LA Metro – Success

of A Program

Management

Information

System

By: Julie Owen

LA Metro Background

2

3rd largest public transportation system in US

Most populous county in US

88 incorporated cities

Service area covers 1,433 mi²

Transportation planner, designer

builder, operator

Worst traffic delay in the US annual delay

per traveler

What is Measure R?

3

Sales tax measure approved in 2008

$40B in transportation upgrades

30 year program, 550,000 new jobs

Rail network expansion with airport connections

Add carpool lanes, build freeway connectors

Construct sound walls along freeways

Local street improvements

Expectations

4

Measure R Largest Transportation Program

Increased oversight and accountability

Potential aggressive / accelerated schedule

Maxes out Metro resources

Increased expectations for project delivery

Delivery strategy 4-5 project at a time

Current structure 1-2 projects at a time

Paradigm shift required

Challenges

5

Outdated technologies

Manual data manipulation

Departmental Silo’s

Differing information

Challenging audit trails

Redundant data and disconnected

Computerized summary reports not available

Cost reporting in spreadsheets.

Untimely reporting of information

PMIS Solution

6

Project Cost Management Project Schedule Management

•Industry Leader

•Advancing Technologies

•Integrates to Other Oracle

Products

•Deep project controls capabilities

•Integration expertise

•Excel-like, ease-of-use

•Built-in reporting

•Customizable

PMIS Requirements

7

Centralized repository

Improved data accuracy

Automated financial data

Proactive / Timely project status

Enhance communication by removing silos

Provide project and program performance, current status, and forecast trends

Data available via web for stakeholders

BETTER QUALITY, MORE TIMELY!

8

PMIS Solution Overview

System Hosting

9

Projects Organization in P6

10

Level 1 Master

Schedules for

Executive Level

reporting of Project

Status and Progress

Detailed Control

Level Schedules to

track contractor level

progress schedules

Schedule Management

11

Summary

and

control

schedules

linked in

database

EcoSys to P6 Schedule Integration

12

Project Status Reports

13

Live

Link to

status

report

Portfolio Level Dashboard

14

Role Based Dashboard

15

Contract Reporting

16

EcoSys Solution Overview

17

Controls Manager Dashboard

Cost Engineer Dashboard

19

20

CM13 Data Spreadsheet

Actual vs. Budget FTE

21

Realized Benefits

22

Data Integration

“Single version of the truth”

Data Quality & security

Elimination of duplicate data entry and manual compilation

Business rule enforcement with version control & audit trail

Reporting Efficiencies

Automated project status reports at the click of a button

Staff efficiencies from reduced manual logging and

redundant data entry

Document, Change Control, Cost Control

More time for proactive analysis; corrective action

Process Standardization

Management visibility into project /program status

Lessons Learned

23

Define requirements, evaluate work processes

Need management sponsor, system facilitator, early adopter champions

Establish goals and communicate progress

Implement focus groups where needed

Process User groups schedule, document, change and cost control

Institutional data standards to facilitate summary and portfolio-level reporting

No institutional WBS and work around required

Coming Soon – Public Facing Website

Interactive view of key project details. Data automated from EcoSys and P6 data sources. Includes approval controls for

publication. Data refreshed monthly.

24

Coming Soon - Risk Tracking

Risk Tracking performed in P6 R8

25

26

Analysis & Management Reports

Earned Value Analysis & Management Reports

Questions