2 GUIDE_Earned Value Presentation Slides.ppt
Post on 14-Apr-2018
224 Views
Preview:
Transcript
7/29/2019 2 GUIDE_Earned Value Presentation Slides.ppt
1/33
1 /33
Earned Value Management
7/29/2019 2 GUIDE_Earned Value Presentation Slides.ppt
2/33
2 /33
Agenda
Comparison with other Methods
EV Management in Practise Earned Value Planned Value
Actual Costs
Schedule Performance Index
Cost Performance Index
General Introduction to EV Reporting
Introduction
7/29/2019 2 GUIDE_Earned Value Presentation Slides.ppt
3/33
3 /33
Example, PV
PV: Value of work scheduledto have been completedat a certain moment in time.
PV = planned % complete * baseline cost
Introduction
7/29/2019 2 GUIDE_Earned Value Presentation Slides.ppt
4/33
4 /33
EV = actual % complete * baseline cost
EV: Value of work actually accomplishedat a certain
moment in time.
Example, EV
Introduction
7/29/2019 2 GUIDE_Earned Value Presentation Slides.ppt
5/33
5 /33
AC: Value that gives insight in how much is paid forthe work actually accomplished.
Actual Costs
Introduction
7/29/2019 2 GUIDE_Earned Value Presentation Slides.ppt
6/33
6 /33
How much Value was originally Planned to have been
Delivered (as of today)?
Planned Value (PV)
How Much Value was Actually Delivered (as of today)?
Earned Value (EV)
How Much has the Project Cost (as of today)?
Actual Cost (AC)
Earned Value explained
Introduction
7/29/2019 2 GUIDE_Earned Value Presentation Slides.ppt
7/337 /33
EV and PV Curve
Introduction
7/29/2019 2 GUIDE_Earned Value Presentation Slides.ppt
8/338 /33
%Complete = Earned Value / Budget at Completion * 100 %Spent = Actual Costs / Budget at Completion * 100 % Over/Under Spent = [(Actual Cost / Earned Value) - 1] * 100
EV Calculations
Introduction
7/29/2019 2 GUIDE_Earned Value Presentation Slides.ppt
9/33
9 /33
Cost Variance (CV) =Earned Value (EV)
Actual Costs (AC)
Schedule Variance (SV) =Earned Value (EV) Planned Value (PV)
Variance Analysis
Introduction
7/29/2019 2 GUIDE_Earned Value Presentation Slides.ppt
10/33
10 /33
Scheduled Performance IndexPerformance Indicators: SPI
PV
EVSPI
1SPI Ahead of schedule1SPI
1SPI
Behind schedule
Exactly on track
Example: 83.0480
400SPI
Introduction
7/29/2019 2 GUIDE_Earned Value Presentation Slides.ppt
11/33
11 /33
Cost Performance IndexPerformance Indicators: CPI
AC
EVCPI
Better than budget
Worse than budget
On Budget
1CPI
1CPI
1CPI
Example: 11.1360
400CPI
Introduction
7/29/2019 2 GUIDE_Earned Value Presentation Slides.ppt
12/33
12 /33
Combining SPI and CPI
Introduction
7/29/2019 2 GUIDE_Earned Value Presentation Slides.ppt
13/33
13 /33
Critical Ratio (CR) = CPI * SPI
Critical ratio
Over all Project performance is excellent1CR
1CR
1CR
Over all Project performance is poor
Project Performance on target
Introduction
7/29/2019 2 GUIDE_Earned Value Presentation Slides.ppt
14/33
14 /33
Ability to influence SPI and SPIAbility to Influence SPI and CPI
AbilitytoInflu
enceSPIandCPI
High ability
to change
Moderate
ability to
change
Low ability to
change
0% 50% 100%75%25%
% Project Complete
As we proceed further through the project,
our ability to change the SPI and CPI values
decreases exponentially. Very early in the project,
the SPI and CPI values are elastic. However,
starting very early in the project, the SPI and CPIvalues will increasingly reflect the final project
condition
Ability to Influence SPI and CPI
AbilitytoInflu
enceSPIandCPI
High ability
to change
Moderate
ability to
change
Low ability to
change
0% 50% 100%75%25%
% Project Complete
As we proceed further through the project,
our ability to change the SPI and CPI values
decreases exponentially. Very early in the project,
the SPI and CPI values are elastic. However,
starting very early in the project, the SPI and CPIvalues will increasingly reflect the final project
condition
Introduction
7/29/2019 2 GUIDE_Earned Value Presentation Slides.ppt
15/33
15 /33
Forecast the future project status Estimate at Completion
= Actual Costs to + [(Budget at Completion Earned Value) / CPI]
= Actual Costs to date date + (Budget at Completion
Earned Value)= Actual Costs to date + a new estimate for all remaining work
Schedule delay or acceleration=(SPI-1)Approved Baseline duration)
Estimated duration at completion= Approved Baseline Duration + Current Schedule Delay or Acceleration= Actual Time Used + (1/SPI) * Remaining Baseline Duration
Forecasting
7/29/2019 2 GUIDE_Earned Value Presentation Slides.ppt
16/33
16 /33
Advantages of EV Reporting Early warnings Costs Forecasting Communication (External) Control
Comparison with other methods
7/29/2019 2 GUIDE_Earned Value Presentation Slides.ppt
17/33
17 /33
Project to date cost versus budgetEV compared to other methods
Advantages Simple
Little effort required
DisadvantagesNo insight in actual finished work
Questionable monetary relativity
Comparison with other methods
7/29/2019 2 GUIDE_Earned Value Presentation Slides.ppt
18/33
18 /33
Project to date versus planned budget at moment in timeEV compared to other methods(2)
Advantages More insight in monetary relativity
DisadvantagesNo insight in which work has beenaccomplished
No insight in value of finished work
Comparison with other methods
7/29/2019 2 GUIDE_Earned Value Presentation Slides.ppt
19/33
19 /33
Milestone trackingEV compared to other methods(3)
AdvantagesInsight in accomplished work
DisadvantagesNo insight in monetary status
No insight in value of accomplished
work
Comparison with other methods
7/29/2019 2 GUIDE_Earned Value Presentation Slides.ppt
20/33
20 /33
Combination of milestone tracking and project to date versus plannedbudget at moment in timeEV compared to other methods(4)
Advantages Insight in accomplished work
More insight in monetary
relativity
DisadvantagesNo insight in value of accomplished
work
Comparison with other methods
7/29/2019 2 GUIDE_Earned Value Presentation Slides.ppt
21/33
21 /33
Standard EV ManagementEV compared to other methods(5)
AdvantagesForecasting ability
Insight in value of
accomplished work in the
current and future situation
External control
Disadvantages Requires realistic planning
More time consuming to administer
Comparison with other methods
7/29/2019 2 GUIDE_Earned Value Presentation Slides.ppt
22/33
22 /33
EV SimplificationEV compared to other methods(6)
AdvantagesSimple, using informationreadily available to most
projects
Common indicators for
comparison with other projects
Disadvantages Relies on realistic estimate of %Complete, (or EV) which may by
nature be more subjective than
tracking the accumulated completion
values of many measurable smaller
units.Assumes that progress and spend
forecasts are linear, which is
normally not the true case.
Comparison with other methods
7/29/2019 2 GUIDE_Earned Value Presentation Slides.ppt
23/33
23 /33
Method of EV Calculation;
Tracking and Reporting Frequency
Threshold Establishment What Cost Elements comprise Planned Value
Whether to track resource actual hours including
Overtime or a standard 8 hour day.
Which resource labour costs should be included? Level of detail of EV management
Baseline Timing
EV Management in Practise
Key Decisions
7/29/2019 2 GUIDE_Earned Value Presentation Slides.ppt
24/33
24 /33
EV management Methods Percentage complete
Physical percentage complete
Fixed percentage from start
EV Management in Practise
7/29/2019 2 GUIDE_Earned Value Presentation Slides.ppt
25/33
25 /33
Level of detail
Examples of levels
The project lifecycle stage
The workstream (activity grouping)
EV Management in Practise
7/29/2019 2 GUIDE_Earned Value Presentation Slides.ppt
26/33
26 /33
Baseline timing
EV Management in Practise
7/29/2019 2 GUIDE_Earned Value Presentation Slides.ppt
27/33
27 /33
Baseline timing
EV Management in Practise
7/29/2019 2 GUIDE_Earned Value Presentation Slides.ppt
28/33
28 /33
Rebaseline and reprofile (2)
EV Management in Practise
7/29/2019 2 GUIDE_Earned Value Presentation Slides.ppt
29/33
29 /33
Example EV Report
7/29/2019 2 GUIDE_Earned Value Presentation Slides.ppt
30/33
30 /33
Example EV Report (2)
7/29/2019 2 GUIDE_Earned Value Presentation Slides.ppt
31/33
31 /33
Example EV Report (3)
7/29/2019 2 GUIDE_Earned Value Presentation Slides.ppt
32/33
32 /33
Example EV Report
7/29/2019 2 GUIDE_Earned Value Presentation Slides.ppt
33/33
33 /33
top related