabin has a heating and defogging unit to take care of cold climatic conditions and is fitted with single lookout glass windows to give a wider view

          bull A snow-cutting type cattle guard has been attached at the driving end of the train for clearing snow from the tracks during winter In view of the peculiar climate of the valley the 1400-horsepower diesel engine for the train has been provided with a heating system for a quick and trouble-free start in the winters A public information system with display and announcement facilities are included in the coaches which have pneumatic suspension for better riding comfort There is also a compartment for physically challenged people with wider doors

          bull Maintenance of all rolling stock and locomotives will be at the newly built Budgam workshop just north of Srinagar

          Responsibilitybull Indian Railways is in charge of the Udhampur-Katra Section (25 km)

          bull Konkan Railway Corporation Limited is in charge of the Katra-Laole Section (90 km) This is arguably the toughest portion of the railway with over 92 of the line either inside a tunnel or on a bridge The bridges comprise of 12 km the tunnels of 72 km and only a minuscule part of this tortuous stretch ie 6 km is on normal ground

          bull IRCON a Public Sector railway construction company is in charge of the Laole-Baramulla Section (175 km) Another tough but less brutal section

          bull HCC has won the tender to construct both the North and South Section of the 11 km Banihal tunnel across the Pir Panjal range for approx US$120 million Work is completed

          bull AFCONS with Ultra Engineering (South Korea) will design and construct the Chenab Bridge for US$130 million

          bull Gammon India with Archirodon Construction (South Africa) will build the Anji Khad Bridge for US$100 million

          Financials

          bull Till April 2011 7165 crore had already been spent While the budget for last year was 1000 crore it has been marginally raised to 1100 crore for current fiscal

          bull Delay in the completion of the project led to an increase in the cost of requiring additional funds The Indian Government previously increased the projected cost of the railway line in 2007 upping the initial estimate of Rs307bn ($5693m) to Rs112bn ($21bn)

          bull The Indian Government has cleared a proposal to earmark Rs190bn ($35bn) of additional funds (Jan 2012)

          Infrastructure and constructionbull Total of over 750 bridges and over 100

          kilometres (62 mi) of tunnels the longest of which is about 11 kilometres (68 mi) in length

          bull The greatest engineering challenges involve the crossing of the Chenab river which involves building a 1315-metre-long (4314 ft) bridge 359 metres (1178 ft) above the river bed and the crossing of the Anji Khad which involves building a 657-metre-long (2156 ft) bridge 186 metres (610 ft) above the river bed

          Pir Panjal Tunnel(T-80)

          Pir Panjal Tunnel(T-80)bull At 1096km long the Pir Panjal Railway Tunnel is Indias longest and Asias 2nd

          longest tunnel

          bull passes through the Pir Panjal mountain range in Jammu and Kashmir in India

          bull aimed at reducing the travel distance between Quazigund and Banihal to only 11 km

          bull cover the distance from the south to the north side of the mountain in 66 minutes

          bull Completed in October 2011

          bull cost of Rs10bn ($2018m)

          bull Construction of the tunnel was carried out by Hindustan Construction Company and took over six years

          Pir Panjal Tunnel(T-80)bull 84m-wide and 73m-high tunnel and is up to 1 100 m below the surface

          bull construction of a 3m-wide road that runs alongside the railway tunnel for maintenance and emergency evacuation

          bull 100 percent water-proof and is also equipped with fire fighting system throughout its entire length

          bull construction of the tunnel started in November 2005 and was complete in 2011

          bull The fascinating fact about the tunnel excavation is that the total excavated quantity was equal to one mountain

          bull It runs 440m below the existing Jawahar Tunnel which is the only road link from the region to the rest of India meant for vehicular traffic only- which usually gets blocked during winters owing to heavy snowfall in the region

          bull due to the changing geological strata of the young Himalayan rock New Australian Tunneling Methodology (NATM) was adopted for the construction

          Chenab Bridgebull The Chenab Bridge will be the highest railway structure of its kind in the world

          35 m higher than the tip of the Eiffel Tower in Paris

          bull The Chenab bridge is 13 km long and has the third largest arch span in the world At 1178 feet it will be the highest bridge in the world once completed

          bull Located near the Salal Hydro Power Dam the bridge was originally planned as a 1315 metre-long bridge having 17 spans

          bull Afcons Infrastructure Limited was awarded the contract for the bridge

          bull While deciding to stop all construction works on the Katra-Qazigund section in 2008 the Railway Ministry had proposed a change in the location of the bridge from the gorge to a wide valley two to three kilometers upstream of the original location Since the newly proposed location had a higher bed level the height of the bridge had it been constructed there would have come down to about 120-150 meters from river bed

          bull The Railways decided to stick to the location it had originally chosen to construct the Chenab Bridge mdash billed as the highest in the world at a height of 359 metres from the river bed At 343 metres Millau Viaduct in France is the tallest bridge in the world

          Operational Accidents amp Casualitiesbull June 2004 mdash Sudhir Kumar Pundir an IRCON Engineer and his brother Sanjay

          were kidnapped and murdered by terrorists in the valley

          bull June 2005 mdash Altaf Hussain A laborer working in a Tunnel at Tathyar (HCC) was killed by a collapse Two others were injured

          bull May 16 2007 mdashdaughter of Mushtaq Ahmad Wagay and daughter of Mohammad Ayub Wani (9 amp 7 yrs)drowned in a ditch constructed by Railway Company

          bull Feb 14 2008 mdash A Nepali labourer Tika Ram Balwari son of Tuya Narayan was killed after a boulder hit him in at Uri Varmul presumably on the Kashmir rail project for HCC

          bull Apr 18 2008 mdash Six labourers of a private company engaged with the Katra-Qazigund railway line project were killed and two others received injuries when a tipper carrying them rolled down into a deep gorge in Lower Juda Morh near Kouri in Reasi district late at night

          bull Mar 27 2011 mdash Two workers were killed at an under-construction railway bridge over the Chenab in Reasi district as a basket attached to a crane carrying them unhooked and fell from a height of more than 100 metres

          Current Status

          bull The USBRL project is divided into four sections

          bull Leg 0 extending 53 kilometres (33 mi) from Jammu to Udhampur completed in April 2005

          bull Leg 1 extending 25 kilometres (16 mi) from Udhampur to Katra Under construction may open in 2013

          bull Leg 2 extending 148 kilometres (92 mi) from Katra to Qazigund Under construction may open in 2017

          bull Leg 3 extending 119 kilometres (74 mi) from Qazigund to Baramulla completed in October 2009

          Inauguration of Kashmir rail linkDate Section Length km

          April 2005 Jammu - Udhampur Current Status

          53

          October 2008 Anantnag - Mazhom 66

          February 2009 Mazhom - Baramulla 35

          October 2009 Quazigund - Anantnag 18

          Delayed owing to construction difficulties

          Udhampur - Quazigund 167

          Inauguration of Final section KVRbull Prime Minister Dr Manmohan

          Singh flagged off a train from Anantnag to Quazigund to inaugurate the final 18 km of the railway through the Kashmir Valley on October 28 2009

          bull The currently isolated line will eventually be joined to the Indian rail network at Udhampur providing an all -weather transport link between the state of Jammu amp Kashmir and the rest of India which has been designated as a national priority

          Thanks

          • Kashmir Rail Project Challenges solutions and current status
          • Kashmir Railway Project (KRP)
          • Project Details
          • Slide 4
          • Challenges
          • Slide 6
          • Slide 7
          • Security Challenges
          • Project Sub sections
          • Slide 10
          • Rolling Stock
          • Rolling Stock (contdhellip)
          • Responsibility
          • Financials
          • Infrastructure and construction
          • Pir Panjal Tunnel(T-80)
          • Slide 17
          • Slide 18
          • Slide 19
          • Chenab Bridge
          • Slide 21
          • Operational Accidents amp Casualities
          • Slide 23
          • Current Status
          • Slide 25
          • Inauguration of Final section KVR
          • Thanks

            Challengesbull Katra-Quazigund leg is the most difficult stretch of this project

            In this leg Salal to Quazigund stretch lies in the territory where virtually no habitation road or tracking path existed

            bull In Katra-Quazigund a significant part of the project lies in tunnels with the longest being about 1096 km

            bull There will be several bridges The tallest bridge is about 359 m above bed level and is over 13 km in length over river Chenab

            bull Water ingress problems have been seen in the Udhampur to Katra section This has required some drastic solutions using steel arches and several feet of shotcrete

            Security Challenges

            bull the regions the line passes through are continuing to face terrorist challenges

            bull The train will pass through some of the most vulnerable areas in the Valley such as Budgam Pulwama Srinagar and Anantnag districts to which militants have clear and easy access in the absence of security

            bull The presence of the international border with Pakistan close by aggravates these challenges

            bull Plans for close circuit cameras at all major bridges tunnels and railway stations have been made Lighting is provided on all major bridges and inside tunnels

            Project Sub sectionsbull Jammu-Udhampur Rail Link Project (53 km) ndash Leg 0

            ndash sub-mountainous region ndash It is 53 km long and has 10 km length of tunnels 36 major bridges and 122 minor bridgesndash his stretch has already been completed and commissioned in April 2005ndash The completion cost of this stretch is Rs 522 crore

            bull Udhampur-Srinagar-Baramulla Rail Link (USBRL) Project (202 km)

            ndash Leg-1 ndash Udhampur-Katra section (25 km )bull involves about 109 km of tunneling Nine major bridges 29 minor bridges and 10

            ROBRUBs in addition to about 3886 lac cum of earthworkbull approximate cost of this stretch is Rs 640 cr bull tallest bridge in this section is 90 m high (Br No 20) and the longest tunnel (T-80) is

            315 km long

            Project Sub sectionsbull Leg-2 ndash Katra-Quazigund (148 km)

            ndash toughest sector ever been constructed on the Indian Railwaysndash full of tunnels and bridgesviaducts Terrain in this region is full of poor geology and

            faults ndash On this section a bridge is being constructed across river Chenab which will have an

            arched span of 465 m and a total length of the bridge is around 13 km This will be about 359 m above the bed level of the river

            ndash The stretch between river Chenab and Banihal is through a virgin territory and requires construction of approximately 300 km of access roads of which about 110 km has already been constructed

            ndash At Quazigund end of this stretch the longest tunnel on Indian Railways is being constructed (Pir Panjal Tunnel) This tunnel is 1095 km long and will pierce through the Pir Panjal range below the snow line

            bull Leg 3-Quazigund-Baramulla (119 km)

            ndash falls in the Kashmir Valley which is a natural bowl surrounded by the mountain rangesndash there are no tunnels heavy bridging is required across rivers canals and roadsndash 64 major bridges and 640 minor bridges in this sectionndash completed in October 2009

            Rolling Stockbull Freight services conveying grain and petroleum products will run

            in between 10- 12 passengers services that are planned to operate daily

            bull An eight-coach DEMU will run on the Quazigund-Baramulla section of line Each coach will carry 90 passengers It will run twice a day in both directions

            bull The train has been fixed with a snow cutter system for clearing snow on the track The temperature in coaches can also be maintained at 20degC during winter

            bull Passenger services will be provided by the new aerodynamic High Power diesel multiple units with special features

            Rolling Stock (contdhellip)bull The air-conditioned coaches have wide windows for a panoramic view

            anti-skid flooring sliding doorways heating facilities an attractive colour scheme and executive class reclining seats inside

            bull The drivers cabin has a heating and defogging unit to take care of cold climatic conditions and is fitted with single lookout glass windows to give a wider view

            bull A snow-cutting type cattle guard has been attached at the driving end of the train for clearing snow from the tracks during winter In view of the peculiar climate of the valley the 1400-horsepower diesel engine for the train has been provided with a heating system for a quick and trouble-free start in the winters A public information system with display and announcement facilities are included in the coaches which have pneumatic suspension for better riding comfort There is also a compartment for physically challenged people with wider doors

            bull Maintenance of all rolling stock and locomotives will be at the newly built Budgam workshop just north of Srinagar

            Responsibilitybull Indian Railways is in charge of the Udhampur-Katra Section (25 km)

            bull Konkan Railway Corporation Limited is in charge of the Katra-Laole Section (90 km) This is arguably the toughest portion of the railway with over 92 of the line either inside a tunnel or on a bridge The bridges comprise of 12 km the tunnels of 72 km and only a minuscule part of this tortuous stretch ie 6 km is on normal ground

            bull IRCON a Public Sector railway construction company is in charge of the Laole-Baramulla Section (175 km) Another tough but less brutal section

            bull HCC has won the tender to construct both the North and South Section of the 11 km Banihal tunnel across the Pir Panjal range for approx US$120 million Work is completed

            bull AFCONS with Ultra Engineering (South Korea) will design and construct the Chenab Bridge for US$130 million

            bull Gammon India with Archirodon Construction (South Africa) will build the Anji Khad Bridge for US$100 million

            Financials

            bull Till April 2011 7165 crore had already been spent While the budget for last year was 1000 crore it has been marginally raised to 1100 crore for current fiscal

            bull Delay in the completion of the project led to an increase in the cost of requiring additional funds The Indian Government previously increased the projected cost of the railway line in 2007 upping the initial estimate of Rs307bn ($5693m) to Rs112bn ($21bn)

            bull The Indian Government has cleared a proposal to earmark Rs190bn ($35bn) of additional funds (Jan 2012)

            Infrastructure and constructionbull Total of over 750 bridges and over 100

            kilometres (62 mi) of tunnels the longest of which is about 11 kilometres (68 mi) in length

            bull The greatest engineering challenges involve the crossing of the Chenab river which involves building a 1315-metre-long (4314 ft) bridge 359 metres (1178 ft) above the river bed and the crossing of the Anji Khad which involves building a 657-metre-long (2156 ft) bridge 186 metres (610 ft) above the river bed

            Pir Panjal Tunnel(T-80)

            Pir Panjal Tunnel(T-80)bull At 1096km long the Pir Panjal Railway Tunnel is Indias longest and Asias 2nd

            longest tunnel

            bull passes through the Pir Panjal mountain range in Jammu and Kashmir in India

            bull aimed at reducing the travel distance between Quazigund and Banihal to only 11 km

            bull cover the distance from the south to the north side of the mountain in 66 minutes

            bull Completed in October 2011

            bull cost of Rs10bn ($2018m)

            bull Construction of the tunnel was carried out by Hindustan Construction Company and took over six years

            Pir Panjal Tunnel(T-80)bull 84m-wide and 73m-high tunnel and is up to 1 100 m below the surface

            bull construction of a 3m-wide road that runs alongside the railway tunnel for maintenance and emergency evacuation

            bull 100 percent water-proof and is also equipped with fire fighting system throughout its entire length

            bull construction of the tunnel started in November 2005 and was complete in 2011

            bull The fascinating fact about the tunnel excavation is that the total excavated quantity was equal to one mountain

            bull It runs 440m below the existing Jawahar Tunnel which is the only road link from the region to the rest of India meant for vehicular traffic only- which usually gets blocked during winters owing to heavy snowfall in the region

            bull due to the changing geological strata of the young Himalayan rock New Australian Tunneling Methodology (NATM) was adopted for the construction

            Chenab Bridgebull The Chenab Bridge will be the highest railway structure of its kind in the world

            35 m higher than the tip of the Eiffel Tower in Paris

            bull The Chenab bridge is 13 km long and has the third largest arch span in the world At 1178 feet it will be the highest bridge in the world once completed

            bull Located near the Salal Hydro Power Dam the bridge was originally planned as a 1315 metre-long bridge having 17 spans

            bull Afcons Infrastructure Limited was awarded the contract for the bridge

            bull While deciding to stop all construction works on the Katra-Qazigund section in 2008 the Railway Ministry had proposed a change in the location of the bridge from the gorge to a wide valley two to three kilometers upstream of the original location Since the newly proposed location had a higher bed level the height of the bridge had it been constructed there would have come down to about 120-150 meters from river bed

            bull The Railways decided to stick to the location it had originally chosen to construct the Chenab Bridge mdash billed as the highest in the world at a height of 359 metres from the river bed At 343 metres Millau Viaduct in France is the tallest bridge in the world

            Operational Accidents amp Casualitiesbull June 2004 mdash Sudhir Kumar Pundir an IRCON Engineer and his brother Sanjay

            were kidnapped and murdered by terrorists in the valley

            bull June 2005 mdash Altaf Hussain A laborer working in a Tunnel at Tathyar (HCC) was killed by a collapse Two others were injured

            bull May 16 2007 mdashdaughter of Mushtaq Ahmad Wagay and daughter of Mohammad Ayub Wani (9 amp 7 yrs)drowned in a ditch constructed by Railway Company

            bull Feb 14 2008 mdash A Nepali labourer Tika Ram Balwari son of Tuya Narayan was killed after a boulder hit him in at Uri Varmul presumably on the Kashmir rail project for HCC

            bull Apr 18 2008 mdash Six labourers of a private company engaged with the Katra-Qazigund railway line project were killed and two others received injuries when a tipper carrying them rolled down into a deep gorge in Lower Juda Morh near Kouri in Reasi district late at night

            bull Mar 27 2011 mdash Two workers were killed at an under-construction railway bridge over the Chenab in Reasi district as a basket attached to a crane carrying them unhooked and fell from a height of more than 100 metres

            Current Status

            bull The USBRL project is divided into four sections

            bull Leg 0 extending 53 kilometres (33 mi) from Jammu to Udhampur completed in April 2005

            bull Leg 1 extending 25 kilometres (16 mi) from Udhampur to Katra Under construction may open in 2013

            bull Leg 2 extending 148 kilometres (92 mi) from Katra to Qazigund Under construction may open in 2017

            bull Leg 3 extending 119 kilometres (74 mi) from Qazigund to Baramulla completed in October 2009

            Inauguration of Kashmir rail linkDate Section Length km

            April 2005 Jammu - Udhampur Current Status

            53

            October 2008 Anantnag - Mazhom 66

            February 2009 Mazhom - Baramulla 35

            October 2009 Quazigund - Anantnag 18

            Delayed owing to construction difficulties

            Udhampur - Quazigund 167

            Inauguration of Final section KVRbull Prime Minister Dr Manmohan

            Singh flagged off a train from Anantnag to Quazigund to inaugurate the final 18 km of the railway through the Kashmir Valley on October 28 2009

            bull The currently isolated line will eventually be joined to the Indian rail network at Udhampur providing an all -weather transport link between the state of Jammu amp Kashmir and the rest of India which has been designated as a national priority

            Thanks

            • Kashmir Rail Project Challenges solutions and current status
            • Kashmir Railway Project (KRP)
            • Project Details
            • Slide 4
            • Challenges
            • Slide 6
            • Slide 7
            • Security Challenges
            • Project Sub sections
            • Slide 10
            • Rolling Stock
            • Rolling Stock (contdhellip)
            • Responsibility
            • Financials
            • Infrastructure and construction
            • Pir Panjal Tunnel(T-80)
            • Slide 17
            • Slide 18
            • Slide 19
            • Chenab Bridge
            • Slide 21
            • Operational Accidents amp Casualities
            • Slide 23
            • Current Status
            • Slide 25
            • Inauguration of Final section KVR
            • Thanks

              Security Challenges

              bull the regions the line passes through are continuing to face terrorist challenges

              bull The train will pass through some of the most vulnerable areas in the Valley such as Budgam Pulwama Srinagar and Anantnag districts to which militants have clear and easy access in the absence of security

              bull The presence of the international border with Pakistan close by aggravates these challenges

              bull Plans for close circuit cameras at all major bridges tunnels and railway stations have been made Lighting is provided on all major bridges and inside tunnels

              Project Sub sectionsbull Jammu-Udhampur Rail Link Project (53 km) ndash Leg 0

              ndash sub-mountainous region ndash It is 53 km long and has 10 km length of tunnels 36 major bridges and 122 minor bridgesndash his stretch has already been completed and commissioned in April 2005ndash The completion cost of this stretch is Rs 522 crore

              bull Udhampur-Srinagar-Baramulla Rail Link (USBRL) Project (202 km)

              ndash Leg-1 ndash Udhampur-Katra section (25 km )bull involves about 109 km of tunneling Nine major bridges 29 minor bridges and 10

              ROBRUBs in addition to about 3886 lac cum of earthworkbull approximate cost of this stretch is Rs 640 cr bull tallest bridge in this section is 90 m high (Br No 20) and the longest tunnel (T-80) is

              315 km long

              Project Sub sectionsbull Leg-2 ndash Katra-Quazigund (148 km)

              ndash toughest sector ever been constructed on the Indian Railwaysndash full of tunnels and bridgesviaducts Terrain in this region is full of poor geology and

              faults ndash On this section a bridge is being constructed across river Chenab which will have an

              arched span of 465 m and a total length of the bridge is around 13 km This will be about 359 m above the bed level of the river

              ndash The stretch between river Chenab and Banihal is through a virgin territory and requires construction of approximately 300 km of access roads of which about 110 km has already been constructed

              ndash At Quazigund end of this stretch the longest tunnel on Indian Railways is being constructed (Pir Panjal Tunnel) This tunnel is 1095 km long and will pierce through the Pir Panjal range below the snow line

              bull Leg 3-Quazigund-Baramulla (119 km)

              ndash falls in the Kashmir Valley which is a natural bowl surrounded by the mountain rangesndash there are no tunnels heavy bridging is required across rivers canals and roadsndash 64 major bridges and 640 minor bridges in this sectionndash completed in October 2009

              Rolling Stockbull Freight services conveying grain and petroleum products will run

              in between 10- 12 passengers services that are planned to operate daily

              bull An eight-coach DEMU will run on the Quazigund-Baramulla section of line Each coach will carry 90 passengers It will run twice a day in both directions

              bull The train has been fixed with a snow cutter system for clearing snow on the track The temperature in coaches can also be maintained at 20degC during winter

              bull Passenger services will be provided by the new aerodynamic High Power diesel multiple units with special features

              Rolling Stock (contdhellip)bull The air-conditioned coaches have wide windows for a panoramic view

              anti-skid flooring sliding doorways heating facilities an attractive colour scheme and executive class reclining seats inside

              bull The drivers cabin has a heating and defogging unit to take care of cold climatic conditions and is fitted with single lookout glass windows to give a wider view

              bull A snow-cutting type cattle guard has been attached at the driving end of the train for clearing snow from the tracks during winter In view of the peculiar climate of the valley the 1400-horsepower diesel engine for the train has been provided with a heating system for a quick and trouble-free start in the winters A public information system with display and announcement facilities are included in the coaches which have pneumatic suspension for better riding comfort There is also a compartment for physically challenged people with wider doors

              bull Maintenance of all rolling stock and locomotives will be at the newly built Budgam workshop just north of Srinagar

              Responsibilitybull Indian Railways is in charge of the Udhampur-Katra Section (25 km)

              bull Konkan Railway Corporation Limited is in charge of the Katra-Laole Section (90 km) This is arguably the toughest portion of the railway with over 92 of the line either inside a tunnel or on a bridge The bridges comprise of 12 km the tunnels of 72 km and only a minuscule part of this tortuous stretch ie 6 km is on normal ground

              bull IRCON a Public Sector railway construction company is in charge of the Laole-Baramulla Section (175 km) Another tough but less brutal section

              bull HCC has won the tender to construct both the North and South Section of the 11 km Banihal tunnel across the Pir Panjal range for approx US$120 million Work is completed

              bull AFCONS with Ultra Engineering (South Korea) will design and construct the Chenab Bridge for US$130 million

              bull Gammon India with Archirodon Construction (South Africa) will build the Anji Khad Bridge for US$100 million

              Financials

              bull Till April 2011 7165 crore had already been spent While the budget for last year was 1000 crore it has been marginally raised to 1100 crore for current fiscal

              bull Delay in the completion of the project led to an increase in the cost of requiring additional funds The Indian Government previously increased the projected cost of the railway line in 2007 upping the initial estimate of Rs307bn ($5693m) to Rs112bn ($21bn)

              bull The Indian Government has cleared a proposal to earmark Rs190bn ($35bn) of additional funds (Jan 2012)

              Infrastructure and constructionbull Total of over 750 bridges and over 100

              kilometres (62 mi) of tunnels the longest of which is about 11 kilometres (68 mi) in length

              bull The greatest engineering challenges involve the crossing of the Chenab river which involves building a 1315-metre-long (4314 ft) bridge 359 metres (1178 ft) above the river bed and the crossing of the Anji Khad which involves building a 657-metre-long (2156 ft) bridge 186 metres (610 ft) above the river bed

              Pir Panjal Tunnel(T-80)

              Pir Panjal Tunnel(T-80)bull At 1096km long the Pir Panjal Railway Tunnel is Indias longest and Asias 2nd

              longest tunnel

              bull passes through the Pir Panjal mountain range in Jammu and Kashmir in India

              bull aimed at reducing the travel distance between Quazigund and Banihal to only 11 km

              bull cover the distance from the south to the north side of the mountain in 66 minutes

              bull Completed in October 2011

              bull cost of Rs10bn ($2018m)

              bull Construction of the tunnel was carried out by Hindustan Construction Company and took over six years

              Pir Panjal Tunnel(T-80)bull 84m-wide and 73m-high tunnel and is up to 1 100 m below the surface

              bull construction of a 3m-wide road that runs alongside the railway tunnel for maintenance and emergency evacuation

              bull 100 percent water-proof and is also equipped with fire fighting system throughout its entire length

              bull construction of the tunnel started in November 2005 and was complete in 2011

              bull The fascinating fact about the tunnel excavation is that the total excavated quantity was equal to one mountain

              bull It runs 440m below the existing Jawahar Tunnel which is the only road link from the region to the rest of India meant for vehicular traffic only- which usually gets blocked during winters owing to heavy snowfall in the region

              bull due to the changing geological strata of the young Himalayan rock New Australian Tunneling Methodology (NATM) was adopted for the construction

              Chenab Bridgebull The Chenab Bridge will be the highest railway structure of its kind in the world

              35 m higher than the tip of the Eiffel Tower in Paris

              bull The Chenab bridge is 13 km long and has the third largest arch span in the world At 1178 feet it will be the highest bridge in the world once completed

              bull Located near the Salal Hydro Power Dam the bridge was originally planned as a 1315 metre-long bridge having 17 spans

              bull Afcons Infrastructure Limited was awarded the contract for the bridge

              bull While deciding to stop all construction works on the Katra-Qazigund section in 2008 the Railway Ministry had proposed a change in the location of the bridge from the gorge to a wide valley two to three kilometers upstream of the original location Since the newly proposed location had a higher bed level the height of the bridge had it been constructed there would have come down to about 120-150 meters from river bed

              bull The Railways decided to stick to the location it had originally chosen to construct the Chenab Bridge mdash billed as the highest in the world at a height of 359 metres from the river bed At 343 metres Millau Viaduct in France is the tallest bridge in the world

              Operational Accidents amp Casualitiesbull June 2004 mdash Sudhir Kumar Pundir an IRCON Engineer and his brother Sanjay

              were kidnapped and murdered by terrorists in the valley

              bull June 2005 mdash Altaf Hussain A laborer working in a Tunnel at Tathyar (HCC) was killed by a collapse Two others were injured

              bull May 16 2007 mdashdaughter of Mushtaq Ahmad Wagay and daughter of Mohammad Ayub Wani (9 amp 7 yrs)drowned in a ditch constructed by Railway Company

              bull Feb 14 2008 mdash A Nepali labourer Tika Ram Balwari son of Tuya Narayan was killed after a boulder hit him in at Uri Varmul presumably on the Kashmir rail project for HCC

              bull Apr 18 2008 mdash Six labourers of a private company engaged with the Katra-Qazigund railway line project were killed and two others received injuries when a tipper carrying them rolled down into a deep gorge in Lower Juda Morh near Kouri in Reasi district late at night

              bull Mar 27 2011 mdash Two workers were killed at an under-construction railway bridge over the Chenab in Reasi district as a basket attached to a crane carrying them unhooked and fell from a height of more than 100 metres

              Current Status

              bull The USBRL project is divided into four sections

              bull Leg 0 extending 53 kilometres (33 mi) from Jammu to Udhampur completed in April 2005

              bull Leg 1 extending 25 kilometres (16 mi) from Udhampur to Katra Under construction may open in 2013

              bull Leg 2 extending 148 kilometres (92 mi) from Katra to Qazigund Under construction may open in 2017

              bull Leg 3 extending 119 kilometres (74 mi) from Qazigund to Baramulla completed in October 2009

              Inauguration of Kashmir rail linkDate Section Length km

              April 2005 Jammu - Udhampur Current Status

              53

              October 2008 Anantnag - Mazhom 66

              February 2009 Mazhom - Baramulla 35

              October 2009 Quazigund - Anantnag 18

              Delayed owing to construction difficulties

              Udhampur - Quazigund 167

              Inauguration of Final section KVRbull Prime Minister Dr Manmohan

              Singh flagged off a train from Anantnag to Quazigund to inaugurate the final 18 km of the railway through the Kashmir Valley on October 28 2009

              bull The currently isolated line will eventually be joined to the Indian rail network at Udhampur providing an all -weather transport link between the state of Jammu amp Kashmir and the rest of India which has been designated as a national priority

              Thanks

              • Kashmir Rail Project Challenges solutions and current status
              • Kashmir Railway Project (KRP)
              • Project Details
              • Slide 4
              • Challenges
              • Slide 6
              • Slide 7
              • Security Challenges
              • Project Sub sections
              • Slide 10
              • Rolling Stock
              • Rolling Stock (contdhellip)
              • Responsibility
              • Financials
              • Infrastructure and construction
              • Pir Panjal Tunnel(T-80)
              • Slide 17
              • Slide 18
              • Slide 19
              • Chenab Bridge
              • Slide 21
              • Operational Accidents amp Casualities
              • Slide 23
              • Current Status
              • Slide 25
              • Inauguration of Final section KVR
              • Thanks

                Project Sub sectionsbull Jammu-Udhampur Rail Link Project (53 km) ndash Leg 0

                ndash sub-mountainous region ndash It is 53 km long and has 10 km length of tunnels 36 major bridges and 122 minor bridgesndash his stretch has already been completed and commissioned in April 2005ndash The completion cost of this stretch is Rs 522 crore

                bull Udhampur-Srinagar-Baramulla Rail Link (USBRL) Project (202 km)

                ndash Leg-1 ndash Udhampur-Katra section (25 km )bull involves about 109 km of tunneling Nine major bridges 29 minor bridges and 10

                ROBRUBs in addition to about 3886 lac cum of earthworkbull approximate cost of this stretch is Rs 640 cr bull tallest bridge in this section is 90 m high (Br No 20) and the longest tunnel (T-80) is

                315 km long

                Project Sub sectionsbull Leg-2 ndash Katra-Quazigund (148 km)

                ndash toughest sector ever been constructed on the Indian Railwaysndash full of tunnels and bridgesviaducts Terrain in this region is full of poor geology and

                faults ndash On this section a bridge is being constructed across river Chenab which will have an

                arched span of 465 m and a total length of the bridge is around 13 km This will be about 359 m above the bed level of the river

                ndash The stretch between river Chenab and Banihal is through a virgin territory and requires construction of approximately 300 km of access roads of which about 110 km has already been constructed

                ndash At Quazigund end of this stretch the longest tunnel on Indian Railways is being constructed (Pir Panjal Tunnel) This tunnel is 1095 km long and will pierce through the Pir Panjal range below the snow line

                bull Leg 3-Quazigund-Baramulla (119 km)

                ndash falls in the Kashmir Valley which is a natural bowl surrounded by the mountain rangesndash there are no tunnels heavy bridging is required across rivers canals and roadsndash 64 major bridges and 640 minor bridges in this sectionndash completed in October 2009

                Rolling Stockbull Freight services conveying grain and petroleum products will run

                in between 10- 12 passengers services that are planned to operate daily

                bull An eight-coach DEMU will run on the Quazigund-Baramulla section of line Each coach will carry 90 passengers It will run twice a day in both directions

                bull The train has been fixed with a snow cutter system for clearing snow on the track The temperature in coaches can also be maintained at 20degC during winter

                bull Passenger services will be provided by the new aerodynamic High Power diesel multiple units with special features

                Rolling Stock (contdhellip)bull The air-conditioned coaches have wide windows for a panoramic view

                anti-skid flooring sliding doorways heating facilities an attractive colour scheme and executive class reclining seats inside

                bull The drivers cabin has a heating and defogging unit to take care of cold climatic conditions and is fitted with single lookout glass windows to give a wider view

                bull A snow-cutting type cattle guard has been attached at the driving end of the train for clearing snow from the tracks during winter In view of the peculiar climate of the valley the 1400-horsepower diesel engine for the train has been provided with a heating system for a quick and trouble-free start in the winters A public information system with display and announcement facilities are included in the coaches which have pneumatic suspension for better riding comfort There is also a compartment for physically challenged people with wider doors

                bull Maintenance of all rolling stock and locomotives will be at the newly built Budgam workshop just north of Srinagar

                Responsibilitybull Indian Railways is in charge of the Udhampur-Katra Section (25 km)

                bull Konkan Railway Corporation Limited is in charge of the Katra-Laole Section (90 km) This is arguably the toughest portion of the railway with over 92 of the line either inside a tunnel or on a bridge The bridges comprise of 12 km the tunnels of 72 km and only a minuscule part of this tortuous stretch ie 6 km is on normal ground

                bull IRCON a Public Sector railway construction company is in charge of the Laole-Baramulla Section (175 km) Another tough but less brutal section

                bull HCC has won the tender to construct both the North and South Section of the 11 km Banihal tunnel across the Pir Panjal range for approx US$120 million Work is completed

                bull AFCONS with Ultra Engineering (South Korea) will design and construct the Chenab Bridge for US$130 million

                bull Gammon India with Archirodon Construction (South Africa) will build the Anji Khad Bridge for US$100 million

                Financials

                bull Till April 2011 7165 crore had already been spent While the budget for last year was 1000 crore it has been marginally raised to 1100 crore for current fiscal

                bull Delay in the completion of the project led to an increase in the cost of requiring additional funds The Indian Government previously increased the projected cost of the railway line in 2007 upping the initial estimate of Rs307bn ($5693m) to Rs112bn ($21bn)

                bull The Indian Government has cleared a proposal to earmark Rs190bn ($35bn) of additional funds (Jan 2012)

                Infrastructure and constructionbull Total of over 750 bridges and over 100

                kilometres (62 mi) of tunnels the longest of which is about 11 kilometres (68 mi) in length

                bull The greatest engineering challenges involve the crossing of the Chenab river which involves building a 1315-metre-long (4314 ft) bridge 359 metres (1178 ft) above the river bed and the crossing of the Anji Khad which involves building a 657-metre-long (2156 ft) bridge 186 metres (610 ft) above the river bed

                Pir Panjal Tunnel(T-80)

                Pir Panjal Tunnel(T-80)bull At 1096km long the Pir Panjal Railway Tunnel is Indias longest and Asias 2nd

                longest tunnel

                bull passes through the Pir Panjal mountain range in Jammu and Kashmir in India

                bull aimed at reducing the travel distance between Quazigund and Banihal to only 11 km

                bull cover the distance from the south to the north side of the mountain in 66 minutes

                bull Completed in October 2011

                bull cost of Rs10bn ($2018m)

                bull Construction of the tunnel was carried out by Hindustan Construction Company and took over six years

                Pir Panjal Tunnel(T-80)bull 84m-wide and 73m-high tunnel and is up to 1 100 m below the surface

                bull construction of a 3m-wide road that runs alongside the railway tunnel for maintenance and emergency evacuation

                bull 100 percent water-proof and is also equipped with fire fighting system throughout its entire length

                bull construction of the tunnel started in November 2005 and was complete in 2011

                bull The fascinating fact about the tunnel excavation is that the total excavated quantity was equal to one mountain

                bull It runs 440m below the existing Jawahar Tunnel which is the only road link from the region to the rest of India meant for vehicular traffic only- which usually gets blocked during winters owing to heavy snowfall in the region

                bull due to the changing geological strata of the young Himalayan rock New Australian Tunneling Methodology (NATM) was adopted for the construction

                Chenab Bridgebull The Chenab Bridge will be the highest railway structure of its kind in the world

                35 m higher than the tip of the Eiffel Tower in Paris

                bull The Chenab bridge is 13 km long and has the third largest arch span in the world At 1178 feet it will be the highest bridge in the world once completed

                bull Located near the Salal Hydro Power Dam the bridge was originally planned as a 1315 metre-long bridge having 17 spans

                bull Afcons Infrastructure Limited was awarded the contract for the bridge

                bull While deciding to stop all construction works on the Katra-Qazigund section in 2008 the Railway Ministry had proposed a change in the location of the bridge from the gorge to a wide valley two to three kilometers upstream of the original location Since the newly proposed location had a higher bed level the height of the bridge had it been constructed there would have come down to about 120-150 meters from river bed

                bull The Railways decided to stick to the location it had originally chosen to construct the Chenab Bridge mdash billed as the highest in the world at a height of 359 metres from the river bed At 343 metres Millau Viaduct in France is the tallest bridge in the world

                Operational Accidents amp Casualitiesbull June 2004 mdash Sudhir Kumar Pundir an IRCON Engineer and his brother Sanjay

                were kidnapped and murdered by terrorists in the valley

                bull June 2005 mdash Altaf Hussain A laborer working in a Tunnel at Tathyar (HCC) was killed by a collapse Two others were injured

                bull May 16 2007 mdashdaughter of Mushtaq Ahmad Wagay and daughter of Mohammad Ayub Wani (9 amp 7 yrs)drowned in a ditch constructed by Railway Company

                bull Feb 14 2008 mdash A Nepali labourer Tika Ram Balwari son of Tuya Narayan was killed after a boulder hit him in at Uri Varmul presumably on the Kashmir rail project for HCC

                bull Apr 18 2008 mdash Six labourers of a private company engaged with the Katra-Qazigund railway line project were killed and two others received injuries when a tipper carrying them rolled down into a deep gorge in Lower Juda Morh near Kouri in Reasi district late at night

                bull Mar 27 2011 mdash Two workers were killed at an under-construction railway bridge over the Chenab in Reasi district as a basket attached to a crane carrying them unhooked and fell from a height of more than 100 metres

                Current Status

                bull The USBRL project is divided into four sections

                bull Leg 0 extending 53 kilometres (33 mi) from Jammu to Udhampur completed in April 2005

                bull Leg 1 extending 25 kilometres (16 mi) from Udhampur to Katra Under construction may open in 2013

                bull Leg 2 extending 148 kilometres (92 mi) from Katra to Qazigund Under construction may open in 2017

                bull Leg 3 extending 119 kilometres (74 mi) from Qazigund to Baramulla completed in October 2009

                Inauguration of Kashmir rail linkDate Section Length km

                April 2005 Jammu - Udhampur Current Status

                53

                October 2008 Anantnag - Mazhom 66

                February 2009 Mazhom - Baramulla 35

                October 2009 Quazigund - Anantnag 18

                Delayed owing to construction difficulties

                Udhampur - Quazigund 167

                Inauguration of Final section KVRbull Prime Minister Dr Manmohan

                Singh flagged off a train from Anantnag to Quazigund to inaugurate the final 18 km of the railway through the Kashmir Valley on October 28 2009

                bull The currently isolated line will eventually be joined to the Indian rail network at Udhampur providing an all -weather transport link between the state of Jammu amp Kashmir and the rest of India which has been designated as a national priority

                Thanks

                • Kashmir Rail Project Challenges solutions and current status
                • Kashmir Railway Project (KRP)
                • Project Details
                • Slide 4
                • Challenges
                • Slide 6
                • Slide 7
                • Security Challenges
                • Project Sub sections
                • Slide 10
                • Rolling Stock
                • Rolling Stock (contdhellip)
                • Responsibility
                • Financials
                • Infrastructure and construction
                • Pir Panjal Tunnel(T-80)
                • Slide 17
                • Slide 18
                • Slide 19
                • Chenab Bridge
                • Slide 21
                • Operational Accidents amp Casualities
                • Slide 23
                • Current Status
                • Slide 25
                • Inauguration of Final section KVR
                • Thanks

                  Project Sub sectionsbull Leg-2 ndash Katra-Quazigund (148 km)

                  ndash toughest sector ever been constructed on the Indian Railwaysndash full of tunnels and bridgesviaducts Terrain in this region is full of poor geology and

                  faults ndash On this section a bridge is being constructed across river Chenab which will have an

                  arched span of 465 m and a total length of the bridge is around 13 km This will be about 359 m above the bed level of the river

                  ndash The stretch between river Chenab and Banihal is through a virgin territory and requires construction of approximately 300 km of access roads of which about 110 km has already been constructed

                  ndash At Quazigund end of this stretch the longest tunnel on Indian Railways is being constructed (Pir Panjal Tunnel) This tunnel is 1095 km long and will pierce through the Pir Panjal range below the snow line

                  bull Leg 3-Quazigund-Baramulla (119 km)

                  ndash falls in the Kashmir Valley which is a natural bowl surrounded by the mountain rangesndash there are no tunnels heavy bridging is required across rivers canals and roadsndash 64 major bridges and 640 minor bridges in this sectionndash completed in October 2009

                  Rolling Stockbull Freight services conveying grain and petroleum products will run

                  in between 10- 12 passengers services that are planned to operate daily

                  bull An eight-coach DEMU will run on the Quazigund-Baramulla section of line Each coach will carry 90 passengers It will run twice a day in both directions

                  bull The train has been fixed with a snow cutter system for clearing snow on the track The temperature in coaches can also be maintained at 20degC during winter

                  bull Passenger services will be provided by the new aerodynamic High Power diesel multiple units with special features

                  Rolling Stock (contdhellip)bull The air-conditioned coaches have wide windows for a panoramic view

                  anti-skid flooring sliding doorways heating facilities an attractive colour scheme and executive class reclining seats inside

                  bull The drivers cabin has a heating and defogging unit to take care of cold climatic conditions and is fitted with single lookout glass windows to give a wider view

                  bull A snow-cutting type cattle guard has been attached at the driving end of the train for clearing snow from the tracks during winter In view of the peculiar climate of the valley the 1400-horsepower diesel engine for the train has been provided with a heating system for a quick and trouble-free start in the winters A public information system with display and announcement facilities are included in the coaches which have pneumatic suspension for better riding comfort There is also a compartment for physically challenged people with wider doors

                  bull Maintenance of all rolling stock and locomotives will be at the newly built Budgam workshop just north of Srinagar

                  Responsibilitybull Indian Railways is in charge of the Udhampur-Katra Section (25 km)

                  bull Konkan Railway Corporation Limited is in charge of the Katra-Laole Section (90 km) This is arguably the toughest portion of the railway with over 92 of the line either inside a tunnel or on a bridge The bridges comprise of 12 km the tunnels of 72 km and only a minuscule part of this tortuous stretch ie 6 km is on normal ground

                  bull IRCON a Public Sector railway construction company is in charge of the Laole-Baramulla Section (175 km) Another tough but less brutal section

                  bull HCC has won the tender to construct both the North and South Section of the 11 km Banihal tunnel across the Pir Panjal range for approx US$120 million Work is completed

                  bull AFCONS with Ultra Engineering (South Korea) will design and construct the Chenab Bridge for US$130 million

                  bull Gammon India with Archirodon Construction (South Africa) will build the Anji Khad Bridge for US$100 million

                  Financials

                  bull Till April 2011 7165 crore had already been spent While the budget for last year was 1000 crore it has been marginally raised to 1100 crore for current fiscal

                  bull Delay in the completion of the project led to an increase in the cost of requiring additional funds The Indian Government previously increased the projected cost of the railway line in 2007 upping the initial estimate of Rs307bn ($5693m) to Rs112bn ($21bn)

                  bull The Indian Government has cleared a proposal to earmark Rs190bn ($35bn) of additional funds (Jan 2012)

                  Infrastructure and constructionbull Total of over 750 bridges and over 100

                  kilometres (62 mi) of tunnels the longest of which is about 11 kilometres (68 mi) in length

                  bull The greatest engineering challenges involve the crossing of the Chenab river which involves building a 1315-metre-long (4314 ft) bridge 359 metres (1178 ft) above the river bed and the crossing of the Anji Khad which involves building a 657-metre-long (2156 ft) bridge 186 metres (610 ft) above the river bed

                  Pir Panjal Tunnel(T-80)

                  Pir Panjal Tunnel(T-80)bull At 1096km long the Pir Panjal Railway Tunnel is Indias longest and Asias 2nd

                  longest tunnel

                  bull passes through the Pir Panjal mountain range in Jammu and Kashmir in India

                  bull aimed at reducing the travel distance between Quazigund and Banihal to only 11 km

                  bull cover the distance from the south to the north side of the mountain in 66 minutes

                  bull Completed in October 2011

                  bull cost of Rs10bn ($2018m)

                  bull Construction of the tunnel was carried out by Hindustan Construction Company and took over six years

                  Pir Panjal Tunnel(T-80)bull 84m-wide and 73m-high tunnel and is up to 1 100 m below the surface

                  bull construction of a 3m-wide road that runs alongside the railway tunnel for maintenance and emergency evacuation

                  bull 100 percent water-proof and is also equipped with fire fighting system throughout its entire length

                  bull construction of the tunnel started in November 2005 and was complete in 2011

                  bull The fascinating fact about the tunnel excavation is that the total excavated quantity was equal to one mountain

                  bull It runs 440m below the existing Jawahar Tunnel which is the only road link from the region to the rest of India meant for vehicular traffic only- which usually gets blocked during winters owing to heavy snowfall in the region

                  bull due to the changing geological strata of the young Himalayan rock New Australian Tunneling Methodology (NATM) was adopted for the construction

                  Chenab Bridgebull The Chenab Bridge will be the highest railway structure of its kind in the world

                  35 m higher than the tip of the Eiffel Tower in Paris

                  bull The Chenab bridge is 13 km long and has the third largest arch span in the world At 1178 feet it will be the highest bridge in the world once completed

                  bull Located near the Salal Hydro Power Dam the bridge was originally planned as a 1315 metre-long bridge having 17 spans

                  bull Afcons Infrastructure Limited was awarded the contract for the bridge

                  bull While deciding to stop all construction works on the Katra-Qazigund section in 2008 the Railway Ministry had proposed a change in the location of the bridge from the gorge to a wide valley two to three kilometers upstream of the original location Since the newly proposed location had a higher bed level the height of the bridge had it been constructed there would have come down to about 120-150 meters from river bed

                  bull The Railways decided to stick to the location it had originally chosen to construct the Chenab Bridge mdash billed as the highest in the world at a height of 359 metres from the river bed At 343 metres Millau Viaduct in France is the tallest bridge in the world

                  Operational Accidents amp Casualitiesbull June 2004 mdash Sudhir Kumar Pundir an IRCON Engineer and his brother Sanjay

                  were kidnapped and murdered by terrorists in the valley

                  bull June 2005 mdash Altaf Hussain A laborer working in a Tunnel at Tathyar (HCC) was killed by a collapse Two others were injured

                  bull May 16 2007 mdashdaughter of Mushtaq Ahmad Wagay and daughter of Mohammad Ayub Wani (9 amp 7 yrs)drowned in a ditch constructed by Railway Company

                  bull Feb 14 2008 mdash A Nepali labourer Tika Ram Balwari son of Tuya Narayan was killed after a boulder hit him in at Uri Varmul presumably on the Kashmir rail project for HCC

                  bull Apr 18 2008 mdash Six labourers of a private company engaged with the Katra-Qazigund railway line project were killed and two others received injuries when a tipper carrying them rolled down into a deep gorge in Lower Juda Morh near Kouri in Reasi district late at night

                  bull Mar 27 2011 mdash Two workers were killed at an under-construction railway bridge over the Chenab in Reasi district as a basket attached to a crane carrying them unhooked and fell from a height of more than 100 metres

                  Current Status

                  bull The USBRL project is divided into four sections

                  bull Leg 0 extending 53 kilometres (33 mi) from Jammu to Udhampur completed in April 2005

                  bull Leg 1 extending 25 kilometres (16 mi) from Udhampur to Katra Under construction may open in 2013

                  bull Leg 2 extending 148 kilometres (92 mi) from Katra to Qazigund Under construction may open in 2017

                  bull Leg 3 extending 119 kilometres (74 mi) from Qazigund to Baramulla completed in October 2009

                  Inauguration of Kashmir rail linkDate Section Length km

                  April 2005 Jammu - Udhampur Current Status

                  53

                  October 2008 Anantnag - Mazhom 66

                  February 2009 Mazhom - Baramulla 35

                  October 2009 Quazigund - Anantnag 18

                  Delayed owing to construction difficulties

                  Udhampur - Quazigund 167

                  Inauguration of Final section KVRbull Prime Minister Dr Manmohan

                  Singh flagged off a train from Anantnag to Quazigund to inaugurate the final 18 km of the railway through the Kashmir Valley on October 28 2009

                  bull The currently isolated line will eventually be joined to the Indian rail network at Udhampur providing an all -weather transport link between the state of Jammu amp Kashmir and the rest of India which has been designated as a national priority

                  Thanks

                  • Kashmir Rail Project Challenges solutions and current status
                  • Kashmir Railway Project (KRP)
                  • Project Details
                  • Slide 4
                  • Challenges
                  • Slide 6
                  • Slide 7
                  • Security Challenges
                  • Project Sub sections
                  • Slide 10
                  • Rolling Stock
                  • Rolling Stock (contdhellip)
                  • Responsibility
                  • Financials
                  • Infrastructure and construction
                  • Pir Panjal Tunnel(T-80)
                  • Slide 17
                  • Slide 18
                  • Slide 19
                  • Chenab Bridge
                  • Slide 21
                  • Operational Accidents amp Casualities
                  • Slide 23
                  • Current Status
                  • Slide 25
                  • Inauguration of Final section KVR
                  • Thanks

                    Rolling Stockbull Freight services conveying grain and petroleum products will run

                    in between 10- 12 passengers services that are planned to operate daily

                    bull An eight-coach DEMU will run on the Quazigund-Baramulla section of line Each coach will carry 90 passengers It will run twice a day in both directions

                    bull The train has been fixed with a snow cutter system for clearing snow on the track The temperature in coaches can also be maintained at 20degC during winter

                    bull Passenger services will be provided by the new aerodynamic High Power diesel multiple units with special features

                    Rolling Stock (contdhellip)bull The air-conditioned coaches have wide windows for a panoramic view

                    anti-skid flooring sliding doorways heating facilities an attractive colour scheme and executive class reclining seats inside

                    bull The drivers cabin has a heating and defogging unit to take care of cold climatic conditions and is fitted with single lookout glass windows to give a wider view

                    bull A snow-cutting type cattle guard has been attached at the driving end of the train for clearing snow from the tracks during winter In view of the peculiar climate of the valley the 1400-horsepower diesel engine for the train has been provided with a heating system for a quick and trouble-free start in the winters A public information system with display and announcement facilities are included in the coaches which have pneumatic suspension for better riding comfort There is also a compartment for physically challenged people with wider doors

                    bull Maintenance of all rolling stock and locomotives will be at the newly built Budgam workshop just north of Srinagar

                    Responsibilitybull Indian Railways is in charge of the Udhampur-Katra Section (25 km)

                    bull Konkan Railway Corporation Limited is in charge of the Katra-Laole Section (90 km) This is arguably the toughest portion of the railway with over 92 of the line either inside a tunnel or on a bridge The bridges comprise of 12 km the tunnels of 72 km and only a minuscule part of this tortuous stretch ie 6 km is on normal ground

                    bull IRCON a Public Sector railway construction company is in charge of the Laole-Baramulla Section (175 km) Another tough but less brutal section

                    bull HCC has won the tender to construct both the North and South Section of the 11 km Banihal tunnel across the Pir Panjal range for approx US$120 million Work is completed

                    bull AFCONS with Ultra Engineering (South Korea) will design and construct the Chenab Bridge for US$130 million

                    bull Gammon India with Archirodon Construction (South Africa) will build the Anji Khad Bridge for US$100 million

                    Financials

                    bull Till April 2011 7165 crore had already been spent While the budget for last year was 1000 crore it has been marginally raised to 1100 crore for current fiscal

                    bull Delay in the completion of the project led to an increase in the cost of requiring additional funds The Indian Government previously increased the projected cost of the railway line in 2007 upping the initial estimate of Rs307bn ($5693m) to Rs112bn ($21bn)

                    bull The Indian Government has cleared a proposal to earmark Rs190bn ($35bn) of additional funds (Jan 2012)

                    Infrastructure and constructionbull Total of over 750 bridges and over 100

                    kilometres (62 mi) of tunnels the longest of which is about 11 kilometres (68 mi) in length

                    bull The greatest engineering challenges involve the crossing of the Chenab river which involves building a 1315-metre-long (4314 ft) bridge 359 metres (1178 ft) above the river bed and the crossing of the Anji Khad which involves building a 657-metre-long (2156 ft) bridge 186 metres (610 ft) above the river bed

                    Pir Panjal Tunnel(T-80)

                    Pir Panjal Tunnel(T-80)bull At 1096km long the Pir Panjal Railway Tunnel is Indias longest and Asias 2nd

                    longest tunnel

                    bull passes through the Pir Panjal mountain range in Jammu and Kashmir in India

                    bull aimed at reducing the travel distance between Quazigund and Banihal to only 11 km

                    bull cover the distance from the south to the north side of the mountain in 66 minutes

                    bull Completed in October 2011

                    bull cost of Rs10bn ($2018m)

                    bull Construction of the tunnel was carried out by Hindustan Construction Company and took over six years

                    Pir Panjal Tunnel(T-80)bull 84m-wide and 73m-high tunnel and is up to 1 100 m below the surface

                    bull construction of a 3m-wide road that runs alongside the railway tunnel for maintenance and emergency evacuation

                    bull 100 percent water-proof and is also equipped with fire fighting system throughout its entire length

                    bull construction of the tunnel started in November 2005 and was complete in 2011

                    bull The fascinating fact about the tunnel excavation is that the total excavated quantity was equal to one mountain

                    bull It runs 440m below the existing Jawahar Tunnel which is the only road link from the region to the rest of India meant for vehicular traffic only- which usually gets blocked during winters owing to heavy snowfall in the region

                    bull due to the changing geological strata of the young Himalayan rock New Australian Tunneling Methodology (NATM) was adopted for the construction

                    Chenab Bridgebull The Chenab Bridge will be the highest railway structure of its kind in the world

                    35 m higher than the tip of the Eiffel Tower in Paris

                    bull The Chenab bridge is 13 km long and has the third largest arch span in the world At 1178 feet it will be the highest bridge in the world once completed

                    bull Located near the Salal Hydro Power Dam the bridge was originally planned as a 1315 metre-long bridge having 17 spans

                    bull Afcons Infrastructure Limited was awarded the contract for the bridge

                    bull While deciding to stop all construction works on the Katra-Qazigund section in 2008 the Railway Ministry had proposed a change in the location of the bridge from the gorge to a wide valley two to three kilometers upstream of the original location Since the newly proposed location had a higher bed level the height of the bridge had it been constructed there would have come down to about 120-150 meters from river bed

                    bull The Railways decided to stick to the location it had originally chosen to construct the Chenab Bridge mdash billed as the highest in the world at a height of 359 metres from the river bed At 343 metres Millau Viaduct in France is the tallest bridge in the world

                    Operational Accidents amp Casualitiesbull June 2004 mdash Sudhir Kumar Pundir an IRCON Engineer and his brother Sanjay

                    were kidnapped and murdered by terrorists in the valley

                    bull June 2005 mdash Altaf Hussain A laborer working in a Tunnel at Tathyar (HCC) was killed by a collapse Two others were injured

                    bull May 16 2007 mdashdaughter of Mushtaq Ahmad Wagay and daughter of Mohammad Ayub Wani (9 amp 7 yrs)drowned in a ditch constructed by Railway Company

                    bull Feb 14 2008 mdash A Nepali labourer Tika Ram Balwari son of Tuya Narayan was killed after a boulder hit him in at Uri Varmul presumably on the Kashmir rail project for HCC

                    bull Apr 18 2008 mdash Six labourers of a private company engaged with the Katra-Qazigund railway line project were killed and two others received injuries when a tipper carrying them rolled down into a deep gorge in Lower Juda Morh near Kouri in Reasi district late at night

                    bull Mar 27 2011 mdash Two workers were killed at an under-construction railway bridge over the Chenab in Reasi district as a basket attached to a crane carrying them unhooked and fell from a height of more than 100 metres

                    Current Status

                    bull The USBRL project is divided into four sections

                    bull Leg 0 extending 53 kilometres (33 mi) from Jammu to Udhampur completed in April 2005

                    bull Leg 1 extending 25 kilometres (16 mi) from Udhampur to Katra Under construction may open in 2013

                    bull Leg 2 extending 148 kilometres (92 mi) from Katra to Qazigund Under construction may open in 2017

                    bull Leg 3 extending 119 kilometres (74 mi) from Qazigund to Baramulla completed in October 2009

                    Inauguration of Kashmir rail linkDate Section Length km

                    April 2005 Jammu - Udhampur Current Status

                    53

                    October 2008 Anantnag - Mazhom 66

                    February 2009 Mazhom - Baramulla 35

                    October 2009 Quazigund - Anantnag 18

                    Delayed owing to construction difficulties

                    Udhampur - Quazigund 167

                    Inauguration of Final section KVRbull Prime Minister Dr Manmohan

                    Singh flagged off a train from Anantnag to Quazigund to inaugurate the final 18 km of the railway through the Kashmir Valley on October 28 2009

                    bull The currently isolated line will eventually be joined to the Indian rail network at Udhampur providing an all -weather transport link between the state of Jammu amp Kashmir and the rest of India which has been designated as a national priority

                    Thanks

                    • Kashmir Rail Project Challenges solutions and current status
                    • Kashmir Railway Project (KRP)
                    • Project Details
                    • Slide 4
                    • Challenges
                    • Slide 6
                    • Slide 7
                    • Security Challenges
                    • Project Sub sections
                    • Slide 10
                    • Rolling Stock
                    • Rolling Stock (contdhellip)
                    • Responsibility
                    • Financials
                    • Infrastructure and construction
                    • Pir Panjal Tunnel(T-80)
                    • Slide 17
                    • Slide 18
                    • Slide 19
                    • Chenab Bridge
                    • Slide 21
                    • Operational Accidents amp Casualities
                    • Slide 23
                    • Current Status
                    • Slide 25
                    • Inauguration of Final section KVR
                    • Thanks

                      Rolling Stock (contdhellip)bull The air-conditioned coaches have wide windows for a panoramic view

                      anti-skid flooring sliding doorways heating facilities an attractive colour scheme and executive class reclining seats inside

                      bull The drivers cabin has a heating and defogging unit to take care of cold climatic conditions and is fitted with single lookout glass windows to give a wider view

                      bull A snow-cutting type cattle guard has been attached at the driving end of the train for clearing snow from the tracks during winter In view of the peculiar climate of the valley the 1400-horsepower diesel engine for the train has been provided with a heating system for a quick and trouble-free start in the winters A public information system with display and announcement facilities are included in the coaches which have pneumatic suspension for better riding comfort There is also a compartment for physically challenged people with wider doors

                      bull Maintenance of all rolling stock and locomotives will be at the newly built Budgam workshop just north of Srinagar

                      Responsibilitybull Indian Railways is in charge of the Udhampur-Katra Section (25 km)

                      bull Konkan Railway Corporation Limited is in charge of the Katra-Laole Section (90 km) This is arguably the toughest portion of the railway with over 92 of the line either inside a tunnel or on a bridge The bridges comprise of 12 km the tunnels of 72 km and only a minuscule part of this tortuous stretch ie 6 km is on normal ground

                      bull IRCON a Public Sector railway construction company is in charge of the Laole-Baramulla Section (175 km) Another tough but less brutal section

                      bull HCC has won the tender to construct both the North and South Section of the 11 km Banihal tunnel across the Pir Panjal range for approx US$120 million Work is completed

                      bull AFCONS with Ultra Engineering (South Korea) will design and construct the Chenab Bridge for US$130 million

                      bull Gammon India with Archirodon Construction (South Africa) will build the Anji Khad Bridge for US$100 million

                      Financials

                      bull Till April 2011 7165 crore had already been spent While the budget for last year was 1000 crore it has been marginally raised to 1100 crore for current fiscal

                      bull Delay in the completion of the project led to an increase in the cost of requiring additional funds The Indian Government previously increased the projected cost of the railway line in 2007 upping the initial estimate of Rs307bn ($5693m) to Rs112bn ($21bn)

                      bull The Indian Government has cleared a proposal to earmark Rs190bn ($35bn) of additional funds (Jan 2012)

                      Infrastructure and constructionbull Total of over 750 bridges and over 100

                      kilometres (62 mi) of tunnels the longest of which is about 11 kilometres (68 mi) in length

                      bull The greatest engineering challenges involve the crossing of the Chenab river which involves building a 1315-metre-long (4314 ft) bridge 359 metres (1178 ft) above the river bed and the crossing of the Anji Khad which involves building a 657-metre-long (2156 ft) bridge 186 metres (610 ft) above the river bed

                      Pir Panjal Tunnel(T-80)

                      Pir Panjal Tunnel(T-80)bull At 1096km long the Pir Panjal Railway Tunnel is Indias longest and Asias 2nd

                      longest tunnel

                      bull passes through the Pir Panjal mountain range in Jammu and Kashmir in India

                      bull aimed at reducing the travel distance between Quazigund and Banihal to only 11 km

                      bull cover the distance from the south to the north side of the mountain in 66 minutes

                      bull Completed in October 2011

                      bull cost of Rs10bn ($2018m)

                      bull Construction of the tunnel was carried out by Hindustan Construction Company and took over six years

                      Pir Panjal Tunnel(T-80)bull 84m-wide and 73m-high tunnel and is up to 1 100 m below the surface

                      bull construction of a 3m-wide road that runs alongside the railway tunnel for maintenance and emergency evacuation

                      bull 100 percent water-proof and is also equipped with fire fighting system throughout its entire length

                      bull construction of the tunnel started in November 2005 and was complete in 2011

                      bull The fascinating fact about the tunnel excavation is that the total excavated quantity was equal to one mountain

                      bull It runs 440m below the existing Jawahar Tunnel which is the only road link from the region to the rest of India meant for vehicular traffic only- which usually gets blocked during winters owing to heavy snowfall in the region

                      bull due to the changing geological strata of the young Himalayan rock New Australian Tunneling Methodology (NATM) was adopted for the construction

                      Chenab Bridgebull The Chenab Bridge will be the highest railway structure of its kind in the world

                      35 m higher than the tip of the Eiffel Tower in Paris

                      bull The Chenab bridge is 13 km long and has the third largest arch span in the world At 1178 feet it will be the highest bridge in the world once completed

                      bull Located near the Salal Hydro Power Dam the bridge was originally planned as a 1315 metre-long bridge having 17 spans

                      bull Afcons Infrastructure Limited was awarded the contract for the bridge

                      bull While deciding to stop all construction works on the Katra-Qazigund section in 2008 the Railway Ministry had proposed a change in the location of the bridge from the gorge to a wide valley two to three kilometers upstream of the original location Since the newly proposed location had a higher bed level the height of the bridge had it been constructed there would have come down to about 120-150 meters from river bed

                      bull The Railways decided to stick to the location it had originally chosen to construct the Chenab Bridge mdash billed as the highest in the world at a height of 359 metres from the river bed At 343 metres Millau Viaduct in France is the tallest bridge in the world

                      Operational Accidents amp Casualitiesbull June 2004 mdash Sudhir Kumar Pundir an IRCON Engineer and his brother Sanjay

                      were kidnapped and murdered by terrorists in the valley

                      bull June 2005 mdash Altaf Hussain A laborer working in a Tunnel at Tathyar (HCC) was killed by a collapse Two others were injured

                      bull May 16 2007 mdashdaughter of Mushtaq Ahmad Wagay and daughter of Mohammad Ayub Wani (9 amp 7 yrs)drowned in a ditch constructed by Railway Company

                      bull Feb 14 2008 mdash A Nepali labourer Tika Ram Balwari son of Tuya Narayan was killed after a boulder hit him in at Uri Varmul presumably on the Kashmir rail project for HCC

                      bull Apr 18 2008 mdash Six labourers of a private company engaged with the Katra-Qazigund railway line project were killed and two others received injuries when a tipper carrying them rolled down into a deep gorge in Lower Juda Morh near Kouri in Reasi district late at night

                      bull Mar 27 2011 mdash Two workers were killed at an under-construction railway bridge over the Chenab in Reasi district as a basket attached to a crane carrying them unhooked and fell from a height of more than 100 metres

                      Current Status

                      bull The USBRL project is divided into four sections

                      bull Leg 0 extending 53 kilometres (33 mi) from Jammu to Udhampur completed in April 2005

                      bull Leg 1 extending 25 kilometres (16 mi) from Udhampur to Katra Under construction may open in 2013

                      bull Leg 2 extending 148 kilometres (92 mi) from Katra to Qazigund Under construction may open in 2017

                      bull Leg 3 extending 119 kilometres (74 mi) from Qazigund to Baramulla completed in October 2009

                      Inauguration of Kashmir rail linkDate Section Length km

                      April 2005 Jammu - Udhampur Current Status

                      53

                      October 2008 Anantnag - Mazhom 66

                      February 2009 Mazhom - Baramulla 35

                      October 2009 Quazigund - Anantnag 18

                      Delayed owing to construction difficulties

                      Udhampur - Quazigund 167

                      Inauguration of Final section KVRbull Prime Minister Dr Manmohan

                      Singh flagged off a train from Anantnag to Quazigund to inaugurate the final 18 km of the railway through the Kashmir Valley on October 28 2009

                      bull The currently isolated line will eventually be joined to the Indian rail network at Udhampur providing an all -weather transport link between the state of Jammu amp Kashmir and the rest of India which has been designated as a national priority

                      Thanks

                      • Kashmir Rail Project Challenges solutions and current status
                      • Kashmir Railway Project (KRP)
                      • Project Details
                      • Slide 4
                      • Challenges
                      • Slide 6
                      • Slide 7
                      • Security Challenges
                      • Project Sub sections
                      • Slide 10
                      • Rolling Stock
                      • Rolling Stock (contdhellip)
                      • Responsibility
                      • Financials
                      • Infrastructure and construction
                      • Pir Panjal Tunnel(T-80)
                      • Slide 17
                      • Slide 18
                      • Slide 19
                      • Chenab Bridge
                      • Slide 21
                      • Operational Accidents amp Casualities
                      • Slide 23
                      • Current Status
                      • Slide 25
                      • Inauguration of Final section KVR
                      • Thanks

                        Responsibilitybull Indian Railways is in charge of the Udhampur-Katra Section (25 km)

                        bull Konkan Railway Corporation Limited is in charge of the Katra-Laole Section (90 km) This is arguably the toughest portion of the railway with over 92 of the line either inside a tunnel or on a bridge The bridges comprise of 12 km the tunnels of 72 km and only a minuscule part of this tortuous stretch ie 6 km is on normal ground

                        bull IRCON a Public Sector railway construction company is in charge of the Laole-Baramulla Section (175 km) Another tough but less brutal section

                        bull HCC has won the tender to construct both the North and South Section of the 11 km Banihal tunnel across the Pir Panjal range for approx US$120 million Work is completed

                        bull AFCONS with Ultra Engineering (South Korea) will design and construct the Chenab Bridge for US$130 million

                        bull Gammon India with Archirodon Construction (South Africa) will build the Anji Khad Bridge for US$100 million

                        Financials

                        bull Till April 2011 7165 crore had already been spent While the budget for last year was 1000 crore it has been marginally raised to 1100 crore for current fiscal

                        bull Delay in the completion of the project led to an increase in the cost of requiring additional funds The Indian Government previously increased the projected cost of the railway line in 2007 upping the initial estimate of Rs307bn ($5693m) to Rs112bn ($21bn)

                        bull The Indian Government has cleared a proposal to earmark Rs190bn ($35bn) of additional funds (Jan 2012)

                        Infrastructure and constructionbull Total of over 750 bridges and over 100

                        kilometres (62 mi) of tunnels the longest of which is about 11 kilometres (68 mi) in length

                        bull The greatest engineering challenges involve the crossing of the Chenab river which involves building a 1315-metre-long (4314 ft) bridge 359 metres (1178 ft) above the river bed and the crossing of the Anji Khad which involves building a 657-metre-long (2156 ft) bridge 186 metres (610 ft) above the river bed

                        Pir Panjal Tunnel(T-80)

                        Pir Panjal Tunnel(T-80)bull At 1096km long the Pir Panjal Railway Tunnel is Indias longest and Asias 2nd

                        longest tunnel

                        bull passes through the Pir Panjal mountain range in Jammu and Kashmir in India

                        bull aimed at reducing the travel distance between Quazigund and Banihal to only 11 km

                        bull cover the distance from the south to the north side of the mountain in 66 minutes

                        bull Completed in October 2011

                        bull cost of Rs10bn ($2018m)

                        bull Construction of the tunnel was carried out by Hindustan Construction Company and took over six years

                        Pir Panjal Tunnel(T-80)bull 84m-wide and 73m-high tunnel and is up to 1 100 m below the surface

                        bull construction of a 3m-wide road that runs alongside the railway tunnel for maintenance and emergency evacuation

                        bull 100 percent water-proof and is also equipped with fire fighting system throughout its entire length

                        bull construction of the tunnel started in November 2005 and was complete in 2011

                        bull The fascinating fact about the tunnel excavation is that the total excavated quantity was equal to one mountain

                        bull It runs 440m below the existing Jawahar Tunnel which is the only road link from the region to the rest of India meant for vehicular traffic only- which usually gets blocked during winters owing to heavy snowfall in the region

                        bull due to the changing geological strata of the young Himalayan rock New Australian Tunneling Methodology (NATM) was adopted for the construction

                        Chenab Bridgebull The Chenab Bridge will be the highest railway structure of its kind in the world

                        35 m higher than the tip of the Eiffel Tower in Paris

                        bull The Chenab bridge is 13 km long and has the third largest arch span in the world At 1178 feet it will be the highest bridge in the world once completed

                        bull Located near the Salal Hydro Power Dam the bridge was originally planned as a 1315 metre-long bridge having 17 spans

                        bull Afcons Infrastructure Limited was awarded the contract for the bridge

                        bull While deciding to stop all construction works on the Katra-Qazigund section in 2008 the Railway Ministry had proposed a change in the location of the bridge from the gorge to a wide valley two to three kilometers upstream of the original location Since the newly proposed location had a higher bed level the height of the bridge had it been constructed there would have come down to about 120-150 meters from river bed

                        bull The Railways decided to stick to the location it had originally chosen to construct the Chenab Bridge mdash billed as the highest in the world at a height of 359 metres from the river bed At 343 metres Millau Viaduct in France is the tallest bridge in the world

                        Operational Accidents amp Casualitiesbull June 2004 mdash Sudhir Kumar Pundir an IRCON Engineer and his brother Sanjay

                        were kidnapped and murdered by terrorists in the valley

                        bull June 2005 mdash Altaf Hussain A laborer working in a Tunnel at Tathyar (HCC) was killed by a collapse Two others were injured

                        bull May 16 2007 mdashdaughter of Mushtaq Ahmad Wagay and daughter of Mohammad Ayub Wani (9 amp 7 yrs)drowned in a ditch constructed by Railway Company

                        bull Feb 14 2008 mdash A Nepali labourer Tika Ram Balwari son of Tuya Narayan was killed after a boulder hit him in at Uri Varmul presumably on the Kashmir rail project for HCC

                        bull Apr 18 2008 mdash Six labourers of a private company engaged with the Katra-Qazigund railway line project were killed and two others received injuries when a tipper carrying them rolled down into a deep gorge in Lower Juda Morh near Kouri in Reasi district late at night

                        bull Mar 27 2011 mdash Two workers were killed at an under-construction railway bridge over the Chenab in Reasi district as a basket attached to a crane carrying them unhooked and fell from a height of more than 100 metres

                        Current Status

                        bull The USBRL project is divided into four sections

                        bull Leg 0 extending 53 kilometres (33 mi) from Jammu to Udhampur completed in April 2005

                        bull Leg 1 extending 25 kilometres (16 mi) from Udhampur to Katra Under construction may open in 2013

                        bull Leg 2 extending 148 kilometres (92 mi) from Katra to Qazigund Under construction may open in 2017

                        bull Leg 3 extending 119 kilometres (74 mi) from Qazigund to Baramulla completed in October 2009

                        Inauguration of Kashmir rail linkDate Section Length km

                        April 2005 Jammu - Udhampur Current Status

                        53

                        October 2008 Anantnag - Mazhom 66

                        February 2009 Mazhom - Baramulla 35

                        October 2009 Quazigund - Anantnag 18

                        Delayed owing to construction difficulties

                        Udhampur - Quazigund 167

                        Inauguration of Final section KVRbull Prime Minister Dr Manmohan

                        Singh flagged off a train from Anantnag to Quazigund to inaugurate the final 18 km of the railway through the Kashmir Valley on October 28 2009

                        bull The currently isolated line will eventually be joined to the Indian rail network at Udhampur providing an all -weather transport link between the state of Jammu amp Kashmir and the rest of India which has been designated as a national priority

                        Thanks

                        • Kashmir Rail Project Challenges solutions and current status
                        • Kashmir Railway Project (KRP)
                        • Project Details
                        • Slide 4
                        • Challenges
                        • Slide 6
                        • Slide 7
                        • Security Challenges
                        • Project Sub sections
                        • Slide 10
                        • Rolling Stock
                        • Rolling Stock (contdhellip)
                        • Responsibility
                        • Financials
                        • Infrastructure and construction
                        • Pir Panjal Tunnel(T-80)
                        • Slide 17
                        • Slide 18
                        • Slide 19
                        • Chenab Bridge
                        • Slide 21
                        • Operational Accidents amp Casualities
                        • Slide 23
                        • Current Status
                        • Slide 25
                        • Inauguration of Final section KVR
                        • Thanks

                          Financials

                          bull Till April 2011 7165 crore had already been spent While the budget for last year was 1000 crore it has been marginally raised to 1100 crore for current fiscal

                          bull Delay in the completion of the project led to an increase in the cost of requiring additional funds The Indian Government previously increased the projected cost of the railway line in 2007 upping the initial estimate of Rs307bn ($5693m) to Rs112bn ($21bn)

                          bull The Indian Government has cleared a proposal to earmark Rs190bn ($35bn) of additional funds (Jan 2012)

                          Infrastructure and constructionbull Total of over 750 bridges and over 100

                          kilometres (62 mi) of tunnels the longest of which is about 11 kilometres (68 mi) in length

                          bull The greatest engineering challenges involve the crossing of the Chenab river which involves building a 1315-metre-long (4314 ft) bridge 359 metres (1178 ft) above the river bed and the crossing of the Anji Khad which involves building a 657-metre-long (2156 ft) bridge 186 metres (610 ft) above the river bed

                          Pir Panjal Tunnel(T-80)

                          Pir Panjal Tunnel(T-80)bull At 1096km long the Pir Panjal Railway Tunnel is Indias longest and Asias 2nd

                          longest tunnel

                          bull passes through the Pir Panjal mountain range in Jammu and Kashmir in India

                          bull aimed at reducing the travel distance between Quazigund and Banihal to only 11 km

                          bull cover the distance from the south to the north side of the mountain in 66 minutes

                          bull Completed in October 2011

                          bull cost of Rs10bn ($2018m)

                          bull Construction of the tunnel was carried out by Hindustan Construction Company and took over six years

                          Pir Panjal Tunnel(T-80)bull 84m-wide and 73m-high tunnel and is up to 1 100 m below the surface

                          bull construction of a 3m-wide road that runs alongside the railway tunnel for maintenance and emergency evacuation

                          bull 100 percent water-proof and is also equipped with fire fighting system throughout its entire length

                          bull construction of the tunnel started in November 2005 and was complete in 2011

                          bull The fascinating fact about the tunnel excavation is that the total excavated quantity was equal to one mountain

                          bull It runs 440m below the existing Jawahar Tunnel which is the only road link from the region to the rest of India meant for vehicular traffic only- which usually gets blocked during winters owing to heavy snowfall in the region

                          bull due to the changing geological strata of the young Himalayan rock New Australian Tunneling Methodology (NATM) was adopted for the construction

                          Chenab Bridgebull The Chenab Bridge will be the highest railway structure of its kind in the world

                          35 m higher than the tip of the Eiffel Tower in Paris

                          bull The Chenab bridge is 13 km long and has the third largest arch span in the world At 1178 feet it will be the highest bridge in the world once completed

                          bull Located near the Salal Hydro Power Dam the bridge was originally planned as a 1315 metre-long bridge having 17 spans

                          bull Afcons Infrastructure Limited was awarded the contract for the bridge

                          bull While deciding to stop all construction works on the Katra-Qazigund section in 2008 the Railway Ministry had proposed a change in the location of the bridge from the gorge to a wide valley two to three kilometers upstream of the original location Since the newly proposed location had a higher bed level the height of the bridge had it been constructed there would have come down to about 120-150 meters from river bed

                          bull The Railways decided to stick to the location it had originally chosen to construct the Chenab Bridge mdash billed as the highest in the world at a height of 359 metres from the river bed At 343 metres Millau Viaduct in France is the tallest bridge in the world

                          Operational Accidents amp Casualitiesbull June 2004 mdash Sudhir Kumar Pundir an IRCON Engineer and his brother Sanjay

                          were kidnapped and murdered by terrorists in the valley

                          bull June 2005 mdash Altaf Hussain A laborer working in a Tunnel at Tathyar (HCC) was killed by a collapse Two others were injured

                          bull May 16 2007 mdashdaughter of Mushtaq Ahmad Wagay and daughter of Mohammad Ayub Wani (9 amp 7 yrs)drowned in a ditch constructed by Railway Company

                          bull Feb 14 2008 mdash A Nepali labourer Tika Ram Balwari son of Tuya Narayan was killed after a boulder hit him in at Uri Varmul presumably on the Kashmir rail project for HCC

                          bull Apr 18 2008 mdash Six labourers of a private company engaged with the Katra-Qazigund railway line project were killed and two others received injuries when a tipper carrying them rolled down into a deep gorge in Lower Juda Morh near Kouri in Reasi district late at night

                          bull Mar 27 2011 mdash Two workers were killed at an under-construction railway bridge over the Chenab in Reasi district as a basket attached to a crane carrying them unhooked and fell from a height of more than 100 metres

                          Current Status

                          bull The USBRL project is divided into four sections

                          bull Leg 0 extending 53 kilometres (33 mi) from Jammu to Udhampur completed in April 2005

                          bull Leg 1 extending 25 kilometres (16 mi) from Udhampur to Katra Under construction may open in 2013

                          bull Leg 2 extending 148 kilometres (92 mi) from Katra to Qazigund Under construction may open in 2017

                          bull Leg 3 extending 119 kilometres (74 mi) from Qazigund to Baramulla completed in October 2009

                          Inauguration of Kashmir rail linkDate Section Length km

                          April 2005 Jammu - Udhampur Current Status

                          53

                          October 2008 Anantnag - Mazhom 66

                          February 2009 Mazhom - Baramulla 35

                          October 2009 Quazigund - Anantnag 18

                          Delayed owing to construction difficulties

                          Udhampur - Quazigund 167

                          Inauguration of Final section KVRbull Prime Minister Dr Manmohan

                          Singh flagged off a train from Anantnag to Quazigund to inaugurate the final 18 km of the railway through the Kashmir Valley on October 28 2009

                          bull The currently isolated line will eventually be joined to the Indian rail network at Udhampur providing an all -weather transport link between the state of Jammu amp Kashmir and the rest of India which has been designated as a national priority

                          Thanks

                          • Kashmir Rail Project Challenges solutions and current status
                          • Kashmir Railway Project (KRP)
                          • Project Details
                          • Slide 4
                          • Challenges
                          • Slide 6
                          • Slide 7
                          • Security Challenges
                          • Project Sub sections
                          • Slide 10
                          • Rolling Stock
                          • Rolling Stock (contdhellip)
                          • Responsibility
                          • Financials
                          • Infrastructure and construction
                          • Pir Panjal Tunnel(T-80)
                          • Slide 17
                          • Slide 18
                          • Slide 19
                          • Chenab Bridge
                          • Slide 21
                          • Operational Accidents amp Casualities
                          • Slide 23
                          • Current Status
                          • Slide 25
                          • Inauguration of Final section KVR
                          • Thanks

                            Infrastructure and constructionbull Total of over 750 bridges and over 100

                            kilometres (62 mi) of tunnels the longest of which is about 11 kilometres (68 mi) in length

                            bull The greatest engineering challenges involve the crossing of the Chenab river which involves building a 1315-metre-long (4314 ft) bridge 359 metres (1178 ft) above the river bed and the crossing of the Anji Khad which involves building a 657-metre-long (2156 ft) bridge 186 metres (610 ft) above the river bed

                            Pir Panjal Tunnel(T-80)

                            Pir Panjal Tunnel(T-80)bull At 1096km long the Pir Panjal Railway Tunnel is Indias longest and Asias 2nd

                            longest tunnel

                            bull passes through the Pir Panjal mountain range in Jammu and Kashmir in India

                            bull aimed at reducing the travel distance between Quazigund and Banihal to only 11 km

                            bull cover the distance from the south to the north side of the mountain in 66 minutes

                            bull Completed in October 2011

                            bull cost of Rs10bn ($2018m)

                            bull Construction of the tunnel was carried out by Hindustan Construction Company and took over six years

                            Pir Panjal Tunnel(T-80)bull 84m-wide and 73m-high tunnel and is up to 1 100 m below the surface

                            bull construction of a 3m-wide road that runs alongside the railway tunnel for maintenance and emergency evacuation

                            bull 100 percent water-proof and is also equipped with fire fighting system throughout its entire length

                            bull construction of the tunnel started in November 2005 and was complete in 2011

                            bull The fascinating fact about the tunnel excavation is that the total excavated quantity was equal to one mountain

                            bull It runs 440m below the existing Jawahar Tunnel which is the only road link from the region to the rest of India meant for vehicular traffic only- which usually gets blocked during winters owing to heavy snowfall in the region

                            bull due to the changing geological strata of the young Himalayan rock New Australian Tunneling Methodology (NATM) was adopted for the construction

                            Chenab Bridgebull The Chenab Bridge will be the highest railway structure of its kind in the world

                            35 m higher than the tip of the Eiffel Tower in Paris

                            bull The Chenab bridge is 13 km long and has the third largest arch span in the world At 1178 feet it will be the highest bridge in the world once completed

                            bull Located near the Salal Hydro Power Dam the bridge was originally planned as a 1315 metre-long bridge having 17 spans

                            bull Afcons Infrastructure Limited was awarded the contract for the bridge

                            bull While deciding to stop all construction works on the Katra-Qazigund section in 2008 the Railway Ministry had proposed a change in the location of the bridge from the gorge to a wide valley two to three kilometers upstream of the original location Since the newly proposed location had a higher bed level the height of the bridge had it been constructed there would have come down to about 120-150 meters from river bed

                            bull The Railways decided to stick to the location it had originally chosen to construct the Chenab Bridge mdash billed as the highest in the world at a height of 359 metres from the river bed At 343 metres Millau Viaduct in France is the tallest bridge in the world

                            Operational Accidents amp Casualitiesbull June 2004 mdash Sudhir Kumar Pundir an IRCON Engineer and his brother Sanjay

                            were kidnapped and murdered by terrorists in the valley

                            bull June 2005 mdash Altaf Hussain A laborer working in a Tunnel at Tathyar (HCC) was killed by a collapse Two others were injured

                            bull May 16 2007 mdashdaughter of Mushtaq Ahmad Wagay and daughter of Mohammad Ayub Wani (9 amp 7 yrs)drowned in a ditch constructed by Railway Company

                            bull Feb 14 2008 mdash A Nepali labourer Tika Ram Balwari son of Tuya Narayan was killed after a boulder hit him in at Uri Varmul presumably on the Kashmir rail project for HCC

                            bull Apr 18 2008 mdash Six labourers of a private company engaged with the Katra-Qazigund railway line project were killed and two others received injuries when a tipper carrying them rolled down into a deep gorge in Lower Juda Morh near Kouri in Reasi district late at night

                            bull Mar 27 2011 mdash Two workers were killed at an under-construction railway bridge over the Chenab in Reasi district as a basket attached to a crane carrying them unhooked and fell from a height of more than 100 metres

                            Current Status

                            bull The USBRL project is divided into four sections

                            bull Leg 0 extending 53 kilometres (33 mi) from Jammu to Udhampur completed in April 2005

                            bull Leg 1 extending 25 kilometres (16 mi) from Udhampur to Katra Under construction may open in 2013

                            bull Leg 2 extending 148 kilometres (92 mi) from Katra to Qazigund Under construction may open in 2017

                            bull Leg 3 extending 119 kilometres (74 mi) from Qazigund to Baramulla completed in October 2009

                            Inauguration of Kashmir rail linkDate Section Length km

                            April 2005 Jammu - Udhampur Current Status

                            53

                            October 2008 Anantnag - Mazhom 66

                            February 2009 Mazhom - Baramulla 35

                            October 2009 Quazigund - Anantnag 18

                            Delayed owing to construction difficulties

                            Udhampur - Quazigund 167

                            Inauguration of Final section KVRbull Prime Minister Dr Manmohan

                            Singh flagged off a train from Anantnag to Quazigund to inaugurate the final 18 km of the railway through the Kashmir Valley on October 28 2009

                            bull The currently isolated line will eventually be joined to the Indian rail network at Udhampur providing an all -weather transport link between the state of Jammu amp Kashmir and the rest of India which has been designated as a national priority

                            Thanks

                            • Kashmir Rail Project Challenges solutions and current status
                            • Kashmir Railway Project (KRP)
                            • Project Details
                            • Slide 4
                            • Challenges
                            • Slide 6
                            • Slide 7
                            • Security Challenges
                            • Project Sub sections
                            • Slide 10
                            • Rolling Stock
                            • Rolling Stock (contdhellip)
                            • Responsibility
                            • Financials
                            • Infrastructure and construction
                            • Pir Panjal Tunnel(T-80)
                            • Slide 17
                            • Slide 18
                            • Slide 19
                            • Chenab Bridge
                            • Slide 21
                            • Operational Accidents amp Casualities
                            • Slide 23
                            • Current Status
                            • Slide 25
                            • Inauguration of Final section KVR
                            • Thanks

                              Pir Panjal Tunnel(T-80)

                              Pir Panjal Tunnel(T-80)bull At 1096km long the Pir Panjal Railway Tunnel is Indias longest and Asias 2nd

                              longest tunnel

                              bull passes through the Pir Panjal mountain range in Jammu and Kashmir in India

                              bull aimed at reducing the travel distance between Quazigund and Banihal to only 11 km

                              bull cover the distance from the south to the north side of the mountain in 66 minutes

                              bull Completed in October 2011

                              bull cost of Rs10bn ($2018m)

                              bull Construction of the tunnel was carried out by Hindustan Construction Company and took over six years

                              Pir Panjal Tunnel(T-80)bull 84m-wide and 73m-high tunnel and is up to 1 100 m below the surface

                              bull construction of a 3m-wide road that runs alongside the railway tunnel for maintenance and emergency evacuation

                              bull 100 percent water-proof and is also equipped with fire fighting system throughout its entire length

                              bull construction of the tunnel started in November 2005 and was complete in 2011

                              bull The fascinating fact about the tunnel excavation is that the total excavated quantity was equal to one mountain

                              bull It runs 440m below the existing Jawahar Tunnel which is the only road link from the region to the rest of India meant for vehicular traffic only- which usually gets blocked during winters owing to heavy snowfall in the region

                              bull due to the changing geological strata of the young Himalayan rock New Australian Tunneling Methodology (NATM) was adopted for the construction

                              Chenab Bridgebull The Chenab Bridge will be the highest railway structure of its kind in the world

                              35 m higher than the tip of the Eiffel Tower in Paris

                              bull The Chenab bridge is 13 km long and has the third largest arch span in the world At 1178 feet it will be the highest bridge in the world once completed

                              bull Located near the Salal Hydro Power Dam the bridge was originally planned as a 1315 metre-long bridge having 17 spans

                              bull Afcons Infrastructure Limited was awarded the contract for the bridge

                              bull While deciding to stop all construction works on the Katra-Qazigund section in 2008 the Railway Ministry had proposed a change in the location of the bridge from the gorge to a wide valley two to three kilometers upstream of the original location Since the newly proposed location had a higher bed level the height of the bridge had it been constructed there would have come down to about 120-150 meters from river bed

                              bull The Railways decided to stick to the location it had originally chosen to construct the Chenab Bridge mdash billed as the highest in the world at a height of 359 metres from the river bed At 343 metres Millau Viaduct in France is the tallest bridge in the world

                              Operational Accidents amp Casualitiesbull June 2004 mdash Sudhir Kumar Pundir an IRCON Engineer and his brother Sanjay

                              were kidnapped and murdered by terrorists in the valley

                              bull June 2005 mdash Altaf Hussain A laborer working in a Tunnel at Tathyar (HCC) was killed by a collapse Two others were injured

                              bull May 16 2007 mdashdaughter of Mushtaq Ahmad Wagay and daughter of Mohammad Ayub Wani (9 amp 7 yrs)drowned in a ditch constructed by Railway Company

                              bull Feb 14 2008 mdash A Nepali labourer Tika Ram Balwari son of Tuya Narayan was killed after a boulder hit him in at Uri Varmul presumably on the Kashmir rail project for HCC

                              bull Apr 18 2008 mdash Six labourers of a private company engaged with the Katra-Qazigund railway line project were killed and two others received injuries when a tipper carrying them rolled down into a deep gorge in Lower Juda Morh near Kouri in Reasi district late at night

                              bull Mar 27 2011 mdash Two workers were killed at an under-construction railway bridge over the Chenab in Reasi district as a basket attached to a crane carrying them unhooked and fell from a height of more than 100 metres

                              Current Status

                              bull The USBRL project is divided into four sections

                              bull Leg 0 extending 53 kilometres (33 mi) from Jammu to Udhampur completed in April 2005

                              bull Leg 1 extending 25 kilometres (16 mi) from Udhampur to Katra Under construction may open in 2013

                              bull Leg 2 extending 148 kilometres (92 mi) from Katra to Qazigund Under construction may open in 2017

                              bull Leg 3 extending 119 kilometres (74 mi) from Qazigund to Baramulla completed in October 2009

                              Inauguration of Kashmir rail linkDate Section Length km

                              April 2005 Jammu - Udhampur Current Status

                              53

                              October 2008 Anantnag - Mazhom 66

                              February 2009 Mazhom - Baramulla 35

                              October 2009 Quazigund - Anantnag 18

                              Delayed owing to construction difficulties

                              Udhampur - Quazigund 167

                              Inauguration of Final section KVRbull Prime Minister Dr Manmohan

                              Singh flagged off a train from Anantnag to Quazigund to inaugurate the final 18 km of the railway through the Kashmir Valley on October 28 2009

                              bull The currently isolated line will eventually be joined to the Indian rail network at Udhampur providing an all -weather transport link between the state of Jammu amp Kashmir and the rest of India which has been designated as a national priority

                              Thanks

                              • Kashmir Rail Project Challenges solutions and current status
                              • Kashmir Railway Project (KRP)
                              • Project Details
                              • Slide 4
                              • Challenges
                              • Slide 6
                              • Slide 7
                              • Security Challenges
                              • Project Sub sections
                              • Slide 10
                              • Rolling Stock
                              • Rolling Stock (contdhellip)
                              • Responsibility
                              • Financials
                              • Infrastructure and construction
                              • Pir Panjal Tunnel(T-80)
                              • Slide 17
                              • Slide 18
                              • Slide 19
                              • Chenab Bridge
                              • Slide 21
                              • Operational Accidents amp Casualities
                              • Slide 23
                              • Current Status
                              • Slide 25
                              • Inauguration of Final section KVR
                              • Thanks

                                Pir Panjal Tunnel(T-80)bull At 1096km long the Pir Panjal Railway Tunnel is Indias longest and Asias 2nd

                                longest tunnel

                                bull passes through the Pir Panjal mountain range in Jammu and Kashmir in India

                                bull aimed at reducing the travel distance between Quazigund and Banihal to only 11 km

                                bull cover the distance from the south to the north side of the mountain in 66 minutes

                                bull Completed in October 2011

                                bull cost of Rs10bn ($2018m)

                                bull Construction of the tunnel was carried out by Hindustan Construction Company and took over six years

                                Pir Panjal Tunnel(T-80)bull 84m-wide and 73m-high tunnel and is up to 1 100 m below the surface

                                bull construction of a 3m-wide road that runs alongside the railway tunnel for maintenance and emergency evacuation

                                bull 100 percent water-proof and is also equipped with fire fighting system throughout its entire length

                                bull construction of the tunnel started in November 2005 and was complete in 2011

                                bull The fascinating fact about the tunnel excavation is that the total excavated quantity was equal to one mountain

                                bull It runs 440m below the existing Jawahar Tunnel which is the only road link from the region to the rest of India meant for vehicular traffic only- which usually gets blocked during winters owing to heavy snowfall in the region

                                bull due to the changing geological strata of the young Himalayan rock New Australian Tunneling Methodology (NATM) was adopted for the construction

                                Chenab Bridgebull The Chenab Bridge will be the highest railway structure of its kind in the world

                                35 m higher than the tip of the Eiffel Tower in Paris

                                bull The Chenab bridge is 13 km long and has the third largest arch span in the world At 1178 feet it will be the highest bridge in the world once completed

                                bull Located near the Salal Hydro Power Dam the bridge was originally planned as a 1315 metre-long bridge having 17 spans

                                bull Afcons Infrastructure Limited was awarded the contract for the bridge

                                bull While deciding to stop all construction works on the Katra-Qazigund section in 2008 the Railway Ministry had proposed a change in the location of the bridge from the gorge to a wide valley two to three kilometers upstream of the original location Since the newly proposed location had a higher bed level the height of the bridge had it been constructed there would have come down to about 120-150 meters from river bed

                                bull The Railways decided to stick to the location it had originally chosen to construct the Chenab Bridge mdash billed as the highest in the world at a height of 359 metres from the river bed At 343 metres Millau Viaduct in France is the tallest bridge in the world

                                Operational Accidents amp Casualitiesbull June 2004 mdash Sudhir Kumar Pundir an IRCON Engineer and his brother Sanjay

                                were kidnapped and murdered by terrorists in the valley

                                bull June 2005 mdash Altaf Hussain A laborer working in a Tunnel at Tathyar (HCC) was killed by a collapse Two others were injured

                                bull May 16 2007 mdashdaughter of Mushtaq Ahmad Wagay and daughter of Mohammad Ayub Wani (9 amp 7 yrs)drowned in a ditch constructed by Railway Company

                                bull Feb 14 2008 mdash A Nepali labourer Tika Ram Balwari son of Tuya Narayan was killed after a boulder hit him in at Uri Varmul presumably on the Kashmir rail project for HCC

                                bull Apr 18 2008 mdash Six labourers of a private company engaged with the Katra-Qazigund railway line project were killed and two others received injuries when a tipper carrying them rolled down into a deep gorge in Lower Juda Morh near Kouri in Reasi district late at night

                                bull Mar 27 2011 mdash Two workers were killed at an under-construction railway bridge over the Chenab in Reasi district as a basket attached to a crane carrying them unhooked and fell from a height of more than 100 metres

                                Current Status

                                bull The USBRL project is divided into four sections

                                bull Leg 0 extending 53 kilometres (33 mi) from Jammu to Udhampur completed in April 2005

                                bull Leg 1 extending 25 kilometres (16 mi) from Udhampur to Katra Under construction may open in 2013

                                bull Leg 2 extending 148 kilometres (92 mi) from Katra to Qazigund Under construction may open in 2017

                                bull Leg 3 extending 119 kilometres (74 mi) from Qazigund to Baramulla completed in October 2009

                                Inauguration of Kashmir rail linkDate Section Length km

                                April 2005 Jammu - Udhampur Current Status

                                53

                                October 2008 Anantnag - Mazhom 66

                                February 2009 Mazhom - Baramulla 35

                                October 2009 Quazigund - Anantnag 18

                                Delayed owing to construction difficulties

                                Udhampur - Quazigund 167

                                Inauguration of Final section KVRbull Prime Minister Dr Manmohan

                                Singh flagged off a train from Anantnag to Quazigund to inaugurate the final 18 km of the railway through the Kashmir Valley on October 28 2009

                                bull The currently isolated line will eventually be joined to the Indian rail network at Udhampur providing an all -weather transport link between the state of Jammu amp Kashmir and the rest of India which has been designated as a national priority

                                Thanks

                                • Kashmir Rail Project Challenges solutions and current status
                                • Kashmir Railway Project (KRP)
                                • Project Details
                                • Slide 4
                                • Challenges
                                • Slide 6
                                • Slide 7
                                • Security Challenges
                                • Project Sub sections
                                • Slide 10
                                • Rolling Stock
                                • Rolling Stock (contdhellip)
                                • Responsibility
                                • Financials
                                • Infrastructure and construction
                                • Pir Panjal Tunnel(T-80)
                                • Slide 17
                                • Slide 18
                                • Slide 19
                                • Chenab Bridge
                                • Slide 21
                                • Operational Accidents amp Casualities
                                • Slide 23
                                • Current Status
                                • Slide 25
                                • Inauguration of Final section KVR
                                • Thanks

                                  Pir Panjal Tunnel(T-80)bull 84m-wide and 73m-high tunnel and is up to 1 100 m below the surface

                                  bull construction of a 3m-wide road that runs alongside the railway tunnel for maintenance and emergency evacuation

                                  bull 100 percent water-proof and is also equipped with fire fighting system throughout its entire length

                                  bull construction of the tunnel started in November 2005 and was complete in 2011

                                  bull The fascinating fact about the tunnel excavation is that the total excavated quantity was equal to one mountain

                                  bull It runs 440m below the existing Jawahar Tunnel which is the only road link from the region to the rest of India meant for vehicular traffic only- which usually gets blocked during winters owing to heavy snowfall in the region

                                  bull due to the changing geological strata of the young Himalayan rock New Australian Tunneling Methodology (NATM) was adopted for the construction

                                  Chenab Bridgebull The Chenab Bridge will be the highest railway structure of its kind in the world

                                  35 m higher than the tip of the Eiffel Tower in Paris

                                  bull The Chenab bridge is 13 km long and has the third largest arch span in the world At 1178 feet it will be the highest bridge in the world once completed

                                  bull Located near the Salal Hydro Power Dam the bridge was originally planned as a 1315 metre-long bridge having 17 spans

                                  bull Afcons Infrastructure Limited was awarded the contract for the bridge

                                  bull While deciding to stop all construction works on the Katra-Qazigund section in 2008 the Railway Ministry had proposed a change in the location of the bridge from the gorge to a wide valley two to three kilometers upstream of the original location Since the newly proposed location had a higher bed level the height of the bridge had it been constructed there would have come down to about 120-150 meters from river bed

                                  bull The Railways decided to stick to the location it had originally chosen to construct the Chenab Bridge mdash billed as the highest in the world at a height of 359 metres from the river bed At 343 metres Millau Viaduct in France is the tallest bridge in the world

                                  Operational Accidents amp Casualitiesbull June 2004 mdash Sudhir Kumar Pundir an IRCON Engineer and his brother Sanjay

                                  were kidnapped and murdered by terrorists in the valley

                                  bull June 2005 mdash Altaf Hussain A laborer working in a Tunnel at Tathyar (HCC) was killed by a collapse Two others were injured

                                  bull May 16 2007 mdashdaughter of Mushtaq Ahmad Wagay and daughter of Mohammad Ayub Wani (9 amp 7 yrs)drowned in a ditch constructed by Railway Company

                                  bull Feb 14 2008 mdash A Nepali labourer Tika Ram Balwari son of Tuya Narayan was killed after a boulder hit him in at Uri Varmul presumably on the Kashmir rail project for HCC

                                  bull Apr 18 2008 mdash Six labourers of a private company engaged with the Katra-Qazigund railway line project were killed and two others received injuries when a tipper carrying them rolled down into a deep gorge in Lower Juda Morh near Kouri in Reasi district late at night

                                  bull Mar 27 2011 mdash Two workers were killed at an under-construction railway bridge over the Chenab in Reasi district as a basket attached to a crane carrying them unhooked and fell from a height of more than 100 metres

                                  Current Status

                                  bull The USBRL project is divided into four sections

                                  bull Leg 0 extending 53 kilometres (33 mi) from Jammu to Udhampur completed in April 2005

                                  bull Leg 1 extending 25 kilometres (16 mi) from Udhampur to Katra Under construction may open in 2013

                                  bull Leg 2 extending 148 kilometres (92 mi) from Katra to Qazigund Under construction may open in 2017

                                  bull Leg 3 extending 119 kilometres (74 mi) from Qazigund to Baramulla completed in October 2009

                                  Inauguration of Kashmir rail linkDate Section Length km

                                  April 2005 Jammu - Udhampur Current Status

                                  53

                                  October 2008 Anantnag - Mazhom 66

                                  February 2009 Mazhom - Baramulla 35

                                  October 2009 Quazigund - Anantnag 18

                                  Delayed owing to construction difficulties

                                  Udhampur - Quazigund 167

                                  Inauguration of Final section KVRbull Prime Minister Dr Manmohan

                                  Singh flagged off a train from Anantnag to Quazigund to inaugurate the final 18 km of the railway through the Kashmir Valley on October 28 2009

                                  bull The currently isolated line will eventually be joined to the Indian rail network at Udhampur providing an all -weather transport link between the state of Jammu amp Kashmir and the rest of India which has been designated as a national priority

                                  Thanks

                                  • Kashmir Rail Project Challenges solutions and current status
                                  • Kashmir Railway Project (KRP)
                                  • Project Details
                                  • Slide 4
                                  • Challenges
                                  • Slide 6
                                  • Slide 7
                                  • Security Challenges
                                  • Project Sub sections
                                  • Slide 10
                                  • Rolling Stock
                                  • Rolling Stock (contdhellip)
                                  • Responsibility
                                  • Financials
                                  • Infrastructure and construction
                                  • Pir Panjal Tunnel(T-80)
                                  • Slide 17
                                  • Slide 18
                                  • Slide 19
                                  • Chenab Bridge
                                  • Slide 21
                                  • Operational Accidents amp Casualities
                                  • Slide 23
                                  • Current Status
                                  • Slide 25
                                  • Inauguration of Final section KVR
                                  • Thanks

                                    Chenab Bridgebull The Chenab Bridge will be the highest railway structure of its kind in the world

                                    35 m higher than the tip of the Eiffel Tower in Paris

                                    bull The Chenab bridge is 13 km long and has the third largest arch span in the world At 1178 feet it will be the highest bridge in the world once completed

                                    bull Located near the Salal Hydro Power Dam the bridge was originally planned as a 1315 metre-long bridge having 17 spans

                                    bull Afcons Infrastructure Limited was awarded the contract for the bridge

                                    bull While deciding to stop all construction works on the Katra-Qazigund section in 2008 the Railway Ministry had proposed a change in the location of the bridge from the gorge to a wide valley two to three kilometers upstream of the original location Since the newly proposed location had a higher bed level the height of the bridge had it been constructed there would have come down to about 120-150 meters from river bed

                                    bull The Railways decided to stick to the location it had originally chosen to construct the Chenab Bridge mdash billed as the highest in the world at a height of 359 metres from the river bed At 343 metres Millau Viaduct in France is the tallest bridge in the world

                                    Operational Accidents amp Casualitiesbull June 2004 mdash Sudhir Kumar Pundir an IRCON Engineer and his brother Sanjay

                                    were kidnapped and murdered by terrorists in the valley

                                    bull June 2005 mdash Altaf Hussain A laborer working in a Tunnel at Tathyar (HCC) was killed by a collapse Two others were injured

                                    bull May 16 2007 mdashdaughter of Mushtaq Ahmad Wagay and daughter of Mohammad Ayub Wani (9 amp 7 yrs)drowned in a ditch constructed by Railway Company

                                    bull Feb 14 2008 mdash A Nepali labourer Tika Ram Balwari son of Tuya Narayan was killed after a boulder hit him in at Uri Varmul presumably on the Kashmir rail project for HCC

                                    bull Apr 18 2008 mdash Six labourers of a private company engaged with the Katra-Qazigund railway line project were killed and two others received injuries when a tipper carrying them rolled down into a deep gorge in Lower Juda Morh near Kouri in Reasi district late at night

                                    bull Mar 27 2011 mdash Two workers were killed at an under-construction railway bridge over the Chenab in Reasi district as a basket attached to a crane carrying them unhooked and fell from a height of more than 100 metres

                                    Current Status

                                    bull The USBRL project is divided into four sections

                                    bull Leg 0 extending 53 kilometres (33 mi) from Jammu to Udhampur completed in April 2005

                                    bull Leg 1 extending 25 kilometres (16 mi) from Udhampur to Katra Under construction may open in 2013

                                    bull Leg 2 extending 148 kilometres (92 mi) from Katra to Qazigund Under construction may open in 2017

                                    bull Leg 3 extending 119 kilometres (74 mi) from Qazigund to Baramulla completed in October 2009

                                    Inauguration of Kashmir rail linkDate Section Length km

                                    April 2005 Jammu - Udhampur Current Status

                                    53

                                    October 2008 Anantnag - Mazhom 66

                                    February 2009 Mazhom - Baramulla 35

                                    October 2009 Quazigund - Anantnag 18

                                    Delayed owing to construction difficulties

                                    Udhampur - Quazigund 167

                                    Inauguration of Final section KVRbull Prime Minister Dr Manmohan

                                    Singh flagged off a train from Anantnag to Quazigund to inaugurate the final 18 km of the railway through the Kashmir Valley on October 28 2009

                                    bull The currently isolated line will eventually be joined to the Indian rail network at Udhampur providing an all -weather transport link between the state of Jammu amp Kashmir and the rest of India which has been designated as a national priority

                                    Thanks

                                    • Kashmir Rail Project Challenges solutions and current status
                                    • Kashmir Railway Project (KRP)
                                    • Project Details
                                    • Slide 4
                                    • Challenges
                                    • Slide 6
                                    • Slide 7
                                    • Security Challenges
                                    • Project Sub sections
                                    • Slide 10
                                    • Rolling Stock
                                    • Rolling Stock (contdhellip)
                                    • Responsibility
                                    • Financials
                                    • Infrastructure and construction
                                    • Pir Panjal Tunnel(T-80)
                                    • Slide 17
                                    • Slide 18
                                    • Slide 19
                                    • Chenab Bridge
                                    • Slide 21
                                    • Operational Accidents amp Casualities
                                    • Slide 23
                                    • Current Status
                                    • Slide 25
                                    • Inauguration of Final section KVR
                                    • Thanks

                                      Operational Accidents amp Casualitiesbull June 2004 mdash Sudhir Kumar Pundir an IRCON Engineer and his brother Sanjay

                                      were kidnapped and murdered by terrorists in the valley

                                      bull June 2005 mdash Altaf Hussain A laborer working in a Tunnel at Tathyar (HCC) was killed by a collapse Two others were injured

                                      bull May 16 2007 mdashdaughter of Mushtaq Ahmad Wagay and daughter of Mohammad Ayub Wani (9 amp 7 yrs)drowned in a ditch constructed by Railway Company

                                      bull Feb 14 2008 mdash A Nepali labourer Tika Ram Balwari son of Tuya Narayan was killed after a boulder hit him in at Uri Varmul presumably on the Kashmir rail project for HCC

                                      bull Apr 18 2008 mdash Six labourers of a private company engaged with the Katra-Qazigund railway line project were killed and two others received injuries when a tipper carrying them rolled down into a deep gorge in Lower Juda Morh near Kouri in Reasi district late at night

                                      bull Mar 27 2011 mdash Two workers were killed at an under-construction railway bridge over the Chenab in Reasi district as a basket attached to a crane carrying them unhooked and fell from a height of more than 100 metres

                                      Current Status

                                      bull The USBRL project is divided into four sections

                                      bull Leg 0 extending 53 kilometres (33 mi) from Jammu to Udhampur completed in April 2005

                                      bull Leg 1 extending 25 kilometres (16 mi) from Udhampur to Katra Under construction may open in 2013

                                      bull Leg 2 extending 148 kilometres (92 mi) from Katra to Qazigund Under construction may open in 2017

                                      bull Leg 3 extending 119 kilometres (74 mi) from Qazigund to Baramulla completed in October 2009

                                      Inauguration of Kashmir rail linkDate Section Length km

                                      April 2005 Jammu - Udhampur Current Status

                                      53

                                      October 2008 Anantnag - Mazhom 66

                                      February 2009 Mazhom - Baramulla 35

                                      October 2009 Quazigund - Anantnag 18

                                      Delayed owing to construction difficulties

                                      Udhampur - Quazigund 167

                                      Inauguration of Final section KVRbull Prime Minister Dr Manmohan

                                      Singh flagged off a train from Anantnag to Quazigund to inaugurate the final 18 km of the railway through the Kashmir Valley on October 28 2009

                                      bull The currently isolated line will eventually be joined to the Indian rail network at Udhampur providing an all -weather transport link between the state of Jammu amp Kashmir and the rest of India which has been designated as a national priority

                                      Thanks

                                      • Kashmir Rail Project Challenges solutions and current status
                                      • Kashmir Railway Project (KRP)
                                      • Project Details
                                      • Slide 4
                                      • Challenges
                                      • Slide 6
                                      • Slide 7
                                      • Security Challenges
                                      • Project Sub sections
                                      • Slide 10
                                      • Rolling Stock
                                      • Rolling Stock (contdhellip)
                                      • Responsibility
                                      • Financials
                                      • Infrastructure and construction
                                      • Pir Panjal Tunnel(T-80)
                                      • Slide 17
                                      • Slide 18
                                      • Slide 19
                                      • Chenab Bridge
                                      • Slide 21
                                      • Operational Accidents amp Casualities
                                      • Slide 23
                                      • Current Status
                                      • Slide 25
                                      • Inauguration of Final section KVR
                                      • Thanks

                                        Current Status

                                        bull The USBRL project is divided into four sections

                                        bull Leg 0 extending 53 kilometres (33 mi) from Jammu to Udhampur completed in April 2005

                                        bull Leg 1 extending 25 kilometres (16 mi) from Udhampur to Katra Under construction may open in 2013

                                        bull Leg 2 extending 148 kilometres (92 mi) from Katra to Qazigund Under construction may open in 2017

                                        bull Leg 3 extending 119 kilometres (74 mi) from Qazigund to Baramulla completed in October 2009

                                        Inauguration of Kashmir rail linkDate Section Length km

                                        April 2005 Jammu - Udhampur Current Status

                                        53

                                        October 2008 Anantnag - Mazhom 66

                                        February 2009 Mazhom - Baramulla 35

                                        October 2009 Quazigund - Anantnag 18

                                        Delayed owing to construction difficulties

                                        Udhampur - Quazigund 167

                                        Inauguration of Final section KVRbull Prime Minister Dr Manmohan

                                        Singh flagged off a train from Anantnag to Quazigund to inaugurate the final 18 km of the railway through the Kashmir Valley on October 28 2009

                                        bull The currently isolated line will eventually be joined to the Indian rail network at Udhampur providing an all -weather transport link between the state of Jammu amp Kashmir and the rest of India which has been designated as a national priority

                                        Thanks

                                        • Kashmir Rail Project Challenges solutions and current status
                                        • Kashmir Railway Project (KRP)
                                        • Project Details
                                        • Slide 4
                                        • Challenges
                                        • Slide 6
                                        • Slide 7
                                        • Security Challenges
                                        • Project Sub sections
                                        • Slide 10
                                        • Rolling Stock
                                        • Rolling Stock (contdhellip)
                                        • Responsibility
                                        • Financials
                                        • Infrastructure and construction
                                        • Pir Panjal Tunnel(T-80)
                                        • Slide 17
                                        • Slide 18
                                        • Slide 19
                                        • Chenab Bridge
                                        • Slide 21
                                        • Operational Accidents amp Casualities
                                        • Slide 23
                                        • Current Status
                                        • Slide 25
                                        • Inauguration of Final section KVR
                                        • Thanks

                                          Inauguration of Kashmir rail linkDate Section Length km

                                          April 2005 Jammu - Udhampur Current Status

                                          53

                                          October 2008 Anantnag - Mazhom 66

                                          February 2009 Mazhom - Baramulla 35

                                          October 2009 Quazigund - Anantnag 18

                                          Delayed owing to construction difficulties

                                          Udhampur - Quazigund 167

                                          Inauguration of Final section KVRbull Prime Minister Dr Manmohan

                                          Singh flagged off a train from Anantnag to Quazigund to inaugurate the final 18 km of the railway through the Kashmir Valley on October 28 2009

                                          bull The currently isolated line will eventually be joined to the Indian rail network at Udhampur providing an all -weather transport link between the state of Jammu amp Kashmir and the rest of India which has been designated as a national priority

                                          Thanks

                                          • Kashmir Rail Project Challenges solutions and current status
                                          • Kashmir Railway Project (KRP)
                                          • Project Details
                                          • Slide 4
                                          • Challenges
                                          • Slide 6
                                          • Slide 7
                                          • Security Challenges
                                          • Project Sub sections
                                          • Slide 10
                                          • Rolling Stock
                                          • Rolling Stock (contdhellip)
                                          • Responsibility
                                          • Financials
                                          • Infrastructure and construction
                                          • Pir Panjal Tunnel(T-80)
                                          • Slide 17
                                          • Slide 18
                                          • Slide 19
                                          • Chenab Bridge
                                          • Slide 21
                                          • Operational Accidents amp Casualities
                                          • Slide 23
                                          • Current Status
                                          • Slide 25
                                          • Inauguration of Final section KVR
                                          • Thanks

                                            Inauguration of Final section KVRbull Prime Minister Dr Manmohan

                                            Singh flagged off a train from Anantnag to Quazigund to inaugurate the final 18 km of the railway through the Kashmir Valley on October 28 2009

                                            bull The currently isolated line will eventually be joined to the Indian rail network at Udhampur providing an all -weather transport link between the state of Jammu amp Kashmir and the rest of India which has been designated as a national priority

                                            Thanks

                                            • Kashmir Rail Project Challenges solutions and current status
                                            • Kashmir Railway Project (KRP)
                                            • Project Details
                                            • Slide 4
                                            • Challenges
                                            • Slide 6
                                            • Slide 7
                                            • Security Challenges
                                            • Project Sub sections
                                            • Slide 10
                                            • Rolling Stock
                                            • Rolling Stock (contdhellip)
                                            • Responsibility
                                            • Financials
                                            • Infrastructure and construction
                                            • Pir Panjal Tunnel(T-80)
                                            • Slide 17
                                            • Slide 18
                                            • Slide 19
                                            • Chenab Bridge
                                            • Slide 21
                                            • Operational Accidents amp Casualities
                                            • Slide 23
                                            • Current Status
                                            • Slide 25
                                            • Inauguration of Final section KVR
                                            • Thanks

                                              Thanks

                                              • Kashmir Rail Project Challenges solutions and current status
                                              • Kashmir Railway Project (KRP)
                                              • Project Details
                                              • Slide 4
                                              • Challenges
                                              • Slide 6
                                              • Slide 7
                                              • Security Challenges
                                              • Project Sub sections
                                              • Slide 10
                                              • Rolling Stock
                                              • Rolling Stock (contdhellip)
                                              • Responsibility
                                              • Financials
                                              • Infrastructure and construction
                                              • Pir Panjal Tunnel(T-80)
                                              • Slide 17
                                              • Slide 18
                                              • Slide 19
                                              • Chenab Bridge
                                              • Slide 21
                                              • Operational Accidents amp Casualities
                                              • Slide 23
                                              • Current Status
                                              • Slide 25
                                              • Inauguration of Final section KVR
                                              • Thanks

                                                top related