Stormwater Planning Policy Changes

Breakfast Seminar

Background to reforms

Chris ChesterfieldCRC for Water Sensitive Cities

History of WSUD

1997

CSIRO Study

1999

BPEM Guidelines

2000

VSAPSMPs

2002

Clearwater

2006

Living Rivers amp Lower

Yarra Capacity Building

Programs

Clause 56

Strong WSUD growth

2010

Municipal IWCM

Targets

2011

SE IWCM Strategy

Victorian Stormwater Committee

2012

Living Victoria Policy

Water for Victoria

2016

History of WSUD

1997

CSIRO Study

1999

BPEM Guidelines

2000

VSAPSMPs

2002

Clearwater

2006

Living Rivers amp Lower

Yarra Capacity Building

Programs

Clause 56

Strong WSUD growth

2010

Municipal IWCM

Targets

2011

SE IWCM Strategy

Victorian Stormwater Committee

2012

Living Victoria Policy

Water for Victoria

2016

Transformational change in urban water

Public Health

1890s

Growth

Post WWII

Efficiency

1990s

TODAY

Liveability Sustainability Resilience

Separate water sewerage drainage systems

Integrated planning and management

6

Inconsistencies and inequities in our approach to stormwater management

Source Property Inc Magazine

Residential dev must meet BPEM under VPP

Most residential dev not required to meet BPEM (other than apartments)

under VPP

Industrial commercial dev must meet BPEM

through DSSsInd com not required to meet BPEM under

VPP

Industrial com dev not required to meet BPEM

under VPP

No PSP guideline IWM plan (equivalents)

IWM in PSP guidelines + PSP IWM plans

Other councils havenrsquot

Some councils have expanded BPEM coverage

Renorsquos and rebuilds not required to meet

BPEM

Residential subdivisions must

meet BPEM

Offsets available

No offsets

No clear mechanism for recovering $$

DSSs for recovering $$ Public roads and

land not required to meet BPEM

Private land must meet

BPEM

VPP = Victoria Planning Provisions

BPEM = the stormwater management standards

DSS = Development Services Schemes

PSP = Precinct Structure Plans

IWM = Integrated Water Management

8

Government commits to improve stormwater management through planning system reforms

9

Terms of Reference

Part A (core)Specific advice on which types of

development of those currently not subject to the Statersquos urban runoff management

objectives should be required to manage their stormwater and the associated reforms

Part B (future directions) Future policy directions for improving

stormwater management and strengthening the links between urban water management and the planning and development system

more broadly

10

Improving Stormwater Management Advisory Committee

Dr Jeremy Cheesman Julie Katz Chris Chesterfield (chair) Sue Porter

11

Wide consultation

6 committee meetings

6 stakeholder workshops

46 submissions7 one on ones

12

Stakeholder feedback

bull Consultation indicated widespread support for application of stormwater standards across all development types

bull Raised a number of implementation issues

bull Planning system only part of the response

13

Stakeholder feedback

Other feedback

bull Offsets are useful if they can be designed to provide net benefits and protect sensitive areas

bull Councils struggle with funding stormwater infrastructure costs

bull Rolesaccountabilities not well definedbull Skills tools and guidance need investmentbull Community awareness lowbull Support for linking IWM plans to planning system

14

Committee submitted its report in September 2018

15

The Committees 18 recommendations include

bull Planning reforms (3) ndash immediate reforms satisfying Part A of the Terms of Reference (ToR)

bull Future policy directions (7) ndash longer term policy directions satisfying Part B of the ToR

bull Supporting actions (8) ndash actions to ensure successful implementation of the (Part A) planning reforms satisfying Part B of the ToR

Committee Recomendations

16

Planning reforms

Rec 1 ndash Expand the stormwater planning provisions (phase 1) That the Victorian Government amend the VPPs to expand the current stormwater management requirements to

bull commercial subdivisions and developmentsbull industrial subdivisions and developmentsbull public-use developmentsbull multi-dwelling residential subdivisions and developments

Rec 2 ndash Expand the stormwater planning provisions (phase 2) That subject to further consultation the development of deemed-to-satisfy solutions (rec 12) adequate guidance and tools (recs 13 14 and 15) and offset processes (rec 5) the Victorian Government amend the VPPs to expand the current stormwater management requirements to

bull single-dwelling developmentsbull extensions over 50 m2

Rec 3 ndash Insert an IWM clause into the Planning Policy Framework (PPF) That the Victorian Government amend the PPF to embed the concepts of IWM objectives and strategies

17

Future policy directions

Rec 4 ndash Amend the building and plumbing controls

Rec 5 ndash Establish effective offsetting arrangements

Rec 6 ndash Clarify local governmentsrsquo roles and responsibilities

Rec 7 ndash Strengthen compliance requirements

Rec 8 ndash Determine funding sources for public stormwater infrastructure

Rec 9 ndash Link water management with urban planning

Rec 10 ndash Set stronger place-based BPEM stormwater performance objectives

18

Rec 11 ndash Strengthen enforcement of stormwater construction requirements

Rec 12 ndash Prepare deemed-to-satisfy solutions

Rec 13 ndash Review the STORM and MUSIC tools

Rec 14 ndash Build technical expertise

Rec 15 ndash Improve guidance

Rec 16 ndash Improve awareness of the VPP changes

Rec 17 ndash Investigate options for rainwater tank maintenance and operation

Rec 18 ndash Broaden rating systems to include IWM

Supporting actions

The new stormwater provisions

Emma Stewart DELWP

20

Government response (to date)

21

Government is currently considering the committeersquos longer-term recommendations and is working with key stakeholders to determine the most effective response and pathways for implementation

Longer term recommendations

22

State-based planning requirements (lsquobeforersquo)

Sourced ELM 2018

23

State-based planning requirements (lsquoafterrsquo)

24

Development types (volume)

Future development estimated impervious area 2020-2050

25

The nitty grittyhellip

26

Amendment VC154

Victoria Planning Provision changesbull New clause (5318) and changes to an existing clause

(5503) to expand the stormwater requirements to more development types

bull New objectives to manage toxicants and encourage broader benefits of stormwater management

27

Whatrsquos in

Applies to an application tobull subdivide land bull construct a building bull construct or carry out works

In both hellip

Clause 5318bull commercial zonesbull industrial zonesbull public-use zones

Clause 5518 bull Construct townhouses

Whatrsquos out of clause 5318

bull Developments and subdivisions approved or lodged prior to the amendment

bull Developments which do not require planning permission

bull Vicsmart applications

bull Applications for land within development or incorporated plans approved before the amendment

bull Extensions and works lt 50m2

bull Applications after the amendment to amend existing planning permits

If in doubt ask a planner

29

Key elements of clauses

Industrial commercial applications (Clause 5318)tobull subdivide land bull construct a building bull construct or carry out works

Stormwater management objectives + standard (W1)

Stormwater management objectives + standard (W2)+ Site management objectives + standard (W3)

Decision guidelines

Same for Clause 5503 (townhouses)

30

Clause 5318 ndash subdivision

Stormwater management standard W1 The stormwater management system should be bull Designed and managed in accordance with the requirements and

to the satisfaction of the relevant drainage authoritybull Designed and managed in accordance with the requirements and

to the satisfaction of the water authority where reuse of stormwater is proposed

bull Designed to meet the current best practice performance objectives for stormwater quality as contained in the BPEM

bull Designed to ensure that flows downstream of the subdivision site are restricted to pre-development levels unless increased flows are approved by the relevant drainage authority and there are no detrimental downstream impacts

bull Designed to contribute to cooling improving local habitat and providing attractive and enjoyable spaces

31

Clause 5318 ndash Buildings and works

Standard W2The stormwater management system should be designed to

bull Meet the current best practice performance objectives for stormwater quality as contained in the BPEM

bull Contribute to cooling improving local habitat and providing attractive and enjoyable spaces

bull Minimise the impact of chemical pollutants and other toxicants including by but not limited to bunding and covering of roofing of storage loading and work areas

32

Townhouses - Standard B9

Clause 5503 ndash Permeability and stormwater management objectives and standard B9

Objectivesbull Similar to 5318 (including the cooling liveability

objective)bull gt20 perviousness objective (unchanged)

Standardbull NEW - cooling liveability objectivebull NEW ndash requirement to meet BPEM

What does this all mean

34

Clause 5318 - Whatrsquos in

35

Urban cooling Reduce heat radiation from buildings and hard surfaces throughbull Shade trees in car parks or over driveways bull More open space and treesbull Green roofsbull Green walls

36

Optionsbull Passive irrigationbull Integrate assets into

communal open spacebull Tree pits and permeable

paving (driveways and carpark)

bull Stormwater harvesting (major developments only)

Infiltration habitat amenity

37

Control harmful chemicals

Optionsbull Careful layoutbull Consider alternative less harmful substancesbull Roofed designated storage areabull Internal drainage design to sewer or a treatment devicebull Bunding

38

Standard W3Standard W3 requires that application describe how the site will be managed prior to and during the construction period The application should set out requirements for managingbull Erosion and sedimentbull Stormwaterbull Litter concrete and other construction wastesbull Chemical contamination

Buildings and works - Site management standard

39

Site management

40

Planning Advisory Note No 75

Implications for industry

Kate MatthewsStormwater Victoria

1 Development proponents- Developers- Consultants (engineers stormwater specialists and planners)- Council (when developing public land lt$1 million)

2 Development assessors- Council statutory planners- Council internal referrals (engineering assets ESD stormwater officers)

3 Strategy- Council strategic planners

4 Melbourne Water

Whorsquos affected

43

What are the implications

bull BPEM - Itrsquos not just subdivisions any more

bull Cost ndash offset or assetbull Early planning and integration ndash more

work up frontbull Not just engineeringbull Varying Council skills and experience

Development Proponents

44

If already have a local policy for WSUDESD no real change

If notbull Workload and resourcingbull Increased detail and technical

contentbull Administrative arrangements ndash

referrals permit conditions ndashmake sure you make 60 stat days

bull Applicant pressure ndash what do you want

bull Assets

Development Assessors

45

bull Structure plans and rezoning ndashopportunities for localregional approach

bull IWM and Stormwater Management Plans ndash opportunities for these to be implemented through the controls spatial opportunities

bull Opportunities for development of Council offset strategies

Strategy

Offsets

bull Developer enters into an agreement with relevant drainage authority to financially contribute to off-site stormwatermanagement in lieu of providing on-site treatment

bull Already available for residential subdivisions in Melbourne (Clause 56) through MWCs Stormwater Quality Offset scheme

What are stormwater quality offsets

X Not drainage contributions (MWC drainage scheme)

X Not development contributions (DCPICP)

47

When to use

bull Not in MW DSS or growth area where therersquos an existing framework for funding SW treatment

bull Onsite treatment not practical or desirable

bull To fund planned localregional stormwater treatment works in that catchment via an existing offset scheme

bull Council and developer both agree to it

48

OffsetsExample ndash Kingston Offset Scheme

Asset ownership and maintenance

bull Whorsquos going to own itbull Whorsquos going to maintain itbull How do you maintain itbull How much will it cost

bull Where is itbull Is maintenance burden

practical for likely future owners

bull Whorsquos going to monitor compliance and how

The detail is in the permit conditions

Application requirements

ldquoAn application must be accompanied by details of the proposed stormwater management system including drainage works and retention detention and discharges of stormwater to the drainage systemrdquo ndash Clause 5318

What does the planning scheme require

But alsohellipNeed to provide sufficient information to Council which demonstrates that you comply and how you comply with all the other standards ndash eg urban coolinghabitatetc BPEM site management pollutant control infiltration (as relevant to development type

51

1 PlansWhat are you doing where is it going and does it fit

2 ModellingDo you (or can you) meet BPEM requirements

3 Written response to standardsHow does your proposal comply with the requirements

52

Application

bull Site plan ndash show all assetsWSUD treatments and any IWM features on the site layout plan with everything else

bull Landscape plan ndash if planting design passive irrigation etc forms part of response to requirements show

bull Site management plan (depending on Council)

bull Separate WSUDIWM plan showing all features on a stripped back background

bull Concept WSUD asset design ndash larger assets only (wetlands bioretention basins sed basin etc) ndash sufficient design detail to confirm spatial requirements

PlansPermit conditions

bull Detailed engineering design bull Site Management Plan (final)bull Asset maintenance plan (final)bull Handover arrangements (if public)

54

STORM ndash Online toolbull Print out of STORM reportbull Make sure meets 100 or

morebull Make sure report inputs and

results match plan

Modelling - SWQ

MUSIC ndash Proprietary softwarebull Provide a copy of the model filebull Print out the modelling resultsbull Provide summary of your model

inputs for each treatment train (iecatchment size impervious treatment area etc)

bull Provide a print out of the model schematic

Bonus points bull Provide details of model

parametersbull Provide results of MUSIC auditor

run (if using Melbourne Water MUSIC Guidelines)

56

Assessment against standards

bull Say what you have done (or will do) to meet each standardbull Donrsquot forget (if WSUD) details of maintenance and asset

ownershipbull Where applicable be explicit why yoursquove chosen (or not chosen) to

respond the way you have Egbull Opportunitiesbull Site constraintsbull Practicaloperational issues bull Brief dot point summary of options analysis if complex

bull Make sure if it doesnrsquot meet the standard it meets the objectivebull Make sure shown on plan and consistent with modelling and rest of

documentation

57

Resources

Local stormwaterWSUD policiesBaysideKingstonCaseyMonashMelbourneYarraMoonee ValleyPort PhilipStonningtonHumeCampaspeBass Coast

Local ESD (including IWM) policies Greater BendigoGreater DandenongHobsons BayWhittleseaWyndhamWhitehorseManninghamMorelandDarebinBanyuleKnoxBrimbank

Council planning resources

Application resources ndashexamplesDELWP Practice Note ndashformal guide to the new controlsMoreland ndash application checklists and example plans for a variety of residential developmentsPort Philip ndash compliance guidelines checklist and examplesMoonee Valley ndash checklists and example plans including site management plans Greater Bendigo ndash WSUD kitBayside ndash application guidelines and example plans

59

Technical guidelines (modelling design construction)

Melbourne Water

STORM calculatorMUSIC auditor - lsquohow torsquo video here

Melbourne Water technical guidelines page- WSUD asset life cycle costings and model maintenance guidelines- MUSIC guidelines- Stormwater harvesting guidelines- WSUD life cycle costings and

maintenance guidelines- Design and construction guidelines

for variety of assetshttpswwwmelbournewatercomauplanning-and-buildingdeveloper-guides-and-resourcesguidelines-drawings-and-checklistsguidelines

Council

South-Eastern Growth Council WSUD guidelines ndash note that some individual Councils have their own addendumsMelbournePort PhilipNorth-West Growth Council WSUD guidelines - note that some individual Councils have their own addendumsGreater BendigoMilduraBallaratBaw BawWyndhamMoreland ndash tree pits and raingardens

60

IWM

Example Council IWM strategiesMelbourneCaseyMonashKingston

Resilient Melbourne ndash IWM information lsquohubrsquoClearwater ndash capacity building and case studiesMelbourne Water ndash funding opportunities for IWM projects

Stormwater offset schemes

KingstonGreater GeelongMelbourne Water ndash non scheme contributions

Site management

EPA guidelines- management of erosion and sediment

Next steps and other stormwater initiatives

Emma Stewart DELWP

62

Next steps

bull Trainingbull The EPArsquos BPEM Reviewbull Offsets policybull Review of STORM bull Building controls

63

State Stormwater policies

64

Thank you

  • Slide Number 1
  • Slide Number 2
  • History of WSUD
  • History of WSUD
  • Transformational change in urban water
  • Inconsistencies and inequities in our approach to stormwater management
  • Slide Number 8
  • Terms of Reference
  • Improving Stormwater Management Advisory Committee
  • Wide consultation
  • Stakeholder feedback
  • Stakeholder feedback
  • Committee submitted its report in September 2018
  • Committee Recomendations
  • Planning reforms
  • Future policy directions
  • Supporting actions
  • Slide Number 19
  • Government response (to date)
  • Longer term recommendations
  • State-based planning requirements (lsquobeforersquo)
  • State-based planning requirements (lsquoafterrsquo)
  • Development types (volume)
  • Slide Number 25
  • Amendment VC154
  • Whatrsquos in
  • Slide Number 28
  • Key elements of clauses
  • Clause 5318 ndash subdivision
  • Clause 5318 ndash Buildings and works
  • Townhouses - Standard B9
  • Slide Number 33
  • Slide Number 34
  • Slide Number 35
  • Slide Number 36
  • Slide Number 37
  • Buildings and works - Site management standard
  • Site management
  • Planning Advisory Note No 75
  • Slide Number 41
  • Slide Number 42
  • Slide Number 43
  • Slide Number 44
  • Slide Number 45
  • Slide Number 46
  • Slide Number 47
  • Slide Number 48
  • Slide Number 49
  • Slide Number 50
  • Slide Number 51
  • Slide Number 52
  • Slide Number 53
  • Slide Number 54
  • Slide Number 55
  • Slide Number 56
  • Slide Number 57
  • Slide Number 58
  • Slide Number 59
  • Slide Number 60
  • Slide Number 61
  • Next steps
  • State Stormwater policies
  • Slide Number 64

    Background to reforms

    Chris ChesterfieldCRC for Water Sensitive Cities

    History of WSUD

    1997

    CSIRO Study

    1999

    BPEM Guidelines

    2000

    VSAPSMPs

    2002

    Clearwater

    2006

    Living Rivers amp Lower

    Yarra Capacity Building

    Programs

    Clause 56

    Strong WSUD growth

    2010

    Municipal IWCM

    Targets

    2011

    SE IWCM Strategy

    Victorian Stormwater Committee

    2012

    Living Victoria Policy

    Water for Victoria

    2016

    History of WSUD

    1997

    CSIRO Study

    1999

    BPEM Guidelines

    2000

    VSAPSMPs

    2002

    Clearwater

    2006

    Living Rivers amp Lower

    Yarra Capacity Building

    Programs

    Clause 56

    Strong WSUD growth

    2010

    Municipal IWCM

    Targets

    2011

    SE IWCM Strategy

    Victorian Stormwater Committee

    2012

    Living Victoria Policy

    Water for Victoria

    2016

    Transformational change in urban water

    Public Health

    1890s

    Growth

    Post WWII

    Efficiency

    1990s

    TODAY

    Liveability Sustainability Resilience

    Separate water sewerage drainage systems

    Integrated planning and management

    6

    Inconsistencies and inequities in our approach to stormwater management

    Source Property Inc Magazine

    Residential dev must meet BPEM under VPP

    Most residential dev not required to meet BPEM (other than apartments)

    under VPP

    Industrial commercial dev must meet BPEM

    through DSSsInd com not required to meet BPEM under

    VPP

    Industrial com dev not required to meet BPEM

    under VPP

    No PSP guideline IWM plan (equivalents)

    IWM in PSP guidelines + PSP IWM plans

    Other councils havenrsquot

    Some councils have expanded BPEM coverage

    Renorsquos and rebuilds not required to meet

    BPEM

    Residential subdivisions must

    meet BPEM

    Offsets available

    No offsets

    No clear mechanism for recovering $$

    DSSs for recovering $$ Public roads and

    land not required to meet BPEM

    Private land must meet

    BPEM

    VPP = Victoria Planning Provisions

    BPEM = the stormwater management standards

    DSS = Development Services Schemes

    PSP = Precinct Structure Plans

    IWM = Integrated Water Management

    8

    Government commits to improve stormwater management through planning system reforms

    9

    Terms of Reference

    Part A (core)Specific advice on which types of

    development of those currently not subject to the Statersquos urban runoff management

    objectives should be required to manage their stormwater and the associated reforms

    Part B (future directions) Future policy directions for improving

    stormwater management and strengthening the links between urban water management and the planning and development system

    more broadly

    10

    Improving Stormwater Management Advisory Committee

    Dr Jeremy Cheesman Julie Katz Chris Chesterfield (chair) Sue Porter

    11

    Wide consultation

    6 committee meetings

    6 stakeholder workshops

    46 submissions7 one on ones

    12

    Stakeholder feedback

    bull Consultation indicated widespread support for application of stormwater standards across all development types

    bull Raised a number of implementation issues

    bull Planning system only part of the response

    13

    Stakeholder feedback

    Other feedback

    bull Offsets are useful if they can be designed to provide net benefits and protect sensitive areas

    bull Councils struggle with funding stormwater infrastructure costs

    bull Rolesaccountabilities not well definedbull Skills tools and guidance need investmentbull Community awareness lowbull Support for linking IWM plans to planning system

    14

    Committee submitted its report in September 2018

    15

    The Committees 18 recommendations include

    bull Planning reforms (3) ndash immediate reforms satisfying Part A of the Terms of Reference (ToR)

    bull Future policy directions (7) ndash longer term policy directions satisfying Part B of the ToR

    bull Supporting actions (8) ndash actions to ensure successful implementation of the (Part A) planning reforms satisfying Part B of the ToR

    Committee Recomendations

    16

    Planning reforms

    Rec 1 ndash Expand the stormwater planning provisions (phase 1) That the Victorian Government amend the VPPs to expand the current stormwater management requirements to

    bull commercial subdivisions and developmentsbull industrial subdivisions and developmentsbull public-use developmentsbull multi-dwelling residential subdivisions and developments

    Rec 2 ndash Expand the stormwater planning provisions (phase 2) That subject to further consultation the development of deemed-to-satisfy solutions (rec 12) adequate guidance and tools (recs 13 14 and 15) and offset processes (rec 5) the Victorian Government amend the VPPs to expand the current stormwater management requirements to

    bull single-dwelling developmentsbull extensions over 50 m2

    Rec 3 ndash Insert an IWM clause into the Planning Policy Framework (PPF) That the Victorian Government amend the PPF to embed the concepts of IWM objectives and strategies

    17

    Future policy directions

    Rec 4 ndash Amend the building and plumbing controls

    Rec 5 ndash Establish effective offsetting arrangements

    Rec 6 ndash Clarify local governmentsrsquo roles and responsibilities

    Rec 7 ndash Strengthen compliance requirements

    Rec 8 ndash Determine funding sources for public stormwater infrastructure

    Rec 9 ndash Link water management with urban planning

    Rec 10 ndash Set stronger place-based BPEM stormwater performance objectives

    18

    Rec 11 ndash Strengthen enforcement of stormwater construction requirements

    Rec 12 ndash Prepare deemed-to-satisfy solutions

    Rec 13 ndash Review the STORM and MUSIC tools

    Rec 14 ndash Build technical expertise

    Rec 15 ndash Improve guidance

    Rec 16 ndash Improve awareness of the VPP changes

    Rec 17 ndash Investigate options for rainwater tank maintenance and operation

    Rec 18 ndash Broaden rating systems to include IWM

    Supporting actions

    The new stormwater provisions

    Emma Stewart DELWP

    20

    Government response (to date)

    21

    Government is currently considering the committeersquos longer-term recommendations and is working with key stakeholders to determine the most effective response and pathways for implementation

    Longer term recommendations

    22

    State-based planning requirements (lsquobeforersquo)

    Sourced ELM 2018

    23

    State-based planning requirements (lsquoafterrsquo)

    24

    Development types (volume)

    Future development estimated impervious area 2020-2050

    25

    The nitty grittyhellip

    26

    Amendment VC154

    Victoria Planning Provision changesbull New clause (5318) and changes to an existing clause

    (5503) to expand the stormwater requirements to more development types

    bull New objectives to manage toxicants and encourage broader benefits of stormwater management

    27

    Whatrsquos in

    Applies to an application tobull subdivide land bull construct a building bull construct or carry out works

    In both hellip

    Clause 5318bull commercial zonesbull industrial zonesbull public-use zones

    Clause 5518 bull Construct townhouses

    Whatrsquos out of clause 5318

    bull Developments and subdivisions approved or lodged prior to the amendment

    bull Developments which do not require planning permission

    bull Vicsmart applications

    bull Applications for land within development or incorporated plans approved before the amendment

    bull Extensions and works lt 50m2

    bull Applications after the amendment to amend existing planning permits

    If in doubt ask a planner

    29

    Key elements of clauses

    Industrial commercial applications (Clause 5318)tobull subdivide land bull construct a building bull construct or carry out works

    Stormwater management objectives + standard (W1)

    Stormwater management objectives + standard (W2)+ Site management objectives + standard (W3)

    Decision guidelines

    Same for Clause 5503 (townhouses)

    30

    Clause 5318 ndash subdivision

    Stormwater management standard W1 The stormwater management system should be bull Designed and managed in accordance with the requirements and

    to the satisfaction of the relevant drainage authoritybull Designed and managed in accordance with the requirements and

    to the satisfaction of the water authority where reuse of stormwater is proposed

    bull Designed to meet the current best practice performance objectives for stormwater quality as contained in the BPEM

    bull Designed to ensure that flows downstream of the subdivision site are restricted to pre-development levels unless increased flows are approved by the relevant drainage authority and there are no detrimental downstream impacts

    bull Designed to contribute to cooling improving local habitat and providing attractive and enjoyable spaces

    31

    Clause 5318 ndash Buildings and works

    Standard W2The stormwater management system should be designed to

    bull Meet the current best practice performance objectives for stormwater quality as contained in the BPEM

    bull Contribute to cooling improving local habitat and providing attractive and enjoyable spaces

    bull Minimise the impact of chemical pollutants and other toxicants including by but not limited to bunding and covering of roofing of storage loading and work areas

    32

    Townhouses - Standard B9

    Clause 5503 ndash Permeability and stormwater management objectives and standard B9

    Objectivesbull Similar to 5318 (including the cooling liveability

    objective)bull gt20 perviousness objective (unchanged)

    Standardbull NEW - cooling liveability objectivebull NEW ndash requirement to meet BPEM

    What does this all mean

    34

    Clause 5318 - Whatrsquos in

    35

    Urban cooling Reduce heat radiation from buildings and hard surfaces throughbull Shade trees in car parks or over driveways bull More open space and treesbull Green roofsbull Green walls

    36

    Optionsbull Passive irrigationbull Integrate assets into

    communal open spacebull Tree pits and permeable

    paving (driveways and carpark)

    bull Stormwater harvesting (major developments only)

    Infiltration habitat amenity

    37

    Control harmful chemicals

    Optionsbull Careful layoutbull Consider alternative less harmful substancesbull Roofed designated storage areabull Internal drainage design to sewer or a treatment devicebull Bunding

    38

    Standard W3Standard W3 requires that application describe how the site will be managed prior to and during the construction period The application should set out requirements for managingbull Erosion and sedimentbull Stormwaterbull Litter concrete and other construction wastesbull Chemical contamination

    Buildings and works - Site management standard

    39

    Site management

    40

    Planning Advisory Note No 75

    Implications for industry

    Kate MatthewsStormwater Victoria

    1 Development proponents- Developers- Consultants (engineers stormwater specialists and planners)- Council (when developing public land lt$1 million)

    2 Development assessors- Council statutory planners- Council internal referrals (engineering assets ESD stormwater officers)

    3 Strategy- Council strategic planners

    4 Melbourne Water

    Whorsquos affected

    43

    What are the implications

    bull BPEM - Itrsquos not just subdivisions any more

    bull Cost ndash offset or assetbull Early planning and integration ndash more

    work up frontbull Not just engineeringbull Varying Council skills and experience

    Development Proponents

    44

    If already have a local policy for WSUDESD no real change

    If notbull Workload and resourcingbull Increased detail and technical

    contentbull Administrative arrangements ndash

    referrals permit conditions ndashmake sure you make 60 stat days

    bull Applicant pressure ndash what do you want

    bull Assets

    Development Assessors

    45

    bull Structure plans and rezoning ndashopportunities for localregional approach

    bull IWM and Stormwater Management Plans ndash opportunities for these to be implemented through the controls spatial opportunities

    bull Opportunities for development of Council offset strategies

    Strategy

    Offsets

    bull Developer enters into an agreement with relevant drainage authority to financially contribute to off-site stormwatermanagement in lieu of providing on-site treatment

    bull Already available for residential subdivisions in Melbourne (Clause 56) through MWCs Stormwater Quality Offset scheme

    What are stormwater quality offsets

    X Not drainage contributions (MWC drainage scheme)

    X Not development contributions (DCPICP)

    47

    When to use

    bull Not in MW DSS or growth area where therersquos an existing framework for funding SW treatment

    bull Onsite treatment not practical or desirable

    bull To fund planned localregional stormwater treatment works in that catchment via an existing offset scheme

    bull Council and developer both agree to it

    48

    OffsetsExample ndash Kingston Offset Scheme

    Asset ownership and maintenance

    bull Whorsquos going to own itbull Whorsquos going to maintain itbull How do you maintain itbull How much will it cost

    bull Where is itbull Is maintenance burden

    practical for likely future owners

    bull Whorsquos going to monitor compliance and how

    The detail is in the permit conditions

    Application requirements

    ldquoAn application must be accompanied by details of the proposed stormwater management system including drainage works and retention detention and discharges of stormwater to the drainage systemrdquo ndash Clause 5318

    What does the planning scheme require

    But alsohellipNeed to provide sufficient information to Council which demonstrates that you comply and how you comply with all the other standards ndash eg urban coolinghabitatetc BPEM site management pollutant control infiltration (as relevant to development type

    51

    1 PlansWhat are you doing where is it going and does it fit

    2 ModellingDo you (or can you) meet BPEM requirements

    3 Written response to standardsHow does your proposal comply with the requirements

    52

    Application

    bull Site plan ndash show all assetsWSUD treatments and any IWM features on the site layout plan with everything else

    bull Landscape plan ndash if planting design passive irrigation etc forms part of response to requirements show

    bull Site management plan (depending on Council)

    bull Separate WSUDIWM plan showing all features on a stripped back background

    bull Concept WSUD asset design ndash larger assets only (wetlands bioretention basins sed basin etc) ndash sufficient design detail to confirm spatial requirements

    PlansPermit conditions

    bull Detailed engineering design bull Site Management Plan (final)bull Asset maintenance plan (final)bull Handover arrangements (if public)

    54

    STORM ndash Online toolbull Print out of STORM reportbull Make sure meets 100 or

    morebull Make sure report inputs and

    results match plan

    Modelling - SWQ

    MUSIC ndash Proprietary softwarebull Provide a copy of the model filebull Print out the modelling resultsbull Provide summary of your model

    inputs for each treatment train (iecatchment size impervious treatment area etc)

    bull Provide a print out of the model schematic

    Bonus points bull Provide details of model

    parametersbull Provide results of MUSIC auditor

    run (if using Melbourne Water MUSIC Guidelines)

    56

    Assessment against standards

    bull Say what you have done (or will do) to meet each standardbull Donrsquot forget (if WSUD) details of maintenance and asset

    ownershipbull Where applicable be explicit why yoursquove chosen (or not chosen) to

    respond the way you have Egbull Opportunitiesbull Site constraintsbull Practicaloperational issues bull Brief dot point summary of options analysis if complex

    bull Make sure if it doesnrsquot meet the standard it meets the objectivebull Make sure shown on plan and consistent with modelling and rest of

    documentation

    57

    Resources

    Local stormwaterWSUD policiesBaysideKingstonCaseyMonashMelbourneYarraMoonee ValleyPort PhilipStonningtonHumeCampaspeBass Coast

    Local ESD (including IWM) policies Greater BendigoGreater DandenongHobsons BayWhittleseaWyndhamWhitehorseManninghamMorelandDarebinBanyuleKnoxBrimbank

    Council planning resources

    Application resources ndashexamplesDELWP Practice Note ndashformal guide to the new controlsMoreland ndash application checklists and example plans for a variety of residential developmentsPort Philip ndash compliance guidelines checklist and examplesMoonee Valley ndash checklists and example plans including site management plans Greater Bendigo ndash WSUD kitBayside ndash application guidelines and example plans

    59

    Technical guidelines (modelling design construction)

    Melbourne Water

    STORM calculatorMUSIC auditor - lsquohow torsquo video here

    Melbourne Water technical guidelines page- WSUD asset life cycle costings and model maintenance guidelines- MUSIC guidelines- Stormwater harvesting guidelines- WSUD life cycle costings and

    maintenance guidelines- Design and construction guidelines

    for variety of assetshttpswwwmelbournewatercomauplanning-and-buildingdeveloper-guides-and-resourcesguidelines-drawings-and-checklistsguidelines

    Council

    South-Eastern Growth Council WSUD guidelines ndash note that some individual Councils have their own addendumsMelbournePort PhilipNorth-West Growth Council WSUD guidelines - note that some individual Councils have their own addendumsGreater BendigoMilduraBallaratBaw BawWyndhamMoreland ndash tree pits and raingardens

    60

    IWM

    Example Council IWM strategiesMelbourneCaseyMonashKingston

    Resilient Melbourne ndash IWM information lsquohubrsquoClearwater ndash capacity building and case studiesMelbourne Water ndash funding opportunities for IWM projects

    Stormwater offset schemes

    KingstonGreater GeelongMelbourne Water ndash non scheme contributions

    Site management

    EPA guidelines- management of erosion and sediment

    Next steps and other stormwater initiatives

    Emma Stewart DELWP

    62

    Next steps

    bull Trainingbull The EPArsquos BPEM Reviewbull Offsets policybull Review of STORM bull Building controls

    63

    State Stormwater policies

    64

    Thank you

    • Slide Number 1
    • Slide Number 2
    • History of WSUD
    • History of WSUD
    • Transformational change in urban water
    • Inconsistencies and inequities in our approach to stormwater management
    • Slide Number 8
    • Terms of Reference
    • Improving Stormwater Management Advisory Committee
    • Wide consultation
    • Stakeholder feedback
    • Stakeholder feedback
    • Committee submitted its report in September 2018
    • Committee Recomendations
    • Planning reforms
    • Future policy directions
    • Supporting actions
    • Slide Number 19
    • Government response (to date)
    • Longer term recommendations
    • State-based planning requirements (lsquobeforersquo)
    • State-based planning requirements (lsquoafterrsquo)
    • Development types (volume)
    • Slide Number 25
    • Amendment VC154
    • Whatrsquos in
    • Slide Number 28
    • Key elements of clauses
    • Clause 5318 ndash subdivision
    • Clause 5318 ndash Buildings and works
    • Townhouses - Standard B9
    • Slide Number 33
    • Slide Number 34
    • Slide Number 35
    • Slide Number 36
    • Slide Number 37
    • Buildings and works - Site management standard
    • Site management
    • Planning Advisory Note No 75
    • Slide Number 41
    • Slide Number 42
    • Slide Number 43
    • Slide Number 44
    • Slide Number 45
    • Slide Number 46
    • Slide Number 47
    • Slide Number 48
    • Slide Number 49
    • Slide Number 50
    • Slide Number 51
    • Slide Number 52
    • Slide Number 53
    • Slide Number 54
    • Slide Number 55
    • Slide Number 56
    • Slide Number 57
    • Slide Number 58
    • Slide Number 59
    • Slide Number 60
    • Slide Number 61
    • Next steps
    • State Stormwater policies
    • Slide Number 64

      History of WSUD

      1997

      CSIRO Study

      1999

      BPEM Guidelines

      2000

      VSAPSMPs

      2002

      Clearwater

      2006

      Living Rivers amp Lower

      Yarra Capacity Building

      Programs

      Clause 56

      Strong WSUD growth

      2010

      Municipal IWCM

      Targets

      2011

      SE IWCM Strategy

      Victorian Stormwater Committee

      2012

      Living Victoria Policy

      Water for Victoria

      2016

      History of WSUD

      1997

      CSIRO Study

      1999

      BPEM Guidelines

      2000

      VSAPSMPs

      2002

      Clearwater

      2006

      Living Rivers amp Lower

      Yarra Capacity Building

      Programs

      Clause 56

      Strong WSUD growth

      2010

      Municipal IWCM

      Targets

      2011

      SE IWCM Strategy

      Victorian Stormwater Committee

      2012

      Living Victoria Policy

      Water for Victoria

      2016

      Transformational change in urban water

      Public Health

      1890s

      Growth

      Post WWII

      Efficiency

      1990s

      TODAY

      Liveability Sustainability Resilience

      Separate water sewerage drainage systems

      Integrated planning and management

      6

      Inconsistencies and inequities in our approach to stormwater management

      Source Property Inc Magazine

      Residential dev must meet BPEM under VPP

      Most residential dev not required to meet BPEM (other than apartments)

      under VPP

      Industrial commercial dev must meet BPEM

      through DSSsInd com not required to meet BPEM under

      VPP

      Industrial com dev not required to meet BPEM

      under VPP

      No PSP guideline IWM plan (equivalents)

      IWM in PSP guidelines + PSP IWM plans

      Other councils havenrsquot

      Some councils have expanded BPEM coverage

      Renorsquos and rebuilds not required to meet

      BPEM

      Residential subdivisions must

      meet BPEM

      Offsets available

      No offsets

      No clear mechanism for recovering $$

      DSSs for recovering $$ Public roads and

      land not required to meet BPEM

      Private land must meet

      BPEM

      VPP = Victoria Planning Provisions

      BPEM = the stormwater management standards

      DSS = Development Services Schemes

      PSP = Precinct Structure Plans

      IWM = Integrated Water Management

      8

      Government commits to improve stormwater management through planning system reforms

      9

      Terms of Reference

      Part A (core)Specific advice on which types of

      development of those currently not subject to the Statersquos urban runoff management

      objectives should be required to manage their stormwater and the associated reforms

      Part B (future directions) Future policy directions for improving

      stormwater management and strengthening the links between urban water management and the planning and development system

      more broadly

      10

      Improving Stormwater Management Advisory Committee

      Dr Jeremy Cheesman Julie Katz Chris Chesterfield (chair) Sue Porter

      11

      Wide consultation

      6 committee meetings

      6 stakeholder workshops

      46 submissions7 one on ones

      12

      Stakeholder feedback

      bull Consultation indicated widespread support for application of stormwater standards across all development types

      bull Raised a number of implementation issues

      bull Planning system only part of the response

      13

      Stakeholder feedback

      Other feedback

      bull Offsets are useful if they can be designed to provide net benefits and protect sensitive areas

      bull Councils struggle with funding stormwater infrastructure costs

      bull Rolesaccountabilities not well definedbull Skills tools and guidance need investmentbull Community awareness lowbull Support for linking IWM plans to planning system

      14

      Committee submitted its report in September 2018

      15

      The Committees 18 recommendations include

      bull Planning reforms (3) ndash immediate reforms satisfying Part A of the Terms of Reference (ToR)

      bull Future policy directions (7) ndash longer term policy directions satisfying Part B of the ToR

      bull Supporting actions (8) ndash actions to ensure successful implementation of the (Part A) planning reforms satisfying Part B of the ToR

      Committee Recomendations

      16

      Planning reforms

      Rec 1 ndash Expand the stormwater planning provisions (phase 1) That the Victorian Government amend the VPPs to expand the current stormwater management requirements to

      bull commercial subdivisions and developmentsbull industrial subdivisions and developmentsbull public-use developmentsbull multi-dwelling residential subdivisions and developments

      Rec 2 ndash Expand the stormwater planning provisions (phase 2) That subject to further consultation the development of deemed-to-satisfy solutions (rec 12) adequate guidance and tools (recs 13 14 and 15) and offset processes (rec 5) the Victorian Government amend the VPPs to expand the current stormwater management requirements to

      bull single-dwelling developmentsbull extensions over 50 m2

      Rec 3 ndash Insert an IWM clause into the Planning Policy Framework (PPF) That the Victorian Government amend the PPF to embed the concepts of IWM objectives and strategies

      17

      Future policy directions

      Rec 4 ndash Amend the building and plumbing controls

      Rec 5 ndash Establish effective offsetting arrangements

      Rec 6 ndash Clarify local governmentsrsquo roles and responsibilities

      Rec 7 ndash Strengthen compliance requirements

      Rec 8 ndash Determine funding sources for public stormwater infrastructure

      Rec 9 ndash Link water management with urban planning

      Rec 10 ndash Set stronger place-based BPEM stormwater performance objectives

      18

      Rec 11 ndash Strengthen enforcement of stormwater construction requirements

      Rec 12 ndash Prepare deemed-to-satisfy solutions

      Rec 13 ndash Review the STORM and MUSIC tools

      Rec 14 ndash Build technical expertise

      Rec 15 ndash Improve guidance

      Rec 16 ndash Improve awareness of the VPP changes

      Rec 17 ndash Investigate options for rainwater tank maintenance and operation

      Rec 18 ndash Broaden rating systems to include IWM

      Supporting actions

      The new stormwater provisions

      Emma Stewart DELWP

      20

      Government response (to date)

      21

      Government is currently considering the committeersquos longer-term recommendations and is working with key stakeholders to determine the most effective response and pathways for implementation

      Longer term recommendations

      22

      State-based planning requirements (lsquobeforersquo)

      Sourced ELM 2018

      23

      State-based planning requirements (lsquoafterrsquo)

      24

      Development types (volume)

      Future development estimated impervious area 2020-2050

      25

      The nitty grittyhellip

      26

      Amendment VC154

      Victoria Planning Provision changesbull New clause (5318) and changes to an existing clause

      (5503) to expand the stormwater requirements to more development types

      bull New objectives to manage toxicants and encourage broader benefits of stormwater management

      27

      Whatrsquos in

      Applies to an application tobull subdivide land bull construct a building bull construct or carry out works

      In both hellip

      Clause 5318bull commercial zonesbull industrial zonesbull public-use zones

      Clause 5518 bull Construct townhouses

      Whatrsquos out of clause 5318

      bull Developments and subdivisions approved or lodged prior to the amendment

      bull Developments which do not require planning permission

      bull Vicsmart applications

      bull Applications for land within development or incorporated plans approved before the amendment

      bull Extensions and works lt 50m2

      bull Applications after the amendment to amend existing planning permits

      If in doubt ask a planner

      29

      Key elements of clauses

      Industrial commercial applications (Clause 5318)tobull subdivide land bull construct a building bull construct or carry out works

      Stormwater management objectives + standard (W1)

      Stormwater management objectives + standard (W2)+ Site management objectives + standard (W3)

      Decision guidelines

      Same for Clause 5503 (townhouses)

      30

      Clause 5318 ndash subdivision

      Stormwater management standard W1 The stormwater management system should be bull Designed and managed in accordance with the requirements and

      to the satisfaction of the relevant drainage authoritybull Designed and managed in accordance with the requirements and

      to the satisfaction of the water authority where reuse of stormwater is proposed

      bull Designed to meet the current best practice performance objectives for stormwater quality as contained in the BPEM

      bull Designed to ensure that flows downstream of the subdivision site are restricted to pre-development levels unless increased flows are approved by the relevant drainage authority and there are no detrimental downstream impacts

      bull Designed to contribute to cooling improving local habitat and providing attractive and enjoyable spaces

      31

      Clause 5318 ndash Buildings and works

      Standard W2The stormwater management system should be designed to

      bull Meet the current best practice performance objectives for stormwater quality as contained in the BPEM

      bull Contribute to cooling improving local habitat and providing attractive and enjoyable spaces

      bull Minimise the impact of chemical pollutants and other toxicants including by but not limited to bunding and covering of roofing of storage loading and work areas

      32

      Townhouses - Standard B9

      Clause 5503 ndash Permeability and stormwater management objectives and standard B9

      Objectivesbull Similar to 5318 (including the cooling liveability

      objective)bull gt20 perviousness objective (unchanged)

      Standardbull NEW - cooling liveability objectivebull NEW ndash requirement to meet BPEM

      What does this all mean

      34

      Clause 5318 - Whatrsquos in

      35

      Urban cooling Reduce heat radiation from buildings and hard surfaces throughbull Shade trees in car parks or over driveways bull More open space and treesbull Green roofsbull Green walls

      36

      Optionsbull Passive irrigationbull Integrate assets into

      communal open spacebull Tree pits and permeable

      paving (driveways and carpark)

      bull Stormwater harvesting (major developments only)

      Infiltration habitat amenity

      37

      Control harmful chemicals

      Optionsbull Careful layoutbull Consider alternative less harmful substancesbull Roofed designated storage areabull Internal drainage design to sewer or a treatment devicebull Bunding

      38

      Standard W3Standard W3 requires that application describe how the site will be managed prior to and during the construction period The application should set out requirements for managingbull Erosion and sedimentbull Stormwaterbull Litter concrete and other construction wastesbull Chemical contamination

      Buildings and works - Site management standard

      39

      Site management

      40

      Planning Advisory Note No 75

      Implications for industry

      Kate MatthewsStormwater Victoria

      1 Development proponents- Developers- Consultants (engineers stormwater specialists and planners)- Council (when developing public land lt$1 million)

      2 Development assessors- Council statutory planners- Council internal referrals (engineering assets ESD stormwater officers)

      3 Strategy- Council strategic planners

      4 Melbourne Water

      Whorsquos affected

      43

      What are the implications

      bull BPEM - Itrsquos not just subdivisions any more

      bull Cost ndash offset or assetbull Early planning and integration ndash more

      work up frontbull Not just engineeringbull Varying Council skills and experience

      Development Proponents

      44

      If already have a local policy for WSUDESD no real change

      If notbull Workload and resourcingbull Increased detail and technical

      contentbull Administrative arrangements ndash

      referrals permit conditions ndashmake sure you make 60 stat days

      bull Applicant pressure ndash what do you want

      bull Assets

      Development Assessors

      45

      bull Structure plans and rezoning ndashopportunities for localregional approach

      bull IWM and Stormwater Management Plans ndash opportunities for these to be implemented through the controls spatial opportunities

      bull Opportunities for development of Council offset strategies

      Strategy

      Offsets

      bull Developer enters into an agreement with relevant drainage authority to financially contribute to off-site stormwatermanagement in lieu of providing on-site treatment

      bull Already available for residential subdivisions in Melbourne (Clause 56) through MWCs Stormwater Quality Offset scheme

      What are stormwater quality offsets

      X Not drainage contributions (MWC drainage scheme)

      X Not development contributions (DCPICP)

      47

      When to use

      bull Not in MW DSS or growth area where therersquos an existing framework for funding SW treatment

      bull Onsite treatment not practical or desirable

      bull To fund planned localregional stormwater treatment works in that catchment via an existing offset scheme

      bull Council and developer both agree to it

      48

      OffsetsExample ndash Kingston Offset Scheme

      Asset ownership and maintenance

      bull Whorsquos going to own itbull Whorsquos going to maintain itbull How do you maintain itbull How much will it cost

      bull Where is itbull Is maintenance burden

      practical for likely future owners

      bull Whorsquos going to monitor compliance and how

      The detail is in the permit conditions

      Application requirements

      ldquoAn application must be accompanied by details of the proposed stormwater management system including drainage works and retention detention and discharges of stormwater to the drainage systemrdquo ndash Clause 5318

      What does the planning scheme require

      But alsohellipNeed to provide sufficient information to Council which demonstrates that you comply and how you comply with all the other standards ndash eg urban coolinghabitatetc BPEM site management pollutant control infiltration (as relevant to development type

      51

      1 PlansWhat are you doing where is it going and does it fit

      2 ModellingDo you (or can you) meet BPEM requirements

      3 Written response to standardsHow does your proposal comply with the requirements

      52

      Application

      bull Site plan ndash show all assetsWSUD treatments and any IWM features on the site layout plan with everything else

      bull Landscape plan ndash if planting design passive irrigation etc forms part of response to requirements show

      bull Site management plan (depending on Council)

      bull Separate WSUDIWM plan showing all features on a stripped back background

      bull Concept WSUD asset design ndash larger assets only (wetlands bioretention basins sed basin etc) ndash sufficient design detail to confirm spatial requirements

      PlansPermit conditions

      bull Detailed engineering design bull Site Management Plan (final)bull Asset maintenance plan (final)bull Handover arrangements (if public)

      54

      STORM ndash Online toolbull Print out of STORM reportbull Make sure meets 100 or

      morebull Make sure report inputs and

      results match plan

      Modelling - SWQ

      MUSIC ndash Proprietary softwarebull Provide a copy of the model filebull Print out the modelling resultsbull Provide summary of your model

      inputs for each treatment train (iecatchment size impervious treatment area etc)

      bull Provide a print out of the model schematic

      Bonus points bull Provide details of model

      parametersbull Provide results of MUSIC auditor

      run (if using Melbourne Water MUSIC Guidelines)

      56

      Assessment against standards

      bull Say what you have done (or will do) to meet each standardbull Donrsquot forget (if WSUD) details of maintenance and asset

      ownershipbull Where applicable be explicit why yoursquove chosen (or not chosen) to

      respond the way you have Egbull Opportunitiesbull Site constraintsbull Practicaloperational issues bull Brief dot point summary of options analysis if complex

      bull Make sure if it doesnrsquot meet the standard it meets the objectivebull Make sure shown on plan and consistent with modelling and rest of

      documentation

      57

      Resources

      Local stormwaterWSUD policiesBaysideKingstonCaseyMonashMelbourneYarraMoonee ValleyPort PhilipStonningtonHumeCampaspeBass Coast

      Local ESD (including IWM) policies Greater BendigoGreater DandenongHobsons BayWhittleseaWyndhamWhitehorseManninghamMorelandDarebinBanyuleKnoxBrimbank

      Council planning resources

      Application resources ndashexamplesDELWP Practice Note ndashformal guide to the new controlsMoreland ndash application checklists and example plans for a variety of residential developmentsPort Philip ndash compliance guidelines checklist and examplesMoonee Valley ndash checklists and example plans including site management plans Greater Bendigo ndash WSUD kitBayside ndash application guidelines and example plans

      59

      Technical guidelines (modelling design construction)

      Melbourne Water

      STORM calculatorMUSIC auditor - lsquohow torsquo video here

      Melbourne Water technical guidelines page- WSUD asset life cycle costings and model maintenance guidelines- MUSIC guidelines- Stormwater harvesting guidelines- WSUD life cycle costings and

      maintenance guidelines- Design and construction guidelines

      for variety of assetshttpswwwmelbournewatercomauplanning-and-buildingdeveloper-guides-and-resourcesguidelines-drawings-and-checklistsguidelines

      Council

      South-Eastern Growth Council WSUD guidelines ndash note that some individual Councils have their own addendumsMelbournePort PhilipNorth-West Growth Council WSUD guidelines - note that some individual Councils have their own addendumsGreater BendigoMilduraBallaratBaw BawWyndhamMoreland ndash tree pits and raingardens

      60

      IWM

      Example Council IWM strategiesMelbourneCaseyMonashKingston

      Resilient Melbourne ndash IWM information lsquohubrsquoClearwater ndash capacity building and case studiesMelbourne Water ndash funding opportunities for IWM projects

      Stormwater offset schemes

      KingstonGreater GeelongMelbourne Water ndash non scheme contributions

      Site management

      EPA guidelines- management of erosion and sediment

      Next steps and other stormwater initiatives

      Emma Stewart DELWP

      62

      Next steps

      bull Trainingbull The EPArsquos BPEM Reviewbull Offsets policybull Review of STORM bull Building controls

      63

      State Stormwater policies

      64

      Thank you

      • Slide Number 1
      • Slide Number 2
      • History of WSUD
      • History of WSUD
      • Transformational change in urban water
      • Inconsistencies and inequities in our approach to stormwater management
      • Slide Number 8
      • Terms of Reference
      • Improving Stormwater Management Advisory Committee
      • Wide consultation
      • Stakeholder feedback
      • Stakeholder feedback
      • Committee submitted its report in September 2018
      • Committee Recomendations
      • Planning reforms
      • Future policy directions
      • Supporting actions
      • Slide Number 19
      • Government response (to date)
      • Longer term recommendations
      • State-based planning requirements (lsquobeforersquo)
      • State-based planning requirements (lsquoafterrsquo)
      • Development types (volume)
      • Slide Number 25
      • Amendment VC154
      • Whatrsquos in
      • Slide Number 28
      • Key elements of clauses
      • Clause 5318 ndash subdivision
      • Clause 5318 ndash Buildings and works
      • Townhouses - Standard B9
      • Slide Number 33
      • Slide Number 34
      • Slide Number 35
      • Slide Number 36
      • Slide Number 37
      • Buildings and works - Site management standard
      • Site management
      • Planning Advisory Note No 75
      • Slide Number 41
      • Slide Number 42
      • Slide Number 43
      • Slide Number 44
      • Slide Number 45
      • Slide Number 46
      • Slide Number 47
      • Slide Number 48
      • Slide Number 49
      • Slide Number 50
      • Slide Number 51
      • Slide Number 52
      • Slide Number 53
      • Slide Number 54
      • Slide Number 55
      • Slide Number 56
      • Slide Number 57
      • Slide Number 58
      • Slide Number 59
      • Slide Number 60
      • Slide Number 61
      • Next steps
      • State Stormwater policies
      • Slide Number 64

        History of WSUD

        1997

        CSIRO Study

        1999

        BPEM Guidelines

        2000

        VSAPSMPs

        2002

        Clearwater

        2006

        Living Rivers amp Lower

        Yarra Capacity Building

        Programs

        Clause 56

        Strong WSUD growth

        2010

        Municipal IWCM

        Targets

        2011

        SE IWCM Strategy

        Victorian Stormwater Committee

        2012

        Living Victoria Policy

        Water for Victoria

        2016

        Transformational change in urban water

        Public Health

        1890s

        Growth

        Post WWII

        Efficiency

        1990s

        TODAY

        Liveability Sustainability Resilience

        Separate water sewerage drainage systems

        Integrated planning and management

        6

        Inconsistencies and inequities in our approach to stormwater management

        Source Property Inc Magazine

        Residential dev must meet BPEM under VPP

        Most residential dev not required to meet BPEM (other than apartments)

        under VPP

        Industrial commercial dev must meet BPEM

        through DSSsInd com not required to meet BPEM under

        VPP

        Industrial com dev not required to meet BPEM

        under VPP

        No PSP guideline IWM plan (equivalents)

        IWM in PSP guidelines + PSP IWM plans

        Other councils havenrsquot

        Some councils have expanded BPEM coverage

        Renorsquos and rebuilds not required to meet

        BPEM

        Residential subdivisions must

        meet BPEM

        Offsets available

        No offsets

        No clear mechanism for recovering $$

        DSSs for recovering $$ Public roads and

        land not required to meet BPEM

        Private land must meet

        BPEM

        VPP = Victoria Planning Provisions

        BPEM = the stormwater management standards

        DSS = Development Services Schemes

        PSP = Precinct Structure Plans

        IWM = Integrated Water Management

        8

        Government commits to improve stormwater management through planning system reforms

        9

        Terms of Reference

        Part A (core)Specific advice on which types of

        development of those currently not subject to the Statersquos urban runoff management

        objectives should be required to manage their stormwater and the associated reforms

        Part B (future directions) Future policy directions for improving

        stormwater management and strengthening the links between urban water management and the planning and development system

        more broadly

        10

        Improving Stormwater Management Advisory Committee

        Dr Jeremy Cheesman Julie Katz Chris Chesterfield (chair) Sue Porter

        11

        Wide consultation

        6 committee meetings

        6 stakeholder workshops

        46 submissions7 one on ones

        12

        Stakeholder feedback

        bull Consultation indicated widespread support for application of stormwater standards across all development types

        bull Raised a number of implementation issues

        bull Planning system only part of the response

        13

        Stakeholder feedback

        Other feedback

        bull Offsets are useful if they can be designed to provide net benefits and protect sensitive areas

        bull Councils struggle with funding stormwater infrastructure costs

        bull Rolesaccountabilities not well definedbull Skills tools and guidance need investmentbull Community awareness lowbull Support for linking IWM plans to planning system

        14

        Committee submitted its report in September 2018

        15

        The Committees 18 recommendations include

        bull Planning reforms (3) ndash immediate reforms satisfying Part A of the Terms of Reference (ToR)

        bull Future policy directions (7) ndash longer term policy directions satisfying Part B of the ToR

        bull Supporting actions (8) ndash actions to ensure successful implementation of the (Part A) planning reforms satisfying Part B of the ToR

        Committee Recomendations

        16

        Planning reforms

        Rec 1 ndash Expand the stormwater planning provisions (phase 1) That the Victorian Government amend the VPPs to expand the current stormwater management requirements to

        bull commercial subdivisions and developmentsbull industrial subdivisions and developmentsbull public-use developmentsbull multi-dwelling residential subdivisions and developments

        Rec 2 ndash Expand the stormwater planning provisions (phase 2) That subject to further consultation the development of deemed-to-satisfy solutions (rec 12) adequate guidance and tools (recs 13 14 and 15) and offset processes (rec 5) the Victorian Government amend the VPPs to expand the current stormwater management requirements to

        bull single-dwelling developmentsbull extensions over 50 m2

        Rec 3 ndash Insert an IWM clause into the Planning Policy Framework (PPF) That the Victorian Government amend the PPF to embed the concepts of IWM objectives and strategies

        17

        Future policy directions

        Rec 4 ndash Amend the building and plumbing controls

        Rec 5 ndash Establish effective offsetting arrangements

        Rec 6 ndash Clarify local governmentsrsquo roles and responsibilities

        Rec 7 ndash Strengthen compliance requirements

        Rec 8 ndash Determine funding sources for public stormwater infrastructure

        Rec 9 ndash Link water management with urban planning

        Rec 10 ndash Set stronger place-based BPEM stormwater performance objectives

        18

        Rec 11 ndash Strengthen enforcement of stormwater construction requirements

        Rec 12 ndash Prepare deemed-to-satisfy solutions

        Rec 13 ndash Review the STORM and MUSIC tools

        Rec 14 ndash Build technical expertise

        Rec 15 ndash Improve guidance

        Rec 16 ndash Improve awareness of the VPP changes

        Rec 17 ndash Investigate options for rainwater tank maintenance and operation

        Rec 18 ndash Broaden rating systems to include IWM

        Supporting actions

        The new stormwater provisions

        Emma Stewart DELWP

        20

        Government response (to date)

        21

        Government is currently considering the committeersquos longer-term recommendations and is working with key stakeholders to determine the most effective response and pathways for implementation

        Longer term recommendations

        22

        State-based planning requirements (lsquobeforersquo)

        Sourced ELM 2018

        23

        State-based planning requirements (lsquoafterrsquo)

        24

        Development types (volume)

        Future development estimated impervious area 2020-2050

        25

        The nitty grittyhellip

        26

        Amendment VC154

        Victoria Planning Provision changesbull New clause (5318) and changes to an existing clause

        (5503) to expand the stormwater requirements to more development types

        bull New objectives to manage toxicants and encourage broader benefits of stormwater management

        27

        Whatrsquos in

        Applies to an application tobull subdivide land bull construct a building bull construct or carry out works

        In both hellip

        Clause 5318bull commercial zonesbull industrial zonesbull public-use zones

        Clause 5518 bull Construct townhouses

        Whatrsquos out of clause 5318

        bull Developments and subdivisions approved or lodged prior to the amendment

        bull Developments which do not require planning permission

        bull Vicsmart applications

        bull Applications for land within development or incorporated plans approved before the amendment

        bull Extensions and works lt 50m2

        bull Applications after the amendment to amend existing planning permits

        If in doubt ask a planner

        29

        Key elements of clauses

        Industrial commercial applications (Clause 5318)tobull subdivide land bull construct a building bull construct or carry out works

        Stormwater management objectives + standard (W1)

        Stormwater management objectives + standard (W2)+ Site management objectives + standard (W3)

        Decision guidelines

        Same for Clause 5503 (townhouses)

        30

        Clause 5318 ndash subdivision

        Stormwater management standard W1 The stormwater management system should be bull Designed and managed in accordance with the requirements and

        to the satisfaction of the relevant drainage authoritybull Designed and managed in accordance with the requirements and

        to the satisfaction of the water authority where reuse of stormwater is proposed

        bull Designed to meet the current best practice performance objectives for stormwater quality as contained in the BPEM

        bull Designed to ensure that flows downstream of the subdivision site are restricted to pre-development levels unless increased flows are approved by the relevant drainage authority and there are no detrimental downstream impacts

        bull Designed to contribute to cooling improving local habitat and providing attractive and enjoyable spaces

        31

        Clause 5318 ndash Buildings and works

        Standard W2The stormwater management system should be designed to

        bull Meet the current best practice performance objectives for stormwater quality as contained in the BPEM

        bull Contribute to cooling improving local habitat and providing attractive and enjoyable spaces

        bull Minimise the impact of chemical pollutants and other toxicants including by but not limited to bunding and covering of roofing of storage loading and work areas

        32

        Townhouses - Standard B9

        Clause 5503 ndash Permeability and stormwater management objectives and standard B9

        Objectivesbull Similar to 5318 (including the cooling liveability

        objective)bull gt20 perviousness objective (unchanged)

        Standardbull NEW - cooling liveability objectivebull NEW ndash requirement to meet BPEM

        What does this all mean

        34

        Clause 5318 - Whatrsquos in

        35

        Urban cooling Reduce heat radiation from buildings and hard surfaces throughbull Shade trees in car parks or over driveways bull More open space and treesbull Green roofsbull Green walls

        36

        Optionsbull Passive irrigationbull Integrate assets into

        communal open spacebull Tree pits and permeable

        paving (driveways and carpark)

        bull Stormwater harvesting (major developments only)

        Infiltration habitat amenity

        37

        Control harmful chemicals

        Optionsbull Careful layoutbull Consider alternative less harmful substancesbull Roofed designated storage areabull Internal drainage design to sewer or a treatment devicebull Bunding

        38

        Standard W3Standard W3 requires that application describe how the site will be managed prior to and during the construction period The application should set out requirements for managingbull Erosion and sedimentbull Stormwaterbull Litter concrete and other construction wastesbull Chemical contamination

        Buildings and works - Site management standard

        39

        Site management

        40

        Planning Advisory Note No 75

        Implications for industry

        Kate MatthewsStormwater Victoria

        1 Development proponents- Developers- Consultants (engineers stormwater specialists and planners)- Council (when developing public land lt$1 million)

        2 Development assessors- Council statutory planners- Council internal referrals (engineering assets ESD stormwater officers)

        3 Strategy- Council strategic planners

        4 Melbourne Water

        Whorsquos affected

        43

        What are the implications

        bull BPEM - Itrsquos not just subdivisions any more

        bull Cost ndash offset or assetbull Early planning and integration ndash more

        work up frontbull Not just engineeringbull Varying Council skills and experience

        Development Proponents

        44

        If already have a local policy for WSUDESD no real change

        If notbull Workload and resourcingbull Increased detail and technical

        contentbull Administrative arrangements ndash

        referrals permit conditions ndashmake sure you make 60 stat days

        bull Applicant pressure ndash what do you want

        bull Assets

        Development Assessors

        45

        bull Structure plans and rezoning ndashopportunities for localregional approach

        bull IWM and Stormwater Management Plans ndash opportunities for these to be implemented through the controls spatial opportunities

        bull Opportunities for development of Council offset strategies

        Strategy

        Offsets

        bull Developer enters into an agreement with relevant drainage authority to financially contribute to off-site stormwatermanagement in lieu of providing on-site treatment

        bull Already available for residential subdivisions in Melbourne (Clause 56) through MWCs Stormwater Quality Offset scheme

        What are stormwater quality offsets

        X Not drainage contributions (MWC drainage scheme)

        X Not development contributions (DCPICP)

        47

        When to use

        bull Not in MW DSS or growth area where therersquos an existing framework for funding SW treatment

        bull Onsite treatment not practical or desirable

        bull To fund planned localregional stormwater treatment works in that catchment via an existing offset scheme

        bull Council and developer both agree to it

        48

        OffsetsExample ndash Kingston Offset Scheme

        Asset ownership and maintenance

        bull Whorsquos going to own itbull Whorsquos going to maintain itbull How do you maintain itbull How much will it cost

        bull Where is itbull Is maintenance burden

        practical for likely future owners

        bull Whorsquos going to monitor compliance and how

        The detail is in the permit conditions

        Application requirements

        ldquoAn application must be accompanied by details of the proposed stormwater management system including drainage works and retention detention and discharges of stormwater to the drainage systemrdquo ndash Clause 5318

        What does the planning scheme require

        But alsohellipNeed to provide sufficient information to Council which demonstrates that you comply and how you comply with all the other standards ndash eg urban coolinghabitatetc BPEM site management pollutant control infiltration (as relevant to development type

        51

        1 PlansWhat are you doing where is it going and does it fit

        2 ModellingDo you (or can you) meet BPEM requirements

        3 Written response to standardsHow does your proposal comply with the requirements

        52

        Application

        bull Site plan ndash show all assetsWSUD treatments and any IWM features on the site layout plan with everything else

        bull Landscape plan ndash if planting design passive irrigation etc forms part of response to requirements show

        bull Site management plan (depending on Council)

        bull Separate WSUDIWM plan showing all features on a stripped back background

        bull Concept WSUD asset design ndash larger assets only (wetlands bioretention basins sed basin etc) ndash sufficient design detail to confirm spatial requirements

        PlansPermit conditions

        bull Detailed engineering design bull Site Management Plan (final)bull Asset maintenance plan (final)bull Handover arrangements (if public)

        54

        STORM ndash Online toolbull Print out of STORM reportbull Make sure meets 100 or

        morebull Make sure report inputs and

        results match plan

        Modelling - SWQ

        MUSIC ndash Proprietary softwarebull Provide a copy of the model filebull Print out the modelling resultsbull Provide summary of your model

        inputs for each treatment train (iecatchment size impervious treatment area etc)

        bull Provide a print out of the model schematic

        Bonus points bull Provide details of model

        parametersbull Provide results of MUSIC auditor

        run (if using Melbourne Water MUSIC Guidelines)

        56

        Assessment against standards

        bull Say what you have done (or will do) to meet each standardbull Donrsquot forget (if WSUD) details of maintenance and asset

        ownershipbull Where applicable be explicit why yoursquove chosen (or not chosen) to

        respond the way you have Egbull Opportunitiesbull Site constraintsbull Practicaloperational issues bull Brief dot point summary of options analysis if complex

        bull Make sure if it doesnrsquot meet the standard it meets the objectivebull Make sure shown on plan and consistent with modelling and rest of

        documentation

        57

        Resources

        Local stormwaterWSUD policiesBaysideKingstonCaseyMonashMelbourneYarraMoonee ValleyPort PhilipStonningtonHumeCampaspeBass Coast

        Local ESD (including IWM) policies Greater BendigoGreater DandenongHobsons BayWhittleseaWyndhamWhitehorseManninghamMorelandDarebinBanyuleKnoxBrimbank

        Council planning resources

        Application resources ndashexamplesDELWP Practice Note ndashformal guide to the new controlsMoreland ndash application checklists and example plans for a variety of residential developmentsPort Philip ndash compliance guidelines checklist and examplesMoonee Valley ndash checklists and example plans including site management plans Greater Bendigo ndash WSUD kitBayside ndash application guidelines and example plans

        59

        Technical guidelines (modelling design construction)

        Melbourne Water

        STORM calculatorMUSIC auditor - lsquohow torsquo video here

        Melbourne Water technical guidelines page- WSUD asset life cycle costings and model maintenance guidelines- MUSIC guidelines- Stormwater harvesting guidelines- WSUD life cycle costings and

        maintenance guidelines- Design and construction guidelines

        for variety of assetshttpswwwmelbournewatercomauplanning-and-buildingdeveloper-guides-and-resourcesguidelines-drawings-and-checklistsguidelines

        Council

        South-Eastern Growth Council WSUD guidelines ndash note that some individual Councils have their own addendumsMelbournePort PhilipNorth-West Growth Council WSUD guidelines - note that some individual Councils have their own addendumsGreater BendigoMilduraBallaratBaw BawWyndhamMoreland ndash tree pits and raingardens

        60

        IWM

        Example Council IWM strategiesMelbourneCaseyMonashKingston

        Resilient Melbourne ndash IWM information lsquohubrsquoClearwater ndash capacity building and case studiesMelbourne Water ndash funding opportunities for IWM projects

        Stormwater offset schemes

        KingstonGreater GeelongMelbourne Water ndash non scheme contributions

        Site management

        EPA guidelines- management of erosion and sediment

        Next steps and other stormwater initiatives

        Emma Stewart DELWP

        62

        Next steps

        bull Trainingbull The EPArsquos BPEM Reviewbull Offsets policybull Review of STORM bull Building controls

        63

        State Stormwater policies

        64

        Thank you

        • Slide Number 1
        • Slide Number 2
        • History of WSUD
        • History of WSUD
        • Transformational change in urban water
        • Inconsistencies and inequities in our approach to stormwater management
        • Slide Number 8
        • Terms of Reference
        • Improving Stormwater Management Advisory Committee
        • Wide consultation
        • Stakeholder feedback
        • Stakeholder feedback
        • Committee submitted its report in September 2018
        • Committee Recomendations
        • Planning reforms
        • Future policy directions
        • Supporting actions
        • Slide Number 19
        • Government response (to date)
        • Longer term recommendations
        • State-based planning requirements (lsquobeforersquo)
        • State-based planning requirements (lsquoafterrsquo)
        • Development types (volume)
        • Slide Number 25
        • Amendment VC154
        • Whatrsquos in
        • Slide Number 28
        • Key elements of clauses
        • Clause 5318 ndash subdivision
        • Clause 5318 ndash Buildings and works
        • Townhouses - Standard B9
        • Slide Number 33
        • Slide Number 34
        • Slide Number 35
        • Slide Number 36
        • Slide Number 37
        • Buildings and works - Site management standard
        • Site management
        • Planning Advisory Note No 75
        • Slide Number 41
        • Slide Number 42
        • Slide Number 43
        • Slide Number 44
        • Slide Number 45
        • Slide Number 46
        • Slide Number 47
        • Slide Number 48
        • Slide Number 49
        • Slide Number 50
        • Slide Number 51
        • Slide Number 52
        • Slide Number 53
        • Slide Number 54
        • Slide Number 55
        • Slide Number 56
        • Slide Number 57
        • Slide Number 58
        • Slide Number 59
        • Slide Number 60
        • Slide Number 61
        • Next steps
        • State Stormwater policies
        • Slide Number 64

          Transformational change in urban water

          Public Health

          1890s

          Growth

          Post WWII

          Efficiency

          1990s

          TODAY

          Liveability Sustainability Resilience

          Separate water sewerage drainage systems

          Integrated planning and management

          6

          Inconsistencies and inequities in our approach to stormwater management

          Source Property Inc Magazine

          Residential dev must meet BPEM under VPP

          Most residential dev not required to meet BPEM (other than apartments)

          under VPP

          Industrial commercial dev must meet BPEM

          through DSSsInd com not required to meet BPEM under

          VPP

          Industrial com dev not required to meet BPEM

          under VPP

          No PSP guideline IWM plan (equivalents)

          IWM in PSP guidelines + PSP IWM plans

          Other councils havenrsquot

          Some councils have expanded BPEM coverage

          Renorsquos and rebuilds not required to meet

          BPEM

          Residential subdivisions must

          meet BPEM

          Offsets available

          No offsets

          No clear mechanism for recovering $$

          DSSs for recovering $$ Public roads and

          land not required to meet BPEM

          Private land must meet

          BPEM

          VPP = Victoria Planning Provisions

          BPEM = the stormwater management standards

          DSS = Development Services Schemes

          PSP = Precinct Structure Plans

          IWM = Integrated Water Management

          8

          Government commits to improve stormwater management through planning system reforms

          9

          Terms of Reference

          Part A (core)Specific advice on which types of

          development of those currently not subject to the Statersquos urban runoff management

          objectives should be required to manage their stormwater and the associated reforms

          Part B (future directions) Future policy directions for improving

          stormwater management and strengthening the links between urban water management and the planning and development system

          more broadly

          10

          Improving Stormwater Management Advisory Committee

          Dr Jeremy Cheesman Julie Katz Chris Chesterfield (chair) Sue Porter

          11

          Wide consultation

          6 committee meetings

          6 stakeholder workshops

          46 submissions7 one on ones

          12

          Stakeholder feedback

          bull Consultation indicated widespread support for application of stormwater standards across all development types

          bull Raised a number of implementation issues

          bull Planning system only part of the response

          13

          Stakeholder feedback

          Other feedback

          bull Offsets are useful if they can be designed to provide net benefits and protect sensitive areas

          bull Councils struggle with funding stormwater infrastructure costs

          bull Rolesaccountabilities not well definedbull Skills tools and guidance need investmentbull Community awareness lowbull Support for linking IWM plans to planning system

          14

          Committee submitted its report in September 2018

          15

          The Committees 18 recommendations include

          bull Planning reforms (3) ndash immediate reforms satisfying Part A of the Terms of Reference (ToR)

          bull Future policy directions (7) ndash longer term policy directions satisfying Part B of the ToR

          bull Supporting actions (8) ndash actions to ensure successful implementation of the (Part A) planning reforms satisfying Part B of the ToR

          Committee Recomendations

          16

          Planning reforms

          Rec 1 ndash Expand the stormwater planning provisions (phase 1) That the Victorian Government amend the VPPs to expand the current stormwater management requirements to

          bull commercial subdivisions and developmentsbull industrial subdivisions and developmentsbull public-use developmentsbull multi-dwelling residential subdivisions and developments

          Rec 2 ndash Expand the stormwater planning provisions (phase 2) That subject to further consultation the development of deemed-to-satisfy solutions (rec 12) adequate guidance and tools (recs 13 14 and 15) and offset processes (rec 5) the Victorian Government amend the VPPs to expand the current stormwater management requirements to

          bull single-dwelling developmentsbull extensions over 50 m2

          Rec 3 ndash Insert an IWM clause into the Planning Policy Framework (PPF) That the Victorian Government amend the PPF to embed the concepts of IWM objectives and strategies

          17

          Future policy directions

          Rec 4 ndash Amend the building and plumbing controls

          Rec 5 ndash Establish effective offsetting arrangements

          Rec 6 ndash Clarify local governmentsrsquo roles and responsibilities

          Rec 7 ndash Strengthen compliance requirements

          Rec 8 ndash Determine funding sources for public stormwater infrastructure

          Rec 9 ndash Link water management with urban planning

          Rec 10 ndash Set stronger place-based BPEM stormwater performance objectives

          18

          Rec 11 ndash Strengthen enforcement of stormwater construction requirements

          Rec 12 ndash Prepare deemed-to-satisfy solutions

          Rec 13 ndash Review the STORM and MUSIC tools

          Rec 14 ndash Build technical expertise

          Rec 15 ndash Improve guidance

          Rec 16 ndash Improve awareness of the VPP changes

          Rec 17 ndash Investigate options for rainwater tank maintenance and operation

          Rec 18 ndash Broaden rating systems to include IWM

          Supporting actions

          The new stormwater provisions

          Emma Stewart DELWP

          20

          Government response (to date)

          21

          Government is currently considering the committeersquos longer-term recommendations and is working with key stakeholders to determine the most effective response and pathways for implementation

          Longer term recommendations

          22

          State-based planning requirements (lsquobeforersquo)

          Sourced ELM 2018

          23

          State-based planning requirements (lsquoafterrsquo)

          24

          Development types (volume)

          Future development estimated impervious area 2020-2050

          25

          The nitty grittyhellip

          26

          Amendment VC154

          Victoria Planning Provision changesbull New clause (5318) and changes to an existing clause

          (5503) to expand the stormwater requirements to more development types

          bull New objectives to manage toxicants and encourage broader benefits of stormwater management

          27

          Whatrsquos in

          Applies to an application tobull subdivide land bull construct a building bull construct or carry out works

          In both hellip

          Clause 5318bull commercial zonesbull industrial zonesbull public-use zones

          Clause 5518 bull Construct townhouses

          Whatrsquos out of clause 5318

          bull Developments and subdivisions approved or lodged prior to the amendment

          bull Developments which do not require planning permission

          bull Vicsmart applications

          bull Applications for land within development or incorporated plans approved before the amendment

          bull Extensions and works lt 50m2

          bull Applications after the amendment to amend existing planning permits

          If in doubt ask a planner

          29

          Key elements of clauses

          Industrial commercial applications (Clause 5318)tobull subdivide land bull construct a building bull construct or carry out works

          Stormwater management objectives + standard (W1)

          Stormwater management objectives + standard (W2)+ Site management objectives + standard (W3)

          Decision guidelines

          Same for Clause 5503 (townhouses)

          30

          Clause 5318 ndash subdivision

          Stormwater management standard W1 The stormwater management system should be bull Designed and managed in accordance with the requirements and

          to the satisfaction of the relevant drainage authoritybull Designed and managed in accordance with the requirements and

          to the satisfaction of the water authority where reuse of stormwater is proposed

          bull Designed to meet the current best practice performance objectives for stormwater quality as contained in the BPEM

          bull Designed to ensure that flows downstream of the subdivision site are restricted to pre-development levels unless increased flows are approved by the relevant drainage authority and there are no detrimental downstream impacts

          bull Designed to contribute to cooling improving local habitat and providing attractive and enjoyable spaces

          31

          Clause 5318 ndash Buildings and works

          Standard W2The stormwater management system should be designed to

          bull Meet the current best practice performance objectives for stormwater quality as contained in the BPEM

          bull Contribute to cooling improving local habitat and providing attractive and enjoyable spaces

          bull Minimise the impact of chemical pollutants and other toxicants including by but not limited to bunding and covering of roofing of storage loading and work areas

          32

          Townhouses - Standard B9

          Clause 5503 ndash Permeability and stormwater management objectives and standard B9

          Objectivesbull Similar to 5318 (including the cooling liveability

          objective)bull gt20 perviousness objective (unchanged)

          Standardbull NEW - cooling liveability objectivebull NEW ndash requirement to meet BPEM

          What does this all mean

          34

          Clause 5318 - Whatrsquos in

          35

          Urban cooling Reduce heat radiation from buildings and hard surfaces throughbull Shade trees in car parks or over driveways bull More open space and treesbull Green roofsbull Green walls

          36

          Optionsbull Passive irrigationbull Integrate assets into

          communal open spacebull Tree pits and permeable

          paving (driveways and carpark)

          bull Stormwater harvesting (major developments only)

          Infiltration habitat amenity

          37

          Control harmful chemicals

          Optionsbull Careful layoutbull Consider alternative less harmful substancesbull Roofed designated storage areabull Internal drainage design to sewer or a treatment devicebull Bunding

          38

          Standard W3Standard W3 requires that application describe how the site will be managed prior to and during the construction period The application should set out requirements for managingbull Erosion and sedimentbull Stormwaterbull Litter concrete and other construction wastesbull Chemical contamination

          Buildings and works - Site management standard

          39

          Site management

          40

          Planning Advisory Note No 75

          Implications for industry

          Kate MatthewsStormwater Victoria

          1 Development proponents- Developers- Consultants (engineers stormwater specialists and planners)- Council (when developing public land lt$1 million)

          2 Development assessors- Council statutory planners- Council internal referrals (engineering assets ESD stormwater officers)

          3 Strategy- Council strategic planners

          4 Melbourne Water

          Whorsquos affected

          43

          What are the implications

          bull BPEM - Itrsquos not just subdivisions any more

          bull Cost ndash offset or assetbull Early planning and integration ndash more

          work up frontbull Not just engineeringbull Varying Council skills and experience

          Development Proponents

          44

          If already have a local policy for WSUDESD no real change

          If notbull Workload and resourcingbull Increased detail and technical

          contentbull Administrative arrangements ndash

          referrals permit conditions ndashmake sure you make 60 stat days

          bull Applicant pressure ndash what do you want

          bull Assets

          Development Assessors

          45

          bull Structure plans and rezoning ndashopportunities for localregional approach

          bull IWM and Stormwater Management Plans ndash opportunities for these to be implemented through the controls spatial opportunities

          bull Opportunities for development of Council offset strategies

          Strategy

          Offsets

          bull Developer enters into an agreement with relevant drainage authority to financially contribute to off-site stormwatermanagement in lieu of providing on-site treatment

          bull Already available for residential subdivisions in Melbourne (Clause 56) through MWCs Stormwater Quality Offset scheme

          What are stormwater quality offsets

          X Not drainage contributions (MWC drainage scheme)

          X Not development contributions (DCPICP)

          47

          When to use

          bull Not in MW DSS or growth area where therersquos an existing framework for funding SW treatment

          bull Onsite treatment not practical or desirable

          bull To fund planned localregional stormwater treatment works in that catchment via an existing offset scheme

          bull Council and developer both agree to it

          48

          OffsetsExample ndash Kingston Offset Scheme

          Asset ownership and maintenance

          bull Whorsquos going to own itbull Whorsquos going to maintain itbull How do you maintain itbull How much will it cost

          bull Where is itbull Is maintenance burden

          practical for likely future owners

          bull Whorsquos going to monitor compliance and how

          The detail is in the permit conditions

          Application requirements

          ldquoAn application must be accompanied by details of the proposed stormwater management system including drainage works and retention detention and discharges of stormwater to the drainage systemrdquo ndash Clause 5318

          What does the planning scheme require

          But alsohellipNeed to provide sufficient information to Council which demonstrates that you comply and how you comply with all the other standards ndash eg urban coolinghabitatetc BPEM site management pollutant control infiltration (as relevant to development type

          51

          1 PlansWhat are you doing where is it going and does it fit

          2 ModellingDo you (or can you) meet BPEM requirements

          3 Written response to standardsHow does your proposal comply with the requirements

          52

          Application

          bull Site plan ndash show all assetsWSUD treatments and any IWM features on the site layout plan with everything else

          bull Landscape plan ndash if planting design passive irrigation etc forms part of response to requirements show

          bull Site management plan (depending on Council)

          bull Separate WSUDIWM plan showing all features on a stripped back background

          bull Concept WSUD asset design ndash larger assets only (wetlands bioretention basins sed basin etc) ndash sufficient design detail to confirm spatial requirements

          PlansPermit conditions

          bull Detailed engineering design bull Site Management Plan (final)bull Asset maintenance plan (final)bull Handover arrangements (if public)

          54

          STORM ndash Online toolbull Print out of STORM reportbull Make sure meets 100 or

          morebull Make sure report inputs and

          results match plan

          Modelling - SWQ

          MUSIC ndash Proprietary softwarebull Provide a copy of the model filebull Print out the modelling resultsbull Provide summary of your model

          inputs for each treatment train (iecatchment size impervious treatment area etc)

          bull Provide a print out of the model schematic

          Bonus points bull Provide details of model

          parametersbull Provide results of MUSIC auditor

          run (if using Melbourne Water MUSIC Guidelines)

          56

          Assessment against standards

          bull Say what you have done (or will do) to meet each standardbull Donrsquot forget (if WSUD) details of maintenance and asset

          ownershipbull Where applicable be explicit why yoursquove chosen (or not chosen) to

          respond the way you have Egbull Opportunitiesbull Site constraintsbull Practicaloperational issues bull Brief dot point summary of options analysis if complex

          bull Make sure if it doesnrsquot meet the standard it meets the objectivebull Make sure shown on plan and consistent with modelling and rest of

          documentation

          57

          Resources

          Local stormwaterWSUD policiesBaysideKingstonCaseyMonashMelbourneYarraMoonee ValleyPort PhilipStonningtonHumeCampaspeBass Coast

          Local ESD (including IWM) policies Greater BendigoGreater DandenongHobsons BayWhittleseaWyndhamWhitehorseManninghamMorelandDarebinBanyuleKnoxBrimbank

          Council planning resources

          Application resources ndashexamplesDELWP Practice Note ndashformal guide to the new controlsMoreland ndash application checklists and example plans for a variety of residential developmentsPort Philip ndash compliance guidelines checklist and examplesMoonee Valley ndash checklists and example plans including site management plans Greater Bendigo ndash WSUD kitBayside ndash application guidelines and example plans

          59

          Technical guidelines (modelling design construction)

          Melbourne Water

          STORM calculatorMUSIC auditor - lsquohow torsquo video here

          Melbourne Water technical guidelines page- WSUD asset life cycle costings and model maintenance guidelines- MUSIC guidelines- Stormwater harvesting guidelines- WSUD life cycle costings and

          maintenance guidelines- Design and construction guidelines

          for variety of assetshttpswwwmelbournewatercomauplanning-and-buildingdeveloper-guides-and-resourcesguidelines-drawings-and-checklistsguidelines

          Council

          South-Eastern Growth Council WSUD guidelines ndash note that some individual Councils have their own addendumsMelbournePort PhilipNorth-West Growth Council WSUD guidelines - note that some individual Councils have their own addendumsGreater BendigoMilduraBallaratBaw BawWyndhamMoreland ndash tree pits and raingardens

          60

          IWM

          Example Council IWM strategiesMelbourneCaseyMonashKingston

          Resilient Melbourne ndash IWM information lsquohubrsquoClearwater ndash capacity building and case studiesMelbourne Water ndash funding opportunities for IWM projects

          Stormwater offset schemes

          KingstonGreater GeelongMelbourne Water ndash non scheme contributions

          Site management

          EPA guidelines- management of erosion and sediment

          Next steps and other stormwater initiatives

          Emma Stewart DELWP

          62

          Next steps

          bull Trainingbull The EPArsquos BPEM Reviewbull Offsets policybull Review of STORM bull Building controls

          63

          State Stormwater policies

          64

          Thank you

          • Slide Number 1
          • Slide Number 2
          • History of WSUD
          • History of WSUD
          • Transformational change in urban water
          • Inconsistencies and inequities in our approach to stormwater management
          • Slide Number 8
          • Terms of Reference
          • Improving Stormwater Management Advisory Committee
          • Wide consultation
          • Stakeholder feedback
          • Stakeholder feedback
          • Committee submitted its report in September 2018
          • Committee Recomendations
          • Planning reforms
          • Future policy directions
          • Supporting actions
          • Slide Number 19
          • Government response (to date)
          • Longer term recommendations
          • State-based planning requirements (lsquobeforersquo)
          • State-based planning requirements (lsquoafterrsquo)
          • Development types (volume)
          • Slide Number 25
          • Amendment VC154
          • Whatrsquos in
          • Slide Number 28
          • Key elements of clauses
          • Clause 5318 ndash subdivision
          • Clause 5318 ndash Buildings and works
          • Townhouses - Standard B9
          • Slide Number 33
          • Slide Number 34
          • Slide Number 35
          • Slide Number 36
          • Slide Number 37
          • Buildings and works - Site management standard
          • Site management
          • Planning Advisory Note No 75
          • Slide Number 41
          • Slide Number 42
          • Slide Number 43
          • Slide Number 44
          • Slide Number 45
          • Slide Number 46
          • Slide Number 47
          • Slide Number 48
          • Slide Number 49
          • Slide Number 50
          • Slide Number 51
          • Slide Number 52
          • Slide Number 53
          • Slide Number 54
          • Slide Number 55
          • Slide Number 56
          • Slide Number 57
          • Slide Number 58
          • Slide Number 59
          • Slide Number 60
          • Slide Number 61
          • Next steps
          • State Stormwater policies
          • Slide Number 64

            6

            Inconsistencies and inequities in our approach to stormwater management

            Source Property Inc Magazine

            Residential dev must meet BPEM under VPP

            Most residential dev not required to meet BPEM (other than apartments)

            under VPP

            Industrial commercial dev must meet BPEM

            through DSSsInd com not required to meet BPEM under

            VPP

            Industrial com dev not required to meet BPEM

            under VPP

            No PSP guideline IWM plan (equivalents)

            IWM in PSP guidelines + PSP IWM plans

            Other councils havenrsquot

            Some councils have expanded BPEM coverage

            Renorsquos and rebuilds not required to meet

            BPEM

            Residential subdivisions must

            meet BPEM

            Offsets available

            No offsets

            No clear mechanism for recovering $$

            DSSs for recovering $$ Public roads and

            land not required to meet BPEM

            Private land must meet

            BPEM

            VPP = Victoria Planning Provisions

            BPEM = the stormwater management standards

            DSS = Development Services Schemes

            PSP = Precinct Structure Plans

            IWM = Integrated Water Management

            8

            Government commits to improve stormwater management through planning system reforms

            9

            Terms of Reference

            Part A (core)Specific advice on which types of

            development of those currently not subject to the Statersquos urban runoff management

            objectives should be required to manage their stormwater and the associated reforms

            Part B (future directions) Future policy directions for improving

            stormwater management and strengthening the links between urban water management and the planning and development system

            more broadly

            10

            Improving Stormwater Management Advisory Committee

            Dr Jeremy Cheesman Julie Katz Chris Chesterfield (chair) Sue Porter

            11

            Wide consultation

            6 committee meetings

            6 stakeholder workshops

            46 submissions7 one on ones

            12

            Stakeholder feedback

            bull Consultation indicated widespread support for application of stormwater standards across all development types

            bull Raised a number of implementation issues

            bull Planning system only part of the response

            13

            Stakeholder feedback

            Other feedback

            bull Offsets are useful if they can be designed to provide net benefits and protect sensitive areas

            bull Councils struggle with funding stormwater infrastructure costs

            bull Rolesaccountabilities not well definedbull Skills tools and guidance need investmentbull Community awareness lowbull Support for linking IWM plans to planning system

            14

            Committee submitted its report in September 2018

            15

            The Committees 18 recommendations include

            bull Planning reforms (3) ndash immediate reforms satisfying Part A of the Terms of Reference (ToR)

            bull Future policy directions (7) ndash longer term policy directions satisfying Part B of the ToR

            bull Supporting actions (8) ndash actions to ensure successful implementation of the (Part A) planning reforms satisfying Part B of the ToR

            Committee Recomendations

            16

            Planning reforms

            Rec 1 ndash Expand the stormwater planning provisions (phase 1) That the Victorian Government amend the VPPs to expand the current stormwater management requirements to

            bull commercial subdivisions and developmentsbull industrial subdivisions and developmentsbull public-use developmentsbull multi-dwelling residential subdivisions and developments

            Rec 2 ndash Expand the stormwater planning provisions (phase 2) That subject to further consultation the development of deemed-to-satisfy solutions (rec 12) adequate guidance and tools (recs 13 14 and 15) and offset processes (rec 5) the Victorian Government amend the VPPs to expand the current stormwater management requirements to

            bull single-dwelling developmentsbull extensions over 50 m2

            Rec 3 ndash Insert an IWM clause into the Planning Policy Framework (PPF) That the Victorian Government amend the PPF to embed the concepts of IWM objectives and strategies

            17

            Future policy directions

            Rec 4 ndash Amend the building and plumbing controls

            Rec 5 ndash Establish effective offsetting arrangements

            Rec 6 ndash Clarify local governmentsrsquo roles and responsibilities

            Rec 7 ndash Strengthen compliance requirements

            Rec 8 ndash Determine funding sources for public stormwater infrastructure

            Rec 9 ndash Link water management with urban planning

            Rec 10 ndash Set stronger place-based BPEM stormwater performance objectives

            18

            Rec 11 ndash Strengthen enforcement of stormwater construction requirements

            Rec 12 ndash Prepare deemed-to-satisfy solutions

            Rec 13 ndash Review the STORM and MUSIC tools

            Rec 14 ndash Build technical expertise

            Rec 15 ndash Improve guidance

            Rec 16 ndash Improve awareness of the VPP changes

            Rec 17 ndash Investigate options for rainwater tank maintenance and operation

            Rec 18 ndash Broaden rating systems to include IWM

            Supporting actions

            The new stormwater provisions

            Emma Stewart DELWP

            20

            Government response (to date)

            21

            Government is currently considering the committeersquos longer-term recommendations and is working with key stakeholders to determine the most effective response and pathways for implementation

            Longer term recommendations

            22

            State-based planning requirements (lsquobeforersquo)

            Sourced ELM 2018

            23

            State-based planning requirements (lsquoafterrsquo)

            24

            Development types (volume)

            Future development estimated impervious area 2020-2050

            25

            The nitty grittyhellip

            26

            Amendment VC154

            Victoria Planning Provision changesbull New clause (5318) and changes to an existing clause

            (5503) to expand the stormwater requirements to more development types

            bull New objectives to manage toxicants and encourage broader benefits of stormwater management

            27

            Whatrsquos in

            Applies to an application tobull subdivide land bull construct a building bull construct or carry out works

            In both hellip

            Clause 5318bull commercial zonesbull industrial zonesbull public-use zones

            Clause 5518 bull Construct townhouses

            Whatrsquos out of clause 5318

            bull Developments and subdivisions approved or lodged prior to the amendment

            bull Developments which do not require planning permission

            bull Vicsmart applications

            bull Applications for land within development or incorporated plans approved before the amendment

            bull Extensions and works lt 50m2

            bull Applications after the amendment to amend existing planning permits

            If in doubt ask a planner

            29

            Key elements of clauses

            Industrial commercial applications (Clause 5318)tobull subdivide land bull construct a building bull construct or carry out works

            Stormwater management objectives + standard (W1)

            Stormwater management objectives + standard (W2)+ Site management objectives + standard (W3)

            Decision guidelines

            Same for Clause 5503 (townhouses)

            30

            Clause 5318 ndash subdivision

            Stormwater management standard W1 The stormwater management system should be bull Designed and managed in accordance with the requirements and

            to the satisfaction of the relevant drainage authoritybull Designed and managed in accordance with the requirements and

            to the satisfaction of the water authority where reuse of stormwater is proposed

            bull Designed to meet the current best practice performance objectives for stormwater quality as contained in the BPEM

            bull Designed to ensure that flows downstream of the subdivision site are restricted to pre-development levels unless increased flows are approved by the relevant drainage authority and there are no detrimental downstream impacts

            bull Designed to contribute to cooling improving local habitat and providing attractive and enjoyable spaces

            31

            Clause 5318 ndash Buildings and works

            Standard W2The stormwater management system should be designed to

            bull Meet the current best practice performance objectives for stormwater quality as contained in the BPEM

            bull Contribute to cooling improving local habitat and providing attractive and enjoyable spaces

            bull Minimise the impact of chemical pollutants and other toxicants including by but not limited to bunding and covering of roofing of storage loading and work areas

            32

            Townhouses - Standard B9

            Clause 5503 ndash Permeability and stormwater management objectives and standard B9

            Objectivesbull Similar to 5318 (including the cooling liveability

            objective)bull gt20 perviousness objective (unchanged)

            Standardbull NEW - cooling liveability objectivebull NEW ndash requirement to meet BPEM

            What does this all mean

            34

            Clause 5318 - Whatrsquos in

            35

            Urban cooling Reduce heat radiation from buildings and hard surfaces throughbull Shade trees in car parks or over driveways bull More open space and treesbull Green roofsbull Green walls

            36

            Optionsbull Passive irrigationbull Integrate assets into

            communal open spacebull Tree pits and permeable

            paving (driveways and carpark)

            bull Stormwater harvesting (major developments only)

            Infiltration habitat amenity

            37

            Control harmful chemicals

            Optionsbull Careful layoutbull Consider alternative less harmful substancesbull Roofed designated storage areabull Internal drainage design to sewer or a treatment devicebull Bunding

            38

            Standard W3Standard W3 requires that application describe how the site will be managed prior to and during the construction period The application should set out requirements for managingbull Erosion and sedimentbull Stormwaterbull Litter concrete and other construction wastesbull Chemical contamination

            Buildings and works - Site management standard

            39

            Site management

            40

            Planning Advisory Note No 75

            Implications for industry

            Kate MatthewsStormwater Victoria

            1 Development proponents- Developers- Consultants (engineers stormwater specialists and planners)- Council (when developing public land lt$1 million)

            2 Development assessors- Council statutory planners- Council internal referrals (engineering assets ESD stormwater officers)

            3 Strategy- Council strategic planners

            4 Melbourne Water

            Whorsquos affected

            43

            What are the implications

            bull BPEM - Itrsquos not just subdivisions any more

            bull Cost ndash offset or assetbull Early planning and integration ndash more

            work up frontbull Not just engineeringbull Varying Council skills and experience

            Development Proponents

            44

            If already have a local policy for WSUDESD no real change

            If notbull Workload and resourcingbull Increased detail and technical

            contentbull Administrative arrangements ndash

            referrals permit conditions ndashmake sure you make 60 stat days

            bull Applicant pressure ndash what do you want

            bull Assets

            Development Assessors

            45

            bull Structure plans and rezoning ndashopportunities for localregional approach

            bull IWM and Stormwater Management Plans ndash opportunities for these to be implemented through the controls spatial opportunities

            bull Opportunities for development of Council offset strategies

            Strategy

            Offsets

            bull Developer enters into an agreement with relevant drainage authority to financially contribute to off-site stormwatermanagement in lieu of providing on-site treatment

            bull Already available for residential subdivisions in Melbourne (Clause 56) through MWCs Stormwater Quality Offset scheme

            What are stormwater quality offsets

            X Not drainage contributions (MWC drainage scheme)

            X Not development contributions (DCPICP)

            47

            When to use

            bull Not in MW DSS or growth area where therersquos an existing framework for funding SW treatment

            bull Onsite treatment not practical or desirable

            bull To fund planned localregional stormwater treatment works in that catchment via an existing offset scheme

            bull Council and developer both agree to it

            48

            OffsetsExample ndash Kingston Offset Scheme

            Asset ownership and maintenance

            bull Whorsquos going to own itbull Whorsquos going to maintain itbull How do you maintain itbull How much will it cost

            bull Where is itbull Is maintenance burden

            practical for likely future owners

            bull Whorsquos going to monitor compliance and how

            The detail is in the permit conditions

            Application requirements

            ldquoAn application must be accompanied by details of the proposed stormwater management system including drainage works and retention detention and discharges of stormwater to the drainage systemrdquo ndash Clause 5318

            What does the planning scheme require

            But alsohellipNeed to provide sufficient information to Council which demonstrates that you comply and how you comply with all the other standards ndash eg urban coolinghabitatetc BPEM site management pollutant control infiltration (as relevant to development type

            51

            1 PlansWhat are you doing where is it going and does it fit

            2 ModellingDo you (or can you) meet BPEM requirements

            3 Written response to standardsHow does your proposal comply with the requirements

            52

            Application

            bull Site plan ndash show all assetsWSUD treatments and any IWM features on the site layout plan with everything else

            bull Landscape plan ndash if planting design passive irrigation etc forms part of response to requirements show

            bull Site management plan (depending on Council)

            bull Separate WSUDIWM plan showing all features on a stripped back background

            bull Concept WSUD asset design ndash larger assets only (wetlands bioretention basins sed basin etc) ndash sufficient design detail to confirm spatial requirements

            PlansPermit conditions

            bull Detailed engineering design bull Site Management Plan (final)bull Asset maintenance plan (final)bull Handover arrangements (if public)

            54

            STORM ndash Online toolbull Print out of STORM reportbull Make sure meets 100 or

            morebull Make sure report inputs and

            results match plan

            Modelling - SWQ

            MUSIC ndash Proprietary softwarebull Provide a copy of the model filebull Print out the modelling resultsbull Provide summary of your model

            inputs for each treatment train (iecatchment size impervious treatment area etc)

            bull Provide a print out of the model schematic

            Bonus points bull Provide details of model

            parametersbull Provide results of MUSIC auditor

            run (if using Melbourne Water MUSIC Guidelines)

            56

            Assessment against standards

            bull Say what you have done (or will do) to meet each standardbull Donrsquot forget (if WSUD) details of maintenance and asset

            ownershipbull Where applicable be explicit why yoursquove chosen (or not chosen) to

            respond the way you have Egbull Opportunitiesbull Site constraintsbull Practicaloperational issues bull Brief dot point summary of options analysis if complex

            bull Make sure if it doesnrsquot meet the standard it meets the objectivebull Make sure shown on plan and consistent with modelling and rest of

            documentation

            57

            Resources

            Local stormwaterWSUD policiesBaysideKingstonCaseyMonashMelbourneYarraMoonee ValleyPort PhilipStonningtonHumeCampaspeBass Coast

            Local ESD (including IWM) policies Greater BendigoGreater DandenongHobsons BayWhittleseaWyndhamWhitehorseManninghamMorelandDarebinBanyuleKnoxBrimbank

            Council planning resources

            Application resources ndashexamplesDELWP Practice Note ndashformal guide to the new controlsMoreland ndash application checklists and example plans for a variety of residential developmentsPort Philip ndash compliance guidelines checklist and examplesMoonee Valley ndash checklists and example plans including site management plans Greater Bendigo ndash WSUD kitBayside ndash application guidelines and example plans

            59

            Technical guidelines (modelling design construction)

            Melbourne Water

            STORM calculatorMUSIC auditor - lsquohow torsquo video here

            Melbourne Water technical guidelines page- WSUD asset life cycle costings and model maintenance guidelines- MUSIC guidelines- Stormwater harvesting guidelines- WSUD life cycle costings and

            maintenance guidelines- Design and construction guidelines

            for variety of assetshttpswwwmelbournewatercomauplanning-and-buildingdeveloper-guides-and-resourcesguidelines-drawings-and-checklistsguidelines

            Council

            South-Eastern Growth Council WSUD guidelines ndash note that some individual Councils have their own addendumsMelbournePort PhilipNorth-West Growth Council WSUD guidelines - note that some individual Councils have their own addendumsGreater BendigoMilduraBallaratBaw BawWyndhamMoreland ndash tree pits and raingardens

            60

            IWM

            Example Council IWM strategiesMelbourneCaseyMonashKingston

            Resilient Melbourne ndash IWM information lsquohubrsquoClearwater ndash capacity building and case studiesMelbourne Water ndash funding opportunities for IWM projects

            Stormwater offset schemes

            KingstonGreater GeelongMelbourne Water ndash non scheme contributions

            Site management

            EPA guidelines- management of erosion and sediment

            Next steps and other stormwater initiatives

            Emma Stewart DELWP

            62

            Next steps

            bull Trainingbull The EPArsquos BPEM Reviewbull Offsets policybull Review of STORM bull Building controls

            63

            State Stormwater policies

            64

            Thank you

            • Slide Number 1
            • Slide Number 2
            • History of WSUD
            • History of WSUD
            • Transformational change in urban water
            • Inconsistencies and inequities in our approach to stormwater management
            • Slide Number 8
            • Terms of Reference
            • Improving Stormwater Management Advisory Committee
            • Wide consultation
            • Stakeholder feedback
            • Stakeholder feedback
            • Committee submitted its report in September 2018
            • Committee Recomendations
            • Planning reforms
            • Future policy directions
            • Supporting actions
            • Slide Number 19
            • Government response (to date)
            • Longer term recommendations
            • State-based planning requirements (lsquobeforersquo)
            • State-based planning requirements (lsquoafterrsquo)
            • Development types (volume)
            • Slide Number 25
            • Amendment VC154
            • Whatrsquos in
            • Slide Number 28
            • Key elements of clauses
            • Clause 5318 ndash subdivision
            • Clause 5318 ndash Buildings and works
            • Townhouses - Standard B9
            • Slide Number 33
            • Slide Number 34
            • Slide Number 35
            • Slide Number 36
            • Slide Number 37
            • Buildings and works - Site management standard
            • Site management
            • Planning Advisory Note No 75
            • Slide Number 41
            • Slide Number 42
            • Slide Number 43
            • Slide Number 44
            • Slide Number 45
            • Slide Number 46
            • Slide Number 47
            • Slide Number 48
            • Slide Number 49
            • Slide Number 50
            • Slide Number 51
            • Slide Number 52
            • Slide Number 53
            • Slide Number 54
            • Slide Number 55
            • Slide Number 56
            • Slide Number 57
            • Slide Number 58
            • Slide Number 59
            • Slide Number 60
            • Slide Number 61
            • Next steps
            • State Stormwater policies
            • Slide Number 64

              8

              Government commits to improve stormwater management through planning system reforms

              9

              Terms of Reference

              Part A (core)Specific advice on which types of

              development of those currently not subject to the Statersquos urban runoff management

              objectives should be required to manage their stormwater and the associated reforms

              Part B (future directions) Future policy directions for improving

              stormwater management and strengthening the links between urban water management and the planning and development system

              more broadly

              10

              Improving Stormwater Management Advisory Committee

              Dr Jeremy Cheesman Julie Katz Chris Chesterfield (chair) Sue Porter

              11

              Wide consultation

              6 committee meetings

              6 stakeholder workshops

              46 submissions7 one on ones

              12

              Stakeholder feedback

              bull Consultation indicated widespread support for application of stormwater standards across all development types

              bull Raised a number of implementation issues

              bull Planning system only part of the response

              13

              Stakeholder feedback

              Other feedback

              bull Offsets are useful if they can be designed to provide net benefits and protect sensitive areas

              bull Councils struggle with funding stormwater infrastructure costs

              bull Rolesaccountabilities not well definedbull Skills tools and guidance need investmentbull Community awareness lowbull Support for linking IWM plans to planning system

              14

              Committee submitted its report in September 2018

              15

              The Committees 18 recommendations include

              bull Planning reforms (3) ndash immediate reforms satisfying Part A of the Terms of Reference (ToR)

              bull Future policy directions (7) ndash longer term policy directions satisfying Part B of the ToR

              bull Supporting actions (8) ndash actions to ensure successful implementation of the (Part A) planning reforms satisfying Part B of the ToR

              Committee Recomendations

              16

              Planning reforms

              Rec 1 ndash Expand the stormwater planning provisions (phase 1) That the Victorian Government amend the VPPs to expand the current stormwater management requirements to

              bull commercial subdivisions and developmentsbull industrial subdivisions and developmentsbull public-use developmentsbull multi-dwelling residential subdivisions and developments

              Rec 2 ndash Expand the stormwater planning provisions (phase 2) That subject to further consultation the development of deemed-to-satisfy solutions (rec 12) adequate guidance and tools (recs 13 14 and 15) and offset processes (rec 5) the Victorian Government amend the VPPs to expand the current stormwater management requirements to

              bull single-dwelling developmentsbull extensions over 50 m2

              Rec 3 ndash Insert an IWM clause into the Planning Policy Framework (PPF) That the Victorian Government amend the PPF to embed the concepts of IWM objectives and strategies

              17

              Future policy directions

              Rec 4 ndash Amend the building and plumbing controls

              Rec 5 ndash Establish effective offsetting arrangements

              Rec 6 ndash Clarify local governmentsrsquo roles and responsibilities

              Rec 7 ndash Strengthen compliance requirements

              Rec 8 ndash Determine funding sources for public stormwater infrastructure

              Rec 9 ndash Link water management with urban planning

              Rec 10 ndash Set stronger place-based BPEM stormwater performance objectives

              18

              Rec 11 ndash Strengthen enforcement of stormwater construction requirements

              Rec 12 ndash Prepare deemed-to-satisfy solutions

              Rec 13 ndash Review the STORM and MUSIC tools

              Rec 14 ndash Build technical expertise

              Rec 15 ndash Improve guidance

              Rec 16 ndash Improve awareness of the VPP changes

              Rec 17 ndash Investigate options for rainwater tank maintenance and operation

              Rec 18 ndash Broaden rating systems to include IWM

              Supporting actions

              The new stormwater provisions

              Emma Stewart DELWP

              20

              Government response (to date)

              21

              Government is currently considering the committeersquos longer-term recommendations and is working with key stakeholders to determine the most effective response and pathways for implementation

              Longer term recommendations

              22

              State-based planning requirements (lsquobeforersquo)

              Sourced ELM 2018

              23

              State-based planning requirements (lsquoafterrsquo)

              24

              Development types (volume)

              Future development estimated impervious area 2020-2050

              25

              The nitty grittyhellip

              26

              Amendment VC154

              Victoria Planning Provision changesbull New clause (5318) and changes to an existing clause

              (5503) to expand the stormwater requirements to more development types

              bull New objectives to manage toxicants and encourage broader benefits of stormwater management

              27

              Whatrsquos in

              Applies to an application tobull subdivide land bull construct a building bull construct or carry out works

              In both hellip

              Clause 5318bull commercial zonesbull industrial zonesbull public-use zones

              Clause 5518 bull Construct townhouses

              Whatrsquos out of clause 5318

              bull Developments and subdivisions approved or lodged prior to the amendment

              bull Developments which do not require planning permission

              bull Vicsmart applications

              bull Applications for land within development or incorporated plans approved before the amendment

              bull Extensions and works lt 50m2

              bull Applications after the amendment to amend existing planning permits

              If in doubt ask a planner

              29

              Key elements of clauses

              Industrial commercial applications (Clause 5318)tobull subdivide land bull construct a building bull construct or carry out works

              Stormwater management objectives + standard (W1)

              Stormwater management objectives + standard (W2)+ Site management objectives + standard (W3)

              Decision guidelines

              Same for Clause 5503 (townhouses)

              30

              Clause 5318 ndash subdivision

              Stormwater management standard W1 The stormwater management system should be bull Designed and managed in accordance with the requirements and

              to the satisfaction of the relevant drainage authoritybull Designed and managed in accordance with the requirements and

              to the satisfaction of the water authority where reuse of stormwater is proposed

              bull Designed to meet the current best practice performance objectives for stormwater quality as contained in the BPEM

              bull Designed to ensure that flows downstream of the subdivision site are restricted to pre-development levels unless increased flows are approved by the relevant drainage authority and there are no detrimental downstream impacts

              bull Designed to contribute to cooling improving local habitat and providing attractive and enjoyable spaces

              31

              Clause 5318 ndash Buildings and works

              Standard W2The stormwater management system should be designed to

              bull Meet the current best practice performance objectives for stormwater quality as contained in the BPEM

              bull Contribute to cooling improving local habitat and providing attractive and enjoyable spaces

              bull Minimise the impact of chemical pollutants and other toxicants including by but not limited to bunding and covering of roofing of storage loading and work areas

              32

              Townhouses - Standard B9

              Clause 5503 ndash Permeability and stormwater management objectives and standard B9

              Objectivesbull Similar to 5318 (including the cooling liveability

              objective)bull gt20 perviousness objective (unchanged)

              Standardbull NEW - cooling liveability objectivebull NEW ndash requirement to meet BPEM

              What does this all mean

              34

              Clause 5318 - Whatrsquos in

              35

              Urban cooling Reduce heat radiation from buildings and hard surfaces throughbull Shade trees in car parks or over driveways bull More open space and treesbull Green roofsbull Green walls

              36

              Optionsbull Passive irrigationbull Integrate assets into

              communal open spacebull Tree pits and permeable

              paving (driveways and carpark)

              bull Stormwater harvesting (major developments only)

              Infiltration habitat amenity

              37

              Control harmful chemicals

              Optionsbull Careful layoutbull Consider alternative less harmful substancesbull Roofed designated storage areabull Internal drainage design to sewer or a treatment devicebull Bunding

              38

              Standard W3Standard W3 requires that application describe how the site will be managed prior to and during the construction period The application should set out requirements for managingbull Erosion and sedimentbull Stormwaterbull Litter concrete and other construction wastesbull Chemical contamination

              Buildings and works - Site management standard

              39

              Site management

              40

              Planning Advisory Note No 75

              Implications for industry

              Kate MatthewsStormwater Victoria

              1 Development proponents- Developers- Consultants (engineers stormwater specialists and planners)- Council (when developing public land lt$1 million)

              2 Development assessors- Council statutory planners- Council internal referrals (engineering assets ESD stormwater officers)

              3 Strategy- Council strategic planners

              4 Melbourne Water

              Whorsquos affected

              43

              What are the implications

              bull BPEM - Itrsquos not just subdivisions any more

              bull Cost ndash offset or assetbull Early planning and integration ndash more

              work up frontbull Not just engineeringbull Varying Council skills and experience

              Development Proponents

              44

              If already have a local policy for WSUDESD no real change

              If notbull Workload and resourcingbull Increased detail and technical

              contentbull Administrative arrangements ndash

              referrals permit conditions ndashmake sure you make 60 stat days

              bull Applicant pressure ndash what do you want

              bull Assets

              Development Assessors

              45

              bull Structure plans and rezoning ndashopportunities for localregional approach

              bull IWM and Stormwater Management Plans ndash opportunities for these to be implemented through the controls spatial opportunities

              bull Opportunities for development of Council offset strategies

              Strategy

              Offsets

              bull Developer enters into an agreement with relevant drainage authority to financially contribute to off-site stormwatermanagement in lieu of providing on-site treatment

              bull Already available for residential subdivisions in Melbourne (Clause 56) through MWCs Stormwater Quality Offset scheme

              What are stormwater quality offsets

              X Not drainage contributions (MWC drainage scheme)

              X Not development contributions (DCPICP)

              47

              When to use

              bull Not in MW DSS or growth area where therersquos an existing framework for funding SW treatment

              bull Onsite treatment not practical or desirable

              bull To fund planned localregional stormwater treatment works in that catchment via an existing offset scheme

              bull Council and developer both agree to it

              48

              OffsetsExample ndash Kingston Offset Scheme

              Asset ownership and maintenance

              bull Whorsquos going to own itbull Whorsquos going to maintain itbull How do you maintain itbull How much will it cost

              bull Where is itbull Is maintenance burden

              practical for likely future owners

              bull Whorsquos going to monitor compliance and how

              The detail is in the permit conditions

              Application requirements

              ldquoAn application must be accompanied by details of the proposed stormwater management system including drainage works and retention detention and discharges of stormwater to the drainage systemrdquo ndash Clause 5318

              What does the planning scheme require

              But alsohellipNeed to provide sufficient information to Council which demonstrates that you comply and how you comply with all the other standards ndash eg urban coolinghabitatetc BPEM site management pollutant control infiltration (as relevant to development type

              51

              1 PlansWhat are you doing where is it going and does it fit

              2 ModellingDo you (or can you) meet BPEM requirements

              3 Written response to standardsHow does your proposal comply with the requirements

              52

              Application

              bull Site plan ndash show all assetsWSUD treatments and any IWM features on the site layout plan with everything else

              bull Landscape plan ndash if planting design passive irrigation etc forms part of response to requirements show

              bull Site management plan (depending on Council)

              bull Separate WSUDIWM plan showing all features on a stripped back background

              bull Concept WSUD asset design ndash larger assets only (wetlands bioretention basins sed basin etc) ndash sufficient design detail to confirm spatial requirements

              PlansPermit conditions

              bull Detailed engineering design bull Site Management Plan (final)bull Asset maintenance plan (final)bull Handover arrangements (if public)

              54

              STORM ndash Online toolbull Print out of STORM reportbull Make sure meets 100 or

              morebull Make sure report inputs and

              results match plan

              Modelling - SWQ

              MUSIC ndash Proprietary softwarebull Provide a copy of the model filebull Print out the modelling resultsbull Provide summary of your model

              inputs for each treatment train (iecatchment size impervious treatment area etc)

              bull Provide a print out of the model schematic

              Bonus points bull Provide details of model

              parametersbull Provide results of MUSIC auditor

              run (if using Melbourne Water MUSIC Guidelines)

              56

              Assessment against standards

              bull Say what you have done (or will do) to meet each standardbull Donrsquot forget (if WSUD) details of maintenance and asset

              ownershipbull Where applicable be explicit why yoursquove chosen (or not chosen) to

              respond the way you have Egbull Opportunitiesbull Site constraintsbull Practicaloperational issues bull Brief dot point summary of options analysis if complex

              bull Make sure if it doesnrsquot meet the standard it meets the objectivebull Make sure shown on plan and consistent with modelling and rest of

              documentation

              57

              Resources

              Local stormwaterWSUD policiesBaysideKingstonCaseyMonashMelbourneYarraMoonee ValleyPort PhilipStonningtonHumeCampaspeBass Coast

              Local ESD (including IWM) policies Greater BendigoGreater DandenongHobsons BayWhittleseaWyndhamWhitehorseManninghamMorelandDarebinBanyuleKnoxBrimbank

              Council planning resources

              Application resources ndashexamplesDELWP Practice Note ndashformal guide to the new controlsMoreland ndash application checklists and example plans for a variety of residential developmentsPort Philip ndash compliance guidelines checklist and examplesMoonee Valley ndash checklists and example plans including site management plans Greater Bendigo ndash WSUD kitBayside ndash application guidelines and example plans

              59

              Technical guidelines (modelling design construction)

              Melbourne Water

              STORM calculatorMUSIC auditor - lsquohow torsquo video here

              Melbourne Water technical guidelines page- WSUD asset life cycle costings and model maintenance guidelines- MUSIC guidelines- Stormwater harvesting guidelines- WSUD life cycle costings and

              maintenance guidelines- Design and construction guidelines

              for variety of assetshttpswwwmelbournewatercomauplanning-and-buildingdeveloper-guides-and-resourcesguidelines-drawings-and-checklistsguidelines

              Council

              South-Eastern Growth Council WSUD guidelines ndash note that some individual Councils have their own addendumsMelbournePort PhilipNorth-West Growth Council WSUD guidelines - note that some individual Councils have their own addendumsGreater BendigoMilduraBallaratBaw BawWyndhamMoreland ndash tree pits and raingardens

              60

              IWM

              Example Council IWM strategiesMelbourneCaseyMonashKingston

              Resilient Melbourne ndash IWM information lsquohubrsquoClearwater ndash capacity building and case studiesMelbourne Water ndash funding opportunities for IWM projects

              Stormwater offset schemes

              KingstonGreater GeelongMelbourne Water ndash non scheme contributions

              Site management

              EPA guidelines- management of erosion and sediment

              Next steps and other stormwater initiatives

              Emma Stewart DELWP

              62

              Next steps

              bull Trainingbull The EPArsquos BPEM Reviewbull Offsets policybull Review of STORM bull Building controls

              63

              State Stormwater policies

              64

              Thank you

              • Slide Number 1
              • Slide Number 2
              • History of WSUD
              • History of WSUD
              • Transformational change in urban water
              • Inconsistencies and inequities in our approach to stormwater management
              • Slide Number 8
              • Terms of Reference
              • Improving Stormwater Management Advisory Committee
              • Wide consultation
              • Stakeholder feedback
              • Stakeholder feedback
              • Committee submitted its report in September 2018
              • Committee Recomendations
              • Planning reforms
              • Future policy directions
              • Supporting actions
              • Slide Number 19
              • Government response (to date)
              • Longer term recommendations
              • State-based planning requirements (lsquobeforersquo)
              • State-based planning requirements (lsquoafterrsquo)
              • Development types (volume)
              • Slide Number 25
              • Amendment VC154
              • Whatrsquos in
              • Slide Number 28
              • Key elements of clauses
              • Clause 5318 ndash subdivision
              • Clause 5318 ndash Buildings and works
              • Townhouses - Standard B9
              • Slide Number 33
              • Slide Number 34
              • Slide Number 35
              • Slide Number 36
              • Slide Number 37
              • Buildings and works - Site management standard
              • Site management
              • Planning Advisory Note No 75
              • Slide Number 41
              • Slide Number 42
              • Slide Number 43
              • Slide Number 44
              • Slide Number 45
              • Slide Number 46
              • Slide Number 47
              • Slide Number 48
              • Slide Number 49
              • Slide Number 50
              • Slide Number 51
              • Slide Number 52
              • Slide Number 53
              • Slide Number 54
              • Slide Number 55
              • Slide Number 56
              • Slide Number 57
              • Slide Number 58
              • Slide Number 59
              • Slide Number 60
              • Slide Number 61
              • Next steps
              • State Stormwater policies
              • Slide Number 64

                9

                Terms of Reference

                Part A (core)Specific advice on which types of

                development of those currently not subject to the Statersquos urban runoff management

                objectives should be required to manage their stormwater and the associated reforms

                Part B (future directions) Future policy directions for improving

                stormwater management and strengthening the links between urban water management and the planning and development system

                more broadly

                10

                Improving Stormwater Management Advisory Committee

                Dr Jeremy Cheesman Julie Katz Chris Chesterfield (chair) Sue Porter

                11

                Wide consultation

                6 committee meetings

                6 stakeholder workshops

                46 submissions7 one on ones

                12

                Stakeholder feedback

                bull Consultation indicated widespread support for application of stormwater standards across all development types

                bull Raised a number of implementation issues

                bull Planning system only part of the response

                13

                Stakeholder feedback

                Other feedback

                bull Offsets are useful if they can be designed to provide net benefits and protect sensitive areas

                bull Councils struggle with funding stormwater infrastructure costs

                bull Rolesaccountabilities not well definedbull Skills tools and guidance need investmentbull Community awareness lowbull Support for linking IWM plans to planning system

                14

                Committee submitted its report in September 2018

                15

                The Committees 18 recommendations include

                bull Planning reforms (3) ndash immediate reforms satisfying Part A of the Terms of Reference (ToR)

                bull Future policy directions (7) ndash longer term policy directions satisfying Part B of the ToR

                bull Supporting actions (8) ndash actions to ensure successful implementation of the (Part A) planning reforms satisfying Part B of the ToR

                Committee Recomendations

                16

                Planning reforms

                Rec 1 ndash Expand the stormwater planning provisions (phase 1) That the Victorian Government amend the VPPs to expand the current stormwater management requirements to

                bull commercial subdivisions and developmentsbull industrial subdivisions and developmentsbull public-use developmentsbull multi-dwelling residential subdivisions and developments

                Rec 2 ndash Expand the stormwater planning provisions (phase 2) That subject to further consultation the development of deemed-to-satisfy solutions (rec 12) adequate guidance and tools (recs 13 14 and 15) and offset processes (rec 5) the Victorian Government amend the VPPs to expand the current stormwater management requirements to

                bull single-dwelling developmentsbull extensions over 50 m2

                Rec 3 ndash Insert an IWM clause into the Planning Policy Framework (PPF) That the Victorian Government amend the PPF to embed the concepts of IWM objectives and strategies

                17

                Future policy directions

                Rec 4 ndash Amend the building and plumbing controls

                Rec 5 ndash Establish effective offsetting arrangements

                Rec 6 ndash Clarify local governmentsrsquo roles and responsibilities

                Rec 7 ndash Strengthen compliance requirements

                Rec 8 ndash Determine funding sources for public stormwater infrastructure

                Rec 9 ndash Link water management with urban planning

                Rec 10 ndash Set stronger place-based BPEM stormwater performance objectives

                18

                Rec 11 ndash Strengthen enforcement of stormwater construction requirements

                Rec 12 ndash Prepare deemed-to-satisfy solutions

                Rec 13 ndash Review the STORM and MUSIC tools

                Rec 14 ndash Build technical expertise

                Rec 15 ndash Improve guidance

                Rec 16 ndash Improve awareness of the VPP changes

                Rec 17 ndash Investigate options for rainwater tank maintenance and operation

                Rec 18 ndash Broaden rating systems to include IWM

                Supporting actions

                The new stormwater provisions

                Emma Stewart DELWP

                20

                Government response (to date)

                21

                Government is currently considering the committeersquos longer-term recommendations and is working with key stakeholders to determine the most effective response and pathways for implementation

                Longer term recommendations

                22

                State-based planning requirements (lsquobeforersquo)

                Sourced ELM 2018

                23

                State-based planning requirements (lsquoafterrsquo)

                24

                Development types (volume)

                Future development estimated impervious area 2020-2050

                25

                The nitty grittyhellip

                26

                Amendment VC154

                Victoria Planning Provision changesbull New clause (5318) and changes to an existing clause

                (5503) to expand the stormwater requirements to more development types

                bull New objectives to manage toxicants and encourage broader benefits of stormwater management

                27

                Whatrsquos in

                Applies to an application tobull subdivide land bull construct a building bull construct or carry out works

                In both hellip

                Clause 5318bull commercial zonesbull industrial zonesbull public-use zones

                Clause 5518 bull Construct townhouses

                Whatrsquos out of clause 5318

                bull Developments and subdivisions approved or lodged prior to the amendment

                bull Developments which do not require planning permission

                bull Vicsmart applications

                bull Applications for land within development or incorporated plans approved before the amendment

                bull Extensions and works lt 50m2

                bull Applications after the amendment to amend existing planning permits

                If in doubt ask a planner

                29

                Key elements of clauses

                Industrial commercial applications (Clause 5318)tobull subdivide land bull construct a building bull construct or carry out works

                Stormwater management objectives + standard (W1)

                Stormwater management objectives + standard (W2)+ Site management objectives + standard (W3)

                Decision guidelines

                Same for Clause 5503 (townhouses)

                30

                Clause 5318 ndash subdivision

                Stormwater management standard W1 The stormwater management system should be bull Designed and managed in accordance with the requirements and

                to the satisfaction of the relevant drainage authoritybull Designed and managed in accordance with the requirements and

                to the satisfaction of the water authority where reuse of stormwater is proposed

                bull Designed to meet the current best practice performance objectives for stormwater quality as contained in the BPEM

                bull Designed to ensure that flows downstream of the subdivision site are restricted to pre-development levels unless increased flows are approved by the relevant drainage authority and there are no detrimental downstream impacts

                bull Designed to contribute to cooling improving local habitat and providing attractive and enjoyable spaces

                31

                Clause 5318 ndash Buildings and works

                Standard W2The stormwater management system should be designed to

                bull Meet the current best practice performance objectives for stormwater quality as contained in the BPEM

                bull Contribute to cooling improving local habitat and providing attractive and enjoyable spaces

                bull Minimise the impact of chemical pollutants and other toxicants including by but not limited to bunding and covering of roofing of storage loading and work areas

                32

                Townhouses - Standard B9

                Clause 5503 ndash Permeability and stormwater management objectives and standard B9

                Objectivesbull Similar to 5318 (including the cooling liveability

                objective)bull gt20 perviousness objective (unchanged)

                Standardbull NEW - cooling liveability objectivebull NEW ndash requirement to meet BPEM

                What does this all mean

                34

                Clause 5318 - Whatrsquos in

                35

                Urban cooling Reduce heat radiation from buildings and hard surfaces throughbull Shade trees in car parks or over driveways bull More open space and treesbull Green roofsbull Green walls

                36

                Optionsbull Passive irrigationbull Integrate assets into

                communal open spacebull Tree pits and permeable

                paving (driveways and carpark)

                bull Stormwater harvesting (major developments only)

                Infiltration habitat amenity

                37

                Control harmful chemicals

                Optionsbull Careful layoutbull Consider alternative less harmful substancesbull Roofed designated storage areabull Internal drainage design to sewer or a treatment devicebull Bunding

                38

                Standard W3Standard W3 requires that application describe how the site will be managed prior to and during the construction period The application should set out requirements for managingbull Erosion and sedimentbull Stormwaterbull Litter concrete and other construction wastesbull Chemical contamination

                Buildings and works - Site management standard

                39

                Site management

                40

                Planning Advisory Note No 75

                Implications for industry

                Kate MatthewsStormwater Victoria

                1 Development proponents- Developers- Consultants (engineers stormwater specialists and planners)- Council (when developing public land lt$1 million)

                2 Development assessors- Council statutory planners- Council internal referrals (engineering assets ESD stormwater officers)

                3 Strategy- Council strategic planners

                4 Melbourne Water

                Whorsquos affected

                43

                What are the implications

                bull BPEM - Itrsquos not just subdivisions any more

                bull Cost ndash offset or assetbull Early planning and integration ndash more

                work up frontbull Not just engineeringbull Varying Council skills and experience

                Development Proponents

                44

                If already have a local policy for WSUDESD no real change

                If notbull Workload and resourcingbull Increased detail and technical

                contentbull Administrative arrangements ndash

                referrals permit conditions ndashmake sure you make 60 stat days

                bull Applicant pressure ndash what do you want

                bull Assets

                Development Assessors

                45

                bull Structure plans and rezoning ndashopportunities for localregional approach

                bull IWM and Stormwater Management Plans ndash opportunities for these to be implemented through the controls spatial opportunities

                bull Opportunities for development of Council offset strategies

                Strategy

                Offsets

                bull Developer enters into an agreement with relevant drainage authority to financially contribute to off-site stormwatermanagement in lieu of providing on-site treatment

                bull Already available for residential subdivisions in Melbourne (Clause 56) through MWCs Stormwater Quality Offset scheme

                What are stormwater quality offsets

                X Not drainage contributions (MWC drainage scheme)

                X Not development contributions (DCPICP)

                47

                When to use

                bull Not in MW DSS or growth area where therersquos an existing framework for funding SW treatment

                bull Onsite treatment not practical or desirable

                bull To fund planned localregional stormwater treatment works in that catchment via an existing offset scheme

                bull Council and developer both agree to it

                48

                OffsetsExample ndash Kingston Offset Scheme

                Asset ownership and maintenance

                bull Whorsquos going to own itbull Whorsquos going to maintain itbull How do you maintain itbull How much will it cost

                bull Where is itbull Is maintenance burden

                practical for likely future owners

                bull Whorsquos going to monitor compliance and how

                The detail is in the permit conditions

                Application requirements

                ldquoAn application must be accompanied by details of the proposed stormwater management system including drainage works and retention detention and discharges of stormwater to the drainage systemrdquo ndash Clause 5318

                What does the planning scheme require

                But alsohellipNeed to provide sufficient information to Council which demonstrates that you comply and how you comply with all the other standards ndash eg urban coolinghabitatetc BPEM site management pollutant control infiltration (as relevant to development type

                51

                1 PlansWhat are you doing where is it going and does it fit

                2 ModellingDo you (or can you) meet BPEM requirements

                3 Written response to standardsHow does your proposal comply with the requirements

                52

                Application

                bull Site plan ndash show all assetsWSUD treatments and any IWM features on the site layout plan with everything else

                bull Landscape plan ndash if planting design passive irrigation etc forms part of response to requirements show

                bull Site management plan (depending on Council)

                bull Separate WSUDIWM plan showing all features on a stripped back background

                bull Concept WSUD asset design ndash larger assets only (wetlands bioretention basins sed basin etc) ndash sufficient design detail to confirm spatial requirements

                PlansPermit conditions

                bull Detailed engineering design bull Site Management Plan (final)bull Asset maintenance plan (final)bull Handover arrangements (if public)

                54

                STORM ndash Online toolbull Print out of STORM reportbull Make sure meets 100 or

                morebull Make sure report inputs and

                results match plan

                Modelling - SWQ

                MUSIC ndash Proprietary softwarebull Provide a copy of the model filebull Print out the modelling resultsbull Provide summary of your model

                inputs for each treatment train (iecatchment size impervious treatment area etc)

                bull Provide a print out of the model schematic

                Bonus points bull Provide details of model

                parametersbull Provide results of MUSIC auditor

                run (if using Melbourne Water MUSIC Guidelines)

                56

                Assessment against standards

                bull Say what you have done (or will do) to meet each standardbull Donrsquot forget (if WSUD) details of maintenance and asset

                ownershipbull Where applicable be explicit why yoursquove chosen (or not chosen) to

                respond the way you have Egbull Opportunitiesbull Site constraintsbull Practicaloperational issues bull Brief dot point summary of options analysis if complex

                bull Make sure if it doesnrsquot meet the standard it meets the objectivebull Make sure shown on plan and consistent with modelling and rest of

                documentation

                57

                Resources

                Local stormwaterWSUD policiesBaysideKingstonCaseyMonashMelbourneYarraMoonee ValleyPort PhilipStonningtonHumeCampaspeBass Coast

                Local ESD (including IWM) policies Greater BendigoGreater DandenongHobsons BayWhittleseaWyndhamWhitehorseManninghamMorelandDarebinBanyuleKnoxBrimbank

                Council planning resources

                Application resources ndashexamplesDELWP Practice Note ndashformal guide to the new controlsMoreland ndash application checklists and example plans for a variety of residential developmentsPort Philip ndash compliance guidelines checklist and examplesMoonee Valley ndash checklists and example plans including site management plans Greater Bendigo ndash WSUD kitBayside ndash application guidelines and example plans

                59

                Technical guidelines (modelling design construction)

                Melbourne Water

                STORM calculatorMUSIC auditor - lsquohow torsquo video here

                Melbourne Water technical guidelines page- WSUD asset life cycle costings and model maintenance guidelines- MUSIC guidelines- Stormwater harvesting guidelines- WSUD life cycle costings and

                maintenance guidelines- Design and construction guidelines

                for variety of assetshttpswwwmelbournewatercomauplanning-and-buildingdeveloper-guides-and-resourcesguidelines-drawings-and-checklistsguidelines

                Council

                South-Eastern Growth Council WSUD guidelines ndash note that some individual Councils have their own addendumsMelbournePort PhilipNorth-West Growth Council WSUD guidelines - note that some individual Councils have their own addendumsGreater BendigoMilduraBallaratBaw BawWyndhamMoreland ndash tree pits and raingardens

                60

                IWM

                Example Council IWM strategiesMelbourneCaseyMonashKingston

                Resilient Melbourne ndash IWM information lsquohubrsquoClearwater ndash capacity building and case studiesMelbourne Water ndash funding opportunities for IWM projects

                Stormwater offset schemes

                KingstonGreater GeelongMelbourne Water ndash non scheme contributions

                Site management

                EPA guidelines- management of erosion and sediment

                Next steps and other stormwater initiatives

                Emma Stewart DELWP

                62

                Next steps

                bull Trainingbull The EPArsquos BPEM Reviewbull Offsets policybull Review of STORM bull Building controls

                63

                State Stormwater policies

                64

                Thank you

                • Slide Number 1
                • Slide Number 2
                • History of WSUD
                • History of WSUD
                • Transformational change in urban water
                • Inconsistencies and inequities in our approach to stormwater management
                • Slide Number 8
                • Terms of Reference
                • Improving Stormwater Management Advisory Committee
                • Wide consultation
                • Stakeholder feedback
                • Stakeholder feedback
                • Committee submitted its report in September 2018
                • Committee Recomendations
                • Planning reforms
                • Future policy directions
                • Supporting actions
                • Slide Number 19
                • Government response (to date)
                • Longer term recommendations
                • State-based planning requirements (lsquobeforersquo)
                • State-based planning requirements (lsquoafterrsquo)
                • Development types (volume)
                • Slide Number 25
                • Amendment VC154
                • Whatrsquos in
                • Slide Number 28
                • Key elements of clauses
                • Clause 5318 ndash subdivision
                • Clause 5318 ndash Buildings and works
                • Townhouses - Standard B9
                • Slide Number 33
                • Slide Number 34
                • Slide Number 35
                • Slide Number 36
                • Slide Number 37
                • Buildings and works - Site management standard
                • Site management
                • Planning Advisory Note No 75
                • Slide Number 41
                • Slide Number 42
                • Slide Number 43
                • Slide Number 44
                • Slide Number 45
                • Slide Number 46
                • Slide Number 47
                • Slide Number 48
                • Slide Number 49
                • Slide Number 50
                • Slide Number 51
                • Slide Number 52
                • Slide Number 53
                • Slide Number 54
                • Slide Number 55
                • Slide Number 56
                • Slide Number 57
                • Slide Number 58
                • Slide Number 59
                • Slide Number 60
                • Slide Number 61
                • Next steps
                • State Stormwater policies
                • Slide Number 64

                  10

                  Improving Stormwater Management Advisory Committee

                  Dr Jeremy Cheesman Julie Katz Chris Chesterfield (chair) Sue Porter

                  11

                  Wide consultation

                  6 committee meetings

                  6 stakeholder workshops

                  46 submissions7 one on ones

                  12

                  Stakeholder feedback

                  bull Consultation indicated widespread support for application of stormwater standards across all development types

                  bull Raised a number of implementation issues

                  bull Planning system only part of the response

                  13

                  Stakeholder feedback

                  Other feedback

                  bull Offsets are useful if they can be designed to provide net benefits and protect sensitive areas

                  bull Councils struggle with funding stormwater infrastructure costs

                  bull Rolesaccountabilities not well definedbull Skills tools and guidance need investmentbull Community awareness lowbull Support for linking IWM plans to planning system

                  14

                  Committee submitted its report in September 2018

                  15

                  The Committees 18 recommendations include

                  bull Planning reforms (3) ndash immediate reforms satisfying Part A of the Terms of Reference (ToR)

                  bull Future policy directions (7) ndash longer term policy directions satisfying Part B of the ToR

                  bull Supporting actions (8) ndash actions to ensure successful implementation of the (Part A) planning reforms satisfying Part B of the ToR

                  Committee Recomendations

                  16

                  Planning reforms

                  Rec 1 ndash Expand the stormwater planning provisions (phase 1) That the Victorian Government amend the VPPs to expand the current stormwater management requirements to

                  bull commercial subdivisions and developmentsbull industrial subdivisions and developmentsbull public-use developmentsbull multi-dwelling residential subdivisions and developments

                  Rec 2 ndash Expand the stormwater planning provisions (phase 2) That subject to further consultation the development of deemed-to-satisfy solutions (rec 12) adequate guidance and tools (recs 13 14 and 15) and offset processes (rec 5) the Victorian Government amend the VPPs to expand the current stormwater management requirements to

                  bull single-dwelling developmentsbull extensions over 50 m2

                  Rec 3 ndash Insert an IWM clause into the Planning Policy Framework (PPF) That the Victorian Government amend the PPF to embed the concepts of IWM objectives and strategies

                  17

                  Future policy directions

                  Rec 4 ndash Amend the building and plumbing controls

                  Rec 5 ndash Establish effective offsetting arrangements

                  Rec 6 ndash Clarify local governmentsrsquo roles and responsibilities

                  Rec 7 ndash Strengthen compliance requirements

                  Rec 8 ndash Determine funding sources for public stormwater infrastructure

                  Rec 9 ndash Link water management with urban planning

                  Rec 10 ndash Set stronger place-based BPEM stormwater performance objectives

                  18

                  Rec 11 ndash Strengthen enforcement of stormwater construction requirements

                  Rec 12 ndash Prepare deemed-to-satisfy solutions

                  Rec 13 ndash Review the STORM and MUSIC tools

                  Rec 14 ndash Build technical expertise

                  Rec 15 ndash Improve guidance

                  Rec 16 ndash Improve awareness of the VPP changes

                  Rec 17 ndash Investigate options for rainwater tank maintenance and operation

                  Rec 18 ndash Broaden rating systems to include IWM

                  Supporting actions

                  The new stormwater provisions

                  Emma Stewart DELWP

                  20

                  Government response (to date)

                  21

                  Government is currently considering the committeersquos longer-term recommendations and is working with key stakeholders to determine the most effective response and pathways for implementation

                  Longer term recommendations

                  22

                  State-based planning requirements (lsquobeforersquo)

                  Sourced ELM 2018

                  23

                  State-based planning requirements (lsquoafterrsquo)

                  24

                  Development types (volume)

                  Future development estimated impervious area 2020-2050

                  25

                  The nitty grittyhellip

                  26

                  Amendment VC154

                  Victoria Planning Provision changesbull New clause (5318) and changes to an existing clause

                  (5503) to expand the stormwater requirements to more development types

                  bull New objectives to manage toxicants and encourage broader benefits of stormwater management

                  27

                  Whatrsquos in

                  Applies to an application tobull subdivide land bull construct a building bull construct or carry out works

                  In both hellip

                  Clause 5318bull commercial zonesbull industrial zonesbull public-use zones

                  Clause 5518 bull Construct townhouses

                  Whatrsquos out of clause 5318

                  bull Developments and subdivisions approved or lodged prior to the amendment

                  bull Developments which do not require planning permission

                  bull Vicsmart applications

                  bull Applications for land within development or incorporated plans approved before the amendment

                  bull Extensions and works lt 50m2

                  bull Applications after the amendment to amend existing planning permits

                  If in doubt ask a planner

                  29

                  Key elements of clauses

                  Industrial commercial applications (Clause 5318)tobull subdivide land bull construct a building bull construct or carry out works

                  Stormwater management objectives + standard (W1)

                  Stormwater management objectives + standard (W2)+ Site management objectives + standard (W3)

                  Decision guidelines

                  Same for Clause 5503 (townhouses)

                  30

                  Clause 5318 ndash subdivision

                  Stormwater management standard W1 The stormwater management system should be bull Designed and managed in accordance with the requirements and

                  to the satisfaction of the relevant drainage authoritybull Designed and managed in accordance with the requirements and

                  to the satisfaction of the water authority where reuse of stormwater is proposed

                  bull Designed to meet the current best practice performance objectives for stormwater quality as contained in the BPEM

                  bull Designed to ensure that flows downstream of the subdivision site are restricted to pre-development levels unless increased flows are approved by the relevant drainage authority and there are no detrimental downstream impacts

                  bull Designed to contribute to cooling improving local habitat and providing attractive and enjoyable spaces

                  31

                  Clause 5318 ndash Buildings and works

                  Standard W2The stormwater management system should be designed to

                  bull Meet the current best practice performance objectives for stormwater quality as contained in the BPEM

                  bull Contribute to cooling improving local habitat and providing attractive and enjoyable spaces

                  bull Minimise the impact of chemical pollutants and other toxicants including by but not limited to bunding and covering of roofing of storage loading and work areas

                  32

                  Townhouses - Standard B9

                  Clause 5503 ndash Permeability and stormwater management objectives and standard B9

                  Objectivesbull Similar to 5318 (including the cooling liveability

                  objective)bull gt20 perviousness objective (unchanged)

                  Standardbull NEW - cooling liveability objectivebull NEW ndash requirement to meet BPEM

                  What does this all mean

                  34

                  Clause 5318 - Whatrsquos in

                  35

                  Urban cooling Reduce heat radiation from buildings and hard surfaces throughbull Shade trees in car parks or over driveways bull More open space and treesbull Green roofsbull Green walls

                  36

                  Optionsbull Passive irrigationbull Integrate assets into

                  communal open spacebull Tree pits and permeable

                  paving (driveways and carpark)

                  bull Stormwater harvesting (major developments only)

                  Infiltration habitat amenity

                  37

                  Control harmful chemicals

                  Optionsbull Careful layoutbull Consider alternative less harmful substancesbull Roofed designated storage areabull Internal drainage design to sewer or a treatment devicebull Bunding

                  38

                  Standard W3Standard W3 requires that application describe how the site will be managed prior to and during the construction period The application should set out requirements for managingbull Erosion and sedimentbull Stormwaterbull Litter concrete and other construction wastesbull Chemical contamination

                  Buildings and works - Site management standard

                  39

                  Site management

                  40

                  Planning Advisory Note No 75

                  Implications for industry

                  Kate MatthewsStormwater Victoria

                  1 Development proponents- Developers- Consultants (engineers stormwater specialists and planners)- Council (when developing public land lt$1 million)

                  2 Development assessors- Council statutory planners- Council internal referrals (engineering assets ESD stormwater officers)

                  3 Strategy- Council strategic planners

                  4 Melbourne Water

                  Whorsquos affected

                  43

                  What are the implications

                  bull BPEM - Itrsquos not just subdivisions any more

                  bull Cost ndash offset or assetbull Early planning and integration ndash more

                  work up frontbull Not just engineeringbull Varying Council skills and experience

                  Development Proponents

                  44

                  If already have a local policy for WSUDESD no real change

                  If notbull Workload and resourcingbull Increased detail and technical

                  contentbull Administrative arrangements ndash

                  referrals permit conditions ndashmake sure you make 60 stat days

                  bull Applicant pressure ndash what do you want

                  bull Assets

                  Development Assessors

                  45

                  bull Structure plans and rezoning ndashopportunities for localregional approach

                  bull IWM and Stormwater Management Plans ndash opportunities for these to be implemented through the controls spatial opportunities

                  bull Opportunities for development of Council offset strategies

                  Strategy

                  Offsets

                  bull Developer enters into an agreement with relevant drainage authority to financially contribute to off-site stormwatermanagement in lieu of providing on-site treatment

                  bull Already available for residential subdivisions in Melbourne (Clause 56) through MWCs Stormwater Quality Offset scheme

                  What are stormwater quality offsets

                  X Not drainage contributions (MWC drainage scheme)

                  X Not development contributions (DCPICP)

                  47

                  When to use

                  bull Not in MW DSS or growth area where therersquos an existing framework for funding SW treatment

                  bull Onsite treatment not practical or desirable

                  bull To fund planned localregional stormwater treatment works in that catchment via an existing offset scheme

                  bull Council and developer both agree to it

                  48

                  OffsetsExample ndash Kingston Offset Scheme

                  Asset ownership and maintenance

                  bull Whorsquos going to own itbull Whorsquos going to maintain itbull How do you maintain itbull How much will it cost

                  bull Where is itbull Is maintenance burden

                  practical for likely future owners

                  bull Whorsquos going to monitor compliance and how

                  The detail is in the permit conditions

                  Application requirements

                  ldquoAn application must be accompanied by details of the proposed stormwater management system including drainage works and retention detention and discharges of stormwater to the drainage systemrdquo ndash Clause 5318

                  What does the planning scheme require

                  But alsohellipNeed to provide sufficient information to Council which demonstrates that you comply and how you comply with all the other standards ndash eg urban coolinghabitatetc BPEM site management pollutant control infiltration (as relevant to development type

                  51

                  1 PlansWhat are you doing where is it going and does it fit

                  2 ModellingDo you (or can you) meet BPEM requirements

                  3 Written response to standardsHow does your proposal comply with the requirements

                  52

                  Application

                  bull Site plan ndash show all assetsWSUD treatments and any IWM features on the site layout plan with everything else

                  bull Landscape plan ndash if planting design passive irrigation etc forms part of response to requirements show

                  bull Site management plan (depending on Council)

                  bull Separate WSUDIWM plan showing all features on a stripped back background

                  bull Concept WSUD asset design ndash larger assets only (wetlands bioretention basins sed basin etc) ndash sufficient design detail to confirm spatial requirements

                  PlansPermit conditions

                  bull Detailed engineering design bull Site Management Plan (final)bull Asset maintenance plan (final)bull Handover arrangements (if public)

                  54

                  STORM ndash Online toolbull Print out of STORM reportbull Make sure meets 100 or

                  morebull Make sure report inputs and

                  results match plan

                  Modelling - SWQ

                  MUSIC ndash Proprietary softwarebull Provide a copy of the model filebull Print out the modelling resultsbull Provide summary of your model

                  inputs for each treatment train (iecatchment size impervious treatment area etc)

                  bull Provide a print out of the model schematic

                  Bonus points bull Provide details of model

                  parametersbull Provide results of MUSIC auditor

                  run (if using Melbourne Water MUSIC Guidelines)

                  56

                  Assessment against standards

                  bull Say what you have done (or will do) to meet each standardbull Donrsquot forget (if WSUD) details of maintenance and asset

                  ownershipbull Where applicable be explicit why yoursquove chosen (or not chosen) to

                  respond the way you have Egbull Opportunitiesbull Site constraintsbull Practicaloperational issues bull Brief dot point summary of options analysis if complex

                  bull Make sure if it doesnrsquot meet the standard it meets the objectivebull Make sure shown on plan and consistent with modelling and rest of

                  documentation

                  57

                  Resources

                  Local stormwaterWSUD policiesBaysideKingstonCaseyMonashMelbourneYarraMoonee ValleyPort PhilipStonningtonHumeCampaspeBass Coast

                  Local ESD (including IWM) policies Greater BendigoGreater DandenongHobsons BayWhittleseaWyndhamWhitehorseManninghamMorelandDarebinBanyuleKnoxBrimbank

                  Council planning resources

                  Application resources ndashexamplesDELWP Practice Note ndashformal guide to the new controlsMoreland ndash application checklists and example plans for a variety of residential developmentsPort Philip ndash compliance guidelines checklist and examplesMoonee Valley ndash checklists and example plans including site management plans Greater Bendigo ndash WSUD kitBayside ndash application guidelines and example plans

                  59

                  Technical guidelines (modelling design construction)

                  Melbourne Water

                  STORM calculatorMUSIC auditor - lsquohow torsquo video here

                  Melbourne Water technical guidelines page- WSUD asset life cycle costings and model maintenance guidelines- MUSIC guidelines- Stormwater harvesting guidelines- WSUD life cycle costings and

                  maintenance guidelines- Design and construction guidelines

                  for variety of assetshttpswwwmelbournewatercomauplanning-and-buildingdeveloper-guides-and-resourcesguidelines-drawings-and-checklistsguidelines

                  Council

                  South-Eastern Growth Council WSUD guidelines ndash note that some individual Councils have their own addendumsMelbournePort PhilipNorth-West Growth Council WSUD guidelines - note that some individual Councils have their own addendumsGreater BendigoMilduraBallaratBaw BawWyndhamMoreland ndash tree pits and raingardens

                  60

                  IWM

                  Example Council IWM strategiesMelbourneCaseyMonashKingston

                  Resilient Melbourne ndash IWM information lsquohubrsquoClearwater ndash capacity building and case studiesMelbourne Water ndash funding opportunities for IWM projects

                  Stormwater offset schemes

                  KingstonGreater GeelongMelbourne Water ndash non scheme contributions

                  Site management

                  EPA guidelines- management of erosion and sediment

                  Next steps and other stormwater initiatives

                  Emma Stewart DELWP

                  62

                  Next steps

                  bull Trainingbull The EPArsquos BPEM Reviewbull Offsets policybull Review of STORM bull Building controls

                  63

                  State Stormwater policies

                  64

                  Thank you

                  • Slide Number 1
                  • Slide Number 2
                  • History of WSUD
                  • History of WSUD
                  • Transformational change in urban water
                  • Inconsistencies and inequities in our approach to stormwater management
                  • Slide Number 8
                  • Terms of Reference
                  • Improving Stormwater Management Advisory Committee
                  • Wide consultation
                  • Stakeholder feedback
                  • Stakeholder feedback
                  • Committee submitted its report in September 2018
                  • Committee Recomendations
                  • Planning reforms
                  • Future policy directions
                  • Supporting actions
                  • Slide Number 19
                  • Government response (to date)
                  • Longer term recommendations
                  • State-based planning requirements (lsquobeforersquo)
                  • State-based planning requirements (lsquoafterrsquo)
                  • Development types (volume)
                  • Slide Number 25
                  • Amendment VC154
                  • Whatrsquos in
                  • Slide Number 28
                  • Key elements of clauses
                  • Clause 5318 ndash subdivision
                  • Clause 5318 ndash Buildings and works
                  • Townhouses - Standard B9
                  • Slide Number 33
                  • Slide Number 34
                  • Slide Number 35
                  • Slide Number 36
                  • Slide Number 37
                  • Buildings and works - Site management standard
                  • Site management
                  • Planning Advisory Note No 75
                  • Slide Number 41
                  • Slide Number 42
                  • Slide Number 43
                  • Slide Number 44
                  • Slide Number 45
                  • Slide Number 46
                  • Slide Number 47
                  • Slide Number 48
                  • Slide Number 49
                  • Slide Number 50
                  • Slide Number 51
                  • Slide Number 52
                  • Slide Number 53
                  • Slide Number 54
                  • Slide Number 55
                  • Slide Number 56
                  • Slide Number 57
                  • Slide Number 58
                  • Slide Number 59
                  • Slide Number 60
                  • Slide Number 61
                  • Next steps
                  • State Stormwater policies
                  • Slide Number 64

                    11

                    Wide consultation

                    6 committee meetings

                    6 stakeholder workshops

                    46 submissions7 one on ones

                    12

                    Stakeholder feedback

                    bull Consultation indicated widespread support for application of stormwater standards across all development types

                    bull Raised a number of implementation issues

                    bull Planning system only part of the response

                    13

                    Stakeholder feedback

                    Other feedback

                    bull Offsets are useful if they can be designed to provide net benefits and protect sensitive areas

                    bull Councils struggle with funding stormwater infrastructure costs

                    bull Rolesaccountabilities not well definedbull Skills tools and guidance need investmentbull Community awareness lowbull Support for linking IWM plans to planning system

                    14

                    Committee submitted its report in September 2018

                    15

                    The Committees 18 recommendations include

                    bull Planning reforms (3) ndash immediate reforms satisfying Part A of the Terms of Reference (ToR)

                    bull Future policy directions (7) ndash longer term policy directions satisfying Part B of the ToR

                    bull Supporting actions (8) ndash actions to ensure successful implementation of the (Part A) planning reforms satisfying Part B of the ToR

                    Committee Recomendations

                    16

                    Planning reforms

                    Rec 1 ndash Expand the stormwater planning provisions (phase 1) That the Victorian Government amend the VPPs to expand the current stormwater management requirements to

                    bull commercial subdivisions and developmentsbull industrial subdivisions and developmentsbull public-use developmentsbull multi-dwelling residential subdivisions and developments

                    Rec 2 ndash Expand the stormwater planning provisions (phase 2) That subject to further consultation the development of deemed-to-satisfy solutions (rec 12) adequate guidance and tools (recs 13 14 and 15) and offset processes (rec 5) the Victorian Government amend the VPPs to expand the current stormwater management requirements to

                    bull single-dwelling developmentsbull extensions over 50 m2

                    Rec 3 ndash Insert an IWM clause into the Planning Policy Framework (PPF) That the Victorian Government amend the PPF to embed the concepts of IWM objectives and strategies

                    17

                    Future policy directions

                    Rec 4 ndash Amend the building and plumbing controls

                    Rec 5 ndash Establish effective offsetting arrangements

                    Rec 6 ndash Clarify local governmentsrsquo roles and responsibilities

                    Rec 7 ndash Strengthen compliance requirements

                    Rec 8 ndash Determine funding sources for public stormwater infrastructure

                    Rec 9 ndash Link water management with urban planning

                    Rec 10 ndash Set stronger place-based BPEM stormwater performance objectives

                    18

                    Rec 11 ndash Strengthen enforcement of stormwater construction requirements

                    Rec 12 ndash Prepare deemed-to-satisfy solutions

                    Rec 13 ndash Review the STORM and MUSIC tools

                    Rec 14 ndash Build technical expertise

                    Rec 15 ndash Improve guidance

                    Rec 16 ndash Improve awareness of the VPP changes

                    Rec 17 ndash Investigate options for rainwater tank maintenance and operation

                    Rec 18 ndash Broaden rating systems to include IWM

                    Supporting actions

                    The new stormwater provisions

                    Emma Stewart DELWP

                    20

                    Government response (to date)

                    21

                    Government is currently considering the committeersquos longer-term recommendations and is working with key stakeholders to determine the most effective response and pathways for implementation

                    Longer term recommendations

                    22

                    State-based planning requirements (lsquobeforersquo)

                    Sourced ELM 2018

                    23

                    State-based planning requirements (lsquoafterrsquo)

                    24

                    Development types (volume)

                    Future development estimated impervious area 2020-2050

                    25

                    The nitty grittyhellip

                    26

                    Amendment VC154

                    Victoria Planning Provision changesbull New clause (5318) and changes to an existing clause

                    (5503) to expand the stormwater requirements to more development types

                    bull New objectives to manage toxicants and encourage broader benefits of stormwater management

                    27

                    Whatrsquos in

                    Applies to an application tobull subdivide land bull construct a building bull construct or carry out works

                    In both hellip

                    Clause 5318bull commercial zonesbull industrial zonesbull public-use zones

                    Clause 5518 bull Construct townhouses

                    Whatrsquos out of clause 5318

                    bull Developments and subdivisions approved or lodged prior to the amendment

                    bull Developments which do not require planning permission

                    bull Vicsmart applications

                    bull Applications for land within development or incorporated plans approved before the amendment

                    bull Extensions and works lt 50m2

                    bull Applications after the amendment to amend existing planning permits

                    If in doubt ask a planner

                    29

                    Key elements of clauses

                    Industrial commercial applications (Clause 5318)tobull subdivide land bull construct a building bull construct or carry out works

                    Stormwater management objectives + standard (W1)

                    Stormwater management objectives + standard (W2)+ Site management objectives + standard (W3)

                    Decision guidelines

                    Same for Clause 5503 (townhouses)

                    30

                    Clause 5318 ndash subdivision

                    Stormwater management standard W1 The stormwater management system should be bull Designed and managed in accordance with the requirements and

                    to the satisfaction of the relevant drainage authoritybull Designed and managed in accordance with the requirements and

                    to the satisfaction of the water authority where reuse of stormwater is proposed

                    bull Designed to meet the current best practice performance objectives for stormwater quality as contained in the BPEM

                    bull Designed to ensure that flows downstream of the subdivision site are restricted to pre-development levels unless increased flows are approved by the relevant drainage authority and there are no detrimental downstream impacts

                    bull Designed to contribute to cooling improving local habitat and providing attractive and enjoyable spaces

                    31

                    Clause 5318 ndash Buildings and works

                    Standard W2The stormwater management system should be designed to

                    bull Meet the current best practice performance objectives for stormwater quality as contained in the BPEM

                    bull Contribute to cooling improving local habitat and providing attractive and enjoyable spaces

                    bull Minimise the impact of chemical pollutants and other toxicants including by but not limited to bunding and covering of roofing of storage loading and work areas

                    32

                    Townhouses - Standard B9

                    Clause 5503 ndash Permeability and stormwater management objectives and standard B9

                    Objectivesbull Similar to 5318 (including the cooling liveability

                    objective)bull gt20 perviousness objective (unchanged)

                    Standardbull NEW - cooling liveability objectivebull NEW ndash requirement to meet BPEM

                    What does this all mean

                    34

                    Clause 5318 - Whatrsquos in

                    35

                    Urban cooling Reduce heat radiation from buildings and hard surfaces throughbull Shade trees in car parks or over driveways bull More open space and treesbull Green roofsbull Green walls

                    36

                    Optionsbull Passive irrigationbull Integrate assets into

                    communal open spacebull Tree pits and permeable

                    paving (driveways and carpark)

                    bull Stormwater harvesting (major developments only)

                    Infiltration habitat amenity

                    37

                    Control harmful chemicals

                    Optionsbull Careful layoutbull Consider alternative less harmful substancesbull Roofed designated storage areabull Internal drainage design to sewer or a treatment devicebull Bunding

                    38

                    Standard W3Standard W3 requires that application describe how the site will be managed prior to and during the construction period The application should set out requirements for managingbull Erosion and sedimentbull Stormwaterbull Litter concrete and other construction wastesbull Chemical contamination

                    Buildings and works - Site management standard

                    39

                    Site management

                    40

                    Planning Advisory Note No 75

                    Implications for industry

                    Kate MatthewsStormwater Victoria

                    1 Development proponents- Developers- Consultants (engineers stormwater specialists and planners)- Council (when developing public land lt$1 million)

                    2 Development assessors- Council statutory planners- Council internal referrals (engineering assets ESD stormwater officers)

                    3 Strategy- Council strategic planners

                    4 Melbourne Water

                    Whorsquos affected

                    43

                    What are the implications

                    bull BPEM - Itrsquos not just subdivisions any more

                    bull Cost ndash offset or assetbull Early planning and integration ndash more

                    work up frontbull Not just engineeringbull Varying Council skills and experience

                    Development Proponents

                    44

                    If already have a local policy for WSUDESD no real change

                    If notbull Workload and resourcingbull Increased detail and technical

                    contentbull Administrative arrangements ndash

                    referrals permit conditions ndashmake sure you make 60 stat days

                    bull Applicant pressure ndash what do you want

                    bull Assets

                    Development Assessors

                    45

                    bull Structure plans and rezoning ndashopportunities for localregional approach

                    bull IWM and Stormwater Management Plans ndash opportunities for these to be implemented through the controls spatial opportunities

                    bull Opportunities for development of Council offset strategies

                    Strategy

                    Offsets

                    bull Developer enters into an agreement with relevant drainage authority to financially contribute to off-site stormwatermanagement in lieu of providing on-site treatment

                    bull Already available for residential subdivisions in Melbourne (Clause 56) through MWCs Stormwater Quality Offset scheme

                    What are stormwater quality offsets

                    X Not drainage contributions (MWC drainage scheme)

                    X Not development contributions (DCPICP)

                    47

                    When to use

                    bull Not in MW DSS or growth area where therersquos an existing framework for funding SW treatment

                    bull Onsite treatment not practical or desirable

                    bull To fund planned localregional stormwater treatment works in that catchment via an existing offset scheme

                    bull Council and developer both agree to it

                    48

                    OffsetsExample ndash Kingston Offset Scheme

                    Asset ownership and maintenance

                    bull Whorsquos going to own itbull Whorsquos going to maintain itbull How do you maintain itbull How much will it cost

                    bull Where is itbull Is maintenance burden

                    practical for likely future owners

                    bull Whorsquos going to monitor compliance and how

                    The detail is in the permit conditions

                    Application requirements

                    ldquoAn application must be accompanied by details of the proposed stormwater management system including drainage works and retention detention and discharges of stormwater to the drainage systemrdquo ndash Clause 5318

                    What does the planning scheme require

                    But alsohellipNeed to provide sufficient information to Council which demonstrates that you comply and how you comply with all the other standards ndash eg urban coolinghabitatetc BPEM site management pollutant control infiltration (as relevant to development type

                    51

                    1 PlansWhat are you doing where is it going and does it fit

                    2 ModellingDo you (or can you) meet BPEM requirements

                    3 Written response to standardsHow does your proposal comply with the requirements

                    52

                    Application

                    bull Site plan ndash show all assetsWSUD treatments and any IWM features on the site layout plan with everything else

                    bull Landscape plan ndash if planting design passive irrigation etc forms part of response to requirements show

                    bull Site management plan (depending on Council)

                    bull Separate WSUDIWM plan showing all features on a stripped back background

                    bull Concept WSUD asset design ndash larger assets only (wetlands bioretention basins sed basin etc) ndash sufficient design detail to confirm spatial requirements

                    PlansPermit conditions

                    bull Detailed engineering design bull Site Management Plan (final)bull Asset maintenance plan (final)bull Handover arrangements (if public)

                    54

                    STORM ndash Online toolbull Print out of STORM reportbull Make sure meets 100 or

                    morebull Make sure report inputs and

                    results match plan

                    Modelling - SWQ

                    MUSIC ndash Proprietary softwarebull Provide a copy of the model filebull Print out the modelling resultsbull Provide summary of your model

                    inputs for each treatment train (iecatchment size impervious treatment area etc)

                    bull Provide a print out of the model schematic

                    Bonus points bull Provide details of model

                    parametersbull Provide results of MUSIC auditor

                    run (if using Melbourne Water MUSIC Guidelines)

                    56

                    Assessment against standards

                    bull Say what you have done (or will do) to meet each standardbull Donrsquot forget (if WSUD) details of maintenance and asset

                    ownershipbull Where applicable be explicit why yoursquove chosen (or not chosen) to

                    respond the way you have Egbull Opportunitiesbull Site constraintsbull Practicaloperational issues bull Brief dot point summary of options analysis if complex

                    bull Make sure if it doesnrsquot meet the standard it meets the objectivebull Make sure shown on plan and consistent with modelling and rest of

                    documentation

                    57

                    Resources

                    Local stormwaterWSUD policiesBaysideKingstonCaseyMonashMelbourneYarraMoonee ValleyPort PhilipStonningtonHumeCampaspeBass Coast

                    Local ESD (including IWM) policies Greater BendigoGreater DandenongHobsons BayWhittleseaWyndhamWhitehorseManninghamMorelandDarebinBanyuleKnoxBrimbank

                    Council planning resources

                    Application resources ndashexamplesDELWP Practice Note ndashformal guide to the new controlsMoreland ndash application checklists and example plans for a variety of residential developmentsPort Philip ndash compliance guidelines checklist and examplesMoonee Valley ndash checklists and example plans including site management plans Greater Bendigo ndash WSUD kitBayside ndash application guidelines and example plans

                    59

                    Technical guidelines (modelling design construction)

                    Melbourne Water

                    STORM calculatorMUSIC auditor - lsquohow torsquo video here

                    Melbourne Water technical guidelines page- WSUD asset life cycle costings and model maintenance guidelines- MUSIC guidelines- Stormwater harvesting guidelines- WSUD life cycle costings and

                    maintenance guidelines- Design and construction guidelines

                    for variety of assetshttpswwwmelbournewatercomauplanning-and-buildingdeveloper-guides-and-resourcesguidelines-drawings-and-checklistsguidelines

                    Council

                    South-Eastern Growth Council WSUD guidelines ndash note that some individual Councils have their own addendumsMelbournePort PhilipNorth-West Growth Council WSUD guidelines - note that some individual Councils have their own addendumsGreater BendigoMilduraBallaratBaw BawWyndhamMoreland ndash tree pits and raingardens

                    60

                    IWM

                    Example Council IWM strategiesMelbourneCaseyMonashKingston

                    Resilient Melbourne ndash IWM information lsquohubrsquoClearwater ndash capacity building and case studiesMelbourne Water ndash funding opportunities for IWM projects

                    Stormwater offset schemes

                    KingstonGreater GeelongMelbourne Water ndash non scheme contributions

                    Site management

                    EPA guidelines- management of erosion and sediment

                    Next steps and other stormwater initiatives

                    Emma Stewart DELWP

                    62

                    Next steps

                    bull Trainingbull The EPArsquos BPEM Reviewbull Offsets policybull Review of STORM bull Building controls

                    63

                    State Stormwater policies

                    64

                    Thank you

                    • Slide Number 1
                    • Slide Number 2
                    • History of WSUD
                    • History of WSUD
                    • Transformational change in urban water
                    • Inconsistencies and inequities in our approach to stormwater management
                    • Slide Number 8
                    • Terms of Reference
                    • Improving Stormwater Management Advisory Committee
                    • Wide consultation
                    • Stakeholder feedback
                    • Stakeholder feedback
                    • Committee submitted its report in September 2018
                    • Committee Recomendations
                    • Planning reforms
                    • Future policy directions
                    • Supporting actions
                    • Slide Number 19
                    • Government response (to date)
                    • Longer term recommendations
                    • State-based planning requirements (lsquobeforersquo)
                    • State-based planning requirements (lsquoafterrsquo)
                    • Development types (volume)
                    • Slide Number 25
                    • Amendment VC154
                    • Whatrsquos in
                    • Slide Number 28
                    • Key elements of clauses
                    • Clause 5318 ndash subdivision
                    • Clause 5318 ndash Buildings and works
                    • Townhouses - Standard B9
                    • Slide Number 33
                    • Slide Number 34
                    • Slide Number 35
                    • Slide Number 36
                    • Slide Number 37
                    • Buildings and works - Site management standard
                    • Site management
                    • Planning Advisory Note No 75
                    • Slide Number 41
                    • Slide Number 42
                    • Slide Number 43
                    • Slide Number 44
                    • Slide Number 45
                    • Slide Number 46
                    • Slide Number 47
                    • Slide Number 48
                    • Slide Number 49
                    • Slide Number 50
                    • Slide Number 51
                    • Slide Number 52
                    • Slide Number 53
                    • Slide Number 54
                    • Slide Number 55
                    • Slide Number 56
                    • Slide Number 57
                    • Slide Number 58
                    • Slide Number 59
                    • Slide Number 60
                    • Slide Number 61
                    • Next steps
                    • State Stormwater policies
                    • Slide Number 64

                      12

                      Stakeholder feedback

                      bull Consultation indicated widespread support for application of stormwater standards across all development types

                      bull Raised a number of implementation issues

                      bull Planning system only part of the response

                      13

                      Stakeholder feedback

                      Other feedback

                      bull Offsets are useful if they can be designed to provide net benefits and protect sensitive areas

                      bull Councils struggle with funding stormwater infrastructure costs

                      bull Rolesaccountabilities not well definedbull Skills tools and guidance need investmentbull Community awareness lowbull Support for linking IWM plans to planning system

                      14

                      Committee submitted its report in September 2018

                      15

                      The Committees 18 recommendations include

                      bull Planning reforms (3) ndash immediate reforms satisfying Part A of the Terms of Reference (ToR)

                      bull Future policy directions (7) ndash longer term policy directions satisfying Part B of the ToR

                      bull Supporting actions (8) ndash actions to ensure successful implementation of the (Part A) planning reforms satisfying Part B of the ToR

                      Committee Recomendations

                      16

                      Planning reforms

                      Rec 1 ndash Expand the stormwater planning provisions (phase 1) That the Victorian Government amend the VPPs to expand the current stormwater management requirements to

                      bull commercial subdivisions and developmentsbull industrial subdivisions and developmentsbull public-use developmentsbull multi-dwelling residential subdivisions and developments

                      Rec 2 ndash Expand the stormwater planning provisions (phase 2) That subject to further consultation the development of deemed-to-satisfy solutions (rec 12) adequate guidance and tools (recs 13 14 and 15) and offset processes (rec 5) the Victorian Government amend the VPPs to expand the current stormwater management requirements to

                      bull single-dwelling developmentsbull extensions over 50 m2

                      Rec 3 ndash Insert an IWM clause into the Planning Policy Framework (PPF) That the Victorian Government amend the PPF to embed the concepts of IWM objectives and strategies

                      17

                      Future policy directions

                      Rec 4 ndash Amend the building and plumbing controls

                      Rec 5 ndash Establish effective offsetting arrangements

                      Rec 6 ndash Clarify local governmentsrsquo roles and responsibilities

                      Rec 7 ndash Strengthen compliance requirements

                      Rec 8 ndash Determine funding sources for public stormwater infrastructure

                      Rec 9 ndash Link water management with urban planning

                      Rec 10 ndash Set stronger place-based BPEM stormwater performance objectives

                      18

                      Rec 11 ndash Strengthen enforcement of stormwater construction requirements

                      Rec 12 ndash Prepare deemed-to-satisfy solutions

                      Rec 13 ndash Review the STORM and MUSIC tools

                      Rec 14 ndash Build technical expertise

                      Rec 15 ndash Improve guidance

                      Rec 16 ndash Improve awareness of the VPP changes

                      Rec 17 ndash Investigate options for rainwater tank maintenance and operation

                      Rec 18 ndash Broaden rating systems to include IWM

                      Supporting actions

                      The new stormwater provisions

                      Emma Stewart DELWP

                      20

                      Government response (to date)

                      21

                      Government is currently considering the committeersquos longer-term recommendations and is working with key stakeholders to determine the most effective response and pathways for implementation

                      Longer term recommendations

                      22

                      State-based planning requirements (lsquobeforersquo)

                      Sourced ELM 2018

                      23

                      State-based planning requirements (lsquoafterrsquo)

                      24

                      Development types (volume)

                      Future development estimated impervious area 2020-2050

                      25

                      The nitty grittyhellip

                      26

                      Amendment VC154

                      Victoria Planning Provision changesbull New clause (5318) and changes to an existing clause

                      (5503) to expand the stormwater requirements to more development types

                      bull New objectives to manage toxicants and encourage broader benefits of stormwater management

                      27

                      Whatrsquos in

                      Applies to an application tobull subdivide land bull construct a building bull construct or carry out works

                      In both hellip

                      Clause 5318bull commercial zonesbull industrial zonesbull public-use zones

                      Clause 5518 bull Construct townhouses

                      Whatrsquos out of clause 5318

                      bull Developments and subdivisions approved or lodged prior to the amendment

                      bull Developments which do not require planning permission

                      bull Vicsmart applications

                      bull Applications for land within development or incorporated plans approved before the amendment

                      bull Extensions and works lt 50m2

                      bull Applications after the amendment to amend existing planning permits

                      If in doubt ask a planner

                      29

                      Key elements of clauses

                      Industrial commercial applications (Clause 5318)tobull subdivide land bull construct a building bull construct or carry out works

                      Stormwater management objectives + standard (W1)

                      Stormwater management objectives + standard (W2)+ Site management objectives + standard (W3)

                      Decision guidelines

                      Same for Clause 5503 (townhouses)

                      30

                      Clause 5318 ndash subdivision

                      Stormwater management standard W1 The stormwater management system should be bull Designed and managed in accordance with the requirements and

                      to the satisfaction of the relevant drainage authoritybull Designed and managed in accordance with the requirements and

                      to the satisfaction of the water authority where reuse of stormwater is proposed

                      bull Designed to meet the current best practice performance objectives for stormwater quality as contained in the BPEM

                      bull Designed to ensure that flows downstream of the subdivision site are restricted to pre-development levels unless increased flows are approved by the relevant drainage authority and there are no detrimental downstream impacts

                      bull Designed to contribute to cooling improving local habitat and providing attractive and enjoyable spaces

                      31

                      Clause 5318 ndash Buildings and works

                      Standard W2The stormwater management system should be designed to

                      bull Meet the current best practice performance objectives for stormwater quality as contained in the BPEM

                      bull Contribute to cooling improving local habitat and providing attractive and enjoyable spaces

                      bull Minimise the impact of chemical pollutants and other toxicants including by but not limited to bunding and covering of roofing of storage loading and work areas

                      32

                      Townhouses - Standard B9

                      Clause 5503 ndash Permeability and stormwater management objectives and standard B9

                      Objectivesbull Similar to 5318 (including the cooling liveability

                      objective)bull gt20 perviousness objective (unchanged)

                      Standardbull NEW - cooling liveability objectivebull NEW ndash requirement to meet BPEM

                      What does this all mean

                      34

                      Clause 5318 - Whatrsquos in

                      35

                      Urban cooling Reduce heat radiation from buildings and hard surfaces throughbull Shade trees in car parks or over driveways bull More open space and treesbull Green roofsbull Green walls

                      36

                      Optionsbull Passive irrigationbull Integrate assets into

                      communal open spacebull Tree pits and permeable

                      paving (driveways and carpark)

                      bull Stormwater harvesting (major developments only)

                      Infiltration habitat amenity

                      37

                      Control harmful chemicals

                      Optionsbull Careful layoutbull Consider alternative less harmful substancesbull Roofed designated storage areabull Internal drainage design to sewer or a treatment devicebull Bunding

                      38

                      Standard W3Standard W3 requires that application describe how the site will be managed prior to and during the construction period The application should set out requirements for managingbull Erosion and sedimentbull Stormwaterbull Litter concrete and other construction wastesbull Chemical contamination

                      Buildings and works - Site management standard

                      39

                      Site management

                      40

                      Planning Advisory Note No 75

                      Implications for industry

                      Kate MatthewsStormwater Victoria

                      1 Development proponents- Developers- Consultants (engineers stormwater specialists and planners)- Council (when developing public land lt$1 million)

                      2 Development assessors- Council statutory planners- Council internal referrals (engineering assets ESD stormwater officers)

                      3 Strategy- Council strategic planners

                      4 Melbourne Water

                      Whorsquos affected

                      43

                      What are the implications

                      bull BPEM - Itrsquos not just subdivisions any more

                      bull Cost ndash offset or assetbull Early planning and integration ndash more

                      work up frontbull Not just engineeringbull Varying Council skills and experience

                      Development Proponents

                      44

                      If already have a local policy for WSUDESD no real change

                      If notbull Workload and resourcingbull Increased detail and technical

                      contentbull Administrative arrangements ndash

                      referrals permit conditions ndashmake sure you make 60 stat days

                      bull Applicant pressure ndash what do you want

                      bull Assets

                      Development Assessors

                      45

                      bull Structure plans and rezoning ndashopportunities for localregional approach

                      bull IWM and Stormwater Management Plans ndash opportunities for these to be implemented through the controls spatial opportunities

                      bull Opportunities for development of Council offset strategies

                      Strategy

                      Offsets

                      bull Developer enters into an agreement with relevant drainage authority to financially contribute to off-site stormwatermanagement in lieu of providing on-site treatment

                      bull Already available for residential subdivisions in Melbourne (Clause 56) through MWCs Stormwater Quality Offset scheme

                      What are stormwater quality offsets

                      X Not drainage contributions (MWC drainage scheme)

                      X Not development contributions (DCPICP)

                      47

                      When to use

                      bull Not in MW DSS or growth area where therersquos an existing framework for funding SW treatment

                      bull Onsite treatment not practical or desirable

                      bull To fund planned localregional stormwater treatment works in that catchment via an existing offset scheme

                      bull Council and developer both agree to it

                      48

                      OffsetsExample ndash Kingston Offset Scheme

                      Asset ownership and maintenance

                      bull Whorsquos going to own itbull Whorsquos going to maintain itbull How do you maintain itbull How much will it cost

                      bull Where is itbull Is maintenance burden

                      practical for likely future owners

                      bull Whorsquos going to monitor compliance and how

                      The detail is in the permit conditions

                      Application requirements

                      ldquoAn application must be accompanied by details of the proposed stormwater management system including drainage works and retention detention and discharges of stormwater to the drainage systemrdquo ndash Clause 5318

                      What does the planning scheme require

                      But alsohellipNeed to provide sufficient information to Council which demonstrates that you comply and how you comply with all the other standards ndash eg urban coolinghabitatetc BPEM site management pollutant control infiltration (as relevant to development type

                      51

                      1 PlansWhat are you doing where is it going and does it fit

                      2 ModellingDo you (or can you) meet BPEM requirements

                      3 Written response to standardsHow does your proposal comply with the requirements

                      52

                      Application

                      bull Site plan ndash show all assetsWSUD treatments and any IWM features on the site layout plan with everything else

                      bull Landscape plan ndash if planting design passive irrigation etc forms part of response to requirements show

                      bull Site management plan (depending on Council)

                      bull Separate WSUDIWM plan showing all features on a stripped back background

                      bull Concept WSUD asset design ndash larger assets only (wetlands bioretention basins sed basin etc) ndash sufficient design detail to confirm spatial requirements

                      PlansPermit conditions

                      bull Detailed engineering design bull Site Management Plan (final)bull Asset maintenance plan (final)bull Handover arrangements (if public)

                      54

                      STORM ndash Online toolbull Print out of STORM reportbull Make sure meets 100 or

                      morebull Make sure report inputs and

                      results match plan

                      Modelling - SWQ

                      MUSIC ndash Proprietary softwarebull Provide a copy of the model filebull Print out the modelling resultsbull Provide summary of your model

                      inputs for each treatment train (iecatchment size impervious treatment area etc)

                      bull Provide a print out of the model schematic

                      Bonus points bull Provide details of model

                      parametersbull Provide results of MUSIC auditor

                      run (if using Melbourne Water MUSIC Guidelines)

                      56

                      Assessment against standards

                      bull Say what you have done (or will do) to meet each standardbull Donrsquot forget (if WSUD) details of maintenance and asset

                      ownershipbull Where applicable be explicit why yoursquove chosen (or not chosen) to

                      respond the way you have Egbull Opportunitiesbull Site constraintsbull Practicaloperational issues bull Brief dot point summary of options analysis if complex

                      bull Make sure if it doesnrsquot meet the standard it meets the objectivebull Make sure shown on plan and consistent with modelling and rest of

                      documentation

                      57

                      Resources

                      Local stormwaterWSUD policiesBaysideKingstonCaseyMonashMelbourneYarraMoonee ValleyPort PhilipStonningtonHumeCampaspeBass Coast

                      Local ESD (including IWM) policies Greater BendigoGreater DandenongHobsons BayWhittleseaWyndhamWhitehorseManninghamMorelandDarebinBanyuleKnoxBrimbank

                      Council planning resources

                      Application resources ndashexamplesDELWP Practice Note ndashformal guide to the new controlsMoreland ndash application checklists and example plans for a variety of residential developmentsPort Philip ndash compliance guidelines checklist and examplesMoonee Valley ndash checklists and example plans including site management plans Greater Bendigo ndash WSUD kitBayside ndash application guidelines and example plans

                      59

                      Technical guidelines (modelling design construction)

                      Melbourne Water

                      STORM calculatorMUSIC auditor - lsquohow torsquo video here

                      Melbourne Water technical guidelines page- WSUD asset life cycle costings and model maintenance guidelines- MUSIC guidelines- Stormwater harvesting guidelines- WSUD life cycle costings and

                      maintenance guidelines- Design and construction guidelines

                      for variety of assetshttpswwwmelbournewatercomauplanning-and-buildingdeveloper-guides-and-resourcesguidelines-drawings-and-checklistsguidelines

                      Council

                      South-Eastern Growth Council WSUD guidelines ndash note that some individual Councils have their own addendumsMelbournePort PhilipNorth-West Growth Council WSUD guidelines - note that some individual Councils have their own addendumsGreater BendigoMilduraBallaratBaw BawWyndhamMoreland ndash tree pits and raingardens

                      60

                      IWM

                      Example Council IWM strategiesMelbourneCaseyMonashKingston

                      Resilient Melbourne ndash IWM information lsquohubrsquoClearwater ndash capacity building and case studiesMelbourne Water ndash funding opportunities for IWM projects

                      Stormwater offset schemes

                      KingstonGreater GeelongMelbourne Water ndash non scheme contributions

                      Site management

                      EPA guidelines- management of erosion and sediment

                      Next steps and other stormwater initiatives

                      Emma Stewart DELWP

                      62

                      Next steps

                      bull Trainingbull The EPArsquos BPEM Reviewbull Offsets policybull Review of STORM bull Building controls

                      63

                      State Stormwater policies

                      64

                      Thank you

                      • Slide Number 1
                      • Slide Number 2
                      • History of WSUD
                      • History of WSUD
                      • Transformational change in urban water
                      • Inconsistencies and inequities in our approach to stormwater management
                      • Slide Number 8
                      • Terms of Reference
                      • Improving Stormwater Management Advisory Committee
                      • Wide consultation
                      • Stakeholder feedback
                      • Stakeholder feedback
                      • Committee submitted its report in September 2018
                      • Committee Recomendations
                      • Planning reforms
                      • Future policy directions
                      • Supporting actions
                      • Slide Number 19
                      • Government response (to date)
                      • Longer term recommendations
                      • State-based planning requirements (lsquobeforersquo)
                      • State-based planning requirements (lsquoafterrsquo)
                      • Development types (volume)
                      • Slide Number 25
                      • Amendment VC154
                      • Whatrsquos in
                      • Slide Number 28
                      • Key elements of clauses
                      • Clause 5318 ndash subdivision
                      • Clause 5318 ndash Buildings and works
                      • Townhouses - Standard B9
                      • Slide Number 33
                      • Slide Number 34
                      • Slide Number 35
                      • Slide Number 36
                      • Slide Number 37
                      • Buildings and works - Site management standard
                      • Site management
                      • Planning Advisory Note No 75
                      • Slide Number 41
                      • Slide Number 42
                      • Slide Number 43
                      • Slide Number 44
                      • Slide Number 45
                      • Slide Number 46
                      • Slide Number 47
                      • Slide Number 48
                      • Slide Number 49
                      • Slide Number 50
                      • Slide Number 51
                      • Slide Number 52
                      • Slide Number 53
                      • Slide Number 54
                      • Slide Number 55
                      • Slide Number 56
                      • Slide Number 57
                      • Slide Number 58
                      • Slide Number 59
                      • Slide Number 60
                      • Slide Number 61
                      • Next steps
                      • State Stormwater policies
                      • Slide Number 64

                        13

                        Stakeholder feedback

                        Other feedback

                        bull Offsets are useful if they can be designed to provide net benefits and protect sensitive areas

                        bull Councils struggle with funding stormwater infrastructure costs

                        bull Rolesaccountabilities not well definedbull Skills tools and guidance need investmentbull Community awareness lowbull Support for linking IWM plans to planning system

                        14

                        Committee submitted its report in September 2018

                        15

                        The Committees 18 recommendations include

                        bull Planning reforms (3) ndash immediate reforms satisfying Part A of the Terms of Reference (ToR)

                        bull Future policy directions (7) ndash longer term policy directions satisfying Part B of the ToR

                        bull Supporting actions (8) ndash actions to ensure successful implementation of the (Part A) planning reforms satisfying Part B of the ToR

                        Committee Recomendations

                        16

                        Planning reforms

                        Rec 1 ndash Expand the stormwater planning provisions (phase 1) That the Victorian Government amend the VPPs to expand the current stormwater management requirements to

                        bull commercial subdivisions and developmentsbull industrial subdivisions and developmentsbull public-use developmentsbull multi-dwelling residential subdivisions and developments

                        Rec 2 ndash Expand the stormwater planning provisions (phase 2) That subject to further consultation the development of deemed-to-satisfy solutions (rec 12) adequate guidance and tools (recs 13 14 and 15) and offset processes (rec 5) the Victorian Government amend the VPPs to expand the current stormwater management requirements to

                        bull single-dwelling developmentsbull extensions over 50 m2

                        Rec 3 ndash Insert an IWM clause into the Planning Policy Framework (PPF) That the Victorian Government amend the PPF to embed the concepts of IWM objectives and strategies

                        17

                        Future policy directions

                        Rec 4 ndash Amend the building and plumbing controls

                        Rec 5 ndash Establish effective offsetting arrangements

                        Rec 6 ndash Clarify local governmentsrsquo roles and responsibilities

                        Rec 7 ndash Strengthen compliance requirements

                        Rec 8 ndash Determine funding sources for public stormwater infrastructure

                        Rec 9 ndash Link water management with urban planning

                        Rec 10 ndash Set stronger place-based BPEM stormwater performance objectives

                        18

                        Rec 11 ndash Strengthen enforcement of stormwater construction requirements

                        Rec 12 ndash Prepare deemed-to-satisfy solutions

                        Rec 13 ndash Review the STORM and MUSIC tools

                        Rec 14 ndash Build technical expertise

                        Rec 15 ndash Improve guidance

                        Rec 16 ndash Improve awareness of the VPP changes

                        Rec 17 ndash Investigate options for rainwater tank maintenance and operation

                        Rec 18 ndash Broaden rating systems to include IWM

                        Supporting actions

                        The new stormwater provisions

                        Emma Stewart DELWP

                        20

                        Government response (to date)

                        21

                        Government is currently considering the committeersquos longer-term recommendations and is working with key stakeholders to determine the most effective response and pathways for implementation

                        Longer term recommendations

                        22

                        State-based planning requirements (lsquobeforersquo)

                        Sourced ELM 2018

                        23

                        State-based planning requirements (lsquoafterrsquo)

                        24

                        Development types (volume)

                        Future development estimated impervious area 2020-2050

                        25

                        The nitty grittyhellip

                        26

                        Amendment VC154

                        Victoria Planning Provision changesbull New clause (5318) and changes to an existing clause

                        (5503) to expand the stormwater requirements to more development types

                        bull New objectives to manage toxicants and encourage broader benefits of stormwater management

                        27

                        Whatrsquos in

                        Applies to an application tobull subdivide land bull construct a building bull construct or carry out works

                        In both hellip

                        Clause 5318bull commercial zonesbull industrial zonesbull public-use zones

                        Clause 5518 bull Construct townhouses

                        Whatrsquos out of clause 5318

                        bull Developments and subdivisions approved or lodged prior to the amendment

                        bull Developments which do not require planning permission

                        bull Vicsmart applications

                        bull Applications for land within development or incorporated plans approved before the amendment

                        bull Extensions and works lt 50m2

                        bull Applications after the amendment to amend existing planning permits

                        If in doubt ask a planner

                        29

                        Key elements of clauses

                        Industrial commercial applications (Clause 5318)tobull subdivide land bull construct a building bull construct or carry out works

                        Stormwater management objectives + standard (W1)

                        Stormwater management objectives + standard (W2)+ Site management objectives + standard (W3)

                        Decision guidelines

                        Same for Clause 5503 (townhouses)

                        30

                        Clause 5318 ndash subdivision

                        Stormwater management standard W1 The stormwater management system should be bull Designed and managed in accordance with the requirements and

                        to the satisfaction of the relevant drainage authoritybull Designed and managed in accordance with the requirements and

                        to the satisfaction of the water authority where reuse of stormwater is proposed

                        bull Designed to meet the current best practice performance objectives for stormwater quality as contained in the BPEM

                        bull Designed to ensure that flows downstream of the subdivision site are restricted to pre-development levels unless increased flows are approved by the relevant drainage authority and there are no detrimental downstream impacts

                        bull Designed to contribute to cooling improving local habitat and providing attractive and enjoyable spaces

                        31

                        Clause 5318 ndash Buildings and works

                        Standard W2The stormwater management system should be designed to

                        bull Meet the current best practice performance objectives for stormwater quality as contained in the BPEM

                        bull Contribute to cooling improving local habitat and providing attractive and enjoyable spaces

                        bull Minimise the impact of chemical pollutants and other toxicants including by but not limited to bunding and covering of roofing of storage loading and work areas

                        32

                        Townhouses - Standard B9

                        Clause 5503 ndash Permeability and stormwater management objectives and standard B9

                        Objectivesbull Similar to 5318 (including the cooling liveability

                        objective)bull gt20 perviousness objective (unchanged)

                        Standardbull NEW - cooling liveability objectivebull NEW ndash requirement to meet BPEM

                        What does this all mean

                        34

                        Clause 5318 - Whatrsquos in

                        35

                        Urban cooling Reduce heat radiation from buildings and hard surfaces throughbull Shade trees in car parks or over driveways bull More open space and treesbull Green roofsbull Green walls

                        36

                        Optionsbull Passive irrigationbull Integrate assets into

                        communal open spacebull Tree pits and permeable

                        paving (driveways and carpark)

                        bull Stormwater harvesting (major developments only)

                        Infiltration habitat amenity

                        37

                        Control harmful chemicals

                        Optionsbull Careful layoutbull Consider alternative less harmful substancesbull Roofed designated storage areabull Internal drainage design to sewer or a treatment devicebull Bunding

                        38

                        Standard W3Standard W3 requires that application describe how the site will be managed prior to and during the construction period The application should set out requirements for managingbull Erosion and sedimentbull Stormwaterbull Litter concrete and other construction wastesbull Chemical contamination

                        Buildings and works - Site management standard

                        39

                        Site management

                        40

                        Planning Advisory Note No 75

                        Implications for industry

                        Kate MatthewsStormwater Victoria

                        1 Development proponents- Developers- Consultants (engineers stormwater specialists and planners)- Council (when developing public land lt$1 million)

                        2 Development assessors- Council statutory planners- Council internal referrals (engineering assets ESD stormwater officers)

                        3 Strategy- Council strategic planners

                        4 Melbourne Water

                        Whorsquos affected

                        43

                        What are the implications

                        bull BPEM - Itrsquos not just subdivisions any more

                        bull Cost ndash offset or assetbull Early planning and integration ndash more

                        work up frontbull Not just engineeringbull Varying Council skills and experience

                        Development Proponents

                        44

                        If already have a local policy for WSUDESD no real change

                        If notbull Workload and resourcingbull Increased detail and technical

                        contentbull Administrative arrangements ndash

                        referrals permit conditions ndashmake sure you make 60 stat days

                        bull Applicant pressure ndash what do you want

                        bull Assets

                        Development Assessors

                        45

                        bull Structure plans and rezoning ndashopportunities for localregional approach

                        bull IWM and Stormwater Management Plans ndash opportunities for these to be implemented through the controls spatial opportunities

                        bull Opportunities for development of Council offset strategies

                        Strategy

                        Offsets

                        bull Developer enters into an agreement with relevant drainage authority to financially contribute to off-site stormwatermanagement in lieu of providing on-site treatment

                        bull Already available for residential subdivisions in Melbourne (Clause 56) through MWCs Stormwater Quality Offset scheme

                        What are stormwater quality offsets

                        X Not drainage contributions (MWC drainage scheme)

                        X Not development contributions (DCPICP)

                        47

                        When to use

                        bull Not in MW DSS or growth area where therersquos an existing framework for funding SW treatment

                        bull Onsite treatment not practical or desirable

                        bull To fund planned localregional stormwater treatment works in that catchment via an existing offset scheme

                        bull Council and developer both agree to it

                        48

                        OffsetsExample ndash Kingston Offset Scheme

                        Asset ownership and maintenance

                        bull Whorsquos going to own itbull Whorsquos going to maintain itbull How do you maintain itbull How much will it cost

                        bull Where is itbull Is maintenance burden

                        practical for likely future owners

                        bull Whorsquos going to monitor compliance and how

                        The detail is in the permit conditions

                        Application requirements

                        ldquoAn application must be accompanied by details of the proposed stormwater management system including drainage works and retention detention and discharges of stormwater to the drainage systemrdquo ndash Clause 5318

                        What does the planning scheme require

                        But alsohellipNeed to provide sufficient information to Council which demonstrates that you comply and how you comply with all the other standards ndash eg urban coolinghabitatetc BPEM site management pollutant control infiltration (as relevant to development type

                        51

                        1 PlansWhat are you doing where is it going and does it fit

                        2 ModellingDo you (or can you) meet BPEM requirements

                        3 Written response to standardsHow does your proposal comply with the requirements

                        52

                        Application

                        bull Site plan ndash show all assetsWSUD treatments and any IWM features on the site layout plan with everything else

                        bull Landscape plan ndash if planting design passive irrigation etc forms part of response to requirements show

                        bull Site management plan (depending on Council)

                        bull Separate WSUDIWM plan showing all features on a stripped back background

                        bull Concept WSUD asset design ndash larger assets only (wetlands bioretention basins sed basin etc) ndash sufficient design detail to confirm spatial requirements

                        PlansPermit conditions

                        bull Detailed engineering design bull Site Management Plan (final)bull Asset maintenance plan (final)bull Handover arrangements (if public)

                        54

                        STORM ndash Online toolbull Print out of STORM reportbull Make sure meets 100 or

                        morebull Make sure report inputs and

                        results match plan

                        Modelling - SWQ

                        MUSIC ndash Proprietary softwarebull Provide a copy of the model filebull Print out the modelling resultsbull Provide summary of your model

                        inputs for each treatment train (iecatchment size impervious treatment area etc)

                        bull Provide a print out of the model schematic

                        Bonus points bull Provide details of model

                        parametersbull Provide results of MUSIC auditor

                        run (if using Melbourne Water MUSIC Guidelines)

                        56

                        Assessment against standards

                        bull Say what you have done (or will do) to meet each standardbull Donrsquot forget (if WSUD) details of maintenance and asset

                        ownershipbull Where applicable be explicit why yoursquove chosen (or not chosen) to

                        respond the way you have Egbull Opportunitiesbull Site constraintsbull Practicaloperational issues bull Brief dot point summary of options analysis if complex

                        bull Make sure if it doesnrsquot meet the standard it meets the objectivebull Make sure shown on plan and consistent with modelling and rest of

                        documentation

                        57

                        Resources

                        Local stormwaterWSUD policiesBaysideKingstonCaseyMonashMelbourneYarraMoonee ValleyPort PhilipStonningtonHumeCampaspeBass Coast

                        Local ESD (including IWM) policies Greater BendigoGreater DandenongHobsons BayWhittleseaWyndhamWhitehorseManninghamMorelandDarebinBanyuleKnoxBrimbank

                        Council planning resources

                        Application resources ndashexamplesDELWP Practice Note ndashformal guide to the new controlsMoreland ndash application checklists and example plans for a variety of residential developmentsPort Philip ndash compliance guidelines checklist and examplesMoonee Valley ndash checklists and example plans including site management plans Greater Bendigo ndash WSUD kitBayside ndash application guidelines and example plans

                        59

                        Technical guidelines (modelling design construction)

                        Melbourne Water

                        STORM calculatorMUSIC auditor - lsquohow torsquo video here

                        Melbourne Water technical guidelines page- WSUD asset life cycle costings and model maintenance guidelines- MUSIC guidelines- Stormwater harvesting guidelines- WSUD life cycle costings and

                        maintenance guidelines- Design and construction guidelines

                        for variety of assetshttpswwwmelbournewatercomauplanning-and-buildingdeveloper-guides-and-resourcesguidelines-drawings-and-checklistsguidelines

                        Council

                        South-Eastern Growth Council WSUD guidelines ndash note that some individual Councils have their own addendumsMelbournePort PhilipNorth-West Growth Council WSUD guidelines - note that some individual Councils have their own addendumsGreater BendigoMilduraBallaratBaw BawWyndhamMoreland ndash tree pits and raingardens

                        60

                        IWM

                        Example Council IWM strategiesMelbourneCaseyMonashKingston

                        Resilient Melbourne ndash IWM information lsquohubrsquoClearwater ndash capacity building and case studiesMelbourne Water ndash funding opportunities for IWM projects

                        Stormwater offset schemes

                        KingstonGreater GeelongMelbourne Water ndash non scheme contributions

                        Site management

                        EPA guidelines- management of erosion and sediment

                        Next steps and other stormwater initiatives

                        Emma Stewart DELWP

                        62

                        Next steps

                        bull Trainingbull The EPArsquos BPEM Reviewbull Offsets policybull Review of STORM bull Building controls

                        63

                        State Stormwater policies

                        64

                        Thank you

                        • Slide Number 1
                        • Slide Number 2
                        • History of WSUD
                        • History of WSUD
                        • Transformational change in urban water
                        • Inconsistencies and inequities in our approach to stormwater management
                        • Slide Number 8
                        • Terms of Reference
                        • Improving Stormwater Management Advisory Committee
                        • Wide consultation
                        • Stakeholder feedback
                        • Stakeholder feedback
                        • Committee submitted its report in September 2018
                        • Committee Recomendations
                        • Planning reforms
                        • Future policy directions
                        • Supporting actions
                        • Slide Number 19
                        • Government response (to date)
                        • Longer term recommendations
                        • State-based planning requirements (lsquobeforersquo)
                        • State-based planning requirements (lsquoafterrsquo)
                        • Development types (volume)
                        • Slide Number 25
                        • Amendment VC154
                        • Whatrsquos in
                        • Slide Number 28
                        • Key elements of clauses
                        • Clause 5318 ndash subdivision
                        • Clause 5318 ndash Buildings and works
                        • Townhouses - Standard B9
                        • Slide Number 33
                        • Slide Number 34
                        • Slide Number 35
                        • Slide Number 36
                        • Slide Number 37
                        • Buildings and works - Site management standard
                        • Site management
                        • Planning Advisory Note No 75
                        • Slide Number 41
                        • Slide Number 42
                        • Slide Number 43
                        • Slide Number 44
                        • Slide Number 45
                        • Slide Number 46
                        • Slide Number 47
                        • Slide Number 48
                        • Slide Number 49
                        • Slide Number 50
                        • Slide Number 51
                        • Slide Number 52
                        • Slide Number 53
                        • Slide Number 54
                        • Slide Number 55
                        • Slide Number 56
                        • Slide Number 57
                        • Slide Number 58
                        • Slide Number 59
                        • Slide Number 60
                        • Slide Number 61
                        • Next steps
                        • State Stormwater policies
                        • Slide Number 64

                          14

                          Committee submitted its report in September 2018

                          15

                          The Committees 18 recommendations include

                          bull Planning reforms (3) ndash immediate reforms satisfying Part A of the Terms of Reference (ToR)

                          bull Future policy directions (7) ndash longer term policy directions satisfying Part B of the ToR

                          bull Supporting actions (8) ndash actions to ensure successful implementation of the (Part A) planning reforms satisfying Part B of the ToR

                          Committee Recomendations

                          16

                          Planning reforms

                          Rec 1 ndash Expand the stormwater planning provisions (phase 1) That the Victorian Government amend the VPPs to expand the current stormwater management requirements to

                          bull commercial subdivisions and developmentsbull industrial subdivisions and developmentsbull public-use developmentsbull multi-dwelling residential subdivisions and developments

                          Rec 2 ndash Expand the stormwater planning provisions (phase 2) That subject to further consultation the development of deemed-to-satisfy solutions (rec 12) adequate guidance and tools (recs 13 14 and 15) and offset processes (rec 5) the Victorian Government amend the VPPs to expand the current stormwater management requirements to

                          bull single-dwelling developmentsbull extensions over 50 m2

                          Rec 3 ndash Insert an IWM clause into the Planning Policy Framework (PPF) That the Victorian Government amend the PPF to embed the concepts of IWM objectives and strategies

                          17

                          Future policy directions

                          Rec 4 ndash Amend the building and plumbing controls

                          Rec 5 ndash Establish effective offsetting arrangements

                          Rec 6 ndash Clarify local governmentsrsquo roles and responsibilities

                          Rec 7 ndash Strengthen compliance requirements

                          Rec 8 ndash Determine funding sources for public stormwater infrastructure

                          Rec 9 ndash Link water management with urban planning

                          Rec 10 ndash Set stronger place-based BPEM stormwater performance objectives

                          18

                          Rec 11 ndash Strengthen enforcement of stormwater construction requirements

                          Rec 12 ndash Prepare deemed-to-satisfy solutions

                          Rec 13 ndash Review the STORM and MUSIC tools

                          Rec 14 ndash Build technical expertise

                          Rec 15 ndash Improve guidance

                          Rec 16 ndash Improve awareness of the VPP changes

                          Rec 17 ndash Investigate options for rainwater tank maintenance and operation

                          Rec 18 ndash Broaden rating systems to include IWM

                          Supporting actions

                          The new stormwater provisions

                          Emma Stewart DELWP

                          20

                          Government response (to date)

                          21

                          Government is currently considering the committeersquos longer-term recommendations and is working with key stakeholders to determine the most effective response and pathways for implementation

                          Longer term recommendations

                          22

                          State-based planning requirements (lsquobeforersquo)

                          Sourced ELM 2018

                          23

                          State-based planning requirements (lsquoafterrsquo)

                          24

                          Development types (volume)

                          Future development estimated impervious area 2020-2050

                          25

                          The nitty grittyhellip

                          26

                          Amendment VC154

                          Victoria Planning Provision changesbull New clause (5318) and changes to an existing clause

                          (5503) to expand the stormwater requirements to more development types

                          bull New objectives to manage toxicants and encourage broader benefits of stormwater management

                          27

                          Whatrsquos in

                          Applies to an application tobull subdivide land bull construct a building bull construct or carry out works

                          In both hellip

                          Clause 5318bull commercial zonesbull industrial zonesbull public-use zones

                          Clause 5518 bull Construct townhouses

                          Whatrsquos out of clause 5318

                          bull Developments and subdivisions approved or lodged prior to the amendment

                          bull Developments which do not require planning permission

                          bull Vicsmart applications

                          bull Applications for land within development or incorporated plans approved before the amendment

                          bull Extensions and works lt 50m2

                          bull Applications after the amendment to amend existing planning permits

                          If in doubt ask a planner

                          29

                          Key elements of clauses

                          Industrial commercial applications (Clause 5318)tobull subdivide land bull construct a building bull construct or carry out works

                          Stormwater management objectives + standard (W1)

                          Stormwater management objectives + standard (W2)+ Site management objectives + standard (W3)

                          Decision guidelines

                          Same for Clause 5503 (townhouses)

                          30

                          Clause 5318 ndash subdivision

                          Stormwater management standard W1 The stormwater management system should be bull Designed and managed in accordance with the requirements and

                          to the satisfaction of the relevant drainage authoritybull Designed and managed in accordance with the requirements and

                          to the satisfaction of the water authority where reuse of stormwater is proposed

                          bull Designed to meet the current best practice performance objectives for stormwater quality as contained in the BPEM

                          bull Designed to ensure that flows downstream of the subdivision site are restricted to pre-development levels unless increased flows are approved by the relevant drainage authority and there are no detrimental downstream impacts

                          bull Designed to contribute to cooling improving local habitat and providing attractive and enjoyable spaces

                          31

                          Clause 5318 ndash Buildings and works

                          Standard W2The stormwater management system should be designed to

                          bull Meet the current best practice performance objectives for stormwater quality as contained in the BPEM

                          bull Contribute to cooling improving local habitat and providing attractive and enjoyable spaces

                          bull Minimise the impact of chemical pollutants and other toxicants including by but not limited to bunding and covering of roofing of storage loading and work areas

                          32

                          Townhouses - Standard B9

                          Clause 5503 ndash Permeability and stormwater management objectives and standard B9

                          Objectivesbull Similar to 5318 (including the cooling liveability

                          objective)bull gt20 perviousness objective (unchanged)

                          Standardbull NEW - cooling liveability objectivebull NEW ndash requirement to meet BPEM

                          What does this all mean

                          34

                          Clause 5318 - Whatrsquos in

                          35

                          Urban cooling Reduce heat radiation from buildings and hard surfaces throughbull Shade trees in car parks or over driveways bull More open space and treesbull Green roofsbull Green walls

                          36

                          Optionsbull Passive irrigationbull Integrate assets into

                          communal open spacebull Tree pits and permeable

                          paving (driveways and carpark)

                          bull Stormwater harvesting (major developments only)

                          Infiltration habitat amenity

                          37

                          Control harmful chemicals

                          Optionsbull Careful layoutbull Consider alternative less harmful substancesbull Roofed designated storage areabull Internal drainage design to sewer or a treatment devicebull Bunding

                          38

                          Standard W3Standard W3 requires that application describe how the site will be managed prior to and during the construction period The application should set out requirements for managingbull Erosion and sedimentbull Stormwaterbull Litter concrete and other construction wastesbull Chemical contamination

                          Buildings and works - Site management standard

                          39

                          Site management

                          40

                          Planning Advisory Note No 75

                          Implications for industry

                          Kate MatthewsStormwater Victoria

                          1 Development proponents- Developers- Consultants (engineers stormwater specialists and planners)- Council (when developing public land lt$1 million)

                          2 Development assessors- Council statutory planners- Council internal referrals (engineering assets ESD stormwater officers)

                          3 Strategy- Council strategic planners

                          4 Melbourne Water

                          Whorsquos affected

                          43

                          What are the implications

                          bull BPEM - Itrsquos not just subdivisions any more

                          bull Cost ndash offset or assetbull Early planning and integration ndash more

                          work up frontbull Not just engineeringbull Varying Council skills and experience

                          Development Proponents

                          44

                          If already have a local policy for WSUDESD no real change

                          If notbull Workload and resourcingbull Increased detail and technical

                          contentbull Administrative arrangements ndash

                          referrals permit conditions ndashmake sure you make 60 stat days

                          bull Applicant pressure ndash what do you want

                          bull Assets

                          Development Assessors

                          45

                          bull Structure plans and rezoning ndashopportunities for localregional approach

                          bull IWM and Stormwater Management Plans ndash opportunities for these to be implemented through the controls spatial opportunities

                          bull Opportunities for development of Council offset strategies

                          Strategy

                          Offsets

                          bull Developer enters into an agreement with relevant drainage authority to financially contribute to off-site stormwatermanagement in lieu of providing on-site treatment

                          bull Already available for residential subdivisions in Melbourne (Clause 56) through MWCs Stormwater Quality Offset scheme

                          What are stormwater quality offsets

                          X Not drainage contributions (MWC drainage scheme)

                          X Not development contributions (DCPICP)

                          47

                          When to use

                          bull Not in MW DSS or growth area where therersquos an existing framework for funding SW treatment

                          bull Onsite treatment not practical or desirable

                          bull To fund planned localregional stormwater treatment works in that catchment via an existing offset scheme

                          bull Council and developer both agree to it

                          48

                          OffsetsExample ndash Kingston Offset Scheme

                          Asset ownership and maintenance

                          bull Whorsquos going to own itbull Whorsquos going to maintain itbull How do you maintain itbull How much will it cost

                          bull Where is itbull Is maintenance burden

                          practical for likely future owners

                          bull Whorsquos going to monitor compliance and how

                          The detail is in the permit conditions

                          Application requirements

                          ldquoAn application must be accompanied by details of the proposed stormwater management system including drainage works and retention detention and discharges of stormwater to the drainage systemrdquo ndash Clause 5318

                          What does the planning scheme require

                          But alsohellipNeed to provide sufficient information to Council which demonstrates that you comply and how you comply with all the other standards ndash eg urban coolinghabitatetc BPEM site management pollutant control infiltration (as relevant to development type

                          51

                          1 PlansWhat are you doing where is it going and does it fit

                          2 ModellingDo you (or can you) meet BPEM requirements

                          3 Written response to standardsHow does your proposal comply with the requirements

                          52

                          Application

                          bull Site plan ndash show all assetsWSUD treatments and any IWM features on the site layout plan with everything else

                          bull Landscape plan ndash if planting design passive irrigation etc forms part of response to requirements show

                          bull Site management plan (depending on Council)

                          bull Separate WSUDIWM plan showing all features on a stripped back background

                          bull Concept WSUD asset design ndash larger assets only (wetlands bioretention basins sed basin etc) ndash sufficient design detail to confirm spatial requirements

                          PlansPermit conditions

                          bull Detailed engineering design bull Site Management Plan (final)bull Asset maintenance plan (final)bull Handover arrangements (if public)

                          54

                          STORM ndash Online toolbull Print out of STORM reportbull Make sure meets 100 or

                          morebull Make sure report inputs and

                          results match plan

                          Modelling - SWQ

                          MUSIC ndash Proprietary softwarebull Provide a copy of the model filebull Print out the modelling resultsbull Provide summary of your model

                          inputs for each treatment train (iecatchment size impervious treatment area etc)

                          bull Provide a print out of the model schematic

                          Bonus points bull Provide details of model

                          parametersbull Provide results of MUSIC auditor

                          run (if using Melbourne Water MUSIC Guidelines)

                          56

                          Assessment against standards

                          bull Say what you have done (or will do) to meet each standardbull Donrsquot forget (if WSUD) details of maintenance and asset

                          ownershipbull Where applicable be explicit why yoursquove chosen (or not chosen) to

                          respond the way you have Egbull Opportunitiesbull Site constraintsbull Practicaloperational issues bull Brief dot point summary of options analysis if complex

                          bull Make sure if it doesnrsquot meet the standard it meets the objectivebull Make sure shown on plan and consistent with modelling and rest of

                          documentation

                          57

                          Resources

                          Local stormwaterWSUD policiesBaysideKingstonCaseyMonashMelbourneYarraMoonee ValleyPort PhilipStonningtonHumeCampaspeBass Coast

                          Local ESD (including IWM) policies Greater BendigoGreater DandenongHobsons BayWhittleseaWyndhamWhitehorseManninghamMorelandDarebinBanyuleKnoxBrimbank

                          Council planning resources

                          Application resources ndashexamplesDELWP Practice Note ndashformal guide to the new controlsMoreland ndash application checklists and example plans for a variety of residential developmentsPort Philip ndash compliance guidelines checklist and examplesMoonee Valley ndash checklists and example plans including site management plans Greater Bendigo ndash WSUD kitBayside ndash application guidelines and example plans

                          59

                          Technical guidelines (modelling design construction)

                          Melbourne Water

                          STORM calculatorMUSIC auditor - lsquohow torsquo video here

                          Melbourne Water technical guidelines page- WSUD asset life cycle costings and model maintenance guidelines- MUSIC guidelines- Stormwater harvesting guidelines- WSUD life cycle costings and

                          maintenance guidelines- Design and construction guidelines

                          for variety of assetshttpswwwmelbournewatercomauplanning-and-buildingdeveloper-guides-and-resourcesguidelines-drawings-and-checklistsguidelines

                          Council

                          South-Eastern Growth Council WSUD guidelines ndash note that some individual Councils have their own addendumsMelbournePort PhilipNorth-West Growth Council WSUD guidelines - note that some individual Councils have their own addendumsGreater BendigoMilduraBallaratBaw BawWyndhamMoreland ndash tree pits and raingardens

                          60

                          IWM

                          Example Council IWM strategiesMelbourneCaseyMonashKingston

                          Resilient Melbourne ndash IWM information lsquohubrsquoClearwater ndash capacity building and case studiesMelbourne Water ndash funding opportunities for IWM projects

                          Stormwater offset schemes

                          KingstonGreater GeelongMelbourne Water ndash non scheme contributions

                          Site management

                          EPA guidelines- management of erosion and sediment

                          Next steps and other stormwater initiatives

                          Emma Stewart DELWP

                          62

                          Next steps

                          bull Trainingbull The EPArsquos BPEM Reviewbull Offsets policybull Review of STORM bull Building controls

                          63

                          State Stormwater policies

                          64

                          Thank you

                          • Slide Number 1
                          • Slide Number 2
                          • History of WSUD
                          • History of WSUD
                          • Transformational change in urban water
                          • Inconsistencies and inequities in our approach to stormwater management
                          • Slide Number 8
                          • Terms of Reference
                          • Improving Stormwater Management Advisory Committee
                          • Wide consultation
                          • Stakeholder feedback
                          • Stakeholder feedback
                          • Committee submitted its report in September 2018
                          • Committee Recomendations
                          • Planning reforms
                          • Future policy directions
                          • Supporting actions
                          • Slide Number 19
                          • Government response (to date)
                          • Longer term recommendations
                          • State-based planning requirements (lsquobeforersquo)
                          • State-based planning requirements (lsquoafterrsquo)
                          • Development types (volume)
                          • Slide Number 25
                          • Amendment VC154
                          • Whatrsquos in
                          • Slide Number 28
                          • Key elements of clauses
                          • Clause 5318 ndash subdivision
                          • Clause 5318 ndash Buildings and works
                          • Townhouses - Standard B9
                          • Slide Number 33
                          • Slide Number 34
                          • Slide Number 35
                          • Slide Number 36
                          • Slide Number 37
                          • Buildings and works - Site management standard
                          • Site management
                          • Planning Advisory Note No 75
                          • Slide Number 41
                          • Slide Number 42
                          • Slide Number 43
                          • Slide Number 44
                          • Slide Number 45
                          • Slide Number 46
                          • Slide Number 47
                          • Slide Number 48
                          • Slide Number 49
                          • Slide Number 50
                          • Slide Number 51
                          • Slide Number 52
                          • Slide Number 53
                          • Slide Number 54
                          • Slide Number 55
                          • Slide Number 56
                          • Slide Number 57
                          • Slide Number 58
                          • Slide Number 59
                          • Slide Number 60
                          • Slide Number 61
                          • Next steps
                          • State Stormwater policies
                          • Slide Number 64

                            15

                            The Committees 18 recommendations include

                            bull Planning reforms (3) ndash immediate reforms satisfying Part A of the Terms of Reference (ToR)

                            bull Future policy directions (7) ndash longer term policy directions satisfying Part B of the ToR

                            bull Supporting actions (8) ndash actions to ensure successful implementation of the (Part A) planning reforms satisfying Part B of the ToR

                            Committee Recomendations

                            16

                            Planning reforms

                            Rec 1 ndash Expand the stormwater planning provisions (phase 1) That the Victorian Government amend the VPPs to expand the current stormwater management requirements to

                            bull commercial subdivisions and developmentsbull industrial subdivisions and developmentsbull public-use developmentsbull multi-dwelling residential subdivisions and developments

                            Rec 2 ndash Expand the stormwater planning provisions (phase 2) That subject to further consultation the development of deemed-to-satisfy solutions (rec 12) adequate guidance and tools (recs 13 14 and 15) and offset processes (rec 5) the Victorian Government amend the VPPs to expand the current stormwater management requirements to

                            bull single-dwelling developmentsbull extensions over 50 m2

                            Rec 3 ndash Insert an IWM clause into the Planning Policy Framework (PPF) That the Victorian Government amend the PPF to embed the concepts of IWM objectives and strategies

                            17

                            Future policy directions

                            Rec 4 ndash Amend the building and plumbing controls

                            Rec 5 ndash Establish effective offsetting arrangements

                            Rec 6 ndash Clarify local governmentsrsquo roles and responsibilities

                            Rec 7 ndash Strengthen compliance requirements

                            Rec 8 ndash Determine funding sources for public stormwater infrastructure

                            Rec 9 ndash Link water management with urban planning

                            Rec 10 ndash Set stronger place-based BPEM stormwater performance objectives

                            18

                            Rec 11 ndash Strengthen enforcement of stormwater construction requirements

                            Rec 12 ndash Prepare deemed-to-satisfy solutions

                            Rec 13 ndash Review the STORM and MUSIC tools

                            Rec 14 ndash Build technical expertise

                            Rec 15 ndash Improve guidance

                            Rec 16 ndash Improve awareness of the VPP changes

                            Rec 17 ndash Investigate options for rainwater tank maintenance and operation

                            Rec 18 ndash Broaden rating systems to include IWM

                            Supporting actions

                            The new stormwater provisions

                            Emma Stewart DELWP

                            20

                            Government response (to date)

                            21

                            Government is currently considering the committeersquos longer-term recommendations and is working with key stakeholders to determine the most effective response and pathways for implementation

                            Longer term recommendations

                            22

                            State-based planning requirements (lsquobeforersquo)

                            Sourced ELM 2018

                            23

                            State-based planning requirements (lsquoafterrsquo)

                            24

                            Development types (volume)

                            Future development estimated impervious area 2020-2050

                            25

                            The nitty grittyhellip

                            26

                            Amendment VC154

                            Victoria Planning Provision changesbull New clause (5318) and changes to an existing clause

                            (5503) to expand the stormwater requirements to more development types

                            bull New objectives to manage toxicants and encourage broader benefits of stormwater management

                            27

                            Whatrsquos in

                            Applies to an application tobull subdivide land bull construct a building bull construct or carry out works

                            In both hellip

                            Clause 5318bull commercial zonesbull industrial zonesbull public-use zones

                            Clause 5518 bull Construct townhouses

                            Whatrsquos out of clause 5318

                            bull Developments and subdivisions approved or lodged prior to the amendment

                            bull Developments which do not require planning permission

                            bull Vicsmart applications

                            bull Applications for land within development or incorporated plans approved before the amendment

                            bull Extensions and works lt 50m2

                            bull Applications after the amendment to amend existing planning permits

                            If in doubt ask a planner

                            29

                            Key elements of clauses

                            Industrial commercial applications (Clause 5318)tobull subdivide land bull construct a building bull construct or carry out works

                            Stormwater management objectives + standard (W1)

                            Stormwater management objectives + standard (W2)+ Site management objectives + standard (W3)

                            Decision guidelines

                            Same for Clause 5503 (townhouses)

                            30

                            Clause 5318 ndash subdivision

                            Stormwater management standard W1 The stormwater management system should be bull Designed and managed in accordance with the requirements and

                            to the satisfaction of the relevant drainage authoritybull Designed and managed in accordance with the requirements and

                            to the satisfaction of the water authority where reuse of stormwater is proposed

                            bull Designed to meet the current best practice performance objectives for stormwater quality as contained in the BPEM

                            bull Designed to ensure that flows downstream of the subdivision site are restricted to pre-development levels unless increased flows are approved by the relevant drainage authority and there are no detrimental downstream impacts

                            bull Designed to contribute to cooling improving local habitat and providing attractive and enjoyable spaces

                            31

                            Clause 5318 ndash Buildings and works

                            Standard W2The stormwater management system should be designed to

                            bull Meet the current best practice performance objectives for stormwater quality as contained in the BPEM

                            bull Contribute to cooling improving local habitat and providing attractive and enjoyable spaces

                            bull Minimise the impact of chemical pollutants and other toxicants including by but not limited to bunding and covering of roofing of storage loading and work areas

                            32

                            Townhouses - Standard B9

                            Clause 5503 ndash Permeability and stormwater management objectives and standard B9

                            Objectivesbull Similar to 5318 (including the cooling liveability

                            objective)bull gt20 perviousness objective (unchanged)

                            Standardbull NEW - cooling liveability objectivebull NEW ndash requirement to meet BPEM

                            What does this all mean

                            34

                            Clause 5318 - Whatrsquos in

                            35

                            Urban cooling Reduce heat radiation from buildings and hard surfaces throughbull Shade trees in car parks or over driveways bull More open space and treesbull Green roofsbull Green walls

                            36

                            Optionsbull Passive irrigationbull Integrate assets into

                            communal open spacebull Tree pits and permeable

                            paving (driveways and carpark)

                            bull Stormwater harvesting (major developments only)

                            Infiltration habitat amenity

                            37

                            Control harmful chemicals

                            Optionsbull Careful layoutbull Consider alternative less harmful substancesbull Roofed designated storage areabull Internal drainage design to sewer or a treatment devicebull Bunding

                            38

                            Standard W3Standard W3 requires that application describe how the site will be managed prior to and during the construction period The application should set out requirements for managingbull Erosion and sedimentbull Stormwaterbull Litter concrete and other construction wastesbull Chemical contamination

                            Buildings and works - Site management standard

                            39

                            Site management

                            40

                            Planning Advisory Note No 75

                            Implications for industry

                            Kate MatthewsStormwater Victoria

                            1 Development proponents- Developers- Consultants (engineers stormwater specialists and planners)- Council (when developing public land lt$1 million)

                            2 Development assessors- Council statutory planners- Council internal referrals (engineering assets ESD stormwater officers)

                            3 Strategy- Council strategic planners

                            4 Melbourne Water

                            Whorsquos affected

                            43

                            What are the implications

                            bull BPEM - Itrsquos not just subdivisions any more

                            bull Cost ndash offset or assetbull Early planning and integration ndash more

                            work up frontbull Not just engineeringbull Varying Council skills and experience

                            Development Proponents

                            44

                            If already have a local policy for WSUDESD no real change

                            If notbull Workload and resourcingbull Increased detail and technical

                            contentbull Administrative arrangements ndash

                            referrals permit conditions ndashmake sure you make 60 stat days

                            bull Applicant pressure ndash what do you want

                            bull Assets

                            Development Assessors

                            45

                            bull Structure plans and rezoning ndashopportunities for localregional approach

                            bull IWM and Stormwater Management Plans ndash opportunities for these to be implemented through the controls spatial opportunities

                            bull Opportunities for development of Council offset strategies

                            Strategy

                            Offsets

                            bull Developer enters into an agreement with relevant drainage authority to financially contribute to off-site stormwatermanagement in lieu of providing on-site treatment

                            bull Already available for residential subdivisions in Melbourne (Clause 56) through MWCs Stormwater Quality Offset scheme

                            What are stormwater quality offsets

                            X Not drainage contributions (MWC drainage scheme)

                            X Not development contributions (DCPICP)

                            47

                            When to use

                            bull Not in MW DSS or growth area where therersquos an existing framework for funding SW treatment

                            bull Onsite treatment not practical or desirable

                            bull To fund planned localregional stormwater treatment works in that catchment via an existing offset scheme

                            bull Council and developer both agree to it

                            48

                            OffsetsExample ndash Kingston Offset Scheme

                            Asset ownership and maintenance

                            bull Whorsquos going to own itbull Whorsquos going to maintain itbull How do you maintain itbull How much will it cost

                            bull Where is itbull Is maintenance burden

                            practical for likely future owners

                            bull Whorsquos going to monitor compliance and how

                            The detail is in the permit conditions

                            Application requirements

                            ldquoAn application must be accompanied by details of the proposed stormwater management system including drainage works and retention detention and discharges of stormwater to the drainage systemrdquo ndash Clause 5318

                            What does the planning scheme require

                            But alsohellipNeed to provide sufficient information to Council which demonstrates that you comply and how you comply with all the other standards ndash eg urban coolinghabitatetc BPEM site management pollutant control infiltration (as relevant to development type

                            51

                            1 PlansWhat are you doing where is it going and does it fit

                            2 ModellingDo you (or can you) meet BPEM requirements

                            3 Written response to standardsHow does your proposal comply with the requirements

                            52

                            Application

                            bull Site plan ndash show all assetsWSUD treatments and any IWM features on the site layout plan with everything else

                            bull Landscape plan ndash if planting design passive irrigation etc forms part of response to requirements show

                            bull Site management plan (depending on Council)

                            bull Separate WSUDIWM plan showing all features on a stripped back background

                            bull Concept WSUD asset design ndash larger assets only (wetlands bioretention basins sed basin etc) ndash sufficient design detail to confirm spatial requirements

                            PlansPermit conditions

                            bull Detailed engineering design bull Site Management Plan (final)bull Asset maintenance plan (final)bull Handover arrangements (if public)

                            54

                            STORM ndash Online toolbull Print out of STORM reportbull Make sure meets 100 or

                            morebull Make sure report inputs and

                            results match plan

                            Modelling - SWQ

                            MUSIC ndash Proprietary softwarebull Provide a copy of the model filebull Print out the modelling resultsbull Provide summary of your model

                            inputs for each treatment train (iecatchment size impervious treatment area etc)

                            bull Provide a print out of the model schematic

                            Bonus points bull Provide details of model

                            parametersbull Provide results of MUSIC auditor

                            run (if using Melbourne Water MUSIC Guidelines)

                            56

                            Assessment against standards

                            bull Say what you have done (or will do) to meet each standardbull Donrsquot forget (if WSUD) details of maintenance and asset

                            ownershipbull Where applicable be explicit why yoursquove chosen (or not chosen) to

                            respond the way you have Egbull Opportunitiesbull Site constraintsbull Practicaloperational issues bull Brief dot point summary of options analysis if complex

                            bull Make sure if it doesnrsquot meet the standard it meets the objectivebull Make sure shown on plan and consistent with modelling and rest of

                            documentation

                            57

                            Resources

                            Local stormwaterWSUD policiesBaysideKingstonCaseyMonashMelbourneYarraMoonee ValleyPort PhilipStonningtonHumeCampaspeBass Coast

                            Local ESD (including IWM) policies Greater BendigoGreater DandenongHobsons BayWhittleseaWyndhamWhitehorseManninghamMorelandDarebinBanyuleKnoxBrimbank

                            Council planning resources

                            Application resources ndashexamplesDELWP Practice Note ndashformal guide to the new controlsMoreland ndash application checklists and example plans for a variety of residential developmentsPort Philip ndash compliance guidelines checklist and examplesMoonee Valley ndash checklists and example plans including site management plans Greater Bendigo ndash WSUD kitBayside ndash application guidelines and example plans

                            59

                            Technical guidelines (modelling design construction)

                            Melbourne Water

                            STORM calculatorMUSIC auditor - lsquohow torsquo video here

                            Melbourne Water technical guidelines page- WSUD asset life cycle costings and model maintenance guidelines- MUSIC guidelines- Stormwater harvesting guidelines- WSUD life cycle costings and

                            maintenance guidelines- Design and construction guidelines

                            for variety of assetshttpswwwmelbournewatercomauplanning-and-buildingdeveloper-guides-and-resourcesguidelines-drawings-and-checklistsguidelines

                            Council

                            South-Eastern Growth Council WSUD guidelines ndash note that some individual Councils have their own addendumsMelbournePort PhilipNorth-West Growth Council WSUD guidelines - note that some individual Councils have their own addendumsGreater BendigoMilduraBallaratBaw BawWyndhamMoreland ndash tree pits and raingardens

                            60

                            IWM

                            Example Council IWM strategiesMelbourneCaseyMonashKingston

                            Resilient Melbourne ndash IWM information lsquohubrsquoClearwater ndash capacity building and case studiesMelbourne Water ndash funding opportunities for IWM projects

                            Stormwater offset schemes

                            KingstonGreater GeelongMelbourne Water ndash non scheme contributions

                            Site management

                            EPA guidelines- management of erosion and sediment

                            Next steps and other stormwater initiatives

                            Emma Stewart DELWP

                            62

                            Next steps

                            bull Trainingbull The EPArsquos BPEM Reviewbull Offsets policybull Review of STORM bull Building controls

                            63

                            State Stormwater policies

                            64

                            Thank you

                            • Slide Number 1
                            • Slide Number 2
                            • History of WSUD
                            • History of WSUD
                            • Transformational change in urban water
                            • Inconsistencies and inequities in our approach to stormwater management
                            • Slide Number 8
                            • Terms of Reference
                            • Improving Stormwater Management Advisory Committee
                            • Wide consultation
                            • Stakeholder feedback
                            • Stakeholder feedback
                            • Committee submitted its report in September 2018
                            • Committee Recomendations
                            • Planning reforms
                            • Future policy directions
                            • Supporting actions
                            • Slide Number 19
                            • Government response (to date)
                            • Longer term recommendations
                            • State-based planning requirements (lsquobeforersquo)
                            • State-based planning requirements (lsquoafterrsquo)
                            • Development types (volume)
                            • Slide Number 25
                            • Amendment VC154
                            • Whatrsquos in
                            • Slide Number 28
                            • Key elements of clauses
                            • Clause 5318 ndash subdivision
                            • Clause 5318 ndash Buildings and works
                            • Townhouses - Standard B9
                            • Slide Number 33
                            • Slide Number 34
                            • Slide Number 35
                            • Slide Number 36
                            • Slide Number 37
                            • Buildings and works - Site management standard
                            • Site management
                            • Planning Advisory Note No 75
                            • Slide Number 41
                            • Slide Number 42
                            • Slide Number 43
                            • Slide Number 44
                            • Slide Number 45
                            • Slide Number 46
                            • Slide Number 47
                            • Slide Number 48
                            • Slide Number 49
                            • Slide Number 50
                            • Slide Number 51
                            • Slide Number 52
                            • Slide Number 53
                            • Slide Number 54
                            • Slide Number 55
                            • Slide Number 56
                            • Slide Number 57
                            • Slide Number 58
                            • Slide Number 59
                            • Slide Number 60
                            • Slide Number 61
                            • Next steps
                            • State Stormwater policies
                            • Slide Number 64

                              16

                              Planning reforms

                              Rec 1 ndash Expand the stormwater planning provisions (phase 1) That the Victorian Government amend the VPPs to expand the current stormwater management requirements to

                              bull commercial subdivisions and developmentsbull industrial subdivisions and developmentsbull public-use developmentsbull multi-dwelling residential subdivisions and developments

                              Rec 2 ndash Expand the stormwater planning provisions (phase 2) That subject to further consultation the development of deemed-to-satisfy solutions (rec 12) adequate guidance and tools (recs 13 14 and 15) and offset processes (rec 5) the Victorian Government amend the VPPs to expand the current stormwater management requirements to

                              bull single-dwelling developmentsbull extensions over 50 m2

                              Rec 3 ndash Insert an IWM clause into the Planning Policy Framework (PPF) That the Victorian Government amend the PPF to embed the concepts of IWM objectives and strategies

                              17

                              Future policy directions

                              Rec 4 ndash Amend the building and plumbing controls

                              Rec 5 ndash Establish effective offsetting arrangements

                              Rec 6 ndash Clarify local governmentsrsquo roles and responsibilities

                              Rec 7 ndash Strengthen compliance requirements

                              Rec 8 ndash Determine funding sources for public stormwater infrastructure

                              Rec 9 ndash Link water management with urban planning

                              Rec 10 ndash Set stronger place-based BPEM stormwater performance objectives

                              18

                              Rec 11 ndash Strengthen enforcement of stormwater construction requirements

                              Rec 12 ndash Prepare deemed-to-satisfy solutions

                              Rec 13 ndash Review the STORM and MUSIC tools

                              Rec 14 ndash Build technical expertise

                              Rec 15 ndash Improve guidance

                              Rec 16 ndash Improve awareness of the VPP changes

                              Rec 17 ndash Investigate options for rainwater tank maintenance and operation

                              Rec 18 ndash Broaden rating systems to include IWM

                              Supporting actions

                              The new stormwater provisions

                              Emma Stewart DELWP

                              20

                              Government response (to date)

                              21

                              Government is currently considering the committeersquos longer-term recommendations and is working with key stakeholders to determine the most effective response and pathways for implementation

                              Longer term recommendations

                              22

                              State-based planning requirements (lsquobeforersquo)

                              Sourced ELM 2018

                              23

                              State-based planning requirements (lsquoafterrsquo)

                              24

                              Development types (volume)

                              Future development estimated impervious area 2020-2050

                              25

                              The nitty grittyhellip

                              26

                              Amendment VC154

                              Victoria Planning Provision changesbull New clause (5318) and changes to an existing clause

                              (5503) to expand the stormwater requirements to more development types

                              bull New objectives to manage toxicants and encourage broader benefits of stormwater management

                              27

                              Whatrsquos in

                              Applies to an application tobull subdivide land bull construct a building bull construct or carry out works

                              In both hellip

                              Clause 5318bull commercial zonesbull industrial zonesbull public-use zones

                              Clause 5518 bull Construct townhouses

                              Whatrsquos out of clause 5318

                              bull Developments and subdivisions approved or lodged prior to the amendment

                              bull Developments which do not require planning permission

                              bull Vicsmart applications

                              bull Applications for land within development or incorporated plans approved before the amendment

                              bull Extensions and works lt 50m2

                              bull Applications after the amendment to amend existing planning permits

                              If in doubt ask a planner

                              29

                              Key elements of clauses

                              Industrial commercial applications (Clause 5318)tobull subdivide land bull construct a building bull construct or carry out works

                              Stormwater management objectives + standard (W1)

                              Stormwater management objectives + standard (W2)+ Site management objectives + standard (W3)

                              Decision guidelines

                              Same for Clause 5503 (townhouses)

                              30

                              Clause 5318 ndash subdivision

                              Stormwater management standard W1 The stormwater management system should be bull Designed and managed in accordance with the requirements and

                              to the satisfaction of the relevant drainage authoritybull Designed and managed in accordance with the requirements and

                              to the satisfaction of the water authority where reuse of stormwater is proposed

                              bull Designed to meet the current best practice performance objectives for stormwater quality as contained in the BPEM

                              bull Designed to ensure that flows downstream of the subdivision site are restricted to pre-development levels unless increased flows are approved by the relevant drainage authority and there are no detrimental downstream impacts

                              bull Designed to contribute to cooling improving local habitat and providing attractive and enjoyable spaces

                              31

                              Clause 5318 ndash Buildings and works

                              Standard W2The stormwater management system should be designed to

                              bull Meet the current best practice performance objectives for stormwater quality as contained in the BPEM

                              bull Contribute to cooling improving local habitat and providing attractive and enjoyable spaces

                              bull Minimise the impact of chemical pollutants and other toxicants including by but not limited to bunding and covering of roofing of storage loading and work areas

                              32

                              Townhouses - Standard B9

                              Clause 5503 ndash Permeability and stormwater management objectives and standard B9

                              Objectivesbull Similar to 5318 (including the cooling liveability

                              objective)bull gt20 perviousness objective (unchanged)

                              Standardbull NEW - cooling liveability objectivebull NEW ndash requirement to meet BPEM

                              What does this all mean

                              34

                              Clause 5318 - Whatrsquos in

                              35

                              Urban cooling Reduce heat radiation from buildings and hard surfaces throughbull Shade trees in car parks or over driveways bull More open space and treesbull Green roofsbull Green walls

                              36

                              Optionsbull Passive irrigationbull Integrate assets into

                              communal open spacebull Tree pits and permeable

                              paving (driveways and carpark)

                              bull Stormwater harvesting (major developments only)

                              Infiltration habitat amenity

                              37

                              Control harmful chemicals

                              Optionsbull Careful layoutbull Consider alternative less harmful substancesbull Roofed designated storage areabull Internal drainage design to sewer or a treatment devicebull Bunding

                              38

                              Standard W3Standard W3 requires that application describe how the site will be managed prior to and during the construction period The application should set out requirements for managingbull Erosion and sedimentbull Stormwaterbull Litter concrete and other construction wastesbull Chemical contamination

                              Buildings and works - Site management standard

                              39

                              Site management

                              40

                              Planning Advisory Note No 75

                              Implications for industry

                              Kate MatthewsStormwater Victoria

                              1 Development proponents- Developers- Consultants (engineers stormwater specialists and planners)- Council (when developing public land lt$1 million)

                              2 Development assessors- Council statutory planners- Council internal referrals (engineering assets ESD stormwater officers)

                              3 Strategy- Council strategic planners

                              4 Melbourne Water

                              Whorsquos affected

                              43

                              What are the implications

                              bull BPEM - Itrsquos not just subdivisions any more

                              bull Cost ndash offset or assetbull Early planning and integration ndash more

                              work up frontbull Not just engineeringbull Varying Council skills and experience

                              Development Proponents

                              44

                              If already have a local policy for WSUDESD no real change

                              If notbull Workload and resourcingbull Increased detail and technical

                              contentbull Administrative arrangements ndash

                              referrals permit conditions ndashmake sure you make 60 stat days

                              bull Applicant pressure ndash what do you want

                              bull Assets

                              Development Assessors

                              45

                              bull Structure plans and rezoning ndashopportunities for localregional approach

                              bull IWM and Stormwater Management Plans ndash opportunities for these to be implemented through the controls spatial opportunities

                              bull Opportunities for development of Council offset strategies

                              Strategy

                              Offsets

                              bull Developer enters into an agreement with relevant drainage authority to financially contribute to off-site stormwatermanagement in lieu of providing on-site treatment

                              bull Already available for residential subdivisions in Melbourne (Clause 56) through MWCs Stormwater Quality Offset scheme

                              What are stormwater quality offsets

                              X Not drainage contributions (MWC drainage scheme)

                              X Not development contributions (DCPICP)

                              47

                              When to use

                              bull Not in MW DSS or growth area where therersquos an existing framework for funding SW treatment

                              bull Onsite treatment not practical or desirable

                              bull To fund planned localregional stormwater treatment works in that catchment via an existing offset scheme

                              bull Council and developer both agree to it

                              48

                              OffsetsExample ndash Kingston Offset Scheme

                              Asset ownership and maintenance

                              bull Whorsquos going to own itbull Whorsquos going to maintain itbull How do you maintain itbull How much will it cost

                              bull Where is itbull Is maintenance burden

                              practical for likely future owners

                              bull Whorsquos going to monitor compliance and how

                              The detail is in the permit conditions

                              Application requirements

                              ldquoAn application must be accompanied by details of the proposed stormwater management system including drainage works and retention detention and discharges of stormwater to the drainage systemrdquo ndash Clause 5318

                              What does the planning scheme require

                              But alsohellipNeed to provide sufficient information to Council which demonstrates that you comply and how you comply with all the other standards ndash eg urban coolinghabitatetc BPEM site management pollutant control infiltration (as relevant to development type

                              51

                              1 PlansWhat are you doing where is it going and does it fit

                              2 ModellingDo you (or can you) meet BPEM requirements

                              3 Written response to standardsHow does your proposal comply with the requirements

                              52

                              Application

                              bull Site plan ndash show all assetsWSUD treatments and any IWM features on the site layout plan with everything else

                              bull Landscape plan ndash if planting design passive irrigation etc forms part of response to requirements show

                              bull Site management plan (depending on Council)

                              bull Separate WSUDIWM plan showing all features on a stripped back background

                              bull Concept WSUD asset design ndash larger assets only (wetlands bioretention basins sed basin etc) ndash sufficient design detail to confirm spatial requirements

                              PlansPermit conditions

                              bull Detailed engineering design bull Site Management Plan (final)bull Asset maintenance plan (final)bull Handover arrangements (if public)

                              54

                              STORM ndash Online toolbull Print out of STORM reportbull Make sure meets 100 or

                              morebull Make sure report inputs and

                              results match plan

                              Modelling - SWQ

                              MUSIC ndash Proprietary softwarebull Provide a copy of the model filebull Print out the modelling resultsbull Provide summary of your model

                              inputs for each treatment train (iecatchment size impervious treatment area etc)

                              bull Provide a print out of the model schematic

                              Bonus points bull Provide details of model

                              parametersbull Provide results of MUSIC auditor

                              run (if using Melbourne Water MUSIC Guidelines)

                              56

                              Assessment against standards

                              bull Say what you have done (or will do) to meet each standardbull Donrsquot forget (if WSUD) details of maintenance and asset

                              ownershipbull Where applicable be explicit why yoursquove chosen (or not chosen) to

                              respond the way you have Egbull Opportunitiesbull Site constraintsbull Practicaloperational issues bull Brief dot point summary of options analysis if complex

                              bull Make sure if it doesnrsquot meet the standard it meets the objectivebull Make sure shown on plan and consistent with modelling and rest of

                              documentation

                              57

                              Resources

                              Local stormwaterWSUD policiesBaysideKingstonCaseyMonashMelbourneYarraMoonee ValleyPort PhilipStonningtonHumeCampaspeBass Coast

                              Local ESD (including IWM) policies Greater BendigoGreater DandenongHobsons BayWhittleseaWyndhamWhitehorseManninghamMorelandDarebinBanyuleKnoxBrimbank

                              Council planning resources

                              Application resources ndashexamplesDELWP Practice Note ndashformal guide to the new controlsMoreland ndash application checklists and example plans for a variety of residential developmentsPort Philip ndash compliance guidelines checklist and examplesMoonee Valley ndash checklists and example plans including site management plans Greater Bendigo ndash WSUD kitBayside ndash application guidelines and example plans

                              59

                              Technical guidelines (modelling design construction)

                              Melbourne Water

                              STORM calculatorMUSIC auditor - lsquohow torsquo video here

                              Melbourne Water technical guidelines page- WSUD asset life cycle costings and model maintenance guidelines- MUSIC guidelines- Stormwater harvesting guidelines- WSUD life cycle costings and

                              maintenance guidelines- Design and construction guidelines

                              for variety of assetshttpswwwmelbournewatercomauplanning-and-buildingdeveloper-guides-and-resourcesguidelines-drawings-and-checklistsguidelines

                              Council

                              South-Eastern Growth Council WSUD guidelines ndash note that some individual Councils have their own addendumsMelbournePort PhilipNorth-West Growth Council WSUD guidelines - note that some individual Councils have their own addendumsGreater BendigoMilduraBallaratBaw BawWyndhamMoreland ndash tree pits and raingardens

                              60

                              IWM

                              Example Council IWM strategiesMelbourneCaseyMonashKingston

                              Resilient Melbourne ndash IWM information lsquohubrsquoClearwater ndash capacity building and case studiesMelbourne Water ndash funding opportunities for IWM projects

                              Stormwater offset schemes

                              KingstonGreater GeelongMelbourne Water ndash non scheme contributions

                              Site management

                              EPA guidelines- management of erosion and sediment

                              Next steps and other stormwater initiatives

                              Emma Stewart DELWP

                              62

                              Next steps

                              bull Trainingbull The EPArsquos BPEM Reviewbull Offsets policybull Review of STORM bull Building controls

                              63

                              State Stormwater policies

                              64

                              Thank you

                              • Slide Number 1
                              • Slide Number 2
                              • History of WSUD
                              • History of WSUD
                              • Transformational change in urban water
                              • Inconsistencies and inequities in our approach to stormwater management
                              • Slide Number 8
                              • Terms of Reference
                              • Improving Stormwater Management Advisory Committee
                              • Wide consultation
                              • Stakeholder feedback
                              • Stakeholder feedback
                              • Committee submitted its report in September 2018
                              • Committee Recomendations
                              • Planning reforms
                              • Future policy directions
                              • Supporting actions
                              • Slide Number 19
                              • Government response (to date)
                              • Longer term recommendations
                              • State-based planning requirements (lsquobeforersquo)
                              • State-based planning requirements (lsquoafterrsquo)
                              • Development types (volume)
                              • Slide Number 25
                              • Amendment VC154
                              • Whatrsquos in
                              • Slide Number 28
                              • Key elements of clauses
                              • Clause 5318 ndash subdivision
                              • Clause 5318 ndash Buildings and works
                              • Townhouses - Standard B9
                              • Slide Number 33
                              • Slide Number 34
                              • Slide Number 35
                              • Slide Number 36
                              • Slide Number 37
                              • Buildings and works - Site management standard
                              • Site management
                              • Planning Advisory Note No 75
                              • Slide Number 41
                              • Slide Number 42
                              • Slide Number 43
                              • Slide Number 44
                              • Slide Number 45
                              • Slide Number 46
                              • Slide Number 47
                              • Slide Number 48
                              • Slide Number 49
                              • Slide Number 50
                              • Slide Number 51
                              • Slide Number 52
                              • Slide Number 53
                              • Slide Number 54
                              • Slide Number 55
                              • Slide Number 56
                              • Slide Number 57
                              • Slide Number 58
                              • Slide Number 59
                              • Slide Number 60
                              • Slide Number 61
                              • Next steps
                              • State Stormwater policies
                              • Slide Number 64

                                17

                                Future policy directions

                                Rec 4 ndash Amend the building and plumbing controls

                                Rec 5 ndash Establish effective offsetting arrangements

                                Rec 6 ndash Clarify local governmentsrsquo roles and responsibilities

                                Rec 7 ndash Strengthen compliance requirements

                                Rec 8 ndash Determine funding sources for public stormwater infrastructure

                                Rec 9 ndash Link water management with urban planning

                                Rec 10 ndash Set stronger place-based BPEM stormwater performance objectives

                                18

                                Rec 11 ndash Strengthen enforcement of stormwater construction requirements

                                Rec 12 ndash Prepare deemed-to-satisfy solutions

                                Rec 13 ndash Review the STORM and MUSIC tools

                                Rec 14 ndash Build technical expertise

                                Rec 15 ndash Improve guidance

                                Rec 16 ndash Improve awareness of the VPP changes

                                Rec 17 ndash Investigate options for rainwater tank maintenance and operation

                                Rec 18 ndash Broaden rating systems to include IWM

                                Supporting actions

                                The new stormwater provisions

                                Emma Stewart DELWP

                                20

                                Government response (to date)

                                21

                                Government is currently considering the committeersquos longer-term recommendations and is working with key stakeholders to determine the most effective response and pathways for implementation

                                Longer term recommendations

                                22

                                State-based planning requirements (lsquobeforersquo)

                                Sourced ELM 2018

                                23

                                State-based planning requirements (lsquoafterrsquo)

                                24

                                Development types (volume)

                                Future development estimated impervious area 2020-2050

                                25

                                The nitty grittyhellip

                                26

                                Amendment VC154

                                Victoria Planning Provision changesbull New clause (5318) and changes to an existing clause

                                (5503) to expand the stormwater requirements to more development types

                                bull New objectives to manage toxicants and encourage broader benefits of stormwater management

                                27

                                Whatrsquos in

                                Applies to an application tobull subdivide land bull construct a building bull construct or carry out works

                                In both hellip

                                Clause 5318bull commercial zonesbull industrial zonesbull public-use zones

                                Clause 5518 bull Construct townhouses

                                Whatrsquos out of clause 5318

                                bull Developments and subdivisions approved or lodged prior to the amendment

                                bull Developments which do not require planning permission

                                bull Vicsmart applications

                                bull Applications for land within development or incorporated plans approved before the amendment

                                bull Extensions and works lt 50m2

                                bull Applications after the amendment to amend existing planning permits

                                If in doubt ask a planner

                                29

                                Key elements of clauses

                                Industrial commercial applications (Clause 5318)tobull subdivide land bull construct a building bull construct or carry out works

                                Stormwater management objectives + standard (W1)

                                Stormwater management objectives + standard (W2)+ Site management objectives + standard (W3)

                                Decision guidelines

                                Same for Clause 5503 (townhouses)

                                30

                                Clause 5318 ndash subdivision

                                Stormwater management standard W1 The stormwater management system should be bull Designed and managed in accordance with the requirements and

                                to the satisfaction of the relevant drainage authoritybull Designed and managed in accordance with the requirements and

                                to the satisfaction of the water authority where reuse of stormwater is proposed

                                bull Designed to meet the current best practice performance objectives for stormwater quality as contained in the BPEM

                                bull Designed to ensure that flows downstream of the subdivision site are restricted to pre-development levels unless increased flows are approved by the relevant drainage authority and there are no detrimental downstream impacts

                                bull Designed to contribute to cooling improving local habitat and providing attractive and enjoyable spaces

                                31

                                Clause 5318 ndash Buildings and works

                                Standard W2The stormwater management system should be designed to

                                bull Meet the current best practice performance objectives for stormwater quality as contained in the BPEM

                                bull Contribute to cooling improving local habitat and providing attractive and enjoyable spaces

                                bull Minimise the impact of chemical pollutants and other toxicants including by but not limited to bunding and covering of roofing of storage loading and work areas

                                32

                                Townhouses - Standard B9

                                Clause 5503 ndash Permeability and stormwater management objectives and standard B9

                                Objectivesbull Similar to 5318 (including the cooling liveability

                                objective)bull gt20 perviousness objective (unchanged)

                                Standardbull NEW - cooling liveability objectivebull NEW ndash requirement to meet BPEM

                                What does this all mean

                                34

                                Clause 5318 - Whatrsquos in

                                35

                                Urban cooling Reduce heat radiation from buildings and hard surfaces throughbull Shade trees in car parks or over driveways bull More open space and treesbull Green roofsbull Green walls

                                36

                                Optionsbull Passive irrigationbull Integrate assets into

                                communal open spacebull Tree pits and permeable

                                paving (driveways and carpark)

                                bull Stormwater harvesting (major developments only)

                                Infiltration habitat amenity

                                37

                                Control harmful chemicals

                                Optionsbull Careful layoutbull Consider alternative less harmful substancesbull Roofed designated storage areabull Internal drainage design to sewer or a treatment devicebull Bunding

                                38

                                Standard W3Standard W3 requires that application describe how the site will be managed prior to and during the construction period The application should set out requirements for managingbull Erosion and sedimentbull Stormwaterbull Litter concrete and other construction wastesbull Chemical contamination

                                Buildings and works - Site management standard

                                39

                                Site management

                                40

                                Planning Advisory Note No 75

                                Implications for industry

                                Kate MatthewsStormwater Victoria

                                1 Development proponents- Developers- Consultants (engineers stormwater specialists and planners)- Council (when developing public land lt$1 million)

                                2 Development assessors- Council statutory planners- Council internal referrals (engineering assets ESD stormwater officers)

                                3 Strategy- Council strategic planners

                                4 Melbourne Water

                                Whorsquos affected

                                43

                                What are the implications

                                bull BPEM - Itrsquos not just subdivisions any more

                                bull Cost ndash offset or assetbull Early planning and integration ndash more

                                work up frontbull Not just engineeringbull Varying Council skills and experience

                                Development Proponents

                                44

                                If already have a local policy for WSUDESD no real change

                                If notbull Workload and resourcingbull Increased detail and technical

                                contentbull Administrative arrangements ndash

                                referrals permit conditions ndashmake sure you make 60 stat days

                                bull Applicant pressure ndash what do you want

                                bull Assets

                                Development Assessors

                                45

                                bull Structure plans and rezoning ndashopportunities for localregional approach

                                bull IWM and Stormwater Management Plans ndash opportunities for these to be implemented through the controls spatial opportunities

                                bull Opportunities for development of Council offset strategies

                                Strategy

                                Offsets

                                bull Developer enters into an agreement with relevant drainage authority to financially contribute to off-site stormwatermanagement in lieu of providing on-site treatment

                                bull Already available for residential subdivisions in Melbourne (Clause 56) through MWCs Stormwater Quality Offset scheme

                                What are stormwater quality offsets

                                X Not drainage contributions (MWC drainage scheme)

                                X Not development contributions (DCPICP)

                                47

                                When to use

                                bull Not in MW DSS or growth area where therersquos an existing framework for funding SW treatment

                                bull Onsite treatment not practical or desirable

                                bull To fund planned localregional stormwater treatment works in that catchment via an existing offset scheme

                                bull Council and developer both agree to it

                                48

                                OffsetsExample ndash Kingston Offset Scheme

                                Asset ownership and maintenance

                                bull Whorsquos going to own itbull Whorsquos going to maintain itbull How do you maintain itbull How much will it cost

                                bull Where is itbull Is maintenance burden

                                practical for likely future owners

                                bull Whorsquos going to monitor compliance and how

                                The detail is in the permit conditions

                                Application requirements

                                ldquoAn application must be accompanied by details of the proposed stormwater management system including drainage works and retention detention and discharges of stormwater to the drainage systemrdquo ndash Clause 5318

                                What does the planning scheme require

                                But alsohellipNeed to provide sufficient information to Council which demonstrates that you comply and how you comply with all the other standards ndash eg urban coolinghabitatetc BPEM site management pollutant control infiltration (as relevant to development type

                                51

                                1 PlansWhat are you doing where is it going and does it fit

                                2 ModellingDo you (or can you) meet BPEM requirements

                                3 Written response to standardsHow does your proposal comply with the requirements

                                52

                                Application

                                bull Site plan ndash show all assetsWSUD treatments and any IWM features on the site layout plan with everything else

                                bull Landscape plan ndash if planting design passive irrigation etc forms part of response to requirements show

                                bull Site management plan (depending on Council)

                                bull Separate WSUDIWM plan showing all features on a stripped back background

                                bull Concept WSUD asset design ndash larger assets only (wetlands bioretention basins sed basin etc) ndash sufficient design detail to confirm spatial requirements

                                PlansPermit conditions

                                bull Detailed engineering design bull Site Management Plan (final)bull Asset maintenance plan (final)bull Handover arrangements (if public)

                                54

                                STORM ndash Online toolbull Print out of STORM reportbull Make sure meets 100 or

                                morebull Make sure report inputs and

                                results match plan

                                Modelling - SWQ

                                MUSIC ndash Proprietary softwarebull Provide a copy of the model filebull Print out the modelling resultsbull Provide summary of your model

                                inputs for each treatment train (iecatchment size impervious treatment area etc)

                                bull Provide a print out of the model schematic

                                Bonus points bull Provide details of model

                                parametersbull Provide results of MUSIC auditor

                                run (if using Melbourne Water MUSIC Guidelines)

                                56

                                Assessment against standards

                                bull Say what you have done (or will do) to meet each standardbull Donrsquot forget (if WSUD) details of maintenance and asset

                                ownershipbull Where applicable be explicit why yoursquove chosen (or not chosen) to

                                respond the way you have Egbull Opportunitiesbull Site constraintsbull Practicaloperational issues bull Brief dot point summary of options analysis if complex

                                bull Make sure if it doesnrsquot meet the standard it meets the objectivebull Make sure shown on plan and consistent with modelling and rest of

                                documentation

                                57

                                Resources

                                Local stormwaterWSUD policiesBaysideKingstonCaseyMonashMelbourneYarraMoonee ValleyPort PhilipStonningtonHumeCampaspeBass Coast

                                Local ESD (including IWM) policies Greater BendigoGreater DandenongHobsons BayWhittleseaWyndhamWhitehorseManninghamMorelandDarebinBanyuleKnoxBrimbank

                                Council planning resources

                                Application resources ndashexamplesDELWP Practice Note ndashformal guide to the new controlsMoreland ndash application checklists and example plans for a variety of residential developmentsPort Philip ndash compliance guidelines checklist and examplesMoonee Valley ndash checklists and example plans including site management plans Greater Bendigo ndash WSUD kitBayside ndash application guidelines and example plans

                                59

                                Technical guidelines (modelling design construction)

                                Melbourne Water

                                STORM calculatorMUSIC auditor - lsquohow torsquo video here

                                Melbourne Water technical guidelines page- WSUD asset life cycle costings and model maintenance guidelines- MUSIC guidelines- Stormwater harvesting guidelines- WSUD life cycle costings and

                                maintenance guidelines- Design and construction guidelines

                                for variety of assetshttpswwwmelbournewatercomauplanning-and-buildingdeveloper-guides-and-resourcesguidelines-drawings-and-checklistsguidelines

                                Council

                                South-Eastern Growth Council WSUD guidelines ndash note that some individual Councils have their own addendumsMelbournePort PhilipNorth-West Growth Council WSUD guidelines - note that some individual Councils have their own addendumsGreater BendigoMilduraBallaratBaw BawWyndhamMoreland ndash tree pits and raingardens

                                60

                                IWM

                                Example Council IWM strategiesMelbourneCaseyMonashKingston

                                Resilient Melbourne ndash IWM information lsquohubrsquoClearwater ndash capacity building and case studiesMelbourne Water ndash funding opportunities for IWM projects

                                Stormwater offset schemes

                                KingstonGreater GeelongMelbourne Water ndash non scheme contributions

                                Site management

                                EPA guidelines- management of erosion and sediment

                                Next steps and other stormwater initiatives

                                Emma Stewart DELWP

                                62

                                Next steps

                                bull Trainingbull The EPArsquos BPEM Reviewbull Offsets policybull Review of STORM bull Building controls

                                63

                                State Stormwater policies

                                64

                                Thank you

                                • Slide Number 1
                                • Slide Number 2
                                • History of WSUD
                                • History of WSUD
                                • Transformational change in urban water
                                • Inconsistencies and inequities in our approach to stormwater management
                                • Slide Number 8
                                • Terms of Reference
                                • Improving Stormwater Management Advisory Committee
                                • Wide consultation
                                • Stakeholder feedback
                                • Stakeholder feedback
                                • Committee submitted its report in September 2018
                                • Committee Recomendations
                                • Planning reforms
                                • Future policy directions
                                • Supporting actions
                                • Slide Number 19
                                • Government response (to date)
                                • Longer term recommendations
                                • State-based planning requirements (lsquobeforersquo)
                                • State-based planning requirements (lsquoafterrsquo)
                                • Development types (volume)
                                • Slide Number 25
                                • Amendment VC154
                                • Whatrsquos in
                                • Slide Number 28
                                • Key elements of clauses
                                • Clause 5318 ndash subdivision
                                • Clause 5318 ndash Buildings and works
                                • Townhouses - Standard B9
                                • Slide Number 33
                                • Slide Number 34
                                • Slide Number 35
                                • Slide Number 36
                                • Slide Number 37
                                • Buildings and works - Site management standard
                                • Site management
                                • Planning Advisory Note No 75
                                • Slide Number 41
                                • Slide Number 42
                                • Slide Number 43
                                • Slide Number 44
                                • Slide Number 45
                                • Slide Number 46
                                • Slide Number 47
                                • Slide Number 48
                                • Slide Number 49
                                • Slide Number 50
                                • Slide Number 51
                                • Slide Number 52
                                • Slide Number 53
                                • Slide Number 54
                                • Slide Number 55
                                • Slide Number 56
                                • Slide Number 57
                                • Slide Number 58
                                • Slide Number 59
                                • Slide Number 60
                                • Slide Number 61
                                • Next steps
                                • State Stormwater policies
                                • Slide Number 64

                                  18

                                  Rec 11 ndash Strengthen enforcement of stormwater construction requirements

                                  Rec 12 ndash Prepare deemed-to-satisfy solutions

                                  Rec 13 ndash Review the STORM and MUSIC tools

                                  Rec 14 ndash Build technical expertise

                                  Rec 15 ndash Improve guidance

                                  Rec 16 ndash Improve awareness of the VPP changes

                                  Rec 17 ndash Investigate options for rainwater tank maintenance and operation

                                  Rec 18 ndash Broaden rating systems to include IWM

                                  Supporting actions

                                  The new stormwater provisions

                                  Emma Stewart DELWP

                                  20

                                  Government response (to date)

                                  21

                                  Government is currently considering the committeersquos longer-term recommendations and is working with key stakeholders to determine the most effective response and pathways for implementation

                                  Longer term recommendations

                                  22

                                  State-based planning requirements (lsquobeforersquo)

                                  Sourced ELM 2018

                                  23

                                  State-based planning requirements (lsquoafterrsquo)

                                  24

                                  Development types (volume)

                                  Future development estimated impervious area 2020-2050

                                  25

                                  The nitty grittyhellip

                                  26

                                  Amendment VC154

                                  Victoria Planning Provision changesbull New clause (5318) and changes to an existing clause

                                  (5503) to expand the stormwater requirements to more development types

                                  bull New objectives to manage toxicants and encourage broader benefits of stormwater management

                                  27

                                  Whatrsquos in

                                  Applies to an application tobull subdivide land bull construct a building bull construct or carry out works

                                  In both hellip

                                  Clause 5318bull commercial zonesbull industrial zonesbull public-use zones

                                  Clause 5518 bull Construct townhouses

                                  Whatrsquos out of clause 5318

                                  bull Developments and subdivisions approved or lodged prior to the amendment

                                  bull Developments which do not require planning permission

                                  bull Vicsmart applications

                                  bull Applications for land within development or incorporated plans approved before the amendment

                                  bull Extensions and works lt 50m2

                                  bull Applications after the amendment to amend existing planning permits

                                  If in doubt ask a planner

                                  29

                                  Key elements of clauses

                                  Industrial commercial applications (Clause 5318)tobull subdivide land bull construct a building bull construct or carry out works

                                  Stormwater management objectives + standard (W1)

                                  Stormwater management objectives + standard (W2)+ Site management objectives + standard (W3)

                                  Decision guidelines

                                  Same for Clause 5503 (townhouses)

                                  30

                                  Clause 5318 ndash subdivision

                                  Stormwater management standard W1 The stormwater management system should be bull Designed and managed in accordance with the requirements and

                                  to the satisfaction of the relevant drainage authoritybull Designed and managed in accordance with the requirements and

                                  to the satisfaction of the water authority where reuse of stormwater is proposed

                                  bull Designed to meet the current best practice performance objectives for stormwater quality as contained in the BPEM

                                  bull Designed to ensure that flows downstream of the subdivision site are restricted to pre-development levels unless increased flows are approved by the relevant drainage authority and there are no detrimental downstream impacts

                                  bull Designed to contribute to cooling improving local habitat and providing attractive and enjoyable spaces

                                  31

                                  Clause 5318 ndash Buildings and works

                                  Standard W2The stormwater management system should be designed to

                                  bull Meet the current best practice performance objectives for stormwater quality as contained in the BPEM

                                  bull Contribute to cooling improving local habitat and providing attractive and enjoyable spaces

                                  bull Minimise the impact of chemical pollutants and other toxicants including by but not limited to bunding and covering of roofing of storage loading and work areas

                                  32

                                  Townhouses - Standard B9

                                  Clause 5503 ndash Permeability and stormwater management objectives and standard B9

                                  Objectivesbull Similar to 5318 (including the cooling liveability

                                  objective)bull gt20 perviousness objective (unchanged)

                                  Standardbull NEW - cooling liveability objectivebull NEW ndash requirement to meet BPEM

                                  What does this all mean

                                  34

                                  Clause 5318 - Whatrsquos in

                                  35

                                  Urban cooling Reduce heat radiation from buildings and hard surfaces throughbull Shade trees in car parks or over driveways bull More open space and treesbull Green roofsbull Green walls

                                  36

                                  Optionsbull Passive irrigationbull Integrate assets into

                                  communal open spacebull Tree pits and permeable

                                  paving (driveways and carpark)

                                  bull Stormwater harvesting (major developments only)

                                  Infiltration habitat amenity

                                  37

                                  Control harmful chemicals

                                  Optionsbull Careful layoutbull Consider alternative less harmful substancesbull Roofed designated storage areabull Internal drainage design to sewer or a treatment devicebull Bunding

                                  38

                                  Standard W3Standard W3 requires that application describe how the site will be managed prior to and during the construction period The application should set out requirements for managingbull Erosion and sedimentbull Stormwaterbull Litter concrete and other construction wastesbull Chemical contamination

                                  Buildings and works - Site management standard

                                  39

                                  Site management

                                  40

                                  Planning Advisory Note No 75

                                  Implications for industry

                                  Kate MatthewsStormwater Victoria

                                  1 Development proponents- Developers- Consultants (engineers stormwater specialists and planners)- Council (when developing public land lt$1 million)

                                  2 Development assessors- Council statutory planners- Council internal referrals (engineering assets ESD stormwater officers)

                                  3 Strategy- Council strategic planners

                                  4 Melbourne Water

                                  Whorsquos affected

                                  43

                                  What are the implications

                                  bull BPEM - Itrsquos not just subdivisions any more

                                  bull Cost ndash offset or assetbull Early planning and integration ndash more

                                  work up frontbull Not just engineeringbull Varying Council skills and experience

                                  Development Proponents

                                  44

                                  If already have a local policy for WSUDESD no real change

                                  If notbull Workload and resourcingbull Increased detail and technical

                                  contentbull Administrative arrangements ndash

                                  referrals permit conditions ndashmake sure you make 60 stat days

                                  bull Applicant pressure ndash what do you want

                                  bull Assets

                                  Development Assessors

                                  45

                                  bull Structure plans and rezoning ndashopportunities for localregional approach

                                  bull IWM and Stormwater Management Plans ndash opportunities for these to be implemented through the controls spatial opportunities

                                  bull Opportunities for development of Council offset strategies

                                  Strategy

                                  Offsets

                                  bull Developer enters into an agreement with relevant drainage authority to financially contribute to off-site stormwatermanagement in lieu of providing on-site treatment

                                  bull Already available for residential subdivisions in Melbourne (Clause 56) through MWCs Stormwater Quality Offset scheme

                                  What are stormwater quality offsets

                                  X Not drainage contributions (MWC drainage scheme)

                                  X Not development contributions (DCPICP)

                                  47

                                  When to use

                                  bull Not in MW DSS or growth area where therersquos an existing framework for funding SW treatment

                                  bull Onsite treatment not practical or desirable

                                  bull To fund planned localregional stormwater treatment works in that catchment via an existing offset scheme

                                  bull Council and developer both agree to it

                                  48

                                  OffsetsExample ndash Kingston Offset Scheme

                                  Asset ownership and maintenance

                                  bull Whorsquos going to own itbull Whorsquos going to maintain itbull How do you maintain itbull How much will it cost

                                  bull Where is itbull Is maintenance burden

                                  practical for likely future owners

                                  bull Whorsquos going to monitor compliance and how

                                  The detail is in the permit conditions

                                  Application requirements

                                  ldquoAn application must be accompanied by details of the proposed stormwater management system including drainage works and retention detention and discharges of stormwater to the drainage systemrdquo ndash Clause 5318

                                  What does the planning scheme require

                                  But alsohellipNeed to provide sufficient information to Council which demonstrates that you comply and how you comply with all the other standards ndash eg urban coolinghabitatetc BPEM site management pollutant control infiltration (as relevant to development type

                                  51

                                  1 PlansWhat are you doing where is it going and does it fit

                                  2 ModellingDo you (or can you) meet BPEM requirements

                                  3 Written response to standardsHow does your proposal comply with the requirements

                                  52

                                  Application

                                  bull Site plan ndash show all assetsWSUD treatments and any IWM features on the site layout plan with everything else

                                  bull Landscape plan ndash if planting design passive irrigation etc forms part of response to requirements show

                                  bull Site management plan (depending on Council)

                                  bull Separate WSUDIWM plan showing all features on a stripped back background

                                  bull Concept WSUD asset design ndash larger assets only (wetlands bioretention basins sed basin etc) ndash sufficient design detail to confirm spatial requirements

                                  PlansPermit conditions

                                  bull Detailed engineering design bull Site Management Plan (final)bull Asset maintenance plan (final)bull Handover arrangements (if public)

                                  54

                                  STORM ndash Online toolbull Print out of STORM reportbull Make sure meets 100 or

                                  morebull Make sure report inputs and

                                  results match plan

                                  Modelling - SWQ

                                  MUSIC ndash Proprietary softwarebull Provide a copy of the model filebull Print out the modelling resultsbull Provide summary of your model

                                  inputs for each treatment train (iecatchment size impervious treatment area etc)

                                  bull Provide a print out of the model schematic

                                  Bonus points bull Provide details of model

                                  parametersbull Provide results of MUSIC auditor

                                  run (if using Melbourne Water MUSIC Guidelines)

                                  56

                                  Assessment against standards

                                  bull Say what you have done (or will do) to meet each standardbull Donrsquot forget (if WSUD) details of maintenance and asset

                                  ownershipbull Where applicable be explicit why yoursquove chosen (or not chosen) to

                                  respond the way you have Egbull Opportunitiesbull Site constraintsbull Practicaloperational issues bull Brief dot point summary of options analysis if complex

                                  bull Make sure if it doesnrsquot meet the standard it meets the objectivebull Make sure shown on plan and consistent with modelling and rest of

                                  documentation

                                  57

                                  Resources

                                  Local stormwaterWSUD policiesBaysideKingstonCaseyMonashMelbourneYarraMoonee ValleyPort PhilipStonningtonHumeCampaspeBass Coast

                                  Local ESD (including IWM) policies Greater BendigoGreater DandenongHobsons BayWhittleseaWyndhamWhitehorseManninghamMorelandDarebinBanyuleKnoxBrimbank

                                  Council planning resources

                                  Application resources ndashexamplesDELWP Practice Note ndashformal guide to the new controlsMoreland ndash application checklists and example plans for a variety of residential developmentsPort Philip ndash compliance guidelines checklist and examplesMoonee Valley ndash checklists and example plans including site management plans Greater Bendigo ndash WSUD kitBayside ndash application guidelines and example plans

                                  59

                                  Technical guidelines (modelling design construction)

                                  Melbourne Water

                                  STORM calculatorMUSIC auditor - lsquohow torsquo video here

                                  Melbourne Water technical guidelines page- WSUD asset life cycle costings and model maintenance guidelines- MUSIC guidelines- Stormwater harvesting guidelines- WSUD life cycle costings and

                                  maintenance guidelines- Design and construction guidelines

                                  for variety of assetshttpswwwmelbournewatercomauplanning-and-buildingdeveloper-guides-and-resourcesguidelines-drawings-and-checklistsguidelines

                                  Council

                                  South-Eastern Growth Council WSUD guidelines ndash note that some individual Councils have their own addendumsMelbournePort PhilipNorth-West Growth Council WSUD guidelines - note that some individual Councils have their own addendumsGreater BendigoMilduraBallaratBaw BawWyndhamMoreland ndash tree pits and raingardens

                                  60

                                  IWM

                                  Example Council IWM strategiesMelbourneCaseyMonashKingston

                                  Resilient Melbourne ndash IWM information lsquohubrsquoClearwater ndash capacity building and case studiesMelbourne Water ndash funding opportunities for IWM projects

                                  Stormwater offset schemes

                                  KingstonGreater GeelongMelbourne Water ndash non scheme contributions

                                  Site management

                                  EPA guidelines- management of erosion and sediment

                                  Next steps and other stormwater initiatives

                                  Emma Stewart DELWP

                                  62

                                  Next steps

                                  bull Trainingbull The EPArsquos BPEM Reviewbull Offsets policybull Review of STORM bull Building controls

                                  63

                                  State Stormwater policies

                                  64

                                  Thank you

                                  • Slide Number 1
                                  • Slide Number 2
                                  • History of WSUD
                                  • History of WSUD
                                  • Transformational change in urban water
                                  • Inconsistencies and inequities in our approach to stormwater management
                                  • Slide Number 8
                                  • Terms of Reference
                                  • Improving Stormwater Management Advisory Committee
                                  • Wide consultation
                                  • Stakeholder feedback
                                  • Stakeholder feedback
                                  • Committee submitted its report in September 2018
                                  • Committee Recomendations
                                  • Planning reforms
                                  • Future policy directions
                                  • Supporting actions
                                  • Slide Number 19
                                  • Government response (to date)
                                  • Longer term recommendations
                                  • State-based planning requirements (lsquobeforersquo)
                                  • State-based planning requirements (lsquoafterrsquo)
                                  • Development types (volume)
                                  • Slide Number 25
                                  • Amendment VC154
                                  • Whatrsquos in
                                  • Slide Number 28
                                  • Key elements of clauses
                                  • Clause 5318 ndash subdivision
                                  • Clause 5318 ndash Buildings and works
                                  • Townhouses - Standard B9
                                  • Slide Number 33
                                  • Slide Number 34
                                  • Slide Number 35
                                  • Slide Number 36
                                  • Slide Number 37
                                  • Buildings and works - Site management standard
                                  • Site management
                                  • Planning Advisory Note No 75
                                  • Slide Number 41
                                  • Slide Number 42
                                  • Slide Number 43
                                  • Slide Number 44
                                  • Slide Number 45
                                  • Slide Number 46
                                  • Slide Number 47
                                  • Slide Number 48
                                  • Slide Number 49
                                  • Slide Number 50
                                  • Slide Number 51
                                  • Slide Number 52
                                  • Slide Number 53
                                  • Slide Number 54
                                  • Slide Number 55
                                  • Slide Number 56
                                  • Slide Number 57
                                  • Slide Number 58
                                  • Slide Number 59
                                  • Slide Number 60
                                  • Slide Number 61
                                  • Next steps
                                  • State Stormwater policies
                                  • Slide Number 64

                                    The new stormwater provisions

                                    Emma Stewart DELWP

                                    20

                                    Government response (to date)

                                    21

                                    Government is currently considering the committeersquos longer-term recommendations and is working with key stakeholders to determine the most effective response and pathways for implementation

                                    Longer term recommendations

                                    22

                                    State-based planning requirements (lsquobeforersquo)

                                    Sourced ELM 2018

                                    23

                                    State-based planning requirements (lsquoafterrsquo)

                                    24

                                    Development types (volume)

                                    Future development estimated impervious area 2020-2050

                                    25

                                    The nitty grittyhellip

                                    26

                                    Amendment VC154

                                    Victoria Planning Provision changesbull New clause (5318) and changes to an existing clause

                                    (5503) to expand the stormwater requirements to more development types

                                    bull New objectives to manage toxicants and encourage broader benefits of stormwater management

                                    27

                                    Whatrsquos in

                                    Applies to an application tobull subdivide land bull construct a building bull construct or carry out works

                                    In both hellip

                                    Clause 5318bull commercial zonesbull industrial zonesbull public-use zones

                                    Clause 5518 bull Construct townhouses

                                    Whatrsquos out of clause 5318

                                    bull Developments and subdivisions approved or lodged prior to the amendment

                                    bull Developments which do not require planning permission

                                    bull Vicsmart applications

                                    bull Applications for land within development or incorporated plans approved before the amendment

                                    bull Extensions and works lt 50m2

                                    bull Applications after the amendment to amend existing planning permits

                                    If in doubt ask a planner

                                    29

                                    Key elements of clauses

                                    Industrial commercial applications (Clause 5318)tobull subdivide land bull construct a building bull construct or carry out works

                                    Stormwater management objectives + standard (W1)

                                    Stormwater management objectives + standard (W2)+ Site management objectives + standard (W3)

                                    Decision guidelines

                                    Same for Clause 5503 (townhouses)

                                    30

                                    Clause 5318 ndash subdivision

                                    Stormwater management standard W1 The stormwater management system should be bull Designed and managed in accordance with the requirements and

                                    to the satisfaction of the relevant drainage authoritybull Designed and managed in accordance with the requirements and

                                    to the satisfaction of the water authority where reuse of stormwater is proposed

                                    bull Designed to meet the current best practice performance objectives for stormwater quality as contained in the BPEM

                                    bull Designed to ensure that flows downstream of the subdivision site are restricted to pre-development levels unless increased flows are approved by the relevant drainage authority and there are no detrimental downstream impacts

                                    bull Designed to contribute to cooling improving local habitat and providing attractive and enjoyable spaces

                                    31

                                    Clause 5318 ndash Buildings and works

                                    Standard W2The stormwater management system should be designed to

                                    bull Meet the current best practice performance objectives for stormwater quality as contained in the BPEM

                                    bull Contribute to cooling improving local habitat and providing attractive and enjoyable spaces

                                    bull Minimise the impact of chemical pollutants and other toxicants including by but not limited to bunding and covering of roofing of storage loading and work areas

                                    32

                                    Townhouses - Standard B9

                                    Clause 5503 ndash Permeability and stormwater management objectives and standard B9

                                    Objectivesbull Similar to 5318 (including the cooling liveability

                                    objective)bull gt20 perviousness objective (unchanged)

                                    Standardbull NEW - cooling liveability objectivebull NEW ndash requirement to meet BPEM

                                    What does this all mean

                                    34

                                    Clause 5318 - Whatrsquos in

                                    35

                                    Urban cooling Reduce heat radiation from buildings and hard surfaces throughbull Shade trees in car parks or over driveways bull More open space and treesbull Green roofsbull Green walls

                                    36

                                    Optionsbull Passive irrigationbull Integrate assets into

                                    communal open spacebull Tree pits and permeable

                                    paving (driveways and carpark)

                                    bull Stormwater harvesting (major developments only)

                                    Infiltration habitat amenity

                                    37

                                    Control harmful chemicals

                                    Optionsbull Careful layoutbull Consider alternative less harmful substancesbull Roofed designated storage areabull Internal drainage design to sewer or a treatment devicebull Bunding

                                    38

                                    Standard W3Standard W3 requires that application describe how the site will be managed prior to and during the construction period The application should set out requirements for managingbull Erosion and sedimentbull Stormwaterbull Litter concrete and other construction wastesbull Chemical contamination

                                    Buildings and works - Site management standard

                                    39

                                    Site management

                                    40

                                    Planning Advisory Note No 75

                                    Implications for industry

                                    Kate MatthewsStormwater Victoria

                                    1 Development proponents- Developers- Consultants (engineers stormwater specialists and planners)- Council (when developing public land lt$1 million)

                                    2 Development assessors- Council statutory planners- Council internal referrals (engineering assets ESD stormwater officers)

                                    3 Strategy- Council strategic planners

                                    4 Melbourne Water

                                    Whorsquos affected

                                    43

                                    What are the implications

                                    bull BPEM - Itrsquos not just subdivisions any more

                                    bull Cost ndash offset or assetbull Early planning and integration ndash more

                                    work up frontbull Not just engineeringbull Varying Council skills and experience

                                    Development Proponents

                                    44

                                    If already have a local policy for WSUDESD no real change

                                    If notbull Workload and resourcingbull Increased detail and technical

                                    contentbull Administrative arrangements ndash

                                    referrals permit conditions ndashmake sure you make 60 stat days

                                    bull Applicant pressure ndash what do you want

                                    bull Assets

                                    Development Assessors

                                    45

                                    bull Structure plans and rezoning ndashopportunities for localregional approach

                                    bull IWM and Stormwater Management Plans ndash opportunities for these to be implemented through the controls spatial opportunities

                                    bull Opportunities for development of Council offset strategies

                                    Strategy

                                    Offsets

                                    bull Developer enters into an agreement with relevant drainage authority to financially contribute to off-site stormwatermanagement in lieu of providing on-site treatment

                                    bull Already available for residential subdivisions in Melbourne (Clause 56) through MWCs Stormwater Quality Offset scheme

                                    What are stormwater quality offsets

                                    X Not drainage contributions (MWC drainage scheme)

                                    X Not development contributions (DCPICP)

                                    47

                                    When to use

                                    bull Not in MW DSS or growth area where therersquos an existing framework for funding SW treatment

                                    bull Onsite treatment not practical or desirable

                                    bull To fund planned localregional stormwater treatment works in that catchment via an existing offset scheme

                                    bull Council and developer both agree to it

                                    48

                                    OffsetsExample ndash Kingston Offset Scheme

                                    Asset ownership and maintenance

                                    bull Whorsquos going to own itbull Whorsquos going to maintain itbull How do you maintain itbull How much will it cost

                                    bull Where is itbull Is maintenance burden

                                    practical for likely future owners

                                    bull Whorsquos going to monitor compliance and how

                                    The detail is in the permit conditions

                                    Application requirements

                                    ldquoAn application must be accompanied by details of the proposed stormwater management system including drainage works and retention detention and discharges of stormwater to the drainage systemrdquo ndash Clause 5318

                                    What does the planning scheme require

                                    But alsohellipNeed to provide sufficient information to Council which demonstrates that you comply and how you comply with all the other standards ndash eg urban coolinghabitatetc BPEM site management pollutant control infiltration (as relevant to development type

                                    51

                                    1 PlansWhat are you doing where is it going and does it fit

                                    2 ModellingDo you (or can you) meet BPEM requirements

                                    3 Written response to standardsHow does your proposal comply with the requirements

                                    52

                                    Application

                                    bull Site plan ndash show all assetsWSUD treatments and any IWM features on the site layout plan with everything else

                                    bull Landscape plan ndash if planting design passive irrigation etc forms part of response to requirements show

                                    bull Site management plan (depending on Council)

                                    bull Separate WSUDIWM plan showing all features on a stripped back background

                                    bull Concept WSUD asset design ndash larger assets only (wetlands bioretention basins sed basin etc) ndash sufficient design detail to confirm spatial requirements

                                    PlansPermit conditions

                                    bull Detailed engineering design bull Site Management Plan (final)bull Asset maintenance plan (final)bull Handover arrangements (if public)

                                    54

                                    STORM ndash Online toolbull Print out of STORM reportbull Make sure meets 100 or

                                    morebull Make sure report inputs and

                                    results match plan

                                    Modelling - SWQ

                                    MUSIC ndash Proprietary softwarebull Provide a copy of the model filebull Print out the modelling resultsbull Provide summary of your model

                                    inputs for each treatment train (iecatchment size impervious treatment area etc)

                                    bull Provide a print out of the model schematic

                                    Bonus points bull Provide details of model

                                    parametersbull Provide results of MUSIC auditor

                                    run (if using Melbourne Water MUSIC Guidelines)

                                    56

                                    Assessment against standards

                                    bull Say what you have done (or will do) to meet each standardbull Donrsquot forget (if WSUD) details of maintenance and asset

                                    ownershipbull Where applicable be explicit why yoursquove chosen (or not chosen) to

                                    respond the way you have Egbull Opportunitiesbull Site constraintsbull Practicaloperational issues bull Brief dot point summary of options analysis if complex

                                    bull Make sure if it doesnrsquot meet the standard it meets the objectivebull Make sure shown on plan and consistent with modelling and rest of

                                    documentation

                                    57

                                    Resources

                                    Local stormwaterWSUD policiesBaysideKingstonCaseyMonashMelbourneYarraMoonee ValleyPort PhilipStonningtonHumeCampaspeBass Coast

                                    Local ESD (including IWM) policies Greater BendigoGreater DandenongHobsons BayWhittleseaWyndhamWhitehorseManninghamMorelandDarebinBanyuleKnoxBrimbank

                                    Council planning resources

                                    Application resources ndashexamplesDELWP Practice Note ndashformal guide to the new controlsMoreland ndash application checklists and example plans for a variety of residential developmentsPort Philip ndash compliance guidelines checklist and examplesMoonee Valley ndash checklists and example plans including site management plans Greater Bendigo ndash WSUD kitBayside ndash application guidelines and example plans

                                    59

                                    Technical guidelines (modelling design construction)

                                    Melbourne Water

                                    STORM calculatorMUSIC auditor - lsquohow torsquo video here

                                    Melbourne Water technical guidelines page- WSUD asset life cycle costings and model maintenance guidelines- MUSIC guidelines- Stormwater harvesting guidelines- WSUD life cycle costings and

                                    maintenance guidelines- Design and construction guidelines

                                    for variety of assetshttpswwwmelbournewatercomauplanning-and-buildingdeveloper-guides-and-resourcesguidelines-drawings-and-checklistsguidelines

                                    Council

                                    South-Eastern Growth Council WSUD guidelines ndash note that some individual Councils have their own addendumsMelbournePort PhilipNorth-West Growth Council WSUD guidelines - note that some individual Councils have their own addendumsGreater BendigoMilduraBallaratBaw BawWyndhamMoreland ndash tree pits and raingardens

                                    60

                                    IWM

                                    Example Council IWM strategiesMelbourneCaseyMonashKingston

                                    Resilient Melbourne ndash IWM information lsquohubrsquoClearwater ndash capacity building and case studiesMelbourne Water ndash funding opportunities for IWM projects

                                    Stormwater offset schemes

                                    KingstonGreater GeelongMelbourne Water ndash non scheme contributions

                                    Site management

                                    EPA guidelines- management of erosion and sediment

                                    Next steps and other stormwater initiatives

                                    Emma Stewart DELWP

                                    62

                                    Next steps

                                    bull Trainingbull The EPArsquos BPEM Reviewbull Offsets policybull Review of STORM bull Building controls

                                    63

                                    State Stormwater policies

                                    64

                                    Thank you

                                    • Slide Number 1
                                    • Slide Number 2
                                    • History of WSUD
                                    • History of WSUD
                                    • Transformational change in urban water
                                    • Inconsistencies and inequities in our approach to stormwater management
                                    • Slide Number 8
                                    • Terms of Reference
                                    • Improving Stormwater Management Advisory Committee
                                    • Wide consultation
                                    • Stakeholder feedback
                                    • Stakeholder feedback
                                    • Committee submitted its report in September 2018
                                    • Committee Recomendations
                                    • Planning reforms
                                    • Future policy directions
                                    • Supporting actions
                                    • Slide Number 19
                                    • Government response (to date)
                                    • Longer term recommendations
                                    • State-based planning requirements (lsquobeforersquo)
                                    • State-based planning requirements (lsquoafterrsquo)
                                    • Development types (volume)
                                    • Slide Number 25
                                    • Amendment VC154
                                    • Whatrsquos in
                                    • Slide Number 28
                                    • Key elements of clauses
                                    • Clause 5318 ndash subdivision
                                    • Clause 5318 ndash Buildings and works
                                    • Townhouses - Standard B9
                                    • Slide Number 33
                                    • Slide Number 34
                                    • Slide Number 35
                                    • Slide Number 36
                                    • Slide Number 37
                                    • Buildings and works - Site management standard
                                    • Site management
                                    • Planning Advisory Note No 75
                                    • Slide Number 41
                                    • Slide Number 42
                                    • Slide Number 43
                                    • Slide Number 44
                                    • Slide Number 45
                                    • Slide Number 46
                                    • Slide Number 47
                                    • Slide Number 48
                                    • Slide Number 49
                                    • Slide Number 50
                                    • Slide Number 51
                                    • Slide Number 52
                                    • Slide Number 53
                                    • Slide Number 54
                                    • Slide Number 55
                                    • Slide Number 56
                                    • Slide Number 57
                                    • Slide Number 58
                                    • Slide Number 59
                                    • Slide Number 60
                                    • Slide Number 61
                                    • Next steps
                                    • State Stormwater policies
                                    • Slide Number 64

                                      20

                                      Government response (to date)

                                      21

                                      Government is currently considering the committeersquos longer-term recommendations and is working with key stakeholders to determine the most effective response and pathways for implementation

                                      Longer term recommendations

                                      22

                                      State-based planning requirements (lsquobeforersquo)

                                      Sourced ELM 2018

                                      23

                                      State-based planning requirements (lsquoafterrsquo)

                                      24

                                      Development types (volume)

                                      Future development estimated impervious area 2020-2050

                                      25

                                      The nitty grittyhellip

                                      26

                                      Amendment VC154

                                      Victoria Planning Provision changesbull New clause (5318) and changes to an existing clause

                                      (5503) to expand the stormwater requirements to more development types

                                      bull New objectives to manage toxicants and encourage broader benefits of stormwater management

                                      27

                                      Whatrsquos in

                                      Applies to an application tobull subdivide land bull construct a building bull construct or carry out works

                                      In both hellip

                                      Clause 5318bull commercial zonesbull industrial zonesbull public-use zones

                                      Clause 5518 bull Construct townhouses

                                      Whatrsquos out of clause 5318

                                      bull Developments and subdivisions approved or lodged prior to the amendment

                                      bull Developments which do not require planning permission

                                      bull Vicsmart applications

                                      bull Applications for land within development or incorporated plans approved before the amendment

                                      bull Extensions and works lt 50m2

                                      bull Applications after the amendment to amend existing planning permits

                                      If in doubt ask a planner

                                      29

                                      Key elements of clauses

                                      Industrial commercial applications (Clause 5318)tobull subdivide land bull construct a building bull construct or carry out works

                                      Stormwater management objectives + standard (W1)

                                      Stormwater management objectives + standard (W2)+ Site management objectives + standard (W3)

                                      Decision guidelines

                                      Same for Clause 5503 (townhouses)

                                      30

                                      Clause 5318 ndash subdivision

                                      Stormwater management standard W1 The stormwater management system should be bull Designed and managed in accordance with the requirements and

                                      to the satisfaction of the relevant drainage authoritybull Designed and managed in accordance with the requirements and

                                      to the satisfaction of the water authority where reuse of stormwater is proposed

                                      bull Designed to meet the current best practice performance objectives for stormwater quality as contained in the BPEM

                                      bull Designed to ensure that flows downstream of the subdivision site are restricted to pre-development levels unless increased flows are approved by the relevant drainage authority and there are no detrimental downstream impacts

                                      bull Designed to contribute to cooling improving local habitat and providing attractive and enjoyable spaces

                                      31

                                      Clause 5318 ndash Buildings and works

                                      Standard W2The stormwater management system should be designed to

                                      bull Meet the current best practice performance objectives for stormwater quality as contained in the BPEM

                                      bull Contribute to cooling improving local habitat and providing attractive and enjoyable spaces

                                      bull Minimise the impact of chemical pollutants and other toxicants including by but not limited to bunding and covering of roofing of storage loading and work areas

                                      32

                                      Townhouses - Standard B9

                                      Clause 5503 ndash Permeability and stormwater management objectives and standard B9

                                      Objectivesbull Similar to 5318 (including the cooling liveability

                                      objective)bull gt20 perviousness objective (unchanged)

                                      Standardbull NEW - cooling liveability objectivebull NEW ndash requirement to meet BPEM

                                      What does this all mean

                                      34

                                      Clause 5318 - Whatrsquos in

                                      35

                                      Urban cooling Reduce heat radiation from buildings and hard surfaces throughbull Shade trees in car parks or over driveways bull More open space and treesbull Green roofsbull Green walls

                                      36

                                      Optionsbull Passive irrigationbull Integrate assets into

                                      communal open spacebull Tree pits and permeable

                                      paving (driveways and carpark)

                                      bull Stormwater harvesting (major developments only)

                                      Infiltration habitat amenity

                                      37

                                      Control harmful chemicals

                                      Optionsbull Careful layoutbull Consider alternative less harmful substancesbull Roofed designated storage areabull Internal drainage design to sewer or a treatment devicebull Bunding

                                      38

                                      Standard W3Standard W3 requires that application describe how the site will be managed prior to and during the construction period The application should set out requirements for managingbull Erosion and sedimentbull Stormwaterbull Litter concrete and other construction wastesbull Chemical contamination

                                      Buildings and works - Site management standard

                                      39

                                      Site management

                                      40

                                      Planning Advisory Note No 75

                                      Implications for industry

                                      Kate MatthewsStormwater Victoria

                                      1 Development proponents- Developers- Consultants (engineers stormwater specialists and planners)- Council (when developing public land lt$1 million)

                                      2 Development assessors- Council statutory planners- Council internal referrals (engineering assets ESD stormwater officers)

                                      3 Strategy- Council strategic planners

                                      4 Melbourne Water

                                      Whorsquos affected

                                      43

                                      What are the implications

                                      bull BPEM - Itrsquos not just subdivisions any more

                                      bull Cost ndash offset or assetbull Early planning and integration ndash more

                                      work up frontbull Not just engineeringbull Varying Council skills and experience

                                      Development Proponents

                                      44

                                      If already have a local policy for WSUDESD no real change

                                      If notbull Workload and resourcingbull Increased detail and technical

                                      contentbull Administrative arrangements ndash

                                      referrals permit conditions ndashmake sure you make 60 stat days

                                      bull Applicant pressure ndash what do you want

                                      bull Assets

                                      Development Assessors

                                      45

                                      bull Structure plans and rezoning ndashopportunities for localregional approach

                                      bull IWM and Stormwater Management Plans ndash opportunities for these to be implemented through the controls spatial opportunities

                                      bull Opportunities for development of Council offset strategies

                                      Strategy

                                      Offsets

                                      bull Developer enters into an agreement with relevant drainage authority to financially contribute to off-site stormwatermanagement in lieu of providing on-site treatment

                                      bull Already available for residential subdivisions in Melbourne (Clause 56) through MWCs Stormwater Quality Offset scheme

                                      What are stormwater quality offsets

                                      X Not drainage contributions (MWC drainage scheme)

                                      X Not development contributions (DCPICP)

                                      47

                                      When to use

                                      bull Not in MW DSS or growth area where therersquos an existing framework for funding SW treatment

                                      bull Onsite treatment not practical or desirable

                                      bull To fund planned localregional stormwater treatment works in that catchment via an existing offset scheme

                                      bull Council and developer both agree to it

                                      48

                                      OffsetsExample ndash Kingston Offset Scheme

                                      Asset ownership and maintenance

                                      bull Whorsquos going to own itbull Whorsquos going to maintain itbull How do you maintain itbull How much will it cost

                                      bull Where is itbull Is maintenance burden

                                      practical for likely future owners

                                      bull Whorsquos going to monitor compliance and how

                                      The detail is in the permit conditions

                                      Application requirements

                                      ldquoAn application must be accompanied by details of the proposed stormwater management system including drainage works and retention detention and discharges of stormwater to the drainage systemrdquo ndash Clause 5318

                                      What does the planning scheme require

                                      But alsohellipNeed to provide sufficient information to Council which demonstrates that you comply and how you comply with all the other standards ndash eg urban coolinghabitatetc BPEM site management pollutant control infiltration (as relevant to development type

                                      51

                                      1 PlansWhat are you doing where is it going and does it fit

                                      2 ModellingDo you (or can you) meet BPEM requirements

                                      3 Written response to standardsHow does your proposal comply with the requirements

                                      52

                                      Application

                                      bull Site plan ndash show all assetsWSUD treatments and any IWM features on the site layout plan with everything else

                                      bull Landscape plan ndash if planting design passive irrigation etc forms part of response to requirements show

                                      bull Site management plan (depending on Council)

                                      bull Separate WSUDIWM plan showing all features on a stripped back background

                                      bull Concept WSUD asset design ndash larger assets only (wetlands bioretention basins sed basin etc) ndash sufficient design detail to confirm spatial requirements

                                      PlansPermit conditions

                                      bull Detailed engineering design bull Site Management Plan (final)bull Asset maintenance plan (final)bull Handover arrangements (if public)

                                      54

                                      STORM ndash Online toolbull Print out of STORM reportbull Make sure meets 100 or

                                      morebull Make sure report inputs and

                                      results match plan

                                      Modelling - SWQ

                                      MUSIC ndash Proprietary softwarebull Provide a copy of the model filebull Print out the modelling resultsbull Provide summary of your model

                                      inputs for each treatment train (iecatchment size impervious treatment area etc)

                                      bull Provide a print out of the model schematic

                                      Bonus points bull Provide details of model

                                      parametersbull Provide results of MUSIC auditor

                                      run (if using Melbourne Water MUSIC Guidelines)

                                      56

                                      Assessment against standards

                                      bull Say what you have done (or will do) to meet each standardbull Donrsquot forget (if WSUD) details of maintenance and asset

                                      ownershipbull Where applicable be explicit why yoursquove chosen (or not chosen) to

                                      respond the way you have Egbull Opportunitiesbull Site constraintsbull Practicaloperational issues bull Brief dot point summary of options analysis if complex

                                      bull Make sure if it doesnrsquot meet the standard it meets the objectivebull Make sure shown on plan and consistent with modelling and rest of

                                      documentation

                                      57

                                      Resources

                                      Local stormwaterWSUD policiesBaysideKingstonCaseyMonashMelbourneYarraMoonee ValleyPort PhilipStonningtonHumeCampaspeBass Coast

                                      Local ESD (including IWM) policies Greater BendigoGreater DandenongHobsons BayWhittleseaWyndhamWhitehorseManninghamMorelandDarebinBanyuleKnoxBrimbank

                                      Council planning resources

                                      Application resources ndashexamplesDELWP Practice Note ndashformal guide to the new controlsMoreland ndash application checklists and example plans for a variety of residential developmentsPort Philip ndash compliance guidelines checklist and examplesMoonee Valley ndash checklists and example plans including site management plans Greater Bendigo ndash WSUD kitBayside ndash application guidelines and example plans

                                      59

                                      Technical guidelines (modelling design construction)

                                      Melbourne Water

                                      STORM calculatorMUSIC auditor - lsquohow torsquo video here

                                      Melbourne Water technical guidelines page- WSUD asset life cycle costings and model maintenance guidelines- MUSIC guidelines- Stormwater harvesting guidelines- WSUD life cycle costings and

                                      maintenance guidelines- Design and construction guidelines

                                      for variety of assetshttpswwwmelbournewatercomauplanning-and-buildingdeveloper-guides-and-resourcesguidelines-drawings-and-checklistsguidelines

                                      Council

                                      South-Eastern Growth Council WSUD guidelines ndash note that some individual Councils have their own addendumsMelbournePort PhilipNorth-West Growth Council WSUD guidelines - note that some individual Councils have their own addendumsGreater BendigoMilduraBallaratBaw BawWyndhamMoreland ndash tree pits and raingardens

                                      60

                                      IWM

                                      Example Council IWM strategiesMelbourneCaseyMonashKingston

                                      Resilient Melbourne ndash IWM information lsquohubrsquoClearwater ndash capacity building and case studiesMelbourne Water ndash funding opportunities for IWM projects

                                      Stormwater offset schemes

                                      KingstonGreater GeelongMelbourne Water ndash non scheme contributions

                                      Site management

                                      EPA guidelines- management of erosion and sediment

                                      Next steps and other stormwater initiatives

                                      Emma Stewart DELWP

                                      62

                                      Next steps

                                      bull Trainingbull The EPArsquos BPEM Reviewbull Offsets policybull Review of STORM bull Building controls

                                      63

                                      State Stormwater policies

                                      64

                                      Thank you

                                      • Slide Number 1
                                      • Slide Number 2
                                      • History of WSUD
                                      • History of WSUD
                                      • Transformational change in urban water
                                      • Inconsistencies and inequities in our approach to stormwater management
                                      • Slide Number 8
                                      • Terms of Reference
                                      • Improving Stormwater Management Advisory Committee
                                      • Wide consultation
                                      • Stakeholder feedback
                                      • Stakeholder feedback
                                      • Committee submitted its report in September 2018
                                      • Committee Recomendations
                                      • Planning reforms
                                      • Future policy directions
                                      • Supporting actions
                                      • Slide Number 19
                                      • Government response (to date)
                                      • Longer term recommendations
                                      • State-based planning requirements (lsquobeforersquo)
                                      • State-based planning requirements (lsquoafterrsquo)
                                      • Development types (volume)
                                      • Slide Number 25
                                      • Amendment VC154
                                      • Whatrsquos in
                                      • Slide Number 28
                                      • Key elements of clauses
                                      • Clause 5318 ndash subdivision
                                      • Clause 5318 ndash Buildings and works
                                      • Townhouses - Standard B9
                                      • Slide Number 33
                                      • Slide Number 34
                                      • Slide Number 35
                                      • Slide Number 36
                                      • Slide Number 37
                                      • Buildings and works - Site management standard
                                      • Site management
                                      • Planning Advisory Note No 75
                                      • Slide Number 41
                                      • Slide Number 42
                                      • Slide Number 43
                                      • Slide Number 44
                                      • Slide Number 45
                                      • Slide Number 46
                                      • Slide Number 47
                                      • Slide Number 48
                                      • Slide Number 49
                                      • Slide Number 50
                                      • Slide Number 51
                                      • Slide Number 52
                                      • Slide Number 53
                                      • Slide Number 54
                                      • Slide Number 55
                                      • Slide Number 56
                                      • Slide Number 57
                                      • Slide Number 58
                                      • Slide Number 59
                                      • Slide Number 60
                                      • Slide Number 61
                                      • Next steps
                                      • State Stormwater policies
                                      • Slide Number 64

                                        21

                                        Government is currently considering the committeersquos longer-term recommendations and is working with key stakeholders to determine the most effective response and pathways for implementation

                                        Longer term recommendations

                                        22

                                        State-based planning requirements (lsquobeforersquo)

                                        Sourced ELM 2018

                                        23

                                        State-based planning requirements (lsquoafterrsquo)

                                        24

                                        Development types (volume)

                                        Future development estimated impervious area 2020-2050

                                        25

                                        The nitty grittyhellip

                                        26

                                        Amendment VC154

                                        Victoria Planning Provision changesbull New clause (5318) and changes to an existing clause

                                        (5503) to expand the stormwater requirements to more development types

                                        bull New objectives to manage toxicants and encourage broader benefits of stormwater management

                                        27

                                        Whatrsquos in

                                        Applies to an application tobull subdivide land bull construct a building bull construct or carry out works

                                        In both hellip

                                        Clause 5318bull commercial zonesbull industrial zonesbull public-use zones

                                        Clause 5518 bull Construct townhouses

                                        Whatrsquos out of clause 5318

                                        bull Developments and subdivisions approved or lodged prior to the amendment

                                        bull Developments which do not require planning permission

                                        bull Vicsmart applications

                                        bull Applications for land within development or incorporated plans approved before the amendment

                                        bull Extensions and works lt 50m2

                                        bull Applications after the amendment to amend existing planning permits

                                        If in doubt ask a planner

                                        29

                                        Key elements of clauses

                                        Industrial commercial applications (Clause 5318)tobull subdivide land bull construct a building bull construct or carry out works

                                        Stormwater management objectives + standard (W1)

                                        Stormwater management objectives + standard (W2)+ Site management objectives + standard (W3)

                                        Decision guidelines

                                        Same for Clause 5503 (townhouses)

                                        30

                                        Clause 5318 ndash subdivision

                                        Stormwater management standard W1 The stormwater management system should be bull Designed and managed in accordance with the requirements and

                                        to the satisfaction of the relevant drainage authoritybull Designed and managed in accordance with the requirements and

                                        to the satisfaction of the water authority where reuse of stormwater is proposed

                                        bull Designed to meet the current best practice performance objectives for stormwater quality as contained in the BPEM

                                        bull Designed to ensure that flows downstream of the subdivision site are restricted to pre-development levels unless increased flows are approved by the relevant drainage authority and there are no detrimental downstream impacts

                                        bull Designed to contribute to cooling improving local habitat and providing attractive and enjoyable spaces

                                        31

                                        Clause 5318 ndash Buildings and works

                                        Standard W2The stormwater management system should be designed to

                                        bull Meet the current best practice performance objectives for stormwater quality as contained in the BPEM

                                        bull Contribute to cooling improving local habitat and providing attractive and enjoyable spaces

                                        bull Minimise the impact of chemical pollutants and other toxicants including by but not limited to bunding and covering of roofing of storage loading and work areas

                                        32

                                        Townhouses - Standard B9

                                        Clause 5503 ndash Permeability and stormwater management objectives and standard B9

                                        Objectivesbull Similar to 5318 (including the cooling liveability

                                        objective)bull gt20 perviousness objective (unchanged)

                                        Standardbull NEW - cooling liveability objectivebull NEW ndash requirement to meet BPEM

                                        What does this all mean

                                        34

                                        Clause 5318 - Whatrsquos in

                                        35

                                        Urban cooling Reduce heat radiation from buildings and hard surfaces throughbull Shade trees in car parks or over driveways bull More open space and treesbull Green roofsbull Green walls

                                        36

                                        Optionsbull Passive irrigationbull Integrate assets into

                                        communal open spacebull Tree pits and permeable

                                        paving (driveways and carpark)

                                        bull Stormwater harvesting (major developments only)

                                        Infiltration habitat amenity

                                        37

                                        Control harmful chemicals

                                        Optionsbull Careful layoutbull Consider alternative less harmful substancesbull Roofed designated storage areabull Internal drainage design to sewer or a treatment devicebull Bunding

                                        38

                                        Standard W3Standard W3 requires that application describe how the site will be managed prior to and during the construction period The application should set out requirements for managingbull Erosion and sedimentbull Stormwaterbull Litter concrete and other construction wastesbull Chemical contamination

                                        Buildings and works - Site management standard

                                        39

                                        Site management

                                        40

                                        Planning Advisory Note No 75

                                        Implications for industry

                                        Kate MatthewsStormwater Victoria

                                        1 Development proponents- Developers- Consultants (engineers stormwater specialists and planners)- Council (when developing public land lt$1 million)

                                        2 Development assessors- Council statutory planners- Council internal referrals (engineering assets ESD stormwater officers)

                                        3 Strategy- Council strategic planners

                                        4 Melbourne Water

                                        Whorsquos affected

                                        43

                                        What are the implications

                                        bull BPEM - Itrsquos not just subdivisions any more

                                        bull Cost ndash offset or assetbull Early planning and integration ndash more

                                        work up frontbull Not just engineeringbull Varying Council skills and experience

                                        Development Proponents

                                        44

                                        If already have a local policy for WSUDESD no real change

                                        If notbull Workload and resourcingbull Increased detail and technical

                                        contentbull Administrative arrangements ndash

                                        referrals permit conditions ndashmake sure you make 60 stat days

                                        bull Applicant pressure ndash what do you want

                                        bull Assets

                                        Development Assessors

                                        45

                                        bull Structure plans and rezoning ndashopportunities for localregional approach

                                        bull IWM and Stormwater Management Plans ndash opportunities for these to be implemented through the controls spatial opportunities

                                        bull Opportunities for development of Council offset strategies

                                        Strategy

                                        Offsets

                                        bull Developer enters into an agreement with relevant drainage authority to financially contribute to off-site stormwatermanagement in lieu of providing on-site treatment

                                        bull Already available for residential subdivisions in Melbourne (Clause 56) through MWCs Stormwater Quality Offset scheme

                                        What are stormwater quality offsets

                                        X Not drainage contributions (MWC drainage scheme)

                                        X Not development contributions (DCPICP)

                                        47

                                        When to use

                                        bull Not in MW DSS or growth area where therersquos an existing framework for funding SW treatment

                                        bull Onsite treatment not practical or desirable

                                        bull To fund planned localregional stormwater treatment works in that catchment via an existing offset scheme

                                        bull Council and developer both agree to it

                                        48

                                        OffsetsExample ndash Kingston Offset Scheme

                                        Asset ownership and maintenance

                                        bull Whorsquos going to own itbull Whorsquos going to maintain itbull How do you maintain itbull How much will it cost

                                        bull Where is itbull Is maintenance burden

                                        practical for likely future owners

                                        bull Whorsquos going to monitor compliance and how

                                        The detail is in the permit conditions

                                        Application requirements

                                        ldquoAn application must be accompanied by details of the proposed stormwater management system including drainage works and retention detention and discharges of stormwater to the drainage systemrdquo ndash Clause 5318

                                        What does the planning scheme require

                                        But alsohellipNeed to provide sufficient information to Council which demonstrates that you comply and how you comply with all the other standards ndash eg urban coolinghabitatetc BPEM site management pollutant control infiltration (as relevant to development type

                                        51

                                        1 PlansWhat are you doing where is it going and does it fit

                                        2 ModellingDo you (or can you) meet BPEM requirements

                                        3 Written response to standardsHow does your proposal comply with the requirements

                                        52

                                        Application

                                        bull Site plan ndash show all assetsWSUD treatments and any IWM features on the site layout plan with everything else

                                        bull Landscape plan ndash if planting design passive irrigation etc forms part of response to requirements show

                                        bull Site management plan (depending on Council)

                                        bull Separate WSUDIWM plan showing all features on a stripped back background

                                        bull Concept WSUD asset design ndash larger assets only (wetlands bioretention basins sed basin etc) ndash sufficient design detail to confirm spatial requirements

                                        PlansPermit conditions

                                        bull Detailed engineering design bull Site Management Plan (final)bull Asset maintenance plan (final)bull Handover arrangements (if public)

                                        54

                                        STORM ndash Online toolbull Print out of STORM reportbull Make sure meets 100 or

                                        morebull Make sure report inputs and

                                        results match plan

                                        Modelling - SWQ

                                        MUSIC ndash Proprietary softwarebull Provide a copy of the model filebull Print out the modelling resultsbull Provide summary of your model

                                        inputs for each treatment train (iecatchment size impervious treatment area etc)

                                        bull Provide a print out of the model schematic

                                        Bonus points bull Provide details of model

                                        parametersbull Provide results of MUSIC auditor

                                        run (if using Melbourne Water MUSIC Guidelines)

                                        56

                                        Assessment against standards

                                        bull Say what you have done (or will do) to meet each standardbull Donrsquot forget (if WSUD) details of maintenance and asset

                                        ownershipbull Where applicable be explicit why yoursquove chosen (or not chosen) to

                                        respond the way you have Egbull Opportunitiesbull Site constraintsbull Practicaloperational issues bull Brief dot point summary of options analysis if complex

                                        bull Make sure if it doesnrsquot meet the standard it meets the objectivebull Make sure shown on plan and consistent with modelling and rest of

                                        documentation

                                        57

                                        Resources

                                        Local stormwaterWSUD policiesBaysideKingstonCaseyMonashMelbourneYarraMoonee ValleyPort PhilipStonningtonHumeCampaspeBass Coast

                                        Local ESD (including IWM) policies Greater BendigoGreater DandenongHobsons BayWhittleseaWyndhamWhitehorseManninghamMorelandDarebinBanyuleKnoxBrimbank

                                        Council planning resources

                                        Application resources ndashexamplesDELWP Practice Note ndashformal guide to the new controlsMoreland ndash application checklists and example plans for a variety of residential developmentsPort Philip ndash compliance guidelines checklist and examplesMoonee Valley ndash checklists and example plans including site management plans Greater Bendigo ndash WSUD kitBayside ndash application guidelines and example plans

                                        59

                                        Technical guidelines (modelling design construction)

                                        Melbourne Water

                                        STORM calculatorMUSIC auditor - lsquohow torsquo video here

                                        Melbourne Water technical guidelines page- WSUD asset life cycle costings and model maintenance guidelines- MUSIC guidelines- Stormwater harvesting guidelines- WSUD life cycle costings and

                                        maintenance guidelines- Design and construction guidelines

                                        for variety of assetshttpswwwmelbournewatercomauplanning-and-buildingdeveloper-guides-and-resourcesguidelines-drawings-and-checklistsguidelines

                                        Council

                                        South-Eastern Growth Council WSUD guidelines ndash note that some individual Councils have their own addendumsMelbournePort PhilipNorth-West Growth Council WSUD guidelines - note that some individual Councils have their own addendumsGreater BendigoMilduraBallaratBaw BawWyndhamMoreland ndash tree pits and raingardens

                                        60

                                        IWM

                                        Example Council IWM strategiesMelbourneCaseyMonashKingston

                                        Resilient Melbourne ndash IWM information lsquohubrsquoClearwater ndash capacity building and case studiesMelbourne Water ndash funding opportunities for IWM projects

                                        Stormwater offset schemes

                                        KingstonGreater GeelongMelbourne Water ndash non scheme contributions

                                        Site management

                                        EPA guidelines- management of erosion and sediment

                                        Next steps and other stormwater initiatives

                                        Emma Stewart DELWP

                                        62

                                        Next steps

                                        bull Trainingbull The EPArsquos BPEM Reviewbull Offsets policybull Review of STORM bull Building controls

                                        63

                                        State Stormwater policies

                                        64

                                        Thank you

                                        • Slide Number 1
                                        • Slide Number 2
                                        • History of WSUD
                                        • History of WSUD
                                        • Transformational change in urban water
                                        • Inconsistencies and inequities in our approach to stormwater management
                                        • Slide Number 8
                                        • Terms of Reference
                                        • Improving Stormwater Management Advisory Committee
                                        • Wide consultation
                                        • Stakeholder feedback
                                        • Stakeholder feedback
                                        • Committee submitted its report in September 2018
                                        • Committee Recomendations
                                        • Planning reforms
                                        • Future policy directions
                                        • Supporting actions
                                        • Slide Number 19
                                        • Government response (to date)
                                        • Longer term recommendations
                                        • State-based planning requirements (lsquobeforersquo)
                                        • State-based planning requirements (lsquoafterrsquo)
                                        • Development types (volume)
                                        • Slide Number 25
                                        • Amendment VC154
                                        • Whatrsquos in
                                        • Slide Number 28
                                        • Key elements of clauses
                                        • Clause 5318 ndash subdivision
                                        • Clause 5318 ndash Buildings and works
                                        • Townhouses - Standard B9
                                        • Slide Number 33
                                        • Slide Number 34
                                        • Slide Number 35
                                        • Slide Number 36
                                        • Slide Number 37
                                        • Buildings and works - Site management standard
                                        • Site management
                                        • Planning Advisory Note No 75
                                        • Slide Number 41
                                        • Slide Number 42
                                        • Slide Number 43
                                        • Slide Number 44
                                        • Slide Number 45
                                        • Slide Number 46
                                        • Slide Number 47
                                        • Slide Number 48
                                        • Slide Number 49
                                        • Slide Number 50
                                        • Slide Number 51
                                        • Slide Number 52
                                        • Slide Number 53
                                        • Slide Number 54
                                        • Slide Number 55
                                        • Slide Number 56
                                        • Slide Number 57
                                        • Slide Number 58
                                        • Slide Number 59
                                        • Slide Number 60
                                        • Slide Number 61
                                        • Next steps
                                        • State Stormwater policies
                                        • Slide Number 64

                                          22

                                          State-based planning requirements (lsquobeforersquo)

                                          Sourced ELM 2018

                                          23

                                          State-based planning requirements (lsquoafterrsquo)

                                          24

                                          Development types (volume)

                                          Future development estimated impervious area 2020-2050

                                          25

                                          The nitty grittyhellip

                                          26

                                          Amendment VC154

                                          Victoria Planning Provision changesbull New clause (5318) and changes to an existing clause

                                          (5503) to expand the stormwater requirements to more development types

                                          bull New objectives to manage toxicants and encourage broader benefits of stormwater management

                                          27

                                          Whatrsquos in

                                          Applies to an application tobull subdivide land bull construct a building bull construct or carry out works

                                          In both hellip

                                          Clause 5318bull commercial zonesbull industrial zonesbull public-use zones

                                          Clause 5518 bull Construct townhouses

                                          Whatrsquos out of clause 5318

                                          bull Developments and subdivisions approved or lodged prior to the amendment

                                          bull Developments which do not require planning permission

                                          bull Vicsmart applications

                                          bull Applications for land within development or incorporated plans approved before the amendment

                                          bull Extensions and works lt 50m2

                                          bull Applications after the amendment to amend existing planning permits

                                          If in doubt ask a planner

                                          29

                                          Key elements of clauses

                                          Industrial commercial applications (Clause 5318)tobull subdivide land bull construct a building bull construct or carry out works

                                          Stormwater management objectives + standard (W1)

                                          Stormwater management objectives + standard (W2)+ Site management objectives + standard (W3)

                                          Decision guidelines

                                          Same for Clause 5503 (townhouses)

                                          30

                                          Clause 5318 ndash subdivision

                                          Stormwater management standard W1 The stormwater management system should be bull Designed and managed in accordance with the requirements and

                                          to the satisfaction of the relevant drainage authoritybull Designed and managed in accordance with the requirements and

                                          to the satisfaction of the water authority where reuse of stormwater is proposed

                                          bull Designed to meet the current best practice performance objectives for stormwater quality as contained in the BPEM

                                          bull Designed to ensure that flows downstream of the subdivision site are restricted to pre-development levels unless increased flows are approved by the relevant drainage authority and there are no detrimental downstream impacts

                                          bull Designed to contribute to cooling improving local habitat and providing attractive and enjoyable spaces

                                          31

                                          Clause 5318 ndash Buildings and works

                                          Standard W2The stormwater management system should be designed to

                                          bull Meet the current best practice performance objectives for stormwater quality as contained in the BPEM

                                          bull Contribute to cooling improving local habitat and providing attractive and enjoyable spaces

                                          bull Minimise the impact of chemical pollutants and other toxicants including by but not limited to bunding and covering of roofing of storage loading and work areas

                                          32

                                          Townhouses - Standard B9

                                          Clause 5503 ndash Permeability and stormwater management objectives and standard B9

                                          Objectivesbull Similar to 5318 (including the cooling liveability

                                          objective)bull gt20 perviousness objective (unchanged)

                                          Standardbull NEW - cooling liveability objectivebull NEW ndash requirement to meet BPEM

                                          What does this all mean

                                          34

                                          Clause 5318 - Whatrsquos in

                                          35

                                          Urban cooling Reduce heat radiation from buildings and hard surfaces throughbull Shade trees in car parks or over driveways bull More open space and treesbull Green roofsbull Green walls

                                          36

                                          Optionsbull Passive irrigationbull Integrate assets into

                                          communal open spacebull Tree pits and permeable

                                          paving (driveways and carpark)

                                          bull Stormwater harvesting (major developments only)

                                          Infiltration habitat amenity

                                          37

                                          Control harmful chemicals

                                          Optionsbull Careful layoutbull Consider alternative less harmful substancesbull Roofed designated storage areabull Internal drainage design to sewer or a treatment devicebull Bunding

                                          38

                                          Standard W3Standard W3 requires that application describe how the site will be managed prior to and during the construction period The application should set out requirements for managingbull Erosion and sedimentbull Stormwaterbull Litter concrete and other construction wastesbull Chemical contamination

                                          Buildings and works - Site management standard

                                          39

                                          Site management

                                          40

                                          Planning Advisory Note No 75

                                          Implications for industry

                                          Kate MatthewsStormwater Victoria

                                          1 Development proponents- Developers- Consultants (engineers stormwater specialists and planners)- Council (when developing public land lt$1 million)

                                          2 Development assessors- Council statutory planners- Council internal referrals (engineering assets ESD stormwater officers)

                                          3 Strategy- Council strategic planners

                                          4 Melbourne Water

                                          Whorsquos affected

                                          43

                                          What are the implications

                                          bull BPEM - Itrsquos not just subdivisions any more

                                          bull Cost ndash offset or assetbull Early planning and integration ndash more

                                          work up frontbull Not just engineeringbull Varying Council skills and experience

                                          Development Proponents

                                          44

                                          If already have a local policy for WSUDESD no real change

                                          If notbull Workload and resourcingbull Increased detail and technical

                                          contentbull Administrative arrangements ndash

                                          referrals permit conditions ndashmake sure you make 60 stat days

                                          bull Applicant pressure ndash what do you want

                                          bull Assets

                                          Development Assessors

                                          45

                                          bull Structure plans and rezoning ndashopportunities for localregional approach

                                          bull IWM and Stormwater Management Plans ndash opportunities for these to be implemented through the controls spatial opportunities

                                          bull Opportunities for development of Council offset strategies

                                          Strategy

                                          Offsets

                                          bull Developer enters into an agreement with relevant drainage authority to financially contribute to off-site stormwatermanagement in lieu of providing on-site treatment

                                          bull Already available for residential subdivisions in Melbourne (Clause 56) through MWCs Stormwater Quality Offset scheme

                                          What are stormwater quality offsets

                                          X Not drainage contributions (MWC drainage scheme)

                                          X Not development contributions (DCPICP)

                                          47

                                          When to use

                                          bull Not in MW DSS or growth area where therersquos an existing framework for funding SW treatment

                                          bull Onsite treatment not practical or desirable

                                          bull To fund planned localregional stormwater treatment works in that catchment via an existing offset scheme

                                          bull Council and developer both agree to it

                                          48

                                          OffsetsExample ndash Kingston Offset Scheme

                                          Asset ownership and maintenance

                                          bull Whorsquos going to own itbull Whorsquos going to maintain itbull How do you maintain itbull How much will it cost

                                          bull Where is itbull Is maintenance burden

                                          practical for likely future owners

                                          bull Whorsquos going to monitor compliance and how

                                          The detail is in the permit conditions

                                          Application requirements

                                          ldquoAn application must be accompanied by details of the proposed stormwater management system including drainage works and retention detention and discharges of stormwater to the drainage systemrdquo ndash Clause 5318

                                          What does the planning scheme require

                                          But alsohellipNeed to provide sufficient information to Council which demonstrates that you comply and how you comply with all the other standards ndash eg urban coolinghabitatetc BPEM site management pollutant control infiltration (as relevant to development type

                                          51

                                          1 PlansWhat are you doing where is it going and does it fit

                                          2 ModellingDo you (or can you) meet BPEM requirements

                                          3 Written response to standardsHow does your proposal comply with the requirements

                                          52

                                          Application

                                          bull Site plan ndash show all assetsWSUD treatments and any IWM features on the site layout plan with everything else

                                          bull Landscape plan ndash if planting design passive irrigation etc forms part of response to requirements show

                                          bull Site management plan (depending on Council)

                                          bull Separate WSUDIWM plan showing all features on a stripped back background

                                          bull Concept WSUD asset design ndash larger assets only (wetlands bioretention basins sed basin etc) ndash sufficient design detail to confirm spatial requirements

                                          PlansPermit conditions

                                          bull Detailed engineering design bull Site Management Plan (final)bull Asset maintenance plan (final)bull Handover arrangements (if public)

                                          54

                                          STORM ndash Online toolbull Print out of STORM reportbull Make sure meets 100 or

                                          morebull Make sure report inputs and

                                          results match plan

                                          Modelling - SWQ

                                          MUSIC ndash Proprietary softwarebull Provide a copy of the model filebull Print out the modelling resultsbull Provide summary of your model

                                          inputs for each treatment train (iecatchment size impervious treatment area etc)

                                          bull Provide a print out of the model schematic

                                          Bonus points bull Provide details of model

                                          parametersbull Provide results of MUSIC auditor

                                          run (if using Melbourne Water MUSIC Guidelines)

                                          56

                                          Assessment against standards

                                          bull Say what you have done (or will do) to meet each standardbull Donrsquot forget (if WSUD) details of maintenance and asset

                                          ownershipbull Where applicable be explicit why yoursquove chosen (or not chosen) to

                                          respond the way you have Egbull Opportunitiesbull Site constraintsbull Practicaloperational issues bull Brief dot point summary of options analysis if complex

                                          bull Make sure if it doesnrsquot meet the standard it meets the objectivebull Make sure shown on plan and consistent with modelling and rest of

                                          documentation

                                          57

                                          Resources

                                          Local stormwaterWSUD policiesBaysideKingstonCaseyMonashMelbourneYarraMoonee ValleyPort PhilipStonningtonHumeCampaspeBass Coast

                                          Local ESD (including IWM) policies Greater BendigoGreater DandenongHobsons BayWhittleseaWyndhamWhitehorseManninghamMorelandDarebinBanyuleKnoxBrimbank

                                          Council planning resources

                                          Application resources ndashexamplesDELWP Practice Note ndashformal guide to the new controlsMoreland ndash application checklists and example plans for a variety of residential developmentsPort Philip ndash compliance guidelines checklist and examplesMoonee Valley ndash checklists and example plans including site management plans Greater Bendigo ndash WSUD kitBayside ndash application guidelines and example plans

                                          59

                                          Technical guidelines (modelling design construction)

                                          Melbourne Water

                                          STORM calculatorMUSIC auditor - lsquohow torsquo video here

                                          Melbourne Water technical guidelines page- WSUD asset life cycle costings and model maintenance guidelines- MUSIC guidelines- Stormwater harvesting guidelines- WSUD life cycle costings and

                                          maintenance guidelines- Design and construction guidelines

                                          for variety of assetshttpswwwmelbournewatercomauplanning-and-buildingdeveloper-guides-and-resourcesguidelines-drawings-and-checklistsguidelines

                                          Council

                                          South-Eastern Growth Council WSUD guidelines ndash note that some individual Councils have their own addendumsMelbournePort PhilipNorth-West Growth Council WSUD guidelines - note that some individual Councils have their own addendumsGreater BendigoMilduraBallaratBaw BawWyndhamMoreland ndash tree pits and raingardens

                                          60

                                          IWM

                                          Example Council IWM strategiesMelbourneCaseyMonashKingston

                                          Resilient Melbourne ndash IWM information lsquohubrsquoClearwater ndash capacity building and case studiesMelbourne Water ndash funding opportunities for IWM projects

                                          Stormwater offset schemes

                                          KingstonGreater GeelongMelbourne Water ndash non scheme contributions

                                          Site management

                                          EPA guidelines- management of erosion and sediment

                                          Next steps and other stormwater initiatives

                                          Emma Stewart DELWP

                                          62

                                          Next steps

                                          bull Trainingbull The EPArsquos BPEM Reviewbull Offsets policybull Review of STORM bull Building controls

                                          63

                                          State Stormwater policies

                                          64

                                          Thank you

                                          • Slide Number 1
                                          • Slide Number 2
                                          • History of WSUD
                                          • History of WSUD
                                          • Transformational change in urban water
                                          • Inconsistencies and inequities in our approach to stormwater management
                                          • Slide Number 8
                                          • Terms of Reference
                                          • Improving Stormwater Management Advisory Committee
                                          • Wide consultation
                                          • Stakeholder feedback
                                          • Stakeholder feedback
                                          • Committee submitted its report in September 2018
                                          • Committee Recomendations
                                          • Planning reforms
                                          • Future policy directions
                                          • Supporting actions
                                          • Slide Number 19
                                          • Government response (to date)
                                          • Longer term recommendations
                                          • State-based planning requirements (lsquobeforersquo)
                                          • State-based planning requirements (lsquoafterrsquo)
                                          • Development types (volume)
                                          • Slide Number 25
                                          • Amendment VC154
                                          • Whatrsquos in
                                          • Slide Number 28
                                          • Key elements of clauses
                                          • Clause 5318 ndash subdivision
                                          • Clause 5318 ndash Buildings and works
                                          • Townhouses - Standard B9
                                          • Slide Number 33
                                          • Slide Number 34
                                          • Slide Number 35
                                          • Slide Number 36
                                          • Slide Number 37
                                          • Buildings and works - Site management standard
                                          • Site management
                                          • Planning Advisory Note No 75
                                          • Slide Number 41
                                          • Slide Number 42
                                          • Slide Number 43
                                          • Slide Number 44
                                          • Slide Number 45
                                          • Slide Number 46
                                          • Slide Number 47
                                          • Slide Number 48
                                          • Slide Number 49
                                          • Slide Number 50
                                          • Slide Number 51
                                          • Slide Number 52
                                          • Slide Number 53
                                          • Slide Number 54
                                          • Slide Number 55
                                          • Slide Number 56
                                          • Slide Number 57
                                          • Slide Number 58
                                          • Slide Number 59
                                          • Slide Number 60
                                          • Slide Number 61
                                          • Next steps
                                          • State Stormwater policies
                                          • Slide Number 64

                                            23

                                            State-based planning requirements (lsquoafterrsquo)

                                            24

                                            Development types (volume)

                                            Future development estimated impervious area 2020-2050

                                            25

                                            The nitty grittyhellip

                                            26

                                            Amendment VC154

                                            Victoria Planning Provision changesbull New clause (5318) and changes to an existing clause

                                            (5503) to expand the stormwater requirements to more development types

                                            bull New objectives to manage toxicants and encourage broader benefits of stormwater management

                                            27

                                            Whatrsquos in

                                            Applies to an application tobull subdivide land bull construct a building bull construct or carry out works

                                            In both hellip

                                            Clause 5318bull commercial zonesbull industrial zonesbull public-use zones

                                            Clause 5518 bull Construct townhouses

                                            Whatrsquos out of clause 5318

                                            bull Developments and subdivisions approved or lodged prior to the amendment

                                            bull Developments which do not require planning permission

                                            bull Vicsmart applications

                                            bull Applications for land within development or incorporated plans approved before the amendment

                                            bull Extensions and works lt 50m2

                                            bull Applications after the amendment to amend existing planning permits

                                            If in doubt ask a planner

                                            29

                                            Key elements of clauses

                                            Industrial commercial applications (Clause 5318)tobull subdivide land bull construct a building bull construct or carry out works

                                            Stormwater management objectives + standard (W1)

                                            Stormwater management objectives + standard (W2)+ Site management objectives + standard (W3)

                                            Decision guidelines

                                            Same for Clause 5503 (townhouses)

                                            30

                                            Clause 5318 ndash subdivision

                                            Stormwater management standard W1 The stormwater management system should be bull Designed and managed in accordance with the requirements and

                                            to the satisfaction of the relevant drainage authoritybull Designed and managed in accordance with the requirements and

                                            to the satisfaction of the water authority where reuse of stormwater is proposed

                                            bull Designed to meet the current best practice performance objectives for stormwater quality as contained in the BPEM

                                            bull Designed to ensure that flows downstream of the subdivision site are restricted to pre-development levels unless increased flows are approved by the relevant drainage authority and there are no detrimental downstream impacts

                                            bull Designed to contribute to cooling improving local habitat and providing attractive and enjoyable spaces

                                            31

                                            Clause 5318 ndash Buildings and works

                                            Standard W2The stormwater management system should be designed to

                                            bull Meet the current best practice performance objectives for stormwater quality as contained in the BPEM

                                            bull Contribute to cooling improving local habitat and providing attractive and enjoyable spaces

                                            bull Minimise the impact of chemical pollutants and other toxicants including by but not limited to bunding and covering of roofing of storage loading and work areas

                                            32

                                            Townhouses - Standard B9

                                            Clause 5503 ndash Permeability and stormwater management objectives and standard B9

                                            Objectivesbull Similar to 5318 (including the cooling liveability

                                            objective)bull gt20 perviousness objective (unchanged)

                                            Standardbull NEW - cooling liveability objectivebull NEW ndash requirement to meet BPEM

                                            What does this all mean

                                            34

                                            Clause 5318 - Whatrsquos in

                                            35

                                            Urban cooling Reduce heat radiation from buildings and hard surfaces throughbull Shade trees in car parks or over driveways bull More open space and treesbull Green roofsbull Green walls

                                            36

                                            Optionsbull Passive irrigationbull Integrate assets into

                                            communal open spacebull Tree pits and permeable

                                            paving (driveways and carpark)

                                            bull Stormwater harvesting (major developments only)

                                            Infiltration habitat amenity

                                            37

                                            Control harmful chemicals

                                            Optionsbull Careful layoutbull Consider alternative less harmful substancesbull Roofed designated storage areabull Internal drainage design to sewer or a treatment devicebull Bunding

                                            38

                                            Standard W3Standard W3 requires that application describe how the site will be managed prior to and during the construction period The application should set out requirements for managingbull Erosion and sedimentbull Stormwaterbull Litter concrete and other construction wastesbull Chemical contamination

                                            Buildings and works - Site management standard

                                            39

                                            Site management

                                            40

                                            Planning Advisory Note No 75

                                            Implications for industry

                                            Kate MatthewsStormwater Victoria

                                            1 Development proponents- Developers- Consultants (engineers stormwater specialists and planners)- Council (when developing public land lt$1 million)

                                            2 Development assessors- Council statutory planners- Council internal referrals (engineering assets ESD stormwater officers)

                                            3 Strategy- Council strategic planners

                                            4 Melbourne Water

                                            Whorsquos affected

                                            43

                                            What are the implications

                                            bull BPEM - Itrsquos not just subdivisions any more

                                            bull Cost ndash offset or assetbull Early planning and integration ndash more

                                            work up frontbull Not just engineeringbull Varying Council skills and experience

                                            Development Proponents

                                            44

                                            If already have a local policy for WSUDESD no real change

                                            If notbull Workload and resourcingbull Increased detail and technical

                                            contentbull Administrative arrangements ndash

                                            referrals permit conditions ndashmake sure you make 60 stat days

                                            bull Applicant pressure ndash what do you want

                                            bull Assets

                                            Development Assessors

                                            45

                                            bull Structure plans and rezoning ndashopportunities for localregional approach

                                            bull IWM and Stormwater Management Plans ndash opportunities for these to be implemented through the controls spatial opportunities

                                            bull Opportunities for development of Council offset strategies

                                            Strategy

                                            Offsets

                                            bull Developer enters into an agreement with relevant drainage authority to financially contribute to off-site stormwatermanagement in lieu of providing on-site treatment

                                            bull Already available for residential subdivisions in Melbourne (Clause 56) through MWCs Stormwater Quality Offset scheme

                                            What are stormwater quality offsets

                                            X Not drainage contributions (MWC drainage scheme)

                                            X Not development contributions (DCPICP)

                                            47

                                            When to use

                                            bull Not in MW DSS or growth area where therersquos an existing framework for funding SW treatment

                                            bull Onsite treatment not practical or desirable

                                            bull To fund planned localregional stormwater treatment works in that catchment via an existing offset scheme

                                            bull Council and developer both agree to it

                                            48

                                            OffsetsExample ndash Kingston Offset Scheme

                                            Asset ownership and maintenance

                                            bull Whorsquos going to own itbull Whorsquos going to maintain itbull How do you maintain itbull How much will it cost

                                            bull Where is itbull Is maintenance burden

                                            practical for likely future owners

                                            bull Whorsquos going to monitor compliance and how

                                            The detail is in the permit conditions

                                            Application requirements

                                            ldquoAn application must be accompanied by details of the proposed stormwater management system including drainage works and retention detention and discharges of stormwater to the drainage systemrdquo ndash Clause 5318

                                            What does the planning scheme require

                                            But alsohellipNeed to provide sufficient information to Council which demonstrates that you comply and how you comply with all the other standards ndash eg urban coolinghabitatetc BPEM site management pollutant control infiltration (as relevant to development type

                                            51

                                            1 PlansWhat are you doing where is it going and does it fit

                                            2 ModellingDo you (or can you) meet BPEM requirements

                                            3 Written response to standardsHow does your proposal comply with the requirements

                                            52

                                            Application

                                            bull Site plan ndash show all assetsWSUD treatments and any IWM features on the site layout plan with everything else

                                            bull Landscape plan ndash if planting design passive irrigation etc forms part of response to requirements show

                                            bull Site management plan (depending on Council)

                                            bull Separate WSUDIWM plan showing all features on a stripped back background

                                            bull Concept WSUD asset design ndash larger assets only (wetlands bioretention basins sed basin etc) ndash sufficient design detail to confirm spatial requirements

                                            PlansPermit conditions

                                            bull Detailed engineering design bull Site Management Plan (final)bull Asset maintenance plan (final)bull Handover arrangements (if public)

                                            54

                                            STORM ndash Online toolbull Print out of STORM reportbull Make sure meets 100 or

                                            morebull Make sure report inputs and

                                            results match plan

                                            Modelling - SWQ

                                            MUSIC ndash Proprietary softwarebull Provide a copy of the model filebull Print out the modelling resultsbull Provide summary of your model

                                            inputs for each treatment train (iecatchment size impervious treatment area etc)

                                            bull Provide a print out of the model schematic

                                            Bonus points bull Provide details of model

                                            parametersbull Provide results of MUSIC auditor

                                            run (if using Melbourne Water MUSIC Guidelines)

                                            56

                                            Assessment against standards

                                            bull Say what you have done (or will do) to meet each standardbull Donrsquot forget (if WSUD) details of maintenance and asset

                                            ownershipbull Where applicable be explicit why yoursquove chosen (or not chosen) to

                                            respond the way you have Egbull Opportunitiesbull Site constraintsbull Practicaloperational issues bull Brief dot point summary of options analysis if complex

                                            bull Make sure if it doesnrsquot meet the standard it meets the objectivebull Make sure shown on plan and consistent with modelling and rest of

                                            documentation

                                            57

                                            Resources

                                            Local stormwaterWSUD policiesBaysideKingstonCaseyMonashMelbourneYarraMoonee ValleyPort PhilipStonningtonHumeCampaspeBass Coast

                                            Local ESD (including IWM) policies Greater BendigoGreater DandenongHobsons BayWhittleseaWyndhamWhitehorseManninghamMorelandDarebinBanyuleKnoxBrimbank

                                            Council planning resources

                                            Application resources ndashexamplesDELWP Practice Note ndashformal guide to the new controlsMoreland ndash application checklists and example plans for a variety of residential developmentsPort Philip ndash compliance guidelines checklist and examplesMoonee Valley ndash checklists and example plans including site management plans Greater Bendigo ndash WSUD kitBayside ndash application guidelines and example plans

                                            59

                                            Technical guidelines (modelling design construction)

                                            Melbourne Water

                                            STORM calculatorMUSIC auditor - lsquohow torsquo video here

                                            Melbourne Water technical guidelines page- WSUD asset life cycle costings and model maintenance guidelines- MUSIC guidelines- Stormwater harvesting guidelines- WSUD life cycle costings and

                                            maintenance guidelines- Design and construction guidelines

                                            for variety of assetshttpswwwmelbournewatercomauplanning-and-buildingdeveloper-guides-and-resourcesguidelines-drawings-and-checklistsguidelines

                                            Council

                                            South-Eastern Growth Council WSUD guidelines ndash note that some individual Councils have their own addendumsMelbournePort PhilipNorth-West Growth Council WSUD guidelines - note that some individual Councils have their own addendumsGreater BendigoMilduraBallaratBaw BawWyndhamMoreland ndash tree pits and raingardens

                                            60

                                            IWM

                                            Example Council IWM strategiesMelbourneCaseyMonashKingston

                                            Resilient Melbourne ndash IWM information lsquohubrsquoClearwater ndash capacity building and case studiesMelbourne Water ndash funding opportunities for IWM projects

                                            Stormwater offset schemes

                                            KingstonGreater GeelongMelbourne Water ndash non scheme contributions

                                            Site management

                                            EPA guidelines- management of erosion and sediment

                                            Next steps and other stormwater initiatives

                                            Emma Stewart DELWP

                                            62

                                            Next steps

                                            bull Trainingbull The EPArsquos BPEM Reviewbull Offsets policybull Review of STORM bull Building controls

                                            63

                                            State Stormwater policies

                                            64

                                            Thank you

                                            • Slide Number 1
                                            • Slide Number 2
                                            • History of WSUD
                                            • History of WSUD
                                            • Transformational change in urban water
                                            • Inconsistencies and inequities in our approach to stormwater management
                                            • Slide Number 8
                                            • Terms of Reference
                                            • Improving Stormwater Management Advisory Committee
                                            • Wide consultation
                                            • Stakeholder feedback
                                            • Stakeholder feedback
                                            • Committee submitted its report in September 2018
                                            • Committee Recomendations
                                            • Planning reforms
                                            • Future policy directions
                                            • Supporting actions
                                            • Slide Number 19
                                            • Government response (to date)
                                            • Longer term recommendations
                                            • State-based planning requirements (lsquobeforersquo)
                                            • State-based planning requirements (lsquoafterrsquo)
                                            • Development types (volume)
                                            • Slide Number 25
                                            • Amendment VC154
                                            • Whatrsquos in
                                            • Slide Number 28
                                            • Key elements of clauses
                                            • Clause 5318 ndash subdivision
                                            • Clause 5318 ndash Buildings and works
                                            • Townhouses - Standard B9
                                            • Slide Number 33
                                            • Slide Number 34
                                            • Slide Number 35
                                            • Slide Number 36
                                            • Slide Number 37
                                            • Buildings and works - Site management standard
                                            • Site management
                                            • Planning Advisory Note No 75
                                            • Slide Number 41
                                            • Slide Number 42
                                            • Slide Number 43
                                            • Slide Number 44
                                            • Slide Number 45
                                            • Slide Number 46
                                            • Slide Number 47
                                            • Slide Number 48
                                            • Slide Number 49
                                            • Slide Number 50
                                            • Slide Number 51
                                            • Slide Number 52
                                            • Slide Number 53
                                            • Slide Number 54
                                            • Slide Number 55
                                            • Slide Number 56
                                            • Slide Number 57
                                            • Slide Number 58
                                            • Slide Number 59
                                            • Slide Number 60
                                            • Slide Number 61
                                            • Next steps
                                            • State Stormwater policies
                                            • Slide Number 64

                                              24

                                              Development types (volume)

                                              Future development estimated impervious area 2020-2050

                                              25

                                              The nitty grittyhellip

                                              26

                                              Amendment VC154

                                              Victoria Planning Provision changesbull New clause (5318) and changes to an existing clause

                                              (5503) to expand the stormwater requirements to more development types

                                              bull New objectives to manage toxicants and encourage broader benefits of stormwater management

                                              27

                                              Whatrsquos in

                                              Applies to an application tobull subdivide land bull construct a building bull construct or carry out works

                                              In both hellip

                                              Clause 5318bull commercial zonesbull industrial zonesbull public-use zones

                                              Clause 5518 bull Construct townhouses

                                              Whatrsquos out of clause 5318

                                              bull Developments and subdivisions approved or lodged prior to the amendment

                                              bull Developments which do not require planning permission

                                              bull Vicsmart applications

                                              bull Applications for land within development or incorporated plans approved before the amendment

                                              bull Extensions and works lt 50m2

                                              bull Applications after the amendment to amend existing planning permits

                                              If in doubt ask a planner

                                              29

                                              Key elements of clauses

                                              Industrial commercial applications (Clause 5318)tobull subdivide land bull construct a building bull construct or carry out works

                                              Stormwater management objectives + standard (W1)

                                              Stormwater management objectives + standard (W2)+ Site management objectives + standard (W3)

                                              Decision guidelines

                                              Same for Clause 5503 (townhouses)

                                              30

                                              Clause 5318 ndash subdivision

                                              Stormwater management standard W1 The stormwater management system should be bull Designed and managed in accordance with the requirements and

                                              to the satisfaction of the relevant drainage authoritybull Designed and managed in accordance with the requirements and

                                              to the satisfaction of the water authority where reuse of stormwater is proposed

                                              bull Designed to meet the current best practice performance objectives for stormwater quality as contained in the BPEM

                                              bull Designed to ensure that flows downstream of the subdivision site are restricted to pre-development levels unless increased flows are approved by the relevant drainage authority and there are no detrimental downstream impacts

                                              bull Designed to contribute to cooling improving local habitat and providing attractive and enjoyable spaces

                                              31

                                              Clause 5318 ndash Buildings and works

                                              Standard W2The stormwater management system should be designed to

                                              bull Meet the current best practice performance objectives for stormwater quality as contained in the BPEM

                                              bull Contribute to cooling improving local habitat and providing attractive and enjoyable spaces

                                              bull Minimise the impact of chemical pollutants and other toxicants including by but not limited to bunding and covering of roofing of storage loading and work areas

                                              32

                                              Townhouses - Standard B9

                                              Clause 5503 ndash Permeability and stormwater management objectives and standard B9

                                              Objectivesbull Similar to 5318 (including the cooling liveability

                                              objective)bull gt20 perviousness objective (unchanged)

                                              Standardbull NEW - cooling liveability objectivebull NEW ndash requirement to meet BPEM

                                              What does this all mean

                                              34

                                              Clause 5318 - Whatrsquos in

                                              35

                                              Urban cooling Reduce heat radiation from buildings and hard surfaces throughbull Shade trees in car parks or over driveways bull More open space and treesbull Green roofsbull Green walls

                                              36

                                              Optionsbull Passive irrigationbull Integrate assets into

                                              communal open spacebull Tree pits and permeable

                                              paving (driveways and carpark)

                                              bull Stormwater harvesting (major developments only)

                                              Infiltration habitat amenity

                                              37

                                              Control harmful chemicals

                                              Optionsbull Careful layoutbull Consider alternative less harmful substancesbull Roofed designated storage areabull Internal drainage design to sewer or a treatment devicebull Bunding

                                              38

                                              Standard W3Standard W3 requires that application describe how the site will be managed prior to and during the construction period The application should set out requirements for managingbull Erosion and sedimentbull Stormwaterbull Litter concrete and other construction wastesbull Chemical contamination

                                              Buildings and works - Site management standard

                                              39

                                              Site management

                                              40

                                              Planning Advisory Note No 75

                                              Implications for industry

                                              Kate MatthewsStormwater Victoria

                                              1 Development proponents- Developers- Consultants (engineers stormwater specialists and planners)- Council (when developing public land lt$1 million)

                                              2 Development assessors- Council statutory planners- Council internal referrals (engineering assets ESD stormwater officers)

                                              3 Strategy- Council strategic planners

                                              4 Melbourne Water

                                              Whorsquos affected

                                              43

                                              What are the implications

                                              bull BPEM - Itrsquos not just subdivisions any more

                                              bull Cost ndash offset or assetbull Early planning and integration ndash more

                                              work up frontbull Not just engineeringbull Varying Council skills and experience

                                              Development Proponents

                                              44

                                              If already have a local policy for WSUDESD no real change

                                              If notbull Workload and resourcingbull Increased detail and technical

                                              contentbull Administrative arrangements ndash

                                              referrals permit conditions ndashmake sure you make 60 stat days

                                              bull Applicant pressure ndash what do you want

                                              bull Assets

                                              Development Assessors

                                              45

                                              bull Structure plans and rezoning ndashopportunities for localregional approach

                                              bull IWM and Stormwater Management Plans ndash opportunities for these to be implemented through the controls spatial opportunities

                                              bull Opportunities for development of Council offset strategies

                                              Strategy

                                              Offsets

                                              bull Developer enters into an agreement with relevant drainage authority to financially contribute to off-site stormwatermanagement in lieu of providing on-site treatment

                                              bull Already available for residential subdivisions in Melbourne (Clause 56) through MWCs Stormwater Quality Offset scheme

                                              What are stormwater quality offsets

                                              X Not drainage contributions (MWC drainage scheme)

                                              X Not development contributions (DCPICP)

                                              47

                                              When to use

                                              bull Not in MW DSS or growth area where therersquos an existing framework for funding SW treatment

                                              bull Onsite treatment not practical or desirable

                                              bull To fund planned localregional stormwater treatment works in that catchment via an existing offset scheme

                                              bull Council and developer both agree to it

                                              48

                                              OffsetsExample ndash Kingston Offset Scheme

                                              Asset ownership and maintenance

                                              bull Whorsquos going to own itbull Whorsquos going to maintain itbull How do you maintain itbull How much will it cost

                                              bull Where is itbull Is maintenance burden

                                              practical for likely future owners

                                              bull Whorsquos going to monitor compliance and how

                                              The detail is in the permit conditions

                                              Application requirements

                                              ldquoAn application must be accompanied by details of the proposed stormwater management system including drainage works and retention detention and discharges of stormwater to the drainage systemrdquo ndash Clause 5318

                                              What does the planning scheme require

                                              But alsohellipNeed to provide sufficient information to Council which demonstrates that you comply and how you comply with all the other standards ndash eg urban coolinghabitatetc BPEM site management pollutant control infiltration (as relevant to development type

                                              51

                                              1 PlansWhat are you doing where is it going and does it fit

                                              2 ModellingDo you (or can you) meet BPEM requirements

                                              3 Written response to standardsHow does your proposal comply with the requirements

                                              52

                                              Application

                                              bull Site plan ndash show all assetsWSUD treatments and any IWM features on the site layout plan with everything else

                                              bull Landscape plan ndash if planting design passive irrigation etc forms part of response to requirements show

                                              bull Site management plan (depending on Council)

                                              bull Separate WSUDIWM plan showing all features on a stripped back background

                                              bull Concept WSUD asset design ndash larger assets only (wetlands bioretention basins sed basin etc) ndash sufficient design detail to confirm spatial requirements

                                              PlansPermit conditions

                                              bull Detailed engineering design bull Site Management Plan (final)bull Asset maintenance plan (final)bull Handover arrangements (if public)

                                              54

                                              STORM ndash Online toolbull Print out of STORM reportbull Make sure meets 100 or

                                              morebull Make sure report inputs and

                                              results match plan

                                              Modelling - SWQ

                                              MUSIC ndash Proprietary softwarebull Provide a copy of the model filebull Print out the modelling resultsbull Provide summary of your model

                                              inputs for each treatment train (iecatchment size impervious treatment area etc)

                                              bull Provide a print out of the model schematic

                                              Bonus points bull Provide details of model

                                              parametersbull Provide results of MUSIC auditor

                                              run (if using Melbourne Water MUSIC Guidelines)

                                              56

                                              Assessment against standards

                                              bull Say what you have done (or will do) to meet each standardbull Donrsquot forget (if WSUD) details of maintenance and asset

                                              ownershipbull Where applicable be explicit why yoursquove chosen (or not chosen) to

                                              respond the way you have Egbull Opportunitiesbull Site constraintsbull Practicaloperational issues bull Brief dot point summary of options analysis if complex

                                              bull Make sure if it doesnrsquot meet the standard it meets the objectivebull Make sure shown on plan and consistent with modelling and rest of

                                              documentation

                                              57

                                              Resources

                                              Local stormwaterWSUD policiesBaysideKingstonCaseyMonashMelbourneYarraMoonee ValleyPort PhilipStonningtonHumeCampaspeBass Coast

                                              Local ESD (including IWM) policies Greater BendigoGreater DandenongHobsons BayWhittleseaWyndhamWhitehorseManninghamMorelandDarebinBanyuleKnoxBrimbank

                                              Council planning resources

                                              Application resources ndashexamplesDELWP Practice Note ndashformal guide to the new controlsMoreland ndash application checklists and example plans for a variety of residential developmentsPort Philip ndash compliance guidelines checklist and examplesMoonee Valley ndash checklists and example plans including site management plans Greater Bendigo ndash WSUD kitBayside ndash application guidelines and example plans

                                              59

                                              Technical guidelines (modelling design construction)

                                              Melbourne Water

                                              STORM calculatorMUSIC auditor - lsquohow torsquo video here

                                              Melbourne Water technical guidelines page- WSUD asset life cycle costings and model maintenance guidelines- MUSIC guidelines- Stormwater harvesting guidelines- WSUD life cycle costings and

                                              maintenance guidelines- Design and construction guidelines

                                              for variety of assetshttpswwwmelbournewatercomauplanning-and-buildingdeveloper-guides-and-resourcesguidelines-drawings-and-checklistsguidelines

                                              Council

                                              South-Eastern Growth Council WSUD guidelines ndash note that some individual Councils have their own addendumsMelbournePort PhilipNorth-West Growth Council WSUD guidelines - note that some individual Councils have their own addendumsGreater BendigoMilduraBallaratBaw BawWyndhamMoreland ndash tree pits and raingardens

                                              60

                                              IWM

                                              Example Council IWM strategiesMelbourneCaseyMonashKingston

                                              Resilient Melbourne ndash IWM information lsquohubrsquoClearwater ndash capacity building and case studiesMelbourne Water ndash funding opportunities for IWM projects

                                              Stormwater offset schemes

                                              KingstonGreater GeelongMelbourne Water ndash non scheme contributions

                                              Site management

                                              EPA guidelines- management of erosion and sediment

                                              Next steps and other stormwater initiatives

                                              Emma Stewart DELWP

                                              62

                                              Next steps

                                              bull Trainingbull The EPArsquos BPEM Reviewbull Offsets policybull Review of STORM bull Building controls

                                              63

                                              State Stormwater policies

                                              64

                                              Thank you

                                              • Slide Number 1
                                              • Slide Number 2
                                              • History of WSUD
                                              • History of WSUD
                                              • Transformational change in urban water
                                              • Inconsistencies and inequities in our approach to stormwater management
                                              • Slide Number 8
                                              • Terms of Reference
                                              • Improving Stormwater Management Advisory Committee
                                              • Wide consultation
                                              • Stakeholder feedback
                                              • Stakeholder feedback
                                              • Committee submitted its report in September 2018
                                              • Committee Recomendations
                                              • Planning reforms
                                              • Future policy directions
                                              • Supporting actions
                                              • Slide Number 19
                                              • Government response (to date)
                                              • Longer term recommendations
                                              • State-based planning requirements (lsquobeforersquo)
                                              • State-based planning requirements (lsquoafterrsquo)
                                              • Development types (volume)
                                              • Slide Number 25
                                              • Amendment VC154
                                              • Whatrsquos in
                                              • Slide Number 28
                                              • Key elements of clauses
                                              • Clause 5318 ndash subdivision
                                              • Clause 5318 ndash Buildings and works
                                              • Townhouses - Standard B9
                                              • Slide Number 33
                                              • Slide Number 34
                                              • Slide Number 35
                                              • Slide Number 36
                                              • Slide Number 37
                                              • Buildings and works - Site management standard
                                              • Site management
                                              • Planning Advisory Note No 75
                                              • Slide Number 41
                                              • Slide Number 42
                                              • Slide Number 43
                                              • Slide Number 44
                                              • Slide Number 45
                                              • Slide Number 46
                                              • Slide Number 47
                                              • Slide Number 48
                                              • Slide Number 49
                                              • Slide Number 50
                                              • Slide Number 51
                                              • Slide Number 52
                                              • Slide Number 53
                                              • Slide Number 54
                                              • Slide Number 55
                                              • Slide Number 56
                                              • Slide Number 57
                                              • Slide Number 58
                                              • Slide Number 59
                                              • Slide Number 60
                                              • Slide Number 61
                                              • Next steps
                                              • State Stormwater policies
                                              • Slide Number 64

                                                25

                                                The nitty grittyhellip

                                                26

                                                Amendment VC154

                                                Victoria Planning Provision changesbull New clause (5318) and changes to an existing clause

                                                (5503) to expand the stormwater requirements to more development types

                                                bull New objectives to manage toxicants and encourage broader benefits of stormwater management

                                                27

                                                Whatrsquos in

                                                Applies to an application tobull subdivide land bull construct a building bull construct or carry out works

                                                In both hellip

                                                Clause 5318bull commercial zonesbull industrial zonesbull public-use zones

                                                Clause 5518 bull Construct townhouses

                                                Whatrsquos out of clause 5318

                                                bull Developments and subdivisions approved or lodged prior to the amendment

                                                bull Developments which do not require planning permission

                                                bull Vicsmart applications

                                                bull Applications for land within development or incorporated plans approved before the amendment

                                                bull Extensions and works lt 50m2

                                                bull Applications after the amendment to amend existing planning permits

                                                If in doubt ask a planner

                                                29

                                                Key elements of clauses

                                                Industrial commercial applications (Clause 5318)tobull subdivide land bull construct a building bull construct or carry out works

                                                Stormwater management objectives + standard (W1)

                                                Stormwater management objectives + standard (W2)+ Site management objectives + standard (W3)

                                                Decision guidelines

                                                Same for Clause 5503 (townhouses)

                                                30

                                                Clause 5318 ndash subdivision

                                                Stormwater management standard W1 The stormwater management system should be bull Designed and managed in accordance with the requirements and

                                                to the satisfaction of the relevant drainage authoritybull Designed and managed in accordance with the requirements and

                                                to the satisfaction of the water authority where reuse of stormwater is proposed

                                                bull Designed to meet the current best practice performance objectives for stormwater quality as contained in the BPEM

                                                bull Designed to ensure that flows downstream of the subdivision site are restricted to pre-development levels unless increased flows are approved by the relevant drainage authority and there are no detrimental downstream impacts

                                                bull Designed to contribute to cooling improving local habitat and providing attractive and enjoyable spaces

                                                31

                                                Clause 5318 ndash Buildings and works

                                                Standard W2The stormwater management system should be designed to

                                                bull Meet the current best practice performance objectives for stormwater quality as contained in the BPEM

                                                bull Contribute to cooling improving local habitat and providing attractive and enjoyable spaces

                                                bull Minimise the impact of chemical pollutants and other toxicants including by but not limited to bunding and covering of roofing of storage loading and work areas

                                                32

                                                Townhouses - Standard B9

                                                Clause 5503 ndash Permeability and stormwater management objectives and standard B9

                                                Objectivesbull Similar to 5318 (including the cooling liveability

                                                objective)bull gt20 perviousness objective (unchanged)

                                                Standardbull NEW - cooling liveability objectivebull NEW ndash requirement to meet BPEM

                                                What does this all mean

                                                34

                                                Clause 5318 - Whatrsquos in

                                                35

                                                Urban cooling Reduce heat radiation from buildings and hard surfaces throughbull Shade trees in car parks or over driveways bull More open space and treesbull Green roofsbull Green walls

                                                36

                                                Optionsbull Passive irrigationbull Integrate assets into

                                                communal open spacebull Tree pits and permeable

                                                paving (driveways and carpark)

                                                bull Stormwater harvesting (major developments only)

                                                Infiltration habitat amenity

                                                37

                                                Control harmful chemicals

                                                Optionsbull Careful layoutbull Consider alternative less harmful substancesbull Roofed designated storage areabull Internal drainage design to sewer or a treatment devicebull Bunding

                                                38

                                                Standard W3Standard W3 requires that application describe how the site will be managed prior to and during the construction period The application should set out requirements for managingbull Erosion and sedimentbull Stormwaterbull Litter concrete and other construction wastesbull Chemical contamination

                                                Buildings and works - Site management standard

                                                39

                                                Site management

                                                40

                                                Planning Advisory Note No 75

                                                Implications for industry

                                                Kate MatthewsStormwater Victoria

                                                1 Development proponents- Developers- Consultants (engineers stormwater specialists and planners)- Council (when developing public land lt$1 million)

                                                2 Development assessors- Council statutory planners- Council internal referrals (engineering assets ESD stormwater officers)

                                                3 Strategy- Council strategic planners

                                                4 Melbourne Water

                                                Whorsquos affected

                                                43

                                                What are the implications

                                                bull BPEM - Itrsquos not just subdivisions any more

                                                bull Cost ndash offset or assetbull Early planning and integration ndash more

                                                work up frontbull Not just engineeringbull Varying Council skills and experience

                                                Development Proponents

                                                44

                                                If already have a local policy for WSUDESD no real change

                                                If notbull Workload and resourcingbull Increased detail and technical

                                                contentbull Administrative arrangements ndash

                                                referrals permit conditions ndashmake sure you make 60 stat days

                                                bull Applicant pressure ndash what do you want

                                                bull Assets

                                                Development Assessors

                                                45

                                                bull Structure plans and rezoning ndashopportunities for localregional approach

                                                bull IWM and Stormwater Management Plans ndash opportunities for these to be implemented through the controls spatial opportunities

                                                bull Opportunities for development of Council offset strategies

                                                Strategy

                                                Offsets

                                                bull Developer enters into an agreement with relevant drainage authority to financially contribute to off-site stormwatermanagement in lieu of providing on-site treatment

                                                bull Already available for residential subdivisions in Melbourne (Clause 56) through MWCs Stormwater Quality Offset scheme

                                                What are stormwater quality offsets

                                                X Not drainage contributions (MWC drainage scheme)

                                                X Not development contributions (DCPICP)

                                                47

                                                When to use

                                                bull Not in MW DSS or growth area where therersquos an existing framework for funding SW treatment

                                                bull Onsite treatment not practical or desirable

                                                bull To fund planned localregional stormwater treatment works in that catchment via an existing offset scheme

                                                bull Council and developer both agree to it

                                                48

                                                OffsetsExample ndash Kingston Offset Scheme

                                                Asset ownership and maintenance

                                                bull Whorsquos going to own itbull Whorsquos going to maintain itbull How do you maintain itbull How much will it cost

                                                bull Where is itbull Is maintenance burden

                                                practical for likely future owners

                                                bull Whorsquos going to monitor compliance and how

                                                The detail is in the permit conditions

                                                Application requirements

                                                ldquoAn application must be accompanied by details of the proposed stormwater management system including drainage works and retention detention and discharges of stormwater to the drainage systemrdquo ndash Clause 5318

                                                What does the planning scheme require

                                                But alsohellipNeed to provide sufficient information to Council which demonstrates that you comply and how you comply with all the other standards ndash eg urban coolinghabitatetc BPEM site management pollutant control infiltration (as relevant to development type

                                                51

                                                1 PlansWhat are you doing where is it going and does it fit

                                                2 ModellingDo you (or can you) meet BPEM requirements

                                                3 Written response to standardsHow does your proposal comply with the requirements

                                                52

                                                Application

                                                bull Site plan ndash show all assetsWSUD treatments and any IWM features on the site layout plan with everything else

                                                bull Landscape plan ndash if planting design passive irrigation etc forms part of response to requirements show

                                                bull Site management plan (depending on Council)

                                                bull Separate WSUDIWM plan showing all features on a stripped back background

                                                bull Concept WSUD asset design ndash larger assets only (wetlands bioretention basins sed basin etc) ndash sufficient design detail to confirm spatial requirements

                                                PlansPermit conditions

                                                bull Detailed engineering design bull Site Management Plan (final)bull Asset maintenance plan (final)bull Handover arrangements (if public)

                                                54

                                                STORM ndash Online toolbull Print out of STORM reportbull Make sure meets 100 or

                                                morebull Make sure report inputs and

                                                results match plan

                                                Modelling - SWQ

                                                MUSIC ndash Proprietary softwarebull Provide a copy of the model filebull Print out the modelling resultsbull Provide summary of your model

                                                inputs for each treatment train (iecatchment size impervious treatment area etc)

                                                bull Provide a print out of the model schematic

                                                Bonus points bull Provide details of model

                                                parametersbull Provide results of MUSIC auditor

                                                run (if using Melbourne Water MUSIC Guidelines)

                                                56

                                                Assessment against standards

                                                bull Say what you have done (or will do) to meet each standardbull Donrsquot forget (if WSUD) details of maintenance and asset

                                                ownershipbull Where applicable be explicit why yoursquove chosen (or not chosen) to

                                                respond the way you have Egbull Opportunitiesbull Site constraintsbull Practicaloperational issues bull Brief dot point summary of options analysis if complex

                                                bull Make sure if it doesnrsquot meet the standard it meets the objectivebull Make sure shown on plan and consistent with modelling and rest of

                                                documentation

                                                57

                                                Resources

                                                Local stormwaterWSUD policiesBaysideKingstonCaseyMonashMelbourneYarraMoonee ValleyPort PhilipStonningtonHumeCampaspeBass Coast

                                                Local ESD (including IWM) policies Greater BendigoGreater DandenongHobsons BayWhittleseaWyndhamWhitehorseManninghamMorelandDarebinBanyuleKnoxBrimbank

                                                Council planning resources

                                                Application resources ndashexamplesDELWP Practice Note ndashformal guide to the new controlsMoreland ndash application checklists and example plans for a variety of residential developmentsPort Philip ndash compliance guidelines checklist and examplesMoonee Valley ndash checklists and example plans including site management plans Greater Bendigo ndash WSUD kitBayside ndash application guidelines and example plans

                                                59

                                                Technical guidelines (modelling design construction)

                                                Melbourne Water

                                                STORM calculatorMUSIC auditor - lsquohow torsquo video here

                                                Melbourne Water technical guidelines page- WSUD asset life cycle costings and model maintenance guidelines- MUSIC guidelines- Stormwater harvesting guidelines- WSUD life cycle costings and

                                                maintenance guidelines- Design and construction guidelines

                                                for variety of assetshttpswwwmelbournewatercomauplanning-and-buildingdeveloper-guides-and-resourcesguidelines-drawings-and-checklistsguidelines

                                                Council

                                                South-Eastern Growth Council WSUD guidelines ndash note that some individual Councils have their own addendumsMelbournePort PhilipNorth-West Growth Council WSUD guidelines - note that some individual Councils have their own addendumsGreater BendigoMilduraBallaratBaw BawWyndhamMoreland ndash tree pits and raingardens

                                                60

                                                IWM

                                                Example Council IWM strategiesMelbourneCaseyMonashKingston

                                                Resilient Melbourne ndash IWM information lsquohubrsquoClearwater ndash capacity building and case studiesMelbourne Water ndash funding opportunities for IWM projects

                                                Stormwater offset schemes

                                                KingstonGreater GeelongMelbourne Water ndash non scheme contributions

                                                Site management

                                                EPA guidelines- management of erosion and sediment

                                                Next steps and other stormwater initiatives

                                                Emma Stewart DELWP

                                                62

                                                Next steps

                                                bull Trainingbull The EPArsquos BPEM Reviewbull Offsets policybull Review of STORM bull Building controls

                                                63

                                                State Stormwater policies

                                                64

                                                Thank you

                                                • Slide Number 1
                                                • Slide Number 2
                                                • History of WSUD
                                                • History of WSUD
                                                • Transformational change in urban water
                                                • Inconsistencies and inequities in our approach to stormwater management
                                                • Slide Number 8
                                                • Terms of Reference
                                                • Improving Stormwater Management Advisory Committee
                                                • Wide consultation
                                                • Stakeholder feedback
                                                • Stakeholder feedback
                                                • Committee submitted its report in September 2018
                                                • Committee Recomendations
                                                • Planning reforms
                                                • Future policy directions
                                                • Supporting actions
                                                • Slide Number 19
                                                • Government response (to date)
                                                • Longer term recommendations
                                                • State-based planning requirements (lsquobeforersquo)
                                                • State-based planning requirements (lsquoafterrsquo)
                                                • Development types (volume)
                                                • Slide Number 25
                                                • Amendment VC154
                                                • Whatrsquos in
                                                • Slide Number 28
                                                • Key elements of clauses
                                                • Clause 5318 ndash subdivision
                                                • Clause 5318 ndash Buildings and works
                                                • Townhouses - Standard B9
                                                • Slide Number 33
                                                • Slide Number 34
                                                • Slide Number 35
                                                • Slide Number 36
                                                • Slide Number 37
                                                • Buildings and works - Site management standard
                                                • Site management
                                                • Planning Advisory Note No 75
                                                • Slide Number 41
                                                • Slide Number 42
                                                • Slide Number 43
                                                • Slide Number 44
                                                • Slide Number 45
                                                • Slide Number 46
                                                • Slide Number 47
                                                • Slide Number 48
                                                • Slide Number 49
                                                • Slide Number 50
                                                • Slide Number 51
                                                • Slide Number 52
                                                • Slide Number 53
                                                • Slide Number 54
                                                • Slide Number 55
                                                • Slide Number 56
                                                • Slide Number 57
                                                • Slide Number 58
                                                • Slide Number 59
                                                • Slide Number 60
                                                • Slide Number 61
                                                • Next steps
                                                • State Stormwater policies
                                                • Slide Number 64

                                                  26

                                                  Amendment VC154

                                                  Victoria Planning Provision changesbull New clause (5318) and changes to an existing clause

                                                  (5503) to expand the stormwater requirements to more development types

                                                  bull New objectives to manage toxicants and encourage broader benefits of stormwater management

                                                  27

                                                  Whatrsquos in

                                                  Applies to an application tobull subdivide land bull construct a building bull construct or carry out works

                                                  In both hellip

                                                  Clause 5318bull commercial zonesbull industrial zonesbull public-use zones

                                                  Clause 5518 bull Construct townhouses

                                                  Whatrsquos out of clause 5318

                                                  bull Developments and subdivisions approved or lodged prior to the amendment

                                                  bull Developments which do not require planning permission

                                                  bull Vicsmart applications

                                                  bull Applications for land within development or incorporated plans approved before the amendment

                                                  bull Extensions and works lt 50m2

                                                  bull Applications after the amendment to amend existing planning permits

                                                  If in doubt ask a planner

                                                  29

                                                  Key elements of clauses

                                                  Industrial commercial applications (Clause 5318)tobull subdivide land bull construct a building bull construct or carry out works

                                                  Stormwater management objectives + standard (W1)

                                                  Stormwater management objectives + standard (W2)+ Site management objectives + standard (W3)

                                                  Decision guidelines

                                                  Same for Clause 5503 (townhouses)

                                                  30

                                                  Clause 5318 ndash subdivision

                                                  Stormwater management standard W1 The stormwater management system should be bull Designed and managed in accordance with the requirements and

                                                  to the satisfaction of the relevant drainage authoritybull Designed and managed in accordance with the requirements and

                                                  to the satisfaction of the water authority where reuse of stormwater is proposed

                                                  bull Designed to meet the current best practice performance objectives for stormwater quality as contained in the BPEM

                                                  bull Designed to ensure that flows downstream of the subdivision site are restricted to pre-development levels unless increased flows are approved by the relevant drainage authority and there are no detrimental downstream impacts

                                                  bull Designed to contribute to cooling improving local habitat and providing attractive and enjoyable spaces

                                                  31

                                                  Clause 5318 ndash Buildings and works

                                                  Standard W2The stormwater management system should be designed to

                                                  bull Meet the current best practice performance objectives for stormwater quality as contained in the BPEM

                                                  bull Contribute to cooling improving local habitat and providing attractive and enjoyable spaces

                                                  bull Minimise the impact of chemical pollutants and other toxicants including by but not limited to bunding and covering of roofing of storage loading and work areas

                                                  32

                                                  Townhouses - Standard B9

                                                  Clause 5503 ndash Permeability and stormwater management objectives and standard B9

                                                  Objectivesbull Similar to 5318 (including the cooling liveability

                                                  objective)bull gt20 perviousness objective (unchanged)

                                                  Standardbull NEW - cooling liveability objectivebull NEW ndash requirement to meet BPEM

                                                  What does this all mean

                                                  34

                                                  Clause 5318 - Whatrsquos in

                                                  35

                                                  Urban cooling Reduce heat radiation from buildings and hard surfaces throughbull Shade trees in car parks or over driveways bull More open space and treesbull Green roofsbull Green walls

                                                  36

                                                  Optionsbull Passive irrigationbull Integrate assets into

                                                  communal open spacebull Tree pits and permeable

                                                  paving (driveways and carpark)

                                                  bull Stormwater harvesting (major developments only)

                                                  Infiltration habitat amenity

                                                  37

                                                  Control harmful chemicals

                                                  Optionsbull Careful layoutbull Consider alternative less harmful substancesbull Roofed designated storage areabull Internal drainage design to sewer or a treatment devicebull Bunding

                                                  38

                                                  Standard W3Standard W3 requires that application describe how the site will be managed prior to and during the construction period The application should set out requirements for managingbull Erosion and sedimentbull Stormwaterbull Litter concrete and other construction wastesbull Chemical contamination

                                                  Buildings and works - Site management standard

                                                  39

                                                  Site management

                                                  40

                                                  Planning Advisory Note No 75

                                                  Implications for industry

                                                  Kate MatthewsStormwater Victoria

                                                  1 Development proponents- Developers- Consultants (engineers stormwater specialists and planners)- Council (when developing public land lt$1 million)

                                                  2 Development assessors- Council statutory planners- Council internal referrals (engineering assets ESD stormwater officers)

                                                  3 Strategy- Council strategic planners

                                                  4 Melbourne Water

                                                  Whorsquos affected

                                                  43

                                                  What are the implications

                                                  bull BPEM - Itrsquos not just subdivisions any more

                                                  bull Cost ndash offset or assetbull Early planning and integration ndash more

                                                  work up frontbull Not just engineeringbull Varying Council skills and experience

                                                  Development Proponents

                                                  44

                                                  If already have a local policy for WSUDESD no real change

                                                  If notbull Workload and resourcingbull Increased detail and technical

                                                  contentbull Administrative arrangements ndash

                                                  referrals permit conditions ndashmake sure you make 60 stat days

                                                  bull Applicant pressure ndash what do you want

                                                  bull Assets

                                                  Development Assessors

                                                  45

                                                  bull Structure plans and rezoning ndashopportunities for localregional approach

                                                  bull IWM and Stormwater Management Plans ndash opportunities for these to be implemented through the controls spatial opportunities

                                                  bull Opportunities for development of Council offset strategies

                                                  Strategy

                                                  Offsets

                                                  bull Developer enters into an agreement with relevant drainage authority to financially contribute to off-site stormwatermanagement in lieu of providing on-site treatment

                                                  bull Already available for residential subdivisions in Melbourne (Clause 56) through MWCs Stormwater Quality Offset scheme

                                                  What are stormwater quality offsets

                                                  X Not drainage contributions (MWC drainage scheme)

                                                  X Not development contributions (DCPICP)

                                                  47

                                                  When to use

                                                  bull Not in MW DSS or growth area where therersquos an existing framework for funding SW treatment

                                                  bull Onsite treatment not practical or desirable

                                                  bull To fund planned localregional stormwater treatment works in that catchment via an existing offset scheme

                                                  bull Council and developer both agree to it

                                                  48

                                                  OffsetsExample ndash Kingston Offset Scheme

                                                  Asset ownership and maintenance

                                                  bull Whorsquos going to own itbull Whorsquos going to maintain itbull How do you maintain itbull How much will it cost

                                                  bull Where is itbull Is maintenance burden

                                                  practical for likely future owners

                                                  bull Whorsquos going to monitor compliance and how

                                                  The detail is in the permit conditions

                                                  Application requirements

                                                  ldquoAn application must be accompanied by details of the proposed stormwater management system including drainage works and retention detention and discharges of stormwater to the drainage systemrdquo ndash Clause 5318

                                                  What does the planning scheme require

                                                  But alsohellipNeed to provide sufficient information to Council which demonstrates that you comply and how you comply with all the other standards ndash eg urban coolinghabitatetc BPEM site management pollutant control infiltration (as relevant to development type

                                                  51

                                                  1 PlansWhat are you doing where is it going and does it fit

                                                  2 ModellingDo you (or can you) meet BPEM requirements

                                                  3 Written response to standardsHow does your proposal comply with the requirements

                                                  52

                                                  Application

                                                  bull Site plan ndash show all assetsWSUD treatments and any IWM features on the site layout plan with everything else

                                                  bull Landscape plan ndash if planting design passive irrigation etc forms part of response to requirements show

                                                  bull Site management plan (depending on Council)

                                                  bull Separate WSUDIWM plan showing all features on a stripped back background

                                                  bull Concept WSUD asset design ndash larger assets only (wetlands bioretention basins sed basin etc) ndash sufficient design detail to confirm spatial requirements

                                                  PlansPermit conditions

                                                  bull Detailed engineering design bull Site Management Plan (final)bull Asset maintenance plan (final)bull Handover arrangements (if public)

                                                  54

                                                  STORM ndash Online toolbull Print out of STORM reportbull Make sure meets 100 or

                                                  morebull Make sure report inputs and

                                                  results match plan

                                                  Modelling - SWQ

                                                  MUSIC ndash Proprietary softwarebull Provide a copy of the model filebull Print out the modelling resultsbull Provide summary of your model

                                                  inputs for each treatment train (iecatchment size impervious treatment area etc)

                                                  bull Provide a print out of the model schematic

                                                  Bonus points bull Provide details of model

                                                  parametersbull Provide results of MUSIC auditor

                                                  run (if using Melbourne Water MUSIC Guidelines)

                                                  56

                                                  Assessment against standards

                                                  bull Say what you have done (or will do) to meet each standardbull Donrsquot forget (if WSUD) details of maintenance and asset

                                                  ownershipbull Where applicable be explicit why yoursquove chosen (or not chosen) to

                                                  respond the way you have Egbull Opportunitiesbull Site constraintsbull Practicaloperational issues bull Brief dot point summary of options analysis if complex

                                                  bull Make sure if it doesnrsquot meet the standard it meets the objectivebull Make sure shown on plan and consistent with modelling and rest of

                                                  documentation

                                                  57

                                                  Resources

                                                  Local stormwaterWSUD policiesBaysideKingstonCaseyMonashMelbourneYarraMoonee ValleyPort PhilipStonningtonHumeCampaspeBass Coast

                                                  Local ESD (including IWM) policies Greater BendigoGreater DandenongHobsons BayWhittleseaWyndhamWhitehorseManninghamMorelandDarebinBanyuleKnoxBrimbank

                                                  Council planning resources

                                                  Application resources ndashexamplesDELWP Practice Note ndashformal guide to the new controlsMoreland ndash application checklists and example plans for a variety of residential developmentsPort Philip ndash compliance guidelines checklist and examplesMoonee Valley ndash checklists and example plans including site management plans Greater Bendigo ndash WSUD kitBayside ndash application guidelines and example plans

                                                  59

                                                  Technical guidelines (modelling design construction)

                                                  Melbourne Water

                                                  STORM calculatorMUSIC auditor - lsquohow torsquo video here

                                                  Melbourne Water technical guidelines page- WSUD asset life cycle costings and model maintenance guidelines- MUSIC guidelines- Stormwater harvesting guidelines- WSUD life cycle costings and

                                                  maintenance guidelines- Design and construction guidelines

                                                  for variety of assetshttpswwwmelbournewatercomauplanning-and-buildingdeveloper-guides-and-resourcesguidelines-drawings-and-checklistsguidelines

                                                  Council

                                                  South-Eastern Growth Council WSUD guidelines ndash note that some individual Councils have their own addendumsMelbournePort PhilipNorth-West Growth Council WSUD guidelines - note that some individual Councils have their own addendumsGreater BendigoMilduraBallaratBaw BawWyndhamMoreland ndash tree pits and raingardens

                                                  60

                                                  IWM

                                                  Example Council IWM strategiesMelbourneCaseyMonashKingston

                                                  Resilient Melbourne ndash IWM information lsquohubrsquoClearwater ndash capacity building and case studiesMelbourne Water ndash funding opportunities for IWM projects

                                                  Stormwater offset schemes

                                                  KingstonGreater GeelongMelbourne Water ndash non scheme contributions

                                                  Site management

                                                  EPA guidelines- management of erosion and sediment

                                                  Next steps and other stormwater initiatives

                                                  Emma Stewart DELWP

                                                  62

                                                  Next steps

                                                  bull Trainingbull The EPArsquos BPEM Reviewbull Offsets policybull Review of STORM bull Building controls

                                                  63

                                                  State Stormwater policies

                                                  64

                                                  Thank you

                                                  • Slide Number 1
                                                  • Slide Number 2
                                                  • History of WSUD
                                                  • History of WSUD
                                                  • Transformational change in urban water
                                                  • Inconsistencies and inequities in our approach to stormwater management
                                                  • Slide Number 8
                                                  • Terms of Reference
                                                  • Improving Stormwater Management Advisory Committee
                                                  • Wide consultation
                                                  • Stakeholder feedback
                                                  • Stakeholder feedback
                                                  • Committee submitted its report in September 2018
                                                  • Committee Recomendations
                                                  • Planning reforms
                                                  • Future policy directions
                                                  • Supporting actions
                                                  • Slide Number 19
                                                  • Government response (to date)
                                                  • Longer term recommendations
                                                  • State-based planning requirements (lsquobeforersquo)
                                                  • State-based planning requirements (lsquoafterrsquo)
                                                  • Development types (volume)
                                                  • Slide Number 25
                                                  • Amendment VC154
                                                  • Whatrsquos in
                                                  • Slide Number 28
                                                  • Key elements of clauses
                                                  • Clause 5318 ndash subdivision
                                                  • Clause 5318 ndash Buildings and works
                                                  • Townhouses - Standard B9
                                                  • Slide Number 33
                                                  • Slide Number 34
                                                  • Slide Number 35
                                                  • Slide Number 36
                                                  • Slide Number 37
                                                  • Buildings and works - Site management standard
                                                  • Site management
                                                  • Planning Advisory Note No 75
                                                  • Slide Number 41
                                                  • Slide Number 42
                                                  • Slide Number 43
                                                  • Slide Number 44
                                                  • Slide Number 45
                                                  • Slide Number 46
                                                  • Slide Number 47
                                                  • Slide Number 48
                                                  • Slide Number 49
                                                  • Slide Number 50
                                                  • Slide Number 51
                                                  • Slide Number 52
                                                  • Slide Number 53
                                                  • Slide Number 54
                                                  • Slide Number 55
                                                  • Slide Number 56
                                                  • Slide Number 57
                                                  • Slide Number 58
                                                  • Slide Number 59
                                                  • Slide Number 60
                                                  • Slide Number 61
                                                  • Next steps
                                                  • State Stormwater policies
                                                  • Slide Number 64

                                                    27

                                                    Whatrsquos in

                                                    Applies to an application tobull subdivide land bull construct a building bull construct or carry out works

                                                    In both hellip

                                                    Clause 5318bull commercial zonesbull industrial zonesbull public-use zones

                                                    Clause 5518 bull Construct townhouses

                                                    Whatrsquos out of clause 5318

                                                    bull Developments and subdivisions approved or lodged prior to the amendment

                                                    bull Developments which do not require planning permission

                                                    bull Vicsmart applications

                                                    bull Applications for land within development or incorporated plans approved before the amendment

                                                    bull Extensions and works lt 50m2

                                                    bull Applications after the amendment to amend existing planning permits

                                                    If in doubt ask a planner

                                                    29

                                                    Key elements of clauses

                                                    Industrial commercial applications (Clause 5318)tobull subdivide land bull construct a building bull construct or carry out works

                                                    Stormwater management objectives + standard (W1)

                                                    Stormwater management objectives + standard (W2)+ Site management objectives + standard (W3)

                                                    Decision guidelines

                                                    Same for Clause 5503 (townhouses)

                                                    30

                                                    Clause 5318 ndash subdivision

                                                    Stormwater management standard W1 The stormwater management system should be bull Designed and managed in accordance with the requirements and

                                                    to the satisfaction of the relevant drainage authoritybull Designed and managed in accordance with the requirements and

                                                    to the satisfaction of the water authority where reuse of stormwater is proposed

                                                    bull Designed to meet the current best practice performance objectives for stormwater quality as contained in the BPEM

                                                    bull Designed to ensure that flows downstream of the subdivision site are restricted to pre-development levels unless increased flows are approved by the relevant drainage authority and there are no detrimental downstream impacts

                                                    bull Designed to contribute to cooling improving local habitat and providing attractive and enjoyable spaces

                                                    31

                                                    Clause 5318 ndash Buildings and works

                                                    Standard W2The stormwater management system should be designed to

                                                    bull Meet the current best practice performance objectives for stormwater quality as contained in the BPEM

                                                    bull Contribute to cooling improving local habitat and providing attractive and enjoyable spaces

                                                    bull Minimise the impact of chemical pollutants and other toxicants including by but not limited to bunding and covering of roofing of storage loading and work areas

                                                    32

                                                    Townhouses - Standard B9

                                                    Clause 5503 ndash Permeability and stormwater management objectives and standard B9

                                                    Objectivesbull Similar to 5318 (including the cooling liveability

                                                    objective)bull gt20 perviousness objective (unchanged)

                                                    Standardbull NEW - cooling liveability objectivebull NEW ndash requirement to meet BPEM

                                                    What does this all mean

                                                    34

                                                    Clause 5318 - Whatrsquos in

                                                    35

                                                    Urban cooling Reduce heat radiation from buildings and hard surfaces throughbull Shade trees in car parks or over driveways bull More open space and treesbull Green roofsbull Green walls

                                                    36

                                                    Optionsbull Passive irrigationbull Integrate assets into

                                                    communal open spacebull Tree pits and permeable

                                                    paving (driveways and carpark)

                                                    bull Stormwater harvesting (major developments only)

                                                    Infiltration habitat amenity

                                                    37

                                                    Control harmful chemicals

                                                    Optionsbull Careful layoutbull Consider alternative less harmful substancesbull Roofed designated storage areabull Internal drainage design to sewer or a treatment devicebull Bunding

                                                    38

                                                    Standard W3Standard W3 requires that application describe how the site will be managed prior to and during the construction period The application should set out requirements for managingbull Erosion and sedimentbull Stormwaterbull Litter concrete and other construction wastesbull Chemical contamination

                                                    Buildings and works - Site management standard

                                                    39

                                                    Site management

                                                    40

                                                    Planning Advisory Note No 75

                                                    Implications for industry

                                                    Kate MatthewsStormwater Victoria

                                                    1 Development proponents- Developers- Consultants (engineers stormwater specialists and planners)- Council (when developing public land lt$1 million)

                                                    2 Development assessors- Council statutory planners- Council internal referrals (engineering assets ESD stormwater officers)

                                                    3 Strategy- Council strategic planners

                                                    4 Melbourne Water

                                                    Whorsquos affected

                                                    43

                                                    What are the implications

                                                    bull BPEM - Itrsquos not just subdivisions any more

                                                    bull Cost ndash offset or assetbull Early planning and integration ndash more

                                                    work up frontbull Not just engineeringbull Varying Council skills and experience

                                                    Development Proponents

                                                    44

                                                    If already have a local policy for WSUDESD no real change

                                                    If notbull Workload and resourcingbull Increased detail and technical

                                                    contentbull Administrative arrangements ndash

                                                    referrals permit conditions ndashmake sure you make 60 stat days

                                                    bull Applicant pressure ndash what do you want

                                                    bull Assets

                                                    Development Assessors

                                                    45

                                                    bull Structure plans and rezoning ndashopportunities for localregional approach

                                                    bull IWM and Stormwater Management Plans ndash opportunities for these to be implemented through the controls spatial opportunities

                                                    bull Opportunities for development of Council offset strategies

                                                    Strategy

                                                    Offsets

                                                    bull Developer enters into an agreement with relevant drainage authority to financially contribute to off-site stormwatermanagement in lieu of providing on-site treatment

                                                    bull Already available for residential subdivisions in Melbourne (Clause 56) through MWCs Stormwater Quality Offset scheme

                                                    What are stormwater quality offsets

                                                    X Not drainage contributions (MWC drainage scheme)

                                                    X Not development contributions (DCPICP)

                                                    47

                                                    When to use

                                                    bull Not in MW DSS or growth area where therersquos an existing framework for funding SW treatment

                                                    bull Onsite treatment not practical or desirable

                                                    bull To fund planned localregional stormwater treatment works in that catchment via an existing offset scheme

                                                    bull Council and developer both agree to it

                                                    48

                                                    OffsetsExample ndash Kingston Offset Scheme

                                                    Asset ownership and maintenance

                                                    bull Whorsquos going to own itbull Whorsquos going to maintain itbull How do you maintain itbull How much will it cost

                                                    bull Where is itbull Is maintenance burden

                                                    practical for likely future owners

                                                    bull Whorsquos going to monitor compliance and how

                                                    The detail is in the permit conditions

                                                    Application requirements

                                                    ldquoAn application must be accompanied by details of the proposed stormwater management system including drainage works and retention detention and discharges of stormwater to the drainage systemrdquo ndash Clause 5318

                                                    What does the planning scheme require

                                                    But alsohellipNeed to provide sufficient information to Council which demonstrates that you comply and how you comply with all the other standards ndash eg urban coolinghabitatetc BPEM site management pollutant control infiltration (as relevant to development type

                                                    51

                                                    1 PlansWhat are you doing where is it going and does it fit

                                                    2 ModellingDo you (or can you) meet BPEM requirements

                                                    3 Written response to standardsHow does your proposal comply with the requirements

                                                    52

                                                    Application

                                                    bull Site plan ndash show all assetsWSUD treatments and any IWM features on the site layout plan with everything else

                                                    bull Landscape plan ndash if planting design passive irrigation etc forms part of response to requirements show

                                                    bull Site management plan (depending on Council)

                                                    bull Separate WSUDIWM plan showing all features on a stripped back background

                                                    bull Concept WSUD asset design ndash larger assets only (wetlands bioretention basins sed basin etc) ndash sufficient design detail to confirm spatial requirements

                                                    PlansPermit conditions

                                                    bull Detailed engineering design bull Site Management Plan (final)bull Asset maintenance plan (final)bull Handover arrangements (if public)

                                                    54

                                                    STORM ndash Online toolbull Print out of STORM reportbull Make sure meets 100 or

                                                    morebull Make sure report inputs and

                                                    results match plan

                                                    Modelling - SWQ

                                                    MUSIC ndash Proprietary softwarebull Provide a copy of the model filebull Print out the modelling resultsbull Provide summary of your model

                                                    inputs for each treatment train (iecatchment size impervious treatment area etc)

                                                    bull Provide a print out of the model schematic

                                                    Bonus points bull Provide details of model

                                                    parametersbull Provide results of MUSIC auditor

                                                    run (if using Melbourne Water MUSIC Guidelines)

                                                    56

                                                    Assessment against standards

                                                    bull Say what you have done (or will do) to meet each standardbull Donrsquot forget (if WSUD) details of maintenance and asset

                                                    ownershipbull Where applicable be explicit why yoursquove chosen (or not chosen) to

                                                    respond the way you have Egbull Opportunitiesbull Site constraintsbull Practicaloperational issues bull Brief dot point summary of options analysis if complex

                                                    bull Make sure if it doesnrsquot meet the standard it meets the objectivebull Make sure shown on plan and consistent with modelling and rest of

                                                    documentation

                                                    57

                                                    Resources

                                                    Local stormwaterWSUD policiesBaysideKingstonCaseyMonashMelbourneYarraMoonee ValleyPort PhilipStonningtonHumeCampaspeBass Coast

                                                    Local ESD (including IWM) policies Greater BendigoGreater DandenongHobsons BayWhittleseaWyndhamWhitehorseManninghamMorelandDarebinBanyuleKnoxBrimbank

                                                    Council planning resources

                                                    Application resources ndashexamplesDELWP Practice Note ndashformal guide to the new controlsMoreland ndash application checklists and example plans for a variety of residential developmentsPort Philip ndash compliance guidelines checklist and examplesMoonee Valley ndash checklists and example plans including site management plans Greater Bendigo ndash WSUD kitBayside ndash application guidelines and example plans

                                                    59

                                                    Technical guidelines (modelling design construction)

                                                    Melbourne Water

                                                    STORM calculatorMUSIC auditor - lsquohow torsquo video here

                                                    Melbourne Water technical guidelines page- WSUD asset life cycle costings and model maintenance guidelines- MUSIC guidelines- Stormwater harvesting guidelines- WSUD life cycle costings and

                                                    maintenance guidelines- Design and construction guidelines

                                                    for variety of assetshttpswwwmelbournewatercomauplanning-and-buildingdeveloper-guides-and-resourcesguidelines-drawings-and-checklistsguidelines

                                                    Council

                                                    South-Eastern Growth Council WSUD guidelines ndash note that some individual Councils have their own addendumsMelbournePort PhilipNorth-West Growth Council WSUD guidelines - note that some individual Councils have their own addendumsGreater BendigoMilduraBallaratBaw BawWyndhamMoreland ndash tree pits and raingardens

                                                    60

                                                    IWM

                                                    Example Council IWM strategiesMelbourneCaseyMonashKingston

                                                    Resilient Melbourne ndash IWM information lsquohubrsquoClearwater ndash capacity building and case studiesMelbourne Water ndash funding opportunities for IWM projects

                                                    Stormwater offset schemes

                                                    KingstonGreater GeelongMelbourne Water ndash non scheme contributions

                                                    Site management

                                                    EPA guidelines- management of erosion and sediment

                                                    Next steps and other stormwater initiatives

                                                    Emma Stewart DELWP

                                                    62

                                                    Next steps

                                                    bull Trainingbull The EPArsquos BPEM Reviewbull Offsets policybull Review of STORM bull Building controls

                                                    63

                                                    State Stormwater policies

                                                    64

                                                    Thank you

                                                    • Slide Number 1
                                                    • Slide Number 2
                                                    • History of WSUD
                                                    • History of WSUD
                                                    • Transformational change in urban water
                                                    • Inconsistencies and inequities in our approach to stormwater management
                                                    • Slide Number 8
                                                    • Terms of Reference
                                                    • Improving Stormwater Management Advisory Committee
                                                    • Wide consultation
                                                    • Stakeholder feedback
                                                    • Stakeholder feedback
                                                    • Committee submitted its report in September 2018
                                                    • Committee Recomendations
                                                    • Planning reforms
                                                    • Future policy directions
                                                    • Supporting actions
                                                    • Slide Number 19
                                                    • Government response (to date)
                                                    • Longer term recommendations
                                                    • State-based planning requirements (lsquobeforersquo)
                                                    • State-based planning requirements (lsquoafterrsquo)
                                                    • Development types (volume)
                                                    • Slide Number 25
                                                    • Amendment VC154
                                                    • Whatrsquos in
                                                    • Slide Number 28
                                                    • Key elements of clauses
                                                    • Clause 5318 ndash subdivision
                                                    • Clause 5318 ndash Buildings and works
                                                    • Townhouses - Standard B9
                                                    • Slide Number 33
                                                    • Slide Number 34
                                                    • Slide Number 35
                                                    • Slide Number 36
                                                    • Slide Number 37
                                                    • Buildings and works - Site management standard
                                                    • Site management
                                                    • Planning Advisory Note No 75
                                                    • Slide Number 41
                                                    • Slide Number 42
                                                    • Slide Number 43
                                                    • Slide Number 44
                                                    • Slide Number 45
                                                    • Slide Number 46
                                                    • Slide Number 47
                                                    • Slide Number 48
                                                    • Slide Number 49
                                                    • Slide Number 50
                                                    • Slide Number 51
                                                    • Slide Number 52
                                                    • Slide Number 53
                                                    • Slide Number 54
                                                    • Slide Number 55
                                                    • Slide Number 56
                                                    • Slide Number 57
                                                    • Slide Number 58
                                                    • Slide Number 59
                                                    • Slide Number 60
                                                    • Slide Number 61
                                                    • Next steps
                                                    • State Stormwater policies
                                                    • Slide Number 64

                                                      Whatrsquos out of clause 5318

                                                      bull Developments and subdivisions approved or lodged prior to the amendment

                                                      bull Developments which do not require planning permission

                                                      bull Vicsmart applications

                                                      bull Applications for land within development or incorporated plans approved before the amendment

                                                      bull Extensions and works lt 50m2

                                                      bull Applications after the amendment to amend existing planning permits

                                                      If in doubt ask a planner

                                                      29

                                                      Key elements of clauses

                                                      Industrial commercial applications (Clause 5318)tobull subdivide land bull construct a building bull construct or carry out works

                                                      Stormwater management objectives + standard (W1)

                                                      Stormwater management objectives + standard (W2)+ Site management objectives + standard (W3)

                                                      Decision guidelines

                                                      Same for Clause 5503 (townhouses)

                                                      30

                                                      Clause 5318 ndash subdivision

                                                      Stormwater management standard W1 The stormwater management system should be bull Designed and managed in accordance with the requirements and

                                                      to the satisfaction of the relevant drainage authoritybull Designed and managed in accordance with the requirements and

                                                      to the satisfaction of the water authority where reuse of stormwater is proposed

                                                      bull Designed to meet the current best practice performance objectives for stormwater quality as contained in the BPEM

                                                      bull Designed to ensure that flows downstream of the subdivision site are restricted to pre-development levels unless increased flows are approved by the relevant drainage authority and there are no detrimental downstream impacts

                                                      bull Designed to contribute to cooling improving local habitat and providing attractive and enjoyable spaces

                                                      31

                                                      Clause 5318 ndash Buildings and works

                                                      Standard W2The stormwater management system should be designed to

                                                      bull Meet the current best practice performance objectives for stormwater quality as contained in the BPEM

                                                      bull Contribute to cooling improving local habitat and providing attractive and enjoyable spaces

                                                      bull Minimise the impact of chemical pollutants and other toxicants including by but not limited to bunding and covering of roofing of storage loading and work areas

                                                      32

                                                      Townhouses - Standard B9

                                                      Clause 5503 ndash Permeability and stormwater management objectives and standard B9

                                                      Objectivesbull Similar to 5318 (including the cooling liveability

                                                      objective)bull gt20 perviousness objective (unchanged)

                                                      Standardbull NEW - cooling liveability objectivebull NEW ndash requirement to meet BPEM

                                                      What does this all mean

                                                      34

                                                      Clause 5318 - Whatrsquos in

                                                      35

                                                      Urban cooling Reduce heat radiation from buildings and hard surfaces throughbull Shade trees in car parks or over driveways bull More open space and treesbull Green roofsbull Green walls

                                                      36

                                                      Optionsbull Passive irrigationbull Integrate assets into

                                                      communal open spacebull Tree pits and permeable

                                                      paving (driveways and carpark)

                                                      bull Stormwater harvesting (major developments only)

                                                      Infiltration habitat amenity

                                                      37

                                                      Control harmful chemicals

                                                      Optionsbull Careful layoutbull Consider alternative less harmful substancesbull Roofed designated storage areabull Internal drainage design to sewer or a treatment devicebull Bunding

                                                      38

                                                      Standard W3Standard W3 requires that application describe how the site will be managed prior to and during the construction period The application should set out requirements for managingbull Erosion and sedimentbull Stormwaterbull Litter concrete and other construction wastesbull Chemical contamination

                                                      Buildings and works - Site management standard

                                                      39

                                                      Site management

                                                      40

                                                      Planning Advisory Note No 75

                                                      Implications for industry

                                                      Kate MatthewsStormwater Victoria

                                                      1 Development proponents- Developers- Consultants (engineers stormwater specialists and planners)- Council (when developing public land lt$1 million)

                                                      2 Development assessors- Council statutory planners- Council internal referrals (engineering assets ESD stormwater officers)

                                                      3 Strategy- Council strategic planners

                                                      4 Melbourne Water

                                                      Whorsquos affected

                                                      43

                                                      What are the implications

                                                      bull BPEM - Itrsquos not just subdivisions any more

                                                      bull Cost ndash offset or assetbull Early planning and integration ndash more

                                                      work up frontbull Not just engineeringbull Varying Council skills and experience

                                                      Development Proponents

                                                      44

                                                      If already have a local policy for WSUDESD no real change

                                                      If notbull Workload and resourcingbull Increased detail and technical

                                                      contentbull Administrative arrangements ndash

                                                      referrals permit conditions ndashmake sure you make 60 stat days

                                                      bull Applicant pressure ndash what do you want

                                                      bull Assets

                                                      Development Assessors

                                                      45

                                                      bull Structure plans and rezoning ndashopportunities for localregional approach

                                                      bull IWM and Stormwater Management Plans ndash opportunities for these to be implemented through the controls spatial opportunities

                                                      bull Opportunities for development of Council offset strategies

                                                      Strategy

                                                      Offsets

                                                      bull Developer enters into an agreement with relevant drainage authority to financially contribute to off-site stormwatermanagement in lieu of providing on-site treatment

                                                      bull Already available for residential subdivisions in Melbourne (Clause 56) through MWCs Stormwater Quality Offset scheme

                                                      What are stormwater quality offsets

                                                      X Not drainage contributions (MWC drainage scheme)

                                                      X Not development contributions (DCPICP)

                                                      47

                                                      When to use

                                                      bull Not in MW DSS or growth area where therersquos an existing framework for funding SW treatment

                                                      bull Onsite treatment not practical or desirable

                                                      bull To fund planned localregional stormwater treatment works in that catchment via an existing offset scheme

                                                      bull Council and developer both agree to it

                                                      48

                                                      OffsetsExample ndash Kingston Offset Scheme

                                                      Asset ownership and maintenance

                                                      bull Whorsquos going to own itbull Whorsquos going to maintain itbull How do you maintain itbull How much will it cost

                                                      bull Where is itbull Is maintenance burden

                                                      practical for likely future owners

                                                      bull Whorsquos going to monitor compliance and how

                                                      The detail is in the permit conditions

                                                      Application requirements

                                                      ldquoAn application must be accompanied by details of the proposed stormwater management system including drainage works and retention detention and discharges of stormwater to the drainage systemrdquo ndash Clause 5318

                                                      What does the planning scheme require

                                                      But alsohellipNeed to provide sufficient information to Council which demonstrates that you comply and how you comply with all the other standards ndash eg urban coolinghabitatetc BPEM site management pollutant control infiltration (as relevant to development type

                                                      51

                                                      1 PlansWhat are you doing where is it going and does it fit

                                                      2 ModellingDo you (or can you) meet BPEM requirements

                                                      3 Written response to standardsHow does your proposal comply with the requirements

                                                      52

                                                      Application

                                                      bull Site plan ndash show all assetsWSUD treatments and any IWM features on the site layout plan with everything else

                                                      bull Landscape plan ndash if planting design passive irrigation etc forms part of response to requirements show

                                                      bull Site management plan (depending on Council)

                                                      bull Separate WSUDIWM plan showing all features on a stripped back background

                                                      bull Concept WSUD asset design ndash larger assets only (wetlands bioretention basins sed basin etc) ndash sufficient design detail to confirm spatial requirements

                                                      PlansPermit conditions

                                                      bull Detailed engineering design bull Site Management Plan (final)bull Asset maintenance plan (final)bull Handover arrangements (if public)

                                                      54

                                                      STORM ndash Online toolbull Print out of STORM reportbull Make sure meets 100 or

                                                      morebull Make sure report inputs and

                                                      results match plan

                                                      Modelling - SWQ

                                                      MUSIC ndash Proprietary softwarebull Provide a copy of the model filebull Print out the modelling resultsbull Provide summary of your model

                                                      inputs for each treatment train (iecatchment size impervious treatment area etc)

                                                      bull Provide a print out of the model schematic

                                                      Bonus points bull Provide details of model

                                                      parametersbull Provide results of MUSIC auditor

                                                      run (if using Melbourne Water MUSIC Guidelines)

                                                      56

                                                      Assessment against standards

                                                      bull Say what you have done (or will do) to meet each standardbull Donrsquot forget (if WSUD) details of maintenance and asset

                                                      ownershipbull Where applicable be explicit why yoursquove chosen (or not chosen) to

                                                      respond the way you have Egbull Opportunitiesbull Site constraintsbull Practicaloperational issues bull Brief dot point summary of options analysis if complex

                                                      bull Make sure if it doesnrsquot meet the standard it meets the objectivebull Make sure shown on plan and consistent with modelling and rest of

                                                      documentation

                                                      57

                                                      Resources

                                                      Local stormwaterWSUD policiesBaysideKingstonCaseyMonashMelbourneYarraMoonee ValleyPort PhilipStonningtonHumeCampaspeBass Coast

                                                      Local ESD (including IWM) policies Greater BendigoGreater DandenongHobsons BayWhittleseaWyndhamWhitehorseManninghamMorelandDarebinBanyuleKnoxBrimbank

                                                      Council planning resources

                                                      Application resources ndashexamplesDELWP Practice Note ndashformal guide to the new controlsMoreland ndash application checklists and example plans for a variety of residential developmentsPort Philip ndash compliance guidelines checklist and examplesMoonee Valley ndash checklists and example plans including site management plans Greater Bendigo ndash WSUD kitBayside ndash application guidelines and example plans

                                                      59

                                                      Technical guidelines (modelling design construction)

                                                      Melbourne Water

                                                      STORM calculatorMUSIC auditor - lsquohow torsquo video here

                                                      Melbourne Water technical guidelines page- WSUD asset life cycle costings and model maintenance guidelines- MUSIC guidelines- Stormwater harvesting guidelines- WSUD life cycle costings and

                                                      maintenance guidelines- Design and construction guidelines

                                                      for variety of assetshttpswwwmelbournewatercomauplanning-and-buildingdeveloper-guides-and-resourcesguidelines-drawings-and-checklistsguidelines

                                                      Council

                                                      South-Eastern Growth Council WSUD guidelines ndash note that some individual Councils have their own addendumsMelbournePort PhilipNorth-West Growth Council WSUD guidelines - note that some individual Councils have their own addendumsGreater BendigoMilduraBallaratBaw BawWyndhamMoreland ndash tree pits and raingardens

                                                      60

                                                      IWM

                                                      Example Council IWM strategiesMelbourneCaseyMonashKingston

                                                      Resilient Melbourne ndash IWM information lsquohubrsquoClearwater ndash capacity building and case studiesMelbourne Water ndash funding opportunities for IWM projects

                                                      Stormwater offset schemes

                                                      KingstonGreater GeelongMelbourne Water ndash non scheme contributions

                                                      Site management

                                                      EPA guidelines- management of erosion and sediment

                                                      Next steps and other stormwater initiatives

                                                      Emma Stewart DELWP

                                                      62

                                                      Next steps

                                                      bull Trainingbull The EPArsquos BPEM Reviewbull Offsets policybull Review of STORM bull Building controls

                                                      63

                                                      State Stormwater policies

                                                      64

                                                      Thank you

                                                      • Slide Number 1
                                                      • Slide Number 2
                                                      • History of WSUD
                                                      • History of WSUD
                                                      • Transformational change in urban water
                                                      • Inconsistencies and inequities in our approach to stormwater management
                                                      • Slide Number 8
                                                      • Terms of Reference
                                                      • Improving Stormwater Management Advisory Committee
                                                      • Wide consultation
                                                      • Stakeholder feedback
                                                      • Stakeholder feedback
                                                      • Committee submitted its report in September 2018
                                                      • Committee Recomendations
                                                      • Planning reforms
                                                      • Future policy directions
                                                      • Supporting actions
                                                      • Slide Number 19
                                                      • Government response (to date)
                                                      • Longer term recommendations
                                                      • State-based planning requirements (lsquobeforersquo)
                                                      • State-based planning requirements (lsquoafterrsquo)
                                                      • Development types (volume)
                                                      • Slide Number 25
                                                      • Amendment VC154
                                                      • Whatrsquos in
                                                      • Slide Number 28
                                                      • Key elements of clauses
                                                      • Clause 5318 ndash subdivision
                                                      • Clause 5318 ndash Buildings and works
                                                      • Townhouses - Standard B9
                                                      • Slide Number 33
                                                      • Slide Number 34
                                                      • Slide Number 35
                                                      • Slide Number 36
                                                      • Slide Number 37
                                                      • Buildings and works - Site management standard
                                                      • Site management
                                                      • Planning Advisory Note No 75
                                                      • Slide Number 41
                                                      • Slide Number 42
                                                      • Slide Number 43
                                                      • Slide Number 44
                                                      • Slide Number 45
                                                      • Slide Number 46
                                                      • Slide Number 47
                                                      • Slide Number 48
                                                      • Slide Number 49
                                                      • Slide Number 50
                                                      • Slide Number 51
                                                      • Slide Number 52
                                                      • Slide Number 53
                                                      • Slide Number 54
                                                      • Slide Number 55
                                                      • Slide Number 56
                                                      • Slide Number 57
                                                      • Slide Number 58
                                                      • Slide Number 59
                                                      • Slide Number 60
                                                      • Slide Number 61
                                                      • Next steps
                                                      • State Stormwater policies
                                                      • Slide Number 64

                                                        29

                                                        Key elements of clauses

                                                        Industrial commercial applications (Clause 5318)tobull subdivide land bull construct a building bull construct or carry out works

                                                        Stormwater management objectives + standard (W1)

                                                        Stormwater management objectives + standard (W2)+ Site management objectives + standard (W3)

                                                        Decision guidelines

                                                        Same for Clause 5503 (townhouses)

                                                        30

                                                        Clause 5318 ndash subdivision

                                                        Stormwater management standard W1 The stormwater management system should be bull Designed and managed in accordance with the requirements and

                                                        to the satisfaction of the relevant drainage authoritybull Designed and managed in accordance with the requirements and

                                                        to the satisfaction of the water authority where reuse of stormwater is proposed

                                                        bull Designed to meet the current best practice performance objectives for stormwater quality as contained in the BPEM

                                                        bull Designed to ensure that flows downstream of the subdivision site are restricted to pre-development levels unless increased flows are approved by the relevant drainage authority and there are no detrimental downstream impacts

                                                        bull Designed to contribute to cooling improving local habitat and providing attractive and enjoyable spaces

                                                        31

                                                        Clause 5318 ndash Buildings and works

                                                        Standard W2The stormwater management system should be designed to

                                                        bull Meet the current best practice performance objectives for stormwater quality as contained in the BPEM

                                                        bull Contribute to cooling improving local habitat and providing attractive and enjoyable spaces

                                                        bull Minimise the impact of chemical pollutants and other toxicants including by but not limited to bunding and covering of roofing of storage loading and work areas

                                                        32

                                                        Townhouses - Standard B9

                                                        Clause 5503 ndash Permeability and stormwater management objectives and standard B9

                                                        Objectivesbull Similar to 5318 (including the cooling liveability

                                                        objective)bull gt20 perviousness objective (unchanged)

                                                        Standardbull NEW - cooling liveability objectivebull NEW ndash requirement to meet BPEM

                                                        What does this all mean

                                                        34

                                                        Clause 5318 - Whatrsquos in

                                                        35

                                                        Urban cooling Reduce heat radiation from buildings and hard surfaces throughbull Shade trees in car parks or over driveways bull More open space and treesbull Green roofsbull Green walls

                                                        36

                                                        Optionsbull Passive irrigationbull Integrate assets into

                                                        communal open spacebull Tree pits and permeable

                                                        paving (driveways and carpark)

                                                        bull Stormwater harvesting (major developments only)

                                                        Infiltration habitat amenity

                                                        37

                                                        Control harmful chemicals

                                                        Optionsbull Careful layoutbull Consider alternative less harmful substancesbull Roofed designated storage areabull Internal drainage design to sewer or a treatment devicebull Bunding

                                                        38

                                                        Standard W3Standard W3 requires that application describe how the site will be managed prior to and during the construction period The application should set out requirements for managingbull Erosion and sedimentbull Stormwaterbull Litter concrete and other construction wastesbull Chemical contamination

                                                        Buildings and works - Site management standard

                                                        39

                                                        Site management

                                                        40

                                                        Planning Advisory Note No 75

                                                        Implications for industry

                                                        Kate MatthewsStormwater Victoria

                                                        1 Development proponents- Developers- Consultants (engineers stormwater specialists and planners)- Council (when developing public land lt$1 million)

                                                        2 Development assessors- Council statutory planners- Council internal referrals (engineering assets ESD stormwater officers)

                                                        3 Strategy- Council strategic planners

                                                        4 Melbourne Water

                                                        Whorsquos affected

                                                        43

                                                        What are the implications

                                                        bull BPEM - Itrsquos not just subdivisions any more

                                                        bull Cost ndash offset or assetbull Early planning and integration ndash more

                                                        work up frontbull Not just engineeringbull Varying Council skills and experience

                                                        Development Proponents

                                                        44

                                                        If already have a local policy for WSUDESD no real change

                                                        If notbull Workload and resourcingbull Increased detail and technical

                                                        contentbull Administrative arrangements ndash

                                                        referrals permit conditions ndashmake sure you make 60 stat days

                                                        bull Applicant pressure ndash what do you want

                                                        bull Assets

                                                        Development Assessors

                                                        45

                                                        bull Structure plans and rezoning ndashopportunities for localregional approach

                                                        bull IWM and Stormwater Management Plans ndash opportunities for these to be implemented through the controls spatial opportunities

                                                        bull Opportunities for development of Council offset strategies

                                                        Strategy

                                                        Offsets

                                                        bull Developer enters into an agreement with relevant drainage authority to financially contribute to off-site stormwatermanagement in lieu of providing on-site treatment

                                                        bull Already available for residential subdivisions in Melbourne (Clause 56) through MWCs Stormwater Quality Offset scheme

                                                        What are stormwater quality offsets

                                                        X Not drainage contributions (MWC drainage scheme)

                                                        X Not development contributions (DCPICP)

                                                        47

                                                        When to use

                                                        bull Not in MW DSS or growth area where therersquos an existing framework for funding SW treatment

                                                        bull Onsite treatment not practical or desirable

                                                        bull To fund planned localregional stormwater treatment works in that catchment via an existing offset scheme

                                                        bull Council and developer both agree to it

                                                        48

                                                        OffsetsExample ndash Kingston Offset Scheme

                                                        Asset ownership and maintenance

                                                        bull Whorsquos going to own itbull Whorsquos going to maintain itbull How do you maintain itbull How much will it cost

                                                        bull Where is itbull Is maintenance burden

                                                        practical for likely future owners

                                                        bull Whorsquos going to monitor compliance and how

                                                        The detail is in the permit conditions

                                                        Application requirements

                                                        ldquoAn application must be accompanied by details of the proposed stormwater management system including drainage works and retention detention and discharges of stormwater to the drainage systemrdquo ndash Clause 5318

                                                        What does the planning scheme require

                                                        But alsohellipNeed to provide sufficient information to Council which demonstrates that you comply and how you comply with all the other standards ndash eg urban coolinghabitatetc BPEM site management pollutant control infiltration (as relevant to development type

                                                        51

                                                        1 PlansWhat are you doing where is it going and does it fit

                                                        2 ModellingDo you (or can you) meet BPEM requirements

                                                        3 Written response to standardsHow does your proposal comply with the requirements

                                                        52

                                                        Application

                                                        bull Site plan ndash show all assetsWSUD treatments and any IWM features on the site layout plan with everything else

                                                        bull Landscape plan ndash if planting design passive irrigation etc forms part of response to requirements show

                                                        bull Site management plan (depending on Council)

                                                        bull Separate WSUDIWM plan showing all features on a stripped back background

                                                        bull Concept WSUD asset design ndash larger assets only (wetlands bioretention basins sed basin etc) ndash sufficient design detail to confirm spatial requirements

                                                        PlansPermit conditions

                                                        bull Detailed engineering design bull Site Management Plan (final)bull Asset maintenance plan (final)bull Handover arrangements (if public)

                                                        54

                                                        STORM ndash Online toolbull Print out of STORM reportbull Make sure meets 100 or

                                                        morebull Make sure report inputs and

                                                        results match plan

                                                        Modelling - SWQ

                                                        MUSIC ndash Proprietary softwarebull Provide a copy of the model filebull Print out the modelling resultsbull Provide summary of your model

                                                        inputs for each treatment train (iecatchment size impervious treatment area etc)

                                                        bull Provide a print out of the model schematic

                                                        Bonus points bull Provide details of model

                                                        parametersbull Provide results of MUSIC auditor

                                                        run (if using Melbourne Water MUSIC Guidelines)

                                                        56

                                                        Assessment against standards

                                                        bull Say what you have done (or will do) to meet each standardbull Donrsquot forget (if WSUD) details of maintenance and asset

                                                        ownershipbull Where applicable be explicit why yoursquove chosen (or not chosen) to

                                                        respond the way you have Egbull Opportunitiesbull Site constraintsbull Practicaloperational issues bull Brief dot point summary of options analysis if complex

                                                        bull Make sure if it doesnrsquot meet the standard it meets the objectivebull Make sure shown on plan and consistent with modelling and rest of

                                                        documentation

                                                        57

                                                        Resources

                                                        Local stormwaterWSUD policiesBaysideKingstonCaseyMonashMelbourneYarraMoonee ValleyPort PhilipStonningtonHumeCampaspeBass Coast

                                                        Local ESD (including IWM) policies Greater BendigoGreater DandenongHobsons BayWhittleseaWyndhamWhitehorseManninghamMorelandDarebinBanyuleKnoxBrimbank

                                                        Council planning resources

                                                        Application resources ndashexamplesDELWP Practice Note ndashformal guide to the new controlsMoreland ndash application checklists and example plans for a variety of residential developmentsPort Philip ndash compliance guidelines checklist and examplesMoonee Valley ndash checklists and example plans including site management plans Greater Bendigo ndash WSUD kitBayside ndash application guidelines and example plans

                                                        59

                                                        Technical guidelines (modelling design construction)

                                                        Melbourne Water

                                                        STORM calculatorMUSIC auditor - lsquohow torsquo video here

                                                        Melbourne Water technical guidelines page- WSUD asset life cycle costings and model maintenance guidelines- MUSIC guidelines- Stormwater harvesting guidelines- WSUD life cycle costings and

                                                        maintenance guidelines- Design and construction guidelines

                                                        for variety of assetshttpswwwmelbournewatercomauplanning-and-buildingdeveloper-guides-and-resourcesguidelines-drawings-and-checklistsguidelines

                                                        Council

                                                        South-Eastern Growth Council WSUD guidelines ndash note that some individual Councils have their own addendumsMelbournePort PhilipNorth-West Growth Council WSUD guidelines - note that some individual Councils have their own addendumsGreater BendigoMilduraBallaratBaw BawWyndhamMoreland ndash tree pits and raingardens

                                                        60

                                                        IWM

                                                        Example Council IWM strategiesMelbourneCaseyMonashKingston

                                                        Resilient Melbourne ndash IWM information lsquohubrsquoClearwater ndash capacity building and case studiesMelbourne Water ndash funding opportunities for IWM projects

                                                        Stormwater offset schemes

                                                        KingstonGreater GeelongMelbourne Water ndash non scheme contributions

                                                        Site management

                                                        EPA guidelines- management of erosion and sediment

                                                        Next steps and other stormwater initiatives

                                                        Emma Stewart DELWP

                                                        62

                                                        Next steps

                                                        bull Trainingbull The EPArsquos BPEM Reviewbull Offsets policybull Review of STORM bull Building controls

                                                        63

                                                        State Stormwater policies

                                                        64

                                                        Thank you

                                                        • Slide Number 1
                                                        • Slide Number 2
                                                        • History of WSUD
                                                        • History of WSUD
                                                        • Transformational change in urban water
                                                        • Inconsistencies and inequities in our approach to stormwater management
                                                        • Slide Number 8
                                                        • Terms of Reference
                                                        • Improving Stormwater Management Advisory Committee
                                                        • Wide consultation
                                                        • Stakeholder feedback
                                                        • Stakeholder feedback
                                                        • Committee submitted its report in September 2018
                                                        • Committee Recomendations
                                                        • Planning reforms
                                                        • Future policy directions
                                                        • Supporting actions
                                                        • Slide Number 19
                                                        • Government response (to date)
                                                        • Longer term recommendations
                                                        • State-based planning requirements (lsquobeforersquo)
                                                        • State-based planning requirements (lsquoafterrsquo)
                                                        • Development types (volume)
                                                        • Slide Number 25
                                                        • Amendment VC154
                                                        • Whatrsquos in
                                                        • Slide Number 28
                                                        • Key elements of clauses
                                                        • Clause 5318 ndash subdivision
                                                        • Clause 5318 ndash Buildings and works
                                                        • Townhouses - Standard B9
                                                        • Slide Number 33
                                                        • Slide Number 34
                                                        • Slide Number 35
                                                        • Slide Number 36
                                                        • Slide Number 37
                                                        • Buildings and works - Site management standard
                                                        • Site management
                                                        • Planning Advisory Note No 75
                                                        • Slide Number 41
                                                        • Slide Number 42
                                                        • Slide Number 43
                                                        • Slide Number 44
                                                        • Slide Number 45
                                                        • Slide Number 46
                                                        • Slide Number 47
                                                        • Slide Number 48
                                                        • Slide Number 49
                                                        • Slide Number 50
                                                        • Slide Number 51
                                                        • Slide Number 52
                                                        • Slide Number 53
                                                        • Slide Number 54
                                                        • Slide Number 55
                                                        • Slide Number 56
                                                        • Slide Number 57
                                                        • Slide Number 58
                                                        • Slide Number 59
                                                        • Slide Number 60
                                                        • Slide Number 61
                                                        • Next steps
                                                        • State Stormwater policies
                                                        • Slide Number 64

                                                          30

                                                          Clause 5318 ndash subdivision

                                                          Stormwater management standard W1 The stormwater management system should be bull Designed and managed in accordance with the requirements and

                                                          to the satisfaction of the relevant drainage authoritybull Designed and managed in accordance with the requirements and

                                                          to the satisfaction of the water authority where reuse of stormwater is proposed

                                                          bull Designed to meet the current best practice performance objectives for stormwater quality as contained in the BPEM

                                                          bull Designed to ensure that flows downstream of the subdivision site are restricted to pre-development levels unless increased flows are approved by the relevant drainage authority and there are no detrimental downstream impacts

                                                          bull Designed to contribute to cooling improving local habitat and providing attractive and enjoyable spaces

                                                          31

                                                          Clause 5318 ndash Buildings and works

                                                          Standard W2The stormwater management system should be designed to

                                                          bull Meet the current best practice performance objectives for stormwater quality as contained in the BPEM

                                                          bull Contribute to cooling improving local habitat and providing attractive and enjoyable spaces

                                                          bull Minimise the impact of chemical pollutants and other toxicants including by but not limited to bunding and covering of roofing of storage loading and work areas

                                                          32

                                                          Townhouses - Standard B9

                                                          Clause 5503 ndash Permeability and stormwater management objectives and standard B9

                                                          Objectivesbull Similar to 5318 (including the cooling liveability

                                                          objective)bull gt20 perviousness objective (unchanged)

                                                          Standardbull NEW - cooling liveability objectivebull NEW ndash requirement to meet BPEM

                                                          What does this all mean

                                                          34

                                                          Clause 5318 - Whatrsquos in

                                                          35

                                                          Urban cooling Reduce heat radiation from buildings and hard surfaces throughbull Shade trees in car parks or over driveways bull More open space and treesbull Green roofsbull Green walls

                                                          36

                                                          Optionsbull Passive irrigationbull Integrate assets into

                                                          communal open spacebull Tree pits and permeable

                                                          paving (driveways and carpark)

                                                          bull Stormwater harvesting (major developments only)

                                                          Infiltration habitat amenity

                                                          37

                                                          Control harmful chemicals

                                                          Optionsbull Careful layoutbull Consider alternative less harmful substancesbull Roofed designated storage areabull Internal drainage design to sewer or a treatment devicebull Bunding

                                                          38

                                                          Standard W3Standard W3 requires that application describe how the site will be managed prior to and during the construction period The application should set out requirements for managingbull Erosion and sedimentbull Stormwaterbull Litter concrete and other construction wastesbull Chemical contamination

                                                          Buildings and works - Site management standard

                                                          39

                                                          Site management

                                                          40

                                                          Planning Advisory Note No 75

                                                          Implications for industry

                                                          Kate MatthewsStormwater Victoria

                                                          1 Development proponents- Developers- Consultants (engineers stormwater specialists and planners)- Council (when developing public land lt$1 million)

                                                          2 Development assessors- Council statutory planners- Council internal referrals (engineering assets ESD stormwater officers)

                                                          3 Strategy- Council strategic planners

                                                          4 Melbourne Water

                                                          Whorsquos affected

                                                          43

                                                          What are the implications

                                                          bull BPEM - Itrsquos not just subdivisions any more

                                                          bull Cost ndash offset or assetbull Early planning and integration ndash more

                                                          work up frontbull Not just engineeringbull Varying Council skills and experience

                                                          Development Proponents

                                                          44

                                                          If already have a local policy for WSUDESD no real change

                                                          If notbull Workload and resourcingbull Increased detail and technical

                                                          contentbull Administrative arrangements ndash

                                                          referrals permit conditions ndashmake sure you make 60 stat days

                                                          bull Applicant pressure ndash what do you want

                                                          bull Assets

                                                          Development Assessors

                                                          45

                                                          bull Structure plans and rezoning ndashopportunities for localregional approach

                                                          bull IWM and Stormwater Management Plans ndash opportunities for these to be implemented through the controls spatial opportunities

                                                          bull Opportunities for development of Council offset strategies

                                                          Strategy

                                                          Offsets

                                                          bull Developer enters into an agreement with relevant drainage authority to financially contribute to off-site stormwatermanagement in lieu of providing on-site treatment

                                                          bull Already available for residential subdivisions in Melbourne (Clause 56) through MWCs Stormwater Quality Offset scheme

                                                          What are stormwater quality offsets

                                                          X Not drainage contributions (MWC drainage scheme)

                                                          X Not development contributions (DCPICP)

                                                          47

                                                          When to use

                                                          bull Not in MW DSS or growth area where therersquos an existing framework for funding SW treatment

                                                          bull Onsite treatment not practical or desirable

                                                          bull To fund planned localregional stormwater treatment works in that catchment via an existing offset scheme

                                                          bull Council and developer both agree to it

                                                          48

                                                          OffsetsExample ndash Kingston Offset Scheme

                                                          Asset ownership and maintenance

                                                          bull Whorsquos going to own itbull Whorsquos going to maintain itbull How do you maintain itbull How much will it cost

                                                          bull Where is itbull Is maintenance burden

                                                          practical for likely future owners

                                                          bull Whorsquos going to monitor compliance and how

                                                          The detail is in the permit conditions

                                                          Application requirements

                                                          ldquoAn application must be accompanied by details of the proposed stormwater management system including drainage works and retention detention and discharges of stormwater to the drainage systemrdquo ndash Clause 5318

                                                          What does the planning scheme require

                                                          But alsohellipNeed to provide sufficient information to Council which demonstrates that you comply and how you comply with all the other standards ndash eg urban coolinghabitatetc BPEM site management pollutant control infiltration (as relevant to development type

                                                          51

                                                          1 PlansWhat are you doing where is it going and does it fit

                                                          2 ModellingDo you (or can you) meet BPEM requirements

                                                          3 Written response to standardsHow does your proposal comply with the requirements

                                                          52

                                                          Application

                                                          bull Site plan ndash show all assetsWSUD treatments and any IWM features on the site layout plan with everything else

                                                          bull Landscape plan ndash if planting design passive irrigation etc forms part of response to requirements show

                                                          bull Site management plan (depending on Council)

                                                          bull Separate WSUDIWM plan showing all features on a stripped back background

                                                          bull Concept WSUD asset design ndash larger assets only (wetlands bioretention basins sed basin etc) ndash sufficient design detail to confirm spatial requirements

                                                          PlansPermit conditions

                                                          bull Detailed engineering design bull Site Management Plan (final)bull Asset maintenance plan (final)bull Handover arrangements (if public)

                                                          54

                                                          STORM ndash Online toolbull Print out of STORM reportbull Make sure meets 100 or

                                                          morebull Make sure report inputs and

                                                          results match plan

                                                          Modelling - SWQ

                                                          MUSIC ndash Proprietary softwarebull Provide a copy of the model filebull Print out the modelling resultsbull Provide summary of your model

                                                          inputs for each treatment train (iecatchment size impervious treatment area etc)

                                                          bull Provide a print out of the model schematic

                                                          Bonus points bull Provide details of model

                                                          parametersbull Provide results of MUSIC auditor

                                                          run (if using Melbourne Water MUSIC Guidelines)

                                                          56

                                                          Assessment against standards

                                                          bull Say what you have done (or will do) to meet each standardbull Donrsquot forget (if WSUD) details of maintenance and asset

                                                          ownershipbull Where applicable be explicit why yoursquove chosen (or not chosen) to

                                                          respond the way you have Egbull Opportunitiesbull Site constraintsbull Practicaloperational issues bull Brief dot point summary of options analysis if complex

                                                          bull Make sure if it doesnrsquot meet the standard it meets the objectivebull Make sure shown on plan and consistent with modelling and rest of

                                                          documentation

                                                          57

                                                          Resources

                                                          Local stormwaterWSUD policiesBaysideKingstonCaseyMonashMelbourneYarraMoonee ValleyPort PhilipStonningtonHumeCampaspeBass Coast

                                                          Local ESD (including IWM) policies Greater BendigoGreater DandenongHobsons BayWhittleseaWyndhamWhitehorseManninghamMorelandDarebinBanyuleKnoxBrimbank

                                                          Council planning resources

                                                          Application resources ndashexamplesDELWP Practice Note ndashformal guide to the new controlsMoreland ndash application checklists and example plans for a variety of residential developmentsPort Philip ndash compliance guidelines checklist and examplesMoonee Valley ndash checklists and example plans including site management plans Greater Bendigo ndash WSUD kitBayside ndash application guidelines and example plans

                                                          59

                                                          Technical guidelines (modelling design construction)

                                                          Melbourne Water

                                                          STORM calculatorMUSIC auditor - lsquohow torsquo video here

                                                          Melbourne Water technical guidelines page- WSUD asset life cycle costings and model maintenance guidelines- MUSIC guidelines- Stormwater harvesting guidelines- WSUD life cycle costings and

                                                          maintenance guidelines- Design and construction guidelines

                                                          for variety of assetshttpswwwmelbournewatercomauplanning-and-buildingdeveloper-guides-and-resourcesguidelines-drawings-and-checklistsguidelines

                                                          Council

                                                          South-Eastern Growth Council WSUD guidelines ndash note that some individual Councils have their own addendumsMelbournePort PhilipNorth-West Growth Council WSUD guidelines - note that some individual Councils have their own addendumsGreater BendigoMilduraBallaratBaw BawWyndhamMoreland ndash tree pits and raingardens

                                                          60

                                                          IWM

                                                          Example Council IWM strategiesMelbourneCaseyMonashKingston

                                                          Resilient Melbourne ndash IWM information lsquohubrsquoClearwater ndash capacity building and case studiesMelbourne Water ndash funding opportunities for IWM projects

                                                          Stormwater offset schemes

                                                          KingstonGreater GeelongMelbourne Water ndash non scheme contributions

                                                          Site management

                                                          EPA guidelines- management of erosion and sediment

                                                          Next steps and other stormwater initiatives

                                                          Emma Stewart DELWP

                                                          62

                                                          Next steps

                                                          bull Trainingbull The EPArsquos BPEM Reviewbull Offsets policybull Review of STORM bull Building controls

                                                          63

                                                          State Stormwater policies

                                                          64

                                                          Thank you

                                                          • Slide Number 1
                                                          • Slide Number 2
                                                          • History of WSUD
                                                          • History of WSUD
                                                          • Transformational change in urban water
                                                          • Inconsistencies and inequities in our approach to stormwater management
                                                          • Slide Number 8
                                                          • Terms of Reference
                                                          • Improving Stormwater Management Advisory Committee
                                                          • Wide consultation
                                                          • Stakeholder feedback
                                                          • Stakeholder feedback
                                                          • Committee submitted its report in September 2018
                                                          • Committee Recomendations
                                                          • Planning reforms
                                                          • Future policy directions
                                                          • Supporting actions
                                                          • Slide Number 19
                                                          • Government response (to date)
                                                          • Longer term recommendations
                                                          • State-based planning requirements (lsquobeforersquo)
                                                          • State-based planning requirements (lsquoafterrsquo)
                                                          • Development types (volume)
                                                          • Slide Number 25
                                                          • Amendment VC154
                                                          • Whatrsquos in
                                                          • Slide Number 28
                                                          • Key elements of clauses
                                                          • Clause 5318 ndash subdivision
                                                          • Clause 5318 ndash Buildings and works
                                                          • Townhouses - Standard B9
                                                          • Slide Number 33
                                                          • Slide Number 34
                                                          • Slide Number 35
                                                          • Slide Number 36
                                                          • Slide Number 37
                                                          • Buildings and works - Site management standard
                                                          • Site management
                                                          • Planning Advisory Note No 75
                                                          • Slide Number 41
                                                          • Slide Number 42
                                                          • Slide Number 43
                                                          • Slide Number 44
                                                          • Slide Number 45
                                                          • Slide Number 46
                                                          • Slide Number 47
                                                          • Slide Number 48
                                                          • Slide Number 49
                                                          • Slide Number 50
                                                          • Slide Number 51
                                                          • Slide Number 52
                                                          • Slide Number 53
                                                          • Slide Number 54
                                                          • Slide Number 55
                                                          • Slide Number 56
                                                          • Slide Number 57
                                                          • Slide Number 58
                                                          • Slide Number 59
                                                          • Slide Number 60
                                                          • Slide Number 61
                                                          • Next steps
                                                          • State Stormwater policies
                                                          • Slide Number 64

                                                            31

                                                            Clause 5318 ndash Buildings and works

                                                            Standard W2The stormwater management system should be designed to

                                                            bull Meet the current best practice performance objectives for stormwater quality as contained in the BPEM

                                                            bull Contribute to cooling improving local habitat and providing attractive and enjoyable spaces

                                                            bull Minimise the impact of chemical pollutants and other toxicants including by but not limited to bunding and covering of roofing of storage loading and work areas

                                                            32

                                                            Townhouses - Standard B9

                                                            Clause 5503 ndash Permeability and stormwater management objectives and standard B9

                                                            Objectivesbull Similar to 5318 (including the cooling liveability

                                                            objective)bull gt20 perviousness objective (unchanged)

                                                            Standardbull NEW - cooling liveability objectivebull NEW ndash requirement to meet BPEM

                                                            What does this all mean

                                                            34

                                                            Clause 5318 - Whatrsquos in

                                                            35

                                                            Urban cooling Reduce heat radiation from buildings and hard surfaces throughbull Shade trees in car parks or over driveways bull More open space and treesbull Green roofsbull Green walls

                                                            36

                                                            Optionsbull Passive irrigationbull Integrate assets into

                                                            communal open spacebull Tree pits and permeable

                                                            paving (driveways and carpark)

                                                            bull Stormwater harvesting (major developments only)

                                                            Infiltration habitat amenity

                                                            37

                                                            Control harmful chemicals

                                                            Optionsbull Careful layoutbull Consider alternative less harmful substancesbull Roofed designated storage areabull Internal drainage design to sewer or a treatment devicebull Bunding

                                                            38

                                                            Standard W3Standard W3 requires that application describe how the site will be managed prior to and during the construction period The application should set out requirements for managingbull Erosion and sedimentbull Stormwaterbull Litter concrete and other construction wastesbull Chemical contamination

                                                            Buildings and works - Site management standard

                                                            39

                                                            Site management

                                                            40

                                                            Planning Advisory Note No 75

                                                            Implications for industry

                                                            Kate MatthewsStormwater Victoria

                                                            1 Development proponents- Developers- Consultants (engineers stormwater specialists and planners)- Council (when developing public land lt$1 million)

                                                            2 Development assessors- Council statutory planners- Council internal referrals (engineering assets ESD stormwater officers)

                                                            3 Strategy- Council strategic planners

                                                            4 Melbourne Water

                                                            Whorsquos affected

                                                            43

                                                            What are the implications

                                                            bull BPEM - Itrsquos not just subdivisions any more

                                                            bull Cost ndash offset or assetbull Early planning and integration ndash more

                                                            work up frontbull Not just engineeringbull Varying Council skills and experience

                                                            Development Proponents

                                                            44

                                                            If already have a local policy for WSUDESD no real change

                                                            If notbull Workload and resourcingbull Increased detail and technical

                                                            contentbull Administrative arrangements ndash

                                                            referrals permit conditions ndashmake sure you make 60 stat days

                                                            bull Applicant pressure ndash what do you want

                                                            bull Assets

                                                            Development Assessors

                                                            45

                                                            bull Structure plans and rezoning ndashopportunities for localregional approach

                                                            bull IWM and Stormwater Management Plans ndash opportunities for these to be implemented through the controls spatial opportunities

                                                            bull Opportunities for development of Council offset strategies

                                                            Strategy

                                                            Offsets

                                                            bull Developer enters into an agreement with relevant drainage authority to financially contribute to off-site stormwatermanagement in lieu of providing on-site treatment

                                                            bull Already available for residential subdivisions in Melbourne (Clause 56) through MWCs Stormwater Quality Offset scheme

                                                            What are stormwater quality offsets

                                                            X Not drainage contributions (MWC drainage scheme)

                                                            X Not development contributions (DCPICP)

                                                            47

                                                            When to use

                                                            bull Not in MW DSS or growth area where therersquos an existing framework for funding SW treatment

                                                            bull Onsite treatment not practical or desirable

                                                            bull To fund planned localregional stormwater treatment works in that catchment via an existing offset scheme

                                                            bull Council and developer both agree to it

                                                            48

                                                            OffsetsExample ndash Kingston Offset Scheme

                                                            Asset ownership and maintenance

                                                            bull Whorsquos going to own itbull Whorsquos going to maintain itbull How do you maintain itbull How much will it cost

                                                            bull Where is itbull Is maintenance burden

                                                            practical for likely future owners

                                                            bull Whorsquos going to monitor compliance and how

                                                            The detail is in the permit conditions

                                                            Application requirements

                                                            ldquoAn application must be accompanied by details of the proposed stormwater management system including drainage works and retention detention and discharges of stormwater to the drainage systemrdquo ndash Clause 5318

                                                            What does the planning scheme require

                                                            But alsohellipNeed to provide sufficient information to Council which demonstrates that you comply and how you comply with all the other standards ndash eg urban coolinghabitatetc BPEM site management pollutant control infiltration (as relevant to development type

                                                            51

                                                            1 PlansWhat are you doing where is it going and does it fit

                                                            2 ModellingDo you (or can you) meet BPEM requirements

                                                            3 Written response to standardsHow does your proposal comply with the requirements

                                                            52

                                                            Application

                                                            bull Site plan ndash show all assetsWSUD treatments and any IWM features on the site layout plan with everything else

                                                            bull Landscape plan ndash if planting design passive irrigation etc forms part of response to requirements show

                                                            bull Site management plan (depending on Council)

                                                            bull Separate WSUDIWM plan showing all features on a stripped back background

                                                            bull Concept WSUD asset design ndash larger assets only (wetlands bioretention basins sed basin etc) ndash sufficient design detail to confirm spatial requirements

                                                            PlansPermit conditions

                                                            bull Detailed engineering design bull Site Management Plan (final)bull Asset maintenance plan (final)bull Handover arrangements (if public)

                                                            54

                                                            STORM ndash Online toolbull Print out of STORM reportbull Make sure meets 100 or

                                                            morebull Make sure report inputs and

                                                            results match plan

                                                            Modelling - SWQ

                                                            MUSIC ndash Proprietary softwarebull Provide a copy of the model filebull Print out the modelling resultsbull Provide summary of your model

                                                            inputs for each treatment train (iecatchment size impervious treatment area etc)

                                                            bull Provide a print out of the model schematic

                                                            Bonus points bull Provide details of model

                                                            parametersbull Provide results of MUSIC auditor

                                                            run (if using Melbourne Water MUSIC Guidelines)

                                                            56

                                                            Assessment against standards

                                                            bull Say what you have done (or will do) to meet each standardbull Donrsquot forget (if WSUD) details of maintenance and asset

                                                            ownershipbull Where applicable be explicit why yoursquove chosen (or not chosen) to

                                                            respond the way you have Egbull Opportunitiesbull Site constraintsbull Practicaloperational issues bull Brief dot point summary of options analysis if complex

                                                            bull Make sure if it doesnrsquot meet the standard it meets the objectivebull Make sure shown on plan and consistent with modelling and rest of

                                                            documentation

                                                            57

                                                            Resources

                                                            Local stormwaterWSUD policiesBaysideKingstonCaseyMonashMelbourneYarraMoonee ValleyPort PhilipStonningtonHumeCampaspeBass Coast

                                                            Local ESD (including IWM) policies Greater BendigoGreater DandenongHobsons BayWhittleseaWyndhamWhitehorseManninghamMorelandDarebinBanyuleKnoxBrimbank

                                                            Council planning resources

                                                            Application resources ndashexamplesDELWP Practice Note ndashformal guide to the new controlsMoreland ndash application checklists and example plans for a variety of residential developmentsPort Philip ndash compliance guidelines checklist and examplesMoonee Valley ndash checklists and example plans including site management plans Greater Bendigo ndash WSUD kitBayside ndash application guidelines and example plans

                                                            59

                                                            Technical guidelines (modelling design construction)

                                                            Melbourne Water

                                                            STORM calculatorMUSIC auditor - lsquohow torsquo video here

                                                            Melbourne Water technical guidelines page- WSUD asset life cycle costings and model maintenance guidelines- MUSIC guidelines- Stormwater harvesting guidelines- WSUD life cycle costings and

                                                            maintenance guidelines- Design and construction guidelines

                                                            for variety of assetshttpswwwmelbournewatercomauplanning-and-buildingdeveloper-guides-and-resourcesguidelines-drawings-and-checklistsguidelines

                                                            Council

                                                            South-Eastern Growth Council WSUD guidelines ndash note that some individual Councils have their own addendumsMelbournePort PhilipNorth-West Growth Council WSUD guidelines - note that some individual Councils have their own addendumsGreater BendigoMilduraBallaratBaw BawWyndhamMoreland ndash tree pits and raingardens

                                                            60

                                                            IWM

                                                            Example Council IWM strategiesMelbourneCaseyMonashKingston

                                                            Resilient Melbourne ndash IWM information lsquohubrsquoClearwater ndash capacity building and case studiesMelbourne Water ndash funding opportunities for IWM projects

                                                            Stormwater offset schemes

                                                            KingstonGreater GeelongMelbourne Water ndash non scheme contributions

                                                            Site management

                                                            EPA guidelines- management of erosion and sediment

                                                            Next steps and other stormwater initiatives

                                                            Emma Stewart DELWP

                                                            62

                                                            Next steps

                                                            bull Trainingbull The EPArsquos BPEM Reviewbull Offsets policybull Review of STORM bull Building controls

                                                            63

                                                            State Stormwater policies

                                                            64

                                                            Thank you

                                                            • Slide Number 1
                                                            • Slide Number 2
                                                            • History of WSUD
                                                            • History of WSUD
                                                            • Transformational change in urban water
                                                            • Inconsistencies and inequities in our approach to stormwater management
                                                            • Slide Number 8
                                                            • Terms of Reference
                                                            • Improving Stormwater Management Advisory Committee
                                                            • Wide consultation
                                                            • Stakeholder feedback
                                                            • Stakeholder feedback
                                                            • Committee submitted its report in September 2018
                                                            • Committee Recomendations
                                                            • Planning reforms
                                                            • Future policy directions
                                                            • Supporting actions
                                                            • Slide Number 19
                                                            • Government response (to date)
                                                            • Longer term recommendations
                                                            • State-based planning requirements (lsquobeforersquo)
                                                            • State-based planning requirements (lsquoafterrsquo)
                                                            • Development types (volume)
                                                            • Slide Number 25
                                                            • Amendment VC154
                                                            • Whatrsquos in
                                                            • Slide Number 28
                                                            • Key elements of clauses
                                                            • Clause 5318 ndash subdivision
                                                            • Clause 5318 ndash Buildings and works
                                                            • Townhouses - Standard B9
                                                            • Slide Number 33
                                                            • Slide Number 34
                                                            • Slide Number 35
                                                            • Slide Number 36
                                                            • Slide Number 37
                                                            • Buildings and works - Site management standard
                                                            • Site management
                                                            • Planning Advisory Note No 75
                                                            • Slide Number 41
                                                            • Slide Number 42
                                                            • Slide Number 43
                                                            • Slide Number 44
                                                            • Slide Number 45
                                                            • Slide Number 46
                                                            • Slide Number 47
                                                            • Slide Number 48
                                                            • Slide Number 49
                                                            • Slide Number 50
                                                            • Slide Number 51
                                                            • Slide Number 52
                                                            • Slide Number 53
                                                            • Slide Number 54
                                                            • Slide Number 55
                                                            • Slide Number 56
                                                            • Slide Number 57
                                                            • Slide Number 58
                                                            • Slide Number 59
                                                            • Slide Number 60
                                                            • Slide Number 61
                                                            • Next steps
                                                            • State Stormwater policies
                                                            • Slide Number 64

                                                              32

                                                              Townhouses - Standard B9

                                                              Clause 5503 ndash Permeability and stormwater management objectives and standard B9

                                                              Objectivesbull Similar to 5318 (including the cooling liveability

                                                              objective)bull gt20 perviousness objective (unchanged)

                                                              Standardbull NEW - cooling liveability objectivebull NEW ndash requirement to meet BPEM

                                                              What does this all mean

                                                              34

                                                              Clause 5318 - Whatrsquos in

                                                              35

                                                              Urban cooling Reduce heat radiation from buildings and hard surfaces throughbull Shade trees in car parks or over driveways bull More open space and treesbull Green roofsbull Green walls

                                                              36

                                                              Optionsbull Passive irrigationbull Integrate assets into

                                                              communal open spacebull Tree pits and permeable

                                                              paving (driveways and carpark)

                                                              bull Stormwater harvesting (major developments only)

                                                              Infiltration habitat amenity

                                                              37

                                                              Control harmful chemicals

                                                              Optionsbull Careful layoutbull Consider alternative less harmful substancesbull Roofed designated storage areabull Internal drainage design to sewer or a treatment devicebull Bunding

                                                              38

                                                              Standard W3Standard W3 requires that application describe how the site will be managed prior to and during the construction period The application should set out requirements for managingbull Erosion and sedimentbull Stormwaterbull Litter concrete and other construction wastesbull Chemical contamination

                                                              Buildings and works - Site management standard

                                                              39

                                                              Site management

                                                              40

                                                              Planning Advisory Note No 75

                                                              Implications for industry

                                                              Kate MatthewsStormwater Victoria

                                                              1 Development proponents- Developers- Consultants (engineers stormwater specialists and planners)- Council (when developing public land lt$1 million)

                                                              2 Development assessors- Council statutory planners- Council internal referrals (engineering assets ESD stormwater officers)

                                                              3 Strategy- Council strategic planners

                                                              4 Melbourne Water

                                                              Whorsquos affected

                                                              43

                                                              What are the implications

                                                              bull BPEM - Itrsquos not just subdivisions any more

                                                              bull Cost ndash offset or assetbull Early planning and integration ndash more

                                                              work up frontbull Not just engineeringbull Varying Council skills and experience

                                                              Development Proponents

                                                              44

                                                              If already have a local policy for WSUDESD no real change

                                                              If notbull Workload and resourcingbull Increased detail and technical

                                                              contentbull Administrative arrangements ndash

                                                              referrals permit conditions ndashmake sure you make 60 stat days

                                                              bull Applicant pressure ndash what do you want

                                                              bull Assets

                                                              Development Assessors

                                                              45

                                                              bull Structure plans and rezoning ndashopportunities for localregional approach

                                                              bull IWM and Stormwater Management Plans ndash opportunities for these to be implemented through the controls spatial opportunities

                                                              bull Opportunities for development of Council offset strategies

                                                              Strategy

                                                              Offsets

                                                              bull Developer enters into an agreement with relevant drainage authority to financially contribute to off-site stormwatermanagement in lieu of providing on-site treatment

                                                              bull Already available for residential subdivisions in Melbourne (Clause 56) through MWCs Stormwater Quality Offset scheme

                                                              What are stormwater quality offsets

                                                              X Not drainage contributions (MWC drainage scheme)

                                                              X Not development contributions (DCPICP)

                                                              47

                                                              When to use

                                                              bull Not in MW DSS or growth area where therersquos an existing framework for funding SW treatment

                                                              bull Onsite treatment not practical or desirable

                                                              bull To fund planned localregional stormwater treatment works in that catchment via an existing offset scheme

                                                              bull Council and developer both agree to it

                                                              48

                                                              OffsetsExample ndash Kingston Offset Scheme

                                                              Asset ownership and maintenance

                                                              bull Whorsquos going to own itbull Whorsquos going to maintain itbull How do you maintain itbull How much will it cost

                                                              bull Where is itbull Is maintenance burden

                                                              practical for likely future owners

                                                              bull Whorsquos going to monitor compliance and how

                                                              The detail is in the permit conditions

                                                              Application requirements

                                                              ldquoAn application must be accompanied by details of the proposed stormwater management system including drainage works and retention detention and discharges of stormwater to the drainage systemrdquo ndash Clause 5318

                                                              What does the planning scheme require

                                                              But alsohellipNeed to provide sufficient information to Council which demonstrates that you comply and how you comply with all the other standards ndash eg urban coolinghabitatetc BPEM site management pollutant control infiltration (as relevant to development type

                                                              51

                                                              1 PlansWhat are you doing where is it going and does it fit

                                                              2 ModellingDo you (or can you) meet BPEM requirements

                                                              3 Written response to standardsHow does your proposal comply with the requirements

                                                              52

                                                              Application

                                                              bull Site plan ndash show all assetsWSUD treatments and any IWM features on the site layout plan with everything else

                                                              bull Landscape plan ndash if planting design passive irrigation etc forms part of response to requirements show

                                                              bull Site management plan (depending on Council)

                                                              bull Separate WSUDIWM plan showing all features on a stripped back background

                                                              bull Concept WSUD asset design ndash larger assets only (wetlands bioretention basins sed basin etc) ndash sufficient design detail to confirm spatial requirements

                                                              PlansPermit conditions

                                                              bull Detailed engineering design bull Site Management Plan (final)bull Asset maintenance plan (final)bull Handover arrangements (if public)

                                                              54

                                                              STORM ndash Online toolbull Print out of STORM reportbull Make sure meets 100 or

                                                              morebull Make sure report inputs and

                                                              results match plan

                                                              Modelling - SWQ

                                                              MUSIC ndash Proprietary softwarebull Provide a copy of the model filebull Print out the modelling resultsbull Provide summary of your model

                                                              inputs for each treatment train (iecatchment size impervious treatment area etc)

                                                              bull Provide a print out of the model schematic

                                                              Bonus points bull Provide details of model

                                                              parametersbull Provide results of MUSIC auditor

                                                              run (if using Melbourne Water MUSIC Guidelines)

                                                              56

                                                              Assessment against standards

                                                              bull Say what you have done (or will do) to meet each standardbull Donrsquot forget (if WSUD) details of maintenance and asset

                                                              ownershipbull Where applicable be explicit why yoursquove chosen (or not chosen) to

                                                              respond the way you have Egbull Opportunitiesbull Site constraintsbull Practicaloperational issues bull Brief dot point summary of options analysis if complex

                                                              bull Make sure if it doesnrsquot meet the standard it meets the objectivebull Make sure shown on plan and consistent with modelling and rest of

                                                              documentation

                                                              57

                                                              Resources

                                                              Local stormwaterWSUD policiesBaysideKingstonCaseyMonashMelbourneYarraMoonee ValleyPort PhilipStonningtonHumeCampaspeBass Coast

                                                              Local ESD (including IWM) policies Greater BendigoGreater DandenongHobsons BayWhittleseaWyndhamWhitehorseManninghamMorelandDarebinBanyuleKnoxBrimbank

                                                              Council planning resources

                                                              Application resources ndashexamplesDELWP Practice Note ndashformal guide to the new controlsMoreland ndash application checklists and example plans for a variety of residential developmentsPort Philip ndash compliance guidelines checklist and examplesMoonee Valley ndash checklists and example plans including site management plans Greater Bendigo ndash WSUD kitBayside ndash application guidelines and example plans

                                                              59

                                                              Technical guidelines (modelling design construction)

                                                              Melbourne Water

                                                              STORM calculatorMUSIC auditor - lsquohow torsquo video here

                                                              Melbourne Water technical guidelines page- WSUD asset life cycle costings and model maintenance guidelines- MUSIC guidelines- Stormwater harvesting guidelines- WSUD life cycle costings and

                                                              maintenance guidelines- Design and construction guidelines

                                                              for variety of assetshttpswwwmelbournewatercomauplanning-and-buildingdeveloper-guides-and-resourcesguidelines-drawings-and-checklistsguidelines

                                                              Council

                                                              South-Eastern Growth Council WSUD guidelines ndash note that some individual Councils have their own addendumsMelbournePort PhilipNorth-West Growth Council WSUD guidelines - note that some individual Councils have their own addendumsGreater BendigoMilduraBallaratBaw BawWyndhamMoreland ndash tree pits and raingardens

                                                              60

                                                              IWM

                                                              Example Council IWM strategiesMelbourneCaseyMonashKingston

                                                              Resilient Melbourne ndash IWM information lsquohubrsquoClearwater ndash capacity building and case studiesMelbourne Water ndash funding opportunities for IWM projects

                                                              Stormwater offset schemes

                                                              KingstonGreater GeelongMelbourne Water ndash non scheme contributions

                                                              Site management

                                                              EPA guidelines- management of erosion and sediment

                                                              Next steps and other stormwater initiatives

                                                              Emma Stewart DELWP

                                                              62

                                                              Next steps

                                                              bull Trainingbull The EPArsquos BPEM Reviewbull Offsets policybull Review of STORM bull Building controls

                                                              63

                                                              State Stormwater policies

                                                              64

                                                              Thank you

                                                              • Slide Number 1
                                                              • Slide Number 2
                                                              • History of WSUD
                                                              • History of WSUD
                                                              • Transformational change in urban water
                                                              • Inconsistencies and inequities in our approach to stormwater management
                                                              • Slide Number 8
                                                              • Terms of Reference
                                                              • Improving Stormwater Management Advisory Committee
                                                              • Wide consultation
                                                              • Stakeholder feedback
                                                              • Stakeholder feedback
                                                              • Committee submitted its report in September 2018
                                                              • Committee Recomendations
                                                              • Planning reforms
                                                              • Future policy directions
                                                              • Supporting actions
                                                              • Slide Number 19
                                                              • Government response (to date)
                                                              • Longer term recommendations
                                                              • State-based planning requirements (lsquobeforersquo)
                                                              • State-based planning requirements (lsquoafterrsquo)
                                                              • Development types (volume)
                                                              • Slide Number 25
                                                              • Amendment VC154
                                                              • Whatrsquos in
                                                              • Slide Number 28
                                                              • Key elements of clauses
                                                              • Clause 5318 ndash subdivision
                                                              • Clause 5318 ndash Buildings and works
                                                              • Townhouses - Standard B9
                                                              • Slide Number 33
                                                              • Slide Number 34
                                                              • Slide Number 35
                                                              • Slide Number 36
                                                              • Slide Number 37
                                                              • Buildings and works - Site management standard
                                                              • Site management
                                                              • Planning Advisory Note No 75
                                                              • Slide Number 41
                                                              • Slide Number 42
                                                              • Slide Number 43
                                                              • Slide Number 44
                                                              • Slide Number 45
                                                              • Slide Number 46
                                                              • Slide Number 47
                                                              • Slide Number 48
                                                              • Slide Number 49
                                                              • Slide Number 50
                                                              • Slide Number 51
                                                              • Slide Number 52
                                                              • Slide Number 53
                                                              • Slide Number 54
                                                              • Slide Number 55
                                                              • Slide Number 56
                                                              • Slide Number 57
                                                              • Slide Number 58
                                                              • Slide Number 59
                                                              • Slide Number 60
                                                              • Slide Number 61
                                                              • Next steps
                                                              • State Stormwater policies
                                                              • Slide Number 64

                                                                What does this all mean

                                                                34

                                                                Clause 5318 - Whatrsquos in

                                                                35

                                                                Urban cooling Reduce heat radiation from buildings and hard surfaces throughbull Shade trees in car parks or over driveways bull More open space and treesbull Green roofsbull Green walls

                                                                36

                                                                Optionsbull Passive irrigationbull Integrate assets into

                                                                communal open spacebull Tree pits and permeable

                                                                paving (driveways and carpark)

                                                                bull Stormwater harvesting (major developments only)

                                                                Infiltration habitat amenity

                                                                37

                                                                Control harmful chemicals

                                                                Optionsbull Careful layoutbull Consider alternative less harmful substancesbull Roofed designated storage areabull Internal drainage design to sewer or a treatment devicebull Bunding

                                                                38

                                                                Standard W3Standard W3 requires that application describe how the site will be managed prior to and during the construction period The application should set out requirements for managingbull Erosion and sedimentbull Stormwaterbull Litter concrete and other construction wastesbull Chemical contamination

                                                                Buildings and works - Site management standard

                                                                39

                                                                Site management

                                                                40

                                                                Planning Advisory Note No 75

                                                                Implications for industry

                                                                Kate MatthewsStormwater Victoria

                                                                1 Development proponents- Developers- Consultants (engineers stormwater specialists and planners)- Council (when developing public land lt$1 million)

                                                                2 Development assessors- Council statutory planners- Council internal referrals (engineering assets ESD stormwater officers)

                                                                3 Strategy- Council strategic planners

                                                                4 Melbourne Water

                                                                Whorsquos affected

                                                                43

                                                                What are the implications

                                                                bull BPEM - Itrsquos not just subdivisions any more

                                                                bull Cost ndash offset or assetbull Early planning and integration ndash more

                                                                work up frontbull Not just engineeringbull Varying Council skills and experience

                                                                Development Proponents

                                                                44

                                                                If already have a local policy for WSUDESD no real change

                                                                If notbull Workload and resourcingbull Increased detail and technical

                                                                contentbull Administrative arrangements ndash

                                                                referrals permit conditions ndashmake sure you make 60 stat days

                                                                bull Applicant pressure ndash what do you want

                                                                bull Assets

                                                                Development Assessors

                                                                45

                                                                bull Structure plans and rezoning ndashopportunities for localregional approach

                                                                bull IWM and Stormwater Management Plans ndash opportunities for these to be implemented through the controls spatial opportunities

                                                                bull Opportunities for development of Council offset strategies

                                                                Strategy

                                                                Offsets

                                                                bull Developer enters into an agreement with relevant drainage authority to financially contribute to off-site stormwatermanagement in lieu of providing on-site treatment

                                                                bull Already available for residential subdivisions in Melbourne (Clause 56) through MWCs Stormwater Quality Offset scheme

                                                                What are stormwater quality offsets

                                                                X Not drainage contributions (MWC drainage scheme)

                                                                X Not development contributions (DCPICP)

                                                                47

                                                                When to use

                                                                bull Not in MW DSS or growth area where therersquos an existing framework for funding SW treatment

                                                                bull Onsite treatment not practical or desirable

                                                                bull To fund planned localregional stormwater treatment works in that catchment via an existing offset scheme

                                                                bull Council and developer both agree to it

                                                                48

                                                                OffsetsExample ndash Kingston Offset Scheme

                                                                Asset ownership and maintenance

                                                                bull Whorsquos going to own itbull Whorsquos going to maintain itbull How do you maintain itbull How much will it cost

                                                                bull Where is itbull Is maintenance burden

                                                                practical for likely future owners

                                                                bull Whorsquos going to monitor compliance and how

                                                                The detail is in the permit conditions

                                                                Application requirements

                                                                ldquoAn application must be accompanied by details of the proposed stormwater management system including drainage works and retention detention and discharges of stormwater to the drainage systemrdquo ndash Clause 5318

                                                                What does the planning scheme require

                                                                But alsohellipNeed to provide sufficient information to Council which demonstrates that you comply and how you comply with all the other standards ndash eg urban coolinghabitatetc BPEM site management pollutant control infiltration (as relevant to development type

                                                                51

                                                                1 PlansWhat are you doing where is it going and does it fit

                                                                2 ModellingDo you (or can you) meet BPEM requirements

                                                                3 Written response to standardsHow does your proposal comply with the requirements

                                                                52

                                                                Application

                                                                bull Site plan ndash show all assetsWSUD treatments and any IWM features on the site layout plan with everything else

                                                                bull Landscape plan ndash if planting design passive irrigation etc forms part of response to requirements show

                                                                bull Site management plan (depending on Council)

                                                                bull Separate WSUDIWM plan showing all features on a stripped back background

                                                                bull Concept WSUD asset design ndash larger assets only (wetlands bioretention basins sed basin etc) ndash sufficient design detail to confirm spatial requirements

                                                                PlansPermit conditions

                                                                bull Detailed engineering design bull Site Management Plan (final)bull Asset maintenance plan (final)bull Handover arrangements (if public)

                                                                54

                                                                STORM ndash Online toolbull Print out of STORM reportbull Make sure meets 100 or

                                                                morebull Make sure report inputs and

                                                                results match plan

                                                                Modelling - SWQ

                                                                MUSIC ndash Proprietary softwarebull Provide a copy of the model filebull Print out the modelling resultsbull Provide summary of your model

                                                                inputs for each treatment train (iecatchment size impervious treatment area etc)

                                                                bull Provide a print out of the model schematic

                                                                Bonus points bull Provide details of model

                                                                parametersbull Provide results of MUSIC auditor

                                                                run (if using Melbourne Water MUSIC Guidelines)

                                                                56

                                                                Assessment against standards

                                                                bull Say what you have done (or will do) to meet each standardbull Donrsquot forget (if WSUD) details of maintenance and asset

                                                                ownershipbull Where applicable be explicit why yoursquove chosen (or not chosen) to

                                                                respond the way you have Egbull Opportunitiesbull Site constraintsbull Practicaloperational issues bull Brief dot point summary of options analysis if complex

                                                                bull Make sure if it doesnrsquot meet the standard it meets the objectivebull Make sure shown on plan and consistent with modelling and rest of

                                                                documentation

                                                                57

                                                                Resources

                                                                Local stormwaterWSUD policiesBaysideKingstonCaseyMonashMelbourneYarraMoonee ValleyPort PhilipStonningtonHumeCampaspeBass Coast

                                                                Local ESD (including IWM) policies Greater BendigoGreater DandenongHobsons BayWhittleseaWyndhamWhitehorseManninghamMorelandDarebinBanyuleKnoxBrimbank

                                                                Council planning resources

                                                                Application resources ndashexamplesDELWP Practice Note ndashformal guide to the new controlsMoreland ndash application checklists and example plans for a variety of residential developmentsPort Philip ndash compliance guidelines checklist and examplesMoonee Valley ndash checklists and example plans including site management plans Greater Bendigo ndash WSUD kitBayside ndash application guidelines and example plans

                                                                59

                                                                Technical guidelines (modelling design construction)

                                                                Melbourne Water

                                                                STORM calculatorMUSIC auditor - lsquohow torsquo video here

                                                                Melbourne Water technical guidelines page- WSUD asset life cycle costings and model maintenance guidelines- MUSIC guidelines- Stormwater harvesting guidelines- WSUD life cycle costings and

                                                                maintenance guidelines- Design and construction guidelines

                                                                for variety of assetshttpswwwmelbournewatercomauplanning-and-buildingdeveloper-guides-and-resourcesguidelines-drawings-and-checklistsguidelines

                                                                Council

                                                                South-Eastern Growth Council WSUD guidelines ndash note that some individual Councils have their own addendumsMelbournePort PhilipNorth-West Growth Council WSUD guidelines - note that some individual Councils have their own addendumsGreater BendigoMilduraBallaratBaw BawWyndhamMoreland ndash tree pits and raingardens

                                                                60

                                                                IWM

                                                                Example Council IWM strategiesMelbourneCaseyMonashKingston

                                                                Resilient Melbourne ndash IWM information lsquohubrsquoClearwater ndash capacity building and case studiesMelbourne Water ndash funding opportunities for IWM projects

                                                                Stormwater offset schemes

                                                                KingstonGreater GeelongMelbourne Water ndash non scheme contributions

                                                                Site management

                                                                EPA guidelines- management of erosion and sediment

                                                                Next steps and other stormwater initiatives

                                                                Emma Stewart DELWP

                                                                62

                                                                Next steps

                                                                bull Trainingbull The EPArsquos BPEM Reviewbull Offsets policybull Review of STORM bull Building controls

                                                                63

                                                                State Stormwater policies

                                                                64

                                                                Thank you

                                                                • Slide Number 1
                                                                • Slide Number 2
                                                                • History of WSUD
                                                                • History of WSUD
                                                                • Transformational change in urban water
                                                                • Inconsistencies and inequities in our approach to stormwater management
                                                                • Slide Number 8
                                                                • Terms of Reference
                                                                • Improving Stormwater Management Advisory Committee
                                                                • Wide consultation
                                                                • Stakeholder feedback
                                                                • Stakeholder feedback
                                                                • Committee submitted its report in September 2018
                                                                • Committee Recomendations
                                                                • Planning reforms
                                                                • Future policy directions
                                                                • Supporting actions
                                                                • Slide Number 19
                                                                • Government response (to date)
                                                                • Longer term recommendations
                                                                • State-based planning requirements (lsquobeforersquo)
                                                                • State-based planning requirements (lsquoafterrsquo)
                                                                • Development types (volume)
                                                                • Slide Number 25
                                                                • Amendment VC154
                                                                • Whatrsquos in
                                                                • Slide Number 28
                                                                • Key elements of clauses
                                                                • Clause 5318 ndash subdivision
                                                                • Clause 5318 ndash Buildings and works
                                                                • Townhouses - Standard B9
                                                                • Slide Number 33
                                                                • Slide Number 34
                                                                • Slide Number 35
                                                                • Slide Number 36
                                                                • Slide Number 37
                                                                • Buildings and works - Site management standard
                                                                • Site management
                                                                • Planning Advisory Note No 75
                                                                • Slide Number 41
                                                                • Slide Number 42
                                                                • Slide Number 43
                                                                • Slide Number 44
                                                                • Slide Number 45
                                                                • Slide Number 46
                                                                • Slide Number 47
                                                                • Slide Number 48
                                                                • Slide Number 49
                                                                • Slide Number 50
                                                                • Slide Number 51
                                                                • Slide Number 52
                                                                • Slide Number 53
                                                                • Slide Number 54
                                                                • Slide Number 55
                                                                • Slide Number 56
                                                                • Slide Number 57
                                                                • Slide Number 58
                                                                • Slide Number 59
                                                                • Slide Number 60
                                                                • Slide Number 61
                                                                • Next steps
                                                                • State Stormwater policies
                                                                • Slide Number 64

                                                                  34

                                                                  Clause 5318 - Whatrsquos in

                                                                  35

                                                                  Urban cooling Reduce heat radiation from buildings and hard surfaces throughbull Shade trees in car parks or over driveways bull More open space and treesbull Green roofsbull Green walls

                                                                  36

                                                                  Optionsbull Passive irrigationbull Integrate assets into

                                                                  communal open spacebull Tree pits and permeable

                                                                  paving (driveways and carpark)

                                                                  bull Stormwater harvesting (major developments only)

                                                                  Infiltration habitat amenity

                                                                  37

                                                                  Control harmful chemicals

                                                                  Optionsbull Careful layoutbull Consider alternative less harmful substancesbull Roofed designated storage areabull Internal drainage design to sewer or a treatment devicebull Bunding

                                                                  38

                                                                  Standard W3Standard W3 requires that application describe how the site will be managed prior to and during the construction period The application should set out requirements for managingbull Erosion and sedimentbull Stormwaterbull Litter concrete and other construction wastesbull Chemical contamination

                                                                  Buildings and works - Site management standard

                                                                  39

                                                                  Site management

                                                                  40

                                                                  Planning Advisory Note No 75

                                                                  Implications for industry

                                                                  Kate MatthewsStormwater Victoria

                                                                  1 Development proponents- Developers- Consultants (engineers stormwater specialists and planners)- Council (when developing public land lt$1 million)

                                                                  2 Development assessors- Council statutory planners- Council internal referrals (engineering assets ESD stormwater officers)

                                                                  3 Strategy- Council strategic planners

                                                                  4 Melbourne Water

                                                                  Whorsquos affected

                                                                  43

                                                                  What are the implications

                                                                  bull BPEM - Itrsquos not just subdivisions any more

                                                                  bull Cost ndash offset or assetbull Early planning and integration ndash more

                                                                  work up frontbull Not just engineeringbull Varying Council skills and experience

                                                                  Development Proponents

                                                                  44

                                                                  If already have a local policy for WSUDESD no real change

                                                                  If notbull Workload and resourcingbull Increased detail and technical

                                                                  contentbull Administrative arrangements ndash

                                                                  referrals permit conditions ndashmake sure you make 60 stat days

                                                                  bull Applicant pressure ndash what do you want

                                                                  bull Assets

                                                                  Development Assessors

                                                                  45

                                                                  bull Structure plans and rezoning ndashopportunities for localregional approach

                                                                  bull IWM and Stormwater Management Plans ndash opportunities for these to be implemented through the controls spatial opportunities

                                                                  bull Opportunities for development of Council offset strategies

                                                                  Strategy

                                                                  Offsets

                                                                  bull Developer enters into an agreement with relevant drainage authority to financially contribute to off-site stormwatermanagement in lieu of providing on-site treatment

                                                                  bull Already available for residential subdivisions in Melbourne (Clause 56) through MWCs Stormwater Quality Offset scheme

                                                                  What are stormwater quality offsets

                                                                  X Not drainage contributions (MWC drainage scheme)

                                                                  X Not development contributions (DCPICP)

                                                                  47

                                                                  When to use

                                                                  bull Not in MW DSS or growth area where therersquos an existing framework for funding SW treatment

                                                                  bull Onsite treatment not practical or desirable

                                                                  bull To fund planned localregional stormwater treatment works in that catchment via an existing offset scheme

                                                                  bull Council and developer both agree to it

                                                                  48

                                                                  OffsetsExample ndash Kingston Offset Scheme

                                                                  Asset ownership and maintenance

                                                                  bull Whorsquos going to own itbull Whorsquos going to maintain itbull How do you maintain itbull How much will it cost

                                                                  bull Where is itbull Is maintenance burden

                                                                  practical for likely future owners

                                                                  bull Whorsquos going to monitor compliance and how

                                                                  The detail is in the permit conditions

                                                                  Application requirements

                                                                  ldquoAn application must be accompanied by details of the proposed stormwater management system including drainage works and retention detention and discharges of stormwater to the drainage systemrdquo ndash Clause 5318

                                                                  What does the planning scheme require

                                                                  But alsohellipNeed to provide sufficient information to Council which demonstrates that you comply and how you comply with all the other standards ndash eg urban coolinghabitatetc BPEM site management pollutant control infiltration (as relevant to development type

                                                                  51

                                                                  1 PlansWhat are you doing where is it going and does it fit

                                                                  2 ModellingDo you (or can you) meet BPEM requirements

                                                                  3 Written response to standardsHow does your proposal comply with the requirements

                                                                  52

                                                                  Application

                                                                  bull Site plan ndash show all assetsWSUD treatments and any IWM features on the site layout plan with everything else

                                                                  bull Landscape plan ndash if planting design passive irrigation etc forms part of response to requirements show

                                                                  bull Site management plan (depending on Council)

                                                                  bull Separate WSUDIWM plan showing all features on a stripped back background

                                                                  bull Concept WSUD asset design ndash larger assets only (wetlands bioretention basins sed basin etc) ndash sufficient design detail to confirm spatial requirements

                                                                  PlansPermit conditions

                                                                  bull Detailed engineering design bull Site Management Plan (final)bull Asset maintenance plan (final)bull Handover arrangements (if public)

                                                                  54

                                                                  STORM ndash Online toolbull Print out of STORM reportbull Make sure meets 100 or

                                                                  morebull Make sure report inputs and

                                                                  results match plan

                                                                  Modelling - SWQ

                                                                  MUSIC ndash Proprietary softwarebull Provide a copy of the model filebull Print out the modelling resultsbull Provide summary of your model

                                                                  inputs for each treatment train (iecatchment size impervious treatment area etc)

                                                                  bull Provide a print out of the model schematic

                                                                  Bonus points bull Provide details of model

                                                                  parametersbull Provide results of MUSIC auditor

                                                                  run (if using Melbourne Water MUSIC Guidelines)

                                                                  56

                                                                  Assessment against standards

                                                                  bull Say what you have done (or will do) to meet each standardbull Donrsquot forget (if WSUD) details of maintenance and asset

                                                                  ownershipbull Where applicable be explicit why yoursquove chosen (or not chosen) to

                                                                  respond the way you have Egbull Opportunitiesbull Site constraintsbull Practicaloperational issues bull Brief dot point summary of options analysis if complex

                                                                  bull Make sure if it doesnrsquot meet the standard it meets the objectivebull Make sure shown on plan and consistent with modelling and rest of

                                                                  documentation

                                                                  57

                                                                  Resources

                                                                  Local stormwaterWSUD policiesBaysideKingstonCaseyMonashMelbourneYarraMoonee ValleyPort PhilipStonningtonHumeCampaspeBass Coast

                                                                  Local ESD (including IWM) policies Greater BendigoGreater DandenongHobsons BayWhittleseaWyndhamWhitehorseManninghamMorelandDarebinBanyuleKnoxBrimbank

                                                                  Council planning resources

                                                                  Application resources ndashexamplesDELWP Practice Note ndashformal guide to the new controlsMoreland ndash application checklists and example plans for a variety of residential developmentsPort Philip ndash compliance guidelines checklist and examplesMoonee Valley ndash checklists and example plans including site management plans Greater Bendigo ndash WSUD kitBayside ndash application guidelines and example plans

                                                                  59

                                                                  Technical guidelines (modelling design construction)

                                                                  Melbourne Water

                                                                  STORM calculatorMUSIC auditor - lsquohow torsquo video here

                                                                  Melbourne Water technical guidelines page- WSUD asset life cycle costings and model maintenance guidelines- MUSIC guidelines- Stormwater harvesting guidelines- WSUD life cycle costings and

                                                                  maintenance guidelines- Design and construction guidelines

                                                                  for variety of assetshttpswwwmelbournewatercomauplanning-and-buildingdeveloper-guides-and-resourcesguidelines-drawings-and-checklistsguidelines

                                                                  Council

                                                                  South-Eastern Growth Council WSUD guidelines ndash note that some individual Councils have their own addendumsMelbournePort PhilipNorth-West Growth Council WSUD guidelines - note that some individual Councils have their own addendumsGreater BendigoMilduraBallaratBaw BawWyndhamMoreland ndash tree pits and raingardens

                                                                  60

                                                                  IWM

                                                                  Example Council IWM strategiesMelbourneCaseyMonashKingston

                                                                  Resilient Melbourne ndash IWM information lsquohubrsquoClearwater ndash capacity building and case studiesMelbourne Water ndash funding opportunities for IWM projects

                                                                  Stormwater offset schemes

                                                                  KingstonGreater GeelongMelbourne Water ndash non scheme contributions

                                                                  Site management

                                                                  EPA guidelines- management of erosion and sediment

                                                                  Next steps and other stormwater initiatives

                                                                  Emma Stewart DELWP

                                                                  62

                                                                  Next steps

                                                                  bull Trainingbull The EPArsquos BPEM Reviewbull Offsets policybull Review of STORM bull Building controls

                                                                  63

                                                                  State Stormwater policies

                                                                  64

                                                                  Thank you

                                                                  • Slide Number 1
                                                                  • Slide Number 2
                                                                  • History of WSUD
                                                                  • History of WSUD
                                                                  • Transformational change in urban water
                                                                  • Inconsistencies and inequities in our approach to stormwater management
                                                                  • Slide Number 8
                                                                  • Terms of Reference
                                                                  • Improving Stormwater Management Advisory Committee
                                                                  • Wide consultation
                                                                  • Stakeholder feedback
                                                                  • Stakeholder feedback
                                                                  • Committee submitted its report in September 2018
                                                                  • Committee Recomendations
                                                                  • Planning reforms
                                                                  • Future policy directions
                                                                  • Supporting actions
                                                                  • Slide Number 19
                                                                  • Government response (to date)
                                                                  • Longer term recommendations
                                                                  • State-based planning requirements (lsquobeforersquo)
                                                                  • State-based planning requirements (lsquoafterrsquo)
                                                                  • Development types (volume)
                                                                  • Slide Number 25
                                                                  • Amendment VC154
                                                                  • Whatrsquos in
                                                                  • Slide Number 28
                                                                  • Key elements of clauses
                                                                  • Clause 5318 ndash subdivision
                                                                  • Clause 5318 ndash Buildings and works
                                                                  • Townhouses - Standard B9
                                                                  • Slide Number 33
                                                                  • Slide Number 34
                                                                  • Slide Number 35
                                                                  • Slide Number 36
                                                                  • Slide Number 37
                                                                  • Buildings and works - Site management standard
                                                                  • Site management
                                                                  • Planning Advisory Note No 75
                                                                  • Slide Number 41
                                                                  • Slide Number 42
                                                                  • Slide Number 43
                                                                  • Slide Number 44
                                                                  • Slide Number 45
                                                                  • Slide Number 46
                                                                  • Slide Number 47
                                                                  • Slide Number 48
                                                                  • Slide Number 49
                                                                  • Slide Number 50
                                                                  • Slide Number 51
                                                                  • Slide Number 52
                                                                  • Slide Number 53
                                                                  • Slide Number 54
                                                                  • Slide Number 55
                                                                  • Slide Number 56
                                                                  • Slide Number 57
                                                                  • Slide Number 58
                                                                  • Slide Number 59
                                                                  • Slide Number 60
                                                                  • Slide Number 61
                                                                  • Next steps
                                                                  • State Stormwater policies
                                                                  • Slide Number 64

                                                                    35

                                                                    Urban cooling Reduce heat radiation from buildings and hard surfaces throughbull Shade trees in car parks or over driveways bull More open space and treesbull Green roofsbull Green walls

                                                                    36

                                                                    Optionsbull Passive irrigationbull Integrate assets into

                                                                    communal open spacebull Tree pits and permeable

                                                                    paving (driveways and carpark)

                                                                    bull Stormwater harvesting (major developments only)

                                                                    Infiltration habitat amenity

                                                                    37

                                                                    Control harmful chemicals

                                                                    Optionsbull Careful layoutbull Consider alternative less harmful substancesbull Roofed designated storage areabull Internal drainage design to sewer or a treatment devicebull Bunding

                                                                    38

                                                                    Standard W3Standard W3 requires that application describe how the site will be managed prior to and during the construction period The application should set out requirements for managingbull Erosion and sedimentbull Stormwaterbull Litter concrete and other construction wastesbull Chemical contamination

                                                                    Buildings and works - Site management standard

                                                                    39

                                                                    Site management

                                                                    40

                                                                    Planning Advisory Note No 75

                                                                    Implications for industry

                                                                    Kate MatthewsStormwater Victoria

                                                                    1 Development proponents- Developers- Consultants (engineers stormwater specialists and planners)- Council (when developing public land lt$1 million)

                                                                    2 Development assessors- Council statutory planners- Council internal referrals (engineering assets ESD stormwater officers)

                                                                    3 Strategy- Council strategic planners

                                                                    4 Melbourne Water

                                                                    Whorsquos affected

                                                                    43

                                                                    What are the implications

                                                                    bull BPEM - Itrsquos not just subdivisions any more

                                                                    bull Cost ndash offset or assetbull Early planning and integration ndash more

                                                                    work up frontbull Not just engineeringbull Varying Council skills and experience

                                                                    Development Proponents

                                                                    44

                                                                    If already have a local policy for WSUDESD no real change

                                                                    If notbull Workload and resourcingbull Increased detail and technical

                                                                    contentbull Administrative arrangements ndash

                                                                    referrals permit conditions ndashmake sure you make 60 stat days

                                                                    bull Applicant pressure ndash what do you want

                                                                    bull Assets

                                                                    Development Assessors

                                                                    45

                                                                    bull Structure plans and rezoning ndashopportunities for localregional approach

                                                                    bull IWM and Stormwater Management Plans ndash opportunities for these to be implemented through the controls spatial opportunities

                                                                    bull Opportunities for development of Council offset strategies

                                                                    Strategy

                                                                    Offsets

                                                                    bull Developer enters into an agreement with relevant drainage authority to financially contribute to off-site stormwatermanagement in lieu of providing on-site treatment

                                                                    bull Already available for residential subdivisions in Melbourne (Clause 56) through MWCs Stormwater Quality Offset scheme

                                                                    What are stormwater quality offsets

                                                                    X Not drainage contributions (MWC drainage scheme)

                                                                    X Not development contributions (DCPICP)

                                                                    47

                                                                    When to use

                                                                    bull Not in MW DSS or growth area where therersquos an existing framework for funding SW treatment

                                                                    bull Onsite treatment not practical or desirable

                                                                    bull To fund planned localregional stormwater treatment works in that catchment via an existing offset scheme

                                                                    bull Council and developer both agree to it

                                                                    48

                                                                    OffsetsExample ndash Kingston Offset Scheme

                                                                    Asset ownership and maintenance

                                                                    bull Whorsquos going to own itbull Whorsquos going to maintain itbull How do you maintain itbull How much will it cost

                                                                    bull Where is itbull Is maintenance burden

                                                                    practical for likely future owners

                                                                    bull Whorsquos going to monitor compliance and how

                                                                    The detail is in the permit conditions

                                                                    Application requirements

                                                                    ldquoAn application must be accompanied by details of the proposed stormwater management system including drainage works and retention detention and discharges of stormwater to the drainage systemrdquo ndash Clause 5318

                                                                    What does the planning scheme require

                                                                    But alsohellipNeed to provide sufficient information to Council which demonstrates that you comply and how you comply with all the other standards ndash eg urban coolinghabitatetc BPEM site management pollutant control infiltration (as relevant to development type

                                                                    51

                                                                    1 PlansWhat are you doing where is it going and does it fit

                                                                    2 ModellingDo you (or can you) meet BPEM requirements

                                                                    3 Written response to standardsHow does your proposal comply with the requirements

                                                                    52

                                                                    Application

                                                                    bull Site plan ndash show all assetsWSUD treatments and any IWM features on the site layout plan with everything else

                                                                    bull Landscape plan ndash if planting design passive irrigation etc forms part of response to requirements show

                                                                    bull Site management plan (depending on Council)

                                                                    bull Separate WSUDIWM plan showing all features on a stripped back background

                                                                    bull Concept WSUD asset design ndash larger assets only (wetlands bioretention basins sed basin etc) ndash sufficient design detail to confirm spatial requirements

                                                                    PlansPermit conditions

                                                                    bull Detailed engineering design bull Site Management Plan (final)bull Asset maintenance plan (final)bull Handover arrangements (if public)

                                                                    54

                                                                    STORM ndash Online toolbull Print out of STORM reportbull Make sure meets 100 or

                                                                    morebull Make sure report inputs and

                                                                    results match plan

                                                                    Modelling - SWQ

                                                                    MUSIC ndash Proprietary softwarebull Provide a copy of the model filebull Print out the modelling resultsbull Provide summary of your model

                                                                    inputs for each treatment train (iecatchment size impervious treatment area etc)

                                                                    bull Provide a print out of the model schematic

                                                                    Bonus points bull Provide details of model

                                                                    parametersbull Provide results of MUSIC auditor

                                                                    run (if using Melbourne Water MUSIC Guidelines)

                                                                    56

                                                                    Assessment against standards

                                                                    bull Say what you have done (or will do) to meet each standardbull Donrsquot forget (if WSUD) details of maintenance and asset

                                                                    ownershipbull Where applicable be explicit why yoursquove chosen (or not chosen) to

                                                                    respond the way you have Egbull Opportunitiesbull Site constraintsbull Practicaloperational issues bull Brief dot point summary of options analysis if complex

                                                                    bull Make sure if it doesnrsquot meet the standard it meets the objectivebull Make sure shown on plan and consistent with modelling and rest of

                                                                    documentation

                                                                    57

                                                                    Resources

                                                                    Local stormwaterWSUD policiesBaysideKingstonCaseyMonashMelbourneYarraMoonee ValleyPort PhilipStonningtonHumeCampaspeBass Coast

                                                                    Local ESD (including IWM) policies Greater BendigoGreater DandenongHobsons BayWhittleseaWyndhamWhitehorseManninghamMorelandDarebinBanyuleKnoxBrimbank

                                                                    Council planning resources

                                                                    Application resources ndashexamplesDELWP Practice Note ndashformal guide to the new controlsMoreland ndash application checklists and example plans for a variety of residential developmentsPort Philip ndash compliance guidelines checklist and examplesMoonee Valley ndash checklists and example plans including site management plans Greater Bendigo ndash WSUD kitBayside ndash application guidelines and example plans

                                                                    59

                                                                    Technical guidelines (modelling design construction)

                                                                    Melbourne Water

                                                                    STORM calculatorMUSIC auditor - lsquohow torsquo video here

                                                                    Melbourne Water technical guidelines page- WSUD asset life cycle costings and model maintenance guidelines- MUSIC guidelines- Stormwater harvesting guidelines- WSUD life cycle costings and

                                                                    maintenance guidelines- Design and construction guidelines

                                                                    for variety of assetshttpswwwmelbournewatercomauplanning-and-buildingdeveloper-guides-and-resourcesguidelines-drawings-and-checklistsguidelines

                                                                    Council

                                                                    South-Eastern Growth Council WSUD guidelines ndash note that some individual Councils have their own addendumsMelbournePort PhilipNorth-West Growth Council WSUD guidelines - note that some individual Councils have their own addendumsGreater BendigoMilduraBallaratBaw BawWyndhamMoreland ndash tree pits and raingardens

                                                                    60

                                                                    IWM

                                                                    Example Council IWM strategiesMelbourneCaseyMonashKingston

                                                                    Resilient Melbourne ndash IWM information lsquohubrsquoClearwater ndash capacity building and case studiesMelbourne Water ndash funding opportunities for IWM projects

                                                                    Stormwater offset schemes

                                                                    KingstonGreater GeelongMelbourne Water ndash non scheme contributions

                                                                    Site management

                                                                    EPA guidelines- management of erosion and sediment

                                                                    Next steps and other stormwater initiatives

                                                                    Emma Stewart DELWP

                                                                    62

                                                                    Next steps

                                                                    bull Trainingbull The EPArsquos BPEM Reviewbull Offsets policybull Review of STORM bull Building controls

                                                                    63

                                                                    State Stormwater policies

                                                                    64

                                                                    Thank you

                                                                    • Slide Number 1
                                                                    • Slide Number 2
                                                                    • History of WSUD
                                                                    • History of WSUD
                                                                    • Transformational change in urban water
                                                                    • Inconsistencies and inequities in our approach to stormwater management
                                                                    • Slide Number 8
                                                                    • Terms of Reference
                                                                    • Improving Stormwater Management Advisory Committee
                                                                    • Wide consultation
                                                                    • Stakeholder feedback
                                                                    • Stakeholder feedback
                                                                    • Committee submitted its report in September 2018
                                                                    • Committee Recomendations
                                                                    • Planning reforms
                                                                    • Future policy directions
                                                                    • Supporting actions
                                                                    • Slide Number 19
                                                                    • Government response (to date)
                                                                    • Longer term recommendations
                                                                    • State-based planning requirements (lsquobeforersquo)
                                                                    • State-based planning requirements (lsquoafterrsquo)
                                                                    • Development types (volume)
                                                                    • Slide Number 25
                                                                    • Amendment VC154
                                                                    • Whatrsquos in
                                                                    • Slide Number 28
                                                                    • Key elements of clauses
                                                                    • Clause 5318 ndash subdivision
                                                                    • Clause 5318 ndash Buildings and works
                                                                    • Townhouses - Standard B9
                                                                    • Slide Number 33
                                                                    • Slide Number 34
                                                                    • Slide Number 35
                                                                    • Slide Number 36
                                                                    • Slide Number 37
                                                                    • Buildings and works - Site management standard
                                                                    • Site management
                                                                    • Planning Advisory Note No 75
                                                                    • Slide Number 41
                                                                    • Slide Number 42
                                                                    • Slide Number 43
                                                                    • Slide Number 44
                                                                    • Slide Number 45
                                                                    • Slide Number 46
                                                                    • Slide Number 47
                                                                    • Slide Number 48
                                                                    • Slide Number 49
                                                                    • Slide Number 50
                                                                    • Slide Number 51
                                                                    • Slide Number 52
                                                                    • Slide Number 53
                                                                    • Slide Number 54
                                                                    • Slide Number 55
                                                                    • Slide Number 56
                                                                    • Slide Number 57
                                                                    • Slide Number 58
                                                                    • Slide Number 59
                                                                    • Slide Number 60
                                                                    • Slide Number 61
                                                                    • Next steps
                                                                    • State Stormwater policies
                                                                    • Slide Number 64

                                                                      36

                                                                      Optionsbull Passive irrigationbull Integrate assets into

                                                                      communal open spacebull Tree pits and permeable

                                                                      paving (driveways and carpark)

                                                                      bull Stormwater harvesting (major developments only)

                                                                      Infiltration habitat amenity

                                                                      37

                                                                      Control harmful chemicals

                                                                      Optionsbull Careful layoutbull Consider alternative less harmful substancesbull Roofed designated storage areabull Internal drainage design to sewer or a treatment devicebull Bunding

                                                                      38

                                                                      Standard W3Standard W3 requires that application describe how the site will be managed prior to and during the construction period The application should set out requirements for managingbull Erosion and sedimentbull Stormwaterbull Litter concrete and other construction wastesbull Chemical contamination

                                                                      Buildings and works - Site management standard

                                                                      39

                                                                      Site management

                                                                      40

                                                                      Planning Advisory Note No 75

                                                                      Implications for industry

                                                                      Kate MatthewsStormwater Victoria

                                                                      1 Development proponents- Developers- Consultants (engineers stormwater specialists and planners)- Council (when developing public land lt$1 million)

                                                                      2 Development assessors- Council statutory planners- Council internal referrals (engineering assets ESD stormwater officers)

                                                                      3 Strategy- Council strategic planners

                                                                      4 Melbourne Water

                                                                      Whorsquos affected

                                                                      43

                                                                      What are the implications

                                                                      bull BPEM - Itrsquos not just subdivisions any more

                                                                      bull Cost ndash offset or assetbull Early planning and integration ndash more

                                                                      work up frontbull Not just engineeringbull Varying Council skills and experience

                                                                      Development Proponents

                                                                      44

                                                                      If already have a local policy for WSUDESD no real change

                                                                      If notbull Workload and resourcingbull Increased detail and technical

                                                                      contentbull Administrative arrangements ndash

                                                                      referrals permit conditions ndashmake sure you make 60 stat days

                                                                      bull Applicant pressure ndash what do you want

                                                                      bull Assets

                                                                      Development Assessors

                                                                      45

                                                                      bull Structure plans and rezoning ndashopportunities for localregional approach

                                                                      bull IWM and Stormwater Management Plans ndash opportunities for these to be implemented through the controls spatial opportunities

                                                                      bull Opportunities for development of Council offset strategies

                                                                      Strategy

                                                                      Offsets

                                                                      bull Developer enters into an agreement with relevant drainage authority to financially contribute to off-site stormwatermanagement in lieu of providing on-site treatment

                                                                      bull Already available for residential subdivisions in Melbourne (Clause 56) through MWCs Stormwater Quality Offset scheme

                                                                      What are stormwater quality offsets

                                                                      X Not drainage contributions (MWC drainage scheme)

                                                                      X Not development contributions (DCPICP)

                                                                      47

                                                                      When to use

                                                                      bull Not in MW DSS or growth area where therersquos an existing framework for funding SW treatment

                                                                      bull Onsite treatment not practical or desirable

                                                                      bull To fund planned localregional stormwater treatment works in that catchment via an existing offset scheme

                                                                      bull Council and developer both agree to it

                                                                      48

                                                                      OffsetsExample ndash Kingston Offset Scheme

                                                                      Asset ownership and maintenance

                                                                      bull Whorsquos going to own itbull Whorsquos going to maintain itbull How do you maintain itbull How much will it cost

                                                                      bull Where is itbull Is maintenance burden

                                                                      practical for likely future owners

                                                                      bull Whorsquos going to monitor compliance and how

                                                                      The detail is in the permit conditions

                                                                      Application requirements

                                                                      ldquoAn application must be accompanied by details of the proposed stormwater management system including drainage works and retention detention and discharges of stormwater to the drainage systemrdquo ndash Clause 5318

                                                                      What does the planning scheme require

                                                                      But alsohellipNeed to provide sufficient information to Council which demonstrates that you comply and how you comply with all the other standards ndash eg urban coolinghabitatetc BPEM site management pollutant control infiltration (as relevant to development type

                                                                      51

                                                                      1 PlansWhat are you doing where is it going and does it fit

                                                                      2 ModellingDo you (or can you) meet BPEM requirements

                                                                      3 Written response to standardsHow does your proposal comply with the requirements

                                                                      52

                                                                      Application

                                                                      bull Site plan ndash show all assetsWSUD treatments and any IWM features on the site layout plan with everything else

                                                                      bull Landscape plan ndash if planting design passive irrigation etc forms part of response to requirements show

                                                                      bull Site management plan (depending on Council)

                                                                      bull Separate WSUDIWM plan showing all features on a stripped back background

                                                                      bull Concept WSUD asset design ndash larger assets only (wetlands bioretention basins sed basin etc) ndash sufficient design detail to confirm spatial requirements

                                                                      PlansPermit conditions

                                                                      bull Detailed engineering design bull Site Management Plan (final)bull Asset maintenance plan (final)bull Handover arrangements (if public)

                                                                      54

                                                                      STORM ndash Online toolbull Print out of STORM reportbull Make sure meets 100 or

                                                                      morebull Make sure report inputs and

                                                                      results match plan

                                                                      Modelling - SWQ

                                                                      MUSIC ndash Proprietary softwarebull Provide a copy of the model filebull Print out the modelling resultsbull Provide summary of your model

                                                                      inputs for each treatment train (iecatchment size impervious treatment area etc)

                                                                      bull Provide a print out of the model schematic

                                                                      Bonus points bull Provide details of model

                                                                      parametersbull Provide results of MUSIC auditor

                                                                      run (if using Melbourne Water MUSIC Guidelines)

                                                                      56

                                                                      Assessment against standards

                                                                      bull Say what you have done (or will do) to meet each standardbull Donrsquot forget (if WSUD) details of maintenance and asset

                                                                      ownershipbull Where applicable be explicit why yoursquove chosen (or not chosen) to

                                                                      respond the way you have Egbull Opportunitiesbull Site constraintsbull Practicaloperational issues bull Brief dot point summary of options analysis if complex

                                                                      bull Make sure if it doesnrsquot meet the standard it meets the objectivebull Make sure shown on plan and consistent with modelling and rest of

                                                                      documentation

                                                                      57

                                                                      Resources

                                                                      Local stormwaterWSUD policiesBaysideKingstonCaseyMonashMelbourneYarraMoonee ValleyPort PhilipStonningtonHumeCampaspeBass Coast

                                                                      Local ESD (including IWM) policies Greater BendigoGreater DandenongHobsons BayWhittleseaWyndhamWhitehorseManninghamMorelandDarebinBanyuleKnoxBrimbank

                                                                      Council planning resources

                                                                      Application resources ndashexamplesDELWP Practice Note ndashformal guide to the new controlsMoreland ndash application checklists and example plans for a variety of residential developmentsPort Philip ndash compliance guidelines checklist and examplesMoonee Valley ndash checklists and example plans including site management plans Greater Bendigo ndash WSUD kitBayside ndash application guidelines and example plans

                                                                      59

                                                                      Technical guidelines (modelling design construction)

                                                                      Melbourne Water

                                                                      STORM calculatorMUSIC auditor - lsquohow torsquo video here

                                                                      Melbourne Water technical guidelines page- WSUD asset life cycle costings and model maintenance guidelines- MUSIC guidelines- Stormwater harvesting guidelines- WSUD life cycle costings and

                                                                      maintenance guidelines- Design and construction guidelines

                                                                      for variety of assetshttpswwwmelbournewatercomauplanning-and-buildingdeveloper-guides-and-resourcesguidelines-drawings-and-checklistsguidelines

                                                                      Council

                                                                      South-Eastern Growth Council WSUD guidelines ndash note that some individual Councils have their own addendumsMelbournePort PhilipNorth-West Growth Council WSUD guidelines - note that some individual Councils have their own addendumsGreater BendigoMilduraBallaratBaw BawWyndhamMoreland ndash tree pits and raingardens

                                                                      60

                                                                      IWM

                                                                      Example Council IWM strategiesMelbourneCaseyMonashKingston

                                                                      Resilient Melbourne ndash IWM information lsquohubrsquoClearwater ndash capacity building and case studiesMelbourne Water ndash funding opportunities for IWM projects

                                                                      Stormwater offset schemes

                                                                      KingstonGreater GeelongMelbourne Water ndash non scheme contributions

                                                                      Site management

                                                                      EPA guidelines- management of erosion and sediment

                                                                      Next steps and other stormwater initiatives

                                                                      Emma Stewart DELWP

                                                                      62

                                                                      Next steps

                                                                      bull Trainingbull The EPArsquos BPEM Reviewbull Offsets policybull Review of STORM bull Building controls

                                                                      63

                                                                      State Stormwater policies

                                                                      64

                                                                      Thank you

                                                                      • Slide Number 1
                                                                      • Slide Number 2
                                                                      • History of WSUD
                                                                      • History of WSUD
                                                                      • Transformational change in urban water
                                                                      • Inconsistencies and inequities in our approach to stormwater management
                                                                      • Slide Number 8
                                                                      • Terms of Reference
                                                                      • Improving Stormwater Management Advisory Committee
                                                                      • Wide consultation
                                                                      • Stakeholder feedback
                                                                      • Stakeholder feedback
                                                                      • Committee submitted its report in September 2018
                                                                      • Committee Recomendations
                                                                      • Planning reforms
                                                                      • Future policy directions
                                                                      • Supporting actions
                                                                      • Slide Number 19
                                                                      • Government response (to date)
                                                                      • Longer term recommendations
                                                                      • State-based planning requirements (lsquobeforersquo)
                                                                      • State-based planning requirements (lsquoafterrsquo)
                                                                      • Development types (volume)
                                                                      • Slide Number 25
                                                                      • Amendment VC154
                                                                      • Whatrsquos in
                                                                      • Slide Number 28
                                                                      • Key elements of clauses
                                                                      • Clause 5318 ndash subdivision
                                                                      • Clause 5318 ndash Buildings and works
                                                                      • Townhouses - Standard B9
                                                                      • Slide Number 33
                                                                      • Slide Number 34
                                                                      • Slide Number 35
                                                                      • Slide Number 36
                                                                      • Slide Number 37
                                                                      • Buildings and works - Site management standard
                                                                      • Site management
                                                                      • Planning Advisory Note No 75
                                                                      • Slide Number 41
                                                                      • Slide Number 42
                                                                      • Slide Number 43
                                                                      • Slide Number 44
                                                                      • Slide Number 45
                                                                      • Slide Number 46
                                                                      • Slide Number 47
                                                                      • Slide Number 48
                                                                      • Slide Number 49
                                                                      • Slide Number 50
                                                                      • Slide Number 51
                                                                      • Slide Number 52
                                                                      • Slide Number 53
                                                                      • Slide Number 54
                                                                      • Slide Number 55
                                                                      • Slide Number 56
                                                                      • Slide Number 57
                                                                      • Slide Number 58
                                                                      • Slide Number 59
                                                                      • Slide Number 60
                                                                      • Slide Number 61
                                                                      • Next steps
                                                                      • State Stormwater policies
                                                                      • Slide Number 64

                                                                        37

                                                                        Control harmful chemicals

                                                                        Optionsbull Careful layoutbull Consider alternative less harmful substancesbull Roofed designated storage areabull Internal drainage design to sewer or a treatment devicebull Bunding

                                                                        38

                                                                        Standard W3Standard W3 requires that application describe how the site will be managed prior to and during the construction period The application should set out requirements for managingbull Erosion and sedimentbull Stormwaterbull Litter concrete and other construction wastesbull Chemical contamination

                                                                        Buildings and works - Site management standard

                                                                        39

                                                                        Site management

                                                                        40

                                                                        Planning Advisory Note No 75

                                                                        Implications for industry

                                                                        Kate MatthewsStormwater Victoria

                                                                        1 Development proponents- Developers- Consultants (engineers stormwater specialists and planners)- Council (when developing public land lt$1 million)

                                                                        2 Development assessors- Council statutory planners- Council internal referrals (engineering assets ESD stormwater officers)

                                                                        3 Strategy- Council strategic planners

                                                                        4 Melbourne Water

                                                                        Whorsquos affected

                                                                        43

                                                                        What are the implications

                                                                        bull BPEM - Itrsquos not just subdivisions any more

                                                                        bull Cost ndash offset or assetbull Early planning and integration ndash more

                                                                        work up frontbull Not just engineeringbull Varying Council skills and experience

                                                                        Development Proponents

                                                                        44

                                                                        If already have a local policy for WSUDESD no real change

                                                                        If notbull Workload and resourcingbull Increased detail and technical

                                                                        contentbull Administrative arrangements ndash

                                                                        referrals permit conditions ndashmake sure you make 60 stat days

                                                                        bull Applicant pressure ndash what do you want

                                                                        bull Assets

                                                                        Development Assessors

                                                                        45

                                                                        bull Structure plans and rezoning ndashopportunities for localregional approach

                                                                        bull IWM and Stormwater Management Plans ndash opportunities for these to be implemented through the controls spatial opportunities

                                                                        bull Opportunities for development of Council offset strategies

                                                                        Strategy

                                                                        Offsets

                                                                        bull Developer enters into an agreement with relevant drainage authority to financially contribute to off-site stormwatermanagement in lieu of providing on-site treatment

                                                                        bull Already available for residential subdivisions in Melbourne (Clause 56) through MWCs Stormwater Quality Offset scheme

                                                                        What are stormwater quality offsets

                                                                        X Not drainage contributions (MWC drainage scheme)

                                                                        X Not development contributions (DCPICP)

                                                                        47

                                                                        When to use

                                                                        bull Not in MW DSS or growth area where therersquos an existing framework for funding SW treatment

                                                                        bull Onsite treatment not practical or desirable

                                                                        bull To fund planned localregional stormwater treatment works in that catchment via an existing offset scheme

                                                                        bull Council and developer both agree to it

                                                                        48

                                                                        OffsetsExample ndash Kingston Offset Scheme

                                                                        Asset ownership and maintenance

                                                                        bull Whorsquos going to own itbull Whorsquos going to maintain itbull How do you maintain itbull How much will it cost

                                                                        bull Where is itbull Is maintenance burden

                                                                        practical for likely future owners

                                                                        bull Whorsquos going to monitor compliance and how

                                                                        The detail is in the permit conditions

                                                                        Application requirements

                                                                        ldquoAn application must be accompanied by details of the proposed stormwater management system including drainage works and retention detention and discharges of stormwater to the drainage systemrdquo ndash Clause 5318

                                                                        What does the planning scheme require

                                                                        But alsohellipNeed to provide sufficient information to Council which demonstrates that you comply and how you comply with all the other standards ndash eg urban coolinghabitatetc BPEM site management pollutant control infiltration (as relevant to development type

                                                                        51

                                                                        1 PlansWhat are you doing where is it going and does it fit

                                                                        2 ModellingDo you (or can you) meet BPEM requirements

                                                                        3 Written response to standardsHow does your proposal comply with the requirements

                                                                        52

                                                                        Application

                                                                        bull Site plan ndash show all assetsWSUD treatments and any IWM features on the site layout plan with everything else

                                                                        bull Landscape plan ndash if planting design passive irrigation etc forms part of response to requirements show

                                                                        bull Site management plan (depending on Council)

                                                                        bull Separate WSUDIWM plan showing all features on a stripped back background

                                                                        bull Concept WSUD asset design ndash larger assets only (wetlands bioretention basins sed basin etc) ndash sufficient design detail to confirm spatial requirements

                                                                        PlansPermit conditions

                                                                        bull Detailed engineering design bull Site Management Plan (final)bull Asset maintenance plan (final)bull Handover arrangements (if public)

                                                                        54

                                                                        STORM ndash Online toolbull Print out of STORM reportbull Make sure meets 100 or

                                                                        morebull Make sure report inputs and

                                                                        results match plan

                                                                        Modelling - SWQ

                                                                        MUSIC ndash Proprietary softwarebull Provide a copy of the model filebull Print out the modelling resultsbull Provide summary of your model

                                                                        inputs for each treatment train (iecatchment size impervious treatment area etc)

                                                                        bull Provide a print out of the model schematic

                                                                        Bonus points bull Provide details of model

                                                                        parametersbull Provide results of MUSIC auditor

                                                                        run (if using Melbourne Water MUSIC Guidelines)

                                                                        56

                                                                        Assessment against standards

                                                                        bull Say what you have done (or will do) to meet each standardbull Donrsquot forget (if WSUD) details of maintenance and asset

                                                                        ownershipbull Where applicable be explicit why yoursquove chosen (or not chosen) to

                                                                        respond the way you have Egbull Opportunitiesbull Site constraintsbull Practicaloperational issues bull Brief dot point summary of options analysis if complex

                                                                        bull Make sure if it doesnrsquot meet the standard it meets the objectivebull Make sure shown on plan and consistent with modelling and rest of

                                                                        documentation

                                                                        57

                                                                        Resources

                                                                        Local stormwaterWSUD policiesBaysideKingstonCaseyMonashMelbourneYarraMoonee ValleyPort PhilipStonningtonHumeCampaspeBass Coast

                                                                        Local ESD (including IWM) policies Greater BendigoGreater DandenongHobsons BayWhittleseaWyndhamWhitehorseManninghamMorelandDarebinBanyuleKnoxBrimbank

                                                                        Council planning resources

                                                                        Application resources ndashexamplesDELWP Practice Note ndashformal guide to the new controlsMoreland ndash application checklists and example plans for a variety of residential developmentsPort Philip ndash compliance guidelines checklist and examplesMoonee Valley ndash checklists and example plans including site management plans Greater Bendigo ndash WSUD kitBayside ndash application guidelines and example plans

                                                                        59

                                                                        Technical guidelines (modelling design construction)

                                                                        Melbourne Water

                                                                        STORM calculatorMUSIC auditor - lsquohow torsquo video here

                                                                        Melbourne Water technical guidelines page- WSUD asset life cycle costings and model maintenance guidelines- MUSIC guidelines- Stormwater harvesting guidelines- WSUD life cycle costings and

                                                                        maintenance guidelines- Design and construction guidelines

                                                                        for variety of assetshttpswwwmelbournewatercomauplanning-and-buildingdeveloper-guides-and-resourcesguidelines-drawings-and-checklistsguidelines

                                                                        Council

                                                                        South-Eastern Growth Council WSUD guidelines ndash note that some individual Councils have their own addendumsMelbournePort PhilipNorth-West Growth Council WSUD guidelines - note that some individual Councils have their own addendumsGreater BendigoMilduraBallaratBaw BawWyndhamMoreland ndash tree pits and raingardens

                                                                        60

                                                                        IWM

                                                                        Example Council IWM strategiesMelbourneCaseyMonashKingston

                                                                        Resilient Melbourne ndash IWM information lsquohubrsquoClearwater ndash capacity building and case studiesMelbourne Water ndash funding opportunities for IWM projects

                                                                        Stormwater offset schemes

                                                                        KingstonGreater GeelongMelbourne Water ndash non scheme contributions

                                                                        Site management

                                                                        EPA guidelines- management of erosion and sediment

                                                                        Next steps and other stormwater initiatives

                                                                        Emma Stewart DELWP

                                                                        62

                                                                        Next steps

                                                                        bull Trainingbull The EPArsquos BPEM Reviewbull Offsets policybull Review of STORM bull Building controls

                                                                        63

                                                                        State Stormwater policies

                                                                        64

                                                                        Thank you

                                                                        • Slide Number 1
                                                                        • Slide Number 2
                                                                        • History of WSUD
                                                                        • History of WSUD
                                                                        • Transformational change in urban water
                                                                        • Inconsistencies and inequities in our approach to stormwater management
                                                                        • Slide Number 8
                                                                        • Terms of Reference
                                                                        • Improving Stormwater Management Advisory Committee
                                                                        • Wide consultation
                                                                        • Stakeholder feedback
                                                                        • Stakeholder feedback
                                                                        • Committee submitted its report in September 2018
                                                                        • Committee Recomendations
                                                                        • Planning reforms
                                                                        • Future policy directions
                                                                        • Supporting actions
                                                                        • Slide Number 19
                                                                        • Government response (to date)
                                                                        • Longer term recommendations
                                                                        • State-based planning requirements (lsquobeforersquo)
                                                                        • State-based planning requirements (lsquoafterrsquo)
                                                                        • Development types (volume)
                                                                        • Slide Number 25
                                                                        • Amendment VC154
                                                                        • Whatrsquos in
                                                                        • Slide Number 28
                                                                        • Key elements of clauses
                                                                        • Clause 5318 ndash subdivision
                                                                        • Clause 5318 ndash Buildings and works
                                                                        • Townhouses - Standard B9
                                                                        • Slide Number 33
                                                                        • Slide Number 34
                                                                        • Slide Number 35
                                                                        • Slide Number 36
                                                                        • Slide Number 37
                                                                        • Buildings and works - Site management standard
                                                                        • Site management
                                                                        • Planning Advisory Note No 75
                                                                        • Slide Number 41
                                                                        • Slide Number 42
                                                                        • Slide Number 43
                                                                        • Slide Number 44
                                                                        • Slide Number 45
                                                                        • Slide Number 46
                                                                        • Slide Number 47
                                                                        • Slide Number 48
                                                                        • Slide Number 49
                                                                        • Slide Number 50
                                                                        • Slide Number 51
                                                                        • Slide Number 52
                                                                        • Slide Number 53
                                                                        • Slide Number 54
                                                                        • Slide Number 55
                                                                        • Slide Number 56
                                                                        • Slide Number 57
                                                                        • Slide Number 58
                                                                        • Slide Number 59
                                                                        • Slide Number 60
                                                                        • Slide Number 61
                                                                        • Next steps
                                                                        • State Stormwater policies
                                                                        • Slide Number 64

                                                                          38

                                                                          Standard W3Standard W3 requires that application describe how the site will be managed prior to and during the construction period The application should set out requirements for managingbull Erosion and sedimentbull Stormwaterbull Litter concrete and other construction wastesbull Chemical contamination

                                                                          Buildings and works - Site management standard

                                                                          39

                                                                          Site management

                                                                          40

                                                                          Planning Advisory Note No 75

                                                                          Implications for industry

                                                                          Kate MatthewsStormwater Victoria

                                                                          1 Development proponents- Developers- Consultants (engineers stormwater specialists and planners)- Council (when developing public land lt$1 million)

                                                                          2 Development assessors- Council statutory planners- Council internal referrals (engineering assets ESD stormwater officers)

                                                                          3 Strategy- Council strategic planners

                                                                          4 Melbourne Water

                                                                          Whorsquos affected

                                                                          43

                                                                          What are the implications

                                                                          bull BPEM - Itrsquos not just subdivisions any more

                                                                          bull Cost ndash offset or assetbull Early planning and integration ndash more

                                                                          work up frontbull Not just engineeringbull Varying Council skills and experience

                                                                          Development Proponents

                                                                          44

                                                                          If already have a local policy for WSUDESD no real change

                                                                          If notbull Workload and resourcingbull Increased detail and technical

                                                                          contentbull Administrative arrangements ndash

                                                                          referrals permit conditions ndashmake sure you make 60 stat days

                                                                          bull Applicant pressure ndash what do you want

                                                                          bull Assets

                                                                          Development Assessors

                                                                          45

                                                                          bull Structure plans and rezoning ndashopportunities for localregional approach

                                                                          bull IWM and Stormwater Management Plans ndash opportunities for these to be implemented through the controls spatial opportunities

                                                                          bull Opportunities for development of Council offset strategies

                                                                          Strategy

                                                                          Offsets

                                                                          bull Developer enters into an agreement with relevant drainage authority to financially contribute to off-site stormwatermanagement in lieu of providing on-site treatment

                                                                          bull Already available for residential subdivisions in Melbourne (Clause 56) through MWCs Stormwater Quality Offset scheme

                                                                          What are stormwater quality offsets

                                                                          X Not drainage contributions (MWC drainage scheme)

                                                                          X Not development contributions (DCPICP)

                                                                          47

                                                                          When to use

                                                                          bull Not in MW DSS or growth area where therersquos an existing framework for funding SW treatment

                                                                          bull Onsite treatment not practical or desirable

                                                                          bull To fund planned localregional stormwater treatment works in that catchment via an existing offset scheme

                                                                          bull Council and developer both agree to it

                                                                          48

                                                                          OffsetsExample ndash Kingston Offset Scheme

                                                                          Asset ownership and maintenance

                                                                          bull Whorsquos going to own itbull Whorsquos going to maintain itbull How do you maintain itbull How much will it cost

                                                                          bull Where is itbull Is maintenance burden

                                                                          practical for likely future owners

                                                                          bull Whorsquos going to monitor compliance and how

                                                                          The detail is in the permit conditions

                                                                          Application requirements

                                                                          ldquoAn application must be accompanied by details of the proposed stormwater management system including drainage works and retention detention and discharges of stormwater to the drainage systemrdquo ndash Clause 5318

                                                                          What does the planning scheme require

                                                                          But alsohellipNeed to provide sufficient information to Council which demonstrates that you comply and how you comply with all the other standards ndash eg urban coolinghabitatetc BPEM site management pollutant control infiltration (as relevant to development type

                                                                          51

                                                                          1 PlansWhat are you doing where is it going and does it fit

                                                                          2 ModellingDo you (or can you) meet BPEM requirements

                                                                          3 Written response to standardsHow does your proposal comply with the requirements

                                                                          52

                                                                          Application

                                                                          bull Site plan ndash show all assetsWSUD treatments and any IWM features on the site layout plan with everything else

                                                                          bull Landscape plan ndash if planting design passive irrigation etc forms part of response to requirements show

                                                                          bull Site management plan (depending on Council)

                                                                          bull Separate WSUDIWM plan showing all features on a stripped back background

                                                                          bull Concept WSUD asset design ndash larger assets only (wetlands bioretention basins sed basin etc) ndash sufficient design detail to confirm spatial requirements

                                                                          PlansPermit conditions

                                                                          bull Detailed engineering design bull Site Management Plan (final)bull Asset maintenance plan (final)bull Handover arrangements (if public)

                                                                          54

                                                                          STORM ndash Online toolbull Print out of STORM reportbull Make sure meets 100 or

                                                                          morebull Make sure report inputs and

                                                                          results match plan

                                                                          Modelling - SWQ

                                                                          MUSIC ndash Proprietary softwarebull Provide a copy of the model filebull Print out the modelling resultsbull Provide summary of your model

                                                                          inputs for each treatment train (iecatchment size impervious treatment area etc)

                                                                          bull Provide a print out of the model schematic

                                                                          Bonus points bull Provide details of model

                                                                          parametersbull Provide results of MUSIC auditor

                                                                          run (if using Melbourne Water MUSIC Guidelines)

                                                                          56

                                                                          Assessment against standards

                                                                          bull Say what you have done (or will do) to meet each standardbull Donrsquot forget (if WSUD) details of maintenance and asset

                                                                          ownershipbull Where applicable be explicit why yoursquove chosen (or not chosen) to

                                                                          respond the way you have Egbull Opportunitiesbull Site constraintsbull Practicaloperational issues bull Brief dot point summary of options analysis if complex

                                                                          bull Make sure if it doesnrsquot meet the standard it meets the objectivebull Make sure shown on plan and consistent with modelling and rest of

                                                                          documentation

                                                                          57

                                                                          Resources

                                                                          Local stormwaterWSUD policiesBaysideKingstonCaseyMonashMelbourneYarraMoonee ValleyPort PhilipStonningtonHumeCampaspeBass Coast

                                                                          Local ESD (including IWM) policies Greater BendigoGreater DandenongHobsons BayWhittleseaWyndhamWhitehorseManninghamMorelandDarebinBanyuleKnoxBrimbank

                                                                          Council planning resources

                                                                          Application resources ndashexamplesDELWP Practice Note ndashformal guide to the new controlsMoreland ndash application checklists and example plans for a variety of residential developmentsPort Philip ndash compliance guidelines checklist and examplesMoonee Valley ndash checklists and example plans including site management plans Greater Bendigo ndash WSUD kitBayside ndash application guidelines and example plans

                                                                          59

                                                                          Technical guidelines (modelling design construction)

                                                                          Melbourne Water

                                                                          STORM calculatorMUSIC auditor - lsquohow torsquo video here

                                                                          Melbourne Water technical guidelines page- WSUD asset life cycle costings and model maintenance guidelines- MUSIC guidelines- Stormwater harvesting guidelines- WSUD life cycle costings and

                                                                          maintenance guidelines- Design and construction guidelines

                                                                          for variety of assetshttpswwwmelbournewatercomauplanning-and-buildingdeveloper-guides-and-resourcesguidelines-drawings-and-checklistsguidelines

                                                                          Council

                                                                          South-Eastern Growth Council WSUD guidelines ndash note that some individual Councils have their own addendumsMelbournePort PhilipNorth-West Growth Council WSUD guidelines - note that some individual Councils have their own addendumsGreater BendigoMilduraBallaratBaw BawWyndhamMoreland ndash tree pits and raingardens

                                                                          60

                                                                          IWM

                                                                          Example Council IWM strategiesMelbourneCaseyMonashKingston

                                                                          Resilient Melbourne ndash IWM information lsquohubrsquoClearwater ndash capacity building and case studiesMelbourne Water ndash funding opportunities for IWM projects

                                                                          Stormwater offset schemes

                                                                          KingstonGreater GeelongMelbourne Water ndash non scheme contributions

                                                                          Site management

                                                                          EPA guidelines- management of erosion and sediment

                                                                          Next steps and other stormwater initiatives

                                                                          Emma Stewart DELWP

                                                                          62

                                                                          Next steps

                                                                          bull Trainingbull The EPArsquos BPEM Reviewbull Offsets policybull Review of STORM bull Building controls

                                                                          63

                                                                          State Stormwater policies

                                                                          64

                                                                          Thank you

                                                                          • Slide Number 1
                                                                          • Slide Number 2
                                                                          • History of WSUD
                                                                          • History of WSUD
                                                                          • Transformational change in urban water
                                                                          • Inconsistencies and inequities in our approach to stormwater management
                                                                          • Slide Number 8
                                                                          • Terms of Reference
                                                                          • Improving Stormwater Management Advisory Committee
                                                                          • Wide consultation
                                                                          • Stakeholder feedback
                                                                          • Stakeholder feedback
                                                                          • Committee submitted its report in September 2018
                                                                          • Committee Recomendations
                                                                          • Planning reforms
                                                                          • Future policy directions
                                                                          • Supporting actions
                                                                          • Slide Number 19
                                                                          • Government response (to date)
                                                                          • Longer term recommendations
                                                                          • State-based planning requirements (lsquobeforersquo)
                                                                          • State-based planning requirements (lsquoafterrsquo)
                                                                          • Development types (volume)
                                                                          • Slide Number 25
                                                                          • Amendment VC154
                                                                          • Whatrsquos in
                                                                          • Slide Number 28
                                                                          • Key elements of clauses
                                                                          • Clause 5318 ndash subdivision
                                                                          • Clause 5318 ndash Buildings and works
                                                                          • Townhouses - Standard B9
                                                                          • Slide Number 33
                                                                          • Slide Number 34
                                                                          • Slide Number 35
                                                                          • Slide Number 36
                                                                          • Slide Number 37
                                                                          • Buildings and works - Site management standard
                                                                          • Site management
                                                                          • Planning Advisory Note No 75
                                                                          • Slide Number 41
                                                                          • Slide Number 42
                                                                          • Slide Number 43
                                                                          • Slide Number 44
                                                                          • Slide Number 45
                                                                          • Slide Number 46
                                                                          • Slide Number 47
                                                                          • Slide Number 48
                                                                          • Slide Number 49
                                                                          • Slide Number 50
                                                                          • Slide Number 51
                                                                          • Slide Number 52
                                                                          • Slide Number 53
                                                                          • Slide Number 54
                                                                          • Slide Number 55
                                                                          • Slide Number 56
                                                                          • Slide Number 57
                                                                          • Slide Number 58
                                                                          • Slide Number 59
                                                                          • Slide Number 60
                                                                          • Slide Number 61
                                                                          • Next steps
                                                                          • State Stormwater policies
                                                                          • Slide Number 64

                                                                            39

                                                                            Site management

                                                                            40

                                                                            Planning Advisory Note No 75

                                                                            Implications for industry

                                                                            Kate MatthewsStormwater Victoria

                                                                            1 Development proponents- Developers- Consultants (engineers stormwater specialists and planners)- Council (when developing public land lt$1 million)

                                                                            2 Development assessors- Council statutory planners- Council internal referrals (engineering assets ESD stormwater officers)

                                                                            3 Strategy- Council strategic planners

                                                                            4 Melbourne Water

                                                                            Whorsquos affected

                                                                            43

                                                                            What are the implications

                                                                            bull BPEM - Itrsquos not just subdivisions any more

                                                                            bull Cost ndash offset or assetbull Early planning and integration ndash more

                                                                            work up frontbull Not just engineeringbull Varying Council skills and experience

                                                                            Development Proponents

                                                                            44

                                                                            If already have a local policy for WSUDESD no real change

                                                                            If notbull Workload and resourcingbull Increased detail and technical

                                                                            contentbull Administrative arrangements ndash

                                                                            referrals permit conditions ndashmake sure you make 60 stat days

                                                                            bull Applicant pressure ndash what do you want

                                                                            bull Assets

                                                                            Development Assessors

                                                                            45

                                                                            bull Structure plans and rezoning ndashopportunities for localregional approach

                                                                            bull IWM and Stormwater Management Plans ndash opportunities for these to be implemented through the controls spatial opportunities

                                                                            bull Opportunities for development of Council offset strategies

                                                                            Strategy

                                                                            Offsets

                                                                            bull Developer enters into an agreement with relevant drainage authority to financially contribute to off-site stormwatermanagement in lieu of providing on-site treatment

                                                                            bull Already available for residential subdivisions in Melbourne (Clause 56) through MWCs Stormwater Quality Offset scheme

                                                                            What are stormwater quality offsets

                                                                            X Not drainage contributions (MWC drainage scheme)

                                                                            X Not development contributions (DCPICP)

                                                                            47

                                                                            When to use

                                                                            bull Not in MW DSS or growth area where therersquos an existing framework for funding SW treatment

                                                                            bull Onsite treatment not practical or desirable

                                                                            bull To fund planned localregional stormwater treatment works in that catchment via an existing offset scheme

                                                                            bull Council and developer both agree to it

                                                                            48

                                                                            OffsetsExample ndash Kingston Offset Scheme

                                                                            Asset ownership and maintenance

                                                                            bull Whorsquos going to own itbull Whorsquos going to maintain itbull How do you maintain itbull How much will it cost

                                                                            bull Where is itbull Is maintenance burden

                                                                            practical for likely future owners

                                                                            bull Whorsquos going to monitor compliance and how

                                                                            The detail is in the permit conditions

                                                                            Application requirements

                                                                            ldquoAn application must be accompanied by details of the proposed stormwater management system including drainage works and retention detention and discharges of stormwater to the drainage systemrdquo ndash Clause 5318

                                                                            What does the planning scheme require

                                                                            But alsohellipNeed to provide sufficient information to Council which demonstrates that you comply and how you comply with all the other standards ndash eg urban coolinghabitatetc BPEM site management pollutant control infiltration (as relevant to development type

                                                                            51

                                                                            1 PlansWhat are you doing where is it going and does it fit

                                                                            2 ModellingDo you (or can you) meet BPEM requirements

                                                                            3 Written response to standardsHow does your proposal comply with the requirements

                                                                            52

                                                                            Application

                                                                            bull Site plan ndash show all assetsWSUD treatments and any IWM features on the site layout plan with everything else

                                                                            bull Landscape plan ndash if planting design passive irrigation etc forms part of response to requirements show

                                                                            bull Site management plan (depending on Council)

                                                                            bull Separate WSUDIWM plan showing all features on a stripped back background

                                                                            bull Concept WSUD asset design ndash larger assets only (wetlands bioretention basins sed basin etc) ndash sufficient design detail to confirm spatial requirements

                                                                            PlansPermit conditions

                                                                            bull Detailed engineering design bull Site Management Plan (final)bull Asset maintenance plan (final)bull Handover arrangements (if public)

                                                                            54

                                                                            STORM ndash Online toolbull Print out of STORM reportbull Make sure meets 100 or

                                                                            morebull Make sure report inputs and

                                                                            results match plan

                                                                            Modelling - SWQ

                                                                            MUSIC ndash Proprietary softwarebull Provide a copy of the model filebull Print out the modelling resultsbull Provide summary of your model

                                                                            inputs for each treatment train (iecatchment size impervious treatment area etc)

                                                                            bull Provide a print out of the model schematic

                                                                            Bonus points bull Provide details of model

                                                                            parametersbull Provide results of MUSIC auditor

                                                                            run (if using Melbourne Water MUSIC Guidelines)

                                                                            56

                                                                            Assessment against standards

                                                                            bull Say what you have done (or will do) to meet each standardbull Donrsquot forget (if WSUD) details of maintenance and asset

                                                                            ownershipbull Where applicable be explicit why yoursquove chosen (or not chosen) to

                                                                            respond the way you have Egbull Opportunitiesbull Site constraintsbull Practicaloperational issues bull Brief dot point summary of options analysis if complex

                                                                            bull Make sure if it doesnrsquot meet the standard it meets the objectivebull Make sure shown on plan and consistent with modelling and rest of

                                                                            documentation

                                                                            57

                                                                            Resources

                                                                            Local stormwaterWSUD policiesBaysideKingstonCaseyMonashMelbourneYarraMoonee ValleyPort PhilipStonningtonHumeCampaspeBass Coast

                                                                            Local ESD (including IWM) policies Greater BendigoGreater DandenongHobsons BayWhittleseaWyndhamWhitehorseManninghamMorelandDarebinBanyuleKnoxBrimbank

                                                                            Council planning resources

                                                                            Application resources ndashexamplesDELWP Practice Note ndashformal guide to the new controlsMoreland ndash application checklists and example plans for a variety of residential developmentsPort Philip ndash compliance guidelines checklist and examplesMoonee Valley ndash checklists and example plans including site management plans Greater Bendigo ndash WSUD kitBayside ndash application guidelines and example plans

                                                                            59

                                                                            Technical guidelines (modelling design construction)

                                                                            Melbourne Water

                                                                            STORM calculatorMUSIC auditor - lsquohow torsquo video here

                                                                            Melbourne Water technical guidelines page- WSUD asset life cycle costings and model maintenance guidelines- MUSIC guidelines- Stormwater harvesting guidelines- WSUD life cycle costings and

                                                                            maintenance guidelines- Design and construction guidelines

                                                                            for variety of assetshttpswwwmelbournewatercomauplanning-and-buildingdeveloper-guides-and-resourcesguidelines-drawings-and-checklistsguidelines

                                                                            Council

                                                                            South-Eastern Growth Council WSUD guidelines ndash note that some individual Councils have their own addendumsMelbournePort PhilipNorth-West Growth Council WSUD guidelines - note that some individual Councils have their own addendumsGreater BendigoMilduraBallaratBaw BawWyndhamMoreland ndash tree pits and raingardens

                                                                            60

                                                                            IWM

                                                                            Example Council IWM strategiesMelbourneCaseyMonashKingston

                                                                            Resilient Melbourne ndash IWM information lsquohubrsquoClearwater ndash capacity building and case studiesMelbourne Water ndash funding opportunities for IWM projects

                                                                            Stormwater offset schemes

                                                                            KingstonGreater GeelongMelbourne Water ndash non scheme contributions

                                                                            Site management

                                                                            EPA guidelines- management of erosion and sediment

                                                                            Next steps and other stormwater initiatives

                                                                            Emma Stewart DELWP

                                                                            62

                                                                            Next steps

                                                                            bull Trainingbull The EPArsquos BPEM Reviewbull Offsets policybull Review of STORM bull Building controls

                                                                            63

                                                                            State Stormwater policies

                                                                            64

                                                                            Thank you

                                                                            • Slide Number 1
                                                                            • Slide Number 2
                                                                            • History of WSUD
                                                                            • History of WSUD
                                                                            • Transformational change in urban water
                                                                            • Inconsistencies and inequities in our approach to stormwater management
                                                                            • Slide Number 8
                                                                            • Terms of Reference
                                                                            • Improving Stormwater Management Advisory Committee
                                                                            • Wide consultation
                                                                            • Stakeholder feedback
                                                                            • Stakeholder feedback
                                                                            • Committee submitted its report in September 2018
                                                                            • Committee Recomendations
                                                                            • Planning reforms
                                                                            • Future policy directions
                                                                            • Supporting actions
                                                                            • Slide Number 19
                                                                            • Government response (to date)
                                                                            • Longer term recommendations
                                                                            • State-based planning requirements (lsquobeforersquo)
                                                                            • State-based planning requirements (lsquoafterrsquo)
                                                                            • Development types (volume)
                                                                            • Slide Number 25
                                                                            • Amendment VC154
                                                                            • Whatrsquos in
                                                                            • Slide Number 28
                                                                            • Key elements of clauses
                                                                            • Clause 5318 ndash subdivision
                                                                            • Clause 5318 ndash Buildings and works
                                                                            • Townhouses - Standard B9
                                                                            • Slide Number 33
                                                                            • Slide Number 34
                                                                            • Slide Number 35
                                                                            • Slide Number 36
                                                                            • Slide Number 37
                                                                            • Buildings and works - Site management standard
                                                                            • Site management
                                                                            • Planning Advisory Note No 75
                                                                            • Slide Number 41
                                                                            • Slide Number 42
                                                                            • Slide Number 43
                                                                            • Slide Number 44
                                                                            • Slide Number 45
                                                                            • Slide Number 46
                                                                            • Slide Number 47
                                                                            • Slide Number 48
                                                                            • Slide Number 49
                                                                            • Slide Number 50
                                                                            • Slide Number 51
                                                                            • Slide Number 52
                                                                            • Slide Number 53
                                                                            • Slide Number 54
                                                                            • Slide Number 55
                                                                            • Slide Number 56
                                                                            • Slide Number 57
                                                                            • Slide Number 58
                                                                            • Slide Number 59
                                                                            • Slide Number 60
                                                                            • Slide Number 61
                                                                            • Next steps
                                                                            • State Stormwater policies
                                                                            • Slide Number 64

                                                                              40

                                                                              Planning Advisory Note No 75

                                                                              Implications for industry

                                                                              Kate MatthewsStormwater Victoria

                                                                              1 Development proponents- Developers- Consultants (engineers stormwater specialists and planners)- Council (when developing public land lt$1 million)

                                                                              2 Development assessors- Council statutory planners- Council internal referrals (engineering assets ESD stormwater officers)

                                                                              3 Strategy- Council strategic planners

                                                                              4 Melbourne Water

                                                                              Whorsquos affected

                                                                              43

                                                                              What are the implications

                                                                              bull BPEM - Itrsquos not just subdivisions any more

                                                                              bull Cost ndash offset or assetbull Early planning and integration ndash more

                                                                              work up frontbull Not just engineeringbull Varying Council skills and experience

                                                                              Development Proponents

                                                                              44

                                                                              If already have a local policy for WSUDESD no real change

                                                                              If notbull Workload and resourcingbull Increased detail and technical

                                                                              contentbull Administrative arrangements ndash

                                                                              referrals permit conditions ndashmake sure you make 60 stat days

                                                                              bull Applicant pressure ndash what do you want

                                                                              bull Assets

                                                                              Development Assessors

                                                                              45

                                                                              bull Structure plans and rezoning ndashopportunities for localregional approach

                                                                              bull IWM and Stormwater Management Plans ndash opportunities for these to be implemented through the controls spatial opportunities

                                                                              bull Opportunities for development of Council offset strategies

                                                                              Strategy

                                                                              Offsets

                                                                              bull Developer enters into an agreement with relevant drainage authority to financially contribute to off-site stormwatermanagement in lieu of providing on-site treatment

                                                                              bull Already available for residential subdivisions in Melbourne (Clause 56) through MWCs Stormwater Quality Offset scheme

                                                                              What are stormwater quality offsets

                                                                              X Not drainage contributions (MWC drainage scheme)

                                                                              X Not development contributions (DCPICP)

                                                                              47

                                                                              When to use

                                                                              bull Not in MW DSS or growth area where therersquos an existing framework for funding SW treatment

                                                                              bull Onsite treatment not practical or desirable

                                                                              bull To fund planned localregional stormwater treatment works in that catchment via an existing offset scheme

                                                                              bull Council and developer both agree to it

                                                                              48

                                                                              OffsetsExample ndash Kingston Offset Scheme

                                                                              Asset ownership and maintenance

                                                                              bull Whorsquos going to own itbull Whorsquos going to maintain itbull How do you maintain itbull How much will it cost

                                                                              bull Where is itbull Is maintenance burden

                                                                              practical for likely future owners

                                                                              bull Whorsquos going to monitor compliance and how

                                                                              The detail is in the permit conditions

                                                                              Application requirements

                                                                              ldquoAn application must be accompanied by details of the proposed stormwater management system including drainage works and retention detention and discharges of stormwater to the drainage systemrdquo ndash Clause 5318

                                                                              What does the planning scheme require

                                                                              But alsohellipNeed to provide sufficient information to Council which demonstrates that you comply and how you comply with all the other standards ndash eg urban coolinghabitatetc BPEM site management pollutant control infiltration (as relevant to development type

                                                                              51

                                                                              1 PlansWhat are you doing where is it going and does it fit

                                                                              2 ModellingDo you (or can you) meet BPEM requirements

                                                                              3 Written response to standardsHow does your proposal comply with the requirements

                                                                              52

                                                                              Application

                                                                              bull Site plan ndash show all assetsWSUD treatments and any IWM features on the site layout plan with everything else

                                                                              bull Landscape plan ndash if planting design passive irrigation etc forms part of response to requirements show

                                                                              bull Site management plan (depending on Council)

                                                                              bull Separate WSUDIWM plan showing all features on a stripped back background

                                                                              bull Concept WSUD asset design ndash larger assets only (wetlands bioretention basins sed basin etc) ndash sufficient design detail to confirm spatial requirements

                                                                              PlansPermit conditions

                                                                              bull Detailed engineering design bull Site Management Plan (final)bull Asset maintenance plan (final)bull Handover arrangements (if public)

                                                                              54

                                                                              STORM ndash Online toolbull Print out of STORM reportbull Make sure meets 100 or

                                                                              morebull Make sure report inputs and

                                                                              results match plan

                                                                              Modelling - SWQ

                                                                              MUSIC ndash Proprietary softwarebull Provide a copy of the model filebull Print out the modelling resultsbull Provide summary of your model

                                                                              inputs for each treatment train (iecatchment size impervious treatment area etc)

                                                                              bull Provide a print out of the model schematic

                                                                              Bonus points bull Provide details of model

                                                                              parametersbull Provide results of MUSIC auditor

                                                                              run (if using Melbourne Water MUSIC Guidelines)

                                                                              56

                                                                              Assessment against standards

                                                                              bull Say what you have done (or will do) to meet each standardbull Donrsquot forget (if WSUD) details of maintenance and asset

                                                                              ownershipbull Where applicable be explicit why yoursquove chosen (or not chosen) to

                                                                              respond the way you have Egbull Opportunitiesbull Site constraintsbull Practicaloperational issues bull Brief dot point summary of options analysis if complex

                                                                              bull Make sure if it doesnrsquot meet the standard it meets the objectivebull Make sure shown on plan and consistent with modelling and rest of

                                                                              documentation

                                                                              57

                                                                              Resources

                                                                              Local stormwaterWSUD policiesBaysideKingstonCaseyMonashMelbourneYarraMoonee ValleyPort PhilipStonningtonHumeCampaspeBass Coast

                                                                              Local ESD (including IWM) policies Greater BendigoGreater DandenongHobsons BayWhittleseaWyndhamWhitehorseManninghamMorelandDarebinBanyuleKnoxBrimbank

                                                                              Council planning resources

                                                                              Application resources ndashexamplesDELWP Practice Note ndashformal guide to the new controlsMoreland ndash application checklists and example plans for a variety of residential developmentsPort Philip ndash compliance guidelines checklist and examplesMoonee Valley ndash checklists and example plans including site management plans Greater Bendigo ndash WSUD kitBayside ndash application guidelines and example plans

                                                                              59

                                                                              Technical guidelines (modelling design construction)

                                                                              Melbourne Water

                                                                              STORM calculatorMUSIC auditor - lsquohow torsquo video here

                                                                              Melbourne Water technical guidelines page- WSUD asset life cycle costings and model maintenance guidelines- MUSIC guidelines- Stormwater harvesting guidelines- WSUD life cycle costings and

                                                                              maintenance guidelines- Design and construction guidelines

                                                                              for variety of assetshttpswwwmelbournewatercomauplanning-and-buildingdeveloper-guides-and-resourcesguidelines-drawings-and-checklistsguidelines

                                                                              Council

                                                                              South-Eastern Growth Council WSUD guidelines ndash note that some individual Councils have their own addendumsMelbournePort PhilipNorth-West Growth Council WSUD guidelines - note that some individual Councils have their own addendumsGreater BendigoMilduraBallaratBaw BawWyndhamMoreland ndash tree pits and raingardens

                                                                              60

                                                                              IWM

                                                                              Example Council IWM strategiesMelbourneCaseyMonashKingston

                                                                              Resilient Melbourne ndash IWM information lsquohubrsquoClearwater ndash capacity building and case studiesMelbourne Water ndash funding opportunities for IWM projects

                                                                              Stormwater offset schemes

                                                                              KingstonGreater GeelongMelbourne Water ndash non scheme contributions

                                                                              Site management

                                                                              EPA guidelines- management of erosion and sediment

                                                                              Next steps and other stormwater initiatives

                                                                              Emma Stewart DELWP

                                                                              62

                                                                              Next steps

                                                                              bull Trainingbull The EPArsquos BPEM Reviewbull Offsets policybull Review of STORM bull Building controls

                                                                              63

                                                                              State Stormwater policies

                                                                              64

                                                                              Thank you

                                                                              • Slide Number 1
                                                                              • Slide Number 2
                                                                              • History of WSUD
                                                                              • History of WSUD
                                                                              • Transformational change in urban water
                                                                              • Inconsistencies and inequities in our approach to stormwater management
                                                                              • Slide Number 8
                                                                              • Terms of Reference
                                                                              • Improving Stormwater Management Advisory Committee
                                                                              • Wide consultation
                                                                              • Stakeholder feedback
                                                                              • Stakeholder feedback
                                                                              • Committee submitted its report in September 2018
                                                                              • Committee Recomendations
                                                                              • Planning reforms
                                                                              • Future policy directions
                                                                              • Supporting actions
                                                                              • Slide Number 19
                                                                              • Government response (to date)
                                                                              • Longer term recommendations
                                                                              • State-based planning requirements (lsquobeforersquo)
                                                                              • State-based planning requirements (lsquoafterrsquo)
                                                                              • Development types (volume)
                                                                              • Slide Number 25
                                                                              • Amendment VC154
                                                                              • Whatrsquos in
                                                                              • Slide Number 28
                                                                              • Key elements of clauses
                                                                              • Clause 5318 ndash subdivision
                                                                              • Clause 5318 ndash Buildings and works
                                                                              • Townhouses - Standard B9
                                                                              • Slide Number 33
                                                                              • Slide Number 34
                                                                              • Slide Number 35
                                                                              • Slide Number 36
                                                                              • Slide Number 37
                                                                              • Buildings and works - Site management standard
                                                                              • Site management
                                                                              • Planning Advisory Note No 75
                                                                              • Slide Number 41
                                                                              • Slide Number 42
                                                                              • Slide Number 43
                                                                              • Slide Number 44
                                                                              • Slide Number 45
                                                                              • Slide Number 46
                                                                              • Slide Number 47
                                                                              • Slide Number 48
                                                                              • Slide Number 49
                                                                              • Slide Number 50
                                                                              • Slide Number 51
                                                                              • Slide Number 52
                                                                              • Slide Number 53
                                                                              • Slide Number 54
                                                                              • Slide Number 55
                                                                              • Slide Number 56
                                                                              • Slide Number 57
                                                                              • Slide Number 58
                                                                              • Slide Number 59
                                                                              • Slide Number 60
                                                                              • Slide Number 61
                                                                              • Next steps
                                                                              • State Stormwater policies
                                                                              • Slide Number 64

                                                                                Implications for industry

                                                                                Kate MatthewsStormwater Victoria

                                                                                1 Development proponents- Developers- Consultants (engineers stormwater specialists and planners)- Council (when developing public land lt$1 million)

                                                                                2 Development assessors- Council statutory planners- Council internal referrals (engineering assets ESD stormwater officers)

                                                                                3 Strategy- Council strategic planners

                                                                                4 Melbourne Water

                                                                                Whorsquos affected

                                                                                43

                                                                                What are the implications

                                                                                bull BPEM - Itrsquos not just subdivisions any more

                                                                                bull Cost ndash offset or assetbull Early planning and integration ndash more

                                                                                work up frontbull Not just engineeringbull Varying Council skills and experience

                                                                                Development Proponents

                                                                                44

                                                                                If already have a local policy for WSUDESD no real change

                                                                                If notbull Workload and resourcingbull Increased detail and technical

                                                                                contentbull Administrative arrangements ndash

                                                                                referrals permit conditions ndashmake sure you make 60 stat days

                                                                                bull Applicant pressure ndash what do you want

                                                                                bull Assets

                                                                                Development Assessors

                                                                                45

                                                                                bull Structure plans and rezoning ndashopportunities for localregional approach

                                                                                bull IWM and Stormwater Management Plans ndash opportunities for these to be implemented through the controls spatial opportunities

                                                                                bull Opportunities for development of Council offset strategies

                                                                                Strategy

                                                                                Offsets

                                                                                bull Developer enters into an agreement with relevant drainage authority to financially contribute to off-site stormwatermanagement in lieu of providing on-site treatment

                                                                                bull Already available for residential subdivisions in Melbourne (Clause 56) through MWCs Stormwater Quality Offset scheme

                                                                                What are stormwater quality offsets

                                                                                X Not drainage contributions (MWC drainage scheme)

                                                                                X Not development contributions (DCPICP)

                                                                                47

                                                                                When to use

                                                                                bull Not in MW DSS or growth area where therersquos an existing framework for funding SW treatment

                                                                                bull Onsite treatment not practical or desirable

                                                                                bull To fund planned localregional stormwater treatment works in that catchment via an existing offset scheme

                                                                                bull Council and developer both agree to it

                                                                                48

                                                                                OffsetsExample ndash Kingston Offset Scheme

                                                                                Asset ownership and maintenance

                                                                                bull Whorsquos going to own itbull Whorsquos going to maintain itbull How do you maintain itbull How much will it cost

                                                                                bull Where is itbull Is maintenance burden

                                                                                practical for likely future owners

                                                                                bull Whorsquos going to monitor compliance and how

                                                                                The detail is in the permit conditions

                                                                                Application requirements

                                                                                ldquoAn application must be accompanied by details of the proposed stormwater management system including drainage works and retention detention and discharges of stormwater to the drainage systemrdquo ndash Clause 5318

                                                                                What does the planning scheme require

                                                                                But alsohellipNeed to provide sufficient information to Council which demonstrates that you comply and how you comply with all the other standards ndash eg urban coolinghabitatetc BPEM site management pollutant control infiltration (as relevant to development type

                                                                                51

                                                                                1 PlansWhat are you doing where is it going and does it fit

                                                                                2 ModellingDo you (or can you) meet BPEM requirements

                                                                                3 Written response to standardsHow does your proposal comply with the requirements

                                                                                52

                                                                                Application

                                                                                bull Site plan ndash show all assetsWSUD treatments and any IWM features on the site layout plan with everything else

                                                                                bull Landscape plan ndash if planting design passive irrigation etc forms part of response to requirements show

                                                                                bull Site management plan (depending on Council)

                                                                                bull Separate WSUDIWM plan showing all features on a stripped back background

                                                                                bull Concept WSUD asset design ndash larger assets only (wetlands bioretention basins sed basin etc) ndash sufficient design detail to confirm spatial requirements

                                                                                PlansPermit conditions

                                                                                bull Detailed engineering design bull Site Management Plan (final)bull Asset maintenance plan (final)bull Handover arrangements (if public)

                                                                                54

                                                                                STORM ndash Online toolbull Print out of STORM reportbull Make sure meets 100 or

                                                                                morebull Make sure report inputs and

                                                                                results match plan

                                                                                Modelling - SWQ

                                                                                MUSIC ndash Proprietary softwarebull Provide a copy of the model filebull Print out the modelling resultsbull Provide summary of your model

                                                                                inputs for each treatment train (iecatchment size impervious treatment area etc)

                                                                                bull Provide a print out of the model schematic

                                                                                Bonus points bull Provide details of model

                                                                                parametersbull Provide results of MUSIC auditor

                                                                                run (if using Melbourne Water MUSIC Guidelines)

                                                                                56

                                                                                Assessment against standards

                                                                                bull Say what you have done (or will do) to meet each standardbull Donrsquot forget (if WSUD) details of maintenance and asset

                                                                                ownershipbull Where applicable be explicit why yoursquove chosen (or not chosen) to

                                                                                respond the way you have Egbull Opportunitiesbull Site constraintsbull Practicaloperational issues bull Brief dot point summary of options analysis if complex

                                                                                bull Make sure if it doesnrsquot meet the standard it meets the objectivebull Make sure shown on plan and consistent with modelling and rest of

                                                                                documentation

                                                                                57

                                                                                Resources

                                                                                Local stormwaterWSUD policiesBaysideKingstonCaseyMonashMelbourneYarraMoonee ValleyPort PhilipStonningtonHumeCampaspeBass Coast

                                                                                Local ESD (including IWM) policies Greater BendigoGreater DandenongHobsons BayWhittleseaWyndhamWhitehorseManninghamMorelandDarebinBanyuleKnoxBrimbank

                                                                                Council planning resources

                                                                                Application resources ndashexamplesDELWP Practice Note ndashformal guide to the new controlsMoreland ndash application checklists and example plans for a variety of residential developmentsPort Philip ndash compliance guidelines checklist and examplesMoonee Valley ndash checklists and example plans including site management plans Greater Bendigo ndash WSUD kitBayside ndash application guidelines and example plans

                                                                                59

                                                                                Technical guidelines (modelling design construction)

                                                                                Melbourne Water

                                                                                STORM calculatorMUSIC auditor - lsquohow torsquo video here

                                                                                Melbourne Water technical guidelines page- WSUD asset life cycle costings and model maintenance guidelines- MUSIC guidelines- Stormwater harvesting guidelines- WSUD life cycle costings and

                                                                                maintenance guidelines- Design and construction guidelines

                                                                                for variety of assetshttpswwwmelbournewatercomauplanning-and-buildingdeveloper-guides-and-resourcesguidelines-drawings-and-checklistsguidelines

                                                                                Council

                                                                                South-Eastern Growth Council WSUD guidelines ndash note that some individual Councils have their own addendumsMelbournePort PhilipNorth-West Growth Council WSUD guidelines - note that some individual Councils have their own addendumsGreater BendigoMilduraBallaratBaw BawWyndhamMoreland ndash tree pits and raingardens

                                                                                60

                                                                                IWM

                                                                                Example Council IWM strategiesMelbourneCaseyMonashKingston

                                                                                Resilient Melbourne ndash IWM information lsquohubrsquoClearwater ndash capacity building and case studiesMelbourne Water ndash funding opportunities for IWM projects

                                                                                Stormwater offset schemes

                                                                                KingstonGreater GeelongMelbourne Water ndash non scheme contributions

                                                                                Site management

                                                                                EPA guidelines- management of erosion and sediment

                                                                                Next steps and other stormwater initiatives

                                                                                Emma Stewart DELWP

                                                                                62

                                                                                Next steps

                                                                                bull Trainingbull The EPArsquos BPEM Reviewbull Offsets policybull Review of STORM bull Building controls

                                                                                63

                                                                                State Stormwater policies

                                                                                64

                                                                                Thank you

                                                                                • Slide Number 1
                                                                                • Slide Number 2
                                                                                • History of WSUD
                                                                                • History of WSUD
                                                                                • Transformational change in urban water
                                                                                • Inconsistencies and inequities in our approach to stormwater management
                                                                                • Slide Number 8
                                                                                • Terms of Reference
                                                                                • Improving Stormwater Management Advisory Committee
                                                                                • Wide consultation
                                                                                • Stakeholder feedback
                                                                                • Stakeholder feedback
                                                                                • Committee submitted its report in September 2018
                                                                                • Committee Recomendations
                                                                                • Planning reforms
                                                                                • Future policy directions
                                                                                • Supporting actions
                                                                                • Slide Number 19
                                                                                • Government response (to date)
                                                                                • Longer term recommendations
                                                                                • State-based planning requirements (lsquobeforersquo)
                                                                                • State-based planning requirements (lsquoafterrsquo)
                                                                                • Development types (volume)
                                                                                • Slide Number 25
                                                                                • Amendment VC154
                                                                                • Whatrsquos in
                                                                                • Slide Number 28
                                                                                • Key elements of clauses
                                                                                • Clause 5318 ndash subdivision
                                                                                • Clause 5318 ndash Buildings and works
                                                                                • Townhouses - Standard B9
                                                                                • Slide Number 33
                                                                                • Slide Number 34
                                                                                • Slide Number 35
                                                                                • Slide Number 36
                                                                                • Slide Number 37
                                                                                • Buildings and works - Site management standard
                                                                                • Site management
                                                                                • Planning Advisory Note No 75
                                                                                • Slide Number 41
                                                                                • Slide Number 42
                                                                                • Slide Number 43
                                                                                • Slide Number 44
                                                                                • Slide Number 45
                                                                                • Slide Number 46
                                                                                • Slide Number 47
                                                                                • Slide Number 48
                                                                                • Slide Number 49
                                                                                • Slide Number 50
                                                                                • Slide Number 51
                                                                                • Slide Number 52
                                                                                • Slide Number 53
                                                                                • Slide Number 54
                                                                                • Slide Number 55
                                                                                • Slide Number 56
                                                                                • Slide Number 57
                                                                                • Slide Number 58
                                                                                • Slide Number 59
                                                                                • Slide Number 60
                                                                                • Slide Number 61
                                                                                • Next steps
                                                                                • State Stormwater policies
                                                                                • Slide Number 64

                                                                                  1 Development proponents- Developers- Consultants (engineers stormwater specialists and planners)- Council (when developing public land lt$1 million)

                                                                                  2 Development assessors- Council statutory planners- Council internal referrals (engineering assets ESD stormwater officers)

                                                                                  3 Strategy- Council strategic planners

                                                                                  4 Melbourne Water

                                                                                  Whorsquos affected

                                                                                  43

                                                                                  What are the implications

                                                                                  bull BPEM - Itrsquos not just subdivisions any more

                                                                                  bull Cost ndash offset or assetbull Early planning and integration ndash more

                                                                                  work up frontbull Not just engineeringbull Varying Council skills and experience

                                                                                  Development Proponents

                                                                                  44

                                                                                  If already have a local policy for WSUDESD no real change

                                                                                  If notbull Workload and resourcingbull Increased detail and technical

                                                                                  contentbull Administrative arrangements ndash

                                                                                  referrals permit conditions ndashmake sure you make 60 stat days

                                                                                  bull Applicant pressure ndash what do you want

                                                                                  bull Assets

                                                                                  Development Assessors

                                                                                  45

                                                                                  bull Structure plans and rezoning ndashopportunities for localregional approach

                                                                                  bull IWM and Stormwater Management Plans ndash opportunities for these to be implemented through the controls spatial opportunities

                                                                                  bull Opportunities for development of Council offset strategies

                                                                                  Strategy

                                                                                  Offsets

                                                                                  bull Developer enters into an agreement with relevant drainage authority to financially contribute to off-site stormwatermanagement in lieu of providing on-site treatment

                                                                                  bull Already available for residential subdivisions in Melbourne (Clause 56) through MWCs Stormwater Quality Offset scheme

                                                                                  What are stormwater quality offsets

                                                                                  X Not drainage contributions (MWC drainage scheme)

                                                                                  X Not development contributions (DCPICP)

                                                                                  47

                                                                                  When to use

                                                                                  bull Not in MW DSS or growth area where therersquos an existing framework for funding SW treatment

                                                                                  bull Onsite treatment not practical or desirable

                                                                                  bull To fund planned localregional stormwater treatment works in that catchment via an existing offset scheme

                                                                                  bull Council and developer both agree to it

                                                                                  48

                                                                                  OffsetsExample ndash Kingston Offset Scheme

                                                                                  Asset ownership and maintenance

                                                                                  bull Whorsquos going to own itbull Whorsquos going to maintain itbull How do you maintain itbull How much will it cost

                                                                                  bull Where is itbull Is maintenance burden

                                                                                  practical for likely future owners

                                                                                  bull Whorsquos going to monitor compliance and how

                                                                                  The detail is in the permit conditions

                                                                                  Application requirements

                                                                                  ldquoAn application must be accompanied by details of the proposed stormwater management system including drainage works and retention detention and discharges of stormwater to the drainage systemrdquo ndash Clause 5318

                                                                                  What does the planning scheme require

                                                                                  But alsohellipNeed to provide sufficient information to Council which demonstrates that you comply and how you comply with all the other standards ndash eg urban coolinghabitatetc BPEM site management pollutant control infiltration (as relevant to development type

                                                                                  51

                                                                                  1 PlansWhat are you doing where is it going and does it fit

                                                                                  2 ModellingDo you (or can you) meet BPEM requirements

                                                                                  3 Written response to standardsHow does your proposal comply with the requirements

                                                                                  52

                                                                                  Application

                                                                                  bull Site plan ndash show all assetsWSUD treatments and any IWM features on the site layout plan with everything else

                                                                                  bull Landscape plan ndash if planting design passive irrigation etc forms part of response to requirements show

                                                                                  bull Site management plan (depending on Council)

                                                                                  bull Separate WSUDIWM plan showing all features on a stripped back background

                                                                                  bull Concept WSUD asset design ndash larger assets only (wetlands bioretention basins sed basin etc) ndash sufficient design detail to confirm spatial requirements

                                                                                  PlansPermit conditions

                                                                                  bull Detailed engineering design bull Site Management Plan (final)bull Asset maintenance plan (final)bull Handover arrangements (if public)

                                                                                  54

                                                                                  STORM ndash Online toolbull Print out of STORM reportbull Make sure meets 100 or

                                                                                  morebull Make sure report inputs and

                                                                                  results match plan

                                                                                  Modelling - SWQ

                                                                                  MUSIC ndash Proprietary softwarebull Provide a copy of the model filebull Print out the modelling resultsbull Provide summary of your model

                                                                                  inputs for each treatment train (iecatchment size impervious treatment area etc)

                                                                                  bull Provide a print out of the model schematic

                                                                                  Bonus points bull Provide details of model

                                                                                  parametersbull Provide results of MUSIC auditor

                                                                                  run (if using Melbourne Water MUSIC Guidelines)

                                                                                  56

                                                                                  Assessment against standards

                                                                                  bull Say what you have done (or will do) to meet each standardbull Donrsquot forget (if WSUD) details of maintenance and asset

                                                                                  ownershipbull Where applicable be explicit why yoursquove chosen (or not chosen) to

                                                                                  respond the way you have Egbull Opportunitiesbull Site constraintsbull Practicaloperational issues bull Brief dot point summary of options analysis if complex

                                                                                  bull Make sure if it doesnrsquot meet the standard it meets the objectivebull Make sure shown on plan and consistent with modelling and rest of

                                                                                  documentation

                                                                                  57

                                                                                  Resources

                                                                                  Local stormwaterWSUD policiesBaysideKingstonCaseyMonashMelbourneYarraMoonee ValleyPort PhilipStonningtonHumeCampaspeBass Coast

                                                                                  Local ESD (including IWM) policies Greater BendigoGreater DandenongHobsons BayWhittleseaWyndhamWhitehorseManninghamMorelandDarebinBanyuleKnoxBrimbank

                                                                                  Council planning resources

                                                                                  Application resources ndashexamplesDELWP Practice Note ndashformal guide to the new controlsMoreland ndash application checklists and example plans for a variety of residential developmentsPort Philip ndash compliance guidelines checklist and examplesMoonee Valley ndash checklists and example plans including site management plans Greater Bendigo ndash WSUD kitBayside ndash application guidelines and example plans

                                                                                  59

                                                                                  Technical guidelines (modelling design construction)

                                                                                  Melbourne Water

                                                                                  STORM calculatorMUSIC auditor - lsquohow torsquo video here

                                                                                  Melbourne Water technical guidelines page- WSUD asset life cycle costings and model maintenance guidelines- MUSIC guidelines- Stormwater harvesting guidelines- WSUD life cycle costings and

                                                                                  maintenance guidelines- Design and construction guidelines

                                                                                  for variety of assetshttpswwwmelbournewatercomauplanning-and-buildingdeveloper-guides-and-resourcesguidelines-drawings-and-checklistsguidelines

                                                                                  Council

                                                                                  South-Eastern Growth Council WSUD guidelines ndash note that some individual Councils have their own addendumsMelbournePort PhilipNorth-West Growth Council WSUD guidelines - note that some individual Councils have their own addendumsGreater BendigoMilduraBallaratBaw BawWyndhamMoreland ndash tree pits and raingardens

                                                                                  60

                                                                                  IWM

                                                                                  Example Council IWM strategiesMelbourneCaseyMonashKingston

                                                                                  Resilient Melbourne ndash IWM information lsquohubrsquoClearwater ndash capacity building and case studiesMelbourne Water ndash funding opportunities for IWM projects

                                                                                  Stormwater offset schemes

                                                                                  KingstonGreater GeelongMelbourne Water ndash non scheme contributions

                                                                                  Site management

                                                                                  EPA guidelines- management of erosion and sediment

                                                                                  Next steps and other stormwater initiatives

                                                                                  Emma Stewart DELWP

                                                                                  62

                                                                                  Next steps

                                                                                  bull Trainingbull The EPArsquos BPEM Reviewbull Offsets policybull Review of STORM bull Building controls

                                                                                  63

                                                                                  State Stormwater policies

                                                                                  64

                                                                                  Thank you

                                                                                  • Slide Number 1
                                                                                  • Slide Number 2
                                                                                  • History of WSUD
                                                                                  • History of WSUD
                                                                                  • Transformational change in urban water
                                                                                  • Inconsistencies and inequities in our approach to stormwater management
                                                                                  • Slide Number 8
                                                                                  • Terms of Reference
                                                                                  • Improving Stormwater Management Advisory Committee
                                                                                  • Wide consultation
                                                                                  • Stakeholder feedback
                                                                                  • Stakeholder feedback
                                                                                  • Committee submitted its report in September 2018
                                                                                  • Committee Recomendations
                                                                                  • Planning reforms
                                                                                  • Future policy directions
                                                                                  • Supporting actions
                                                                                  • Slide Number 19
                                                                                  • Government response (to date)
                                                                                  • Longer term recommendations
                                                                                  • State-based planning requirements (lsquobeforersquo)
                                                                                  • State-based planning requirements (lsquoafterrsquo)
                                                                                  • Development types (volume)
                                                                                  • Slide Number 25
                                                                                  • Amendment VC154
                                                                                  • Whatrsquos in
                                                                                  • Slide Number 28
                                                                                  • Key elements of clauses
                                                                                  • Clause 5318 ndash subdivision
                                                                                  • Clause 5318 ndash Buildings and works
                                                                                  • Townhouses - Standard B9
                                                                                  • Slide Number 33
                                                                                  • Slide Number 34
                                                                                  • Slide Number 35
                                                                                  • Slide Number 36
                                                                                  • Slide Number 37
                                                                                  • Buildings and works - Site management standard
                                                                                  • Site management
                                                                                  • Planning Advisory Note No 75
                                                                                  • Slide Number 41
                                                                                  • Slide Number 42
                                                                                  • Slide Number 43
                                                                                  • Slide Number 44
                                                                                  • Slide Number 45
                                                                                  • Slide Number 46
                                                                                  • Slide Number 47
                                                                                  • Slide Number 48
                                                                                  • Slide Number 49
                                                                                  • Slide Number 50
                                                                                  • Slide Number 51
                                                                                  • Slide Number 52
                                                                                  • Slide Number 53
                                                                                  • Slide Number 54
                                                                                  • Slide Number 55
                                                                                  • Slide Number 56
                                                                                  • Slide Number 57
                                                                                  • Slide Number 58
                                                                                  • Slide Number 59
                                                                                  • Slide Number 60
                                                                                  • Slide Number 61
                                                                                  • Next steps
                                                                                  • State Stormwater policies
                                                                                  • Slide Number 64

                                                                                    43

                                                                                    What are the implications

                                                                                    bull BPEM - Itrsquos not just subdivisions any more

                                                                                    bull Cost ndash offset or assetbull Early planning and integration ndash more

                                                                                    work up frontbull Not just engineeringbull Varying Council skills and experience

                                                                                    Development Proponents

                                                                                    44

                                                                                    If already have a local policy for WSUDESD no real change

                                                                                    If notbull Workload and resourcingbull Increased detail and technical

                                                                                    contentbull Administrative arrangements ndash

                                                                                    referrals permit conditions ndashmake sure you make 60 stat days

                                                                                    bull Applicant pressure ndash what do you want

                                                                                    bull Assets

                                                                                    Development Assessors

                                                                                    45

                                                                                    bull Structure plans and rezoning ndashopportunities for localregional approach

                                                                                    bull IWM and Stormwater Management Plans ndash opportunities for these to be implemented through the controls spatial opportunities

                                                                                    bull Opportunities for development of Council offset strategies

                                                                                    Strategy

                                                                                    Offsets

                                                                                    bull Developer enters into an agreement with relevant drainage authority to financially contribute to off-site stormwatermanagement in lieu of providing on-site treatment

                                                                                    bull Already available for residential subdivisions in Melbourne (Clause 56) through MWCs Stormwater Quality Offset scheme

                                                                                    What are stormwater quality offsets

                                                                                    X Not drainage contributions (MWC drainage scheme)

                                                                                    X Not development contributions (DCPICP)

                                                                                    47

                                                                                    When to use

                                                                                    bull Not in MW DSS or growth area where therersquos an existing framework for funding SW treatment

                                                                                    bull Onsite treatment not practical or desirable

                                                                                    bull To fund planned localregional stormwater treatment works in that catchment via an existing offset scheme

                                                                                    bull Council and developer both agree to it

                                                                                    48

                                                                                    OffsetsExample ndash Kingston Offset Scheme

                                                                                    Asset ownership and maintenance

                                                                                    bull Whorsquos going to own itbull Whorsquos going to maintain itbull How do you maintain itbull How much will it cost

                                                                                    bull Where is itbull Is maintenance burden

                                                                                    practical for likely future owners

                                                                                    bull Whorsquos going to monitor compliance and how

                                                                                    The detail is in the permit conditions

                                                                                    Application requirements

                                                                                    ldquoAn application must be accompanied by details of the proposed stormwater management system including drainage works and retention detention and discharges of stormwater to the drainage systemrdquo ndash Clause 5318

                                                                                    What does the planning scheme require

                                                                                    But alsohellipNeed to provide sufficient information to Council which demonstrates that you comply and how you comply with all the other standards ndash eg urban coolinghabitatetc BPEM site management pollutant control infiltration (as relevant to development type

                                                                                    51

                                                                                    1 PlansWhat are you doing where is it going and does it fit

                                                                                    2 ModellingDo you (or can you) meet BPEM requirements

                                                                                    3 Written response to standardsHow does your proposal comply with the requirements

                                                                                    52

                                                                                    Application

                                                                                    bull Site plan ndash show all assetsWSUD treatments and any IWM features on the site layout plan with everything else

                                                                                    bull Landscape plan ndash if planting design passive irrigation etc forms part of response to requirements show

                                                                                    bull Site management plan (depending on Council)

                                                                                    bull Separate WSUDIWM plan showing all features on a stripped back background

                                                                                    bull Concept WSUD asset design ndash larger assets only (wetlands bioretention basins sed basin etc) ndash sufficient design detail to confirm spatial requirements

                                                                                    PlansPermit conditions

                                                                                    bull Detailed engineering design bull Site Management Plan (final)bull Asset maintenance plan (final)bull Handover arrangements (if public)

                                                                                    54

                                                                                    STORM ndash Online toolbull Print out of STORM reportbull Make sure meets 100 or

                                                                                    morebull Make sure report inputs and

                                                                                    results match plan

                                                                                    Modelling - SWQ

                                                                                    MUSIC ndash Proprietary softwarebull Provide a copy of the model filebull Print out the modelling resultsbull Provide summary of your model

                                                                                    inputs for each treatment train (iecatchment size impervious treatment area etc)

                                                                                    bull Provide a print out of the model schematic

                                                                                    Bonus points bull Provide details of model

                                                                                    parametersbull Provide results of MUSIC auditor

                                                                                    run (if using Melbourne Water MUSIC Guidelines)

                                                                                    56

                                                                                    Assessment against standards

                                                                                    bull Say what you have done (or will do) to meet each standardbull Donrsquot forget (if WSUD) details of maintenance and asset

                                                                                    ownershipbull Where applicable be explicit why yoursquove chosen (or not chosen) to

                                                                                    respond the way you have Egbull Opportunitiesbull Site constraintsbull Practicaloperational issues bull Brief dot point summary of options analysis if complex

                                                                                    bull Make sure if it doesnrsquot meet the standard it meets the objectivebull Make sure shown on plan and consistent with modelling and rest of

                                                                                    documentation

                                                                                    57

                                                                                    Resources

                                                                                    Local stormwaterWSUD policiesBaysideKingstonCaseyMonashMelbourneYarraMoonee ValleyPort PhilipStonningtonHumeCampaspeBass Coast

                                                                                    Local ESD (including IWM) policies Greater BendigoGreater DandenongHobsons BayWhittleseaWyndhamWhitehorseManninghamMorelandDarebinBanyuleKnoxBrimbank

                                                                                    Council planning resources

                                                                                    Application resources ndashexamplesDELWP Practice Note ndashformal guide to the new controlsMoreland ndash application checklists and example plans for a variety of residential developmentsPort Philip ndash compliance guidelines checklist and examplesMoonee Valley ndash checklists and example plans including site management plans Greater Bendigo ndash WSUD kitBayside ndash application guidelines and example plans

                                                                                    59

                                                                                    Technical guidelines (modelling design construction)

                                                                                    Melbourne Water

                                                                                    STORM calculatorMUSIC auditor - lsquohow torsquo video here

                                                                                    Melbourne Water technical guidelines page- WSUD asset life cycle costings and model maintenance guidelines- MUSIC guidelines- Stormwater harvesting guidelines- WSUD life cycle costings and

                                                                                    maintenance guidelines- Design and construction guidelines

                                                                                    for variety of assetshttpswwwmelbournewatercomauplanning-and-buildingdeveloper-guides-and-resourcesguidelines-drawings-and-checklistsguidelines

                                                                                    Council

                                                                                    South-Eastern Growth Council WSUD guidelines ndash note that some individual Councils have their own addendumsMelbournePort PhilipNorth-West Growth Council WSUD guidelines - note that some individual Councils have their own addendumsGreater BendigoMilduraBallaratBaw BawWyndhamMoreland ndash tree pits and raingardens

                                                                                    60

                                                                                    IWM

                                                                                    Example Council IWM strategiesMelbourneCaseyMonashKingston

                                                                                    Resilient Melbourne ndash IWM information lsquohubrsquoClearwater ndash capacity building and case studiesMelbourne Water ndash funding opportunities for IWM projects

                                                                                    Stormwater offset schemes

                                                                                    KingstonGreater GeelongMelbourne Water ndash non scheme contributions

                                                                                    Site management

                                                                                    EPA guidelines- management of erosion and sediment

                                                                                    Next steps and other stormwater initiatives

                                                                                    Emma Stewart DELWP

                                                                                    62

                                                                                    Next steps

                                                                                    bull Trainingbull The EPArsquos BPEM Reviewbull Offsets policybull Review of STORM bull Building controls

                                                                                    63

                                                                                    State Stormwater policies

                                                                                    64

                                                                                    Thank you

                                                                                    • Slide Number 1
                                                                                    • Slide Number 2
                                                                                    • History of WSUD
                                                                                    • History of WSUD
                                                                                    • Transformational change in urban water
                                                                                    • Inconsistencies and inequities in our approach to stormwater management
                                                                                    • Slide Number 8
                                                                                    • Terms of Reference
                                                                                    • Improving Stormwater Management Advisory Committee
                                                                                    • Wide consultation
                                                                                    • Stakeholder feedback
                                                                                    • Stakeholder feedback
                                                                                    • Committee submitted its report in September 2018
                                                                                    • Committee Recomendations
                                                                                    • Planning reforms
                                                                                    • Future policy directions
                                                                                    • Supporting actions
                                                                                    • Slide Number 19
                                                                                    • Government response (to date)
                                                                                    • Longer term recommendations
                                                                                    • State-based planning requirements (lsquobeforersquo)
                                                                                    • State-based planning requirements (lsquoafterrsquo)
                                                                                    • Development types (volume)
                                                                                    • Slide Number 25
                                                                                    • Amendment VC154
                                                                                    • Whatrsquos in
                                                                                    • Slide Number 28
                                                                                    • Key elements of clauses
                                                                                    • Clause 5318 ndash subdivision
                                                                                    • Clause 5318 ndash Buildings and works
                                                                                    • Townhouses - Standard B9
                                                                                    • Slide Number 33
                                                                                    • Slide Number 34
                                                                                    • Slide Number 35
                                                                                    • Slide Number 36
                                                                                    • Slide Number 37
                                                                                    • Buildings and works - Site management standard
                                                                                    • Site management
                                                                                    • Planning Advisory Note No 75
                                                                                    • Slide Number 41
                                                                                    • Slide Number 42
                                                                                    • Slide Number 43
                                                                                    • Slide Number 44
                                                                                    • Slide Number 45
                                                                                    • Slide Number 46
                                                                                    • Slide Number 47
                                                                                    • Slide Number 48
                                                                                    • Slide Number 49
                                                                                    • Slide Number 50
                                                                                    • Slide Number 51
                                                                                    • Slide Number 52
                                                                                    • Slide Number 53
                                                                                    • Slide Number 54
                                                                                    • Slide Number 55
                                                                                    • Slide Number 56
                                                                                    • Slide Number 57
                                                                                    • Slide Number 58
                                                                                    • Slide Number 59
                                                                                    • Slide Number 60
                                                                                    • Slide Number 61
                                                                                    • Next steps
                                                                                    • State Stormwater policies
                                                                                    • Slide Number 64

                                                                                      44

                                                                                      If already have a local policy for WSUDESD no real change

                                                                                      If notbull Workload and resourcingbull Increased detail and technical

                                                                                      contentbull Administrative arrangements ndash

                                                                                      referrals permit conditions ndashmake sure you make 60 stat days

                                                                                      bull Applicant pressure ndash what do you want

                                                                                      bull Assets

                                                                                      Development Assessors

                                                                                      45

                                                                                      bull Structure plans and rezoning ndashopportunities for localregional approach

                                                                                      bull IWM and Stormwater Management Plans ndash opportunities for these to be implemented through the controls spatial opportunities

                                                                                      bull Opportunities for development of Council offset strategies

                                                                                      Strategy

                                                                                      Offsets

                                                                                      bull Developer enters into an agreement with relevant drainage authority to financially contribute to off-site stormwatermanagement in lieu of providing on-site treatment

                                                                                      bull Already available for residential subdivisions in Melbourne (Clause 56) through MWCs Stormwater Quality Offset scheme

                                                                                      What are stormwater quality offsets

                                                                                      X Not drainage contributions (MWC drainage scheme)

                                                                                      X Not development contributions (DCPICP)

                                                                                      47

                                                                                      When to use

                                                                                      bull Not in MW DSS or growth area where therersquos an existing framework for funding SW treatment

                                                                                      bull Onsite treatment not practical or desirable

                                                                                      bull To fund planned localregional stormwater treatment works in that catchment via an existing offset scheme

                                                                                      bull Council and developer both agree to it

                                                                                      48

                                                                                      OffsetsExample ndash Kingston Offset Scheme

                                                                                      Asset ownership and maintenance

                                                                                      bull Whorsquos going to own itbull Whorsquos going to maintain itbull How do you maintain itbull How much will it cost

                                                                                      bull Where is itbull Is maintenance burden

                                                                                      practical for likely future owners

                                                                                      bull Whorsquos going to monitor compliance and how

                                                                                      The detail is in the permit conditions

                                                                                      Application requirements

                                                                                      ldquoAn application must be accompanied by details of the proposed stormwater management system including drainage works and retention detention and discharges of stormwater to the drainage systemrdquo ndash Clause 5318

                                                                                      What does the planning scheme require

                                                                                      But alsohellipNeed to provide sufficient information to Council which demonstrates that you comply and how you comply with all the other standards ndash eg urban coolinghabitatetc BPEM site management pollutant control infiltration (as relevant to development type

                                                                                      51

                                                                                      1 PlansWhat are you doing where is it going and does it fit

                                                                                      2 ModellingDo you (or can you) meet BPEM requirements

                                                                                      3 Written response to standardsHow does your proposal comply with the requirements

                                                                                      52

                                                                                      Application

                                                                                      bull Site plan ndash show all assetsWSUD treatments and any IWM features on the site layout plan with everything else

                                                                                      bull Landscape plan ndash if planting design passive irrigation etc forms part of response to requirements show

                                                                                      bull Site management plan (depending on Council)

                                                                                      bull Separate WSUDIWM plan showing all features on a stripped back background

                                                                                      bull Concept WSUD asset design ndash larger assets only (wetlands bioretention basins sed basin etc) ndash sufficient design detail to confirm spatial requirements

                                                                                      PlansPermit conditions

                                                                                      bull Detailed engineering design bull Site Management Plan (final)bull Asset maintenance plan (final)bull Handover arrangements (if public)

                                                                                      54

                                                                                      STORM ndash Online toolbull Print out of STORM reportbull Make sure meets 100 or

                                                                                      morebull Make sure report inputs and

                                                                                      results match plan

                                                                                      Modelling - SWQ

                                                                                      MUSIC ndash Proprietary softwarebull Provide a copy of the model filebull Print out the modelling resultsbull Provide summary of your model

                                                                                      inputs for each treatment train (iecatchment size impervious treatment area etc)

                                                                                      bull Provide a print out of the model schematic

                                                                                      Bonus points bull Provide details of model

                                                                                      parametersbull Provide results of MUSIC auditor

                                                                                      run (if using Melbourne Water MUSIC Guidelines)

                                                                                      56

                                                                                      Assessment against standards

                                                                                      bull Say what you have done (or will do) to meet each standardbull Donrsquot forget (if WSUD) details of maintenance and asset

                                                                                      ownershipbull Where applicable be explicit why yoursquove chosen (or not chosen) to

                                                                                      respond the way you have Egbull Opportunitiesbull Site constraintsbull Practicaloperational issues bull Brief dot point summary of options analysis if complex

                                                                                      bull Make sure if it doesnrsquot meet the standard it meets the objectivebull Make sure shown on plan and consistent with modelling and rest of

                                                                                      documentation

                                                                                      57

                                                                                      Resources

                                                                                      Local stormwaterWSUD policiesBaysideKingstonCaseyMonashMelbourneYarraMoonee ValleyPort PhilipStonningtonHumeCampaspeBass Coast

                                                                                      Local ESD (including IWM) policies Greater BendigoGreater DandenongHobsons BayWhittleseaWyndhamWhitehorseManninghamMorelandDarebinBanyuleKnoxBrimbank

                                                                                      Council planning resources

                                                                                      Application resources ndashexamplesDELWP Practice Note ndashformal guide to the new controlsMoreland ndash application checklists and example plans for a variety of residential developmentsPort Philip ndash compliance guidelines checklist and examplesMoonee Valley ndash checklists and example plans including site management plans Greater Bendigo ndash WSUD kitBayside ndash application guidelines and example plans

                                                                                      59

                                                                                      Technical guidelines (modelling design construction)

                                                                                      Melbourne Water

                                                                                      STORM calculatorMUSIC auditor - lsquohow torsquo video here

                                                                                      Melbourne Water technical guidelines page- WSUD asset life cycle costings and model maintenance guidelines- MUSIC guidelines- Stormwater harvesting guidelines- WSUD life cycle costings and

                                                                                      maintenance guidelines- Design and construction guidelines

                                                                                      for variety of assetshttpswwwmelbournewatercomauplanning-and-buildingdeveloper-guides-and-resourcesguidelines-drawings-and-checklistsguidelines

                                                                                      Council

                                                                                      South-Eastern Growth Council WSUD guidelines ndash note that some individual Councils have their own addendumsMelbournePort PhilipNorth-West Growth Council WSUD guidelines - note that some individual Councils have their own addendumsGreater BendigoMilduraBallaratBaw BawWyndhamMoreland ndash tree pits and raingardens

                                                                                      60

                                                                                      IWM

                                                                                      Example Council IWM strategiesMelbourneCaseyMonashKingston

                                                                                      Resilient Melbourne ndash IWM information lsquohubrsquoClearwater ndash capacity building and case studiesMelbourne Water ndash funding opportunities for IWM projects

                                                                                      Stormwater offset schemes

                                                                                      KingstonGreater GeelongMelbourne Water ndash non scheme contributions

                                                                                      Site management

                                                                                      EPA guidelines- management of erosion and sediment

                                                                                      Next steps and other stormwater initiatives

                                                                                      Emma Stewart DELWP

                                                                                      62

                                                                                      Next steps

                                                                                      bull Trainingbull The EPArsquos BPEM Reviewbull Offsets policybull Review of STORM bull Building controls

                                                                                      63

                                                                                      State Stormwater policies

                                                                                      64

                                                                                      Thank you

                                                                                      • Slide Number 1
                                                                                      • Slide Number 2
                                                                                      • History of WSUD
                                                                                      • History of WSUD
                                                                                      • Transformational change in urban water
                                                                                      • Inconsistencies and inequities in our approach to stormwater management
                                                                                      • Slide Number 8
                                                                                      • Terms of Reference
                                                                                      • Improving Stormwater Management Advisory Committee
                                                                                      • Wide consultation
                                                                                      • Stakeholder feedback
                                                                                      • Stakeholder feedback
                                                                                      • Committee submitted its report in September 2018
                                                                                      • Committee Recomendations
                                                                                      • Planning reforms
                                                                                      • Future policy directions
                                                                                      • Supporting actions
                                                                                      • Slide Number 19
                                                                                      • Government response (to date)
                                                                                      • Longer term recommendations
                                                                                      • State-based planning requirements (lsquobeforersquo)
                                                                                      • State-based planning requirements (lsquoafterrsquo)
                                                                                      • Development types (volume)
                                                                                      • Slide Number 25
                                                                                      • Amendment VC154
                                                                                      • Whatrsquos in
                                                                                      • Slide Number 28
                                                                                      • Key elements of clauses
                                                                                      • Clause 5318 ndash subdivision
                                                                                      • Clause 5318 ndash Buildings and works
                                                                                      • Townhouses - Standard B9
                                                                                      • Slide Number 33
                                                                                      • Slide Number 34
                                                                                      • Slide Number 35
                                                                                      • Slide Number 36
                                                                                      • Slide Number 37
                                                                                      • Buildings and works - Site management standard
                                                                                      • Site management
                                                                                      • Planning Advisory Note No 75
                                                                                      • Slide Number 41
                                                                                      • Slide Number 42
                                                                                      • Slide Number 43
                                                                                      • Slide Number 44
                                                                                      • Slide Number 45
                                                                                      • Slide Number 46
                                                                                      • Slide Number 47
                                                                                      • Slide Number 48
                                                                                      • Slide Number 49
                                                                                      • Slide Number 50
                                                                                      • Slide Number 51
                                                                                      • Slide Number 52
                                                                                      • Slide Number 53
                                                                                      • Slide Number 54
                                                                                      • Slide Number 55
                                                                                      • Slide Number 56
                                                                                      • Slide Number 57
                                                                                      • Slide Number 58
                                                                                      • Slide Number 59
                                                                                      • Slide Number 60
                                                                                      • Slide Number 61
                                                                                      • Next steps
                                                                                      • State Stormwater policies
                                                                                      • Slide Number 64

                                                                                        45

                                                                                        bull Structure plans and rezoning ndashopportunities for localregional approach

                                                                                        bull IWM and Stormwater Management Plans ndash opportunities for these to be implemented through the controls spatial opportunities

                                                                                        bull Opportunities for development of Council offset strategies

                                                                                        Strategy

                                                                                        Offsets

                                                                                        bull Developer enters into an agreement with relevant drainage authority to financially contribute to off-site stormwatermanagement in lieu of providing on-site treatment

                                                                                        bull Already available for residential subdivisions in Melbourne (Clause 56) through MWCs Stormwater Quality Offset scheme

                                                                                        What are stormwater quality offsets

                                                                                        X Not drainage contributions (MWC drainage scheme)

                                                                                        X Not development contributions (DCPICP)

                                                                                        47

                                                                                        When to use

                                                                                        bull Not in MW DSS or growth area where therersquos an existing framework for funding SW treatment

                                                                                        bull Onsite treatment not practical or desirable

                                                                                        bull To fund planned localregional stormwater treatment works in that catchment via an existing offset scheme

                                                                                        bull Council and developer both agree to it

                                                                                        48

                                                                                        OffsetsExample ndash Kingston Offset Scheme

                                                                                        Asset ownership and maintenance

                                                                                        bull Whorsquos going to own itbull Whorsquos going to maintain itbull How do you maintain itbull How much will it cost

                                                                                        bull Where is itbull Is maintenance burden

                                                                                        practical for likely future owners

                                                                                        bull Whorsquos going to monitor compliance and how

                                                                                        The detail is in the permit conditions

                                                                                        Application requirements

                                                                                        ldquoAn application must be accompanied by details of the proposed stormwater management system including drainage works and retention detention and discharges of stormwater to the drainage systemrdquo ndash Clause 5318

                                                                                        What does the planning scheme require

                                                                                        But alsohellipNeed to provide sufficient information to Council which demonstrates that you comply and how you comply with all the other standards ndash eg urban coolinghabitatetc BPEM site management pollutant control infiltration (as relevant to development type

                                                                                        51

                                                                                        1 PlansWhat are you doing where is it going and does it fit

                                                                                        2 ModellingDo you (or can you) meet BPEM requirements

                                                                                        3 Written response to standardsHow does your proposal comply with the requirements

                                                                                        52

                                                                                        Application

                                                                                        bull Site plan ndash show all assetsWSUD treatments and any IWM features on the site layout plan with everything else

                                                                                        bull Landscape plan ndash if planting design passive irrigation etc forms part of response to requirements show

                                                                                        bull Site management plan (depending on Council)

                                                                                        bull Separate WSUDIWM plan showing all features on a stripped back background

                                                                                        bull Concept WSUD asset design ndash larger assets only (wetlands bioretention basins sed basin etc) ndash sufficient design detail to confirm spatial requirements

                                                                                        PlansPermit conditions

                                                                                        bull Detailed engineering design bull Site Management Plan (final)bull Asset maintenance plan (final)bull Handover arrangements (if public)

                                                                                        54

                                                                                        STORM ndash Online toolbull Print out of STORM reportbull Make sure meets 100 or

                                                                                        morebull Make sure report inputs and

                                                                                        results match plan

                                                                                        Modelling - SWQ

                                                                                        MUSIC ndash Proprietary softwarebull Provide a copy of the model filebull Print out the modelling resultsbull Provide summary of your model

                                                                                        inputs for each treatment train (iecatchment size impervious treatment area etc)

                                                                                        bull Provide a print out of the model schematic

                                                                                        Bonus points bull Provide details of model

                                                                                        parametersbull Provide results of MUSIC auditor

                                                                                        run (if using Melbourne Water MUSIC Guidelines)

                                                                                        56

                                                                                        Assessment against standards

                                                                                        bull Say what you have done (or will do) to meet each standardbull Donrsquot forget (if WSUD) details of maintenance and asset

                                                                                        ownershipbull Where applicable be explicit why yoursquove chosen (or not chosen) to

                                                                                        respond the way you have Egbull Opportunitiesbull Site constraintsbull Practicaloperational issues bull Brief dot point summary of options analysis if complex

                                                                                        bull Make sure if it doesnrsquot meet the standard it meets the objectivebull Make sure shown on plan and consistent with modelling and rest of

                                                                                        documentation

                                                                                        57

                                                                                        Resources

                                                                                        Local stormwaterWSUD policiesBaysideKingstonCaseyMonashMelbourneYarraMoonee ValleyPort PhilipStonningtonHumeCampaspeBass Coast

                                                                                        Local ESD (including IWM) policies Greater BendigoGreater DandenongHobsons BayWhittleseaWyndhamWhitehorseManninghamMorelandDarebinBanyuleKnoxBrimbank

                                                                                        Council planning resources

                                                                                        Application resources ndashexamplesDELWP Practice Note ndashformal guide to the new controlsMoreland ndash application checklists and example plans for a variety of residential developmentsPort Philip ndash compliance guidelines checklist and examplesMoonee Valley ndash checklists and example plans including site management plans Greater Bendigo ndash WSUD kitBayside ndash application guidelines and example plans

                                                                                        59

                                                                                        Technical guidelines (modelling design construction)

                                                                                        Melbourne Water

                                                                                        STORM calculatorMUSIC auditor - lsquohow torsquo video here

                                                                                        Melbourne Water technical guidelines page- WSUD asset life cycle costings and model maintenance guidelines- MUSIC guidelines- Stormwater harvesting guidelines- WSUD life cycle costings and

                                                                                        maintenance guidelines- Design and construction guidelines

                                                                                        for variety of assetshttpswwwmelbournewatercomauplanning-and-buildingdeveloper-guides-and-resourcesguidelines-drawings-and-checklistsguidelines

                                                                                        Council

                                                                                        South-Eastern Growth Council WSUD guidelines ndash note that some individual Councils have their own addendumsMelbournePort PhilipNorth-West Growth Council WSUD guidelines - note that some individual Councils have their own addendumsGreater BendigoMilduraBallaratBaw BawWyndhamMoreland ndash tree pits and raingardens

                                                                                        60

                                                                                        IWM

                                                                                        Example Council IWM strategiesMelbourneCaseyMonashKingston

                                                                                        Resilient Melbourne ndash IWM information lsquohubrsquoClearwater ndash capacity building and case studiesMelbourne Water ndash funding opportunities for IWM projects

                                                                                        Stormwater offset schemes

                                                                                        KingstonGreater GeelongMelbourne Water ndash non scheme contributions

                                                                                        Site management

                                                                                        EPA guidelines- management of erosion and sediment

                                                                                        Next steps and other stormwater initiatives

                                                                                        Emma Stewart DELWP

                                                                                        62

                                                                                        Next steps

                                                                                        bull Trainingbull The EPArsquos BPEM Reviewbull Offsets policybull Review of STORM bull Building controls

                                                                                        63

                                                                                        State Stormwater policies

                                                                                        64

                                                                                        Thank you

                                                                                        • Slide Number 1
                                                                                        • Slide Number 2
                                                                                        • History of WSUD
                                                                                        • History of WSUD
                                                                                        • Transformational change in urban water
                                                                                        • Inconsistencies and inequities in our approach to stormwater management
                                                                                        • Slide Number 8
                                                                                        • Terms of Reference
                                                                                        • Improving Stormwater Management Advisory Committee
                                                                                        • Wide consultation
                                                                                        • Stakeholder feedback
                                                                                        • Stakeholder feedback
                                                                                        • Committee submitted its report in September 2018
                                                                                        • Committee Recomendations
                                                                                        • Planning reforms
                                                                                        • Future policy directions
                                                                                        • Supporting actions
                                                                                        • Slide Number 19
                                                                                        • Government response (to date)
                                                                                        • Longer term recommendations
                                                                                        • State-based planning requirements (lsquobeforersquo)
                                                                                        • State-based planning requirements (lsquoafterrsquo)
                                                                                        • Development types (volume)
                                                                                        • Slide Number 25
                                                                                        • Amendment VC154
                                                                                        • Whatrsquos in
                                                                                        • Slide Number 28
                                                                                        • Key elements of clauses
                                                                                        • Clause 5318 ndash subdivision
                                                                                        • Clause 5318 ndash Buildings and works
                                                                                        • Townhouses - Standard B9
                                                                                        • Slide Number 33
                                                                                        • Slide Number 34
                                                                                        • Slide Number 35
                                                                                        • Slide Number 36
                                                                                        • Slide Number 37
                                                                                        • Buildings and works - Site management standard
                                                                                        • Site management
                                                                                        • Planning Advisory Note No 75
                                                                                        • Slide Number 41
                                                                                        • Slide Number 42
                                                                                        • Slide Number 43
                                                                                        • Slide Number 44
                                                                                        • Slide Number 45
                                                                                        • Slide Number 46
                                                                                        • Slide Number 47
                                                                                        • Slide Number 48
                                                                                        • Slide Number 49
                                                                                        • Slide Number 50
                                                                                        • Slide Number 51
                                                                                        • Slide Number 52
                                                                                        • Slide Number 53
                                                                                        • Slide Number 54
                                                                                        • Slide Number 55
                                                                                        • Slide Number 56
                                                                                        • Slide Number 57
                                                                                        • Slide Number 58
                                                                                        • Slide Number 59
                                                                                        • Slide Number 60
                                                                                        • Slide Number 61
                                                                                        • Next steps
                                                                                        • State Stormwater policies
                                                                                        • Slide Number 64

                                                                                          Offsets

                                                                                          bull Developer enters into an agreement with relevant drainage authority to financially contribute to off-site stormwatermanagement in lieu of providing on-site treatment

                                                                                          bull Already available for residential subdivisions in Melbourne (Clause 56) through MWCs Stormwater Quality Offset scheme

                                                                                          What are stormwater quality offsets

                                                                                          X Not drainage contributions (MWC drainage scheme)

                                                                                          X Not development contributions (DCPICP)

                                                                                          47

                                                                                          When to use

                                                                                          bull Not in MW DSS or growth area where therersquos an existing framework for funding SW treatment

                                                                                          bull Onsite treatment not practical or desirable

                                                                                          bull To fund planned localregional stormwater treatment works in that catchment via an existing offset scheme

                                                                                          bull Council and developer both agree to it

                                                                                          48

                                                                                          OffsetsExample ndash Kingston Offset Scheme

                                                                                          Asset ownership and maintenance

                                                                                          bull Whorsquos going to own itbull Whorsquos going to maintain itbull How do you maintain itbull How much will it cost

                                                                                          bull Where is itbull Is maintenance burden

                                                                                          practical for likely future owners

                                                                                          bull Whorsquos going to monitor compliance and how

                                                                                          The detail is in the permit conditions

                                                                                          Application requirements

                                                                                          ldquoAn application must be accompanied by details of the proposed stormwater management system including drainage works and retention detention and discharges of stormwater to the drainage systemrdquo ndash Clause 5318

                                                                                          What does the planning scheme require

                                                                                          But alsohellipNeed to provide sufficient information to Council which demonstrates that you comply and how you comply with all the other standards ndash eg urban coolinghabitatetc BPEM site management pollutant control infiltration (as relevant to development type

                                                                                          51

                                                                                          1 PlansWhat are you doing where is it going and does it fit

                                                                                          2 ModellingDo you (or can you) meet BPEM requirements

                                                                                          3 Written response to standardsHow does your proposal comply with the requirements

                                                                                          52

                                                                                          Application

                                                                                          bull Site plan ndash show all assetsWSUD treatments and any IWM features on the site layout plan with everything else

                                                                                          bull Landscape plan ndash if planting design passive irrigation etc forms part of response to requirements show

                                                                                          bull Site management plan (depending on Council)

                                                                                          bull Separate WSUDIWM plan showing all features on a stripped back background

                                                                                          bull Concept WSUD asset design ndash larger assets only (wetlands bioretention basins sed basin etc) ndash sufficient design detail to confirm spatial requirements

                                                                                          PlansPermit conditions

                                                                                          bull Detailed engineering design bull Site Management Plan (final)bull Asset maintenance plan (final)bull Handover arrangements (if public)

                                                                                          54

                                                                                          STORM ndash Online toolbull Print out of STORM reportbull Make sure meets 100 or

                                                                                          morebull Make sure report inputs and

                                                                                          results match plan

                                                                                          Modelling - SWQ

                                                                                          MUSIC ndash Proprietary softwarebull Provide a copy of the model filebull Print out the modelling resultsbull Provide summary of your model

                                                                                          inputs for each treatment train (iecatchment size impervious treatment area etc)

                                                                                          bull Provide a print out of the model schematic

                                                                                          Bonus points bull Provide details of model

                                                                                          parametersbull Provide results of MUSIC auditor

                                                                                          run (if using Melbourne Water MUSIC Guidelines)

                                                                                          56

                                                                                          Assessment against standards

                                                                                          bull Say what you have done (or will do) to meet each standardbull Donrsquot forget (if WSUD) details of maintenance and asset

                                                                                          ownershipbull Where applicable be explicit why yoursquove chosen (or not chosen) to

                                                                                          respond the way you have Egbull Opportunitiesbull Site constraintsbull Practicaloperational issues bull Brief dot point summary of options analysis if complex

                                                                                          bull Make sure if it doesnrsquot meet the standard it meets the objectivebull Make sure shown on plan and consistent with modelling and rest of

                                                                                          documentation

                                                                                          57

                                                                                          Resources

                                                                                          Local stormwaterWSUD policiesBaysideKingstonCaseyMonashMelbourneYarraMoonee ValleyPort PhilipStonningtonHumeCampaspeBass Coast

                                                                                          Local ESD (including IWM) policies Greater BendigoGreater DandenongHobsons BayWhittleseaWyndhamWhitehorseManninghamMorelandDarebinBanyuleKnoxBrimbank

                                                                                          Council planning resources

                                                                                          Application resources ndashexamplesDELWP Practice Note ndashformal guide to the new controlsMoreland ndash application checklists and example plans for a variety of residential developmentsPort Philip ndash compliance guidelines checklist and examplesMoonee Valley ndash checklists and example plans including site management plans Greater Bendigo ndash WSUD kitBayside ndash application guidelines and example plans

                                                                                          59

                                                                                          Technical guidelines (modelling design construction)

                                                                                          Melbourne Water

                                                                                          STORM calculatorMUSIC auditor - lsquohow torsquo video here

                                                                                          Melbourne Water technical guidelines page- WSUD asset life cycle costings and model maintenance guidelines- MUSIC guidelines- Stormwater harvesting guidelines- WSUD life cycle costings and

                                                                                          maintenance guidelines- Design and construction guidelines

                                                                                          for variety of assetshttpswwwmelbournewatercomauplanning-and-buildingdeveloper-guides-and-resourcesguidelines-drawings-and-checklistsguidelines

                                                                                          Council

                                                                                          South-Eastern Growth Council WSUD guidelines ndash note that some individual Councils have their own addendumsMelbournePort PhilipNorth-West Growth Council WSUD guidelines - note that some individual Councils have their own addendumsGreater BendigoMilduraBallaratBaw BawWyndhamMoreland ndash tree pits and raingardens

                                                                                          60

                                                                                          IWM

                                                                                          Example Council IWM strategiesMelbourneCaseyMonashKingston

                                                                                          Resilient Melbourne ndash IWM information lsquohubrsquoClearwater ndash capacity building and case studiesMelbourne Water ndash funding opportunities for IWM projects

                                                                                          Stormwater offset schemes

                                                                                          KingstonGreater GeelongMelbourne Water ndash non scheme contributions

                                                                                          Site management

                                                                                          EPA guidelines- management of erosion and sediment

                                                                                          Next steps and other stormwater initiatives

                                                                                          Emma Stewart DELWP

                                                                                          62

                                                                                          Next steps

                                                                                          bull Trainingbull The EPArsquos BPEM Reviewbull Offsets policybull Review of STORM bull Building controls

                                                                                          63

                                                                                          State Stormwater policies

                                                                                          64

                                                                                          Thank you

                                                                                          • Slide Number 1
                                                                                          • Slide Number 2
                                                                                          • History of WSUD
                                                                                          • History of WSUD
                                                                                          • Transformational change in urban water
                                                                                          • Inconsistencies and inequities in our approach to stormwater management
                                                                                          • Slide Number 8
                                                                                          • Terms of Reference
                                                                                          • Improving Stormwater Management Advisory Committee
                                                                                          • Wide consultation
                                                                                          • Stakeholder feedback
                                                                                          • Stakeholder feedback
                                                                                          • Committee submitted its report in September 2018
                                                                                          • Committee Recomendations
                                                                                          • Planning reforms
                                                                                          • Future policy directions
                                                                                          • Supporting actions
                                                                                          • Slide Number 19
                                                                                          • Government response (to date)
                                                                                          • Longer term recommendations
                                                                                          • State-based planning requirements (lsquobeforersquo)
                                                                                          • State-based planning requirements (lsquoafterrsquo)
                                                                                          • Development types (volume)
                                                                                          • Slide Number 25
                                                                                          • Amendment VC154
                                                                                          • Whatrsquos in
                                                                                          • Slide Number 28
                                                                                          • Key elements of clauses
                                                                                          • Clause 5318 ndash subdivision
                                                                                          • Clause 5318 ndash Buildings and works
                                                                                          • Townhouses - Standard B9
                                                                                          • Slide Number 33
                                                                                          • Slide Number 34
                                                                                          • Slide Number 35
                                                                                          • Slide Number 36
                                                                                          • Slide Number 37
                                                                                          • Buildings and works - Site management standard
                                                                                          • Site management
                                                                                          • Planning Advisory Note No 75
                                                                                          • Slide Number 41
                                                                                          • Slide Number 42
                                                                                          • Slide Number 43
                                                                                          • Slide Number 44
                                                                                          • Slide Number 45
                                                                                          • Slide Number 46
                                                                                          • Slide Number 47
                                                                                          • Slide Number 48
                                                                                          • Slide Number 49
                                                                                          • Slide Number 50
                                                                                          • Slide Number 51
                                                                                          • Slide Number 52
                                                                                          • Slide Number 53
                                                                                          • Slide Number 54
                                                                                          • Slide Number 55
                                                                                          • Slide Number 56
                                                                                          • Slide Number 57
                                                                                          • Slide Number 58
                                                                                          • Slide Number 59
                                                                                          • Slide Number 60
                                                                                          • Slide Number 61
                                                                                          • Next steps
                                                                                          • State Stormwater policies
                                                                                          • Slide Number 64

                                                                                            47

                                                                                            When to use

                                                                                            bull Not in MW DSS or growth area where therersquos an existing framework for funding SW treatment

                                                                                            bull Onsite treatment not practical or desirable

                                                                                            bull To fund planned localregional stormwater treatment works in that catchment via an existing offset scheme

                                                                                            bull Council and developer both agree to it

                                                                                            48

                                                                                            OffsetsExample ndash Kingston Offset Scheme

                                                                                            Asset ownership and maintenance

                                                                                            bull Whorsquos going to own itbull Whorsquos going to maintain itbull How do you maintain itbull How much will it cost

                                                                                            bull Where is itbull Is maintenance burden

                                                                                            practical for likely future owners

                                                                                            bull Whorsquos going to monitor compliance and how

                                                                                            The detail is in the permit conditions

                                                                                            Application requirements

                                                                                            ldquoAn application must be accompanied by details of the proposed stormwater management system including drainage works and retention detention and discharges of stormwater to the drainage systemrdquo ndash Clause 5318

                                                                                            What does the planning scheme require

                                                                                            But alsohellipNeed to provide sufficient information to Council which demonstrates that you comply and how you comply with all the other standards ndash eg urban coolinghabitatetc BPEM site management pollutant control infiltration (as relevant to development type

                                                                                            51

                                                                                            1 PlansWhat are you doing where is it going and does it fit

                                                                                            2 ModellingDo you (or can you) meet BPEM requirements

                                                                                            3 Written response to standardsHow does your proposal comply with the requirements

                                                                                            52

                                                                                            Application

                                                                                            bull Site plan ndash show all assetsWSUD treatments and any IWM features on the site layout plan with everything else

                                                                                            bull Landscape plan ndash if planting design passive irrigation etc forms part of response to requirements show

                                                                                            bull Site management plan (depending on Council)

                                                                                            bull Separate WSUDIWM plan showing all features on a stripped back background

                                                                                            bull Concept WSUD asset design ndash larger assets only (wetlands bioretention basins sed basin etc) ndash sufficient design detail to confirm spatial requirements

                                                                                            PlansPermit conditions

                                                                                            bull Detailed engineering design bull Site Management Plan (final)bull Asset maintenance plan (final)bull Handover arrangements (if public)

                                                                                            54

                                                                                            STORM ndash Online toolbull Print out of STORM reportbull Make sure meets 100 or

                                                                                            morebull Make sure report inputs and

                                                                                            results match plan

                                                                                            Modelling - SWQ

                                                                                            MUSIC ndash Proprietary softwarebull Provide a copy of the model filebull Print out the modelling resultsbull Provide summary of your model

                                                                                            inputs for each treatment train (iecatchment size impervious treatment area etc)

                                                                                            bull Provide a print out of the model schematic

                                                                                            Bonus points bull Provide details of model

                                                                                            parametersbull Provide results of MUSIC auditor

                                                                                            run (if using Melbourne Water MUSIC Guidelines)

                                                                                            56

                                                                                            Assessment against standards

                                                                                            bull Say what you have done (or will do) to meet each standardbull Donrsquot forget (if WSUD) details of maintenance and asset

                                                                                            ownershipbull Where applicable be explicit why yoursquove chosen (or not chosen) to

                                                                                            respond the way you have Egbull Opportunitiesbull Site constraintsbull Practicaloperational issues bull Brief dot point summary of options analysis if complex

                                                                                            bull Make sure if it doesnrsquot meet the standard it meets the objectivebull Make sure shown on plan and consistent with modelling and rest of

                                                                                            documentation

                                                                                            57

                                                                                            Resources

                                                                                            Local stormwaterWSUD policiesBaysideKingstonCaseyMonashMelbourneYarraMoonee ValleyPort PhilipStonningtonHumeCampaspeBass Coast

                                                                                            Local ESD (including IWM) policies Greater BendigoGreater DandenongHobsons BayWhittleseaWyndhamWhitehorseManninghamMorelandDarebinBanyuleKnoxBrimbank

                                                                                            Council planning resources

                                                                                            Application resources ndashexamplesDELWP Practice Note ndashformal guide to the new controlsMoreland ndash application checklists and example plans for a variety of residential developmentsPort Philip ndash compliance guidelines checklist and examplesMoonee Valley ndash checklists and example plans including site management plans Greater Bendigo ndash WSUD kitBayside ndash application guidelines and example plans

                                                                                            59

                                                                                            Technical guidelines (modelling design construction)

                                                                                            Melbourne Water

                                                                                            STORM calculatorMUSIC auditor - lsquohow torsquo video here

                                                                                            Melbourne Water technical guidelines page- WSUD asset life cycle costings and model maintenance guidelines- MUSIC guidelines- Stormwater harvesting guidelines- WSUD life cycle costings and

                                                                                            maintenance guidelines- Design and construction guidelines

                                                                                            for variety of assetshttpswwwmelbournewatercomauplanning-and-buildingdeveloper-guides-and-resourcesguidelines-drawings-and-checklistsguidelines

                                                                                            Council

                                                                                            South-Eastern Growth Council WSUD guidelines ndash note that some individual Councils have their own addendumsMelbournePort PhilipNorth-West Growth Council WSUD guidelines - note that some individual Councils have their own addendumsGreater BendigoMilduraBallaratBaw BawWyndhamMoreland ndash tree pits and raingardens

                                                                                            60

                                                                                            IWM

                                                                                            Example Council IWM strategiesMelbourneCaseyMonashKingston

                                                                                            Resilient Melbourne ndash IWM information lsquohubrsquoClearwater ndash capacity building and case studiesMelbourne Water ndash funding opportunities for IWM projects

                                                                                            Stormwater offset schemes

                                                                                            KingstonGreater GeelongMelbourne Water ndash non scheme contributions

                                                                                            Site management

                                                                                            EPA guidelines- management of erosion and sediment

                                                                                            Next steps and other stormwater initiatives

                                                                                            Emma Stewart DELWP

                                                                                            62

                                                                                            Next steps

                                                                                            bull Trainingbull The EPArsquos BPEM Reviewbull Offsets policybull Review of STORM bull Building controls

                                                                                            63

                                                                                            State Stormwater policies

                                                                                            64

                                                                                            Thank you

                                                                                            • Slide Number 1
                                                                                            • Slide Number 2
                                                                                            • History of WSUD
                                                                                            • History of WSUD
                                                                                            • Transformational change in urban water
                                                                                            • Inconsistencies and inequities in our approach to stormwater management
                                                                                            • Slide Number 8
                                                                                            • Terms of Reference
                                                                                            • Improving Stormwater Management Advisory Committee
                                                                                            • Wide consultation
                                                                                            • Stakeholder feedback
                                                                                            • Stakeholder feedback
                                                                                            • Committee submitted its report in September 2018
                                                                                            • Committee Recomendations
                                                                                            • Planning reforms
                                                                                            • Future policy directions
                                                                                            • Supporting actions
                                                                                            • Slide Number 19
                                                                                            • Government response (to date)
                                                                                            • Longer term recommendations
                                                                                            • State-based planning requirements (lsquobeforersquo)
                                                                                            • State-based planning requirements (lsquoafterrsquo)
                                                                                            • Development types (volume)
                                                                                            • Slide Number 25
                                                                                            • Amendment VC154
                                                                                            • Whatrsquos in
                                                                                            • Slide Number 28
                                                                                            • Key elements of clauses
                                                                                            • Clause 5318 ndash subdivision
                                                                                            • Clause 5318 ndash Buildings and works
                                                                                            • Townhouses - Standard B9
                                                                                            • Slide Number 33
                                                                                            • Slide Number 34
                                                                                            • Slide Number 35
                                                                                            • Slide Number 36
                                                                                            • Slide Number 37
                                                                                            • Buildings and works - Site management standard
                                                                                            • Site management
                                                                                            • Planning Advisory Note No 75
                                                                                            • Slide Number 41
                                                                                            • Slide Number 42
                                                                                            • Slide Number 43
                                                                                            • Slide Number 44
                                                                                            • Slide Number 45
                                                                                            • Slide Number 46
                                                                                            • Slide Number 47
                                                                                            • Slide Number 48
                                                                                            • Slide Number 49
                                                                                            • Slide Number 50
                                                                                            • Slide Number 51
                                                                                            • Slide Number 52
                                                                                            • Slide Number 53
                                                                                            • Slide Number 54
                                                                                            • Slide Number 55
                                                                                            • Slide Number 56
                                                                                            • Slide Number 57
                                                                                            • Slide Number 58
                                                                                            • Slide Number 59
                                                                                            • Slide Number 60
                                                                                            • Slide Number 61
                                                                                            • Next steps
                                                                                            • State Stormwater policies
                                                                                            • Slide Number 64

                                                                                              48

                                                                                              OffsetsExample ndash Kingston Offset Scheme

                                                                                              Asset ownership and maintenance

                                                                                              bull Whorsquos going to own itbull Whorsquos going to maintain itbull How do you maintain itbull How much will it cost

                                                                                              bull Where is itbull Is maintenance burden

                                                                                              practical for likely future owners

                                                                                              bull Whorsquos going to monitor compliance and how

                                                                                              The detail is in the permit conditions

                                                                                              Application requirements

                                                                                              ldquoAn application must be accompanied by details of the proposed stormwater management system including drainage works and retention detention and discharges of stormwater to the drainage systemrdquo ndash Clause 5318

                                                                                              What does the planning scheme require

                                                                                              But alsohellipNeed to provide sufficient information to Council which demonstrates that you comply and how you comply with all the other standards ndash eg urban coolinghabitatetc BPEM site management pollutant control infiltration (as relevant to development type

                                                                                              51

                                                                                              1 PlansWhat are you doing where is it going and does it fit

                                                                                              2 ModellingDo you (or can you) meet BPEM requirements

                                                                                              3 Written response to standardsHow does your proposal comply with the requirements

                                                                                              52

                                                                                              Application

                                                                                              bull Site plan ndash show all assetsWSUD treatments and any IWM features on the site layout plan with everything else

                                                                                              bull Landscape plan ndash if planting design passive irrigation etc forms part of response to requirements show

                                                                                              bull Site management plan (depending on Council)

                                                                                              bull Separate WSUDIWM plan showing all features on a stripped back background

                                                                                              bull Concept WSUD asset design ndash larger assets only (wetlands bioretention basins sed basin etc) ndash sufficient design detail to confirm spatial requirements

                                                                                              PlansPermit conditions

                                                                                              bull Detailed engineering design bull Site Management Plan (final)bull Asset maintenance plan (final)bull Handover arrangements (if public)

                                                                                              54

                                                                                              STORM ndash Online toolbull Print out of STORM reportbull Make sure meets 100 or

                                                                                              morebull Make sure report inputs and

                                                                                              results match plan

                                                                                              Modelling - SWQ

                                                                                              MUSIC ndash Proprietary softwarebull Provide a copy of the model filebull Print out the modelling resultsbull Provide summary of your model

                                                                                              inputs for each treatment train (iecatchment size impervious treatment area etc)

                                                                                              bull Provide a print out of the model schematic

                                                                                              Bonus points bull Provide details of model

                                                                                              parametersbull Provide results of MUSIC auditor

                                                                                              run (if using Melbourne Water MUSIC Guidelines)

                                                                                              56

                                                                                              Assessment against standards

                                                                                              bull Say what you have done (or will do) to meet each standardbull Donrsquot forget (if WSUD) details of maintenance and asset

                                                                                              ownershipbull Where applicable be explicit why yoursquove chosen (or not chosen) to

                                                                                              respond the way you have Egbull Opportunitiesbull Site constraintsbull Practicaloperational issues bull Brief dot point summary of options analysis if complex

                                                                                              bull Make sure if it doesnrsquot meet the standard it meets the objectivebull Make sure shown on plan and consistent with modelling and rest of

                                                                                              documentation

                                                                                              57

                                                                                              Resources

                                                                                              Local stormwaterWSUD policiesBaysideKingstonCaseyMonashMelbourneYarraMoonee ValleyPort PhilipStonningtonHumeCampaspeBass Coast

                                                                                              Local ESD (including IWM) policies Greater BendigoGreater DandenongHobsons BayWhittleseaWyndhamWhitehorseManninghamMorelandDarebinBanyuleKnoxBrimbank

                                                                                              Council planning resources

                                                                                              Application resources ndashexamplesDELWP Practice Note ndashformal guide to the new controlsMoreland ndash application checklists and example plans for a variety of residential developmentsPort Philip ndash compliance guidelines checklist and examplesMoonee Valley ndash checklists and example plans including site management plans Greater Bendigo ndash WSUD kitBayside ndash application guidelines and example plans

                                                                                              59

                                                                                              Technical guidelines (modelling design construction)

                                                                                              Melbourne Water

                                                                                              STORM calculatorMUSIC auditor - lsquohow torsquo video here

                                                                                              Melbourne Water technical guidelines page- WSUD asset life cycle costings and model maintenance guidelines- MUSIC guidelines- Stormwater harvesting guidelines- WSUD life cycle costings and

                                                                                              maintenance guidelines- Design and construction guidelines

                                                                                              for variety of assetshttpswwwmelbournewatercomauplanning-and-buildingdeveloper-guides-and-resourcesguidelines-drawings-and-checklistsguidelines

                                                                                              Council

                                                                                              South-Eastern Growth Council WSUD guidelines ndash note that some individual Councils have their own addendumsMelbournePort PhilipNorth-West Growth Council WSUD guidelines - note that some individual Councils have their own addendumsGreater BendigoMilduraBallaratBaw BawWyndhamMoreland ndash tree pits and raingardens

                                                                                              60

                                                                                              IWM

                                                                                              Example Council IWM strategiesMelbourneCaseyMonashKingston

                                                                                              Resilient Melbourne ndash IWM information lsquohubrsquoClearwater ndash capacity building and case studiesMelbourne Water ndash funding opportunities for IWM projects

                                                                                              Stormwater offset schemes

                                                                                              KingstonGreater GeelongMelbourne Water ndash non scheme contributions

                                                                                              Site management

                                                                                              EPA guidelines- management of erosion and sediment

                                                                                              Next steps and other stormwater initiatives

                                                                                              Emma Stewart DELWP

                                                                                              62

                                                                                              Next steps

                                                                                              bull Trainingbull The EPArsquos BPEM Reviewbull Offsets policybull Review of STORM bull Building controls

                                                                                              63

                                                                                              State Stormwater policies

                                                                                              64

                                                                                              Thank you

                                                                                              • Slide Number 1
                                                                                              • Slide Number 2
                                                                                              • History of WSUD
                                                                                              • History of WSUD
                                                                                              • Transformational change in urban water
                                                                                              • Inconsistencies and inequities in our approach to stormwater management
                                                                                              • Slide Number 8
                                                                                              • Terms of Reference
                                                                                              • Improving Stormwater Management Advisory Committee
                                                                                              • Wide consultation
                                                                                              • Stakeholder feedback
                                                                                              • Stakeholder feedback
                                                                                              • Committee submitted its report in September 2018
                                                                                              • Committee Recomendations
                                                                                              • Planning reforms
                                                                                              • Future policy directions
                                                                                              • Supporting actions
                                                                                              • Slide Number 19
                                                                                              • Government response (to date)
                                                                                              • Longer term recommendations
                                                                                              • State-based planning requirements (lsquobeforersquo)
                                                                                              • State-based planning requirements (lsquoafterrsquo)
                                                                                              • Development types (volume)
                                                                                              • Slide Number 25
                                                                                              • Amendment VC154
                                                                                              • Whatrsquos in
                                                                                              • Slide Number 28
                                                                                              • Key elements of clauses
                                                                                              • Clause 5318 ndash subdivision
                                                                                              • Clause 5318 ndash Buildings and works
                                                                                              • Townhouses - Standard B9
                                                                                              • Slide Number 33
                                                                                              • Slide Number 34
                                                                                              • Slide Number 35
                                                                                              • Slide Number 36
                                                                                              • Slide Number 37
                                                                                              • Buildings and works - Site management standard
                                                                                              • Site management
                                                                                              • Planning Advisory Note No 75
                                                                                              • Slide Number 41
                                                                                              • Slide Number 42
                                                                                              • Slide Number 43
                                                                                              • Slide Number 44
                                                                                              • Slide Number 45
                                                                                              • Slide Number 46
                                                                                              • Slide Number 47
                                                                                              • Slide Number 48
                                                                                              • Slide Number 49
                                                                                              • Slide Number 50
                                                                                              • Slide Number 51
                                                                                              • Slide Number 52
                                                                                              • Slide Number 53
                                                                                              • Slide Number 54
                                                                                              • Slide Number 55
                                                                                              • Slide Number 56
                                                                                              • Slide Number 57
                                                                                              • Slide Number 58
                                                                                              • Slide Number 59
                                                                                              • Slide Number 60
                                                                                              • Slide Number 61
                                                                                              • Next steps
                                                                                              • State Stormwater policies
                                                                                              • Slide Number 64

                                                                                                Asset ownership and maintenance

                                                                                                bull Whorsquos going to own itbull Whorsquos going to maintain itbull How do you maintain itbull How much will it cost

                                                                                                bull Where is itbull Is maintenance burden

                                                                                                practical for likely future owners

                                                                                                bull Whorsquos going to monitor compliance and how

                                                                                                The detail is in the permit conditions

                                                                                                Application requirements

                                                                                                ldquoAn application must be accompanied by details of the proposed stormwater management system including drainage works and retention detention and discharges of stormwater to the drainage systemrdquo ndash Clause 5318

                                                                                                What does the planning scheme require

                                                                                                But alsohellipNeed to provide sufficient information to Council which demonstrates that you comply and how you comply with all the other standards ndash eg urban coolinghabitatetc BPEM site management pollutant control infiltration (as relevant to development type

                                                                                                51

                                                                                                1 PlansWhat are you doing where is it going and does it fit

                                                                                                2 ModellingDo you (or can you) meet BPEM requirements

                                                                                                3 Written response to standardsHow does your proposal comply with the requirements

                                                                                                52

                                                                                                Application

                                                                                                bull Site plan ndash show all assetsWSUD treatments and any IWM features on the site layout plan with everything else

                                                                                                bull Landscape plan ndash if planting design passive irrigation etc forms part of response to requirements show

                                                                                                bull Site management plan (depending on Council)

                                                                                                bull Separate WSUDIWM plan showing all features on a stripped back background

                                                                                                bull Concept WSUD asset design ndash larger assets only (wetlands bioretention basins sed basin etc) ndash sufficient design detail to confirm spatial requirements

                                                                                                PlansPermit conditions

                                                                                                bull Detailed engineering design bull Site Management Plan (final)bull Asset maintenance plan (final)bull Handover arrangements (if public)

                                                                                                54

                                                                                                STORM ndash Online toolbull Print out of STORM reportbull Make sure meets 100 or

                                                                                                morebull Make sure report inputs and

                                                                                                results match plan

                                                                                                Modelling - SWQ

                                                                                                MUSIC ndash Proprietary softwarebull Provide a copy of the model filebull Print out the modelling resultsbull Provide summary of your model

                                                                                                inputs for each treatment train (iecatchment size impervious treatment area etc)

                                                                                                bull Provide a print out of the model schematic

                                                                                                Bonus points bull Provide details of model

                                                                                                parametersbull Provide results of MUSIC auditor

                                                                                                run (if using Melbourne Water MUSIC Guidelines)

                                                                                                56

                                                                                                Assessment against standards

                                                                                                bull Say what you have done (or will do) to meet each standardbull Donrsquot forget (if WSUD) details of maintenance and asset

                                                                                                ownershipbull Where applicable be explicit why yoursquove chosen (or not chosen) to

                                                                                                respond the way you have Egbull Opportunitiesbull Site constraintsbull Practicaloperational issues bull Brief dot point summary of options analysis if complex

                                                                                                bull Make sure if it doesnrsquot meet the standard it meets the objectivebull Make sure shown on plan and consistent with modelling and rest of

                                                                                                documentation

                                                                                                57

                                                                                                Resources

                                                                                                Local stormwaterWSUD policiesBaysideKingstonCaseyMonashMelbourneYarraMoonee ValleyPort PhilipStonningtonHumeCampaspeBass Coast

                                                                                                Local ESD (including IWM) policies Greater BendigoGreater DandenongHobsons BayWhittleseaWyndhamWhitehorseManninghamMorelandDarebinBanyuleKnoxBrimbank

                                                                                                Council planning resources

                                                                                                Application resources ndashexamplesDELWP Practice Note ndashformal guide to the new controlsMoreland ndash application checklists and example plans for a variety of residential developmentsPort Philip ndash compliance guidelines checklist and examplesMoonee Valley ndash checklists and example plans including site management plans Greater Bendigo ndash WSUD kitBayside ndash application guidelines and example plans

                                                                                                59

                                                                                                Technical guidelines (modelling design construction)

                                                                                                Melbourne Water

                                                                                                STORM calculatorMUSIC auditor - lsquohow torsquo video here

                                                                                                Melbourne Water technical guidelines page- WSUD asset life cycle costings and model maintenance guidelines- MUSIC guidelines- Stormwater harvesting guidelines- WSUD life cycle costings and

                                                                                                maintenance guidelines- Design and construction guidelines

                                                                                                for variety of assetshttpswwwmelbournewatercomauplanning-and-buildingdeveloper-guides-and-resourcesguidelines-drawings-and-checklistsguidelines

                                                                                                Council

                                                                                                South-Eastern Growth Council WSUD guidelines ndash note that some individual Councils have their own addendumsMelbournePort PhilipNorth-West Growth Council WSUD guidelines - note that some individual Councils have their own addendumsGreater BendigoMilduraBallaratBaw BawWyndhamMoreland ndash tree pits and raingardens

                                                                                                60

                                                                                                IWM

                                                                                                Example Council IWM strategiesMelbourneCaseyMonashKingston

                                                                                                Resilient Melbourne ndash IWM information lsquohubrsquoClearwater ndash capacity building and case studiesMelbourne Water ndash funding opportunities for IWM projects

                                                                                                Stormwater offset schemes

                                                                                                KingstonGreater GeelongMelbourne Water ndash non scheme contributions

                                                                                                Site management

                                                                                                EPA guidelines- management of erosion and sediment

                                                                                                Next steps and other stormwater initiatives

                                                                                                Emma Stewart DELWP

                                                                                                62

                                                                                                Next steps

                                                                                                bull Trainingbull The EPArsquos BPEM Reviewbull Offsets policybull Review of STORM bull Building controls

                                                                                                63

                                                                                                State Stormwater policies

                                                                                                64

                                                                                                Thank you

                                                                                                • Slide Number 1
                                                                                                • Slide Number 2
                                                                                                • History of WSUD
                                                                                                • History of WSUD
                                                                                                • Transformational change in urban water
                                                                                                • Inconsistencies and inequities in our approach to stormwater management
                                                                                                • Slide Number 8
                                                                                                • Terms of Reference
                                                                                                • Improving Stormwater Management Advisory Committee
                                                                                                • Wide consultation
                                                                                                • Stakeholder feedback
                                                                                                • Stakeholder feedback
                                                                                                • Committee submitted its report in September 2018
                                                                                                • Committee Recomendations
                                                                                                • Planning reforms
                                                                                                • Future policy directions
                                                                                                • Supporting actions
                                                                                                • Slide Number 19
                                                                                                • Government response (to date)
                                                                                                • Longer term recommendations
                                                                                                • State-based planning requirements (lsquobeforersquo)
                                                                                                • State-based planning requirements (lsquoafterrsquo)
                                                                                                • Development types (volume)
                                                                                                • Slide Number 25
                                                                                                • Amendment VC154
                                                                                                • Whatrsquos in
                                                                                                • Slide Number 28
                                                                                                • Key elements of clauses
                                                                                                • Clause 5318 ndash subdivision
                                                                                                • Clause 5318 ndash Buildings and works
                                                                                                • Townhouses - Standard B9
                                                                                                • Slide Number 33
                                                                                                • Slide Number 34
                                                                                                • Slide Number 35
                                                                                                • Slide Number 36
                                                                                                • Slide Number 37
                                                                                                • Buildings and works - Site management standard
                                                                                                • Site management
                                                                                                • Planning Advisory Note No 75
                                                                                                • Slide Number 41
                                                                                                • Slide Number 42
                                                                                                • Slide Number 43
                                                                                                • Slide Number 44
                                                                                                • Slide Number 45
                                                                                                • Slide Number 46
                                                                                                • Slide Number 47
                                                                                                • Slide Number 48
                                                                                                • Slide Number 49
                                                                                                • Slide Number 50
                                                                                                • Slide Number 51
                                                                                                • Slide Number 52
                                                                                                • Slide Number 53
                                                                                                • Slide Number 54
                                                                                                • Slide Number 55
                                                                                                • Slide Number 56
                                                                                                • Slide Number 57
                                                                                                • Slide Number 58
                                                                                                • Slide Number 59
                                                                                                • Slide Number 60
                                                                                                • Slide Number 61
                                                                                                • Next steps
                                                                                                • State Stormwater policies
                                                                                                • Slide Number 64

                                                                                                  Application requirements

                                                                                                  ldquoAn application must be accompanied by details of the proposed stormwater management system including drainage works and retention detention and discharges of stormwater to the drainage systemrdquo ndash Clause 5318

                                                                                                  What does the planning scheme require

                                                                                                  But alsohellipNeed to provide sufficient information to Council which demonstrates that you comply and how you comply with all the other standards ndash eg urban coolinghabitatetc BPEM site management pollutant control infiltration (as relevant to development type

                                                                                                  51

                                                                                                  1 PlansWhat are you doing where is it going and does it fit

                                                                                                  2 ModellingDo you (or can you) meet BPEM requirements

                                                                                                  3 Written response to standardsHow does your proposal comply with the requirements

                                                                                                  52

                                                                                                  Application

                                                                                                  bull Site plan ndash show all assetsWSUD treatments and any IWM features on the site layout plan with everything else

                                                                                                  bull Landscape plan ndash if planting design passive irrigation etc forms part of response to requirements show

                                                                                                  bull Site management plan (depending on Council)

                                                                                                  bull Separate WSUDIWM plan showing all features on a stripped back background

                                                                                                  bull Concept WSUD asset design ndash larger assets only (wetlands bioretention basins sed basin etc) ndash sufficient design detail to confirm spatial requirements

                                                                                                  PlansPermit conditions

                                                                                                  bull Detailed engineering design bull Site Management Plan (final)bull Asset maintenance plan (final)bull Handover arrangements (if public)

                                                                                                  54

                                                                                                  STORM ndash Online toolbull Print out of STORM reportbull Make sure meets 100 or

                                                                                                  morebull Make sure report inputs and

                                                                                                  results match plan

                                                                                                  Modelling - SWQ

                                                                                                  MUSIC ndash Proprietary softwarebull Provide a copy of the model filebull Print out the modelling resultsbull Provide summary of your model

                                                                                                  inputs for each treatment train (iecatchment size impervious treatment area etc)

                                                                                                  bull Provide a print out of the model schematic

                                                                                                  Bonus points bull Provide details of model

                                                                                                  parametersbull Provide results of MUSIC auditor

                                                                                                  run (if using Melbourne Water MUSIC Guidelines)

                                                                                                  56

                                                                                                  Assessment against standards

                                                                                                  bull Say what you have done (or will do) to meet each standardbull Donrsquot forget (if WSUD) details of maintenance and asset

                                                                                                  ownershipbull Where applicable be explicit why yoursquove chosen (or not chosen) to

                                                                                                  respond the way you have Egbull Opportunitiesbull Site constraintsbull Practicaloperational issues bull Brief dot point summary of options analysis if complex

                                                                                                  bull Make sure if it doesnrsquot meet the standard it meets the objectivebull Make sure shown on plan and consistent with modelling and rest of

                                                                                                  documentation

                                                                                                  57

                                                                                                  Resources

                                                                                                  Local stormwaterWSUD policiesBaysideKingstonCaseyMonashMelbourneYarraMoonee ValleyPort PhilipStonningtonHumeCampaspeBass Coast

                                                                                                  Local ESD (including IWM) policies Greater BendigoGreater DandenongHobsons BayWhittleseaWyndhamWhitehorseManninghamMorelandDarebinBanyuleKnoxBrimbank

                                                                                                  Council planning resources

                                                                                                  Application resources ndashexamplesDELWP Practice Note ndashformal guide to the new controlsMoreland ndash application checklists and example plans for a variety of residential developmentsPort Philip ndash compliance guidelines checklist and examplesMoonee Valley ndash checklists and example plans including site management plans Greater Bendigo ndash WSUD kitBayside ndash application guidelines and example plans

                                                                                                  59

                                                                                                  Technical guidelines (modelling design construction)

                                                                                                  Melbourne Water

                                                                                                  STORM calculatorMUSIC auditor - lsquohow torsquo video here

                                                                                                  Melbourne Water technical guidelines page- WSUD asset life cycle costings and model maintenance guidelines- MUSIC guidelines- Stormwater harvesting guidelines- WSUD life cycle costings and

                                                                                                  maintenance guidelines- Design and construction guidelines

                                                                                                  for variety of assetshttpswwwmelbournewatercomauplanning-and-buildingdeveloper-guides-and-resourcesguidelines-drawings-and-checklistsguidelines

                                                                                                  Council

                                                                                                  South-Eastern Growth Council WSUD guidelines ndash note that some individual Councils have their own addendumsMelbournePort PhilipNorth-West Growth Council WSUD guidelines - note that some individual Councils have their own addendumsGreater BendigoMilduraBallaratBaw BawWyndhamMoreland ndash tree pits and raingardens

                                                                                                  60

                                                                                                  IWM

                                                                                                  Example Council IWM strategiesMelbourneCaseyMonashKingston

                                                                                                  Resilient Melbourne ndash IWM information lsquohubrsquoClearwater ndash capacity building and case studiesMelbourne Water ndash funding opportunities for IWM projects

                                                                                                  Stormwater offset schemes

                                                                                                  KingstonGreater GeelongMelbourne Water ndash non scheme contributions

                                                                                                  Site management

                                                                                                  EPA guidelines- management of erosion and sediment

                                                                                                  Next steps and other stormwater initiatives

                                                                                                  Emma Stewart DELWP

                                                                                                  62

                                                                                                  Next steps

                                                                                                  bull Trainingbull The EPArsquos BPEM Reviewbull Offsets policybull Review of STORM bull Building controls

                                                                                                  63

                                                                                                  State Stormwater policies

                                                                                                  64

                                                                                                  Thank you

                                                                                                  • Slide Number 1
                                                                                                  • Slide Number 2
                                                                                                  • History of WSUD
                                                                                                  • History of WSUD
                                                                                                  • Transformational change in urban water
                                                                                                  • Inconsistencies and inequities in our approach to stormwater management
                                                                                                  • Slide Number 8
                                                                                                  • Terms of Reference
                                                                                                  • Improving Stormwater Management Advisory Committee
                                                                                                  • Wide consultation
                                                                                                  • Stakeholder feedback
                                                                                                  • Stakeholder feedback
                                                                                                  • Committee submitted its report in September 2018
                                                                                                  • Committee Recomendations
                                                                                                  • Planning reforms
                                                                                                  • Future policy directions
                                                                                                  • Supporting actions
                                                                                                  • Slide Number 19
                                                                                                  • Government response (to date)
                                                                                                  • Longer term recommendations
                                                                                                  • State-based planning requirements (lsquobeforersquo)
                                                                                                  • State-based planning requirements (lsquoafterrsquo)
                                                                                                  • Development types (volume)
                                                                                                  • Slide Number 25
                                                                                                  • Amendment VC154
                                                                                                  • Whatrsquos in
                                                                                                  • Slide Number 28
                                                                                                  • Key elements of clauses
                                                                                                  • Clause 5318 ndash subdivision
                                                                                                  • Clause 5318 ndash Buildings and works
                                                                                                  • Townhouses - Standard B9
                                                                                                  • Slide Number 33
                                                                                                  • Slide Number 34
                                                                                                  • Slide Number 35
                                                                                                  • Slide Number 36
                                                                                                  • Slide Number 37
                                                                                                  • Buildings and works - Site management standard
                                                                                                  • Site management
                                                                                                  • Planning Advisory Note No 75
                                                                                                  • Slide Number 41
                                                                                                  • Slide Number 42
                                                                                                  • Slide Number 43
                                                                                                  • Slide Number 44
                                                                                                  • Slide Number 45
                                                                                                  • Slide Number 46
                                                                                                  • Slide Number 47
                                                                                                  • Slide Number 48
                                                                                                  • Slide Number 49
                                                                                                  • Slide Number 50
                                                                                                  • Slide Number 51
                                                                                                  • Slide Number 52
                                                                                                  • Slide Number 53
                                                                                                  • Slide Number 54
                                                                                                  • Slide Number 55
                                                                                                  • Slide Number 56
                                                                                                  • Slide Number 57
                                                                                                  • Slide Number 58
                                                                                                  • Slide Number 59
                                                                                                  • Slide Number 60
                                                                                                  • Slide Number 61
                                                                                                  • Next steps
                                                                                                  • State Stormwater policies
                                                                                                  • Slide Number 64

                                                                                                    51

                                                                                                    1 PlansWhat are you doing where is it going and does it fit

                                                                                                    2 ModellingDo you (or can you) meet BPEM requirements

                                                                                                    3 Written response to standardsHow does your proposal comply with the requirements

                                                                                                    52

                                                                                                    Application

                                                                                                    bull Site plan ndash show all assetsWSUD treatments and any IWM features on the site layout plan with everything else

                                                                                                    bull Landscape plan ndash if planting design passive irrigation etc forms part of response to requirements show

                                                                                                    bull Site management plan (depending on Council)

                                                                                                    bull Separate WSUDIWM plan showing all features on a stripped back background

                                                                                                    bull Concept WSUD asset design ndash larger assets only (wetlands bioretention basins sed basin etc) ndash sufficient design detail to confirm spatial requirements

                                                                                                    PlansPermit conditions

                                                                                                    bull Detailed engineering design bull Site Management Plan (final)bull Asset maintenance plan (final)bull Handover arrangements (if public)

                                                                                                    54

                                                                                                    STORM ndash Online toolbull Print out of STORM reportbull Make sure meets 100 or

                                                                                                    morebull Make sure report inputs and

                                                                                                    results match plan

                                                                                                    Modelling - SWQ

                                                                                                    MUSIC ndash Proprietary softwarebull Provide a copy of the model filebull Print out the modelling resultsbull Provide summary of your model

                                                                                                    inputs for each treatment train (iecatchment size impervious treatment area etc)

                                                                                                    bull Provide a print out of the model schematic

                                                                                                    Bonus points bull Provide details of model

                                                                                                    parametersbull Provide results of MUSIC auditor

                                                                                                    run (if using Melbourne Water MUSIC Guidelines)

                                                                                                    56

                                                                                                    Assessment against standards

                                                                                                    bull Say what you have done (or will do) to meet each standardbull Donrsquot forget (if WSUD) details of maintenance and asset

                                                                                                    ownershipbull Where applicable be explicit why yoursquove chosen (or not chosen) to

                                                                                                    respond the way you have Egbull Opportunitiesbull Site constraintsbull Practicaloperational issues bull Brief dot point summary of options analysis if complex

                                                                                                    bull Make sure if it doesnrsquot meet the standard it meets the objectivebull Make sure shown on plan and consistent with modelling and rest of

                                                                                                    documentation

                                                                                                    57

                                                                                                    Resources

                                                                                                    Local stormwaterWSUD policiesBaysideKingstonCaseyMonashMelbourneYarraMoonee ValleyPort PhilipStonningtonHumeCampaspeBass Coast

                                                                                                    Local ESD (including IWM) policies Greater BendigoGreater DandenongHobsons BayWhittleseaWyndhamWhitehorseManninghamMorelandDarebinBanyuleKnoxBrimbank

                                                                                                    Council planning resources

                                                                                                    Application resources ndashexamplesDELWP Practice Note ndashformal guide to the new controlsMoreland ndash application checklists and example plans for a variety of residential developmentsPort Philip ndash compliance guidelines checklist and examplesMoonee Valley ndash checklists and example plans including site management plans Greater Bendigo ndash WSUD kitBayside ndash application guidelines and example plans

                                                                                                    59

                                                                                                    Technical guidelines (modelling design construction)

                                                                                                    Melbourne Water

                                                                                                    STORM calculatorMUSIC auditor - lsquohow torsquo video here

                                                                                                    Melbourne Water technical guidelines page- WSUD asset life cycle costings and model maintenance guidelines- MUSIC guidelines- Stormwater harvesting guidelines- WSUD life cycle costings and

                                                                                                    maintenance guidelines- Design and construction guidelines

                                                                                                    for variety of assetshttpswwwmelbournewatercomauplanning-and-buildingdeveloper-guides-and-resourcesguidelines-drawings-and-checklistsguidelines

                                                                                                    Council

                                                                                                    South-Eastern Growth Council WSUD guidelines ndash note that some individual Councils have their own addendumsMelbournePort PhilipNorth-West Growth Council WSUD guidelines - note that some individual Councils have their own addendumsGreater BendigoMilduraBallaratBaw BawWyndhamMoreland ndash tree pits and raingardens

                                                                                                    60

                                                                                                    IWM

                                                                                                    Example Council IWM strategiesMelbourneCaseyMonashKingston

                                                                                                    Resilient Melbourne ndash IWM information lsquohubrsquoClearwater ndash capacity building and case studiesMelbourne Water ndash funding opportunities for IWM projects

                                                                                                    Stormwater offset schemes

                                                                                                    KingstonGreater GeelongMelbourne Water ndash non scheme contributions

                                                                                                    Site management

                                                                                                    EPA guidelines- management of erosion and sediment

                                                                                                    Next steps and other stormwater initiatives

                                                                                                    Emma Stewart DELWP

                                                                                                    62

                                                                                                    Next steps

                                                                                                    bull Trainingbull The EPArsquos BPEM Reviewbull Offsets policybull Review of STORM bull Building controls

                                                                                                    63

                                                                                                    State Stormwater policies

                                                                                                    64

                                                                                                    Thank you

                                                                                                    • Slide Number 1
                                                                                                    • Slide Number 2
                                                                                                    • History of WSUD
                                                                                                    • History of WSUD
                                                                                                    • Transformational change in urban water
                                                                                                    • Inconsistencies and inequities in our approach to stormwater management
                                                                                                    • Slide Number 8
                                                                                                    • Terms of Reference
                                                                                                    • Improving Stormwater Management Advisory Committee
                                                                                                    • Wide consultation
                                                                                                    • Stakeholder feedback
                                                                                                    • Stakeholder feedback
                                                                                                    • Committee submitted its report in September 2018
                                                                                                    • Committee Recomendations
                                                                                                    • Planning reforms
                                                                                                    • Future policy directions
                                                                                                    • Supporting actions
                                                                                                    • Slide Number 19
                                                                                                    • Government response (to date)
                                                                                                    • Longer term recommendations
                                                                                                    • State-based planning requirements (lsquobeforersquo)
                                                                                                    • State-based planning requirements (lsquoafterrsquo)
                                                                                                    • Development types (volume)
                                                                                                    • Slide Number 25
                                                                                                    • Amendment VC154
                                                                                                    • Whatrsquos in
                                                                                                    • Slide Number 28
                                                                                                    • Key elements of clauses
                                                                                                    • Clause 5318 ndash subdivision
                                                                                                    • Clause 5318 ndash Buildings and works
                                                                                                    • Townhouses - Standard B9
                                                                                                    • Slide Number 33
                                                                                                    • Slide Number 34
                                                                                                    • Slide Number 35
                                                                                                    • Slide Number 36
                                                                                                    • Slide Number 37
                                                                                                    • Buildings and works - Site management standard
                                                                                                    • Site management
                                                                                                    • Planning Advisory Note No 75
                                                                                                    • Slide Number 41
                                                                                                    • Slide Number 42
                                                                                                    • Slide Number 43
                                                                                                    • Slide Number 44
                                                                                                    • Slide Number 45
                                                                                                    • Slide Number 46
                                                                                                    • Slide Number 47
                                                                                                    • Slide Number 48
                                                                                                    • Slide Number 49
                                                                                                    • Slide Number 50
                                                                                                    • Slide Number 51
                                                                                                    • Slide Number 52
                                                                                                    • Slide Number 53
                                                                                                    • Slide Number 54
                                                                                                    • Slide Number 55
                                                                                                    • Slide Number 56
                                                                                                    • Slide Number 57
                                                                                                    • Slide Number 58
                                                                                                    • Slide Number 59
                                                                                                    • Slide Number 60
                                                                                                    • Slide Number 61
                                                                                                    • Next steps
                                                                                                    • State Stormwater policies
                                                                                                    • Slide Number 64

                                                                                                      52

                                                                                                      Application

                                                                                                      bull Site plan ndash show all assetsWSUD treatments and any IWM features on the site layout plan with everything else

                                                                                                      bull Landscape plan ndash if planting design passive irrigation etc forms part of response to requirements show

                                                                                                      bull Site management plan (depending on Council)

                                                                                                      bull Separate WSUDIWM plan showing all features on a stripped back background

                                                                                                      bull Concept WSUD asset design ndash larger assets only (wetlands bioretention basins sed basin etc) ndash sufficient design detail to confirm spatial requirements

                                                                                                      PlansPermit conditions

                                                                                                      bull Detailed engineering design bull Site Management Plan (final)bull Asset maintenance plan (final)bull Handover arrangements (if public)

                                                                                                      54

                                                                                                      STORM ndash Online toolbull Print out of STORM reportbull Make sure meets 100 or

                                                                                                      morebull Make sure report inputs and

                                                                                                      results match plan

                                                                                                      Modelling - SWQ

                                                                                                      MUSIC ndash Proprietary softwarebull Provide a copy of the model filebull Print out the modelling resultsbull Provide summary of your model

                                                                                                      inputs for each treatment train (iecatchment size impervious treatment area etc)

                                                                                                      bull Provide a print out of the model schematic

                                                                                                      Bonus points bull Provide details of model

                                                                                                      parametersbull Provide results of MUSIC auditor

                                                                                                      run (if using Melbourne Water MUSIC Guidelines)

                                                                                                      56

                                                                                                      Assessment against standards

                                                                                                      bull Say what you have done (or will do) to meet each standardbull Donrsquot forget (if WSUD) details of maintenance and asset

                                                                                                      ownershipbull Where applicable be explicit why yoursquove chosen (or not chosen) to

                                                                                                      respond the way you have Egbull Opportunitiesbull Site constraintsbull Practicaloperational issues bull Brief dot point summary of options analysis if complex

                                                                                                      bull Make sure if it doesnrsquot meet the standard it meets the objectivebull Make sure shown on plan and consistent with modelling and rest of

                                                                                                      documentation

                                                                                                      57

                                                                                                      Resources

                                                                                                      Local stormwaterWSUD policiesBaysideKingstonCaseyMonashMelbourneYarraMoonee ValleyPort PhilipStonningtonHumeCampaspeBass Coast

                                                                                                      Local ESD (including IWM) policies Greater BendigoGreater DandenongHobsons BayWhittleseaWyndhamWhitehorseManninghamMorelandDarebinBanyuleKnoxBrimbank

                                                                                                      Council planning resources

                                                                                                      Application resources ndashexamplesDELWP Practice Note ndashformal guide to the new controlsMoreland ndash application checklists and example plans for a variety of residential developmentsPort Philip ndash compliance guidelines checklist and examplesMoonee Valley ndash checklists and example plans including site management plans Greater Bendigo ndash WSUD kitBayside ndash application guidelines and example plans

                                                                                                      59

                                                                                                      Technical guidelines (modelling design construction)

                                                                                                      Melbourne Water

                                                                                                      STORM calculatorMUSIC auditor - lsquohow torsquo video here

                                                                                                      Melbourne Water technical guidelines page- WSUD asset life cycle costings and model maintenance guidelines- MUSIC guidelines- Stormwater harvesting guidelines- WSUD life cycle costings and

                                                                                                      maintenance guidelines- Design and construction guidelines

                                                                                                      for variety of assetshttpswwwmelbournewatercomauplanning-and-buildingdeveloper-guides-and-resourcesguidelines-drawings-and-checklistsguidelines

                                                                                                      Council

                                                                                                      South-Eastern Growth Council WSUD guidelines ndash note that some individual Councils have their own addendumsMelbournePort PhilipNorth-West Growth Council WSUD guidelines - note that some individual Councils have their own addendumsGreater BendigoMilduraBallaratBaw BawWyndhamMoreland ndash tree pits and raingardens

                                                                                                      60

                                                                                                      IWM

                                                                                                      Example Council IWM strategiesMelbourneCaseyMonashKingston

                                                                                                      Resilient Melbourne ndash IWM information lsquohubrsquoClearwater ndash capacity building and case studiesMelbourne Water ndash funding opportunities for IWM projects

                                                                                                      Stormwater offset schemes

                                                                                                      KingstonGreater GeelongMelbourne Water ndash non scheme contributions

                                                                                                      Site management

                                                                                                      EPA guidelines- management of erosion and sediment

                                                                                                      Next steps and other stormwater initiatives

                                                                                                      Emma Stewart DELWP

                                                                                                      62

                                                                                                      Next steps

                                                                                                      bull Trainingbull The EPArsquos BPEM Reviewbull Offsets policybull Review of STORM bull Building controls

                                                                                                      63

                                                                                                      State Stormwater policies

                                                                                                      64

                                                                                                      Thank you

                                                                                                      • Slide Number 1
                                                                                                      • Slide Number 2
                                                                                                      • History of WSUD
                                                                                                      • History of WSUD
                                                                                                      • Transformational change in urban water
                                                                                                      • Inconsistencies and inequities in our approach to stormwater management
                                                                                                      • Slide Number 8
                                                                                                      • Terms of Reference
                                                                                                      • Improving Stormwater Management Advisory Committee
                                                                                                      • Wide consultation
                                                                                                      • Stakeholder feedback
                                                                                                      • Stakeholder feedback
                                                                                                      • Committee submitted its report in September 2018
                                                                                                      • Committee Recomendations
                                                                                                      • Planning reforms
                                                                                                      • Future policy directions
                                                                                                      • Supporting actions
                                                                                                      • Slide Number 19
                                                                                                      • Government response (to date)
                                                                                                      • Longer term recommendations
                                                                                                      • State-based planning requirements (lsquobeforersquo)
                                                                                                      • State-based planning requirements (lsquoafterrsquo)
                                                                                                      • Development types (volume)
                                                                                                      • Slide Number 25
                                                                                                      • Amendment VC154
                                                                                                      • Whatrsquos in
                                                                                                      • Slide Number 28
                                                                                                      • Key elements of clauses
                                                                                                      • Clause 5318 ndash subdivision
                                                                                                      • Clause 5318 ndash Buildings and works
                                                                                                      • Townhouses - Standard B9
                                                                                                      • Slide Number 33
                                                                                                      • Slide Number 34
                                                                                                      • Slide Number 35
                                                                                                      • Slide Number 36
                                                                                                      • Slide Number 37
                                                                                                      • Buildings and works - Site management standard
                                                                                                      • Site management
                                                                                                      • Planning Advisory Note No 75
                                                                                                      • Slide Number 41
                                                                                                      • Slide Number 42
                                                                                                      • Slide Number 43
                                                                                                      • Slide Number 44
                                                                                                      • Slide Number 45
                                                                                                      • Slide Number 46
                                                                                                      • Slide Number 47
                                                                                                      • Slide Number 48
                                                                                                      • Slide Number 49
                                                                                                      • Slide Number 50
                                                                                                      • Slide Number 51
                                                                                                      • Slide Number 52
                                                                                                      • Slide Number 53
                                                                                                      • Slide Number 54
                                                                                                      • Slide Number 55
                                                                                                      • Slide Number 56
                                                                                                      • Slide Number 57
                                                                                                      • Slide Number 58
                                                                                                      • Slide Number 59
                                                                                                      • Slide Number 60
                                                                                                      • Slide Number 61
                                                                                                      • Next steps
                                                                                                      • State Stormwater policies
                                                                                                      • Slide Number 64

                                                                                                        54

                                                                                                        STORM ndash Online toolbull Print out of STORM reportbull Make sure meets 100 or

                                                                                                        morebull Make sure report inputs and

                                                                                                        results match plan

                                                                                                        Modelling - SWQ

                                                                                                        MUSIC ndash Proprietary softwarebull Provide a copy of the model filebull Print out the modelling resultsbull Provide summary of your model

                                                                                                        inputs for each treatment train (iecatchment size impervious treatment area etc)

                                                                                                        bull Provide a print out of the model schematic

                                                                                                        Bonus points bull Provide details of model

                                                                                                        parametersbull Provide results of MUSIC auditor

                                                                                                        run (if using Melbourne Water MUSIC Guidelines)

                                                                                                        56

                                                                                                        Assessment against standards

                                                                                                        bull Say what you have done (or will do) to meet each standardbull Donrsquot forget (if WSUD) details of maintenance and asset

                                                                                                        ownershipbull Where applicable be explicit why yoursquove chosen (or not chosen) to

                                                                                                        respond the way you have Egbull Opportunitiesbull Site constraintsbull Practicaloperational issues bull Brief dot point summary of options analysis if complex

                                                                                                        bull Make sure if it doesnrsquot meet the standard it meets the objectivebull Make sure shown on plan and consistent with modelling and rest of

                                                                                                        documentation

                                                                                                        57

                                                                                                        Resources

                                                                                                        Local stormwaterWSUD policiesBaysideKingstonCaseyMonashMelbourneYarraMoonee ValleyPort PhilipStonningtonHumeCampaspeBass Coast

                                                                                                        Local ESD (including IWM) policies Greater BendigoGreater DandenongHobsons BayWhittleseaWyndhamWhitehorseManninghamMorelandDarebinBanyuleKnoxBrimbank

                                                                                                        Council planning resources

                                                                                                        Application resources ndashexamplesDELWP Practice Note ndashformal guide to the new controlsMoreland ndash application checklists and example plans for a variety of residential developmentsPort Philip ndash compliance guidelines checklist and examplesMoonee Valley ndash checklists and example plans including site management plans Greater Bendigo ndash WSUD kitBayside ndash application guidelines and example plans

                                                                                                        59

                                                                                                        Technical guidelines (modelling design construction)

                                                                                                        Melbourne Water

                                                                                                        STORM calculatorMUSIC auditor - lsquohow torsquo video here

                                                                                                        Melbourne Water technical guidelines page- WSUD asset life cycle costings and model maintenance guidelines- MUSIC guidelines- Stormwater harvesting guidelines- WSUD life cycle costings and

                                                                                                        maintenance guidelines- Design and construction guidelines

                                                                                                        for variety of assetshttpswwwmelbournewatercomauplanning-and-buildingdeveloper-guides-and-resourcesguidelines-drawings-and-checklistsguidelines

                                                                                                        Council

                                                                                                        South-Eastern Growth Council WSUD guidelines ndash note that some individual Councils have their own addendumsMelbournePort PhilipNorth-West Growth Council WSUD guidelines - note that some individual Councils have their own addendumsGreater BendigoMilduraBallaratBaw BawWyndhamMoreland ndash tree pits and raingardens

                                                                                                        60

                                                                                                        IWM

                                                                                                        Example Council IWM strategiesMelbourneCaseyMonashKingston

                                                                                                        Resilient Melbourne ndash IWM information lsquohubrsquoClearwater ndash capacity building and case studiesMelbourne Water ndash funding opportunities for IWM projects

                                                                                                        Stormwater offset schemes

                                                                                                        KingstonGreater GeelongMelbourne Water ndash non scheme contributions

                                                                                                        Site management

                                                                                                        EPA guidelines- management of erosion and sediment

                                                                                                        Next steps and other stormwater initiatives

                                                                                                        Emma Stewart DELWP

                                                                                                        62

                                                                                                        Next steps

                                                                                                        bull Trainingbull The EPArsquos BPEM Reviewbull Offsets policybull Review of STORM bull Building controls

                                                                                                        63

                                                                                                        State Stormwater policies

                                                                                                        64

                                                                                                        Thank you

                                                                                                        • Slide Number 1
                                                                                                        • Slide Number 2
                                                                                                        • History of WSUD
                                                                                                        • History of WSUD
                                                                                                        • Transformational change in urban water
                                                                                                        • Inconsistencies and inequities in our approach to stormwater management
                                                                                                        • Slide Number 8
                                                                                                        • Terms of Reference
                                                                                                        • Improving Stormwater Management Advisory Committee
                                                                                                        • Wide consultation
                                                                                                        • Stakeholder feedback
                                                                                                        • Stakeholder feedback
                                                                                                        • Committee submitted its report in September 2018
                                                                                                        • Committee Recomendations
                                                                                                        • Planning reforms
                                                                                                        • Future policy directions
                                                                                                        • Supporting actions
                                                                                                        • Slide Number 19
                                                                                                        • Government response (to date)
                                                                                                        • Longer term recommendations
                                                                                                        • State-based planning requirements (lsquobeforersquo)
                                                                                                        • State-based planning requirements (lsquoafterrsquo)
                                                                                                        • Development types (volume)
                                                                                                        • Slide Number 25
                                                                                                        • Amendment VC154
                                                                                                        • Whatrsquos in
                                                                                                        • Slide Number 28
                                                                                                        • Key elements of clauses
                                                                                                        • Clause 5318 ndash subdivision
                                                                                                        • Clause 5318 ndash Buildings and works
                                                                                                        • Townhouses - Standard B9
                                                                                                        • Slide Number 33
                                                                                                        • Slide Number 34
                                                                                                        • Slide Number 35
                                                                                                        • Slide Number 36
                                                                                                        • Slide Number 37
                                                                                                        • Buildings and works - Site management standard
                                                                                                        • Site management
                                                                                                        • Planning Advisory Note No 75
                                                                                                        • Slide Number 41
                                                                                                        • Slide Number 42
                                                                                                        • Slide Number 43
                                                                                                        • Slide Number 44
                                                                                                        • Slide Number 45
                                                                                                        • Slide Number 46
                                                                                                        • Slide Number 47
                                                                                                        • Slide Number 48
                                                                                                        • Slide Number 49
                                                                                                        • Slide Number 50
                                                                                                        • Slide Number 51
                                                                                                        • Slide Number 52
                                                                                                        • Slide Number 53
                                                                                                        • Slide Number 54
                                                                                                        • Slide Number 55
                                                                                                        • Slide Number 56
                                                                                                        • Slide Number 57
                                                                                                        • Slide Number 58
                                                                                                        • Slide Number 59
                                                                                                        • Slide Number 60
                                                                                                        • Slide Number 61
                                                                                                        • Next steps
                                                                                                        • State Stormwater policies
                                                                                                        • Slide Number 64

                                                                                                          56

                                                                                                          Assessment against standards

                                                                                                          bull Say what you have done (or will do) to meet each standardbull Donrsquot forget (if WSUD) details of maintenance and asset

                                                                                                          ownershipbull Where applicable be explicit why yoursquove chosen (or not chosen) to

                                                                                                          respond the way you have Egbull Opportunitiesbull Site constraintsbull Practicaloperational issues bull Brief dot point summary of options analysis if complex

                                                                                                          bull Make sure if it doesnrsquot meet the standard it meets the objectivebull Make sure shown on plan and consistent with modelling and rest of

                                                                                                          documentation

                                                                                                          57

                                                                                                          Resources

                                                                                                          Local stormwaterWSUD policiesBaysideKingstonCaseyMonashMelbourneYarraMoonee ValleyPort PhilipStonningtonHumeCampaspeBass Coast

                                                                                                          Local ESD (including IWM) policies Greater BendigoGreater DandenongHobsons BayWhittleseaWyndhamWhitehorseManninghamMorelandDarebinBanyuleKnoxBrimbank

                                                                                                          Council planning resources

                                                                                                          Application resources ndashexamplesDELWP Practice Note ndashformal guide to the new controlsMoreland ndash application checklists and example plans for a variety of residential developmentsPort Philip ndash compliance guidelines checklist and examplesMoonee Valley ndash checklists and example plans including site management plans Greater Bendigo ndash WSUD kitBayside ndash application guidelines and example plans

                                                                                                          59

                                                                                                          Technical guidelines (modelling design construction)

                                                                                                          Melbourne Water

                                                                                                          STORM calculatorMUSIC auditor - lsquohow torsquo video here

                                                                                                          Melbourne Water technical guidelines page- WSUD asset life cycle costings and model maintenance guidelines- MUSIC guidelines- Stormwater harvesting guidelines- WSUD life cycle costings and

                                                                                                          maintenance guidelines- Design and construction guidelines

                                                                                                          for variety of assetshttpswwwmelbournewatercomauplanning-and-buildingdeveloper-guides-and-resourcesguidelines-drawings-and-checklistsguidelines

                                                                                                          Council

                                                                                                          South-Eastern Growth Council WSUD guidelines ndash note that some individual Councils have their own addendumsMelbournePort PhilipNorth-West Growth Council WSUD guidelines - note that some individual Councils have their own addendumsGreater BendigoMilduraBallaratBaw BawWyndhamMoreland ndash tree pits and raingardens

                                                                                                          60

                                                                                                          IWM

                                                                                                          Example Council IWM strategiesMelbourneCaseyMonashKingston

                                                                                                          Resilient Melbourne ndash IWM information lsquohubrsquoClearwater ndash capacity building and case studiesMelbourne Water ndash funding opportunities for IWM projects

                                                                                                          Stormwater offset schemes

                                                                                                          KingstonGreater GeelongMelbourne Water ndash non scheme contributions

                                                                                                          Site management

                                                                                                          EPA guidelines- management of erosion and sediment

                                                                                                          Next steps and other stormwater initiatives

                                                                                                          Emma Stewart DELWP

                                                                                                          62

                                                                                                          Next steps

                                                                                                          bull Trainingbull The EPArsquos BPEM Reviewbull Offsets policybull Review of STORM bull Building controls

                                                                                                          63

                                                                                                          State Stormwater policies

                                                                                                          64

                                                                                                          Thank you

                                                                                                          • Slide Number 1
                                                                                                          • Slide Number 2
                                                                                                          • History of WSUD
                                                                                                          • History of WSUD
                                                                                                          • Transformational change in urban water
                                                                                                          • Inconsistencies and inequities in our approach to stormwater management
                                                                                                          • Slide Number 8
                                                                                                          • Terms of Reference
                                                                                                          • Improving Stormwater Management Advisory Committee
                                                                                                          • Wide consultation
                                                                                                          • Stakeholder feedback
                                                                                                          • Stakeholder feedback
                                                                                                          • Committee submitted its report in September 2018
                                                                                                          • Committee Recomendations
                                                                                                          • Planning reforms
                                                                                                          • Future policy directions
                                                                                                          • Supporting actions
                                                                                                          • Slide Number 19
                                                                                                          • Government response (to date)
                                                                                                          • Longer term recommendations
                                                                                                          • State-based planning requirements (lsquobeforersquo)
                                                                                                          • State-based planning requirements (lsquoafterrsquo)
                                                                                                          • Development types (volume)
                                                                                                          • Slide Number 25
                                                                                                          • Amendment VC154
                                                                                                          • Whatrsquos in
                                                                                                          • Slide Number 28
                                                                                                          • Key elements of clauses
                                                                                                          • Clause 5318 ndash subdivision
                                                                                                          • Clause 5318 ndash Buildings and works
                                                                                                          • Townhouses - Standard B9
                                                                                                          • Slide Number 33
                                                                                                          • Slide Number 34
                                                                                                          • Slide Number 35
                                                                                                          • Slide Number 36
                                                                                                          • Slide Number 37
                                                                                                          • Buildings and works - Site management standard
                                                                                                          • Site management
                                                                                                          • Planning Advisory Note No 75
                                                                                                          • Slide Number 41
                                                                                                          • Slide Number 42
                                                                                                          • Slide Number 43
                                                                                                          • Slide Number 44
                                                                                                          • Slide Number 45
                                                                                                          • Slide Number 46
                                                                                                          • Slide Number 47
                                                                                                          • Slide Number 48
                                                                                                          • Slide Number 49
                                                                                                          • Slide Number 50
                                                                                                          • Slide Number 51
                                                                                                          • Slide Number 52
                                                                                                          • Slide Number 53
                                                                                                          • Slide Number 54
                                                                                                          • Slide Number 55
                                                                                                          • Slide Number 56
                                                                                                          • Slide Number 57
                                                                                                          • Slide Number 58
                                                                                                          • Slide Number 59
                                                                                                          • Slide Number 60
                                                                                                          • Slide Number 61
                                                                                                          • Next steps
                                                                                                          • State Stormwater policies
                                                                                                          • Slide Number 64

                                                                                                            57

                                                                                                            Resources

                                                                                                            Local stormwaterWSUD policiesBaysideKingstonCaseyMonashMelbourneYarraMoonee ValleyPort PhilipStonningtonHumeCampaspeBass Coast

                                                                                                            Local ESD (including IWM) policies Greater BendigoGreater DandenongHobsons BayWhittleseaWyndhamWhitehorseManninghamMorelandDarebinBanyuleKnoxBrimbank

                                                                                                            Council planning resources

                                                                                                            Application resources ndashexamplesDELWP Practice Note ndashformal guide to the new controlsMoreland ndash application checklists and example plans for a variety of residential developmentsPort Philip ndash compliance guidelines checklist and examplesMoonee Valley ndash checklists and example plans including site management plans Greater Bendigo ndash WSUD kitBayside ndash application guidelines and example plans

                                                                                                            59

                                                                                                            Technical guidelines (modelling design construction)

                                                                                                            Melbourne Water

                                                                                                            STORM calculatorMUSIC auditor - lsquohow torsquo video here

                                                                                                            Melbourne Water technical guidelines page- WSUD asset life cycle costings and model maintenance guidelines- MUSIC guidelines- Stormwater harvesting guidelines- WSUD life cycle costings and

                                                                                                            maintenance guidelines- Design and construction guidelines

                                                                                                            for variety of assetshttpswwwmelbournewatercomauplanning-and-buildingdeveloper-guides-and-resourcesguidelines-drawings-and-checklistsguidelines

                                                                                                            Council

                                                                                                            South-Eastern Growth Council WSUD guidelines ndash note that some individual Councils have their own addendumsMelbournePort PhilipNorth-West Growth Council WSUD guidelines - note that some individual Councils have their own addendumsGreater BendigoMilduraBallaratBaw BawWyndhamMoreland ndash tree pits and raingardens

                                                                                                            60

                                                                                                            IWM

                                                                                                            Example Council IWM strategiesMelbourneCaseyMonashKingston

                                                                                                            Resilient Melbourne ndash IWM information lsquohubrsquoClearwater ndash capacity building and case studiesMelbourne Water ndash funding opportunities for IWM projects

                                                                                                            Stormwater offset schemes

                                                                                                            KingstonGreater GeelongMelbourne Water ndash non scheme contributions

                                                                                                            Site management

                                                                                                            EPA guidelines- management of erosion and sediment

                                                                                                            Next steps and other stormwater initiatives

                                                                                                            Emma Stewart DELWP

                                                                                                            62

                                                                                                            Next steps

                                                                                                            bull Trainingbull The EPArsquos BPEM Reviewbull Offsets policybull Review of STORM bull Building controls

                                                                                                            63

                                                                                                            State Stormwater policies

                                                                                                            64

                                                                                                            Thank you

                                                                                                            • Slide Number 1
                                                                                                            • Slide Number 2
                                                                                                            • History of WSUD
                                                                                                            • History of WSUD
                                                                                                            • Transformational change in urban water
                                                                                                            • Inconsistencies and inequities in our approach to stormwater management
                                                                                                            • Slide Number 8
                                                                                                            • Terms of Reference
                                                                                                            • Improving Stormwater Management Advisory Committee
                                                                                                            • Wide consultation
                                                                                                            • Stakeholder feedback
                                                                                                            • Stakeholder feedback
                                                                                                            • Committee submitted its report in September 2018
                                                                                                            • Committee Recomendations
                                                                                                            • Planning reforms
                                                                                                            • Future policy directions
                                                                                                            • Supporting actions
                                                                                                            • Slide Number 19
                                                                                                            • Government response (to date)
                                                                                                            • Longer term recommendations
                                                                                                            • State-based planning requirements (lsquobeforersquo)
                                                                                                            • State-based planning requirements (lsquoafterrsquo)
                                                                                                            • Development types (volume)
                                                                                                            • Slide Number 25
                                                                                                            • Amendment VC154
                                                                                                            • Whatrsquos in
                                                                                                            • Slide Number 28
                                                                                                            • Key elements of clauses
                                                                                                            • Clause 5318 ndash subdivision
                                                                                                            • Clause 5318 ndash Buildings and works
                                                                                                            • Townhouses - Standard B9
                                                                                                            • Slide Number 33
                                                                                                            • Slide Number 34
                                                                                                            • Slide Number 35
                                                                                                            • Slide Number 36
                                                                                                            • Slide Number 37
                                                                                                            • Buildings and works - Site management standard
                                                                                                            • Site management
                                                                                                            • Planning Advisory Note No 75
                                                                                                            • Slide Number 41
                                                                                                            • Slide Number 42
                                                                                                            • Slide Number 43
                                                                                                            • Slide Number 44
                                                                                                            • Slide Number 45
                                                                                                            • Slide Number 46
                                                                                                            • Slide Number 47
                                                                                                            • Slide Number 48
                                                                                                            • Slide Number 49
                                                                                                            • Slide Number 50
                                                                                                            • Slide Number 51
                                                                                                            • Slide Number 52
                                                                                                            • Slide Number 53
                                                                                                            • Slide Number 54
                                                                                                            • Slide Number 55
                                                                                                            • Slide Number 56
                                                                                                            • Slide Number 57
                                                                                                            • Slide Number 58
                                                                                                            • Slide Number 59
                                                                                                            • Slide Number 60
                                                                                                            • Slide Number 61
                                                                                                            • Next steps
                                                                                                            • State Stormwater policies
                                                                                                            • Slide Number 64

                                                                                                              Resources

                                                                                                              Local stormwaterWSUD policiesBaysideKingstonCaseyMonashMelbourneYarraMoonee ValleyPort PhilipStonningtonHumeCampaspeBass Coast

                                                                                                              Local ESD (including IWM) policies Greater BendigoGreater DandenongHobsons BayWhittleseaWyndhamWhitehorseManninghamMorelandDarebinBanyuleKnoxBrimbank

                                                                                                              Council planning resources

                                                                                                              Application resources ndashexamplesDELWP Practice Note ndashformal guide to the new controlsMoreland ndash application checklists and example plans for a variety of residential developmentsPort Philip ndash compliance guidelines checklist and examplesMoonee Valley ndash checklists and example plans including site management plans Greater Bendigo ndash WSUD kitBayside ndash application guidelines and example plans

                                                                                                              59

                                                                                                              Technical guidelines (modelling design construction)

                                                                                                              Melbourne Water

                                                                                                              STORM calculatorMUSIC auditor - lsquohow torsquo video here

                                                                                                              Melbourne Water technical guidelines page- WSUD asset life cycle costings and model maintenance guidelines- MUSIC guidelines- Stormwater harvesting guidelines- WSUD life cycle costings and

                                                                                                              maintenance guidelines- Design and construction guidelines

                                                                                                              for variety of assetshttpswwwmelbournewatercomauplanning-and-buildingdeveloper-guides-and-resourcesguidelines-drawings-and-checklistsguidelines

                                                                                                              Council

                                                                                                              South-Eastern Growth Council WSUD guidelines ndash note that some individual Councils have their own addendumsMelbournePort PhilipNorth-West Growth Council WSUD guidelines - note that some individual Councils have their own addendumsGreater BendigoMilduraBallaratBaw BawWyndhamMoreland ndash tree pits and raingardens

                                                                                                              60

                                                                                                              IWM

                                                                                                              Example Council IWM strategiesMelbourneCaseyMonashKingston

                                                                                                              Resilient Melbourne ndash IWM information lsquohubrsquoClearwater ndash capacity building and case studiesMelbourne Water ndash funding opportunities for IWM projects

                                                                                                              Stormwater offset schemes

                                                                                                              KingstonGreater GeelongMelbourne Water ndash non scheme contributions

                                                                                                              Site management

                                                                                                              EPA guidelines- management of erosion and sediment

                                                                                                              Next steps and other stormwater initiatives

                                                                                                              Emma Stewart DELWP

                                                                                                              62

                                                                                                              Next steps

                                                                                                              bull Trainingbull The EPArsquos BPEM Reviewbull Offsets policybull Review of STORM bull Building controls

                                                                                                              63

                                                                                                              State Stormwater policies

                                                                                                              64

                                                                                                              Thank you

                                                                                                              • Slide Number 1
                                                                                                              • Slide Number 2
                                                                                                              • History of WSUD
                                                                                                              • History of WSUD
                                                                                                              • Transformational change in urban water
                                                                                                              • Inconsistencies and inequities in our approach to stormwater management
                                                                                                              • Slide Number 8
                                                                                                              • Terms of Reference
                                                                                                              • Improving Stormwater Management Advisory Committee
                                                                                                              • Wide consultation
                                                                                                              • Stakeholder feedback
                                                                                                              • Stakeholder feedback
                                                                                                              • Committee submitted its report in September 2018
                                                                                                              • Committee Recomendations
                                                                                                              • Planning reforms
                                                                                                              • Future policy directions
                                                                                                              • Supporting actions
                                                                                                              • Slide Number 19
                                                                                                              • Government response (to date)
                                                                                                              • Longer term recommendations
                                                                                                              • State-based planning requirements (lsquobeforersquo)
                                                                                                              • State-based planning requirements (lsquoafterrsquo)
                                                                                                              • Development types (volume)
                                                                                                              • Slide Number 25
                                                                                                              • Amendment VC154
                                                                                                              • Whatrsquos in
                                                                                                              • Slide Number 28
                                                                                                              • Key elements of clauses
                                                                                                              • Clause 5318 ndash subdivision
                                                                                                              • Clause 5318 ndash Buildings and works
                                                                                                              • Townhouses - Standard B9
                                                                                                              • Slide Number 33
                                                                                                              • Slide Number 34
                                                                                                              • Slide Number 35
                                                                                                              • Slide Number 36
                                                                                                              • Slide Number 37
                                                                                                              • Buildings and works - Site management standard
                                                                                                              • Site management
                                                                                                              • Planning Advisory Note No 75
                                                                                                              • Slide Number 41
                                                                                                              • Slide Number 42
                                                                                                              • Slide Number 43
                                                                                                              • Slide Number 44
                                                                                                              • Slide Number 45
                                                                                                              • Slide Number 46
                                                                                                              • Slide Number 47
                                                                                                              • Slide Number 48
                                                                                                              • Slide Number 49
                                                                                                              • Slide Number 50
                                                                                                              • Slide Number 51
                                                                                                              • Slide Number 52
                                                                                                              • Slide Number 53
                                                                                                              • Slide Number 54
                                                                                                              • Slide Number 55
                                                                                                              • Slide Number 56
                                                                                                              • Slide Number 57
                                                                                                              • Slide Number 58
                                                                                                              • Slide Number 59
                                                                                                              • Slide Number 60
                                                                                                              • Slide Number 61
                                                                                                              • Next steps
                                                                                                              • State Stormwater policies
                                                                                                              • Slide Number 64

                                                                                                                59

                                                                                                                Technical guidelines (modelling design construction)

                                                                                                                Melbourne Water

                                                                                                                STORM calculatorMUSIC auditor - lsquohow torsquo video here

                                                                                                                Melbourne Water technical guidelines page- WSUD asset life cycle costings and model maintenance guidelines- MUSIC guidelines- Stormwater harvesting guidelines- WSUD life cycle costings and

                                                                                                                maintenance guidelines- Design and construction guidelines

                                                                                                                for variety of assetshttpswwwmelbournewatercomauplanning-and-buildingdeveloper-guides-and-resourcesguidelines-drawings-and-checklistsguidelines

                                                                                                                Council

                                                                                                                South-Eastern Growth Council WSUD guidelines ndash note that some individual Councils have their own addendumsMelbournePort PhilipNorth-West Growth Council WSUD guidelines - note that some individual Councils have their own addendumsGreater BendigoMilduraBallaratBaw BawWyndhamMoreland ndash tree pits and raingardens

                                                                                                                60

                                                                                                                IWM

                                                                                                                Example Council IWM strategiesMelbourneCaseyMonashKingston

                                                                                                                Resilient Melbourne ndash IWM information lsquohubrsquoClearwater ndash capacity building and case studiesMelbourne Water ndash funding opportunities for IWM projects

                                                                                                                Stormwater offset schemes

                                                                                                                KingstonGreater GeelongMelbourne Water ndash non scheme contributions

                                                                                                                Site management

                                                                                                                EPA guidelines- management of erosion and sediment

                                                                                                                Next steps and other stormwater initiatives

                                                                                                                Emma Stewart DELWP

                                                                                                                62

                                                                                                                Next steps

                                                                                                                bull Trainingbull The EPArsquos BPEM Reviewbull Offsets policybull Review of STORM bull Building controls

                                                                                                                63

                                                                                                                State Stormwater policies

                                                                                                                64

                                                                                                                Thank you

                                                                                                                • Slide Number 1
                                                                                                                • Slide Number 2
                                                                                                                • History of WSUD
                                                                                                                • History of WSUD
                                                                                                                • Transformational change in urban water
                                                                                                                • Inconsistencies and inequities in our approach to stormwater management
                                                                                                                • Slide Number 8
                                                                                                                • Terms of Reference
                                                                                                                • Improving Stormwater Management Advisory Committee
                                                                                                                • Wide consultation
                                                                                                                • Stakeholder feedback
                                                                                                                • Stakeholder feedback
                                                                                                                • Committee submitted its report in September 2018
                                                                                                                • Committee Recomendations
                                                                                                                • Planning reforms
                                                                                                                • Future policy directions
                                                                                                                • Supporting actions
                                                                                                                • Slide Number 19
                                                                                                                • Government response (to date)
                                                                                                                • Longer term recommendations
                                                                                                                • State-based planning requirements (lsquobeforersquo)
                                                                                                                • State-based planning requirements (lsquoafterrsquo)
                                                                                                                • Development types (volume)
                                                                                                                • Slide Number 25
                                                                                                                • Amendment VC154
                                                                                                                • Whatrsquos in
                                                                                                                • Slide Number 28
                                                                                                                • Key elements of clauses
                                                                                                                • Clause 5318 ndash subdivision
                                                                                                                • Clause 5318 ndash Buildings and works
                                                                                                                • Townhouses - Standard B9
                                                                                                                • Slide Number 33
                                                                                                                • Slide Number 34
                                                                                                                • Slide Number 35
                                                                                                                • Slide Number 36
                                                                                                                • Slide Number 37
                                                                                                                • Buildings and works - Site management standard
                                                                                                                • Site management
                                                                                                                • Planning Advisory Note No 75
                                                                                                                • Slide Number 41
                                                                                                                • Slide Number 42
                                                                                                                • Slide Number 43
                                                                                                                • Slide Number 44
                                                                                                                • Slide Number 45
                                                                                                                • Slide Number 46
                                                                                                                • Slide Number 47
                                                                                                                • Slide Number 48
                                                                                                                • Slide Number 49
                                                                                                                • Slide Number 50
                                                                                                                • Slide Number 51
                                                                                                                • Slide Number 52
                                                                                                                • Slide Number 53
                                                                                                                • Slide Number 54
                                                                                                                • Slide Number 55
                                                                                                                • Slide Number 56
                                                                                                                • Slide Number 57
                                                                                                                • Slide Number 58
                                                                                                                • Slide Number 59
                                                                                                                • Slide Number 60
                                                                                                                • Slide Number 61
                                                                                                                • Next steps
                                                                                                                • State Stormwater policies
                                                                                                                • Slide Number 64

                                                                                                                  60

                                                                                                                  IWM

                                                                                                                  Example Council IWM strategiesMelbourneCaseyMonashKingston

                                                                                                                  Resilient Melbourne ndash IWM information lsquohubrsquoClearwater ndash capacity building and case studiesMelbourne Water ndash funding opportunities for IWM projects

                                                                                                                  Stormwater offset schemes

                                                                                                                  KingstonGreater GeelongMelbourne Water ndash non scheme contributions

                                                                                                                  Site management

                                                                                                                  EPA guidelines- management of erosion and sediment

                                                                                                                  Next steps and other stormwater initiatives

                                                                                                                  Emma Stewart DELWP

                                                                                                                  62

                                                                                                                  Next steps

                                                                                                                  bull Trainingbull The EPArsquos BPEM Reviewbull Offsets policybull Review of STORM bull Building controls

                                                                                                                  63

                                                                                                                  State Stormwater policies

                                                                                                                  64

                                                                                                                  Thank you

                                                                                                                  • Slide Number 1
                                                                                                                  • Slide Number 2
                                                                                                                  • History of WSUD
                                                                                                                  • History of WSUD
                                                                                                                  • Transformational change in urban water
                                                                                                                  • Inconsistencies and inequities in our approach to stormwater management
                                                                                                                  • Slide Number 8
                                                                                                                  • Terms of Reference
                                                                                                                  • Improving Stormwater Management Advisory Committee
                                                                                                                  • Wide consultation
                                                                                                                  • Stakeholder feedback
                                                                                                                  • Stakeholder feedback
                                                                                                                  • Committee submitted its report in September 2018
                                                                                                                  • Committee Recomendations
                                                                                                                  • Planning reforms
                                                                                                                  • Future policy directions
                                                                                                                  • Supporting actions
                                                                                                                  • Slide Number 19
                                                                                                                  • Government response (to date)
                                                                                                                  • Longer term recommendations
                                                                                                                  • State-based planning requirements (lsquobeforersquo)
                                                                                                                  • State-based planning requirements (lsquoafterrsquo)
                                                                                                                  • Development types (volume)
                                                                                                                  • Slide Number 25
                                                                                                                  • Amendment VC154
                                                                                                                  • Whatrsquos in
                                                                                                                  • Slide Number 28
                                                                                                                  • Key elements of clauses
                                                                                                                  • Clause 5318 ndash subdivision
                                                                                                                  • Clause 5318 ndash Buildings and works
                                                                                                                  • Townhouses - Standard B9
                                                                                                                  • Slide Number 33
                                                                                                                  • Slide Number 34
                                                                                                                  • Slide Number 35
                                                                                                                  • Slide Number 36
                                                                                                                  • Slide Number 37
                                                                                                                  • Buildings and works - Site management standard
                                                                                                                  • Site management
                                                                                                                  • Planning Advisory Note No 75
                                                                                                                  • Slide Number 41
                                                                                                                  • Slide Number 42
                                                                                                                  • Slide Number 43
                                                                                                                  • Slide Number 44
                                                                                                                  • Slide Number 45
                                                                                                                  • Slide Number 46
                                                                                                                  • Slide Number 47
                                                                                                                  • Slide Number 48
                                                                                                                  • Slide Number 49
                                                                                                                  • Slide Number 50
                                                                                                                  • Slide Number 51
                                                                                                                  • Slide Number 52
                                                                                                                  • Slide Number 53
                                                                                                                  • Slide Number 54
                                                                                                                  • Slide Number 55
                                                                                                                  • Slide Number 56
                                                                                                                  • Slide Number 57
                                                                                                                  • Slide Number 58
                                                                                                                  • Slide Number 59
                                                                                                                  • Slide Number 60
                                                                                                                  • Slide Number 61
                                                                                                                  • Next steps
                                                                                                                  • State Stormwater policies
                                                                                                                  • Slide Number 64

                                                                                                                    Next steps and other stormwater initiatives

                                                                                                                    Emma Stewart DELWP

                                                                                                                    62

                                                                                                                    Next steps

                                                                                                                    bull Trainingbull The EPArsquos BPEM Reviewbull Offsets policybull Review of STORM bull Building controls

                                                                                                                    63

                                                                                                                    State Stormwater policies

                                                                                                                    64

                                                                                                                    Thank you

                                                                                                                    • Slide Number 1
                                                                                                                    • Slide Number 2
                                                                                                                    • History of WSUD
                                                                                                                    • History of WSUD
                                                                                                                    • Transformational change in urban water
                                                                                                                    • Inconsistencies and inequities in our approach to stormwater management
                                                                                                                    • Slide Number 8
                                                                                                                    • Terms of Reference
                                                                                                                    • Improving Stormwater Management Advisory Committee
                                                                                                                    • Wide consultation
                                                                                                                    • Stakeholder feedback
                                                                                                                    • Stakeholder feedback
                                                                                                                    • Committee submitted its report in September 2018
                                                                                                                    • Committee Recomendations
                                                                                                                    • Planning reforms
                                                                                                                    • Future policy directions
                                                                                                                    • Supporting actions
                                                                                                                    • Slide Number 19
                                                                                                                    • Government response (to date)
                                                                                                                    • Longer term recommendations
                                                                                                                    • State-based planning requirements (lsquobeforersquo)
                                                                                                                    • State-based planning requirements (lsquoafterrsquo)
                                                                                                                    • Development types (volume)
                                                                                                                    • Slide Number 25
                                                                                                                    • Amendment VC154
                                                                                                                    • Whatrsquos in
                                                                                                                    • Slide Number 28
                                                                                                                    • Key elements of clauses
                                                                                                                    • Clause 5318 ndash subdivision
                                                                                                                    • Clause 5318 ndash Buildings and works
                                                                                                                    • Townhouses - Standard B9
                                                                                                                    • Slide Number 33
                                                                                                                    • Slide Number 34
                                                                                                                    • Slide Number 35
                                                                                                                    • Slide Number 36
                                                                                                                    • Slide Number 37
                                                                                                                    • Buildings and works - Site management standard
                                                                                                                    • Site management
                                                                                                                    • Planning Advisory Note No 75
                                                                                                                    • Slide Number 41
                                                                                                                    • Slide Number 42
                                                                                                                    • Slide Number 43
                                                                                                                    • Slide Number 44
                                                                                                                    • Slide Number 45
                                                                                                                    • Slide Number 46
                                                                                                                    • Slide Number 47
                                                                                                                    • Slide Number 48
                                                                                                                    • Slide Number 49
                                                                                                                    • Slide Number 50
                                                                                                                    • Slide Number 51
                                                                                                                    • Slide Number 52
                                                                                                                    • Slide Number 53
                                                                                                                    • Slide Number 54
                                                                                                                    • Slide Number 55
                                                                                                                    • Slide Number 56
                                                                                                                    • Slide Number 57
                                                                                                                    • Slide Number 58
                                                                                                                    • Slide Number 59
                                                                                                                    • Slide Number 60
                                                                                                                    • Slide Number 61
                                                                                                                    • Next steps
                                                                                                                    • State Stormwater policies
                                                                                                                    • Slide Number 64

                                                                                                                      62

                                                                                                                      Next steps

                                                                                                                      bull Trainingbull The EPArsquos BPEM Reviewbull Offsets policybull Review of STORM bull Building controls

                                                                                                                      63

                                                                                                                      State Stormwater policies

                                                                                                                      64

                                                                                                                      Thank you

                                                                                                                      • Slide Number 1
                                                                                                                      • Slide Number 2
                                                                                                                      • History of WSUD
                                                                                                                      • History of WSUD
                                                                                                                      • Transformational change in urban water
                                                                                                                      • Inconsistencies and inequities in our approach to stormwater management
                                                                                                                      • Slide Number 8
                                                                                                                      • Terms of Reference
                                                                                                                      • Improving Stormwater Management Advisory Committee
                                                                                                                      • Wide consultation
                                                                                                                      • Stakeholder feedback
                                                                                                                      • Stakeholder feedback
                                                                                                                      • Committee submitted its report in September 2018
                                                                                                                      • Committee Recomendations
                                                                                                                      • Planning reforms
                                                                                                                      • Future policy directions
                                                                                                                      • Supporting actions
                                                                                                                      • Slide Number 19
                                                                                                                      • Government response (to date)
                                                                                                                      • Longer term recommendations
                                                                                                                      • State-based planning requirements (lsquobeforersquo)
                                                                                                                      • State-based planning requirements (lsquoafterrsquo)
                                                                                                                      • Development types (volume)
                                                                                                                      • Slide Number 25
                                                                                                                      • Amendment VC154
                                                                                                                      • Whatrsquos in
                                                                                                                      • Slide Number 28
                                                                                                                      • Key elements of clauses
                                                                                                                      • Clause 5318 ndash subdivision
                                                                                                                      • Clause 5318 ndash Buildings and works
                                                                                                                      • Townhouses - Standard B9
                                                                                                                      • Slide Number 33
                                                                                                                      • Slide Number 34
                                                                                                                      • Slide Number 35
                                                                                                                      • Slide Number 36
                                                                                                                      • Slide Number 37
                                                                                                                      • Buildings and works - Site management standard
                                                                                                                      • Site management
                                                                                                                      • Planning Advisory Note No 75
                                                                                                                      • Slide Number 41
                                                                                                                      • Slide Number 42
                                                                                                                      • Slide Number 43
                                                                                                                      • Slide Number 44
                                                                                                                      • Slide Number 45
                                                                                                                      • Slide Number 46
                                                                                                                      • Slide Number 47
                                                                                                                      • Slide Number 48
                                                                                                                      • Slide Number 49
                                                                                                                      • Slide Number 50
                                                                                                                      • Slide Number 51
                                                                                                                      • Slide Number 52
                                                                                                                      • Slide Number 53
                                                                                                                      • Slide Number 54
                                                                                                                      • Slide Number 55
                                                                                                                      • Slide Number 56
                                                                                                                      • Slide Number 57
                                                                                                                      • Slide Number 58
                                                                                                                      • Slide Number 59
                                                                                                                      • Slide Number 60
                                                                                                                      • Slide Number 61
                                                                                                                      • Next steps
                                                                                                                      • State Stormwater policies
                                                                                                                      • Slide Number 64

                                                                                                                        63

                                                                                                                        State Stormwater policies

                                                                                                                        64

                                                                                                                        Thank you

                                                                                                                        • Slide Number 1
                                                                                                                        • Slide Number 2
                                                                                                                        • History of WSUD
                                                                                                                        • History of WSUD
                                                                                                                        • Transformational change in urban water
                                                                                                                        • Inconsistencies and inequities in our approach to stormwater management
                                                                                                                        • Slide Number 8
                                                                                                                        • Terms of Reference
                                                                                                                        • Improving Stormwater Management Advisory Committee
                                                                                                                        • Wide consultation
                                                                                                                        • Stakeholder feedback
                                                                                                                        • Stakeholder feedback
                                                                                                                        • Committee submitted its report in September 2018
                                                                                                                        • Committee Recomendations
                                                                                                                        • Planning reforms
                                                                                                                        • Future policy directions
                                                                                                                        • Supporting actions
                                                                                                                        • Slide Number 19
                                                                                                                        • Government response (to date)
                                                                                                                        • Longer term recommendations
                                                                                                                        • State-based planning requirements (lsquobeforersquo)
                                                                                                                        • State-based planning requirements (lsquoafterrsquo)
                                                                                                                        • Development types (volume)
                                                                                                                        • Slide Number 25
                                                                                                                        • Amendment VC154
                                                                                                                        • Whatrsquos in
                                                                                                                        • Slide Number 28
                                                                                                                        • Key elements of clauses
                                                                                                                        • Clause 5318 ndash subdivision
                                                                                                                        • Clause 5318 ndash Buildings and works
                                                                                                                        • Townhouses - Standard B9
                                                                                                                        • Slide Number 33
                                                                                                                        • Slide Number 34
                                                                                                                        • Slide Number 35
                                                                                                                        • Slide Number 36
                                                                                                                        • Slide Number 37
                                                                                                                        • Buildings and works - Site management standard
                                                                                                                        • Site management
                                                                                                                        • Planning Advisory Note No 75
                                                                                                                        • Slide Number 41
                                                                                                                        • Slide Number 42
                                                                                                                        • Slide Number 43
                                                                                                                        • Slide Number 44
                                                                                                                        • Slide Number 45
                                                                                                                        • Slide Number 46
                                                                                                                        • Slide Number 47
                                                                                                                        • Slide Number 48
                                                                                                                        • Slide Number 49
                                                                                                                        • Slide Number 50
                                                                                                                        • Slide Number 51
                                                                                                                        • Slide Number 52
                                                                                                                        • Slide Number 53
                                                                                                                        • Slide Number 54
                                                                                                                        • Slide Number 55
                                                                                                                        • Slide Number 56
                                                                                                                        • Slide Number 57
                                                                                                                        • Slide Number 58
                                                                                                                        • Slide Number 59
                                                                                                                        • Slide Number 60
                                                                                                                        • Slide Number 61
                                                                                                                        • Next steps
                                                                                                                        • State Stormwater policies
                                                                                                                        • Slide Number 64

                                                                                                                          64

                                                                                                                          Thank you

                                                                                                                          • Slide Number 1
                                                                                                                          • Slide Number 2
                                                                                                                          • History of WSUD
                                                                                                                          • History of WSUD
                                                                                                                          • Transformational change in urban water
                                                                                                                          • Inconsistencies and inequities in our approach to stormwater management
                                                                                                                          • Slide Number 8
                                                                                                                          • Terms of Reference
                                                                                                                          • Improving Stormwater Management Advisory Committee
                                                                                                                          • Wide consultation
                                                                                                                          • Stakeholder feedback
                                                                                                                          • Stakeholder feedback
                                                                                                                          • Committee submitted its report in September 2018
                                                                                                                          • Committee Recomendations
                                                                                                                          • Planning reforms
                                                                                                                          • Future policy directions
                                                                                                                          • Supporting actions
                                                                                                                          • Slide Number 19
                                                                                                                          • Government response (to date)
                                                                                                                          • Longer term recommendations
                                                                                                                          • State-based planning requirements (lsquobeforersquo)
                                                                                                                          • State-based planning requirements (lsquoafterrsquo)
                                                                                                                          • Development types (volume)
                                                                                                                          • Slide Number 25
                                                                                                                          • Amendment VC154
                                                                                                                          • Whatrsquos in
                                                                                                                          • Slide Number 28
                                                                                                                          • Key elements of clauses
                                                                                                                          • Clause 5318 ndash subdivision
                                                                                                                          • Clause 5318 ndash Buildings and works
                                                                                                                          • Townhouses - Standard B9
                                                                                                                          • Slide Number 33
                                                                                                                          • Slide Number 34
                                                                                                                          • Slide Number 35
                                                                                                                          • Slide Number 36
                                                                                                                          • Slide Number 37
                                                                                                                          • Buildings and works - Site management standard
                                                                                                                          • Site management
                                                                                                                          • Planning Advisory Note No 75
                                                                                                                          • Slide Number 41
                                                                                                                          • Slide Number 42
                                                                                                                          • Slide Number 43
                                                                                                                          • Slide Number 44
                                                                                                                          • Slide Number 45
                                                                                                                          • Slide Number 46
                                                                                                                          • Slide Number 47
                                                                                                                          • Slide Number 48
                                                                                                                          • Slide Number 49
                                                                                                                          • Slide Number 50
                                                                                                                          • Slide Number 51
                                                                                                                          • Slide Number 52
                                                                                                                          • Slide Number 53
                                                                                                                          • Slide Number 54
                                                                                                                          • Slide Number 55
                                                                                                                          • Slide Number 56
                                                                                                                          • Slide Number 57
                                                                                                                          • Slide Number 58
                                                                                                                          • Slide Number 59
                                                                                                                          • Slide Number 60
                                                                                                                          • Slide Number 61
                                                                                                                          • Next steps
                                                                                                                          • State Stormwater policies
                                                                                                                          • Slide Number 64

                                                                                                                            top related