© 2011 SAP AG. All rights reserved. 1
Opportunity Roadmap - Fact sheet
Date
<Opp.name> <Client name>
Business Situation (facts), Their Problem, Impact, Need to Act; What if they do nothing?
Clients Need To Act
Management Sponsor of MU
Responsible Consulting Manager
Opportunity Team (+ Role) N.N. (Bid Manager) N.N. (Solution Architect) N.N. (Industry Expert) N.N. (…)
Customer Responsible (GAD, GAM, AE, CEM/CP)
N.N.
Organization of Opportunity Team
abc…
Actual Status/Results
1. …
2. …
Solution ScopeField Service Value PropositionSAPs USPs (differentiators)
Overview of our Offer
abc…
Risks/ Threats
Next Steps
1. ….
Competitors
Price-/Project Type Fixed Price
Margin X%
GD Days X days
* 1.000 EUR
lastchange
Closing Month
Opp OwnerMastercodeCurrent Phase
CompanyOpp / Pipe ID
35 %Probability (personal
judgment)
Solution Fit
Customer Feedback
Conditions/Budget
Staffing/Delivery
X €Education Revenue
nameInvolved Partner
G
Y
R
R
SAP CONFIDENTIALCutover Strategy(with details becomes Cutover Kickoff)
Client
Project Name
Opportunity Owner
CEM / CP
AE / AM
Date
© 2011 SAP AG. All rights reserved. 2
Agenda
1. Cutover Strategy2. Timeline3. Go Live Acceptance Criteria4. Cutover Organization and Responsibilities
4.1. Legacy Team4.2. Migration Team4.3. Business Team
5. Cutover Schedule6. Cutover Simulations7. Cutover Communications8. Contingency Plan9. Implementation Support10. Logistics
© 2011 SAP AG. All rights reserved. 3
Cutover Strategy
Time constraints?
Big bang or phased?
Sequence?
Parallel system with legacy?
© 2011 SAP AG. All rights reserved. 4
High Level Cutover TimelineMo October November December January
Wk
3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4
1 Business Preparation
2 Production Environment Preparation
3 Project Team Preparation
4 Master Data Migration
5 Cutover Preparation
6 Legacy Changes and Shutdown
7 Transaction Data Migration
8 Key Processes Execution
9 Legacy Shutdown
10 Security access enabled
11 Go Live
12 Go Live Support – Hyper Care
13 Go Live Support – Long Term
Cutover Simulations
Kuala Lumpur
Basingsto
ke
New York
© 2011 SAP AG. All rights reserved. 5
Go Live Acceptance Criteria
The business identifies the acceptance criteria during Realization in order to: Maintain the focus on going live on time Focus project team efforts on critical tasks
Acceptance criteria needed for major milestones To begin Production Cutover, for example:
– Acceptable levels of passing for Integration Tests
– Acceptable levels of trained and certified users
– Acceptable levels of open issues
– Acceptable performance criteria
To accept Master Data, for example:– Planned accuracy percent of data load by object
To accept Transactional Data, for example:– Planned accuracy percent of data load by object
– Key processes that execute correctly in Production post migration
– Meeting acceptance criteria allows move to next steps
© 2011 SAP AG. All rights reserved. 6
Cutover Organization
Cutover Manager
Data MigrationTeam Lead
Functional Team Lead
Site coordinators
Key users
LegacyTeam Lead
Business Team Member
Data MigrationTeam
OCM Team Lead
LegacyTeam
© 2011 SAP AG. All rights reserved. 7
Roles and Responsibility
Cutover Manager Creates and maintains master cutover schedule Defines organization and logistics for cutover Manages cutover issues and their resolution Ensures communication to all stakeholders
OCM Team Lead Provides formal communications
Team Leads Create cutover schedule for team as input to the master cutover schedule
Legacy Team Extract data Provide reports to aid in validation
Data Migration Team Lead Creates cutover schedule for data migrations as input to the master cutover schedule Manages data loads prior to cutover Documents results of each data load
Data Migration Team Execute migrations Provide aid in validation
Business Team Members Validate converted data and resolve errors Identify and execute key process tests
Project Team Hyper care period support
Site Coordinators Manages site readiness Manages site issues and their resolution
Key Users First line support
© 2011 SAP AG. All rights reserved. 8
Long term Responsibility
Inventory of legacy systems Identify systems to sunset Identify any modifications needed
Inventory of batch processes to reschedule or cancel
Identification of security access requirements During cutover Post Go Live
© 2011 SAP AG. All rights reserved. 9
Migration Team Responsibility
Determine whether migration is: One-time Multiple times for a file with deltas Determine approach to dual maintenance, as required
Determine sequence of migrations
Document migration quality tracking in Migration Quality Tracking spreadsheet Track record counts, validation work, and time requirements Create an individual spreadsheet for each data load including unit test, simulation loads,
training migration, etc.
Aid the business to cleanse and validate the data
© 2011 SAP AG. All rights reserved. 10
Migration Team Responsibility
Purpose
Objectives & Goal
Migration Plan Strategy & Methods
Planning & Accelerated SAP, (ASAP) Phases
Migration Planning High Level Activities
Go-Live Scope of Activities & Migration
Key Team Members Worksheet
Migration/Cutover Schedules
Top Assumptions
© 2011 SAP AG. All rights reserved. 11
Purpose
The Migration Plan identifies the activities to be performed during the cutover process from getting started through execution of all related tasks: Planning, Acceptance and Execution.
The plan further defines the activities required to facilitate a smooth transition into production for additional SAP functionality.
The major activities of Migration are the migration of master data and getting the Production SAP system functionally and technically ready.
The Migration Plan template is to be re-useable for each separate Migration effort (release schedule).
© 2011 SAP AG. All rights reserved. 12
Objectives and Goals
Objectives
Establish the Process for the Actual Go-Live Transition
Define the Approach and Framework for executing the Cutover
Establish Approval Criteria for Formal Cutover Acceptance
Define Project Team Activities, Roles & Responsibilities
Define Organization Team Activities, Roles & Responsibilities
Define Project Management Activities, Roles and Responsibilities
Goal
The Goal is a plan to ensure a smooth transition to production
Deployment
Organization
Training Data
Security
SystemDesign
Technical Infrastructure
Production
IT Driven Items
Business Driven Items
© 2011 SAP AG. All rights reserved. 13
Migration Plan Strategy & Methods
For each SAP Project Schedule, (release) there will be a separate set of Migration documents created using the following Migration templates: Cutover Schedule Cutover Checklist Final Cutover Checklist
A Cutover Schedule will be maintained for each release schedule tracking all key area milestone dates to ensure all areas are coming together for the individual Migration effort.
A Cutover Checklist will be created with all necessary detail and dependencies and tested/updated via the cutover simulations and lessons learned process.
Acceptance criteria by key area will be defined for each Migration effort using the Final Cutover Acceptance Checklist template.
Lessons Learned from each Migration effort are to be evaluated and included as updates to the Migration Plan going forward.
© 2011 SAP AG. All rights reserved. 14
Migration Planning & AcceleratedSAP Phases
Create Initial Migration
Plan
Go-Live & Support
Blueprint Phase Realization Phase Final Preparation Phase Go-Live
Revise & Finalize Migration Plan
Execute Migration Plan
© 2011 SAP AG. All rights reserved. 15
Migration Planning High Level (Activities)
Test/Re-Test Data Migration
Programs & Files
Test/Re-Test Data Migration
Files
Finalize Data Migration
Files Go-Live
Ongoing System
Maintenance
Test Cutover Activities, Execute
Volume & Stress Testing (Repeat 3X min), Payroll
Interface Testing w/Customer Data
Move Transports into Production, Data migration & Validation in Production,
(Execute All Cutover Activities)
Create & Load Data
Migration Files
Develop Volume & Stress Test Scenarios Apply Latest Support Packs to DEV/QA/Prod
Production Support
Organization Readiness Planning
Create End-User Training Plans
Create SAP Training Materials,Customer Acceptance (CAT), Regression &
Security Roles & Rights Testing
Conduct End-User Training
Realization Phase Final Preparation Phase Go-Live
© 2011 SAP AG. All rights reserved. 16
Go-Live Scope of Activities
Migration Plan Key
Components
• Cutover Strategy
• Cutover Schedule
• Cutover Checklist
• Final Cutover Acceptance Checklist)
• Technical, (Infrastructure)
• Functional (System Design)
• Development (System Design)
• Authorizations (Security Roles & Rights))
• Data Cleansing
• Data migration
• Training
• Organization Change Management
• Project Management
• Infrastructure
• System Design
• Security
• Data
• Training
• Organizational
• Deployment
Key Areas Acceptance Criteria
Legacy SourceData for migration
Legend:
1. Items highlighted in blue are “directly” related to Migration & are tested via the Migration process.
2. Items highlighted in black are “indirectly” related to Migration with the final outcome of the testing being incorporated into the Migration effort.
3. Items highlighted in grey are not part of the Migration effort and are tracked to ensure the overall success of the implementation.
© 2011 SAP AG. All rights reserved. 17
Top Assumptions
System design work (configuration and enhancements) in scope have been completed and integration tested end-to-end.
Interfaces from SAP to external Customer systems in scope have been completed and integration tested end-to-end (with new data set), with receiving system resources confirming both receipt and acceptance. (Requires downstream systems (including those connected to XI) to be locked into SAP integration testing and acceptance schedule.)
Additional development work (authorizations, reports, forms, migrations, etc.) in scope have been completed and tested.
Data to be converted into the new SAP environment has been cleansed, validated and approved for migration into SAP.
The cutover approval process is timely and is based on the approval criteria defined as part of the Migration plan for both the Business owners and Information Technology areas involved.
Pre-requisite and parallel activities are completed and approved prior to the go-live (security roles and rights testing, customer acceptance testing, end-user training, organizational change management activities, etc.).
Resource constraints will be managed based on priority, criticality and urgency.
Each team involved retains the resources and skill sets required to complete the tasks related to their respective areas in the time needed.
No historical data is part of migration/cutover process into SAP for the go-live.
© 2011 SAP AG. All rights reserved. 18
Business Responsibilities
The business identifies: Key personnel and staffing plans New data requirements Preparation for cutover
o Business preparation activitieso Process cut off milestones
Alternative business processes for transition periods Acceptable business shut-down window Key processes to execute in production after data migration End user requirements
– Training or certification requirements– Log on distribution logistics and requirements– Start up procedures– Business resources for cutover:o Key Userso Site Coordinators
The business is responsible for the data Cleansing Validating
Determine dual maintenance requirements, if any
© 2011 SAP AG. All rights reserved. 19
Cutover Schedule
Each functional, data, and technical team lead to maintain a list of cutover activities in Team Cutover Schedule Created before migration to QA box Provided to Cutover Manager for use in QA build Once provided to Cutover Manager, the Team schedules are no longer maintained, as there
is only one Master Cutover Schedule
Cutover Manager merges the Team Schedules into the Master Cutover Schedule Executes merged schedule to build QA box, Prod box, simulation cutovers, and cutover to
production Updates schedule as needed to provide the most error-free cutover to production Re-uses the schedule for each
The Master Cutover Schedule leverages MS Project’s predecessor and successor functionality to enable forecasting of time requirements for cutover
© 2011 SAP AG. All rights reserved. 20
Cutover Simulations
Each functional, data, and technical team lead to maintain a list of cutover activities in Team Cutover Schedule Created before migration to QA box Provided to Cutover Manager for use in QA build Once provided to Cutover Manager, the Team schedules are no longer maintained, as there
is only one Master Cutover Schedule
Cutover Manager merges the Team Schedules into the Master Cutover Schedule Executes merged schedule to build QA box, Prod box, simulation cutovers, and cutover to
production Updates schedule as needed to provide the most error-free cutover to production Re-uses the schedule for each
The Master Cutover Schedule leverages MS Project’s predecessor and successor functionality to enable forecasting of time requirements for cutover
© 2011 SAP AG. All rights reserved. 21
Cutover Communications
Audience Responsible Method Frequency
Project Team Cutover Shift Manager
Project Schedule on shared drive
Voice mail status
Minimum of hourly
Cutover Person Responsible
Cutover Shift Manager
Phone As needed, two hours before needed
Steering Committee and Management
Cutover Shift Manager
Voice mail status Minimum of every 4 hours
Site Coordinators Cutover Shift Manager
Open teleconference line
Minimum of daily
Stakeholders OCM Manager Formal email At pre-determined points
© 2011 SAP AG. All rights reserved. 22
Contingency Plan
Risks and mitigations for cutover
Time required to restore legacy
Position decision points for proceeding with next steps
Identify acceptance requirements for each decision point
© 2011 SAP AG. All rights reserved. 23
Implementation Support
Hyper care period Project team staffs cutover room for 2 weeks Schedule developed for 24 x 7 support Help Desk phone line coordination
Long term Handover to Help Desk after 2 weeks
© 2011 SAP AG. All rights reserved. 24
Logistics
All cutover activities performed in Conference Room 101
Cutover Shift Manager contacts person who is next up for execution at least 2 hours in advance If you are on the cutover schedule, check the phone line for status
All project team members Remain within 1 hour driving distance of the conference room from 12/29 – 1/2 Are reachable via telephone 24 x 7 from 12/25 – 1/6
Building Entry cards function 24 x 7 from 12/20 – 1/15
Food served for cutover team members Count taken from Cutover Shift Schedule If you are additional team member, add your name to list at …
Contact List.xls is located at … Update your information
Thank You!