Acquisition Planning Desktop Guide - Final
Post on 22-Jan-2017
81 Views
Preview:
Transcript
Elevating the Quality of Life in the District
DGS Contracting & Procurement
Acquisition Planning Desktop Guide
FY2017
1
Elevating the Quality of Life in the District
Table of Contents: Overview
• Chapter 1: Introduction
• Chapter 2: Acquisition Planning
• Chapter 3: DGS-APT Legend and Definitions
• Chapter 4: How do I enter information in the DGSAPT Electronic Form?
• Chapter 5: Unplanned Acquisitions
• Chapter 6: DGS-PIF Legend and Definitions
• Chapter 7 : How do I enter information in the DGS-PIF Electronic Form?
• Chapter 8: Querying & Reporting
• Chapter 9: Closing
Page Numbers
3-10
11-15
16-22
23-39
40-44
45-48
49-66
67-73
74-75
2
Elevating the Quality of Life in the District
Chapter 1: Introduction
Overview
• Purpose
• Policy & Law
• DGS Acquisitions - Key Roles and Players
• Who are the division points of contact?
• How does the DGS –APT help DGS divisions and District agencies ?
• How does the C&P division benefit from the use of the Acquisition Planning
Tools ?
3
Elevating the Quality of Life in the District
Purpose
The purpose of acquisition planning is to ensure that the government meets its needs in an effective, economical and timely manner. Acquisition planning ensures compliance with the law and allows for proper lead time for processing procurements. This Desktop Guide provides guidance to assist procurement staff in utilizing data submitted by the divisions in the Department of General Services Acquisition Planning Tool, which is the Contracting and Procurement Division’s official system of record for acquisition plans.
4
Elevating the Quality of Life in the District
Policy & Law
Procurement Practices Reform Act of 2010 (PPRA), effective April 8,2011 ,Section 1105.
The Chief Procurement Officer shall develop and implement a process by which each agency subject to the CPO’s procurement authority shall prepare and submit to the CPO and acquisition plan identifying the size and nature of the anticipated procurement workload for the following fiscal year. Although we are an independent agency the DGS procurement process is subject to the PPRA.Each division shall submit its acquisition plan for the following fiscal year to C&P no later than September 26th of this year
5
Elevating the Quality of Life in the District
DGS Acquisitions Key Roles & Players
Program ManagersProvide a Scope of Work Provide an Independent Government EstimateEstablish Period of Performance Knowledge of the number of contracts in the portfolio Complete Contract E-ValuationKnowledge of Prime and Subprime contract activities Authorize the exercise an option 60-90 Days before the current option expiresAwareness of the Contract CeilingComplete and Submit RQ, DGS – APT, DGS – PIF Share requisition funding type and amount with budget personnelSend an Requests for Modifications Properly allocate task orders across multiple contractors
Contracting and Procurement – Procurement Services BranchApprove RQsIssue Purchase OrdersPrepare modifications Request funding Create and send preliminary notices for contract expiration Process Large Purchases Process Small Purchases – 10 day cycle time (Changes are due to OTR & DOES compliance implementation) Submit OTR & DOES tax compliance Tax affidavitsQuality Assurance for Vendors
6
Elevating the Quality of Life in the District
DGS Acquisitions Key Roles & Players (Continue)
Contracting and Procurement – Policy, Research & Planning Branch Facilitate annual acquisition planning Control and monitor procurement request Facilitate and control Ad- Hoc/ Unplanned procurement request Schedule and forecast procurement activity Conduct Quarterly Reports Conduct Ad-Hoc analysis to mitigate riskCoordinate procurement activity with the C&P Division’s Procurement Service , Procurement Evaluation Branch & Office of the Associate Director
( If Procurements are Greater than $1Million & Mission Critical )
OGC – Legal Draft ContractsLetter ContractsReview RFPsReview DocumentsSupport Evaluation and Award – During the award issuing phase Drafting SupportPost Award Change Orders ModificationsSupport the development of Council Packages
7
Elevating the Quality of Life in the District
Who are the division Points of Contact ?
Office of the Director-Latrena Owens, Jonathan KayneIT- Gregory CottenCommunications- Kenneth DiggsLogistics- Faith ScottHuman Resources- Vikkie GarayProtective Services - Anthony FortuneFacilities Management - Spencer Davis, Donny GonzalezSustainability and Energy Management- Zach DobelbowerCapital Construction- Jeff Bonvechio, Allam Al-AlamiPortfolio- Jonathan Kayne, Mattie Rogers Office of General Counsel- Camille Sabbakhan, Carlos SandovalContracting and Procurement- Yinka Alao, Carissa MayeOCFO/Budget -Henry Wong , Massimo Marchiori , Valerie BrownResource Allocation - Robert Seabrooks , Lanre Akinsemoyin
8
Elevating the Quality of Life in the District
How does the DGS –APT help DGS
divisions and district agencies ?
Kicks-off the process of identifying future needs. Align procurement needs with budgetary resources and strategic
plan. Facilitates the development of timelines that help agencies
proactively prepare requirements and other pertinent procurement documents relative to their needs.
9
Elevating the Quality of Life in the District
How does the C&P division benefit from
the use of Acquisition Planning Tools ?
Forecast procurement needs of stakeholders/customers. Allocate procurement resources more strategically and efficiently to
meet the needs of stakeholders. Execute and effectively monitor and ensure compliance on planned
and unplanned procurements. Reduce delays in the overall procurement process.
10
Elevating the Quality of Life in the District
Chapter 2: Acquisition Planning
Overview
• What is acquisition planning?
• What are the tools to help us with acquisition planning?
• What are the steps ?
11
Elevating the Quality of Life in the District
What is acquisition planning ?
Acquisition planning means the process by which the efforts of all personnel responsible for an acquisition are coordinated and integrated through a comprehensive plan for fulfilling the agency’s needs in a timely manner and at a reasonable cost. It includes developing the overall strategy for managing the acquisition portfolio.
12
Elevating the Quality of Life in the District
What are the tools to help us with
acquisition planning?
1) The Department of General Services Planning Tool (DGS-APT) is an electronic form in the Procurement Automated Support System (PASS) which captures general information a DGS Division that intends to procure goods or services for any given fiscal year.
2) The Department of General Services Project Initiation Form (DGS-PIF) is an electronic form in the Procurement Automated Support System (PASS) which provides general information a DGS Division that intends to procure goods or services for unplanned, emergency and ad-hoc request.
13
Elevating the Quality of Life in the District
Step1. DGS C&P will hold an introductory meeting with each division head and work with
each division to prepare their DGS-APT for the fiscal year.
Step2. Customer Divisions will submit their acquisition plan In the PASS through the D-APT
Electronic Form.
Step3. The Policy Research and Planning Branch & Contracting Specialists will work with
key division personnel to collect data for the D-APT and Facilitate D-APT entries with
division staff.
What are the steps ?
14
Elevating the Quality of Life in the District
Step 4. The Contracting and Procurement Division will analyze the data received from the
divisions and batch acquisitions by procurement type and commodity.
Step 5. Once the DGS-APT is finalized, customer divisions will receive a notification that
there submittal was approved.
Step 6. C&P branches will work together to ensure that the workload is distributed
properly to timely meet the needs of requesting divisions.
Step 7. Procurement is ready for execution !
What are the steps ? (Continue)
15
Elevating the Quality of Life in the District
Chapter 3: DGS-APT Legend and Definitions
Overview
• Legend# -APT is the legend number Icon in this section
• Categories – are various attributes inside the DGS-APT form “My label” is not in
legend. This is for OCTO and OCP use only
• Definitions – descriptions of the categories
16
Elevating the Quality of Life in the District
Legend-DGS-APT (Part 1) : Legend # Categories Definition
APT 1. Title : Priority 0,1,2,3 or 4 Acquisitions
Title should state the priority Levels 0-4 ,for example: Priority 0 Acquisitions - High Priority High Risk, Priority 1 Acquisitions - High Priority Attention is needed, Priority 2 Acquisitions- Moderate Priority
Moderate Risk , Priority 3 Acquisitions - Moderate Priority Low Risk, Priority 4 Acquisitions- Low Priority Low Risk
APT 2. Division Name Requesting Division APT 3. Division/Agency Point of Contact Program Manager - Point of contract full name APT 4. Phone Number Program Manager contact information APT 5. Fiscal Year Fiscal Year that these actions are planned
APT 6. Planned Acquisitions - DGS APT Batch # & Line _ # An individual line item number - This number has to be a unique / individual DGSAPT Line number # per planned acquisition request For Example : DGSAPT276_0
APT 7. Planned Acquisitions - Description The planned acquisition/project title , each project will have an associated description example: DGSAPT276_0 Oak Hill Lighting - Municipal
APT 8. Planned Acquisitions - Commodity Group The commodity group under which the acquisition falls i.e. goods
APT 9. Planned Acquisitions - Funding Source Whether it is Local , Grants , Federal, Capital or Other ( IF Capital and Local funds are both used , please enter in the comment sections
APT 10. Planned Acquisitions - Need By Date Need by Date/ Due date when acquisition is expected ( If you have project plans , please enter them into the attachment )
APT 11. Planned Acquisitions - New Acquisition Is the acquisition new ? ( Yes or No ) APT 12. Planned Acquisitions - Procurement over $1M For metrics and tracking purposes APT 13. Planned Acquisitions - Mission Critical Mission Critical/ Council Packages ( Is this a council package Yes or No ?)
APT 14. Planned Acquisitions - Estimated Amount Estimated dollar value of the individual project. For example: DGSAPT Line # - DGSAPT276_0 Description -Oak Hill Lighting Estimate dollar value - $1,000,000
APT 15. Planned Acquisitions - Partial Letter Contract Needed Will a partial letter will be used to execute parts of this project APT 16. Planned Acquisitions - Existing Contract Number If Acquisition is not new and pre-existing APT 17. Planned Acquisitions - CS , NC , AE services Select if it is Construction , Non- Construction , or Architecture and Engineering Services APT 18. Planned Acquisitions - Can a CBE perform these projects Can this project be set aside for the CBE market ? APT 19. Planned Acquisitions - Can a SBE perform these projects Can this project be set aside for the SBE market ? APT 20. Planned Acquisitions - Green Procurement Can green procurement standards be used for this acquisition request?
APT 21. Planned Acquisitions - Quarter When, in the FY cycle you expect this project to be executed. Note: The quarter should follow the need by date.For example Need By date: Dec 31 2016 , Quarter: Q1
APT 22. Planned Acquisitions - Season When in the Fiscal Year cycle , you expect this project to be executed. Note: The season should follow the quarter and need by date For example. Need By date: Dec 31 2016 , Quarter: Q1, Season: Winter
APT 23. Comments *Optional - Please feel free to enter additional information about your submittal
17
Elevating the Quality of Life in the District
Legend-DGSAPT (Part 2) :
APT 1.
APT 2.
APT 3.
APT 5.
APT 4.
18
Elevating the Quality of Life in the District
Legend-DGSAPT (Part 3) :
APT 6.
APT 6. Batch # APT 6.
Line _ #
APT 7.APT 8.
APT 9.
19
Elevating the Quality of Life in the District
Legend-DGSAPT (Part 4) :
APT 10.
APT 11.
APT 12.APT 13.
20
Elevating the Quality of Life in the District
Legend-DGSAPT (Part 5) :
APT 14.
APT 15.APT 16.
APT 17.
21
Elevating the Quality of Life in the District
Legend-DGSAPT (Part 6) :
APT 18.
APT 19.APT 20.
APT 21.APT 22.
APT 23.
22
Elevating the Quality of Life in the District
Chapter 4: How do I enter information in the DGSAPT Electronic Form?
Overview
• DGS-APT General and Metrics Information Index Table
• Step1 DGS APT Submission Procedure – Log In
• Step 2 DGS APT Submission Procedure-PASS Navigation
• Step 3 DGS APT Submission Procedure-General Information
• Step 4 DGS APT Submission Procedure-Metrics Information
• Step 5 DGS APT Submission Procedure- Submittal
23
Elevating the Quality of Life in the District
Chapter 4: DGS-APT Index TableChapter 3 Legend # Categories Exhibits General & Metrics Information
APT 1. Title : Priority 0,1,2,3 or 4 Acquisitions A4 Step 3 – General Information
APT 2. Division Name A5 Step 3 – General InformationAPT 3. Division/Agency Point of Contact A6 Step 3 – General InformationAPT 4. Phone Number A7 Step 3 – General InformationAPT 5. Fiscal Year A7 Step 3– General Information
APT 6. Planned Acquisitions - DGS APT Batch # & Line _ # A8 Step 4 – Metrics Information
APT 7. Planned Acquisitions - Description A9 Step 4– Metrics Information
APT 8. Planned Acquisitions - Commodity Group A10 Step 4 – Metrics Information
APT 9. Planned Acquisitions - Funding Source A11 Step 4 – Metrics Information
APT 10. Planned Acquisitions - Need By Date A12 Step 4 – Metrics Information
APT 11. Planned Acquisitions - New Acquisition A13 Step 4– Metrics Information
APT 12. Planned Acquisitions - Procurement over $1M A14 Step 4– Metrics Information
APT 13. Planned Acquisitions - Mission Critical A15 Step 4– Metrics Information
APT 14. Planned Acquisitions - Estimated Amount A16 Step 4– Metrics Information
APT 15. Planned Acquisitions - Partial Letter Contract Needed A17 Step 4– Metrics Information
APT 16. Planned Acquisitions - Existing Contract Number A18 Step 4– Metrics Information
APT 17. Planned Acquisitions - CS , NC , AE services A19 Step 4– Metrics Information
APT 18. Planned Acquisitions - Can a CBE perform these projects A20 Step 4– Metrics Information
APT 19. Planned Acquisitions - Can a SBE perform these projects A21 Step 4– Metrics Information
APT 20. Planned Acquisitions - Green Procurement A22 Step 4– Metrics Information
APT 21. Planned Acquisitions - Quarter A23 Step 4– Metrics Information
APT 22. Planned Acquisitions - Season A24 Step 4– Metrics Information
APT 23. Comments A25 Step 4– Metrics Information
24
Elevating the Quality of Life in the District
Chapter 4: Step 1 DGS APT Submission Procedure – Log In
A1. Log in to Pass. Click here for PASS Login page:https://pass.in.dc.gov/Buyer/Main
A2. Enter your User Name and Password. Then click Login to enter PASS. If you have problems with your log in, please contact your DGS-IT department or ITservus
25
Elevating the Quality of Life in the District
Chapter 4: Step 2 DGS APT Submission Procedure-PASS Navigation
A3. scroll over the Common Actionsection
A3. scroll over the More…. Section. Click the drop down
A3. Select and click the DGS Acquisition Planning Tool ( DGS-APT)
26
Elevating the Quality of Life in the District
Chapter 4: Step 3 DGS APT Submission Procedure-General Information
A4. For the Title of the DGS APT Please enter Priority Status: 0,1,2,3,4. Please see DGS-APT Legend slide APT 1 for definition
A5. Please select from the drop box for your division
27
Elevating the Quality of Life in the District
A6. In the Division POC section, click select to find the DGS POC for your submittal
A6. Enter their name and select search.
A6. Select their name.
A6. Click done.
Chapter 4: Step 3 DGS APT Submission Procedure-General Information
28
Elevating the Quality of Life in the District
A7. Once the POC has been selected. Please input the following in the general information section:1. Enter the Phone number 2. Scroll down to select the Fiscal Year
*My label is not in legend; that is for OCTO and OCP use only
Chapter 4: Step 3 DGS APT Submission Procedure-General Information
29
Elevating the Quality of Life in the District
Chapter 4: Step 4 DGS APT Submission Procedure-Metrics Information
A8. Once the general information section has been filled please scroll down and click Add to generate a DGSAPT Batch & Line Number #
You should see the following:DGSAPT300_0
DGSAPT300 – The first (3) Digits of the number are your batch numbers
DGSAPT300_0 – The Last Digit in the DGSAPT batch is your Line number(s)
30
Elevating the Quality of Life in the District
A9. Please enter the project title in the description section.
A10. Next, select the commodity. For drill down information please reference the next slide.
A11. Select from the drop down box for the funding source
A12. After that click calendar icon, to select the Need by date /Due date
Chapter 4: Step 4 DGS APT Submission Procedure-Metrics Information
31
Elevating the Quality of Life in the District
A10. Drill down information - Commodity
For drill down information, here are the following steps :
Select the drop down box Click search for more
Select the drop box in Alland scroll down to the commodity group and select best fit for the type of project
Once you have found the commodity code that best fits your project/ procurement, Click select for the commodity to be included in the DGS-APT
Chapter 4: Step 4 DGS APT Submission Procedure-Metrics Information
32
Elevating the Quality of Life in the District
A13.After the Need by date /Due date has been selected. Select Yes or No A14.For
procurements over $1million dollars Select Yes or No to establish a base line threshold
A15. Next, for Mission Critical/Council Packages please select Yes or No
A16. Enter the dollar value of the procurement
A17. For purposes of tracking letter contracts, please indicate whether this project will require a Partial/ letter contract executed
Chapter 4: Step 4 DGS APT Submission Procedure-Metrics Information
33
Elevating the Quality of Life in the District
A18. If , a pre-existing contract is associated with your submittal then enter the contract number. If not then select N/A
A19. Select from the drop box CS, NC, or AE services
A20. If a CBE can perform select Yes. If not, select No.
A21. If a SBE can perform select Yes. If not, select No.
Chapter 4: Step 4 DGS APT Submission Procedure-Metrics Information
34
Elevating the Quality of Life in the District
A22. If the project is a green procurement select Yes. If not, select No.
A23. Then select from the drop down box the quarter of the procurement. The need by date should follow the quarter
A24. Then select from the drop down box the season the procurement should be submitted.
A25. Please feel free to enter any more description about your submittals
Chapter 4: Step 4 DGS APT Submission Procedure-Metrics Information
35
Elevating the Quality of Life in the District
Completed filled in DGS-APT example A26. Click submit
For Reference Please see - A8
*Optional Comments and add attachment -Please feel free to enter additional information about your submittal. We left this section optional due to the fact that you will still have to provide a comment and attach required documents to the Requisition in the Procurement Automated Support System (PASS)
Chapter 4: Step 5 DGS APT Submission Procedure- Submittal
36
Elevating the Quality of Life in the District
After the DGS-APT has been submitted. Congratulations ! The DGS submittal has been Completed!
A27. After you have submitted the DGS-APT you will see your DGSAPT Batch # and submittal title
DGSAPT317Priority 0 Acquisition
See slide for print view See slide for Status/ Approval flow view
Chapter 4: Step 5 DGS APT Submission Procedure- Submittal
37
Elevating the Quality of Life in the District
Print view
Chapter 4: Step 5 DGS APT Submission Procedure- Submittal
38
Elevating the Quality of Life in the District
Status/ Approval flow view
Chapter 4: Step 5 DGS APT Submission Procedure- Submittal
39
Elevating the Quality of Life in the District
Chapter 5: Unplanned Acquisition
Overview
• What happens if the procurement is unplanned ?
• What are the steps for processing an unplanned procurement ?
40
Elevating the Quality of Life in the District
What happens if the procurement is
unplanned ?
The Contracting and Procurement Division has created the DGS Project Initiation Form ( DGS-PIf ) to help facilitate Ad-hoc procurement requests. The Department of General Services Project Initiation Form (DGS-PIF) is an electronic form similar to the DGS-APT which is in the Procurement Automated Support System (PASS).
41
Elevating the Quality of Life in the District
Step1. The program will identify the unplanned, emergency or partial procurement need
Step2. The Customer Division will log on to Pass to fill out and submit the DGS Project Initiation
Form
Step3. The Policy Research and Planning Branch will receive a notification that a new submittal
has been entered
What are the steps for processing an Unplanned
Procurement ?
42
Elevating the Quality of Life in the District
Step4. The Policy Research and Planning Branch will analyze the data received from the
customer divisions.
Step5. The Policy Research and Planning Branch will then approve the Ad-Hoc procurement
request
Step6. You have Completed the D-PIF process!
What are the steps for processing an Unplanned
Procurement ?
43
Elevating the Quality of Life in the District
Chapter 6: DGS-PIF Legend and Definitions
Overview
• Legend# -PIF is the legend number Icon in this section
• Categories – are various attributes inside the DGS-PIF form *My label is not in
the legend; this is for OCTO and OCP use only
• Definitions – are the description of the categories
44
Elevating the Quality of Life in the District
Legend-DGS-PIF(Part 1) : Legend # Categories Definition
PIF 1. Title : Priority 0,1,2,3 or 4 Acquisitions
Title should state the priority Levels 0-4 ,for example: Priority 0 Acquisitions - High Priority High Risk, Priority 1 Acquisitions - High Priority Attention is needed, Priority 2 Acquisitions-
Moderate Priority Moderate Risk , Priority 3 Acquisitions - Moderate Priority Low Risk, Priority 4 Acquisitions- Low Priority Low Risk
PIF 2. Division Name Requesting Division PIF 3. Division/Agency Point of Contact Program Manager - Point of contract full name PIF 4. Commodity Group The commodity group under which the acquisition falls i.e. goods PIF 5. Phone Number Program Manager contact information
PIF 6. Estimated Contract Date Needed Estimated Contract Date Needed/ Due date when acquisition is expected ( If you have project plans , please enter them into the attachment )
PIF 7. Estimated Dollar Amount Estimated dollar value of the project.
PIF 8. Procurement over $1M For metrics and tracking purposes
PIF 9. Mission Critical Mission Critical/ Council Packages ( Is this a council package Yes or No ?) PIF 10. Green Procurement Can green procurement standard be used for this acquisition request? PIF 11. Procurement Method This option allows you to recommend a procurement method PIF 12. Partial Letter Contract Needed Will a partial letter will be used to execute parts of this project ?
PIF 13. CS , NC , AE services Select if it is a Construction , Non- Construction , or Architecture and Engineering Services PIF 14. Can a CBE perform these projects Can this project be set aside for the CBE market ? PIF 15. Can a SBE perform these projects Can this project be set aside for the SBE market ?
PIF 16. Quarter When, in the FY cycle you expect this project to be executed Note: The quarter should follow the need by date. For example Need By date: Dec 31 2016 , Quarter: Q1
PIF 17. Season When in the Fiscal Year cycle , you expect this project to be executed. Note: The season should follow the quarter and need by date For example. Need By date: Dec 31 2016 ,
Quarter: Q1, Season: Winter PIF 18. Project Scope Please state if the project is a new acquisition , partial/letter contract ,or both PIF 19. Project Description ( Just like the DGS APT ) The acquisitions/project title PIF 20. * DGS APT number if any ? *If the submittal is attached to any planned procurement please select the batch number PIF 21. * DGS APT line *If the submittal is attached to any planned procurement please drill down to the DGSAPT
batch and select the line number PIF 22. Comments *Optional - Please feel free to enter additional information about your submittal
PIF 23. Add attachment * Optional - Documentation are not due until the RQ is initiated in PASS
45
Elevating the Quality of Life in the District
Legend-DGSPIF (Part 2) :
PIF 1.
PIF 2.
PIF 3.
PIF 4.
PIF 5.
PIF 6.
PIF 7.
46
Elevating the Quality of Life in the District
Legend-DGSPIF (Part 3) :
PIF 8.
PIF 9.
PIF 10.
PIF 11.
PIF 12.
PIF 13.
PIF 14.
PIF 15.
PIF 16.
PIF 17.
PIF 18.
PIF 19.
PIF 20.
47
Elevating the Quality of Life in the District
Legend-DGSPIF (Part 4) :
PIF 20.
PIF 21.
PIF 22.
PIF 23.
48
Elevating the Quality of Life in the District
Chapter 7 : How do I enter information in the DGS-PIF Electronic Form?
Overview
• DGS-PIF General and Metrics Information Index Table
• Step1 DGS PIF Submission Procedure – Log In
• Step 2 DGS PIF Submission Procedure-PASS Navigation
• Step 3 DGS PIF Submission Procedure-General Information
• Step 4 DGS PIF Submission Procedure-Metrics Information
• Step 5 DGS PIF Submission Procedure- Submittal
49
Elevating the Quality of Life in the District
Chapter 7 : DGS-PIF Index TableChapter 6 Legend # Categories Exhibits General & Metrics Information
PIF 1. Title : Priority 0,1,2,3 or 4 Acquisitions P4 Step 3 – General Information
PIF 2. Division Name P5 Step 3 – General InformationPIF 3. Division/Agency Point of Contact P6 Step 3 – General InformationPIF 4. Commodity Group P7 Step 3 – General InformationPIF 5. Phone Number P7 Step 3 – General Information
PIF 6. Estimated Contract Date Needed P8 Step 4 – Metrics Information
PIF 7. Estimated Dollar Amount P8 Step 4 – Metrics Information
PIF 8. Procurement over $1M P8 Step 4 – Metrics Information
PIF 9. Mission Critical P8 Step 4 – Metrics InformationPIF 10. Green Procurement P8 Step 4 – Metrics InformationPIF 11. Procurement Method P9 Step 4 – Metrics Information
PIF 12. Partial Letter Contract Needed P9 Step 4 – Metrics InformationPIF 13. CS , NC , AE services P9 Step 4 – Metrics Information
PIF 14. Can a CBE perform these projects P10 Step 4 – Metrics InformationPIF 15. Can a SBE perform these projects P10 Step 4 – Metrics Information
PIF 16. Quarter P10 Step 4 – Metrics Information
PIF 17. Season P10 Step 4 – Metrics Information
PIF 18. Project Scope P11 Step 4 – Metrics InformationPIF 19. Project Description ( Just like the DGS APT ) P11 Step 4 – Metrics InformationPIF 20. * DGS APT number if any ? P12 Step 4 – Metrics InformationPIF 21. * DGS APT line P12 Step 4 – Metrics Information
PIF 22. Comments *Optional Step 4 – Metrics Information
PIF 23. Add attachment *Optional Step 4 – Metrics Information
50
Elevating the Quality of Life in the District
P1. Log in to Pass. Click here for PASS Login page:https://pass.in.dc.gov/Buyer/Main
P2. Enter your User Name and Password. Then click Login to enter PASS. If you have problems with your log in please contact DGS IT department or ITservus
Chapter 7 : Step 1 DGS PIF Submission Procedure – Log In
51
Elevating the Quality of Life in the District
Chapter 7 : Step 2 DGS PIF Submission Procedure-PASS Navigation
P3. scroll over the Common Actionsection
P3. scroll over the More….Section. Click the drop down
P3. Select and click the DGS Project Initiation Form ( DGS-PIF )
52
Elevating the Quality of Life in the District
P4. For the Project Title of the DGS PIF, please enter Priority Status: 0,1,2,3,4. Please see DGS-PIF Legend slide PIF1 for definition
P5. Please select from the drop down box for your division
Chapter 7 : Step 3 DGS PIF Submission Procedure-General Information
53
Elevating the Quality of Life in the District
P6. In the Division POC section, click select to find the DGS POC for your submittal
P6. Enter their name and select search.
P6. Select their name.
P6. Click done.
Chapter 7 : Step 3 DGS PIF Submission Procedure-General Information
54
Elevating the Quality of Life in the District
P7. Once the POC has been selected. Please enter the following in the general information section:1. Select the commodity
group from the drop down 2. Enter the Phone number
Chapter 7 : Step 3 DGS PIF Submission Procedure-General Information
55
Elevating the Quality of Life in the District
P8.Then complete the following metrics information on the DGS-PIF form:
> Select the Calendar date > Enter the estimated dollar amount in your submittal >If Procurement is over $1Million Then select Yes If not
Then select No >If Submittal is a Mission Critical/Council Package
Then select Yes If not Then select No >If Submittal is a Green Procurement Then select Yes If not
Then select No
Chapter 7 : Step 4 DGS PIF Submission Procedure-Metrics Information
56
Elevating the Quality of Life in the District
P9.Then complete the following metrics information on the DGS-PIF form:
> Select the recommended procurement method from the drop down > If Partial /Letter Contract Needed Then select Yes
If Partial /Letter submittal Then select Yes and enter in the comment box Partial Contract Submittal
> Select the type of services from the drop down
Chapter 7 : Step 4 DGS PIF Submission Procedure-Metrics Information
57
Elevating the Quality of Life in the District
P10.Then complete the following metrics information on the DGS-PIF form:
> If A CBE can perform this project Then select Yes If not Then select No > If A SBE can perform this project Then select Yes If not Then select No
> Select from the drop down the quarter > Select from the drop down the season
*Note: The season should follow the quarter and Contract Date
Chapter 7 : Step 4 DGS PIF Submission Procedure-Metrics Information
58
Elevating the Quality of Life in the District
P11. Please enter the Project scope and description:
Project Scope - Please state if the project is a new acquisition , partial/letter contract ,or both.
Project Description - The acquisitions/project title
Chapter 7 : Step 4 DGS PIF Submission Procedure-Metrics Information
59
Elevating the Quality of Life in the District
P12. If Submittal is a Partial Contract of a planned DGS –APT BATCH or LINE # Thenselect from the drop
* Please see next slide for drill down navigation
*Optional Comments and add attachment - Please feel free to enter any more description about your submittal , we left this section optional due to the fact that you will still have to provide a comment and attach required documents to the Requisition
Chapter 7 : Step 4 DGS PIF Submission Procedure-Metrics Information
60
Elevating the Quality of Life in the District
P12. Drill Down Navigation - DGS-APT number if any
For drill down information here are the following steps :
1. Select the drop down box 2. Click search for more
Click search
Chapter 7 : Step 4 DGS PIF Submission Procedure-Metrics Information
61
Elevating the Quality of Life in the District
P12. Drill Down Navigation - DGS-APT number if any
Then click select for the DGS APT BATCH # to be in the DGS-PIF
Once the DGSAPT Batch has been selected
*DGSAPT300 – The first (3) Digits number are your batch numbers
*Then you will need to drill down to select the Line#
DGSAPT300_0 – The Last Digit in the DGSAPT batch is your Line number(s)
Then click select for the DGS APT Line # to be added on the DGS –APT Batch # and DGS –PIF submittal.
Chapter 7 : Step 4 DGS PIF Submission Procedure-Metrics Information
62
Elevating the Quality of Life in the District
Completed DGS-PIF example:P13. Click submit
Chapter 7 : Step 5 DGS PIF Submission Procedure-Submittal
63
Elevating the Quality of Life in the District
After the DGS-PIF has been submitted. Congratulations! The DGS-PIF submittal has been Completed!
P14. After you have submitted the DGS-PIF you will see your DGSPIF # and submittal title
DGSPIF255Priority 0
See slide for print view See slide for Status/ Approval flow view
Chapter 7 : Step 5 DGS PIF Submission Procedure-Submittal
64
Elevating the Quality of Life in the District
Print view
Chapter 7 : Step 5 DGS PIF Submission Procedure-Submittal
65
Elevating the Quality of Life in the District
Status/ Approval flow view
Chapter 4: Step 5 DGS APT Submission Procedure- Submittal
66
Elevating the Quality of Life in the District
Chapter 8: Querying & Reporting
Overview
• Step1 Querying & Reporting Procedure – Log In
• Step 2 Querying & Reporting Procedure-PASS Navigation
• Step 3 Querying & Reporting Procedure-Reporting Selection
• Step 4 Querying & Reporting Procedure-Formatting and Completion
67
Elevating the Quality of Life in the District
R1. Log in to Pass. Click here for PASS Login page:https://pass.in.dc.gov/Buyer/Main
R2. Enter your User Name and Password. Then click Login to enter PASS. If you have problems with your log in please contact your DGS IT or ITservus
Chapter 8: Step 1 Querying & Reporting Procedure – Log In
68
Elevating the Quality of Life in the District
Chapter 8 : Step 2 Querying & Reporting Procedure-PASS Navigation
R3. Scroll over the Manage section
R3. Click reports
69
Elevating the Quality of Life in the District
Chapter 8 : Step 2 Querying & Reporting Procedure -PASS Navigation
R3. Click the New Report
70
Elevating the Quality of Life in the District
Chapter 8 : Step 3 Querying & Reporting Procedure- Reporting
R4. If The report you want to run is for Planned Acquisition Then select DGS Acquisition Planning Tool DGS APT
R4. If The report you want to run is for Unplanned Acquisition Then select DGS Project Initiation Form
R5. Once the report has been selected please click next
71
Elevating the Quality of Life in the District
Chapter 8 : Step 3 Querying & Reporting Procedure- Reporting
R5. Click next to move on to the next step or click previous to go back and change the selection of the reports
72
Elevating the Quality of Life in the District
Chapter 8 : Step 4 Querying & Reporting Procedure- Formatting & Completion
R6. Please do the following for report formatting :
1. Go to REPORT FORMAT and Select the export format. 2. Go to STATUS and select what status you want exported for you query.3. Select the report timeframe for export.4. Select RUN to export your query
Congratulations! The reporting process has been Completed!
73
Elevating the Quality of Life in the District
Chapter 9: Closing
Overview
• Frequently Asked Questions
74
Elevating the Quality of Life in the District
Frequently Asked Questions: Question Answer
What does the acronym DGS –APT Stand for ? DGS – Acquisition Planning Tool
What does the acronym DGS –PIF Stand for ? DGS – Project Initiation Form
What is the purpose of DGS –APT ? A tool to plan, track and report procurements for the upcoming fiscal year
What is the purpose of DGS –PIF ?A tool for use to initiate, track and report unplanned procurements ( Procurements that were not
included in the DGS –APT )
How does DGS-APT benefit the agency/DGS?The adoption of the DGS –APT & DGS PIF will automate the process of disseminating
procurement/budget information to DC council, EOM and the City Administrator. This information will also be used for procurement forecast scheduling and workload management
How do we submit a DGS –APT/DGS PIF?DGS –APT/DGS PIF’s are submitted in the Procurement Automated Support System (PASS ) .
DGS –APT/DGS PIF required/ mandatory ?Yes. Pursuant to under the Procurement Practices Reform Act of 2010 (PPRA), effective April 8,2011
,Section 1105. Without an approved DGS-APT or DGS-PIF you will NOT be able to submit a requisition in PASS for your division
Who is the POC for each division ? Please see the slide # 8
Who is the division budget POC ?The Resource Allocation Division personnel
Is DGS –APT/DGS PIF tied to the division’s budget? Yes. A funding source from division budget should be identified ,prior to adding DGS –APT/DGS PIF in PASS. Funding will be verified prior to issuing a PO
How does the approval flow work for DGS –APT/DGS PIF ?
Each division submits the DGS –APT/DGS PIF in PASS. PASS will notify the C&P Policy Research and Planning Branch staff member responsible for review/ approval via email. The DGS –APT/DGS PIF will
be reviewed by the responsible staff member in C&P’s Policy Research and Planning Branch for approval or denial
DGS –APT/DGS PIF reporting is available ? Yes. There is reporting in PASS ( Please see slide 64 through 73)
Who is the first point of contact for questions regarding DGS –APT/DGS PIF ? C&P’s Policy Research and Planning Branch Program Manager and Project Manager
75