Page 1: Design Refinements|West Plaza

SR 519 Intermodal Access ProjectPhase 2: South Atlantic Corridor

Page 2: Design Refinements|West Plaza

SR 519 Intermodal Access ProjectPhase 2: South Atlantic Corridor

Design Refinements|West Plaza60% Proposed Plan

• Classic industrial architecture

• Define the space• Identify pedestrian/

vehicle conflicts

GOALS:

Page 3: Design Refinements|West Plaza

SR 519 Intermodal Access ProjectPhase 2: South Atlantic Corridor

Design Refinements|West Plaza90% Proposed Plan

Page 4: Design Refinements|West Plaza

SR 519 Intermodal Access ProjectPhase 2: South Atlantic Corridor

Design Refinements|West PlazaElevator & Stairway

Page 5: Design Refinements|West Plaza

SR 519 Intermodal Access ProjectPhase 2: South Atlantic Corridor

Design Refinements|West PlazaElevator & Stairway

Page 6: Design Refinements|West Plaza

SR 519 Intermodal Access ProjectPhase 2: South Atlantic Corridor

Design Refinements|West PlazaElevator & Stairway

Page 7: Design Refinements|West Plaza

SR 519 Intermodal Access ProjectPhase 2: South Atlantic Corridor

Design Refinements|West PlazaElevator & Stairway

Page 8: Design Refinements|West Plaza

SR 519 Intermodal Access ProjectPhase 2: South Atlantic Corridor

Design Refinements|West PlazaElevator & Stairway

Page 9: Design Refinements|West Plaza

SR 519 Intermodal Access ProjectPhase 2: South Atlantic Corridor

Design Refinements|West PlazaRailings

Pedestrian

Stairway Vehicle

Page 10: Design Refinements|West Plaza

SR 519 Intermodal Access ProjectPhase 2: South Atlantic Corridor

Design Refinements|West PlazaBike Rack

Page 11: Design Refinements|West Plaza

SR 519 Intermodal Access ProjectPhase 2: South Atlantic Corridor

Design Refinements|East Plaza60% Proposed Plan

• Simplified circulation• Programmable spaces• Engage the space• Allow art opportunities

GOALS:

Page 12: Design Refinements|West Plaza

SR 519 Intermodal Access ProjectPhase 2: South Atlantic Corridor

Design Refinements|East PlazaDesign Process

• Simplified circulation• Programmable spaces• Engage the space• Allow art opportunities

GOALS:

Page 13: Design Refinements|West Plaza

SR 519 Intermodal Access ProjectPhase 2: South Atlantic Corridor

Design Refinements|East Plaza90% Proposed Plan

Page 14: Design Refinements|West Plaza

SR 519 Intermodal Access ProjectPhase 2: South Atlantic Corridor

Design Refinements|East PlazaSeat Walls

Page 15: Design Refinements|West Plaza

SR 519 Intermodal Access ProjectPhase 2: South Atlantic Corridor

Design Refinements|East PlazaRailings

PedestrianStairway

Vehicle

Page 16: Design Refinements|West Plaza

SR 519 Intermodal Access ProjectPhase 2: South Atlantic Corridor

Design Refinements|East PlazaRailings

Page 17: Design Refinements|West Plaza

SR 519 Intermodal Access ProjectPhase 2: South Atlantic Corridor

Design Refinements|East PlazaWay finding & Signage

Page 18: Design Refinements|West Plaza

SR 519 Intermodal Access ProjectPhase 2: South Atlantic Corridor

Design Refinements|East PlazaWay finding & Signage

Page 19: Design Refinements|West Plaza

SR 519 Intermodal Access ProjectPhase 2: South Atlantic Corridor

Design Refinements|East PlazaWay finding & Signage

Page 20: Design Refinements|West Plaza

SR 519 Intermodal Access ProjectPhase 2: South Atlantic Corridor

Design Refinements|East PlazaPlanting

Page 21: Design Refinements|West Plaza

SR 519 Intermodal Access ProjectPhase 2: South Atlantic Corridor

Design Refinements|East PlazaPlanting

Page 22: Design Refinements|West Plaza

SR 519 Intermodal Access ProjectPhase 2: South Atlantic Corridor

Design Refinements|East PlazaPlanting

Page 23: Design Refinements|West Plaza

SR 519 Intermodal Access ProjectPhase 2: South Atlantic Corridor

Timeline

a.b.

a. Preliminary & Final Design March 200930% presentation to SDC - November 20, 200860% presentation to SDC - January 15, 200990% presentation to SDC - February 19, 2009

b. Construction Civil Package June 2009(landscape & urban design)

c. Bridge Structures July 2009d. Construction Complete June 2010

c.d.