Page 1: Five Behaviors That Can  Reduce Schedule Risk

Five Behaviors That Can Reduce Schedule Risk

Getting Started Today

Craig Peterson, PMP

Multi-Discipline System Engineer

The MITRE Corporation

Co-Author: C. Leigh Filiatrault, PMP

Page 2: Five Behaviors That Can  Reduce Schedule Risk

2

Today’s Presentation

Today’s presentation is about

reducing schedule risk by:

• Identifying and addressing common negative behaviors

• Implementing techniques that reinforce positive behaviors

• Improving risk management

It is assumed that project planning, risk management and project schedules have already been implemented.

Page 3: Five Behaviors That Can  Reduce Schedule Risk

3

Today’s Presentation

Today’s presentation is not about:

• Providing Critical Chain Project Management (CCPM) Training (but there will be a small review)

• Teaching basic project management techniques

• Debating traditional project management vs. CCPM

Underlying Principle: There is no substitute for solid project planning, estimating and risk management practices.

Page 4: Five Behaviors That Can  Reduce Schedule Risk

4

A Project’s Goal

Can we all agree that ……

The GoalProject delivers results that

satisfy customers

Necessary Condition

Meet or exceed technical requirements

Necessary Condition

Meet or exceed technical requirements

Necessary Condition

Meet or exceed schedulecommitment

Necessary Condition

Meet or exceed schedulecommitment

Necessary Condition

Meet or exceed quality requirements

Necessary Condition

Meet or exceed quality requirements

Necessary Condition

Meet or exceed costcommitment

Necessary Condition

Meet or exceed costcommitment

= and= and

Page 5: Five Behaviors That Can  Reduce Schedule Risk

5

What is Seen on Typical Projects

What’s normal …...

Project duration is expanded

Scope is sacrificed to meet deadlines

Quality is traded off

Projects overrun their original budgets

Deliver at anappropriate cost

(Budget)

Deliver the requiredfunctionality

(Scope)

Deliver the appropriate fitness for use (Quality)

Deliver at thecorrect time(Schedule)

Project Project “Tension Pyramid”“Tension Pyramid”

Page 6: Five Behaviors That Can  Reduce Schedule Risk

6

Schedule Estimates

TimeTime

Most LikelyMost Likely{50/50}{50/50}

Eff

ort

Eff

ort Which estimate Which estimate

Is really Is really provided?provided?

??

Page 7: Five Behaviors That Can  Reduce Schedule Risk

7

Why Improvements Not Realized

Tasks do not finish early, despite inflated estimates• Contingency time is wasted

Realize no gains from positive schedule variations• Rarely see tasks completing early!

Critical Path shifts, causing shifts in project focus

Metrics• Collects data about the past to predict the future

…… but does nothing to directly insure completion of project on scheduled date

Page 8: Five Behaviors That Can  Reduce Schedule Risk

8

Theory of Constraints Basics

All businesses are systems (dependent events)

All systems must have a constraint that limits output, and, therefore, non-constraints have excess capacity

System Output = Throughput = Organization’s Goal

System optimum is not the sum of the local optima

Measurements should:• induce what is good for the whole

(system optima = “The Goal”)• direct managers to parts needing attention

Page 9: Five Behaviors That Can  Reduce Schedule Risk

9

Theory of Constraints Basics (cont.)

Therefore:

Time lost at the constraint is lost forever

or

Non-constraint improvements = Waste (in two different categories)

Page 10: Five Behaviors That Can  Reduce Schedule Risk

10

Theory of Constraints Basics (cont.)

Managing the Constraint (The 5 Focusing Steps)• Identify• Exploit• Subordinate• Elevate• Prevent Inertia

Production Management Tool (DBR)• Drum - Constraint sets the system’s pace• Buffer - Never starve the constraint (time lost)• Rope - Constraint controls release of new work

Measurement Point = DBR (Nothing else is needed)

Page 11: Five Behaviors That Can  Reduce Schedule Risk

11

TOC to Critical Chain

The Thinking Process

• Outline the PM process

• Identify Failure Point

• Add “Injections”

• Test for sufficiency

• Critical Chain is born!

Page 12: Five Behaviors That Can  Reduce Schedule Risk

12

Critical Chain & Risk Management

Goldratt calls Critical Chain an Uncertainty Management Tool

Uncertainty does not equal Risk Management here, but ….

• Does build in contingency for low grade risks.

• Reduced schedule means less time for changes.

Page 13: Five Behaviors That Can  Reduce Schedule Risk

13

Pros

Focuses on project constraints.

Dramatic schedule reductions.

Easy project status reporting.

MS Project add-on software exists.

Does not “conflict” with other approaches.

Page 14: Five Behaviors That Can  Reduce Schedule Risk

14

Cons

Resourced schedules required.

Risks not directly addressed by methodology.• Uses buffers to address most risk.• Still need to do some other risk planning/tracking.

Less detail puts greater burden on task leadership.

Must get behavioral changes in place / institutionalized.

Page 15: Five Behaviors That Can  Reduce Schedule Risk

15

Take Away Points

Even if not ready to adopt, consider …...

Manage & protect constraints• Project is the goal Do all see the single goal?

What limits progress?

Change project team behavior• Metrics affects What is being

incentivized?• Make “new habits” Roadrunner

No Multi-TaskingManage to effort (not

)Take-away Line: Or … instead of adopting … take some lesson’s learned! Lets look at the injections

Page 16: Five Behaviors That Can  Reduce Schedule Risk

16

The Five Negative Behaviors

According to CCPM, there are Five Common behaviors that

appear to support good project management, but are

actually, detrimental. They are:

1. Protecting the Estimate

2. Managing to Due Dates verses Estimated Duration (Student Syndrome)

3. Starting Tasks Earlier than Necessary

4. Managing of Key Resources (Constraint Management)

5. Multitasking Resources

Although supportive of generally accepted management practices the five negative behaviors can lead to a projects failure.

Page 17: Five Behaviors That Can  Reduce Schedule Risk

17

Behavior 1:Protecting the Estimate

Definition: Consciously or unconsciously adding

a safety margin to ensure that a project or task

can be completed on time.

Assumption: This margin will be added to provide 90+ percent probability of accurate estimation.

Page 18: Five Behaviors That Can  Reduce Schedule Risk

18

Correcting Behaviors 1:Protecting the Estimate

CCPM advocates:

1. Reduce the estimate to a 50% Probability

2. Add 25% of original estimate to buffer

3. Track extra time (positive & negative) in buffer

Assumption: Negative and positive gains in time balance each other out and the project finishes earlier than the original estimate.

Page 19: Five Behaviors That Can  Reduce Schedule Risk

19

Correcting Behaviors 1: Protecting the Estimate

Reduce Protecting the Estimate risks by:

1. ID’ing the risks driving the size of the contingency

• Review project planning documents

• Discuss the estimate with the estimator

2. Quantify the risks behind the contingency

3. Develop a risk response plan

4. Control and monitor the risks

Goal: Reduce the management reserve or contingency to match the level of risk!

Page 20: Five Behaviors That Can  Reduce Schedule Risk

20

Results: Protecting the Estimate

Countering Protecting the Estimate reduces

risk in non-CCPM projects because:

• Unknown-unknowns reduced

• Risks are openly addressed

• Stakeholders can have more confidence in management reserve or project buffers are appropriate for the task or project.

• Project buffers are equal to their risk

Page 21: Five Behaviors That Can  Reduce Schedule Risk

21

Behavior 2:Student Syndrome

CCPM also calls this the “Student Syndrome”

Definition: Failure to focus 100% on a task at

the start since the due date is in the future.

• People tend to focus on the due dates of tasks, not the amount of effort it will take to complete the task.

• Project participants don’t become 100% focuses until the due date is close.

• The safety margin is consumed early on due to the lack of focus, not the risk events for which it is intend.

Page 22: Five Behaviors That Can  Reduce Schedule Risk

22

Correcting Behaviors 2:Student Syndrome

Units of time should be identified to fit goals. Goals should not be fit into units of time.

CCPM advocates focusing on task estimates rather than deadlines:

• Give team members only the work effort estimates, not the due dates

• Allow only enough time to complete the task

• Capture both late tasks and early completions in buffers

Page 23: Five Behaviors That Can  Reduce Schedule Risk

23

Correcting Behaviors 2:Student Syndrome

To implement the CCPM theory, managers need to change their behavior by focusing on:

• Work estimates (days or hours), not due dates

• How much effort is required to complete the task, not how much has been completed

• Giving positive or acceptable reactions to missed estimates (assuming 50% probability)

Management must change their own expectations to encourage a change in their team’s behavior.

Page 24: Five Behaviors That Can  Reduce Schedule Risk

24

Correcting Behaviors 2:Student Syndrome

Corresponding to management efforts, team members must be willing to change their work habits by:

• Working to achieve tasks on time with 50% probability

• Achieving and reporting early completions

Without supportive team behavior, CCPM theory cannot be executed.

Page 25: Five Behaviors That Can  Reduce Schedule Risk

25

Results:Student Syndrome

Creating the correct management and teambehaviors will improve the project enhanced by:

• Enhancing the accuracy of estimates

• Identifying issues and missing information early

• Providing the opportunity to proactively deal with the unexpected

Page 26: Five Behaviors That Can  Reduce Schedule Risk

26

Behavior 3:Starting Tasks Too Early

Definition: Tasks are started as early as possible,

which is often before all the necessary information

is known.

Don’t “jump the gun.”

Page 27: Five Behaviors That Can  Reduce Schedule Risk

27

Correcting Behavior 3:Starting Tasks Too Early

CCPM advocates starting as late as possible to

prevent:

• Tasks expanding to fill the time allotted

• Rework

Starting too soon leads to rework because:

• A task is begun with incomplete knowledge

• Scope changes

CCPM does not advocate delay for the sake of delay, but rather delay to begin with clearer information and more confidence.

Page 28: Five Behaviors That Can  Reduce Schedule Risk

28

Correcting Behavior 3:Starting Tasks Too Early

Delaying a task until of the latest possible start

date affects Risk Management in two ways:

1. Improves the ability to determine buffer sizes’ based on:

• Tasks Risk

• Project Risk

2. Establishes expectations for the timeframe of future tasks.

“To begin by bluster, but afterwards to take fright…shows a supreme lack of intelligence” Sun Tsu, The Art of War

Page 29: Five Behaviors That Can  Reduce Schedule Risk

29

Results:Starting Tasks Too Early

Delaying a start date to further clarify a project

provides:

• Significant savings, for even a few tasks

• Disincentive for work to expand to fill the time

• More flexibility for key resources

Page 30: Five Behaviors That Can  Reduce Schedule Risk

30

Behavior 4:Management of Key Resources

Definition: Key Resources are the constrained

resources on the project.

Key Resources may be:

• Physical resource such as tool or machinery

• A human resource such as an individual with a unique skills

A process is not a key resource.

Page 31: Five Behaviors That Can  Reduce Schedule Risk

31

Correcting Behaviors 4:Management of Key Resources

CCPM manages key resources by ensuring that:

• Tasks – Constrained resources perform only those tasks that they alone can uniquely fulfill.

• Workload – Excess work is not built up waiting for the constrained resource.

• Timing – Buffers are used to ensure that the work is ready for the resource and that the resource is ready for the work.

Constrained resources should perform only those tasks which can not be performed by other (unconstrained) resources.

Page 32: Five Behaviors That Can  Reduce Schedule Risk

32

Correcting Behaviors 4:Management of Key Resources

Evaluate the allocation of key resources on:

• Tasks – Can alternative resources be applied or can the tasks be completed in another order?

• Workload – Is the volume of work within the capabilities of the key resource?

• Timing – Is the resource available when needed?

• Is the work ready for the resource?

• Can buffers or float be used to create the appropriate timing?

Incorporated management of key resources into the project schedule.

Page 33: Five Behaviors That Can  Reduce Schedule Risk

33

Results:Management of Key Resources

Identifying the key resources and managing

them effectively enables:

• Project planning around tasks and resources as opposed to just deadlines and deliverables

• Proactive coordination of the constrained resource

• Tighter management of schedule variance (and use of buffers)

Page 34: Five Behaviors That Can  Reduce Schedule Risk

34

Behavior 5:Multitasking

Definition: Assigning one person to work on two

or more tasks concurrently.

Multitasking may come from:

• Within the project

• Outside of the project

Few people can apply themselves to multiple concurrent tasks well. More often, all tasks will suffer.

Page 35: Five Behaviors That Can  Reduce Schedule Risk

35

Correcting Behavior 5:Multitasking

CCPM corrects multitasking by:

• Forbidding constrained resources from multitasking

Eliminate multitasking by not allowing it to be scheduled from the start.

Page 36: Five Behaviors That Can  Reduce Schedule Risk

36

Correcting Behavior 5:Multitasking

The Project Manager can:

• Control inside the project

• By rescheduling one or more of the tasks

• By adding other resources

• Influence outside the project

• By escalating a resource conflict

• By creative resource negotiation

Project management’s role is to facilitate the team’s accomplish-ment of the goal and keep them focused on the task at hand.

Page 37: Five Behaviors That Can  Reduce Schedule Risk

37

Results 5:Multitasking

The elimination of multitasking:

• Keeps people focused on their immediate tasks

• Resolves conflicts between priorities

• Keeps people focused on the most critical tasks for the project

• Allows progress to be more accurately measured

Page 38: Five Behaviors That Can  Reduce Schedule Risk

38

Summary

Correcting the Five Common Negative Behaviors in a

traditional project management environment:

• Assumes solid project planning, scheduling and risk management

• Requires changes in both management and team interaction

• Permits individual, grouped or all behaviors being implemented

Page 39: Five Behaviors That Can  Reduce Schedule Risk

39

Summary

Recommendations on Implementing These Behavior Changes:

• Key resource management and multitasking hold lowest implementation risk for most organizations

• Estimate protection, managing to effort, and starting tasks later is dependant on other implementation activities and team behavior changes

Page 40: Five Behaviors That Can  Reduce Schedule Risk

40

Questions

Page 41: Five Behaviors That Can  Reduce Schedule Risk

41

Contact Information