This Briefing is:UNCLASSIFIED
Headquarters Air Combat Command
Mr. Luke Savage Mr. John Kochanowski
HQ ACC/CEBG
ACC GeoBase Service Conceptualization to ImplementationConceptualization to Implementation
Overview
Project Scope
ConceptualizationConceptualization
Implementation PlanImplementation Plan
Lessons LearnedLessons Learned
Project ScopeACC GeoBase Overview
• ACC GeoBase Philosophy• Base Success First
• 3-Phased Implementation Plan
• Heavy Emphasis on Data Stewardship
• Goal: Enhanced Operating Capability
ACC GeoBase Services across ACCACC GeoBase Services across ACC
Project ScopeBasics
• $1.2M GWOT funding secured in support of HLS
• Contracted through GSA Sep 2003
• Contractor
Overview
Project Scope
ConceptualizationConceptualization
Implementation PlanImplementation Plan
Lessons LearnedLessons Learned
ConceptualizationGetting Started
Where to Start?Where to Start? Initial ConsiderationsInitial Considerations• Timeline
• USAF Server Consolidation Policy
• Service Level Agreement
• Certificate to Operate
• Existing Infrastructure
ConceptualizationHeavy Coordination
ConceptualizationPre-planning
What do we have to work with?What do we have to work with?
Rack Space?
SAN Component Space?Rack Electrical Power?
SAN Electrical Power?Cables & Circuits?
Port Availability?
UPS availability?
ConceptualizationInfrastructure
Physical Inspection• Coordinated by ACC Electrical Engineer • Electric Shop questionnaire developed• Determine electrical requirements
Electrical Upgrades• New Distribution Panels, Circuits, Whips, Receptacles• $$ ??• Scheduling
Installation GIO Outreach• Opportunity to work with Comm & CE electrical shops
ConceptualizationSpecial Partnerships
ACC/SCSO CE Information Technology Consultant• Staffs Service Level Agreement• Works Certificate to Operate issues/concerns
AF Public Key Infrastructure (PKI)• PKI office issues certificates• Required for running Secure Sockets Layer (SSL)
ACC Network Operations and Security Center (NOSC)• Server alias• Pushes AFCERTS
Implementation PlanPre-Planning
• Phased Approach
• Design Implementation
• Test Implementation
• Envision Schedule
50% Reachback, 50% ACC GIO
Fly to Destination
Install Oracle, SDE, IMS
Train Onsite Personnel
Information Exchange
Fly Back
Implementation PlanStrategy
• Action Plan• Technical Document• Administrative Guide
https://ce.acc.af.mil/ceo/ceos/geobase/Projects.html
Phase 1Schedule
• Coordinating Schedules with Vendor
Phase 1Hardware Install
• Hardware Procurement• Verify Implementation Configuration
Phase 1System Preparation
• Lockdown Servers• Secure Operating Systems• Alias Server (https://<alias name>)
• Verify Security Protocols• Test website for access
Phase 2Overview
• ESRI
• ArcSDE 8.3, ArcIMS 4.0.1, ArcGIS 8.3
• Oracle
• Oracle Enterprise Manager 9i
Phase 2Schedule
• Schedule Workflow
• Two - 2 person Teams
• Alternating Schedule
Phase 2Service Implementation
GIO, GSI Team, GIS Analyst, GIS TechnicianFinal Comments from GIO
GIO, GSI Team, GIS Analyst, Flight ChiefOutBrief (optional)
AllInformation Exchange
GIS Analyst, GSI TeamTraining/Document System
GIO, Mr. SavageInformation ExchangeThursday
GIO, Mr. SavageWorking Group Meeting (optional)
GIS Analyst, GSI TeamTrainingWednesday
GIS Analyst, GSI TeamHW/SW InstallationTuesday
GIS Analyst, GSI TeamHW/SW Installation
GIO, Mr. SavageInformation Exchange
GIO, Mr. Savage, Flight Chief…In-BriefMonday
AttendeesDescriptionDay
Phase 2Delivery
• General Interface
• Standardization
• No Stovepipes
• CTO Legitimizes
• SMART Development
Lessons LearnedPreparation
• Have an interim CtO
• Establish SLA Early
• Spend time on the plan with all installation support• Increases efficiency• Clear understanding of the level of effort for all parties
• Pilot test 1st Base
Lessons LearnedChallenges
• Manage expectations• Out of the Box functionality – Tools needed?• Keep GIO focused on managing the new system…not on app
development
• COMM’s support for back-ups – from not having an SLA
• Understanding Software Limitations • example: ArcMap Server
• Sustainment
Lessons LearnedSuccesses
• Documentation• Has been used at non-ACC bases
• Level of Coordination with multiple AF organizations
• Letting the base GIO perform install as opposed to HQ staff
Questions/Comments