Lesson 10A - The Drilling Riser
Riser ComponentsRiser TensioningFatigueKill/Choke LinesInspection & MaintenanceReentry
3
Riser system for a floating drilling rig
BOP
RISER JOINTSKILL AND CHOICE LINES
SLIP JOINT OUTER BARRELUPPER BALL JOINT
SLIP JOINT INNER BARREL
RISER TENSION
LOWER BALL JOINT
Mudline
Marine riser = drilling riser, get returns to surface, well control, communications link
4
Integral Marine Riser Joints
Choke and kill lines are integral with the marine riser , flanged connections; clamp, etc
5
Integral Marine Riser Connector
Flanged connection - 6 bolts
NOTE: Choke and Kill Lines
O-ring type seals- inspect when running
6
Integral Marine Riser Connector
7
Marine Riser
Flexible Joint
Flexible joint, binding from high tensile forces, inject lubricant, up to 1,500,000 lbf!
8Upper Section Marine Riser System.
MARINE RISER DIVERTER ASSEMBLY
RISER TENSIONING
LINESTELESCOPIC JOINT
KILL AND CHOKE LINES
FLEXIBLE JOINT
9
Control valve
Vent line
Mud returns
L.P. Annular
A diverter system.Re-directs flow from rig floor to blooey line (10”+), downwind, do not shut in, erosion -10E8
10
Figure 6-6. Vertical steel loops used for kill / choke line transition around the ball joint.
11
The Drilling Riser
Schematic diagram of riser with imposed forces
MEAN WATER LEVEL
RISER ELEMENT
Optimum riser tension to minimize damage to riser and wear-and-tear on tensioners, sag
12
Str
ess
in r
iser
, ki
ps
Applied tension in riser, kips
Maximum stress
Minimum stress
Tension in riser must be not too low and not too high. Set at 118 kips - will fluctuate 100-136 kips ~ 15%
Mean tension
13
Riser Considerations:
Riser Metallurgy is very important. Correct heat treatment is
essential. 80,000 psi min. yield strength and
good toughness is preferred. Preheating, welding & normalizing
after welding is critical for riser integrity & long life.
14
Riser Considerations:
No Field Welding on Riser!
Fatigue of riser cannot be measured prior to some indication of failure.
Routine inspection required.
15
Riser Considerations:
Fatigue is an embrittlement of the metal. It often starts in the vicinity of welds or other places of high stress concentration.
Fatigue is caused by cyclic loading.
16
Riser Inspection:
Visual Inspection of the riser should occur every time the riser is run.
Check all the seals Check all the sealing areas
17
Riser Inspection:
A complete inspection should be made annually.
Dyes: Will detect cracks. To use dyes, paint must be removed.Magnetic Particle Inspection: Sand blast areas around welds prior to magnetic particle inspection.
18
Riser Inspection:
Ultra-Sonic Inspection: May detect cracks below the surface. This test is run inside pipe. Paint removal is not necessary.
X-Ray Inspection: Is for cracks inside the metal. It may miss surface cracks.
*No one technique will find all the cracks.
19
Riser Instrumentation:
Heavy Gauge: Pointer attached to guide line moving in front of graduated board.
Riser Angle Indicator (at ball joint):
2/1y
2x
21
2/12y
2x
tantantan
20
Riser Instrumentation:
Accurate Positioning System: For detecting and monitoring vessel
position.
21
Ball Joint:
A Ball Joint Angle > 4 degrees is an indication that something is wrong!
Vessel is offset Riser tension is inadequate
22
Ball Joint:
Must decrease ball joint angle before operations are resumed.
Remedial Action:
Decrease Offset
Increase Riser Tension
23
Vessel to Seafloor Guidance System
Guidelines are used for guiding equipment from the vessel to the seafloor.
Selection and care of guidelines is critical.
24
Vessel to Seafloor Guidance System
Guidelines should not be tensioned beyond 1/3 of breaking capacity
But…inadequate tension is the most common cause of failure in guidelines
25
Vessel to Seafloor Guidance System
Tension should be maximum when landing the BOP stack, or when landing the riser onto the stack.
When the guidelines are not being used to run equipment, tension may be slacked off to ~ twice the weight of the line in seawater.
26
Table 6-1. Recommendations for
Conventionally Used Guidelines
As water depth increases, larger diameter guidelines must be used.
Higher tensioning is required.
Don’t forget to limit tension to < 1/3 of breaking strength.