Page 1: PMP 03 Project Time Managment

Project Time ManagementBased on PMBOK 5th Edition

Abdelrahman Sheta, PMP,ITIL

1PMP - Project Time Managementfacebook.com/Sheta.Page

Page 2: PMP 03 Project Time Managment

Agenda 6.1 Plan Schedule

Management

6.2 Define Activities

6.3 Sequence Activities

6.4 Estimate Activity Resources

6.5 Estimate Activity Durations

6.6 Develop Schedule

6.7 Control Schedule2PMP - Project Time Managementfacebook.com/Sheta.Page

Page 4: PMP 03 Project Time Managment

Project Time Management

4

Includes the processes required to

accomplish timely completion of the project;

involved 7 processes used to in developing

time schedule

The schedule can have any format.

PMP - Project Time Managementfacebook.com/Sheta.Page

Page 5: PMP 03 Project Time Managment

5PMP - Project Time Managementfacebook.com/Sheta.Page

Page 6: PMP 03 Project Time Managment

6.1 Plan Schedule Management

6

Establishing the policies, procedures, and

documentation for planning, developing,

managing, executing, and controlling the

project schedule.

The key benefit is to provide guidance and

direction on how the project schedule will

be managed.PMP - Project Time Managementfacebook.com/Sheta.Page

Page 7: PMP 03 Project Time Managment

PMP - Project Time Management 7facebook.com/Sheta.Page

Page 8: PMP 03 Project Time Managment

8PMP - Project Time Managementfacebook.com/Sheta.Page

Page 9: PMP 03 Project Time Managment

Plan Schedule Management: Inputs

9

1. Project Management Plan

Scope baselines

Other Information

2. Project Charter

3. Enterprise Environmental Factors

4. Organization Process Assets

PMP - Project Time Managementfacebook.com/Sheta.Page

Page 10: PMP 03 Project Time Managment

Plan Schedule Management: T & T

10

1. Expert Judgment

2. Analytical Techniques

3. Meetings

PMP - Project Time Managementfacebook.com/Sheta.Page

Page 11: PMP 03 Project Time Managment

Plan Schedule Management: Output

11

1. Schedule Management Plan, includes but

not limited to:

Project Schedule Model Development

Level of accuracy

Rules of Performance Management

Reporting Formats

Process Description

PMP - Project Time Managementfacebook.com/Sheta.Page

Page 12: PMP 03 Project Time Managment

6.2 Define Activities

12

Identify the specific actions to be performed to

produce the project deliverables

Activities provide a basis for estimating,

scheduling, executing and monitoring and

controlling the project work.

PMP - Project Time Managementfacebook.com/Sheta.Page

Page 13: PMP 03 Project Time Managment

PMP - Project Time Management 13facebook.com/Sheta.Page

Page 14: PMP 03 Project Time Managment

Define

Activitie

s Data

Flow

14PMP - Project Time Managementfacebook.com/Sheta.Page

Page 15: PMP 03 Project Time Managment

Define Activities: Inputs

15

1. Schedule Management Plan

2. Scope baselines

3. Enterprise Environmental Factors

4. Organizational Process Assets

PMP - Project Time Managementfacebook.com/Sheta.Page

Page 16: PMP 03 Project Time Managment

Define Activities: T & T

16

1. Decomposition

2. Rolling Wave Planning

3. Expert Judgment

PMP - Project Time Managementfacebook.com/Sheta.Page

Page 17: PMP 03 Project Time Managment

Define Activities: Outputs

17

1. Activity List: A list of all the activities that

will be performed on the project and a

description of each activity

2. Activity Attributes

3. Milestone List: A milestone is a significant

point or event in project.

PMP - Project Time Managementfacebook.com/Sheta.Page

Page 18: PMP 03 Project Time Managment

6.3 Sequence Activities

18

The process of identifying and documenting

relationships among the project activities.

Lead/Lag time between activities should be

considered to support a realistic schedule.

Can be performed by a software or

manually.

PMP - Project Time Managementfacebook.com/Sheta.Page

Page 19: PMP 03 Project Time Managment

PMP - Project Time Management 19facebook.com/Sheta.Page

Page 20: PMP 03 Project Time Managment

20PMP - Project Time Managementfacebook.com/Sheta.Page

Page 21: PMP 03 Project Time Managment

Sequence Activities: Inputs

21

1. Schedule Management Plan

2. Activity List

3. Activity Attributes

4. Milestone List

5. Project Scope Statement

6. Enterprise Environmental Factors

7. Organizational Process AssetsPMP - Project Time Managementfacebook.com/Sheta.Page

Page 22: PMP 03 Project Time Managment

Sequence Activities: T & T

22

1. Precedence Diagramming

The most common method of arranging the

project activities visually. Activities are put

in

boxes, called nodes,

and connected with

arrows (Activity on

Node).PMP - Project Time Managementfacebook.com/Sheta.Page

Page 23: PMP 03 Project Time Managment

23PMP - Project Time Managementfacebook.com/Sheta.Page

Page 24: PMP 03 Project Time Managment

Sequence Activities: T & T

24

2. Dependency Determination

• Mandatory Dependency: Hard logic

• Discretionary dependency:

preferred logic, preferential logic, or

soft logic.

• External dependencies

PMP - Project Time Managementfacebook.com/Sheta.Page

Page 25: PMP 03 Project Time Managment

Sequence Activities: T & T

25

3. Applying Leads an Lags

PMP - Project Time Managementfacebook.com/Sheta.Page

Page 26: PMP 03 Project Time Managment

Sequence Activities: Outputs

26

1. Project Schedule Network Diagrams

2. Project Document Updates

PMP - Project Time Managementfacebook.com/Sheta.Page

Page 27: PMP 03 Project Time Managment

Exercise : Draw Network Diagram

PMP - Project Time Management 27

Activity Predecessor

A -

B A

C B, F

D C

E -

F E

G F

facebook.com/Sheta.Page

Page 28: PMP 03 Project Time Managment

Exercise

28

Activity Predecessor

A -

B A

C B, F

D C

E -

F E

G F

PMP - Project Time Managementfacebook.com/Sheta.Page

Page 29: PMP 03 Project Time Managment

6.4 Estimate Activity Resources

29

Estimate the type and quantities of

material, human resources, equipment,

or supplied required to perform each

activity.

PMP - Project Time Managementfacebook.com/Sheta.Page

Page 30: PMP 03 Project Time Managment

PMP - Project Time Management 30facebook.com/Sheta.Page

Page 31: PMP 03 Project Time Managment

31PMP - Project Time Managementfacebook.com/Sheta.Page

Page 32: PMP 03 Project Time Managment

Estimate Activity Resources: Inputs

32

1. Schedule Management Plan

2. Activity List

3. Activity Attributes

4. Resource Calendars

5. Risk Register

6. Activity Cost Estimates

7. Enterprise Environmental Factors

8. Organizational Process AssetsPMP - Project Time Managementfacebook.com/Sheta.Page

Page 33: PMP 03 Project Time Managment

Estimate Activity Resources: T & T

33

1. Expert Judgment

2. Alternatives Analysis

3. Published Estimating Data

4. Bottom-up Estimation

5. Project Management Software

PMP - Project Time Managementfacebook.com/Sheta.Page

Page 34: PMP 03 Project Time Managment

Estimate Activity Resources: Outputs

34

1. Activity Resource Requirements

2. Resource Breakdown Structure

3. Project Document Updates

PMP - Project Time Managementfacebook.com/Sheta.Page

Page 35: PMP 03 Project Time Managment

Quiz

• “Determining the physical resources, quantities

• of each and when they would be used” is called

A. Resources Selection.

B. Resource leveling.

C. Resource Breakdown Structure (RBS).

D. Estimate Activity Resources.

35PMP - Project Time Managementfacebook.com/Sheta.Page

Page 36: PMP 03 Project Time Managment

6.4 Estimate Activity Duration

• The process of approximating the number of

work periods needed to complete individual

activities with estimated resources.

36PMP - Project Time Managementfacebook.com/Sheta.Page

Page 37: PMP 03 Project Time Managment

PMP - Project Time Management 37facebook.com/Sheta.Page

Page 38: PMP 03 Project Time Managment

38PMP - Project Time Managementfacebook.com/Sheta.Page

Page 39: PMP 03 Project Time Managment

Estimate Activity Duration: Inputs(1)

39

1. Schedule Management Plan

2. Activity List.

3. Activity Attributes

4. Activity Resource Requirements

5. Resource Calendar

PMP - Project Time Managementfacebook.com/Sheta.Page

Page 40: PMP 03 Project Time Managment

Estimate Activity Duration: Inputs (2)

40

6. Scope Statement

7. Risk Register

8. Resource Breakdown Structure

9. Enterprise Environmental Factors

10.Organization Process AssetsPMP - Project Time Managementfacebook.com/Sheta.Page

Page 41: PMP 03 Project Time Managment

Estimate Activity Duration: T & T (1)

41

1. Expert Judgment

2. Analogous Estimating (Top-down) -

Use actual values of a similar project

3. Parametric Estimating

4. Group Decision making techniques

5. Reserve Analysis

PMP - Project Time Managementfacebook.com/Sheta.Page

Page 42: PMP 03 Project Time Managment

Estimate Activity Duration: T & T (2)6. Three-point Estimate

42PMP - Project Time Managementfacebook.com/Sheta.Page

Page 43: PMP 03 Project Time Managment

Program Evaluation & Review Technique

(PERT) Uses a weighted average duration estimate to

calculate activity durations.

43PMP - Project Time Managementfacebook.com/Sheta.Page

Page 44: PMP 03 Project Time Managment

Gantt ChartBar charts are relatively easy to read, and are

frequently used in management presentations.

44PMP - Project Time Managementfacebook.com/Sheta.Page

Page 46: PMP 03 Project Time Managment

Estimate Activity Duration: Outputs

46

1. Activity Duration Estimates: Quantitative

estimates of the likely duration of each

activity as well as the range of

possible results ( 10 ± 2 day )

2. Project Document UpdatesPMP - Project Time Managementfacebook.com/Sheta.Page

Page 47: PMP 03 Project Time Managment

Quiz

The optimistic estimate is 1, the pessimistic

estimate is 9 & the most likely estimate is

8. What is the PERT estimate?

A. 9

B. 7

C. 8

D. 6

47PMP - Project Time Managementfacebook.com/Sheta.Page

Page 48: PMP 03 Project Time Managment

6.6 Develop Schedule

48

The process of analyzing activity

sequence, durations, resource

requirements, & schedule constraints

to create a project schedule.

Developing an acceptable schedule is

often an iterative process.

PMP - Project Time Managementfacebook.com/Sheta.Page

Page 49: PMP 03 Project Time Managment

PMP - Project Time Management 49facebook.com/Sheta.Page

Page 51: PMP 03 Project Time Managment

Develop Schedule: Inputs (1)

51

1. Schedule Management Plan

2. Activity List

3. Activity Attributes

4. Project Schedule Network Diagrams

5. Activity Resource Requirements

6. Resource Calendars

7. Activity Duration EstimatesPMP - Project Time Managementfacebook.com/Sheta.Page

Page 52: PMP 03 Project Time Managment

Develop Schedule: Inputs (2)

52

8.Project Scope Statement

9. Risk Register

10.Project Staff Assignment

11.Resource Breakdown Structure

12.Enterprise Environmental

Factors 13.Organizational Process

Assets

PMP - Project Time Managementfacebook.com/Sheta.Page

Page 53: PMP 03 Project Time Managment

Develop Schedule: T & T

53

1. Schedule Network Analysis

2. Critical Path Method

3. Critical Chain Method

4. Resource Optimization Techniques

A. Resource Leveling

B. Resource Smoothing

PMP - Project Time Managementfacebook.com/Sheta.Page

Page 54: PMP 03 Project Time Managment

Develop Schedule: T & T

54

5. Modeling Techniques

• What-if scenario analysis

• Simulation

6. Leads and Lags

7. Schedule Compression

• Crashing

• Fast tracking

8. Scheduling ToolsPMP - Project Time Managementfacebook.com/Sheta.Page

Page 55: PMP 03 Project Time Managment

The longest duration path through a network

diagram which represents the shortest time to

complete theproject

Critical Path

A:2

End

StartD : 2

B : 3 C : 4

E : 2 H : 2

55PMP - Project Time Managementfacebook.com/Sheta.Page

Page 56: PMP 03 Project Time Managment

Critical Chain

56PMP - Project Time Managementfacebook.com/Sheta.Page

Page 57: PMP 03 Project Time Managment

Resource Leveling & Smoothing

57PMP - Project Time Managementfacebook.com/Sheta.Page

Page 58: PMP 03 Project Time Managment

Duration Compression

58

Duration compression is a special case of

mathematical analysis to shorten the project

schedule without changing the project scope

Crashing : cost & schedule tradeoffs are analyzed

to determine how to obtain the greatest amount of

compression for the least incremental cost.

Fast-tracking: doing activities in parallel that

would normally be done in sequence. Fast

tracking often results in rework and usually

increases risk.PMP - Project Time Managementfacebook.com/Sheta.Page

Page 59: PMP 03 Project Time Managment

Develop Schedule: Outputs1. Schedule Baseline

2. Project Schedule• Milestone Charts• Bar Charts• Schedule Network Diagrams

3. Schedule Data

4. Project Calendar

5. Project Management Plan Updates

6. Project Document Updates 59PMP - Project Time Managementfacebook.com/Sheta.Page

Page 60: PMP 03 Project Time Managment

Float

60

• Total float (Slack): the amount of time an

activity can be delayed without delaying the

project end date or/and intermediary milestone.

• Free Float (Slack): the amount of time an activity

can be delayed without delaying the start of its

successor.

• Project Float: the amount of time a project can

be delayed without delaying the externally

imposed project completion date.

PMP - Project Time Managementfacebook.com/Sheta.Page

Page 61: PMP 03 Project Time Managment

QuizWhich of the following is the BEST project

management tool to use to determine the longest

time the project will take?

A. WBS

B. Network Diagram

C. Bar chart

D. Project Charter

61PMP - Project Time Managementfacebook.com/Sheta.Page

Page 62: PMP 03 Project Time Managment

QuizWhich of the following is correct?

A. A schedule can have several critical paths

B. There must be only one critical path

C. The network diagram will change every time

the end date changes

D. A project can never have negative float

62PMP - Project Time Managementfacebook.com/Sheta.Page

Page 63: PMP 03 Project Time Managment

6.6 Control Schedule

63

The process of monitoring the status of

the project to update project progress and

manage changes to schedule baseline.

Concerned with:

Determine current status

Influence the factors that cause changes

Manage actual changes as they occurPMP - Project Time Managementfacebook.com/Sheta.Page

Page 64: PMP 03 Project Time Managment

Control Schedule: Inputs

64

1. Project Management Plan

2. Project Schedule

3. Work Performance Data

4. Project Calendars

5. Schedule Data

6. Organizational Process Assets

PMP - Project Time Managementfacebook.com/Sheta.Page

Page 65: PMP 03 Project Time Managment

Control Schedule: T & T (1)

65

1. Performance Reviews

Trend Analysis

Critical Path Method

Critical Chain Method

Earned Value Management

2. Project Management Software

PMP - Project Time Managementfacebook.com/Sheta.Page

Page 66: PMP 03 Project Time Managment

Control Schedule: T & T (2)

66

3. Resource Optimization Techniques

4. Modeling Techniques

5. Leads and Lags

6. Schedule compression

7. Scheduling ToolPMP - Project Time Managementfacebook.com/Sheta.Page

Page 67: PMP 03 Project Time Managment

Control Schedule: Outputs

67

1. Work Performance Information

2. Schedule Forecasts

3. Change Requests

4. Project Management Plan Update

1. Schedule baseline

2. Schedule Management Plan

3. Cost baseline

5. Project Document Updates

6. Organizational Process Assets Updates PMP - Project Time Managementfacebook.com/Sheta.Page

Page 68: PMP 03 Project Time Managment

QuizAll of the following relate to controlling

the

schedule EXCEPT:

A. Value analysis.

B. Crashing.

C. Float.

D. Mandatory dependencies

68PMP - Project Time Managementfacebook.com/Sheta.Page