1

City Rail LinkAustralian Tunnelling Conference

October 2016

2

Planned Outcomes

• 24 trains per hour in each direction ultimate

track capacity

• 18,000 passengers per hour in each direction

ultimate patronage capacity through 2 new

stations and two modified stations

• Future proofing oversite development

opportunities at each station

• Sustainability IS project target rating ‘excellent’

• 95% reliability target

3

Auckland in 2041

• Auckland is pivotal to the social, economic and cultural development of New Zealand

• More than 700,000 new

residents

• An extra 400,000

dwellings

• Twice as many city centre

and city fringe residents

and employees

• City Centre student

numbers up by 30%

• City centre producing

25% of Auckland’s GDP -

currently 17%

729,000

0

500,000

1,000,000

1,500,000

2,000,000

2,500,000

Growth to2041

2011Population

4

City Wide Benefits

5

CRL Route Plan

6

Delivering the CRL Sustainably

• Targeting zero waste to landfill

• Measuring and reducing carbon

footprint

• Social value through procurement

• e.g. skills legacy, apprenticeships, new jobs

for unemployed

• ‘Leading’ Infrastructure Sustainability rating for integrating Mana Whenua values

• Reporting performance

Setting the benchmark for designing, building and operating sustainable

infrastructure in New Zealand

Infrastructure Sustainability

themes

7

The Project Route

8

Climbing the Hill

9

Tunnels

Platform Tunnels

Running Tunnels

10Initial Construction Phase

Orakei

Sewer

strength

ening

Stormwater

underground

works

Shaft

11

Britomart Station

12

13Diaphragm and Jet Grout Cut off Walls

14

Aotea Station

15

Aotea Geology

16Virtual Station Tour

17

Karangahape Station

18

Mercury Lane entrance

19

Karangahape geology

20Southern Junction Tunnels

21Mt Eden Tunnel Portals

22Mt Eden Station

23Mt Eden Geology

24

Mt Eden Geology

25

Procurement packaging

26

• Contracts 1 & 2 started - to be completed in 2019

• Reference design for contracts C3 – C9 complete

• Initial market engagement completed

• Procurement strategy formulated

• Planning processes progressing well

• Heads of Agreement for funding signed with government

Project Status

27

Thank you