JURUNATURE SDN. BHD. – COMPANY CURRENT TRACK RECORD
NO WORK DESCRIPTION OWNER COMMENCEMENT
DATE CURRENT STATUS
April 30, 2013
1. PROVISION OF HEAT SHIELD FOR TAPIS EOR PROJECT FOR GUE TELOK PLATFORM
EMEPMI April 2013 In Progress
2. SUPPLY AND INSTALLATION OF HEAT SHIELD FOR KINABALU KNPG-B - MMHE PETRONAS
CARIGALI SDN BHD April 2013 In Progress
3. OFFSHORE CARRY OVER WORKS FOR PIPING OF TAPIS-Q TOPSIDES - MMHE EMEPMI April 2013 In Progress
4.
PROVISION FOR PURCHASE OF STRUCTURAL STEEL PIPES FOR TAPIS B WI HTI PIPE SUPPOR TSTOP (AFS003B) – SHAPADU ENERGY & ENGINEERING SDN BHD
EMEPMI April 2013 In Progress
5.
PROVISION FOR PURCHASE OF STRUCTURAL STEEL PIPES FOR TAPIS C PLATFORM TOPSIDE (EXCLUDE LER) - SHAPADU ENERGY & ENGINEERING SDN BHD
EMEPMI April 2013 In Progress
6.
PROVISION OF FABRICATION AND DELIVERY OF 16” SE-PA RISER LOAD BEARING CLAMP AND SLIDING CLAMP FOR MOC YEAR 2013 PIPELINES INSTALLATION - SAPURA KENCANA PETROLEUM C/O TL OFFSHORE SDN BHD
MURPHY SARAWAK OIL. CO. LTD
April 2013 In Progress
7. M03 DAMAGED FPF COATING REPAIR - DAYANG ENTERPRISE SDN BHD SHELL March 2013 Completed
8. M01 DAMAGED PFP COATING REPAIR - DAYANG ENTERPRISE SDN BHD SHELL March 2013 Completed
9.
PROVISION OF SUPPLY AND DELIVERY OF MONEL WELDING INTEGRATED TRANSPORTATION AND INSTALLATION OF OFFSHORE FACILITIES FOR EARLY PRODUCTION SCHEME (EPS), INTEGRATED GAS DEVELOPMENT (IGD) PROJECT, NORTH MALAY BASIN (NMB) FIELD – GOM RESOURCES SDN BHD
HESS EXPLORATION & PRODUCTION
MSIA B.V. March 2013 In Progress
10.
SUPPLY AND DELIVER OF CEILING FINISHES - SUSPENDED CEILING SYSTEM SOUTH ACIS OIL & GAS DEVELOPMENT PROJECT (REPEAT ORDER) - BROOKE DOCKYARD & ENGINEERING WORKS CORPORATION
BROOKE DOCKYARD & ENGINEERING
WORKS CORPORATION
March 18, 2013 In Progress
11.
ENGINEERING,SUPPLY OF MATERIAL, MANUFACTURING, FABRICATION, INSTALLATION AND MODIFICATION OF FIBERGLASS GRATINGS, STAIRTREADS AND GRE HANDRAILS FOR DAMAR A SUBSTRUCTURE PROJECT - MMHE
EMEPMI March 13, 2013 In Progress
JURUNATURE SDN. BHD. – COMPANY CURRENT TRACK RECORD
NO WORK DESCRIPTION OWNER COMMENCEMENT
DATE CURRENT STATUS
April 30, 2013
12. PROVISION OF FIELD JOINT COATING SERVICES FOR EMEPMI 2013 TAPIS & DAMAR OFFSHORE INSTALLATION WORK – TL OFFSHORE
EMEPMI March 8, 2013 In Progress
13.
SUPPLY & DELIVERY OF FIELD JOINT ANTI CORROSION COATING SYSTEM – HEAT SHRINK SLEEVE (RAYCHEM WPC100) FOR EMEPMI 2013 TAPIS & DAMAR OFFSHORE INSTALLATION WORK – TL OFFSHORE
EMEPMI March 8, 2013 In Progress
14. PROVISION OF PIPELINE FIELD JOINT INFILL MATERIAL FOR TAPIS EOR & DAMAR GAS DEVELOPMENT PROJECT Y2013
EMEPMI March 7, 2013 In Progress
15. PROVISION OF FIRE PROTECTION (PFP) AND INSULATION WORK FOR WEST DESARU TOPSIDES - THHE FABRICATORS SDN BHD
AQUATERRA ENERGY LIMITED
March 7, 2013 In Progress
16. PROVISION OF FIELD JOINT COATING SERVICES FOR HESS 2013 PROJECT – GOM RESOURCES
HESS February 26, 2013 In Progress
17. PROVISION TO SUPPLY AND DELIVER CRUDE OIL WASHING MACHINE (COW MACHINE) SUPPLY FOR BERANTAI OPERATION - PETROFAC
PETRONAS January 29, 2013 In Progress
18. SUBCONTRACTOR FOR PASSIVE FIRE PROTECTION WORKS FOR KBB TOSIDES - MMHE
KPOC January 21, 2013 In Progress
19. ARCHITECTURAL INSULATION PACKAGE SUPPLY OF M90 FIRETEX FOR GREATER EKOFISK AREA 2/4 - SMOE
CONOCO PHILIPS January 15, 2013 In Progress
20. PROVISION OF 3
RD CAMPAIGN SEA-FASTENING WORKS OF J-LAY AND PES
TOWER ON BOARD SAPURA 3000 – SAPURA ACERGY SDN BHD SHELL January 11, 2013 In Progress
21.
PROVISION OF SUPPLY AND DELIVERY OF CEILING FINISHES – SUSPENDED CEILING FOR SOUTH ACIS PROJECT – BROOKE DOCKYARD AND ENGINEERING WORKS.
MURPHY January 10, 2013 Completed
22. DESIGN, FABRICATION & DELIVERY OF FIREWALL FOR DAMAR-A TOPSIDE MMHE
EMEPMI January 08, 2013 In Progress
23. SUPPLY OF PAINT EMEPMI December 27, 2013 Completed
JURUNATURE SDN. BHD. – COMPANY CURRENT TRACK RECORD
NO WORK DESCRIPTION OWNER COMMENCEMENT
DATE CURRENT STATUS
April 30, 2013
24.
E & I WORKS-FABRICATION AND INSTALLATION FOR F14DR-A TOPSIDES & F14/F29 PROCESS MODULE – MALAYSIA MARINE AND HEAVY ENGINEERING SDN. BHD.
SHELL December 17, 2012 In Progress
25. STRUCTURE WORKS FOR DAMAR-A PLATFORM (TOPSIDE) - MMHE EMEPMI November 12, 2012 In Progress
26. SUPPLY OF INSULATION MATERIALS FOR FABRICATION OF KEBABANGAN TOPSIDES (5.12M003C) – MALAYSIA MARINE HEAVY ENGINEERING SDN. BHD.
KPOC October 18, 2012 In Progress
27.
SUPPLY, DELIVERY, AND INSTALLATION SUPERVISION OF COMPOSITE MATERIALS (FIBERGLASS) & ACCESSORIES FOR WAVE ZONE GRATING FOR GUNTONG A STRUCTURAL AND PIPING SYSTEM REPAIR PROGRAM, EMEPMI EPCM BROWNFIELD PROJECT.
EMEPMI October 5, 2012 Completed
28. SUPPLY AND DELIVER OF OFFICE EQUIPMENT (HS1146630X FIRE FIGHTING SUIT) HS1146630X FIRE FIGHTING SUIT
UNIVERSITI TELNOLOGI
PETRONAS, TRONOH PERAK
October 2012 Completed
29.
SUPPLY OF INSULATION MATERIALS FOR FABRICATION OF KEBABANGAN TOPSIDES (BOAQ)(5.12M002B) – MALAYSIA MARINE HEAVY ENGINEERING SDN. BHD.
KPOC September 24, 2012 In Progress
30. SUPPLY OF INSULATION MATERIALS FOR FABRICATION OF KEBABANGAN TOPSIDES (5.12M003C) – MALAYSIA MARINE HEAVY ENGINEERING SDN. BHD.
KPOC September 24, 2012 In Progress
31.
PROVISION OF FABRICATION 18” AND 12” FLEXIJOINT BODY SUPPORT ON ERECTOR FOR GUMUSUT KAKAP, J-LAY TOWER REFURBISHMENT 2012 PROJECT – SAPURA ACERGY SDN BHD
SHELL September 13, 2012 Completed
32.
PROVISION OF FABRICATION 8” AND 10” STRESSJOINT BODY SUPPORT ON ERECTOR FOR GUMUSUT KAKAP, J-LAY TOWER REFURBISHMENT 2012 PROJECT – SAPURA ACERGY SDN BHD
SHELL September 12, 2012 Completed
33. PROVISION OF FIELD JOINT COATING SERVICES FOR 8" AND 10" MALIKAI PIPELINE – GOM RESOURCES
SHELL September 11, 2012 Completed
34.
PROVISION OF FABRICATE AND SUPPLY OF WS2 UPPER MAST ELEMENT 2 LIFTING PAD EYE FOR GUMUSUT KAKAP, J-LAY TOWER REFURBISIHMENT 2012 PROJECT – SAPURA ACERGY SDN BHD
SHELL September 5, 2012 In Progress
JURUNATURE SDN. BHD. – COMPANY CURRENT TRACK RECORD
NO WORK DESCRIPTION OWNER COMMENCEMENT
DATE CURRENT STATUS
April 30, 2013
35.
PROVISION OF FABRICATE AND SUPPLY OF NEW 18” ESCALATOR TROLLEY INSERTS, ACCESS TO HPU BOOST PUMPS, WS2 LOWER MAST ELEMENT 2, WS2 HINGE HATCH COVER, WS1 RAIN PROTECTION IMPROVEMENT FOR GUMUSUT KAKAP, J-LAY TOWER REFURBISIHMENT 2012 PROJECT – SAPURA ACERGY SDN BHD
SHELL September 5, 2012 In Progress
36. PROVISION OF TELECOMMUNICATION SYSTEM (VSAT) – SCOPETEL SDN. BHD SCOPETEL August 30, 2012 In Progress
37. PROVISION OF DISPOSAL OF DAMAGED KOSMO, IVECO AND MAN BUSES AND ITS COMPONENTS – SYARIKAT PRASANA NEGARA BERHAD
SPNB August 29, 2012 Completed
38. SUPPLY AND INSTALLATION OF PASSIVE FIRE PROTECTION (PFP) FOR TAPIS Q TOPSIDE – MMHE SDN BHD
EMEPMI August 28, 2012 In Progress
39. SUPPLY AND DELIVERY OF HSS (WPC100M) FOR MALIKAI PIPELINE – GOM RESOURCES
SHELL August 18, 2012 Completed
40. SUPPLY AND INSTALLATION OF PASSIVE FIRE PROTECTION (PFP) FOR TELOK A TOPSIDES – MMHE SDN BHD
EMEPMI August 9, 2012 Completed
41. PROVISION OF VSAT SERVICES IN GULF OF MEXICO – SAPURA ACERGY SDN BHD
GULF August 9, 2012 In Progress
42.
PROVISION OF FIELD JOINT COATING SERVICES AND SUPPLY OF ANTICORROSSION TAPE (SERVIWRAP M30B) FOR 6" X 7.6KM BEKOK-A TO TIONG-A PIPELINE INSTALLATION – GOM RESOURCES
PETRONAS August 2, 2012 Completed
43. SUPPLY OF VINYL COATED CHAIN LINK FABRIC FOR EMEPMI’S TABU A STRUCTURAL REPAIR PROJECT – PERUNDING RANHILL WORLEY
EMEPMI July 31, 2012 Completed
44. SUPPLY AND DELIVER OF HEAVY DUTY ANTI SLIP STEP COVER – TALISMAN MALAYSIA LIMITED
TALISMAN July 12, 2012 Completed
45. PROVISION OF TELECOMMUNICATION SYSTEM FOR TOISA PALADIN – FUGRO GEODETIC (M) SDN BHD
FUGRO GEODETIC July 12, 2012 In Progress
46.
FABRICATION AND INSTALLATION OF STRUCTURE WORKS FOR PACKAGE 1, DECK NORTH AND MISC FOR TAPIR R TOPSIDES PROJECT – SIME DARBY ENGINEERING SDN. BHD.
EMEPMI July 10, 2012 In Progress
JURUNATURE SDN. BHD. – COMPANY CURRENT TRACK RECORD
NO WORK DESCRIPTION OWNER COMMENCEMENT
DATE CURRENT STATUS
April 30, 2013
47.
SUBCONTRACT FOR PIPING WORKS FOR PACKAGE B: B-193 A-Q (LIVING QUARTERS, POWER GENERATION & WATER INJECTION) AND PACKAGE B: B-193 A-P FOR (PGC & AGRU) – SIME DARBY ENGINEERING SDN BHD
OIL AND NATURAL GAS CORPORATION
LTD (ONGC) July 07, 2012 In Progress
48.
SUBCONTRACT FOR PIPING WORKS FOR PACKAGE B: B-193 A-Q (LIVING QUARTERS, POWER GENERATION & WATER INJECTION) – SIME DARBY ENGINEERING SDN BHD
OIL AND NATURAL GAS CORPORATION
LTD (ONGC) July 04, 2012 Completed
49. SUPPLY OF VINYL COATED CHAIN LINK FABRIC FOR EMEPMI’S PALAS A STRUCTURAL REPAIR PROJECT – PERUNDING RANHILL WORLEY
EMEPMI July 04, 2012 Completed
50. SUPPLY AND DELIVER OFSLIDING PLATE FOR FABRICATION ON KBB TOPSIDES (BOAQ) - MMHE
KPOC July 02,2012 In Progress
51.
TO SUPPLY MATERIALS, EQUIPMENT, CONSUMABLES, TOOLS AND MANPOWER FOR COOLING MANIFOLD RELOCATION FOR GUMUSUT KAKAP, J LAY TOWER REFURBISHMENT 2012 PROJECT – SAPURA ACERGY SDN BHD
SHELL June 12, 2012 Completed
52. PROVIDING COMMUNICATION SYSTEMS (VSAT) AND SERVICES IN SUPPORT OF VESSEL DLB264 – GOM RESOURCES
GOM RESOURCES June 11, 2012 In Progress
53. PROVISION OF PULLING & REMOVE CABLE FOR LNGC SERI ALAM – MMHE SDN. BHD.
MISC May 21, 2012 Completed
54. SUPPLY, FABRICATE AND DELIVERY SEA FASTENING FOR CARGO BARGE FOR LAN DO DEVELOPMENT PROJECT – SAPURA ACERGY SDN BHD
TNK VIETNAM BV May 17, 2012 In Progress
55.
PROVISION OF FIELD JOINT COATING SERVICES FOR MOC TRANSPORTATION AND INSTALLATION OF OFFSHORE PIPELINES AND FACILITIES FOR YEAR 2012 – TL OFFSHORE SDN BHD
MURPHY OIL May 9, 2012 Completed
56. SUPPLY AND INSTALLATION OF PASSIVE FIRE PROTECTION AT PM318-PUTERI FWS PIPELINE REPLACEMENT PROJECT - NEWFIELD
NEWFIELD April 9, 2012 Completed
57. PROVISION OF VSAT TELECOMMUNICATION AND SERVICES FOR PETRONAS CARIGALI SDN BHD – IPERINTIS SDN BHD
IPERINTIS April 6, 2012 In Progress
58. PROVIDING COMMUNICATION SYSTEMS (VSAT) AND SERVICES - SCHLUMBERGER GROUP
SCHLUMBERGER April 4, 2012 In Progress
59. PROVIDING COMMUNICATION SYSTEMS (VSAT) AND SERVICES - HALLIBURTON ENERGY SERVICES (M) SDN BHD
HALLIBURTON April 4, 2012 In Progress
JURUNATURE SDN. BHD. – COMPANY CURRENT TRACK RECORD
NO WORK DESCRIPTION OWNER COMMENCEMENT
DATE CURRENT STATUS
April 30, 2013
60. PROVIDING COMMUNICATION SYSTEMS (VSAT) AND SERVICES IN SUPPORT OF HEAVY LIFT PIPE LAY VESSEL LTS3000
L & T SAPURA April 1, 2012 In Progress
61. DESIGN, FABRICATION AND DELIVERY OF FIREWALL FOR TELOK A & B PROJECT – MMHE SDN BHD
SHELL March 23, 2012 In Progress
62. COMMISSIONING OF STABILISED VSAT SERVICES AND VPN ONBOARD MV. WANGSAMAJU – OCEANTECH GEOMATICS
OCEANTECH GEOMATIC
March 14, 2012 In Progress
63.
PROVISION OF FIELD JOINT COATING AND SUPPLY OF ANTI CORROSION TAPE (SERVIWRAP M30B) FOR KEBABANGAN DEVELOPMENT PROJECT – GLOBAL OFFSHORE MALAYSIA
KPOC March 13, 2012 Completed
64.
SUPPLY AND DELIVERY OF HANGER FLANGE, RISER GUARD AND RISER CLAMP FOR PROVISION OF HOOK-UP AND COMMISSIONING FOR PCSB SKO PIPELINE REJUVENATION PROJECT. – CARIMIN ENGINEERING SERVICES
PETRONAS March 12, 2012 Completed
65. PROVISION OF TELECOMMUNICATION SYSTEM (VSAT) – SCOPETEL SDN. BHD SCOPETEL March 5, 2012 In Progress
66.
SUPPLY AND DELIVERY OF ELECTRICAL FITTINGS AND ACCESSORIES FOR TCOT PWSU TAIL END & REMEDIAL WORK FOR EMEPMI EPCM BROWNFIELD PROJECT – PERUNDING RANHILL WORLEY
EMEPMI March 1, 2012 Completed
67. PROVISION OF FIELD JOINT COATING FOR SOGT PROJECT – ALAM SWIBER PETRONAS February 27, 2012 Completed
68.
PROVISION OF FIELD JOINT COATING AND SUPPLY OF HSS (RAYCHEM WPC100M) FOR EMEMPI’S TAPIS EOR REJUVENATION AND TELOK DEVELOMENT PROJECT. – TL OFFSHORE SDN BHD
EMEPMI February 24, 2012 Completed
69. DESIGN, ENGINEERING, AND DELIVERY OF FAIRINGS & THRUST COLLARS FOR DRILLING RISERS – SONGA OFFSHORE
PETRONAS February 22, 2012 Completed
70. PROVIDING STABILISED VSAT SYSTEM FOR SEMI-SUBMERSIBLE RIG, OCEANROVER FOR DEEPWATER PROJECT, KIKEH – DIAMOND OFFSHORE
MURPHY OIL February 14, 2012 In Progress
71. PROVISION OF VSAT SYSTEM AND PROVIDING VPN RENTAL SERVICES FOR DLB264 – GLOBAL OFFSHORE MALAYSIA
GLOBAL OFFSHORE February 09, 2012 In Progress
72. PIPELINE AND SPOOLS FIELD JOINT COATING SERVICES FOR LAN DO DEVELOPMENT PROJECT VIETNAM – SAPURA ACERGY SDN BHD
TNK VIETNAM BV January 20, 2012 Completed
JURUNATURE SDN. BHD. – COMPANY CURRENT TRACK RECORD
NO WORK DESCRIPTION OWNER COMMENCEMENT
DATE CURRENT STATUS
April 30, 2013
73.
PROVISION FOR DETAILED DESIGN ENGINEERING SERVICES FOR PACKAGE THIRD PARTY VERIFICATION OF GUE H RATED FIREWALL TO WITH STAND 30-MINUTES JET FIRE FOR TELOK GAS DEVELOPMENT PROJECT – PERUNDING RANHILL WORLEY SDN BHD
EMEPMI December 29, 2011 Completed
74. PROVISION OF INSTALLATION AND MAINTENANCE OF VPN INTERNET SERVICES – ASIAN SUPPLY BASE SDN BHD
ASIAN SUPPLY BINTULU
December 21, 2011 In Progress
75. SUPPLY AND INSTALLATION OF PASSIVE FIRE PROTECTION AT M01 AND E11 FOR TI-FIX AND IR PROJECT - SHELL
SHELL December 21, 2011 In Progress
76. SUPPLY MANPOWER, EQUIPMENTS AND MATERIALS FOR PM329 EAST PIATU TOPSIDES – KENCANA HL SDN BHD
NEWFIELD December 1, 2011 Completed
77. E & I FABRICATION, INSTALLATION, TESTING, PRE-COMMISSIONING WORK, FOR TAPIS EOR PROJECT (PACKAGE B AND PACKAGE C) – MMHE SDN BHD
EMEPMI December, 2011 Completed
78. PIPING FABRICATION AND INSTALLATION FOR TAPIS Q LIVING QUARTERS – MMHE SDN BHD
EMEPMI November, 2011 In Progress
79. SUPPLY OF H120 FIRE/BLAST WALL FOR KEBABANGAN TOPSIDES – SIME DARBY ENGINEERING SDN BHD
KPOC November 25, 2011 In Progress
80. PROVISION OF FIELD JOINT COATING FOR BCOT PROJECT – ALAM SWIBER PETRONAS October 10, 2011 Completed
81.
PROVISION OF REMOVAL, REPAIR, & REINSTATEMENT OF PASSIVE FIRE PROTECTION CASTING FOR SDV ON BUNGA RAYA-B – APEX ENERGY SDN. BHD.
TALISMAN September 27, 2011 Completed
82.
PROVISION OF PASSIVE FIRE PROTECTION (PFP) SERVICES FOR PCC OF TOPSIDES AND PIPELINE FOR PM318 PUTERI PIPELINE RESTORATION PROJECT – KENCANA HL SDN BHD
NEWFIELD September 15, 2011 Completed
83.
PROVISION OF FIELD JOINT COATING AND SUPPLY OF ANTI CORROSION MATERIAL (SERVIWRAP) FOR 14” AND 24” EXPORT PIPELINE SHORE APPROACH INSTALLATION FOR KEBABANGAN NORTHERN HUB DEVELOPMENT – PBJV GROUP SDN BHD
PETRONAS CARIGALI SDN BHD
September 15, 2011 Completed
84.
PROVISION OF PASSIVE FIRE PROTECTION (PFP), TOOLS/ EQUIPMENT & MATERIALS TO REMOVE THE DEGRADED PFP & APPLICATION OF NEW PFP AT M3PQ-A LIVING QUARTER WEST WALL – SARKU ENGINEERING SERVICES SDN. BHD.
SHELL September 15, 2011 Completed
JURUNATURE SDN. BHD. – COMPANY CURRENT TRACK RECORD
NO WORK DESCRIPTION OWNER COMMENCEMENT
DATE CURRENT STATUS
April 30, 2013
85.
PROVISION OF REMOVAL, REPAIR, & REINSTATEMENT OF PASSIVE FIRE PROTECTION SYSTEM FOR HELANG TOPSIDES (E-9550 & E-9650) – MONT TRINITY
NIPPON OIL September 12, 2011 Completed
86.
PROVISION OF FIELD JOINT COATING AND SUPPLY OF ANTI CORROSION MATERIALS (SERVIWRAP) FOR INTRAGRATED TRANSPORTATION & INSTALLATION OF OFFSHORE FACILITIES (TIONG A) PROJECT – GLOBAL OFFSHORE MALAYSIA SDN BHD
NEWFIELD August 17, 2011 Completed
87. PROVISION OF REMOVAL, REPAIR & REINSTATEMENT OF BLASTWALL ON M3P-Q PLATFORM – DAYANG ENTERPRISE & SSB
SHELL August 5, 2011 Completed
88.
DESIGN, MANUFACTURE AND SUPPLY OF VIV SUSPRESSION STRAKES FOR BLOCK 06.1 PHASE III PROJECT – LAN DO DEVELOPMENT PROJECT – RANHILL WORLEYPARSONS SDN BHD
BP EXPLORATION OPERATING CO. LTD
August 3, 2011 Completed
89. SUPPLY, DELIVERY AND INSTALLATION OF STRAKES FOR GUMUSUT KAKAP JUMPERS - FMC
SHELL June 17,2011 Completed
90.
PROVISION OF FIELD JOINT COATING AND SUPPLY OF ANTI CORROSION MATERIALS (SERVIWRAP) FOR TRANSPORTATION AND INSTALLATION OF OFFSHORE FACILITIES FOR SKO PIPELINE REPLACEMENT PROJECT – TARGET ENERGY CO. (M) SDN. BHD.
PETRONAS CARIGALI SDN BHD
July 25, 2011 Completed
91.
FABRICATION AND INSTALLATION OF TAPIS-R DECK (NORTH) TAPIS-R DECK (SOUTH), TAPIS-R LIVING QUARTERS & BRIDGES SKID BEAM AND TAPIS-Q DECK – MMHE SDN. BHD.
EMEPMI July 15, 2011 In Progress
92. FABRICATION AND INSTALLATION OF TAPIS-R DECK (NORTH), TAPIS-Q DECK, MISCELLANEOUS WORKS TAPIS-Q – MMHE SDN. BHD.
EMEPMI July 3, 2011 In Progress
93. PROVISION OF PIPELINE FIELD JOINT COATING WORKS FOR THE FABRICATION SERVICES OF FLOWLINE JUMPER – LABUAN SHIPYARD
SAPURA ACERGY/ SHELL
April 14, 2011 Completed
94.
PROVISION OF PIPELINE INFIELD FIELD JOINT COATING FOR PCSB INTERGRATED TRANSPORTATION INSTALLATION OF OFFSHORE FACILITIES FOR YEAR 2010-2012 – GLOBAL OFFSHORE MALAYSIA SDN BHD
PETRONAS CARIGALI SDN BHD
April 12, 2011 Completed
95.
PROVISION OF PIPELINE ANTI CORROSION MATERIAL (SERVIWRAP) FOR PCSB INTERGRATED TRANSPORTATION INSTALLATION OF OFFSHORE FACILITIES FOR YEAR 2010-2012 – GLOBAL OFFSHORE MALAYSIA SDN BHD
PETRONAS CARIGALI SDN BHD
March 31, 2011 Completed
JURUNATURE SDN. BHD. – COMPANY CURRENT TRACK RECORD
NO WORK DESCRIPTION OWNER COMMENCEMENT
DATE CURRENT STATUS
April 30, 2013
96. PROVISION OF FIELD JOINT COATING SERVICES FOR F28DR-A/F6K-A PIPELINE PROJECT – TL OFFSHORE SDN BHD
SHELL March 18, 2011 Completed
97.
FABRICATION AND INSTALLATION OF STRUCTURAL WORKS FOR TOPSIDES A-Q COMPRISING PART OF SURVEY, DESIGN, ENGINEERING, PROCUREMENT, FABRICATION, LOAD OUT, TIE-DOWN/SEAFASTENING, TRANSPORTATION, INSTALLATION, HOOK-UP, TESTING, COMMISSIONING (EPCIC) OF PROCESS PLATFORM FOR B-193 PROJECT – SIME DARBY ENGINEERING
OIL AND NATURAL GAS CORPORATION
LTD (ONGC) February 25, 2011 In Progress
98. PROVISION OF PIPELINE MATERIALS WITH SEA SLEEVES C/W EQUIPMENT FOR NEWFIELD’S EAST PIATU INSTALLATION – TL OFFSHORE SDN BHD
NEWFIELD February 24, 2011 Completed
99. PROVISION OF PASSIVE FIRE PROTECTION SERVICES) FOR NEWFIELD'S EAST PIATU'S JACKET & TOPSIDES - KENCANA HL
NEWFIELD February 11, 2011 Completed
100. PROVISION OF FIELD JOINT COATING AND INFILL MATERIALS FOR PUTERI PIPELINE RESTORATION PROJECT – TL OFFSHORE SDN BHD
NEWFIELD February 11, 2011 Completed
101.
PROVISION OF REMOVAL, REPAIR, & REINSTATEMENT OF PASSIVE FIRE PROTECTION SYSTEM FOR CAKERWALLA OFFSHORE - SHAPADU ENERGY & ENGINEERING SDN BHD
CARIGALI HESS February 1, 2011 Completed
102.
PROVISION OF FIELD JOINT COATING, SUPPLY AND INSTALLATION OF CANUSA GTS-PP WRAPID SLEEVE FOR CILIPADI PIPELINE PROJECT – TL OFFSHORE SDN BHD
SHELL January 17, 2011 Completed
103. REPAIR WORKS OF BLASTWALL AND FIREWALL FOR MODULE 3 KUMANG TOPSIDE - OFFSHORE WORKS
PETRONAS CARIGALI SDN BHD
December 13, 2010 Completed
104.
DESIGN, CONSTRUCT, SUPPLY AND DELIVERY OF NOISE ATTENUATORS AND EXPANSION SPOOLS FOR F13 PROCESSING MODULE GLYCOL REBOILER SKID AT E11P-B PLATFORM
SARAWAK SHELL BERHAD
November 24, 2010 Completed
105.
FABRICATION AND INSTALLATION OF THE MOORING PORCHES, CHAIN JACK GANTRIES AND ASSOCIATED PLATFORMS, AND INSTALLATION OF FAIRLEAD FOUNDATIONS FOR GUMUSUT KAKAP FPS HULL (36010863) AT MALAYSIA MARINE AND HEAVY ENGINEERING
SHELL / MISC November 12, 2010 In Progress
106. SUBCONTRACT FOR STRUCTURAL WORKS FOR PROCESS PLATFORM FOR B-193 PROJECT AT SIME DARBY ENGINEERING
OIL AND NATURAL GAS CORPORATION
LTD (ONGC) October 22, 2010 In Progress
107. DESIGN, FABRICATE AND SUPPLY FIRE RATED ROLLER SHUTTER FOR KINABALU NAG DEVELOPMENT PROJECT (KNPG-B) - MMHE
PETRONAS CARIGALI SDN BHD
October 21, 2010 Completed
JURUNATURE SDN. BHD. – COMPANY CURRENT TRACK RECORD
NO WORK DESCRIPTION OWNER COMMENCEMENT
DATE CURRENT STATUS
April 30, 2013
108. SUPPLY AND DELIVERY OF SAFETY EQUIPMENTS FOR SAMARANG (PHASE 1 – ACCELERATED DRILLING) DEVELOPMENT PROJECT – KENCANA PETROLUEM
PETRONAS CARIGALI SDN BHD
October 6, 2010 Completed
109. PROVISION OF BR-B REPLACEMENT – RISER PIPE, CLAMP AND I-TUBE – FIELD JOINT COATING
TALISMAN September 20, 2010 Completed
110.
DESIGN, FABRICATE AND SUPPLY OF BLASTWALL FOR LIVING QUARTERS FOR JACKETS OF PM329 EAST PIATU DEVELOPMENT PROJECT – KENCANA HL
NEWFIELD September 17, 2010 Completed
111. PROVISION OF PIPELINE FIELD JOINT COATING SERVICES AND INFILL MATERIALS FOR PCSB’S SKO PIPELINE PROJECT – TL OFFSHORE
PETRONAS CARIGALI SDN BHD
September 7, 2010 Completed
112. PROVISION OF FLOWLINE AND RISER FIELD JOINT COATING SERVICES FOR GUMUSUT KAKAP PROJECT – SAPURA ACERGY
SHELL August 6, 2010 In Progress
113. UMBRELLA CONTRACTS FOR SALE OF SSB/SSPC SCRAP METAL (600865) SARAWAK SHELL
BERHAD August 03, 2010 In progress
114. SUPPLY AND DELIVERY OF INSTRUMENT FIRE & GAS CABLES FOR MRU-BUNGA ORKID DEV. PROJECT FOR SDE
TALISMAN MALAYSIA LIMITED
July 23, 2010 Completed
115. PROVISION OF PIPELINE FIELD JOINT COATING AND INFILL MATERIAL FOR ST. JOSEPH PIPELINE INSTALLATION ON E3 – TL OFFSHORE
SABAH SHELL PETROLUEM CO. LTD
July 22, 2010 Completed
116.
PROVISION OF THE SERVICE FOR DISPOSAL OF SURPLUS MATERIALS FOR PETRONAS GROUP OF COMPANIES FOR YEAR 2010-2013 (UMBRELLA CONTRACT)
PETROLIAM NASIONAL BERHAD
July 28, 2010 In progress
117. SUPPLY AND DELIVER OF INSTRUMENT CABLES & GLANDS FOR EMEMPI’S SELIGI AND SEMANGKUK PIPELINE REPLACEMENT PROJECT
RANHILL WORLEY PARSONS
June 29, 2010 Completed
118. STRUCTURAL WORK ~(5-TOPSIDES) - EPCIC OF (5) WELLHEAD PLATFORM FOR B-193 PROJECT – SDE
OIL AND NATURAL GAS CORP. LTD
(ONGC) June 12, 2010 In progress
119. SUPPLY OF ELECTRICAL FITTINGS AND ACCESSORIES FOR GUNTONG E AIR UTILITY SYSTEM UPGRADE PROJECT
RANHILL WORLEY PARSONS
May 27, 2010 Completed
120. SUPPLY OF CABLES FOR INTERGRATED PROCUREMENT AND CONSTRUCTION DEVELOPMENT PROJECT (PHASE 1)
SIME DARBY May 18, 2010 Completed
121. PROVISION OF FIELD JOINT COATING SERVICES FOR DEVIL’S CREEK DEVELOPMENT PROJECT
SAPURA ACERGY May 15, 2010 Completed
JURUNATURE SDN. BHD. – COMPANY CURRENT TRACK RECORD
NO WORK DESCRIPTION OWNER COMMENCEMENT
DATE CURRENT STATUS
April 30, 2013
122. SUPPLY OF SERVI-WRAP ANTI-CORROSION MATERIALS SARAWAK SHELL May 13, 2010 Completed
123. SUPPLY OF INSTRUMENT CABLES & CABLE GLANDS FOR TAPIS PUMP FIRE AND GAS SYSTEM UPGRADE PROJECT - EMEPMI
RANHILL WORLEY PARSONS
May 4, 2010 Completed
124. MASTER SERVICE AGREEMENT FOR PROVISION OF VSAT SYSTEM INCLUDING LAN/WAN – TL OFFSHORE SDN BHD
TL OFFSHORE May 1, 2010 In Progress
125. SUPPLY, FABRICATE, INSTALL AND PRE-COMMISSION ONE UNIT OF GYM ROOM FOR BRE
TALISMAN MALAYSIA LIMITED
April 29, 2010 Completed
126. DESIGN, SUPPLY, APPLICATION AND INSTALLATION OF PASSIVE FIRE PROTECTION (PACKAGE NO.SF03) FOR GUMUSUT KAKAP SEMI-FPS PROJECT
MMHE April 21, 2010 Completed
127. APPLICATION OF FOAM INSULATION FOR CAMERON INTERNATIONAL (M) SYSTEM SDN BHD
CAMERON INTERNATIONAL (M)
SDN BHD April 10, 2010 Completed
128. FIELD JOINT COATING WORK AT TLO FOR 2010 MURPHY PIPELINE PROJECT MURPHY OIL CORP March 16, 2010 Completed
129. FIELD JOINT COATING WORK AT GLOBAL OFFSHORE MALAYSIA FOR 2010 PETRONAS PIPELINES PROJECT
PETRONAS CARIGALI
March 16, 2010 Completed
130. SUPPLY OF CABLES FOR F23R-A CILIPADI GAS FIELD DEVELOPMENT PROJECT
PFCE
March 15, 2010 Completed
131. PASSIVE FIRE PROTECTION FOR SARAWAK SHELL E-8 PLATFORM SARAWAK SHELL March 15, 2010 Completed
132. DISPOSAL & REMOVAL OF SCRAP MATERIALS FROM MMHE SARAWAK SHELL March 15, 2010 Completed
133. SALE OF USED/SCRAP MATERIALS AND EQUIPMENT MLNG March 10, 2010 Completed
134. THERMOCOUPLE CABLE FOR BUNGA ORCHID-A TALISMAN MALAYSIA
March 9, 2010 Completed
135. HEAT SHIELD PANELS FOR ABU FIELD PETRONAS CARIGALI
March 3, 2010 Completed
136. SUPPLY AND APPLICATION OF PFP FOR F23DR-A CILIPADI PROJECT AT RFSB FOR PFCE
SARAWAK SHELL BERHAD
February 28, 2010 Completed
137. J-LAY TOWER REFURBISHMENT PROJECT (STRUCTURAL WORKS) FOR SAPURA ACERGY
SHELL / MISC February 25, 2010 Completed
JURUNATURE SDN. BHD. – COMPANY CURRENT TRACK RECORD
NO WORK DESCRIPTION OWNER COMMENCEMENT
DATE CURRENT STATUS
April 30, 2013
138. SUPPLY OF LIGHT WATER STATION PETRONAS CARIGALI
February 5, 2010 Completed
139. BLASTING AND PAINTING FOR JLT STRUCTURE SERVICES FOR GUMUSUT AT SAPURA ACERGY
SHELL/ MISC January 28 2010 Completed
140. SUPPLY OF HEATSHIELDS TO CILIPADI PROJECT AT RFSB FOR PFCE SARAWAK SHELL December 28 2009 Completed
141. DISPOSAL OF EXXON MOBIL OBSOLETE, PROJECT SURPLUS, AND USED MATERIALS
EMEMPI December 8, 2009 Completed
142. S-LAY FIELD JOINT COATING CONTRACT FOR GUMUSUT PIPELINE AT SAPURA ACERGY
SHELL / MISC November 26, 2009 Completed
143. SUPPLY AND APPLICATION OF PFP FOR TANGGA BARAT CPP TOPSIDE @ MMHE
PETRONAS CARIGALI
November 3, 2009 Completed
144. DISPOSAL OF TML SLOW MOVING AND OBSOLETE GOODS AT KSB (SCRAP METAL)
TALISMAN October 30, 2009 Completed
145. SUPPLY OF BLASTWALL FOR F23 (CILIPADI) AT RAMUNIA YARD @ PFCE SARAWAK SHELL October 21, 2009 Completed
146. SUPPLY OF BLASTWALL TO J.R McDERMOTT FOR THE KIPPER TUNA PROJECT
ESSO AUSTRALIA August 25, 2009 Completed
147. SUPPLY OF INSTRUMENT, FIRE & GAS, ELECTRICAL AND TELECOM CABLES TO PFCE AT RAMUNIA FABRICATION YARD FOR 23 TOPSIDE PROJECT
SARAWAK SHELL August 24, 2009 Completed
148. SUPPLY OF AIMS RFP MUDMAT SYSTEM FOR NEWFIELD’S WEST BELUMUT WELLHEAD JACKET AT KENCANA HL
NEWFIELD July 31, 2009 Completed
149. SUPPLY OF CHEMICALS – TRIETHYLENE GLYCOL – 99.9%, 235 KGS DRUM UNDER PRICE AGREEMENT WITH PETRONAS CARIGALI
PETRONAS CARIGALI
July 15, 2009 Completed
150.
ELECTRICAL AND INSTRUMENTATION FABRICATION & HOST TIE & HOOK-UP COMMISSIONING OF GUA FLAREBOOM REPLACEMENT AT BOUSTEAD PENANG SHIPYARD S/B
EXXON MOBIL June 22, 2009 Completed
151. FABRICATION OF INSTRUMENT GAS SKID FOR KUMANG PROJECT AT SDE PETRONAS CARIGALI
June 15, 2009 Completed
152. FIELD JOINT COATING WORK AT TLO FOR 2009 PETRONAS PIPELINE PROJECT PETRONAS CARIGALI
June 8, 2009 Completed
JURUNATURE SDN. BHD. – COMPANY CURRENT TRACK RECORD
NO WORK DESCRIPTION OWNER COMMENCEMENT
DATE CURRENT STATUS
April 30, 2013
153. SUPPLY OF SERVIWRAP TO TLO FOR 2009 PETRONAS PIPELINE PROJECT PETRONAS CARIGALI
May 15 , 2009 Completed
154. FIELD JOINT COATING WORK AT TLO FOR BEKOK-DULANG PROJECT FOR PETRONAS PIPELINE PROJECT
PETRONAS CARIGALI
April 17, 2009 Completed
155. FIELD JOINT COATING WORK AT TLO FOR WEST LUTONG PROJECT FOR PETRONAS PIPELINE PROJECT
PETRONAS CARIGALI
March 6, 2009 Completed
156. FIELD JOINT COATING WORK AT TLO FOR BETTY BAKAU PROJECT FOR PETRONAS PIPELINE PROJECT
PETRONAS CARIGALI
February 12, 2009
Completed
157. PASSIVE FIRE PROTECTION FOR B11 LQ & HELIDECK AT BDEWC, SARAWAK SARAWAK SHELL
BERHAD February 11, 2009 Completed
158. PASSIVE FIRE PROTECTION FOR PC-4 RISER AT BD11 DR-A PLATFORM FOR MMHE
PETRONAS CARIGALI
January 19, 2009 Completed
159. SUPPLY OF ELECTRICAL AND INSTRUMENTATION CABLES FOR F23 VLAP COMPRESSION AT SDE
SARAWAK SHELL BERHAD
January 5, 2009 Completed
160. MARK AND CUT STEEL STRUCTURAL WORKS FOR MCR-A PROJECT AT MMHE MMHE JV WITH
TECHNIP January 2, 2009 Completed
161. FABRICATION OF STRUCTURAL WORKS FOR EAST MODULE TOPSIDES OF GUMUSUT KAPAP AT MMHE
SHELL AND MISC Dec 31, 2008 In progress
162. E & I AND PIPING WORK AT MMHE FOR TANGGA BARAT CPP TOPSIDES PETRONAS CARIGALI
Dec 24, 2008 Completed
163. PASSIVE FIRE PROTECTION FOR B-11 TOPSIDES AT BROOKE DOCK YARD SARAWAK SHELL
BERHAD Dec 19, 2008 Completed
164. SUPPLY OF KOBE ELECTRODES FOR F23-RA TOPSIDES AT RFSB SARAWAK SHELL
BERHAD Dec 19, 2008 Completed
165. INSTRUMENTATION & FGS & TELECON JUNCTION BOX – DULANG B AT KENCANA HL
PETRONAS CARIGALI
November 4, 2008 Completed
166. SUPPLY OF TOTE TANKS PETRONAS CARIGALI
October 29, 2008 Completed
167. SUPPLY OF FIRE RATED WINDOWS FOR KUMANG AND TANGGA BARAT AT SDE
PETRONAS CARIGALI
October 21, 2008 Completed
JURUNATURE SDN. BHD. – COMPANY CURRENT TRACK RECORD
NO WORK DESCRIPTION OWNER COMMENCEMENT
DATE CURRENT STATUS
April 30, 2013
168. SUPPLY OF INSTRUMENT CABLES FOR FPSO RUBY AT MMHE MISC October 15, 2008 Completed
169. STRUCTURAL FABRICATION WORK FOR TANGGA BARAT AT MMHE PETRONAS CARIGALI
October 13, 2008 Completed
170. SUPPLY AND INSTALL KUMANG BLASTWALL/ FIREWALL COMPLETE SYSTEM INCLUDING PFP AT SDE TO MEET FIRE RATINGS
PETRONAS CARIGALI
October 10, 2008 Completed
171. SUPPLY OF ELECTRICAL AND INSTRUMENTATION (E&I) CABLES FOR KUMANG AND TANGGA BARAT AT SDE
PETRONAS CARIGALI
Sept 27, 2008 Completed
172. PIPING FABRICATION WORK FOR B11 KA TOPSIDE @ MMHE SARAWAK SHELL
BERHAD Sept 16, 2008 Completed
173. SUPPLY OF PERSONNEL TRANSFER BASKET AND CABLE GLAND / FITTINGS TO MURPHY OIL
MURPHY SARAWAK OIL CO. LTD
Sept 15, 2008 Completed
174. FIELD JOINT COATING WORK FOR CPOC PIPELINES AT TLO PETRONAS CARIGALI
Sept 10, 2008 Completed
175. PASSIVE FIRE PROTECTION FOR PLUTO PROJECT @ RFSB WOODSIDE ENERGY August 15, 2008 Completed
176. FIELD JOINT COATING WORK AT TLO FOR SCDR-A / E11K-A 12” & 14” PIPELINE PROJECT
SARAWAK SHELL BERHAD
August 1, 2008 Completed
177. SUPPLY OF CANUSA HSS TO TLO FOR SCDR-A / E11K-A 12” & 14” PIPELINE PROJECT
SARAWAK SHELL BERHAD
July 22,2008 Completed
178. SUPPLY OF DOUBLE SKIN HEAT SHIELDS FOR B11 KA PROJECT AT MMHE SARAWAK SHELL
BERHAD June 30, 2008 Completed
179. PASSIVE FIRE PROTECTION OF ANDP-D AT RFSB PETRONAS CARIGALI
June 30, 2008 Completed
180. SUPPLY OF SERVIWRAP FOR CPOC PIPELINE TO TLO PETRONAS CARIGALI
June 26, 2008 Completed
181. E&I, PIPING, MECHANICAL & STRUCTURAL FABRICATION FOR KUMANG CLUSTER DEVELOPMENT / TANGGA BARAT PROJECT @ SDE
PETRONAS CARIGALI
June 11, 2008 Completed
182. DESIGN, SUPPLY, FABRICATION AND INSTALL NEW FIRE AND BLASWALL FOR BR-A
TALISMAN MALAYSIA LIMITED
May 23, 2008 Completed
JURUNATURE SDN. BHD. – COMPANY CURRENT TRACK RECORD
NO WORK DESCRIPTION OWNER COMMENCEMENT
DATE CURRENT STATUS
April 30, 2013
183. PASSIVE FIRE PROTECTION OF GOPA-GOPB AT KHL MURPHY SARAWAK
OIL CO. LTD May 8, 2008 Completed
184. SUPPLY AND DELIVERY OF CONCRETE MATRESSES, SLEEPERS, LIFTING FRAME FOR 24” ANDR-A/TCOT PIPELINE FOR TLO
PETRONAS CARIGALI
April 30, 2008 Completed
185. ELECTRICAL AND INSTRUMENTATION FABRICATION WORK AT RFSB ON ANGSI –D PLATFORM
PETRONAS CARIGALI
April 24, 2008 Completed
186. PFP for F23 AND F6 AT BROOKE DOCKYARD, KUCHING, SARAWAK SARAWAK SHELL
BERHAD April 11, 2008 Completed
187. SUPPLY OF POWER & INSTRUMENTATION CABLES MURPHY SARAWAK
OIL CO. LTD April 10, 2008 Completed
188. SUPPLY OF HEATSHIELDS TO CLOUGH FOR MONTARA PROJECT IN THAILAND CLOUGH (THAILAND)
CO. LTD April 10, 2008 Completed
189. FIELD JOINT COATING SERVICES FOR TALISMAN PIPELINE INSTALLATION TALIMAN MALAYSIA
LIMITED April 10, 2008 Completed
190. FIELD JOINT COATING FOR PETRONAS CARIGALI 2008 PIPELINE INSTALLATION AT TLO FOR 5 PIPELINES
PETRONAS CARIGALI
April 10, 2008 Completed
191. SUPPLY AND APPLICATION OF WET AND CASTING PFP FOR TALISMAN RISERSAND ESDVS
TALIMAN MALAYSIA LIMITED
April 8, 2008 Completed
192. SUPPLY OF FIRE RATED DOORS TO MMHE PETRONAS CARIGALI
April 5, 2008 Completed
193. SUPPLY OF RADIANT HEATSHIELD, LOUVERS AND MISC ITEMS FOR PC 4 @ MMHE
PETRONAS CARIGALI
March 31, 2008 Completed
194. FIELD JOINT COATING FOR KEA- TIA @ PBJV
PETRONAS CARIGALI
March 7, 2008 Completed
195. SUPPLY OF ELECTRICAL OPERATED MONORAIL TROLLEY HOIST, 5 MT – MMHE
MMHE March 7, 2008 Completed
196. SUPPLY OF MANUAL OPERATED GANTRY CRANE TO MMHE MMHE March 7, 2008 Completed
197. ENGINEERING, DESIGN, FABRICATION AND INSTALLATION OF SHELTER CABIN FOR PC4 AT MMHE
PETRONAS CARIGALI
Feb 28, 2008 Completed
JURUNATURE SDN. BHD. – COMPANY CURRENT TRACK RECORD
NO WORK DESCRIPTION OWNER COMMENCEMENT
DATE CURRENT STATUS
April 30, 2013
198. SUPPLY OF LINE PIPES SMLS API TYPE OF VARIOUS SIZES TO MMHE PETRONAS CARIGALI
Jan 17, 2008 Completed
199. SUPPLY OF FIRE RATED DOORS TO TURKMENISTAN GAS DEVELOPMENT PROJECT
MITCO JAPAN SDN BHD
Jan 11, 2008 Completed
200. PASSIVE FIRE PROTECTION FOR BUNGA ORKID @ SDE TALISMAN
MALAYSIA LIMITED Jan 3, 2008 Completed
201. FABRICATION OF GUMUSUT-KAKAP SEMISUBMERSIBLE HULL (PACKAGE 2) SHELL AND MISC December 5, 2007 Completed
202. STRUCTURAL FABRICATION FOR CPOC PROJECT AT MMHE PETRONAS CARGALI
SDN BHD Nov 30, 2007 Completed
203. SUPPLY OF FIRE RATED WINDOWS FOR BUNGA ORKID PROJECT AT SDE TALISMAN
MALAYSIA LIMITED October 23, 2007 Completed
204. SUPPLY OF TOTE TANKS TO EMEPMI EXXON MOBIL Sept 30, 2007 Completed
205. MULTI DISCIPLINE WORKS (STRUCTURE, PIPING, E& I AND BLASTING/ PAINTING FOR PC 4 TOPSIDE WORK @ MMHE
PETRONAS CARGALI SDN BHD
July 26, 2007 Completed
206. FIELD JOINT COATINGS FOR VASAI EAST DEVELOPMENT PROJECT AT RAMUNIA FABRICATORS SDN BHD
OIL & NATURAL GAS CORPORATION,
INDIA August 27,2007 Completed
207. SUPPLY & APPLICATION OF PASSIVE FIRE PROTECTION -TALISMAN NORTHERN FIELD
TALISMAN MALAYSIA LIMITED
August 23, 2007
Completed
208. FIELD JOINT COATINGS FOR JERNEH PIPELINES AT TLO EXXONMOBIL August 8, 2007 Completed
209. FABRICATE BEAM HAUNCH, CROSS OVER SPOOL FOR HIGH PRESSURE MUD LINE AND CRANE BEAM
SAAG DRILLING & WELL SERVICES SDN
BHD August 7, 2007 Completed
210. SUPPLY AND APPLICATION OF PASSIVE FIRE PROTECTION FOR BELUMUT AT RAMUNIA FABRICATORS SDN BHD
PETRONAS CARIGALI SDN BHD
August 5, 2007 Completed
211. FIELD JOINT COATINGS FOR SEMARANG PIPELINES AT TLO PETRONAS CARGALI
SDN BHD July 28, 2007
Completed
212. SUPPLY AND APPLICATION OF PASSIVE FIRE PROTECTION FOR INTRALINE RESOURCES
TALISMAN MALAYSIA LIMITED
July 16, 2007 Completed
JURUNATURE SDN. BHD. – COMPANY CURRENT TRACK RECORD
NO WORK DESCRIPTION OWNER COMMENCEMENT
DATE CURRENT STATUS
April 30, 2013
213. FIELD JOINT COATINGS FOR ANDR-A PIPELINES AT TLO PETRONAS
CARIGALI SDN BHD June 25, 2007
Completed
214. FIELD JOINT COATINGS FOR 18 “ GUE PIPELINE AT TLO EXXONMOBIL June 20, 2007 Completed
215. SUPPLY AND APPLICATION OF PASSIVE FIRE PROTECTION FOR SUMANDAK TOPSIDES
PETRONAS CARIGALI
June 13, 2007 Completed
216. SUPPLY OF SPARES FOR CLOSURE DOOR TO MMHE SARAWAK SHELL
BERHAD June 6, 2007
Completed
217. FIELD JOINT COATINGS FOR BETTY– BORONIA 18” P/L SARAWAK SHELL
BERHAD June 1, 2007 Completed
218. ENGINEERING, PROC, CONSTRUCTION & COMMISSIONING OF FIRE PROTECTION SYSTEM
PETRONAS DAGANGAN BERHAD
May 28, 2007 Completed
219. FIELD JOINT COATING FOR TAPM-3 CAA NORTHEN FIELD DEVELOPMENT TALISMAN
MALAYSIA LIMITED May 22, 2007
Completed
220. SUPPLY AND APPLICATION OF PASSIVE FIRE PROTECTION FOR SCDR-A TOPSIDES
SARAWAK SHELL BERHAD
May 4, 2007 Completed
221. SUPPLY OF SAFETY EQUIPMENT AND LIFE RAFT TO MDFT FOR KIKEH PROJECT
M.D.F.T (KIKEH) LTD May 2, 2007
Completed
222. FIELD JOINT COATINGS FOR ALL SUMANDAK PIPELINES AND SUPPLY OF SERVIWRAP TO TL OFFSHORE
PETRONAS CARIGALI (PCSB)
April 6, 2007 Completed
223. 2007-2009 OFFSHORE FACILITIES TRANSPORT AND INSTALLATION OF FIELD JOINT COATINGS FOR MCDERMOTT
SARAWAK SHELL BERHAD
March 27, 2007 Completed
224. DESIGN, ENGINEERING, FABRICATION AND SUPPLY OF BLASTWALL FOR PCSB’S BELUMUT PROJECT AT RFSB
PETRONAS CARIGALI (PCSB)
March 19, 2007 Completed
225. SUPPLY AND APPLICATION OF PASSIVE FIRE PROTECTION FOR ANGEL GAS TOPSIDE PROJECT AT MMHE
WOODSIDE ENERGY March 15, 2007 Completed
226. FIELD JOINT COATING OF 10” BAP-AA TO BADP-G PIPELINE FOR TL OFFSHORE
PETRONAS CARIGALI (PCSB)
March 1, 2007 Completed
227. DESIGN, ENGINEERING, FABRICATION AND SUPPLY OF BLASTWALL FOR SHELL’S SCDR-A AT MMHE
SARAWAK SHELL March 1, 2007 Completed
JURUNATURE SDN. BHD. – COMPANY CURRENT TRACK RECORD
NO WORK DESCRIPTION OWNER COMMENCEMENT
DATE CURRENT STATUS
April 30, 2013
228. FABRICATION, INSTALLATION, TESTING AND PRE-COMMISSIONING OF PIPINGAND MECHANICAL WORKS FOR SCDR-A TOPSIDES AT MMHE
SARAWAK SHELL February 14, 2007 Completed
229. DESIGN, ENGINEERING AND FABRICATION OF END CLOSURE FOR SHELL’S SCDR-A PROJECT AT MMHE
SARAWAK SHELL February 6, 2007 Completed
230. ENGINEERING, DESIGN & FABRICATION OF PFP CASTINGS FOR METERING RUN - BR-B PLATFORM OFFSHORE
TALISMAN MALAYSIA LIMITED
January 29, 2007 Completed
231. FABRICATE GUMUSUT-KAKAP SEMI-SUBMERSIBLE HULL SHELL January 25, 2007 Completed
232. MULTI DISCIPLINE WORKS (STRUCTURE, PIPING, E& I AND BLASTING/PAINTING FOR F6 REJUVENATION WORKS
SARAWAK SHELL January 23, 2007
Completed
233. DESIGN, ENGINEERING, FABRICATION AND SUPPLY OF HEATSHIELDS FOR MAARI FIELD DEVELOPMENT AT KENCANA HL ENGINEERING
CLOUGH PROJECT INTERNATIONAL PTY
LTD, AUSTRALIA January 17, 2007 Completed
234. DESIGN, ENGINEERING, FABRICATION AND SUPPLY OF HEATSHIELDS FOR ANGEL GAS PROJECT AT MMHE
WOODSIDE ENERGY LTD, AUSTRALIA
January 15, 2007 Completed
235. SUPPLY OF ANTI-SKID BRE STAIRWAYS TALISMAN
MALAYSIA LIMITED January 4, 2007 Completed
236. DESIGN, ENGINEERING, FABRICATION AND SUPPLY OF HEATSHIELDS FOR SCDR-A PROJECT AT MMHE
SARAWAK SHELL Dec 27, 2006 Completed
237. SUPPLY OF INSTR. CABLE CONNECTING BRA AND BRE PAGA SYSTEM TALISMAN
MALAYSIA LIMITED Nov 15, 2006 Completed
238. FIELD JOINT COATING FOR PBJV GROUP SDN BHD FOR WEST LUTONG PROJECT
PETRONAS CARIGALI
Nov 11, 2006 Completed
239. CONTRACT FOR CIVIL WORKS PACKAGE FOR KUANTAN –KERTEH RAILWAY PROJEC, INCL. VEHICULAR, DRAINAGE & UTILITY BOX CULVERTS
PERCON BABENA JOINT VENTURE
October 15, 2006 Completed
240. STRUCTURAL STEEL FABRICATION FOR SUMANDAK SELATAN TOPSIDES AND HOST
PETRONAS CARIGALI
Sept 27, 2006 Completed
241. FJ COATING FOR TLO PCSB AND SHELL August 10, 2006 Completed
242. PIPING WORKS FOR KIKEH FPSO AT MMHE MURPHY OIL August 2, 2006 Completed
JURUNATURE SDN. BHD. – COMPANY CURRENT TRACK RECORD
NO WORK DESCRIPTION OWNER COMMENCEMENT
DATE CURRENT STATUS
April 30, 2013
243. SUPPLY OF HEATSHIELDS FOR F13W PROJECT AT RAMUNIA FABRICATORS SARAWAK SHELL June 15, 2006 Completed
244. SUPPLY OF END CLOSURE DOORS- F13W AT RFSB SARAWAK SHELL June 09, 2006 Completed
245. PASSIVE FIRE PROTECTION FOR KIKEH DTU TOPSIDES MURPHY OIL
May 3, 2006 Completed
246. FIELD JOINT COATINGS AT BARMADA MCDERMOTT TALISMAN
MALAYSIA LIMITED March 14, 2006 Completed
247. FIELD JOINT COATINGS FOR BARMADA MCDERMOTT S/B EXXON MOBIL March 14, 2006 Completed
248. PASSIVE FIRE PROTECTION FOR ARTHIT PFP AT Mc DERMOTT YARD IN BATAM INDONESIA
PTTEP and KBR February 27, 2006 Completed
249. PIPING WORKS FABRICATION FOR MURPHY KIKEH PROJECT @ MMHE MURPHY OIL January 14, 2006 Completed
250. ELECTRICAL AND INSTRUMENTATION FOR MODEC RJS-409 MODULE FABRICATION @ SDE
PETROBRAS December 1, 2005 Completed
251. PIPELINE FIELD JOINT COATING FOR BARAM (MCOT) 16” AND 10” PETRONAS
CARIGALI – TLO Nov 30, 2005 Completed
252. STRUCTURAL FABRICATION FOR MODEC RJS-409 ESPADARTE MODULE FABRICATION @ SDE
PETROBRAS November 1, 2005 Completed
253. SPECIAL STRUCTURAL SPECIAL FABRICATION FOR MURPHY KIKEH PROJECT MURPHY OIL September 9, 2005 Completed
254. SUPPLY AND INSTALL OF FIRESEAL FOR AMENAM KPONO PROJECT TOTAL ELF September 9, 2005 Completed
255. ARCHITECTURAL FITTINGS FOR CLIFF HEAD A PLATFORM AT HL ENGINEERING
ROC OIL, AUSTRALIA August 6, 2005 Completed
256. PFP FOR SHELL E11 –PB SARAWAK SHELL August 3 2005 Completed
257. SUPPLY OF BARUNIA PROTECTIVE RELAYS PETRONAS
CARIGALI SDN BHD August 3, 2005 Completed
JURUNATURE SDN. BHD. – COMPANY CURRENT TRACK RECORD
NO WORK DESCRIPTION OWNER COMMENCEMENT
DATE CURRENT STATUS
April 30, 2013
258. MAJOR STRUCTURAL FABRICATION FOR MURPHY KIKEH DTU SPAR HULL MURPHY OIL May 3, 2005 Completed
259. PFP FOR BARAM TOPSIDE AT BDEWC PETRONAS
CARIGALI SDN BHD April 2005 Completed
260. DESIGN, ENGINEERING AND FABRICATION OF BARAM HEATSHIELD AT BDEWC
PETRONAS CARIGALI SDN BHD
April 2005 Completed
261. BLASTING AND PAINTING WORKS AT SSE FOR GUE EXXONMOBIL March 2005 Completed
262. DESIGN, ENGINEERING AND FABRICATION OF E11 P-B BLASTWALL AT MSE SARAWAK SHELL
BERHAD March 2005 Completed
263. PFP FOR SHELL’S E8-DR-A AT RAMUNIA FABRICATORS SARAWAK SHELL
BERHAD March 2005 Completed
264. PFP FOR SHELL’S F13 SARAWAK SHELL February 2005 Completed
265. PFP FOR BR-E JACKET AND TRIPOD PROJECT AT MSE TALISMAN ENERGY February 2005 Completed
266. PFP FOR BR-E CO2 REMOVAL PROJECT AT SSE TALISMAN ENERGY February 2005 Completed
267. PFP FOR GUNTONG E PROJECT AT SIME SEMBCORP ENGINEERING EXXONMOBIL
EXPLORATION & PRODUCTION INC
January 2005 Completed
268. DESIGN, ENGINEERING AND FABRICATION OF SCKA & SF 13 HEATSHIELDS SARAWAK SHELL
BERHAD October 2004 Completed
269. DESIGN, ENGINEERING AND FABRICATION OF GUNTONG- E BLASTWALL EXXONMOBIL
EXPLORATION & PRODUCTION INC
July 2004 Completed
270. STRUCTURAL STEEL FABRICATION & WELDING AT MSE FOR MOAB TALISMAN ENERGY July 22, 2004 Completed
271. BLASTWALL REINSTAMENT TO H60 RATING – PFP TALISMAN ENERGY July 5, 2004 Completed
272. SUPPLY OF VESSELS UNDER MASTER SPOPT CHARTER PARTY FCF653 EXXONMOBIL
EXPLORATION & PRODUCTION INC
June 26, 2004 Completed
JURUNATURE SDN. BHD. – COMPANY CURRENT TRACK RECORD
NO WORK DESCRIPTION OWNER COMMENCEMENT
DATE CURRENT STATUS
April 30, 2013
273. PASSIVE FIRE PROTECTION SUPPLY AND APPLY FOR AMENAM PROJECT AT SSE TOTAL ELF FINA @
NIGERIA June 2004 Completed
274. SUPPLY OF PRODUCTION & TEG CHEMICALS - 3 YEARS SARAWAK SHELL/
PCSB / NIPPON June 23, 2004 Completed
275. CASTINGS FOR BUNGA RAYA-A PLATFORM TALISMAN ENERGY March 3, 2004 Completed
276. PFP FOR YOHO PROJECT PROTECTION EXXON MOBIL
NIGERIA March 2004 Completed
277. CASTINGS FOR SDV on BUNGA RAYA-A TALISMAN ENERGY December 2003 Completed
278. PFP FOR SERAI PROJECT SARAWAK SHELL September 2003 Completed
279. PFP FOR JINTAN PROJECT PROTECTION SARAWAK SHELL
BERHAD July 2003 Completed
280. INFIELD JOINT COATING FOR NIPPON STEEL (NSC) PETRONAS CARIGALI
May 8, 2003 Completed
281. YOHO PLATFORM ELECTRODE EXXON MOBIL
NIGERIA February 2003 Completed
282. BUNGA RAYA 24” Riser PFP PCSB/TALISMAN February 2003 Completed
283. SHELL M3 BLASTWALL SARAWAK SHELL January 11, 2003 Completed
284. HELANG’s RISER / SDV/ FLANGE / VALVE PFP CASTING NIPPON OIL
EXPLORATION January 2003 Completed
285. MLNG SPHERE PFP MLNG SDN BHD December 2002 Completed
286. LUNDIN RISER / SDV PFP TALISMAN December 2002 Completed
287. HALFDAN HEATSHIELDS ENGINEERING DESIGN SEMBCORP ENGRG
SINGAPORE September 6, 2002 Completed
JURUNATURE SDN. BHD. – COMPANY CURRENT TRACK RECORD
NO WORK DESCRIPTION OWNER COMMENCEMENT
DATE CURRENT STATUS
April 30, 2013
288. SHELL M1 BLASTWALL ENGINEERING DESIGN SARAWAK SHELL
BERHAD September 2002 Completed
289. PASSIVE FIRE PROTECTION USING LEIGH’S PAINTS PFP NIPPON OIL
(HELANG) AT MSE July 15, 2002 Completed
290. MODIFICATION & INSTALL ELECTRICAL WORK FOR SWITCHGEARS (KNDP-A) SARAWAK SHELL
BERHAD Nov 18, 2001 Completed
291. PASSIVE FIRE PROTECTION FOR MLNG3 SLUGCATCHER PETRONAS CARIGALI
October 29, 2001 Completed
292. PASSIVE FIRE PROTECTION USING LEIGH’S PAINTS PFP MALAYSIA LNG
SDN BHD October 20, 2001 Completed
293. PASSIVE FIRE PROTECTION USING LEIGH’S PAINTS PFP PETRONAS CARIGALI
October 15, 2001 Completed
294. SUPPLY/ INSTALL E & I SWITCHGEAR SARAWAK SHELL
BERHAD August 20, 2001 Completed
295. INSULATION CONTRACT WITH PETRA RESOURCES ESSO PRODUCTION
MALAYSIA INC. July 6, 2001 Completed
296. SUPPLY OF ELECTRODES DOTANAH ENGRG &
CONSTRUCTORS July 2, 2001 Completed
297. ELECTRODE SUPPLY FOR NIPPON OIL (HELANG) MALAYSIA
SHIPYARD (MSE) June 15, 2001 Completed
298. ELECTRODE SUPPLY FOR PETRONAS CARIGALI (ANGSI-A) SIME SEMBCORP
ENGINEERING June 15, 2001 Completed
299. ELECTRODE SUPPLY FOR ESSO (SATELIT) AND LARUT MSE February 2001 Completed
300. SUPPLY OF ELECTRODES FOR ESSO (LARUT-A) SIME SEMBCORP
ENGINEERING July 6, 2000 Completed
301. SUPPLY OF ELECTRODES PETRONAS FERTILIZER
TENDER Completed
302. SUPPLY OF CONSUMABLES FOR PETRONAS PETRONAS
AMMONIA SDN BHD TENDER TENDER
JURUNATURE SDN. BHD. – COMPANY CURRENT TRACK RECORD
NO WORK DESCRIPTION OWNER COMMENCEMENT
DATE CURRENT STATUS
April 30, 2013
303. SUPPLY OF CONSUMABLES FOR PCSB PETRONAS CARIGALI
TENDER TENDER
top related