Insert some activities into primavera p6

Post on 23-Jan-2018

426 Views

Category:

Engineering

1 Downloads

Preview:

Click to see full reader

Transcript

Firdaus.yku@gmail.com ‐ 1  

Insert Some Activities into Primavera P6 

 

In this tutorial, we will breakdown all related works for RC structure and steel column only. It will follow 

construction stage point 2 and 3 as we discussed in the previous tutorial. 

2. Foundation stage 

a. Soil Excavation b. Lean concrete and spacer for concrete cover c. Reinforcement bar installation for pad 

footing/pedestal d. Timber formwork for pad footing 

a. Concrete pouring (fc’ 35 MPa) b. Formwork dismantling c. Curing and rectification in case any defect on the 

concrete. 

a. Reinforcement bar fixing for pedestal b. Timber formwork, spacer and support installation c. Concrete pouring 

a. Formwork dismantling, curing and rectification b. Backfill with imported soil (Limestone)  c. Soil compaction for all area. 

 

All works detail above is not required to be transferred into Primavera P6 as project schedule.  

We just highlight some major works as representative of each picture. 

 

Let’s continue our training by finalizing “Pre‐Construction work”  item. Follow previous step by 

adding  3 work  items  as  picture  below and  insert  duration  each  item as  per  your  engineering 

decision. To adjust column size, we can resize it by dragging a line in a blue circle. 

You  can  add  more  work  items  as  preparation  step,  for  instance,  site  office,  documentation, 

measurement, join site visit, project board installation, etc. 

1  2 

3  4 

Firdaus.yku@gmail.com ‐ 2  

  

 

According to construction stages above, we will simplify major jobs of “foundation” to be inserted into 

Primavera P6 project schedule as mentioned below: 

 

a. Pad Footing  b. Pedestal 1. Soil Excavation 2.  Lean concrete 3. Reinforcement bar installation 4. Timber formwork 5. Concrete pouring 6. Formwork dismantling and curing 

 

7. Timber formwork and rebar fixing 8. Concrete pouring 9. Formwork dismantling 10. Backfilling and compaction 

 

There are 2 WBS items under foundation work item, pad footing and pedestal. These items have to be 

inserted into WBS tab as picture below. 

 

Firdaus.yku@gmail.com ‐ 3  

Next step, re‐open activities tab and add some work items as written a list above. 

 

Modify number of duration as you need for your planning in Original Duration column. 

Connection each item will be discussed in next chapter. 

 

3. Ground beam and slab 

Pictures below are construction stage of RC ground beam and slab as next sequence of 

foundation work.  

a. Lean concrete underneath ground beam b. Reinforcement bar installation c. Timber formwork and spacer for concrete cover 

a. Lateral timber support at both side b. Concrete pouring (fc’ 25 MPa) c. Formwork dismantling, curing and rectification 

Firdaus.yku@gmail.com ‐ 4  

a. Timber formwork for RC Column b. Reinforcement bar fixing c. Concrete pouring d. Formwork dismantling e. Curing and rectification 

a. Steel column erection and fixing on RC column b. Steel beam connection with column c. Roof frame installation d. Soil Backfilling and compaction for RC Slab e. Lean concrete f. Wire mesh M8 installation g. Concrete pouring h. Curing and rectification 

 

If we analyse construction stages above, we can divide all major jobs to be 4 WBS as below: 

1. Ground beam 

2. RC Slab 

3. RC column 

4. Steel Column and Beam 

Three (3) WBS are put under ground beam and slab, whereas steel structure is described under Steel 

column and beam as picture below  

 

Firdaus.yku@gmail.com ‐ 5  

In the previous tutorial, there is work item “RC and steel column” under ground beam and slab, it is 

replaced by “Steel column and beam” as mentioned below 

Go to Activities tab as previous instruction, and insert some activities following a list above 

 

 

We just finalized inserting some activities under foundation, ground beam/slab and steel structure. 

Duration can be modified as per your planning. 

Relationship and resources each work item will be discussed in the further tutorial. 

 

top related