Estimating Earthwork - kontrak prosedur 2
Post on 28-Nov-2014
132 Views
Preview:
Transcript
TazriAziz
TazriAziz
Earthwork includes: 1. Excavation 2. Grading: Moving earth to change
elevation 3. Temporary shoring 4. Back fill or fill: Adding earth to
raise grade 5. Compaction: Increasing density 6. Disposal
TazriAziz
A. Job conditionsMaterial typeWater level and moisture contentJob sizeLength of haulHaul road condition (accessibility and
load restrictions)
TazriAziz
B. Management conditionsEquipment conditions and
maintenance practicesSkills of work force and managementPlanning, supervision and
coordination of work.
TazriAziz
J ob Conditions** Excellent Good Fair Poor
Excellent 0.84 0.81 0.76 0.70
Good 0.78 0.75 0.71 0.65
Fair 0.72 0.69 0.65 0.60
Poor 0.63 0.61 0.57 0.52
Management Conditions*
TazriAziz
Meter cube m3 (bank, loose, or
compacted)
Bank (BCY): Materials in its natural state before disturbance (in-place, in-situ)
Loose (LCY): Material that has been compacted or disturbed or loaded
Compacted (CCY): Material after compaction
TazriAziz
1.0
1.25
0.90
1.0 METER CUBE IN NATURAL CONDITION (IN-PLACE YARD)
1.25 METER CUBE AFTER DIGGING (LOOSE YARDS)
0.90 METER CUBE AFTER COMPACTED (COMPACTED YARDS)
In place CompactedLoose
TazriAziz
Bank: VB
Bank Meter Cube (BMC)Density B Lb /BMC
Loose: VL
Loose Meter Cube (LMC)Density L Lb/LMC
Compacted: Vc
Compacted Meter Cube (CMC)Density C LB/CMC
TazriAziz
Swell:A soil increase in volume when it is excavated.
Swell (%) = ( - 1) x 100
Load factor =
Bank Volume = Loose volume x Load factor
Loose densityBank density
Bank densityLoose density
TazriAziz
Shrinkage:
A soil decreases in volume when it is compacted
Shrinkage (%) = (1 - ) x 100
Shrinkage factor = 1 - Shrinkage
Compacted volume
= Bank volume x Shrinkage factor
Bank densityCompacted density
TazriAziz
Material
Loose
(kg/m3)
Bank
(kg/m3)Swell (%)
Load Factor
Clay, dry 1,604 2,024 26 0.79Clay, wet 2,062 2,731 32 0.76Clay and gravel, dry 1,833 2,139 17 0.85Clay and gravel, wet 1,986 2,368 17 0.85Earth, dry 1,693 2,177 29 0.78Earth, moist 1,841 2,353 28 0.78Earth, wet 2,101 2,582 23 0.81Gravel, wet 2,123 2,398 13 0.88Gravel, dry 2,360 2,765 17 0.85Sand, dry 1,986 2,230 12 0.89Sand, wet 2,368 2,689 13 0.88Sand and gravel, dry 2,215 2,483 12 0.89Sand and gravel, wet 2,597 2,865 10 0.91
Exact values will vary with grain size, moisture content, compaction, etc. Test to determine exact values for specific soils.
TazriAziz
Initial
Soil Type Soil Condition Bank Loose CompactedClay Bank 1.00 1.27 0.90
Loose 0.79 1.00 0.71Compacted 1.11 1.41 1.00
Common earth Bank 1.00 1.25 0.90Loose 0.80 1.00 0.72Compacted 1.11 1.39 1.00
Rock (blasted) Bank 1.00 1.50 1.30Loose 0.67 1.00 0.87Compacted 0.77 1.15 1.00
Sand Bank 1.00 1.12 0.95Loose 0.89 1.00 0.85Compacted 1.05 1.18 1.00
Convrted to:
TazriAziz
Angle of Repose2’-0”or more
TazriAziz
For Sloping Sides of Excavation
OriginalGround Line
Solid
Rock
, Sla
te o
r C
em
ente
d S
and a
nd G
ravel
(90
Deg.)
Com
pact
ed A
ngul
ar G
rave
ls
1/2:
1 (6
3 D
eg.)
Reco
mm
ende
d Sl
ope
for A
vera
ge S
oils
1:1
(45
Deg.)
Compacted Sharp
Sand
1 1/2 :1 (3
3 Deg.)
Well Rounded Loose Sand
2:1 (26 Deg.)
TazriAziz
1. End Area Method
2. Contour Line/ Grid Method
TazriAziz
Used in sites where length is much greater than width
TazriAziz
1. End Area Method
a.Take cross-sections at regular intervals, typically, 10m intervals.
b.Calculate the cross-section end areas
c.The volume of earthwork between sections is obtained by taking the average of the end areas at each station in square meter.
TazriAziz
Fill
Cut
80
82
84
86
88
80
84
86
88
82
78
A’ B’ C’ D’ E’ F’
A B C D E F10 10 10 10 10
50m
30
m
TazriAziz
80
78
76
82
80
78
84
82
80
86
84
88
86
90
88
78.5
80.3
82.3
84.2
86.2
88.2
Sec. A’- A
Sec. B’- B
Sec. C’- C
Sec. D’- D
Sec. E’- E
Sec. F’- F
Pro
ject
Cro
ss S
ect
ion
s
TazriAziz
80
79
78
77
76
79.5
78.5
76.7
Section A’- A
Area = = 173.7193 x 1.8
2
Area = = 53.5107 x 1.0
2
TazriAziz
82
81
80
79
78
81.8
80.3
76.7
Section B’- B
Area = = 189.0210 x 1.8
2
Area = = 67.590 x 1.5
2
TazriAziz
Section Emb (CCY) Exc. (BCY) Exc. x B/C(CCY)
Net Exc.(CCY)
Cum Exc(CCY)
A-B 672 224 254 - 418 - 418B-C 567 441 499 - 68 - 486C-D 215 791 896 681 195D-E 0 1031 1167 1167 1362E-F 0 1222 1384 1384 2746
TazriAziz
Used for parking lots and site “leveling”
Grid size from 10mx10m to 50mx50m
the greater the terrain variance the smaller the grid
TazriAziz
Step l
Determine by visual study of the site drawing if the net total will be an import (more fill required than cut) an export (less fill required than cut) or a blend (cut and fill about equal)
Step 2Determine the pattern of calculation points or grid size.
Step 3 Determine elevations at each calculation location, the corners of each grid.
Step 4 Calculate the cubic yards of cut or fill required in each grid cell.
Step 5Add the individual Grid Cell quantities together to arrive at the total cut, total fill volume and the import or volume export yardage required for the job.
TazriAziz
A B C D E F87.6 88.6 89.4 90.4 91.6 93.2
G H J K L M87.4 88.2 89.5 90.6 91.6 92.7
N O P Q R S87.2 87.7 89.0 90.4 91.3 92.0
87.6 88.5 89.3 90.3 91.5 95.0
94.3
93.5
93.1
A B C D E F G60m
88’ 89’ 90’ 91’ 92’ 93’ 94’
No ScaleNotes:1. Bring the entire site to elevation 90.2. All grids are 10m x 10m = 100 sq m3. Present contours
TazriAziz
PurposeGrade the entire site to grade 90’
Quick and DirtyAssume one gridExisting 90.50Proposed 90.00Cut 0.50
Total Cost = = 1.851m310 x 10 x 0.5027
10m
10
m
NeedFill
Need
Cut
90'
90' 91'
90.5'
TazriAziz
Average elevation
=
= 88.08change = 90-88.08
= 1.92m3
If we choose the grid size to be 10mx10m
87.6+88.5+87.6+88.64
87.6
88.6
87.687.6
top related