Project Management
8/13/2019 4 Project Mgt
2/69
2013 Lew Hofmann
Managing Projects
Projects are usually large & infrequent or one-time.
No two projects are the same.
Projects are usually fairly long. Several months to many years
They Involve different people in different phases
Most people are only involved with a part of a project
Even though a project may be under the overallpurview of a single department or group, other
departments are often involved.
8/13/2019 4 Project Mgt
3/69
2013 Lew Hofmann
Projects
The three main goals of projectmanagementare
1. Complete the project on time or earlier.
2. Complete the project on or under budget.
3. Meet the specifications to the satisfaction ofthe customer.
8/13/2019 4 Project Mgt
4/69
8/13/2019 4 Project Mgt
5/69
2013 Lew Hofmann
Pro ject Structu res
Functional Structure: The team is housed in a
specific functional area.Assistance from other
areas must be negotiated.
Pure Project: Team members work exclusively for
the project manager. (Best for large projects.)
Matrix Structure:A compromise between the
functional and project structures. Members remain
in various functional areas and the project manager
coordinates across functional areas. Having two
bosses (dual authority) can cause problems.
8/13/2019 4 Project Mgt
6/69
2013 Lew Hofmann
Project Management Techn iques
PERT CPM GERT
Program Evaluation and Review Technique PERT(Program Evaluation and Review Technique) is
utilized when activity times are uncertain (involved risk).
Critical Path Method CPM(Critical Path Method) is used when activity times
are known and certain.
Graphic Evaluation and Review Technique Rarely used, and then only in very complex projects.
It overcomes many of the limitations of PERT and CPM
Provides much more project flexibility.
8/13/2019 4 Project Mgt
7/69
2013 Lew Hofmann
Project Management Steps
1. Describe the Project (Defining all the tasksthat must be completed, and in what sequence.)
2. Develop a Graph Model(diagram thenetwork showing task relationships)
3. Develop an activity Schedule (Determinethe time estimates for each task)
4. Analyzing cost-time trade-offs(Determine the cost of each task.)
5. Assess Risks (Probability analysis)
8/13/2019 4 Project Mgt
8/69
2013 Lew Hofmann
Step 1
Desc r ibe the p ro ject
What is the project?
When does the project start and end?
What activities make up the project?
Activitiesare defined as the smallest units ofwork that a project manager is expected toschedule and control.
...a managers project description should reflect onlythe level of detail that he or she needs in order to
make scheduling and resource allocation decisions.
Task Ownership: Each activity must havean owner who is responsible for seeing thatthe work is accomplished.
8/13/2019 4 Project Mgt
9/69
2013 Lew Hofmann
Relat ionships
between Act iv i t ies
A project is a sequence of activities. Large projects have interrelated sequences.
Except for the beginning activity/activities, every
activity in a project has one or more activities
that must be done immediately prior.
These are called Precedent (Pre-cee-ent)
activities
Theymust be defined before the project begins.
EG: In order to bury a body you must first dig a hole.
8/13/2019 4 Project Mgt
10/69
2013 Lew Hofmann
Step 2
Develop a Network Model
A Network Diagramvisually displays theinterrelated activities using nodes (circles) andarcs (arrows) that depict the relationships between
activities. It is a graphical diagram.
For very large projects it may only be a numericalarrangement of activities rather than graphical.
Two types of Graphical Network Models Activity On Arc(AOA)
Activity On Node(AON) (We will use AON)
8/13/2019 4 Project Mgt
11/69
2013 Lew Hofmann
Two Types
of Network Models
Activity-on-Arc (AOA)
Activity-on-Node (AON)Activity Activity
Link
We wil l
use th is!D E
Time Time
Activity E
Time
Activity D
8/13/2019 4 Project Mgt
12/69
2013 Lew Hofmann
What AON Nodes look l ike.
The earliest you can completean activity--determined byadding the activity time(duration) to the early start time.
This is the latest you can finishan activity without delayingproject completion. It is thesame as the Late Start time of
the next activity. If there are twoor more subsequent activities,this time is the same as the
earliest of those Late Starttimes.
The is the earliest you can start anactivity. It is determined by the earlyfinish time of the precedent activity. Ifthere are two or more precedentactivities, this time is the same asprecedent activity with the latestEarly Finish time.
This is the Late-Finish time minusthe activity duration.
Slack
Slack (S) is the difference, if any,
between the early start (ES) and latestart times (LS) or the early finish(EF) and late finish (EF) times.
S = LS - ES or S = LF - EF
2013 Lew Hofmann
EarlyStart
EarlyFinish
Late
Finish
Late
Start
Activity
Name
ActivityDuration
8/13/2019 4 Project Mgt
13/69
2013 Lew Hofmann
Example: This homework Ass ignment
EarlyStart
EarlyFinish
Late
Finish
Late
Start
Home-
work #2
1 hour
Slack
If it takes one hour, theearliest you can complete thisassignment is one hour afterclass ends.
One hour after your late starttime.
The earliest you can start thisassignment it is immediately afterthis class ends.
You can wait untilone hour before theclass in which it isdue to start it; inthis case one weekfrom now.
The slack in this case would be one
week, expressed in hours, since thatis the unit of time used for theactivities. It would be how long youcould delay doing the assignment.
2013 Lew Hofmann
8/13/2019 4 Project Mgt
14/69
2013 Lew Hofmann
Precedent
Relat ionshipsPrecedent relationshipsdetermine the sequencefor accomplishing activities. They specify that anygiven activity cannot start until its preceding activityor activities have been completed.
In our AON approach, thenodes (circles) representactivities, and the arcs
(arrows) represent thesequential relationshipsbetween them.
AON
S T U
Activity On Node approach
S precedes T which
precedes U
Nodes are simplified in the following examples.
8/13/2019 4 Project Mgt
15/69
8/13/2019 4 Project Mgt
16/69
2013 Lew Hofmann
Act iv i ty Relat ionsh ips
S
T
U
V
U& Vcant begin until S& T
have been completed.
S
T
U
V
Ucannot begin until S& Thave
been completed. Vcannot begin
until Thas been completed.
8/13/2019 4 Project Mgt
17/69
2013 Lew Hofmann
Act iv i ty Relat ionsh ips
S T V
U
T& Ucannot begin until Shas been
completed; Vcannot begin until both T&Uhave been completed.
8/13/2019 4 Project Mgt
18/69
2013 Lew Hofmann
Logic Errors
C H
G
This is a logic error. C cannot be an
immediate predecessor of both G &H if
G is also an immediate predecessorofH.
Logic errors are hard to identify except on the
network diagrams. If you see a tr iangle, then it is a
logic error. Eliminate the short cut.
8/13/2019 4 Project Mgt
19/69
2013 Lew Hofmann
St. Adolfs Hospital(A sample project)
Immediate
Activity Description Predecessor(s) Responsibility
A Select administrative and medical staff.
B Select site and do site survey.C Select equipment.
D Prepare final construction plans and layout.
E Bring utilities to the site.
F Interview applicants and fill positions in
nursing, support staff, maintenance,
and security.
G Purchase and take delivery of equipment.H Construct the hospital.
I Develop an information system.
J Install the equipment.
K Train nurses and support staff.
8/13/2019 4 Project Mgt
20/69
2013 Lew Hofmann
A Select administrative and medical staff. 12
B Select site and do site survey. 9C Select equipment. A 10
D Prepare final construction plans & layout. B 10
E Bring utilities to the site. B 24
F Interview applicants and fill positions in A 10
nursing, support staff, maintenance,
and security.
G Purchase and take delivery of equipment. C 35H Construct the hospital. D 40
I Develop an information system. A 15
J Install the equipment. E,G,H 4
K Train nurses and support staff. F,I,J 6
St. Adolfs Hospital(A sample pro ject)
Immediate
Activity Description Predecessor(s) Activity Times
*We wont assigning Responsibility data, but it is important in project management.
8/13/2019 4 Project Mgt
21/69
2013 Lew Hofmann
St. Adolfs HospitalDiagramm ing the Network
FinishStart
A
B
C
D
E
F
G
H
I
J
K
Immediate
Predecessors
A 12
B 9
C A 10
D B 10
E B 24
F A 10
G C 35
H D 40
I A 15
J E,G,H 4
K F,I,J 6
Act iv i ty
Times (wks)
8/13/2019 4 Project Mgt
22/69
2013 Lew Hofmann
St. Adolfs Hospi ta lAct iv i ty Paths
FinishStart
A
B
C
D
E
F
G
H
I
J
K
Path Time (wks)
A-I-K 33
A-F-K 28A-C-G-J-K 67
B-D-H-J-K 69
B-E-J-K 43
Paths are sequences ofactivities between a
projects start and finish.
8/13/2019 4 Project Mgt
23/69
2013 Lew Hofmann
St. Adolfs Crit ical Path
FinishStart
A
B
C
D
E
F
G
H
I
J
KPath Time (wks)
A-I-K 33
A-F-K 28
A-C-G-J-K 67
B-D-H-J-K 69
B-E-J-K 43
Project Expected
Time is 69 wks.
The longest path is the
critical path!
8/13/2019 4 Project Mgt
24/69
8/13/2019 4 Project Mgt
25/69
2013 Lew Hofmann
PERTs
Three time-es t imates
OPTIMISTIC TIME: Best time if everything goes
perfectly when doing the activity.
REALISTIC TIME: Most likely time for the activity
PESSIMISTIC TIME:A worst-case situation
B + 4M + PExpected Time = -------------------
6In this example, the most likely time is given a weight of four, and the
other two times (pessimistic and optimistic) are each given weights of one.
Risky act iv i ty t imes make the pro ject length r isky, so there is a need
for r isk assessment based on the prob abi l ity distr ibu t ion of t imes.
(Standard deviation and variance are computed by the software.)
8/13/2019 4 Project Mgt
26/69
2013 Lew Hofmann
Activity slackis the maximum length of time that anactivity can be delayed without delaying the entireproject.
It is the difference between the earliest time wecan start an activity and the latest time we can
start the activity without delaying the project.
The critical path activities have zero slack.
For the St. Adolfs Hospital project, 69 weeks is theproject length because 69 weeks is the longest path.
Project delays beyond the projected completion date
often involve penalties.
Act iv i ty Slack
8/13/2019 4 Project Mgt
27/69
2013 Lew Hofmann
Earliest Start Time(ES) for an activity is the earliest finishtime of the immediately preceding activity.
Earliest Finish Time(EF) for an activity is its earliest starttime plus how long it takes to do it (activity time).
Latest Start Time(LS) is the latest you can finish the activityminus the activitys estimated duration.
Latest Finish Time(LF) is the latest start time plus the activitytime.
The latest finish time is the same as the latest start time of the activity activity
which follows it. (Latest start and finish times for each activity are computed
starting at the projects last activity completion time and working forward.)
Slackis the difference between the Earliest Start and Latest start
times for an activity (or earliest finish and latest finish times.)
Act iv i ty Start and Finish Times
8/13/2019 4 Project Mgt
28/69
2013 Lew Hofmann
Earl iest Start and Earl iest Finish Times
K
6
C
10
G
35
J
4
H
40
B
9
D
10
E
24
I
15
FinishStart
A
12
F
10
0
Earliest start time
12
Earliest finish time
0 9
9 33
9 19 19 59
22 5712 22
59 63
12 27
12 22 63 69
2013 Lew Hofmann
E li t St t d E l i t Fi i h Ti
8/13/2019 4 Project Mgt
29/69
2013 Lew Hofmann
Earl iest Start and Earl iest Finish Times
Crit ical Path
The Crit ical Path
takes 69 weeks
K
6
C
10
G
35
J
4
H
40
B
9
D
10
E
24
I
15
FinishStart
A
12
F
10
0 9
9 33
9 19 19 59
22 5712 22
59 63
12 27
12 22 63 690 12
Path Time (wks)
A-I-K 33
A-F-K 28
A-C-G-J-K 67
B-D-H-J-K 69
B-E-J-K 43
2013 Lew Hofmann
Latest Start and Latest Finish Times
8/13/2019 4 Project Mgt
30/69
2013 Lew Hofmann
K
6
C
10
G
35
J
4
H
40
B
9
D
10
E
24
I
15
FinishStart
A
12
F
10
0 9
9 33
9 19 19 59
22 5712 22
59 63
12 27
12 22 63 690 12
LatestStart and LatestFinish Times(You s tar t with the last act iv i ty and w ork toward th e f i rs t act iv i ty)
48 63
53 63
59 63
24 59
19 59
35 59
14 24
9 19
2 14
0 9
Latest
finish
time
63 69
Latest
start
time
2013 Lew Hofmann
Node Duration ES LS Slack
8/13/2019 4 Project Mgt
31/69
2013 Lew Hofmann
Act iv i ty Slack
Analys is
K
6
C
10
G
35
J
4
H
40
B
9
D
10
E
24
I
15
FinishStart
A
12
F
10
0 9
9 33
9 19 19 59
22 5712 22
59 63
12 27
12 22 63 690 12
48 63
53 63
59 63
24 59
19 59
35 59
14 24
9 19
2 14
0 9
63 69
Slack is the difference betweenLS and ES or EF and LFA 12 0 2 2
B 9 0 0 0
C 10 12 14 2
D 10 9 9 0
E 24 9 35 26
F 10 12 53 41
G 35 22 24 2
H 40 19 19 0
I 15 12 48 36
J 4 59 59 0
K 6 63 63 0
2013 Lew Hofmann
8/13/2019 4 Project Mgt
32/69
2013 Lew Hofmann
Analyz ing
Cost-Time Trade-Offs .
There are always cost-time trade-offs in projectmanagement.
You can completing a project early by hiring more
workers or running extra shifts.There are often penalties if projects extends beyond
some specific date, and a bonus may be provided forearly completion.
Crashinga project means finishing the projectearly by expediting one or more activities.
Not all activities can be shortened.
8/13/2019 4 Project Mgt
33/69
2013 Lew Hofmann
Pro ject Cos ts
Total Project Costs=
direct costs + indirect costs + penalty costs
Direct costsinclude labor, materials, and any other
costs directly related to project activities.
Indirect costsinclude administration, depreciation,financial, and other variable overhead costs.
These can be reduced by reducing total project time.
The shorter the duration of the project, the lower the indirectcosts will be.
Penalty costs are essentially late fees incurred forgoing over the projected due date.
8/13/2019 4 Project Mgt
34/69
2013 Lew Hofmann
We do cost analysis to determine the projectschedule that minimizes total project costs.
When crashing an activity or project, extra money is
spent on direct costs, but money is saved on indirectcosts and possible penalties.
A minimum-cost scheduleis determined by startingwith the normal project time schedule and shorteningactivities along th e cr i t ical pathuntil the costs ofcrashing (direct costs) start to exceed the savings inindirect costs and penalty costs. New critical paths usually appears while doing this.
Minim izing Costs
8/13/2019 4 Project Mgt
35/69
2013 Lew Hofmann
a. Determine the projects critical path(s).
b. Find the activity or activities on the critical path(s)with the lowest cost of crashing (shortening) per week.
c. Reduce the time for this activity until
a. it cannot be further reduced,
b. or another path becomes critical,
c. or the increase in direct costs exceed the savings that result
from lower indirect costs.
d. Repeat this process until the total project costs are nolonger decreasing.
Sophisticated project management software will do this.
St. Adolfs Hospital
Min imum Cost Schedu le
Of the five critical-path activities, the
8/13/2019 4 Project Mgt
36/69
2013 Lew Hofmann
K
6
C
10
G
35
J
4
H
40
B
9
D
10
E
24
I
15
FinishStart
A
12
F
10
0 9
9 33
9 19 19 59
22 5712 22
59 63
12 27
12 22 63 690 12
48 63
53 63
59 63
24 59
19 59
35 59
14 24
9 19
2 14
0 9
63 69
p ,contractor says Dand Hcannot beshortened. Jis the least costly toshortenat $1000 a week. Contractorsays it can be shortened to 1 week.
2012 Lew Hofmann
The project manager must nowcompare the cost of shortening J by 3weeks ($3,000 in additional directcosts) with savings in indirect costs,to see if the total cost is lower.
Shorten from 4
weeks to 1 week
8/13/2019 4 Project Mgt
37/69
2013 Lew Hofmann
Assess ing Risks
Riskis a measure of the probability (andconsequences) of not completing a projecton time.
A major responsibility of the project managerat the start of a project is to develop a risk-management plan.
A Risk-Management Planidentifies the keyrisks to a projects success and prescribesways to circumvent them.
8/13/2019 4 Project Mgt
38/69
2013 Lew Hofmann
Causes o f Pro ject Risk
1. Service/Product Risks: If the project involves a
new service or product, several risks can arise.
Market riskcomes from competition.
Technological riskcan arise from technology advancesmade once the project has started, rendering obsolete the
technology chosen for service or product.
Legal riskfrom liability suits or other legal action.
2. Project Team Problems: Poor member selections
and inexperience, lack of cooperation, etc.
3. Operations Risk: Information inaccuracy, miss-
communications, bad project timing, weather
8/13/2019 4 Project Mgt
39/69
2013 Lew Hofmann
ANALYZING PROBABIL ITIES
What is the probability that our sample project
will finish in 69 weeks as scheduled?
100% (Why?)
Because we used CPM!
(This means we were certainof all of our activity times.)
If we werent certain, we should have used PERT
You only do risk analysis if you use PERT
8/13/2019 4 Project Mgt
40/69
2013 Lew Hofmann
PERT and PROBABIL ITIES
With PERTs three time-estimates, we get a mean
(average) time and a var ianceforeach activityand
each path.
We also get a projectmean time and variance.
In order to compute probabilities (assuming a
normal distribution) we need the activity means andvariances.
Most computer packages calculate this for you.
8/13/2019 4 Project Mgt
41/69
2013 Lew Hofmann
Probabi l i ty
of Project Complet ion
The probability of a project being completed by a givendate is a function of the mean activity times andvariances along the critical path(s).
The probability of a specific act iv i ty being completed bya given date is a function of the mean activity times andvariances along the longest path leading up to thatactivity.
If you have more than one critical path, focus on the pathwith the greatest variance.
A near-critical path may also be a problem,
depending on the mean and variance of its activities.
8/13/2019 4 Project Mgt
42/69
2013 Lew Hofmann
Dist r ibut ions & Probabi l ity
A Beta distribution is often used for the three
estimates of each act iv i ty
This allows skewed distributions.
Optimistic------Most likely-----------------------Pessimistic
(3------------- 5---------------------------------- 11)
Normal distributions are needed for probabilities.
A distribution of act iv i ty-meansis a normal
distribution, even though each activity time may be
a beta distribution.
8/13/2019 4 Project Mgt
43/69
2013 Lew Hofmann
Beta Distr ibut ion
Mean
ma b Time
Probabilit
y
PessimisticOptimistic
Each activity may have its three time
estimates skewed (Beta Distribution), but the
path along which this activities lie has a
normal distribution and thus a mean and
variance.
8/13/2019 4 Project Mgt
44/69
2013 Lew Hofmann
Figu r ing Probab i li t ies
Assume a PERT project critical path takes 40 days, and that the
variance of the critical path is 2.147
You wish to know the probability of the project going over 42 days.
Compute the standard deviation of the critical path. The square root of the variance of 2.147 = Std. Dev. = 1.465
POM/QM software gives you the variance of the critical path.
Compute the Z value: Z = (absolute time difference) / Std. Dev.
In this example, Z= (42 days - 40 days) / 1.465= 1.365
Look up the Zvalue of 1.365in a Normal Distribution table to get
the probability of the project taking 42 days.
Subtract it from 100% to get the probability of going over 42.
8/13/2019 4 Project Mgt
45/69
2013 Lew Hofmann
Look up the Z value (1.365)in the table of normal distribution.
(In this case you need to interpolate between the Z values of .9313 and .9147)
.9139 or 91.39%is the probability of the project taking 42 days.
Thus the probability of going over 42 days is 100 - 91.39 = 8.61%
.9139
8/13/2019 4 Project Mgt
46/69
St Ad lf H it l
8/13/2019 4 Project Mgt
47/69
2013 Lew Hofmann
2= (variances of activities along critical path) z=TC
2
2= 1.78 + 1.78 + 2.78 + 5.44 + 0.11 = 11.89
z= 726911.89
What is the Probability of it taking 72 weeks?
Critical Path = B - D - H - JK = 69 weeks
T=72 weeks C= 69weeks
St. Adolfs HospitalA 69-week Project
Look up Z value in normal distribution tableZ = 0.870
CriticalPathVariance
z=3
3.44818
8/13/2019 4 Project Mgt
48/69
2013 Lew Hofmann
Look up the Z value (0.870) in the table of normal distribution.
.8078 or 80.78%is the probability of the project taking 72 wks.Going over 72 weeks would be 10080.78 = 19.22%
8/13/2019 4 Project Mgt
49/69
2013 Lew Hofmann
Project duration (weeks)
69 72
Probability of
taking 72 weeks
is 0.8078 or
80.78%
Length of
critical path is
69 weeks
Normal distribution:
Mean = 69 weeks;
= 3.45 weeks
Probability of
exceeding 72
weeks is 0.1922
or 19.22%
St. Adolfs HospitalProbability of Completing Project On Time
8/13/2019 4 Project Mgt
50/69
8/13/2019 4 Project Mgt
51/69
2013 Lew Hofmann
Path Mergersoccur when two or more activitypaths combine at a particular node. Both paths mustbe completed up to this point, which will eliminate any
built-up slack. Multitaskingis the performance of multiple project
activities at the same time. Work on some activities isoften delayed for other work.
Loss of Focusby a manager can happen if thecritical path changes frequently.
Failure to have all the needed resources on time.
Resource-Related Prob lems
8/13/2019 4 Project Mgt
52/69
2013 Lew Hofmann
PERT / CPM
ADVANTAGES
Enables Resource Management & Allocation
You can move slack resources to critical points
Focuses on your critical activities
Visualize relationships (The big picture)
Enables Cost analysis
8/13/2019 4 Project Mgt
53/69
2013 Lew Hofmann
PERT / CPM PITFALLS
Can be complex to setup relationships in
large project
Time estimatesare often biased.
Near critical paths are easily overlooked.
8/13/2019 4 Project Mgt
54/69
2013 Lew Hofmann
GERT(Graphical Evaluation and Review Technique)
Gives more flexibilityto project planning than PERT/CPM
Allows any individual activity to either be
completed or not completed (Succeed or fail)
PERT & CPM both require all activities be successfully
completed. GERT does not require this.
GERT Allows looping back (redoing an activity) orskipping an activity entirely.
There are computerized GERT packages.
8/13/2019 4 Project Mgt
55/69
2013 Lew Hofmann
Solved Problem
What is the probabi l i ty of
complet ing the pro ject in
23 weeks?
2013 Lew Hofmann
S l d P bl
8/13/2019 4 Project Mgt
56/69
2013 Lew Hofmann
Solved Problem
2013 Lew Hofmann
8/13/2019 4 Project Mgt
57/69
2013 Lew Hofmann
Solved Problem
Finish
Start
A
4.0
0.0
4.0
4.0
8.0
D
12.0
4.0
8.0
16.0
20.0
E
6.5
9.0
9.0
15.5
15.5
G
4.5
15.5
15.5
20.0
20.0
C
3.5
5.5
5.5
9.0
9.0
F
9.0
5.5
6.5
14.5
15.5
B
5.5
0.0
0.0
5.5
5.5
2013 Lew Hofmann
8/13/2019 4 Project Mgt
58/69
Homework #2
8/13/2019 4 Project Mgt
59/69
2013 Lew Hofmann
Homework #2
Due next week
Problem 1 is on the next slide. Draw thenetwork and solve it manuallyusing the
AON method. No credit if you use thecomputer.
Problems 2and 3are on the following
slides. Use the POM/QM software for these last two
problems.
Problem 1
8/13/2019 4 Project Mgt
60/69
2013 Lew Hofmann
Problem 1Do manually (no computer)
A project has the following precedence relationships and activitytimes. Draw the netwo rk diagram and calculate the total slackfor each act iv i ty . Which act iv i t ies are on the cr i t ical path?
Activity Activity Time (wks)
Immediate
Predecessor(s)
A 4
B 9
C 5 A
D 15 B,CE 12 B
F 4 D
G 8 E
H 7 F,G
PROBLEM 2 (Use POM/QM)1 There are logic errors in the data You will have to run the program in order
8/13/2019 4 Project Mgt
61/69
2013 Lew Hofmann
Activities for Problem #2 Time Precedents
A Demolition of present structures 3 None
B Excavation and filling of site 2 A
C Forming & pouring of concrete 2 BD Construction of steel skeleton 3 C
E Construction of concrete structure 2 C
F Construction of exterior skin 1 D,E
G Installation of plumbing 3 E
H Installation of electrical 3 D,E
I Installation of heating & cooling 3 D,E,F
J Construction of interior flooring 3 I
K Lighting fixtures and finish work 2 J
1. There are logic errorsin the data. You will have to run the program in orderto find them. Then make the appropriate corrections and re-run the problemto get the correct solution. Identify the critical path and its length.
2. Include 4 printouts:Input screen, PERT/CPM results table, Precedencegraph and the Gantt chart of early & late times.
2013 Lew Hofmann
8/13/2019 4 Project Mgt
62/69
Problem #3
8/13/2019 4 Project Mgt
63/69
2013 Lew Hofmann
Activity Precedent Optimistic Most Likely Pessimistic
A - 6 7 8
B A 4 4 4
C A 5 6 8
D B 8 10 10
E B 7 10 15F C 9 9 13
G C 7 7 7
H D 4 6 8I E, F 6 9 11
J G 8 9 10
K H, I, J 3 5 6
Problem #3
2013 Lew Hofmann
8/13/2019 4 Project Mgt
64/69
2013 Lew Hofmann
Sample POM/QM
8/13/2019 4 Project Mgt
65/69
2013 Lew Hofmann
Sample POM/QM
Input Tab le Prin tou t
Note that this is CPM since there is only one time estimate foreach activity. You will need to change the method for PERT.
S l POM/QM
8/13/2019 4 Project Mgt
66/69
2013 Lew Hofmann
Sample POM/QM
Solut ion Tab le pr intou t
8/13/2019 4 Project Mgt
67/69
8/13/2019 4 Project Mgt
68/69
8/13/2019 4 Project Mgt
69/69
POM/QM Print ing Hin t
Avoid using the print screen button on the bottom left
of the screen or in the file menu.
Screen prints are small and very hard to read.
Select the File pull-down menu and use the Printoption.
You can then indicate which items you wish to print
and get a much better output.
OPTION: Download the free program Jing. It is
available for Mac and PC, and what I use for the
printouts on my PPT slides.
htt // t h ith /ji ht l
http://www.techsmith.com/jing.htmlhttp://www.techsmith.com/jing.html
top related