© 2015 Institute of Railway Technology All Rights Reserved www.irt.monash.edu

INSTRUMENTATION

OVERVIEW

IRT has significant experience in the installation of temporary and permanent monitoring systems for trains, bulk ore carriers, draglines, coal trucks, shovels, etc. Systems for measuring:

• Strain • Deflection • Acceleration (vibration) • Noise • Temperature form the backbone of the Institute’s instrumentation capability.

PERMANENT INSTALLATIONS

• Partially Dumped Ore Car Detector — in service for last 15 years at BHPB-IO on Car Dumper #3.

• Briquette Feed Bin weigh system — Installed at Hot Briquetted Iron (HBI) plant.

• Rail Weighbridge — in service at Brookfield Rail to continuously assess loading of iron ore traffic.

• Rail Temperature and Stress Free (SFT) Monitoring – Permanent site established for Rio Tinto in the Pilbara providing continuous feed of ambient and rail temperatures as well as rail SFT movements.

• Track Condition Monitoring – Over 80 Instrumented Ore Cars in service on iron ore railroads, providing rapid feedback on track condition

• BHPB-IO – Wagon alignment monitoring system

BENEFITS

• Prototyped instrumentation results in optimised final installation.

• Improved maintenance scheduling. • Improved production audit data. • Condition monitoring of wheel fleet. • Improved loading procedures. • Improved process control.

Calibration of Rail Weighbridge

Strain Gauge Bridge Termination Logging System for Strain Gauges (Top) and Mounted Strain Gauges (Bottom)

Laser System for Monitoring Wagon Alignments