Agreement with Town of Tioga, LLC. Total Cost Estimate: $6,420,000 Total Estimate for Agreement Portion: $3,700,000 Developer responsible for 9.7% of.

Post on 02-Jan-2016

215 Views

Category:

Documents

2 Downloads

Preview:

Click to see full reader

Transcript

SW 8th Ave Extension Agreement

Agreement with Town of Tioga, LLC

SW 8th Ave Extension

Total Cost Estimate: $6,420,000Total Estimate for Agreement Portion: $3,700,000Developer responsible for 9.7% of CostRemainder reimbursed through SW Impact Fee FundFDOT CIGP Grant: $2,400,000

Total Project: Extension of SW 8th Ave between SW 122nd St and SW 143rd St. Two travel lanes, bike lanes, sidewalk, multiuse path, street trees

This Agreement: Design and Construction of the portion

between SW 122nd and SW 133rd Way

SW 8th Ave Concept Design

SW 8th Ave Concept Design

Staff Recommendation

The Board of County Commissioners approve the agreement with Town of Tioga, LLC to design and construct the SW 8th Avenue extension between SW 122nd St and SW 133rd Way and authorize the Chair's signature.