KONGSBERG PROPRIETARY: This document contains KONGSBERG information which is proprietary and confidential. Any disclosure, copying, distribution or use is prohibited if not otherwise explicitly agreed with KONGSBERG in writing. Any authorised reproduction in whole or in part, must include this legend. © 2013 KONGSBERG – All rights reserved.
Men fossefallsmetoden var ikke død En sørgelig historie med stadig flere akter
Agenda
• Introduksjon • Hvordan det gikk til slutt – tid, kostnad og omfang • Hva skjedde med fossefallet? • Løsningen og prosjektorganisasjonen • Tiltak underveis • Langsiktige tiltak
22.10.2013 WORLD CLASS - through people, technology and dedication Page 2
Introduksjon
• Frode Nordheim – Prosjektleder i Kongsberg Maritimes IT-avdeling siden november
2011 – Leder komplekse interne forbedringsprosjekter for forretnings-
støttesystemer – Prosjektlederutdanning fra Metier Academy – Mastergrad i Informatikk fra Universitetet i Oslo
• Prosjektet – Visjon: Global ressursstyring – Mål: Mer presise prosjektleveranser
22.10.2013 WORLD CLASS - through people, technology and dedication Page 3
22/10/2013 WORLD CLASS - through people, technology and dedication. Page 4
Omfang
Kostnad Tid
Den kjente trekanten
22/10/2013 WORLD CLASS - through people, technology and dedication. Page 5
Kostnad: x 21 Tid: x 4
Hvordan det gikk…
Omfang
22.10.2013 WORLD CLASS - through people, technology and dedication Page 6
18. oktober 2010 8. april 2013 …2011
Og vi går live…
…2012
22/10/2013 WORLD CLASS - through people, technology and dedication. Page 7
Krav
Funksjonell løsning
Teknisk løsning
Implementering
Test
Installasjon
Fossefallet – slik det burde være
22/10/2013 WORLD CLASS - through people, technology and dedication. Page 8
Krav
Funksjonell løsning
Teknisk løsning
Implementering
Test
Installasjon
Høst 2009 April 2013 Vår 2010 November 2011
Fossefallet – slik det så ut til å være seint 2011
22/10/2013 WORLD CLASS - through people, technology and dedication. Page 9
Krav
Funksjonell løsning
Teknisk løsning
Implementering
Test
Installasjon
Høst 2009 April 2013 Vår 2010 November 2011
Fossefallet – slik det viste seg å være
22/10/2013 WORLD CLASS - through people, technology and dedication. Page 10
Krav
Funksjonell løsning
Høst 2009 April 2013
Januar 2012
Vår 2010 November 2011
Fossefallet – slik vi endte opp
Teknisk løsning
Implementering
Test
Installasjon
Funksjonell løsning
22.10.2013 WORLD CLASS - through people, technology and dedication Page 11
Steve McConnell (Software Estimation – Demystifying the Black Art, Microsoft Press, 2006)
Estimation error creeps into estimates from four generic sources: • Inaccurate information about the project being estimated • Inaccurate information about the capabilities of the organization that will
perform the project • Too much chaos in the project to support accurate estimation (that is,
trying to estimate a moving target) • Inaccuracies arising from the estimation process itself
The Cone of Uncertainty
22.10.2013 WORLD CLASS - through people, technology and dedication Page 12
The Cone of uncertainty does not narrow itself
22.10.2013 WORLD CLASS - through people, technology and dedication Page 13
The Cloud of Uncertainty
22/10/2013 Page 14 WORLD CLASS - through people
22.10.2013 WORLD CLASS - through people, technology and dedication Page 15
ERP
HR
Hours Accounting BizTalk
Master Data Cache
MS Project Server
Active Directory
Teknisk kompleksitet
MS Project
DATAKVALITET
22.10.2013 WORLD CLASS - through people, technology and dedication Page 16
Organisatorisk kompleksitet
22.10.2013 WORLD CLASS - through people, technology and dedication Page 17
22.10.2013 WORLD CLASS - through people, technology and dedication Page 19
22.10.2013 WORLD CLASS - through people, technology and dedication Page 20
Fra oppgavestyring per epost til Team Foundation Server
22.10.2013 WORLD CLASS - through people, technology and dedication Page 21
Tettere kommunikasjon Asynkron Synkron Ingen jakt på syndebukker
Prosjektkvalifisering og portefølgestyring
/ 22 / 22-Oct-13
22.10.2013 WORLD CLASS - through people, technology and dedication Page 23
Requirement Specification
High level solution design Implementation System test Deployment
22.10.2013 WORLD CLASS - through people, technology and dedication Page 24
Requirements Detailed
requirements
Functional specification
Technical design
Implementation
Test
Deployment
Læring
• Metodikk og metodekompetanse – Krav- og løsningsspesifisering – Estimering – Test
• Kommunikasjon – Hyppig – Direkte
• Fossefallsmetoden – Kan brukes når usikkerhet og kompleksitet er lav – For øvrig: Bruk smidige og/eller inkrementelle prosesser
22.10.2013 WORLD CLASS - through people, technology and dedication Page 25